Opinion

101 Construction Company v. Lawrence B. Hammet, II

Court
Court of Appeals of Tennessee
Filed
Oct 30, 2019
Status
Published
On the bench
Presiding Judge J. Steven Stafford
Cited by
0 cases
Authority
More cited than 9.4%

stating that the court’s “initial task” is to determine whether the language in a contract is ambiguous

How later courts described this case

  • stating that the court’s “initial task” is to determine whether the language in a contract is ambiguous
  • holding that no ambiguity regarding prejudgment interest existed when a contract compensated for damages
  • holding that federal arbitration statutes did not preempt state law governing unconscionability of the arbitration agreement
  • allowing prejudgment interest when it was first raised in a motion for new trial

Written by the judges who cited it.

The opinion

10/30/2019

IN THE COURT OF APPEALS OF TENNESSEE

AT NASHVILLE

July 10, 2019 Session

101 CONSTRUCTION COMPANY v. LAWRENCE B. HAMMET, II ET AL.

Appeal from the Chancery Court for Davidson County

No. 15-1268-III Louis W. Oliver, III, Chancellor

___________________________________

No. M2018-01321-COA-R3-CV

___________________________________

Plaintiff client sued Defendant attorney and law firm for damages tied to a breach of an

attorney’s fees contract following the completion of an arbitration matter. Following a

jury trial, the jury returned a verdict in favor of defendants. Plaintiff appeals the denial of

its motion for directed verdict and motion for new trial. Because the trial court erred in

denying plaintiff’s motion for directed verdict on interpretation of the written contract at

issue, we reverse the verdict entered by the trial court and remand with instructions to

enter a directed verdict against the attorney and law firm in the amount of $67,335.69 and

to determine whether prejudgment interest is warranted in this case.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed

And Remanded with Instructions

J. STEVEN STAFFORD, P.J., W.S., delivered the opinion of the court, in which FRANK G.

CLEMENT, JR., P.J., M.S., and ANDY D. BENNETT, J., joined.

David G. Thompson, Blind Akrawi, Erik C. Lybeck, Nashville, Tennessee, for the

appellant, 101 Construction Company.

Richard M. Smith, Nashville, Tennessee, for the appellees, Lawrence B. Hammet, II, and

Todd & Floyd, PLC.

OPINION

BACKGROUND

In 2002, Plaintiff/Appellee Lawrence B. Hammet, II (“Mr. Hammet”) began his

legal representation of Appellant 101 Construction Company (“101 Construction”) while

Mr. Hammet worked in a Nashville law firm. In 2003, Mr. Hammet continued

representing 101 Construction when he moved his practice to another law office, which

subsequently became Defendant/Appellant Todd & Floyd, PLC (“the Firm” and together

with Mr. Hammet, “Defendants”).1 Mr. Hammet represented 101 Construction

continuously until 2010, when 101 Construction’s CEO, Saeed Sassan (“Mr. Sassan”),

asked Mr. Hammet to withdraw as counsel as the company suffered from financial

difficulties. At the time, Mr. Hammet’s representation included two arbitration matters

where 101 Construction had not been compensated for its work.

Weeks after Mr. Hammet withdrew as counsel for the two arbitration matters, Mr.

Hammet contacted Mr. Sassan to discuss whether 101 Construction had retained new

counsel and how the 101 Construction file should be transferred. Mr. Hammet later called

Mr. Sassan with an alternative fee proposal that would allow Mr. Hammet to resume

representing 101 Construction at a lower hourly rate than before. Under the proposal, the

Firm would receive $100.00 per billable hour for its work, and an “Additional Fee”

would be assessed by the Firm based on its success in the two outstanding arbitration

matters. Mr. Sassan orally agreed to the terms of the fee agreement in a conversation with

Mr. Hammet. In letters dated December 1, 2010, and December 10, 2010,2 the fee

structure drafted by Mr. Hammet was as follows:

At the conclusion of the matter and the receipt of the final decision

and award of the arbitrator, our firm will be entitled to an additional fee

payment (“Additional Fee”), in addition to the fees earned under the

existing fee agreement, as well as those earned under the new fee

arrangement based upon the Reduced Rate of $100 per hour.

Notwithstanding the above, the Additional Fee is contingent upon the

amount of monetary damages your company is awarded by the Arbitrator in

its final decision (“Awarded Damages”).

The Additional Fee will be calculated at an hourly rate of $150 per

hour (“Bonus Rate”) that will be applied to the hours billed on this matter

from the date of this agreement; but only to the degree of success realized

as a result of the arbitration. The Additional Fee, based upon the Bonus

Rate, shall be calculated on a percentage basis determined by the percent of

the Awarded Damages as compared to the amount of monetary damages

101 Construction requests to be awarded at the close of the arbitration

hearing (“Requested Damages”).

1

At the time of the events in this case, the Firm was named Todd, Floyd & Hammet, PLC. Mr.

Hammet left the Firm before the filing of the complaint in the present case. Voluntarily, Mr. Hammet

assumed joint and several liability in this matter and remains a named party in the present case.

2

The two separate letters related to the two pending arbitration matters, referred to by the parties

as the “Emerald Group matter” and the “H&P Smyrna matter.” The December 1, 2010 letter concerned

the Emerald Group matter, and the December 10, 2010 letter concerned the H&P Smyrna matter.

-2-

By way of example, should the Awarded Damages equal 100% of

the Requested Damages, our firm will then be paid the Additional Fee

determined by applying $150 per hour Bonus Rate to the hours charged by

our firm to their matter from the date of this new agreement. Another

example would be, should the Awarded Damages equal 50% of the amount

of the Requested Damages, our firm then will be paid the Additional Fee by

applying 50% of the $150 per hour Bonus Rate to the hours charged by our

firm to this matter from the date of this agreement. Obviously, the baseline

amount for determining the percentage of Awarded Damages as compared

to Requested Damages for the purposes of calculating the Additional Fee

will not be known until the amount of the Requested Damages is actually

submitted to the arbitrator at the close of the arbitration hearing.

Upon receipt, Mr. Sassan agreed to the terms of the two letters as CEO of 101

Construction by signing the back page of each agreement.

The Firm’s representation of 101 Construction continued as the H&P Smyrna

arbitration was completed in May 2012. The arbitrator awarded the majority of 101

Construction’s claim and less than half of H&P Smyrna’s counterclaim. Mr. Hammet

calculated the Firm’s Additional Fee by separating the claim and the counterclaim into

two fractions, and then placing the awarded damages for each claim as numerators and

the requested damages for each claim as denominators. No prejudgment interest was

included in the calculations. 101 Construction disputed Mr. Hammet’s calculations in

October 2012, but both parties negotiated and eventually compromised on a success rate

that determined the Firm’s Additional Fee. The final fee determination fell generally in

line with the Firm’s proposed calculation. Mr. Sassan later testified that he agreed to the

compromise so 101 Construction could receive proceeds from the arbitration as quickly

as possible.

Months after the H&P Smyrna fee settlement, the arbitration hearing for the

Emerald Group matter occurred in January 2013. When the hearing concluded, 101

Construction sought $769,382.18 in damages in its claim and $319,339.39 in

prejudgment interest. In a counterclaim, Emerald Group sought $253,136.79 in damages.

After evaluating and calculating the claims and counterclaims, the arbitrator granted an

award of $428,934.45 to 101 Construction.3 No prejudgment interest was awarded. The

Firm billed 1,434.20 hours while working on the Emerald Group matter. In calculating

the Additional Fee, Mr. Hammet took the $602,886.78 awarded to 101 Construction in its

original claim and divided that figure from the amount 101 Construction sought in the

3

The arbitrator awarded $602,886.78 based on 101 Construction’s claims, and reduced the award

by $103,941.33 based on the counterclaims against 101 Construction. When the amount paid to 101

Construction to date was subtracted from the contract amount and net contract claims determined by the

arbitrator, the difference was $428,934.45.

-3-

original claim, without considering the prejudgment interest sought.4 Mr. Hammet

calculated a 72% Success Rate, which he applied to the estimated hours that the Firm

worked on 101 Construction’s original claim. Mr. Hammet then took the $103,941.33

charged against 101 Construction in the counterclaim and divided it by the $251,136.79

in alleged counterclaim damages. That calculation resulted in a 41% Success Rate for

Emerald Group, which led Mr. Hammet to apply a 59% Success Rate to the estimated

hours the Firm spent litigating the counterclaim. In all, the Firm sought an Additional Fee

of $152,096.91 from 101 Construction.5 Mr. Hammet explained his calculations in an

email to Mr. Sassan, who did not agree with Mr. Hammet’s findings. The Firm and 101

Construction agreed for the Firm to disburse the undisputed funds from the arbitration to

101 Construction while the matter was resolved. The Firm transferred what it believed to

be its fee out of its trust account after the non-disputed funds were dispersed.

101 Construction filed a complaint against Defendants on October 20, 2015 in

Davidson County Chancery Court. 101 Construction sought $68,669.50 in damages and

alleged that the Firm and Mr. Hammet separately breached the contract at issue by failing

to correctly calculate the Additional Fee under the contract. Instead of the Firm’s two-

pronged calculation, the plaintiff claimed that the Awarded Damages calculation should

have included prejudgment interest and did not allow for separate consideration of

counter-claim awards. In an exhibit filed with the complaint, 101 Construction contended

that the Additional Fee should have been calculated by dividing the net award to 101

Construction ($428,934.45) by the total amount, including prejudgment interest, it

demanded during the arbitration proceeding ($1,106,041.00).6 With a 38.8% Success

Rate, the Additional Fee would be calculated at $83,427.41.7 Mr. Hammet filed a motion

to dismiss while arguing that the gravamen of the complaint was not a breach of contract

matter, but was instead a claim of legal malpractice which was filed beyond the statute of

limitations. The Firm adopted Mr. Hammet’s argument in a separate motion to dismiss.

On January 29, 2016, Davidson County Chancellor Ellen Hobbs Lyle filed an

order recusing herself from the case based on the Defendants’ routine practice in her

court. The case was later transferred to Sumner County Chancellor Louis W. Oliver, III

on February 8, 2016.

4

The defendants concede that Mr. Hammet erroneously calculated the Success Rate in the

Emerald Green matter. While 101 Construction sought $769,382.18 in its original claim, Mr. Hammet

first calculated $839,393.17 as the amount that 101 Construction demanded. The miscalculation led to a

smaller Success Rate than what would have occurred if Mr. Hammet used the correct figures from the

arbitration award.

5

A version of this calculation as shown in 101 Construction’s appellate brief is provided, infra.

6

A version of this calculation as shown in 101 Construction’s appellate brief is provided, infra.

7

At trial and on appeal, 101 Construction alleged that the amount it sought during arbitration was

$1,088,721.57. This would result in a Success Rate of 39.4% and an Additional Fee of $84,761.22. With

these calculations, the damages sought by 101 Construction equal $67,335.69.

-4-

The trial court entered an order denying the Defendants’ motions to dismiss on

May 5, 2016, finding that the gravamen of 101 Construction’s claim was breach of

contract. Mr. Hammet subsequently filed an answer denying liability, raising several

affirmative defenses, and alleging a counterclaim that 101 Construction breached the

contract at issue. The Firm also denied liability and raised several affirmative defenses in

a separate answer. In an amended complaint, 101 Construction renewed its allegations

and included a new demand for a jury trial. In answering the counterclaim, 101

Construction denied Mr. Hammet’s allegations and called for the counterclaim to be

dismissed with prejudice.

101 Construction later filed a motion seeking summary judgment for its claim and

Mr. Hammet’s counterclaim, arguing that the case amounted to a question of law

regarding the interpretation of the contract at issue. In response, Defendants claimed that

they were entitled to summary judgment based on the undisputed facts of the case. The

trial court partially granted and partially denied 101 Construction’s motion for summary

judgment in an order filed on March 6, 2018. The court dismissed Mr. Hammet’s

counterclaim but denied summary judgment on 101 Construction’s breach of contract

claim on the basis that there were disputed issues of material fact.

A jury trial occurred on March 14, 2018. 101 Construction’s proof largely

consisted of the testimony of Mr. Sassan. In contrast, Defendants generally relied on the

testimony of Mr. Hammet. After the presentation of the proof, 101 Construction orally

moved for a directed verdict, arguing that there was no question of fact for the jury to

decide and the breach of contract issue should be decided as a matter of law. The trial

court denied 101 Construction’s motion and instructed the jury to decide whether: 1) the

defendants breached their Fee Agreement with the plaintiff, and 2) if so, what amount of

money should be paid by the defendants to the plaintiff under the Fee Agreement. During

deliberations, the jury asked several questions and twice indicated that it could not come

to a unanimous verdict.8 Eventually, however, the jury returned a unanimous verdict that

the Firm and Mr. Hammet did not breach its Fee Agreement with 101 Construction.

On May 4, 2018, 101 Construction renewed its motion for a directed verdict and

separately moved for a new trial based on issues regarding evidence and various jury

instructions. The renewed motion for a directed verdict also included a claim for

prejudgment interest related to 101 Construction’s alleged damages. After Defendants

opposed the motions, the trial court entered an order on June 19, 2018 that denied the

renewed motion for a directed verdict and the motion for a new trial. This timely appeal

by 101 Construction followed.

8

After two statements indicating that the jury was struggling to reach a unanimous verdict, the

jury asked whether it could change the amount of money paid to 101 Construction if they unanimously

found there was no breach of contract. The trial court later advised the jury that the scenario it proposed

was not possible and instructed the jury to return the next day. Upon their return, the jury asked for a

“better understanding of the word ‘material’ as it relates to material breach.”

-5-

ISSUES PRESENTED

Both parties presented similar issues on appeal. As we perceive them, the issues in

the present case are as follows:

1. Whether the trial court erred in denying Plaintiff’s Motion for a Directed

Verdict.

2. Whether the trial court erred in denying Plaintiff’s Motion for a New Trial.

DISCUSSION

I. Directed Verdict

The main question in this appeal is rooted in the trial court’s denial of 101

Construction’s motion for directed verdict based on the interpretation of the Fee

Agreement between 101 Construction and Mr. Hammet. Tennessee Rule of Civil

Procedure 50.01 governs motions for a directed verdict and states:

A motion for a directed verdict may be made at the close of the evidence

offered by an opposing party or at the close of the case. The court shall

reserve ruling until all parties alleging fault against any other party have

presented their respective proof-in-chief. A party who moves for a directed

verdict at the close of the evidence offered by an opponent may offer

evidence in the event that the motion is not granted, without having

reserved the right so to do and to the same extent as if the motion had not

been made. A motion for a directed verdict which is not granted is not a

waiver of trial by jury even though all parties to the action have moved for

directed verdicts. The order of the court granting a motion for a directed

verdict is effective without any assent of the jury.

Tenn. R. Civ. Pro. 50.01. When considering a trial court’s ruling on a motion for a

directed verdict, we review the ruling de novo and apply the same standards used by the

trial court. Brown v. Crown Entertainment Corp., 181 S.W.3d 268, 281 (Tenn. 2005)

(citing Gaston v. Tenn. Farmers Mut. Ins. Co., 120 S.W.3d 815, 819 (Tenn. 2003)). “A

directed verdict is appropriate only when evidence, viewed reasonably, supports only one

conclusion.” Twenty Holdings, LLC v. Land South TN, LLC, No. M2018-01903-COA-

R3-CV, 2019 WL 4200970 at *6 (Tenn. Ct. App. Sept. 5, 2019) (citing Remco

Equipment Sales, Inc. v. Manz, 952 S.W.2d 437, 439 (Tenn. Ct. App. 1997)). In

reviewing a motion for a directed verdict, courts must take the strongest legitimate view

of the evidence against the directed verdict. Id. (citations omitted). Further, appellate

courts cannot weigh the evidence or evaluate the credibility of witnesses. Johnson v.

Tenn. Farmers Mut. Ins. Co., 205 S.W.3d 364, 370 (Tenn. 2006). A motion for a

directed verdict must be denied if material evidence is disputed or “doubt exists as to the

-6-

conclusions to be drawn from that evidence.” Id. (citing Hurley v. Tenn. Farmers Mut.

Ins. Co., 922 S.W.2d 887, 891 (Tenn. Ct. App. 1995)). “A trial court may, however,

direct a verdict with regard to an issue that can properly be decided as a question of law

because deciding purely legal questions is the court’s responsibility, not the jury’s.” In re

Estate of Marks, 187 S.W.3d 21, 27 (Tenn. Ct. App. 2005).

Generally, the interpretation of written contracts is a matter of law that we review

de novo on the record with no presumption of correctness. Guiliano v. Cleo, Inc., 995

S.W.2d 88, 95 (Tenn. 1999). When resolving issues of contract interpretation, this Court

“is to ascertain the intention of the parties based upon the usual, natural, and ordinary

meaning of the contractual language.” Id. While courts must determine the intent of the

parties from the express terms of the contact, “as an aid to finding that intention, the court

may consider the situation of the parties, the business to which the contract relates, the

subject matter of the contract, the circumstances surrounding the transaction, and

the construction placed on the contract by the parties in carrying out its terms.” Silva v.

Buckley, No. M2002-00045-COA-R3-CV, 2003 WL 23099681 at *2 (Tenn. Ct. App.

Dec. 31, 2003) (citing Simonton v. Huff, 60 S.W.3d 820, 825 (Tenn. Ct. App. 2000)).

Determining the intent of the parties “is generally treated as a question of law because the

words of the contract are definite and undisputed, and in deciding the legal effect of the

words, there is no genuine factual issue left for the jury to decide.” Planters Gin Co. v.

Fed. Compress & Warehouse, Co., Inc., 78 S.W.3d 885, 889-90 (Tenn. 2002) (citing 5

Joseph M. Perillo, Corbin on Contracts, § 24.30 (rev. ed. 1998); Doe v. HCA Health

Servs. of Tenn., Inc., 46 S.W.3d 191, 196 (Tenn. 2001)). However, other established

rules of construction must be applied to determine the parties’ intent from a contract

when its terms are ambiguous or “susceptible to more than one reasonable

interpretation.” Allstate Ins. Co. v. Watson, 195 S.W.3d 609, 611 (Tenn. 2006). As the

Tennessee Supreme Court has explained,

A court’s initial task in construing a contract is to determine whether the

language of the contract is ambiguous. Once found to be ambiguous, a

court applies established rules of construction to determine the parties’

intent. “Only if ambiguity remains after the court applies the pertinent rules

of construction does [the legal meaning of the contract] become a question

of fact” appropriate for a jury. Smith v. Seaboard Coast Line R.R. Co., 639

F.2d 1235, 1239 (5th Cir.1981).

Planters Gin Co., 78 S.W.3d at 890.

In the present case, 101 Construction seeks a directed verdict on its breach of

contract claim. To prevail on a breach of contract claim, a party must prove that a valid

and enforceable contract exists, a breach of that contract occurred through a deficiency in

performance, and damages were caused by the breach. Fed. Ins. Co. v. Winters, 354

-7-

S.W.3d 287, 291 (Tenn. 2011). The only element of the claim disputed by the parties is

whether the breach occurred under the terms of the Fee Agreement, i.e., whether

Defendants breached the contract by retaining more compensation than provided by the

Fee Agreement. In this appeal, 101 Construction argues that the contract at issue did not

contain an ambiguity so as to create a jury question on the interpretation of the contract.

Even if an ambiguity exists, 101 Construction further argues that rules of construction,

particularly contra proferentem9, would lead to a court finding in its favor as a matter of

law. Defendants, however, contend that the trial court correctly found an ambiguity that

led to a mixed question of law and fact. The ambiguity exists, they argue, when

considered in the context of the material facts used by the parties in understanding the

contract and the standard arbitration proceedings that include separate awards for claims

and counterclaims.

Thus, the first question this court must answer is whether an ambiguity exists in

the language of the contract, which left unresolved by the rules of construction, may be

submitted to the jury. See Planters Gin, 78 S.W.3d at 890 (stating that the court’s “initial

task” is to determine whether the language in a contract is ambiguous). A contract is

ambiguous “only when it is of uncertain meaning and may fairly be understood in more

ways than one.” Id. (citing Empress Health & Beauty Spa, Inc. v. Turner, 503 S.W.2d

188, 190–91 (Tenn. 1973)). “A strained construction may not be placed on the language

used to find ambiguity where none exists.” Turner, 503 S.W.2d at 190–91.

A. Calculation of Additional Fee

We begin first with the parties’ disagreement as to the proper method of

calculating the Additional Fee under the Fee Agreement. In order to determine whether

an ambiguity exists as to this dispute so as to support the trial court’s decision to deny the

motion for directed verdict, it is necessary to consider the competing interpretations

submitted the parties. See Allstate Ins., 195 S.W.3d at 611 (stating that a contract is

ambiguous when it is subject to more than one reasonable interpretation). On the one

hand, 101 Construction contends that the language of the Fee Agreement provides for a

single calculation in which the total amount of the damages awarded is divided by the

total amount requested. Under this calculation, the success or failure as to any

counterclaims is considered part and parcel of the entire fee claim, as any recovery on the

counterclaims reduces the overall amount of damages awarded. As provided in its

appellate brief, the Plaintiff’s calculation is as follows:

9

Contra proferentum, or Latin for “against the offeror,” is a contract interpretation doctrine that

construes ambiguities against the drafter of the document. Black’s Law Dictionary 376 (9th ed. 2009).

-8-

Hours Billed

Awarded Damages

Additional Fee = X $150 X Under New

Requested Damages Agreement

In contrast, Defendants contend that the calculation must be performed twice, once with

regard to the affirmative claims raised by 101 Construction and separately with regard to

any counter claims that were raised against 101 Construction in the arbitration. As

presented in 101 Construction’s brief,10 Defendants’ calculation is as follows:

Amount awarded by Arbitrator,

(1) before set oft'for

counterclaims and (2) not

Estimated Percentage of counting prejudgment interest

Time Spent Prosecuting X Hours Billed X X Bonus Rate

Amount requested at close of

Affirmative Claims arbitration hearing, not counting

prejudgment interest

Amount requested by Defendant

as counterclaim at close of

arbitration hearing, not counting

Estimated Percentage of prejudgment interest

X Hours Billed X X Bonus Rate

Time Spent Defending Amount awarded by Arbitrator

Against Counterclaims on counterclaims,(1) before

award on affirmative claims,

and (2) not counting

prejudgment interest

MEI

Additional Fee

To resolve this dispute, we begin with the language of the Fee Agreement:

The Additional Fee will be calculated at an hourly rate of $150 per hour

(“Bonus Rate”) that will be applied to the hours billed on this matter from

the date of this agreement; but only to the degree of success realized as a

result of the arbitration. The Additional Fee, based upon the Bonus Rate,

shall be calculated on a percentage basis determined by the percent of the

Awarded Damages as compared to the amount of monetary damages 101

Construction requests to be awarded at the close of the arbitration hearing

(“Requested Damages”).

Accordingly, the calculation of the Additional Fee required dividing the amount of

damages awarded to 101 Construction by the amount 101 Construction requested at the

end of the arbitration matter. Then, the result would be multiplied by the number of hours

worked and the $150 hourly rate to determine the actual fee.

10

Nothing in Defendants’ appellate brief suggests that 101 Construction’s equation is an

inaccurate statement of their position.

-9-

In our view, 101 Construction’s interpretation of the contract is the only

reasonable interpretation under the circumstances. As noted above, the language of the

contract provides that the Firm is entitled to an additional fee to be determined by

comparing the “Awarded Damages” to the “Requested Damages.” Both of these terms

are defined by the Fee Agreement. Requested Damages refers to those damages

“request[ed] to be awarded at the close of the arbitration hearing,” while Awarded

Damages refers to “the amount of monetary damages [101 Construction] is awarded by

the Arbitrator in its final decision.” Neither of these definitions makes a distinction based

upon whether money was awarded or lost due to the success or failure of a counterclaim.

Instead, the language of the Fee Agreement more closely matches how the Emerald

Group arbitrator handled the overall award by reducing the overall damages awarded to

101 Construction by the amount of damages from successful counterclaims against the

company.

Moreover, no language in the Fee Agreement accounts for the separate claims that

the defendants believe require separate calculations. Importantly, there is no mention in

the Fee Agreement of any counterclaim or otherwise any express indication that

counterclaims should be calculated separately from the damages awarded on affirmative

claims. As such, the specific words used to describe the calculation lend no support to the

theory that counterclaims should be calculated in a distinct manner. Cf. Adler v. Double

Eagle Properties Holdings, LLC, No. W2014-01080-COA-R3-CV, 2015 WL 1543260,

at *10 (Tenn. Ct. App. Apr. 2, 2015) (holding that a contract was not an easement where

the term “easement” was never mentioned in the contract).

Further, Defendants’ calculations run counter to the examples Mr. Hammet

provided in the Fee Agreement to explain the application of the Additional Fee. As stated

in the agreement, if 101 Construction received 100% of its requested damages, the Firm

would receive all of its $150 an hour Bonus Fee rate. If 101 Construction received 50%

of its requested damages, the Firm would receive half of its $150 an hour Bonus Fee rate.

Again, this example shows a single calculation based on money requested and awarded

with nary a mention of counterclaims. To inject a second prong into the calculation to

create a distinction between amounts recovered for claims and counterclaims therefore

directly conflicts with the example provided demonstrating a single calculation taking

into account only amounts requested and recovered.

Defendants argue, however, that this interpretation ignores the context of the Fee

Agreement relative to the pending arbitration. Although context is a relevant

consideration in interpreting a contract, see Silva, 2003 WL 23099681 at *2, we are not

persuaded that this consideration undermines our conclusion. As noted, at the time that

the parties entered into the contract, the Firm was engaged in representation of 101

Construction in two pending arbitrations. Thus, the Firm was well aware of the context of

the representation at the time the contract was drafted and the manner in which claims

- 10 -

and counterclaims are treated in the arbitration context. Despite this knowledge, the Firm

chose to illustrate the calculation necessary for determining the Additional Fee without

reference to a distinction or separation between damages related to claims and

counterclaims. Moreover, the arbitration award at issue in this case supports 101

Construction’s interpretation of the contract, as the arbitrator came to a single award by

simply subtracting the amounts owed on the successful counterclaims from the amounts

awarded on the successful claims.

“‘A contract term is not ambiguous merely because the parties to the contract may

interpret the term in different ways.’” Adler, 2015 WL 1543260, at *8 (quoting Staubach

Retail Services-Southeast, LLC v. H.G. Hill, 160 S.W.3d 521, 526 (Tenn. 2005)). In this

case, Defendants’ interpretation of the contract is simply not supported by the language it

chose to use in drafting the Fee Agreement. Rather, the plain language of the Fee

Agreement, particularly the express example provided therein, provides for a single

calculation of the Additional Fee taking into account only two figures: the damages

requested at the final arbitration hearing and the damage awarded at the conclusion of the

arbitration. In the absence of an ambiguity, we apply the plain language of the contract as

written without resort to extrinsic evidence.11 Adkins v. Bluegrass Estates, Inc., 360

S.W.3d 404, 412 (Tenn. Ct. App. 2011) (quoting Shuttleworth, Williams, Harper,

Waring & Derrick, PLLC v. Smith, No. W2007-02295-COA-R3-CV, 2010 WL 744375,

at *2–3 (Tenn. Ct. App. March 5, 2010)). (“If the contract is unambiguous, then the court

should not go beyond its four corners to ascertain the parties’ intention.”).

As previously discussed, a directed verdict is appropriate “with regard to an issue

that can properly be decided as a question of law because deciding purely legal questions

is the court’s responsibility, not the jury’s.” In re Estate of Marks, 187 S.W.3d at 27.

Interpretation of an unambiguous contract is an issue of law. Guiliano, 995 S.W.2d at 95.

Consequently, the trial court erred in denying 101 Construction’s directed verdict as to

the meaning of the Fee Agreement. Consequently, we reverse the decision of the trial

court and hold, as a matter of law, that the Fee Agreement is entitled to only a single

reasonable interpretation and requires a single calculation as to the amount of the

Additional Fee owed.

B. Prejudgment Interest

In addition to their dispute as to the overall calculation of the Additional Fee, the

parties also dispute whether the contract unambiguously provides that prejudgment

interest should be considered in the calculation. For its part, 101 Construction contends

that no ambiguity exists in the contract and prejudgment interest should be included

among the damages requested and awarded for purposes of calculating the Additional

11

We therefore pretermit any consideration of 101 Construction’s prior acceptance of the

calculation submitted by the Firm in the H&P Smyrna matter with regard to the interpretation of the Fee

Agreement.

- 11 -

Fee. Defendants contend that the contract is ambiguous and that this issue was properly

decided by the jury, which appears to have rejected consideration of prejudgment interest

in the calculation.

In the present case, 101 Construction contends that the Additional Fee should

account for the prejudgment interest it sought, but was not awarded, in the Emerald

Group arbitration matter.12 101 Construction cites Tennessee Code Annotated section 47-

14-123, which considers prejudgment interest “as an element of, or in the nature of,

damages[.]” By that token, 101 Construction argues that no ambiguity exists regarding

the inclusion of prejudgment interest as “Requested Damages” under the calculation of

the Additional Fee. Defendants argue, however, that that prejudgment interest should not

be included in the calculation, as prejudgment interest is an equitable measure of relief

that should be considered only within the scope of the arbitration matter at issue. In their

calculation of the H&P Smyrna matter, prejudgment interest was not included in the

damages sought by 101 Construction.

After our review, we do not discern an ambiguity in the Fee Agreement as to

whether prejudgment interest should be included in the calculation of the Additional Fee.

As previously discussed, the calculation of the Additional Fee requires a comparison of

“Requested Damages” to “Awarded Damages.” Requested Damages refers to “the

amount of monetary damages” requested, whereas Awarded Damages means “the

amount of monetary damages” awarded. Thus, these figures must both be determined by

reference to the “monetary damages” requested and awarded.

Based on our research, we must conclude that the term “monetary damages”

includes prejudgment interest. In Tennessee, prejudgment interest is considered “interest

as an element of, or in the nature of, damages[.]” Tenn. Code Ann. § 47-17-123. A trial

court can award prejudgment interest in its discretion “in accordance with the principles

of equity[.]” Id. When a party is entitled to compensatory damages, a plaintiff can also be

entitled to prejudgment interest “as part of the compensatory damages.” Myint v. Allstate

Ins. Co., 970 S.W.2d 920, 928 (Tenn. 1998). The ruling in Myint called on courts in

Tennessee “to articulate a different, more flexible standard for considering prejudgment

12

The prejudgment interest issue in the present case has been dogged by procedural confusion. In

motions for summary judgment and directed verdicts, 101 Construction contended that, as a matter of

law, prejudgment interest should be calculated as part of the “the amount of material damages” requested

by 101 Construction at the end of the arbitration hearing. The trial court denied each motion, holding that

101 Construction and the defendants had materially different understandings of the terms of the

agreement. Before and after these rulings, however, the trial court presented jury instructions that advised

the jury that “[a]s a matter of law, I’m instructing you that prejudgment interest is a type of monetary

damages.” No objection was made to the instruction as it was given, and no party addressed it further

during jury deliberations, after the verdict, in a subsequent motion for directed verdict, or during this

appeal. Because we resolve this issue as a matter of law, the procedural irregularities are confusing but

not material.

- 12 -

interest claims.” Scholz v. S.B. International, Inc., 40 S.W.3d 78, 83 (Tenn. Ct. App.

2000).

As we construe the Myint decision, the Tennessee Supreme Court

has shifted the balance to favor awarding prejudgment interest whenever

doing so will more fully compensate plaintiffs for the loss of use of their

funds. Fairness will, in almost all cases, require that a successful plaintiff

be fully compensated by the defendant for all losses caused by the

defendant, including the loss of use of money the plaintiff should have

received.

Id. (citations omitted). Following that ruling, this Court has held that an insurance policy

that extended to “all damages” accrued by a policyholder unambiguously included

prejudgment interest as part of the damages covered by the contract. Malone v. Maddox,

No. E2002-01403-COA-R3-CV, 2003 WL 465668 at *5 (Tenn. Ct. App. Feb. 25, 2003).

This Court disagreed with the assertion that “the concept of ‘damages’ alluded to in the

[insurance] coverage does not include prejudgment interest.” Id. In other states, courts

have long held that contracts that include damages are not ambiguous when concerning

whether prejudgment interest applies as damages. See, e.g., Guin v. Ha, 591 P.2d 1281,

1286 (Alaska 1979) (“The issue, therefore, is whether prejudgment interest is an item of

“damages” within the damage liability clause. We believe that our prior decisions

establish . . . that prejudgment interest is an item of compensatory damages.”); Mayer v.

Medical Malpractice Joint Underwriting Ass’n, 663 N.E.2d 274, 276–77 (Mass. App.

Ct. 1996) (holding that no ambiguity regarding prejudgment interest existed when a

contract compensated for damages); Baxley v. Nationwide Mut. Ins. Co., 430 S.E.2d

895, 899 (N.C. 1993) (holding that courts should not limit the definition of a word if an

insurance contract does not limit the term); Austin v. Midgett, 583 S.E.2d 405, 407−408

(N.C. App. 2003) (holding that prejudgment interest should be included as damages in a

contract which does not expressly exclude them as such). Thus, authority in Tennessee

and outside this jurisdiction has generally indicated that the term “damages” includes

prejudgment interest.

Defendants’ argument that the “monetary damages” in the Fee Agreement deal

only with “direct damages” arising out of a breach of contract is also not compelling.

According to Defendants, direct damages does not include prejudgment interest, but

rather includes only damages that “arise naturally or ordinary from a breach of contract.”

Moore Const. Co. v. Clarksville Dep’t of Elec., 707 S.W.2d 1, 14 (Tenn. Ct. App. 1985)

(quoting Roanoke Hospital Association v. Doyle & Russell, Inc., 215 Va. 796, 214

S.E.2d 155, 160 (1975)). Respectfully, Defendants’ argument is not persuasive. The

contract does not require a calculation based on “direct damages,” nor is that term used in

any pleading filed in the trial court. Rather, the Firm, in its wisdom, chose to use the term

“monetary damages” in this contract. Thus, even if we were to assume that the term

- 13 -

“direct damages” does not include prejudgment interest,13 such an assumption would

have no relevance to the question presented in this case regarding the proper

interpretation of the term “monetary damages.” Moreover, while prejudgment interest is

awarded based on equitable considerations, it has continually been classified as a form of

damages regardless of the nature of relief it provides. As stated by this Court, “[d]amages

means damages. It can not fairly be understood here to be ‘something else.’” Marcum v.

Ayers, 398 S.W.3d 624, 628 (Tenn. Ct. App. 2012).

The addition of the word “monetary” does not change our conclusion. The use of

the term monetary damages, like money damages, is considered a common redundancy

for the word damages. Garner’s Dictionary of Legal Usage 586 (3d ed. 2011). Moreover,

there can be no dispute that prejudgment interest is monetary in nature. Consequently, if

the term “damages” generally contemplates an award of prejudgment interest, the term

“monetary damages” maintains the same connotation.

Further, the Defendants’ argument that “[u]se of judicial precedence [sic] to

defined terms in arbitration is not correct” is not well taken. Notwithstanding the

Defendants’ lack of citations to defend this claim, Tennessee courts have consistently

examined judicial precedent in examining matters of arbitration. See, e.g., Berent v.

CMH Homes, Inc., 466 S.W.3d 740 (Tenn. 2015) (holding that federal arbitration

statutes did not preempt state law governing unconscionability of the arbitration

agreement); Pugh’s Lawn Landscape Co., Inc. v. Jaycon Development Corp., 320

S.W.3d 252 (Tenn. 2010) (holding that ordinary, not special, appellate standards of

review apply in arbitration matters); Lasco Inc. v. Inman Construction Corp., 467

S.W.3d 467 (Tenn. Ct. App. 2015) (holding that Tennessee courts can uphold arbitration

awards “in the faces of arguments that the arbitrator exceeded his power, the objections

to the awards concerned the underlying correctness of the award, rather than whether

such an award was authorized pursuant to the arbitration agreement.”). We are not

persuaded to ignore that precedent here.

In sum, Tennessee law recognizes prejudgment interest as a form of damages,

which is generally synonymous with “monetary damages.” The agreement does not

further define the term, which allows this Court to interpret the term with its plain and

ordinary meaning. See Fisher v. Revell, 343 S.W.3d 776, 779 (Tenn. Ct. App. 2009)

(citing Ballard v. North American Life & Casualty Co., 667 S.W.2d 79 (Tenn. Ct. App.

1983) (holding that contractual terms that express the parties’ intent “should be given the

usual, natural, and ordinary meaning.”)). Based on our interpretation, 101 Construction

requested prejudgment interest as part of its damages sought in the arbitration award. The

compensation contract expressly calculated monetary damages requested in the

13

The Firm and Mr. Hammet cite no law that expressly holds that “direct damages” excludes

amounts awarded as prejudgment interest.

- 14 -

arbitration matter. Therefore, 101 Construction is entitled to a directed verdict concerning

breach of contract and the subsequent calculations conducted by the Defendants.14

II. Motion for a New Trial

101 Construction also argues that the trial court erred in failing to grant a new trial

based on issues involving evidence and jury instructions. When appellate courts are

presented with multiple issues on appeal and find one to be dispositive, the remaining

issues have consistently been found as pretermitted. In re Jamie B., No. M2016-01589-

COA-R3-PT, 2017 WL 2829855 at *8 (Tenn. Ct. App. June 30, 2017) (citations omitted).

Because the trial court erred in not granting a directed verdict regarding the defendants’

breach of contract, any additional questions about whether the court should have granted

a new trial are pretermitted.

III. Damages

Given 101 Construction’s entitlement to a directed verdict on grounds of the

calculation of the claims and counterclaims as well as the calculation of prejudgment

interest, we turn now to the calculation of damages that 101 Construction is entitled from

these directed verdicts. As stated in the Fee Agreement, the Additional Fee is determined

by: 1) dividing the Awarded Damages from the Requested Damages to determine the

Success Rate, 2) multiplying the Success Rate by $150 to determine the Bonus Rate, and

3) multiplying the Bonus Rate by the number of hours billed on the matter. By dividing

the amount of recovery ($428,934.45) over the amount of requested damages, which

includes prejudgment interest ($1,088,721.57), the Success Rate is 39.4%. When 39.4%

is multiplied by $150 an hour, the Bonus Rate would equal $59.10 an hour. When $59.10

an hour is multiplied by the 1,434.20 hours billed on the Emerald Group matter, the

resulting Additional Fee is $84,761.22. Because the Firm and Mr. Hammet retained

$152,096.91 after the conclusion of the Emerald Green matter, the defendants overpaid

themselves by $67,335.69.

101 Construction also seeks the award of prejudgment interest on the amount

owed to it. From our review of the record on appeal, 101 Construction first requested

prejudgment interest in its renewed motion for a directed verdict. The failure to

specifically plead prejudgment interest in initial or amended pleadings, however, does not

preclude a court from awarding prejudgment interest. Story v. Lanier, 166 S.W.3d 167,

18081 (Tenn. Ct. App. 1995) (allowing prejudgment interest when it was first raised in

a motion for new trial). Thus, we must conclude that this request was timely made.

14

There is some argument in 101 Construction’s brief as to the affirmative defense of waiver as

raised by Defendants in the trial court. Defendants in their brief assert that waiver is not an issue. Because

the Defendants concede they have not raised a waiver defense to 101 Construction’s claim in this case, we

see no reason to review this issue.

- 15 -

The purpose of awarding prejudgment interest is to fully compensate a plaintiff for

losing access to funds which he or she was legally entitled. Myint, 970 S.W.2d at 927

(citation omitted). As a matter of equity, the certainty and ascertainable nature of the

plaintiff’s claims are used as non-dispositive factors when considering whether to award

prejudgment interest. Id. at 928. As shown through Myint, awards of prejudgment

interest are more likely to occur “whenever doing so will more fully compensate

plaintiffs for the loss of use of their funds.” Scholz, 40 S.W.3d at 83. However,

prejudgment interest may be inappropriate when the party seeking that interest

unreasonably delayed the pursuit of a claim or the legal proceedings after the claim was

made. Id. at 8384 (citations omitted).

Although the issue of prejudgment interest was raised both in the trial court and on

appeal, we must note that little effort was made to argue this issue in either court. For

example, the bulk of 101 Construction’s application for an award of prejudgment interest

is contained in a single footnote of its appellate brief. Perhaps unsurprisingly, Defendants

also do not devote considerable argument to this issue.

An award of prejudgment interest generally involves three questions: (1) whether

to award prejudgment interest; (2) the interest rate to be applied, not to exceed 10% per

annum, and (3) the date upon which interest should accrue. Nothing in 101

Construction’s appellate brief addresses the latter two questions. Moreover, because of

the jury verdict, the trial court was never in a position to exercise its discretion to

consider whether prejudgment interest was warranted and in what manner, based on the

particular equities in this case. Because of the discretionary nature of prejudgment

interest, however, we conclude that the trial court is in the best position to determine this

issue. As such, we remand to the trial court for a determination of whether prejudgment

interest should be awarded, and if so, the appropriate interest rate and accrual date.

CONCLUSION

The judgment of the Davidson County Chancery Court is reversed. This cause is

remanded to the trial court with orders to direct a verdict in favor of 101 Construction

against the Firm and Mr. Hammet in the amount of $67,335.69 and determine whether

prejudgment interest should be awarded, and if so, the proper interest rate and date of

accrual. Costs of this appeal are taxed to the appellees, Lawrence B. Hammet, II, and

Todd & Floyd, PLC, for which execution may issue if necessary.

_________________________________

J. STEVEN STAFFORD, JUDGE

- 16 -