In the United States Court of Federal Claims

No. 19-892C

(Filed: September 23, 2019)

(Re-Filed: October 7, 2019) 1

*********************

LOC PERFORMANCE PRODUCTS,

INC., Bid protest; post-award bid

protest; 28 U.S.C. §

Plaintiff, 1491(b)(4) (2018); 48 C.F.R.

§ 15.306 (2018); technical

v. evaluation; competitive range

determination; responsibility

THE UNITED STATES, determination; prejudice.

Defendant.

*********************

Christian B. Nagel, Tysons, VA, for plaintiff. Gregory R. Hallmark

and Amy L. Fuentes, of counsel.

Eric E. Laufgraben, Trial Attorney, United States Department of

Justice, Civil Division, Commercial Litigation Branch, Washington, DC,

with whom were Joseph H. Hunt, Assistant Attorney General, Robert E.

Kirschman, Jr., Director, Douglas K. Mickle, Assistant Director, for

defendant. Robert B. Nelson, Lieutenant Colonel, U.S. Army, Chief, Trial

Team II, Contract & Fiscal Law Division, U.S. Army Legal Services

Agency, of counsel.

OPINION

BRUGGINK, Judge.

This is a post-award bid protest by Loc Performance Products, Inc.

(“Loc”), of an award by the Army of contracts for armor and turret system

hardware and platform integration kits, which are parts of weapons systems

on military tactical vehicles. The Army awarded contracts to two companies,

1

This opinion was originally issued under seal to permit the parties an

opportunity to propose redactions on or before October 4, 2019. The parties

proposed redactions on October 4, and we adopt their redactions.

O’Gara-Hess & Eisenhardt Armoring Company LLC (“O’Gara”) and Ibis

Tek, Inc. (“Ibis Tek”), neither of which intervened in this protest.

The parties filed cross-motions for judgment on the administrative

record. The matter is fully briefed, and we held oral argument on September

17, 2019. Because the Army rationally evaluated Loc’s proposal and

excluded it from the properly-constructed competitive range, we deny

plaintiff’s motion for judgment on the administrative record and grant the

government’s motion.

BACKGROUND

The Army published a request for proposals (“RFP”) on October 25,

2017, seeking parts of military tactical vehicles’ weapons systems: armor and

turret system hardware and platform integration kits. 2 The Army would

award up to three indefinite delivery, indefinite quantity contracts based on

which proposals offered the best value to the Army. It planned to award

contracts without discussions, but reserved the right to engage in discussions

and to allow offerors to revise their proposals. The solicitation stated that the

Army could set a competitive range and limit it to the greatest number of

offers that would permit efficient competition among the most highly rated

proposals.

The solicitation also repeatedly advised offerors that they were

responsible for providing sufficient detail and evidence to allow the Army to

perform its evaluation. Administrative Record (“AR”) 183-85. The Army

first stated its expected production rates for the solicited products in the

Delivery or Performance section: “Up to 50 kits per month for each of the

Armor Hardware, turret systems and [platform integration kits]

configurations and related spares along with the capability to ramp up within

6 months to a minimum of 300 kits per month of each configuration related

spares.” AR 155.

2

Armor hardware is “Gunner Protection Panels and Kits,” which include

“mechanical, electrical and electromechanical components such as cables,

gunner accessory package, turret drive motors, controllers and transparent

armor.” Administrative Record 138. A turret system is “hatch assembly, slew

bearing and gear ring for tactical vehicles,” which will interface with Gunner

Protection Kits. Id. Platform integration kits “provide the unique mechanical

and electrical interfaces to integrate Remote Weapon Systems [] to a variety

of U.S. Government [] platforms.” Id.

2

A Source Selection Evaluation Board (“SSEB”) would evaluate

proposals on three factors: Technical, Past Performance, and Price. The

Technical factor was most important, and the Technical and Past

Performance factors combined were more important than Price. The Army

could award a contract to other than the lowest-priced offeror or the highest

technically rated offeror.

The Technical factor includes three subfactors: Manufacturing Plan,

Quality Assurance Plan, and Management Plan. The Manufacturing Plan and

Quality Assurance Plan were equally important, and each was more

important than the Management Plan. The Army would evaluate each

subfactor for strengths, weaknesses, and uncertainties. It would assign an

adjectival rating (Outstanding, Good, Acceptable, Marginal, or

Unacceptable) to each subfactor and a cumulative rating for the Technical

factor. Relevant here are the ratings “Acceptable” and “Marginal.” A

“Marginal” Technical rating means that the “[p]roposal has not demonstrated

an adequate approach and understanding of the requirements, and/or risk of

unsuccessful performance is high.” AR 191. An “Acceptable” Technical

rating means that the “[p]roposal meets requirements and indicates an

adequate approach and understanding of the requirements, and risk of

unsuccessful performance is no worse than moderate.” Id. Loc challenges its

overall rating on the Technical factor and its ratings on subfactors 1 and 3.

Under Technical Subfactor 1: Manufacturing Plan, the Army required

a detailed, realistic, supportable plan for producing and testing armor

hardware, turret systems, and platform integration kits. The Army directed

offerors to describe “the complete Armor Hardware, Turret Systems and

[platform integration kits], including cable harness assemblies, gunner

accessory package [], turret drive motors, controllers and transparent armor”

as well as “essential manufacturing facilities and equipment.” AR 263.

The Army also instructed offerors to “[p]rovide a complete flow

diagram of the proposed assembly line, including test, inspection, and build.”

Id. The Army repeated here that offerors must indicate “capability to meet

production rates of a minimum of 50 kits per month as a minimum along with

the capability to ramp up within 6 months to a minimum of 300 kits per

month for each of the configurations.” Id. It also directed offerors to propose

subcontractors and describe their involvement.

Under Technical Subfactor 2: Quality Assurance Plan, the Army

required offerors to describe their Quality Management System and how the

3

offeror would address quality requirements with subcontractors and

suppliers.

Under Technical Subfactor 3: Management Plan, the Army required

offerors to detail how manufacturing would meet the solicitation

requirements. This included a detailed Integrated Master Schedule (“IMS”),

which is a multilayered schedule of tasks for completing the target effort.

The Army explained: “The IMS should include all events to be

accomplished and support each task achievement criteria. Include a

breakdown of the Armor Hardware, Turret Systems and [platform integration

kits] in substantial detail showing specific piece-parts, sub-assemblies and

components required. Include/discuss parts and assemblies that have lead

times in excess of 120 days.” Id.

The Army further required a description of the offeror’s Configuration

Management System, addressing “how engineering changes, deviations and

waivers to drawings and specifications are processed, reviewed, and acted

upon.” Id. The description needed to include the organization of the

Configuration Management System, a chart of individuals involved, and a

plan to address configurations changes with subcontractors.

The solicitation requirements included Sections C.3.4 Start of Work

Meeting, C.3.5 Accident/Incident Report, C.3.6 Warranty, and C.5 OPSEC

Requirements. Each section stated the agency’s basic expectation. For

instance, the start of work meeting would occur within thirty days after

contract award and the minimum warranty was 12 months. The solicitation

also required offerors to propose a first article test plan, which would allow

the Army to respond to the first article test report “[w]ithin 30 calendar days

after receiving the test report.” AR 149.

To satisfy Factor 2 Past Performance, the Army required offerors to

“identify pertinent past history, which indicates that similar efforts of equal

or greater complexity have been performed using the [offeror’s] existing

plant capability and demonstrate satisfaction of customer requirements.” AR

264. It requested a list of contracts in performance or awarded within the past

three years. The Army would evaluate Past Performance for relevance and

quality, assigning a rating of Substantial Confidence, Satisfactory

Confidence, Neutral Confidence, Limited Confidence, or No Confidence.

Loc does not challenge its rating on Past Performance.

Regarding Factor 3 Price, the Army directed offerors to submit pricing

according to the RFP’s Pricing Matrix, which covered pricing for all

4

production and spares line items. The Army would calculate a “total

evaluated price” for each offer and review the contract line items for

unbalanced pricing. The Army would evaluate prices for reasonableness and

use that determination in its best value tradeoff analysis.

Fourteen offerors submitted proposals, which the SSEB evaluated

according to the three factors. It rated Loc “Marginal” on the Technical factor

overall and “Substantial Confidence” on Past Performance. Loc’s total

evaluated price was [ ].

Loc’s Manufacturing Plan, Technical subfactor 1, proposed [

] for manufacturing the armor hardware, turret systems, and platform

integration kits. “Loc’s overarching plan for the production, procurement,

and inspection of the GPK System kits will utilize [

], as well as leverage Loc’s robust supply base.” AR 859.

Loc explained that two kits would be manufactured [ ] whereas

manufacturing the turret system kit required [

]. Loc represented that [

]. Loc provided layouts of its manufacturing capacity in [

].

Loc explained that [ ] had the capacity to produce fifty

gunner protection kit systems per month. It “had identified constraints and

developed plans to meet the demands for ramping up to 300 kits per month.”

AR 876. Loc concluded that, although the [ ] could produce

300 kits per month, the [ ] “would need to [

] or [ ]” to produce 300

kits per month. AR 879. Loc provided some explanation of what [ ]

it would need and stated that “Loc is prepared to [

] or [ ],” but it did not offer a specific

timeline or plan for [ ]. Id.

Loc also included a flow diagram of its assembly line. Its Figure 20

was “a sample production flow diagram that will be utilized for the GPK

System Program at the [ ] facility.” AR 873. That diagram listed four

parts above a diagram of “Example Assembly Flow for four PN’s at the

[ ] Plant.” Id. Loc included a paragraph explaining its assembly line.

On Technical subfactor 1, the SSEB rated Loc’s Manufacturing Plan

“Marginal.” It found a significant weakness regarding the ramp up plan and

a weakness regarding the assembly line flow diagram. A significant

weakness existed because “the offeror [did] not provid[e] a plan or timeline

5

for [ ]

to meet the 300 kits per month production rate.” AR 1756. The SSEB found

“no indication that the rate of 300 kits per month could be reached within a

6 month period.” Id. The SSEB also assigned a moderate risk weakness

because “the offeror did not provide adequate and complete flow diagram of

the proposed assembly line.” Id. Overall, the SSEB concluded that Loc’s

Manufacturing Plan presented a high risk of unsuccessful performance. Loc

protests its Manufacturing Plan rating.

Loc’s Quality Assurance Plan, Technical subfactor 2, provided

narrative and visual explanations of its quality assurance processes. The

SSEB found that Loc’s Quality Assurance Plan was thorough, rating it

“Good.” It assigned Loc a strength for exceeding its expectations and found

no weaknesses. The SSEB concluded that the Loc’s Quality Assurance Plan

presented a low risk of unsuccessful performance. Loc does not protest its

Quality Assurance Plan rating.

Loc’s Management Plan, Technical subfactor 3, provided its IMS, the

multilayered schedule showing how tasks will come together to complete

manufacture, but Loc’s IMS addressed only one part, the [

]. Loc reasoned that the solicitation only instructed offerors to

address parts with particularly long lead times when it stated: “The IMS

should include all events to be accomplished and support each task

achievement criteria. Include a breakdown of the Armor Hardware, Turret

Systems and [platform integration kits] in substantial detail showing specific

piece-parts, sub-assemblies and components required. Include/discuss parts

and assemblies that have lead times in excess of 120 days.” AR 263

(emphasis added). Because only the [ ] had a more than

120-day lead time, Loc limited its discussion to that part in its IMS.

Loc also provided a narrative explanation and flow chart of its

Configuration Management System. That system addressed Engineering

Change Notices and how those notices move through Loc’s management

system. Loc did not use the term “Engineering Change Proposal” or the

acronym “ECP,” but it did discuss Engineering Change Notices.

Loc listed RFP Sections C.3.4 Start of Work Meeting, C.3.5

Accident/Incident Report, C.3.6 Warranty, and C.5 OPSEC Requirements in

its “Responsibility Assignment Matrix,” which was a chart marking who was

responsible for each section. Regarding Section C.3.4 Start of Work Meeting,

Loc stated in its Project Integration Management paragraph that “Loc will

hold a Start of Work [] meeting with Government to establish the baseline

6

requirements and stakeholders’ expectations along with identifying the

[ ] [] to manage the program.” AR 898. Loc also

mentioned the start of work meeting in its Project Communication

Management paragraph, stating that Loc and the government would develop

a[ ] at the start of work meeting. Regarding Section C.5

OPSEC Requirements, in its Project Communication Management paragraph

Loc stated, “Loc has an [ ] to complete annual

OPSEC training for the personnel assigned to the program.” AR 900. Loc did

not provide a dedicated section of its proposal addressing Sections C.3.5

Accident/Incident Report or C.3.6 Warranty.

Regarding the first article test approval process and its relationship to

the production schedule, Loc proposed to deliver the first article test report

on [ ], and begin first month production on [ ].

The SSEB found one significant weakness, two other weaknesses, and

a point of uncertainty in Loc’s Management Plan and rated it “Marginal.” It

determined that Loc’s IMS presented a significant weakness because its

schedule did not include “piece-parts, subassemblies, or components but

instead gave a very high and general overview of the schedule.” AR 1757-

58. The SSEB found that “insufficient detail in the IMS appreciably increases

the risk of unsuccessful contract performance.” AR 1758.

Furthermore, Loc’s Management Plan presented a moderate risk

weakness because it failed to provide an adequate description of the process

for reviewing and acting on engineering changes, specifically how an “ECN

becomes an ECP.” AR 1758. Loc’s Management Plan also presented a

moderate risk weakness because it failed to address the solicitation

requirements for Sections C.3.4 Start of Work Meeting, C.3.5

Accident/Incident Report, C.3.6 Warranty, and C.5 OPSEC Requirements.

Finally, the Army was uncertain regarding the start of production

pending first article test approval because Loc proposed starting production

during the Army’s 30-day approval period. Based on these three weaknesses

and the perceived uncertainty, the Army considered Loc a high risk of

unsuccessful performance. Loc protests its Management Plan rating.

To satisfy the Past Performance factor, Loc provided eight

questionnaire responses, all of which the Army found relevant. Four

responses indicated substantial confidence, three indicated satisfactory

confidence, and one indicated that Loc at least met contractual minimums.

7

The SSEB assigned “Substantial Confidence” to Loc’s ability to perform the

contract based on its past experience. Loc does not protest this assessment.

On Price, the SSEB found that Loc had a total evaluated price of

[ ]. Loc properly proposed unit prices for all line item numbers and

quantity ranges as required by the RFP. The SSEB found, however, that

Loc’s pricing “appears to be unbalanced from quantity range to quantity

range for the [

] . . . .” AR 2237. The

SSEB found that “[

].” Id. The SSEB also compared Loc’s total evaluated price to the

Independent Government Cost Estimate evaluated price, [ ] million,

concluding that Loc’s price was [ ].

Thirteen other offerors submitted proposals. The SSEB rated four

offers “Unacceptable” overall on the Technical factor, meaning they were

ineligible for award. We list the other ten offerors’ ratings below (including

Loc’s ratings for context):

Technical Price Past

Offerors Subfactor 1 Subfactor 2 Subfactor 3

Overall (Millions) Performance

Awardees

Substantial

O’Gara Acceptable Acceptable Good Acceptable [ ]

Confidence

Satisfactory

Ibis Tek Acceptable Acceptable Marginal Acceptable [ ]

Confidence

Also Included in the Competitive Range

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

Excluded from the Competitive Range

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

Substantial

Loc Marginal Good Marginal Marginal [ ]

Confidence

[ ] [ ] [ ] [ ] [ ] [ ] [ ]

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

8

[

[ ] [ ] [ ] [ ] [ ] [ ]

]

After the SSEB completed the evaluation of each factor for each offer,

it “identified several areas of concern.” AR 2183. The SSEB chairperson and

contracting officer briefed the Source Selection Authority (“SSA”), and “[a]t

the conclusion of the briefing, as a result of varying evaluation results and a

range of prices,” the SSA determined that it would be beneficial to enter into

discussions for revision of certain technical points and prices. Id. The SSA

decided to set a competitive range of less than all of the most highly rated

proposals for efficiency.

The Pre-Negotiation Objective memorandum, signed by the

contracting officer after briefing the SSA, provided context for why the

Army decided not to enter into discussions with certain offerors. Regarding

Loc, the Army stated that the combination of Loc’s Technical weaknesses

“increases the risk of unsuccessful contract performance to an unacceptable

level.” AR 2185. The Army concluded that “going into discussions with this

offeror would result in a proposal re-write and therefore, [Loc] will not be

included in the competitive range.” Id.

The competitive range determination began with a summary of what

the Army considered in setting the range:

The Government evaluated proposals and determined which

were the most highly rated and eligible for inclusion in the

competitive range relying on the merits of each offer. The

merits of each offer were determined on the basis of (1) [t]he

quality of the technical proposal based on the ratings of each

proposal against all evaluation Criteria[;] (2) [t]he past

performance rating[; and] (3) [t]he proposed cost/prices.

AR 2207.

Before setting out the “supporting rationale for the factor ratings” for

all offers, the SSA summarized that the competitive range would include

O’Gara, Ibis Tek, [ ] “whose overall initial technical

factor ratings were Acceptable or higher.” AR 2208. The Army planned to

conduct discussions with those five offerors because the Army had identified

weaknesses in all of their Technical proposals and because it had price

concerns about [ ].

9

The SSA repeated the rationale for each offeror’s ratings before

returning to the five offerors in the range. He summarized salient information

for each offeror: the Technical rating (“Good” for [ ] and “Acceptable”

for the other four offerors), the Past Performance rating, and the total

evaluated price of each. The SSA concluded that the Technical and Past

Performance ratings “coupled with their total proposed prices establishes

these Offerors with enough merits to be included in the competitive range as

their proposals offer the best value to the Government.” AR 2268.

The Army allowed offerors in the competitive range to engage in

discussions and revise their proposals. The offerors submitted final proposals

on September 28, 2018. The SSA then completed a source selection decision,

performing a best value tradeoff and finding that O’Gara and Ibis Tek offered

the most benefit to the Army. The contracting officer also completed a price

negotiation memorandum, finding both awardees’ prices reasonable.

In the source selection decision, the SSA compared the Technical,

Past Performance, and Price rankings for each of the five offerors in the

competitive range. The SSA found that O’Gara’s “Acceptable” Technical

rating (the most important factor) coupled with its [ ] evaluated

price in the competitive range made O’Gara “the most advantageous

proposal.” AR 2787. The SSA also noted that O’Gara offered [

].

The Army had the flexibility to award up to three contracts. After it

concluded that O’Gara offered the best value proposal, the SSA found that

“[t]o enhance the production capability and competition during the life of the

contract, it is in the Government’s best interest to secure a second source.”

Id. The SSA decided that, because Ibis Tek also had an “Acceptable”

Technical score, “Satisfactory Confidence” Past Performance score, and the

[ ] evaluated price, Ibis Tek was the next best proposal. The

SSA decided it was worthwhile to award a contract to Ibis Tek, because

“[t]he minimum guarantee for each multiple award contract is low enough

that it makes it beneficial for the Government to pay $100,000.00 to have a

second source available to meet the requirements.” Id. Making two contract

awards increased competition for delivery orders and flexibility for meeting

demand during high demand periods.

The SSA considered [ ] next, due to its highest overall Technical

rating (“[ ]”) paired with a [ ] both awardees. The SSA

determined that it would not be beneficial to the Army to award a third

contract to [ ], because its [ ] proposal meant that it would not

10

offer “realistic competition” to O’Gara and Ibis Tek during contract

performance. AR 2788. The SSA noted that the Army had anticipated that a

third contract might result in an “idle award” and decided to forego awarding

a third contract to [ ]. Id.

Likewise, the SSA weighed the benefits of awarding a contract to

[ ], but concluded that “the best possible mix of production capacity versus

current and future requirements is best satisfied by two contractors.” Id.

Making a third award “would represent disproportionate excess production

capacity in relationship to the anticipated fieldings, resulting in production

capacity and labor force, and thus a detriment rather than a benefit, to all

three contract awardees.” Id. The SSA concluded that “O’Gara and [Ibis Tek]

provide the best overall value to the Government” and would be awarded

contracts. AR 2789.

The contracting officer made a responsibility determination for both

O’Gara and Ibis Tek. Regarding [ ], the contracting officer relied on

review of the System for Award Management and the exclusions recorded

there; the Past Performance Information Retrieval System; the Federal

Awardee Performance and Integrity Information System; and the

information in the pre-award survey prepared by the Defense Contract

Management Agency. The contracting officer determined, among other

responsibility findings, that as of January 2019 [ ] had a satisfactory

performance record and a satisfactory record of integrity and business ethics.

After the Army provided Loc with its post-award briefing, Loc

protested at GAO and GAO dismissed its protest as untimely. Loc filed its

complaint here on June 18, 2019.

DISCUSSION

Plaintiff advances three arguments: (1) that the Army arbitrarily

assigned weaknesses to Loc’s Technical proposal; (2) that the Army

contravened the solicitation by only considering the Technical factor in its

competitive range determination; and (3) that the Army abused its discretion

in assigning “[ ]” to [ ] Past

Performance and improperly determined that it was a responsible contractor.

Our review of the Army’s decisions considers whether they were “arbitrary,

capricious, an abuse of discretion, or otherwise not in accordance with law.”

5 U.S.C. § 706 (2018); 28 U.S.C. §1491(b)(4) (2018). In other words, the

court’s “task is to determine whether the procurement official’s decision

lacked a rational basis or the procurement procedure involved a violation of

11

a regulation or procedure.” Tinton Falls Lodging Realty, LLC v. United

States, 800 F.3d 1353, 1358 (Fed. Cir. 2015) (citation omitted). If the Army’s

decisions fail to meet this standard of review, the protestor must also show

that it was prejudiced by the Army’s conduct, specifically whether, absent

the error, it would have had a substantial chance of receiving the contract.

Bannum, Inc. v. United States, 404 F.3d 1346, 1351-53 (Fed. Cir. 2005).

For the reasons discussed below, Loc has not demonstrated that the

Army’s ratings and competitive range determination lacked a rational basis

or violated the law. Because Loc would not have a substantial chance of

award even if [ ] were excluded, we do not reach the question of [

] representations and responsibility. We therefore deny plaintiff’s

motion for judgment on the administrative record and grant the government’s

motion.

I. The Army Rationally Rated Loc’s Technical Proposal “Marginal.”

Loc disagrees with the Army’s evaluation of its Technical proposal,

arguing that the Army should have rated Loc “Acceptable” and included it in

the competitive range. We disagree. Loc has not shown that the Army’s

rating of Loc as “Marginal” was arbitrary, capricious, or an abuse of

discretion.

An agency is entitled to discretion in its evaluation of offers.

Grumman Data Sys. Corp. v. Widnall, 15 F.3d 1044, 1046 (Fed. Cir. 1994).

Technical evaluations, in particular, are “the minutiae of the procurement

process . . . which involve discretionary determinations of procurement

officials that a court will not second guess.” E.W. Bliss Co. v. United States,

77 F.3d 445, 449 (Fed. Cir. 1996). When a protestor challenges the agency’s

evaluation as arbitrary or capricious, the court looks at whether the agency’s

decision “entirely failed to consider an important aspect of the problem,

offered an explanation for its decision that runs counter to the evidence

before the agency, or is so implausible that it could not be ascribed to a

difference in view or the product of agency expertise.” Motor Vehicle Mfrs.

Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983).

Here, Loc disputes the “Marginal” rating it received on two

subfactors, and on Technical overall, instead of “Acceptable” ratings. The

difference between the ratings is that “Marginal” indicates a belief that the

offer presents a less than adequate approach and understanding or a high risk

of unsuccessful performance, whereas “Acceptable,” one step higher,

12

indicates an adequate approach and understanding or no worse than moderate

risk of unsuccessful performance. AR 191.

Regarding Loc’s “Marginal” Manufacturing Plan, plaintiff has not

demonstrated that the Army failed to consider all of the information Loc

provided or that it implausibly evaluated Loc’s proposal. The Army assigned

Loc a significant weakness because it did not sufficiently explain how it

would ramp up to 300 kits per month in a six-month timeframe using [

] and potentially subcontractors. Although Loc represented that its

[ ] had 300-kit-per-month capacity at the time of the proposal,

Loc also represented that the [ ] would be involved in the

manufacturing process. For the [ ], Loc “would need to [

] or [ ]” to

produce 300 kits per month. AR 879.

The agency’s confusion is completely understandable. Loc’s proposal

regarding production rates was made unclear by its explanation that [

] would be needed to reach peak production rates and that the [

] would require [ ] or [ ] to reach the 300

unit level, but it neglected to give a solid commitment as to when that would

happen. Loc was responsible for presenting information in a detailed, clear

fashion, and the agency acted within its discretion when it determined that

Loc’s Manufacturing Plan did not provide sufficient assurance that Loc was

able to ramp up to a higher production rate within the time required.

The Army also assigned Loc a weakness for failing to provide a

complete flow diagram of its assembly line. Loc provided a flow diagram

depicting the assembly line for four parts, by way of an example. This

diagram left room for reasonable minds to differ on whether the example

[ ] facility assembly line provided a complete picture of Loc’s process

to test, inspect, and build. The Army was not required to read into the

proposal the explanation that the same flow diagram applied to all parts and

was within its discretion to rate Loc “Marginal” on its Manufacturing Plan.

Regarding Loc’s “Marginal” Management Plan, the SSEB assigned

Loc a significant weakness for failing to provide a thorough IMS. The

solicitation stated, “The IMS should include all events to be accomplished

and support each task achievement criteria. Include a breakdown of the

Armor Hardware, Turret Systems and [platform integration kits] in

substantial detail showing specific piece-parts, sub-assemblies and

components required. Include/discuss parts and assemblies that have lead

times in excess of 120 days.” AR 263.

13

Loc read this section to mean that it was only required to address parts

and assemblies with long lead times; in other words, Loc did not believe it

needed to provide “substantial detail showing specific piece-parts, sub-

assemblies and components required.” Id. Loc chose to address only one part

because it was the only part with a lead time of more than 120 days. The

Army understood this section to mean that offerors should address all events

to be accomplished; piece-parts, sub-assemblies, and components required;

and parts and assemblies with long lead times. The Army found Loc’s

approach wanting because it did not cover piece-parts, sub-assemblies, and

components, and it assigned Loc a significant weakness.

We agree with defendant that the last sentence of the section should

not be read to negate the prior two sentences. The IMS section

unambiguously communicates that the Army wanted a detailed, multilayered

schedule, comprehensively reviewing the tasks and all parts involved. The

Army rationally concluded that Loc’s Management Plan presented a

significant weakness. If Loc was confused regarding the amount of detail the

IMS should provide, it had the opportunity to question how the Army would

apply the section prior to submitting its proposal.

The Army also assigned two moderate risk weaknesses and an

uncertainty to Loc’s proposal. The Army found gaps in the information Loc

presented regarding how Loc addressed engineering changes, how Loc

addressed various solicitation sections such as warranty and OPSEC

requirements, and how production would proceed after the first article test.

The SSEB was perhaps ungenerous in filling gaps in Loc’s descriptions, but

Loc did in fact fail to fully address at least two solicitation requirements—

warranty and the accident/incident report—in its proposal. Loc has not

shown that the agency ignored relevant information or reached contradictory

conclusions; instead, the Army exercised its discretion when it found these

to constitute moderate weaknesses.

Even if the Army was incorrect on the moderate risk weaknesses in

Loc’s Management Plan, Loc’s Technical proposal still contained the two

other significant weaknesses we discussed above. Loc failed to show that the

Army improperly rated its Technical proposal “Marginal” overall. As such,

Loc cannot demonstrate that it had a substantial chance of award unless it

can show that the Army was required to include it in the competitive range,

which we address below.

14

II. The Army Properly Set the Competitive Range.

Loc argues that the agency improperly set the competitive range by

using the Technical rating “Acceptable” as the exclusive demarcation line,

while failing to consider the Past Performance and Price factors. We

disagree. The Army considered all factors and was within its discretion to

rely on the Technical factor to determine which offers should be included in

the competitive range.

After an agency evaluates proposals according to the factors stated in

the solicitation, if the agency intends to conduct discussions, it will establish

a competitive range. FAR 15.306(c)(1). “Based on the ratings of each

proposal against all evaluation criteria, the contracting officer shall establish

a competitive range comprised of all of the most highly rated proposals,

unless the range is further reduced for purposes of efficiency . . . .” Id. If the

contracting officer determines that “the number of most highly rated

proposals . . . exceeds the number at which an efficient competition can be

conducted,” and the solicitation notified offerors, “the contracting officer

may limit the number of proposals in the competitive range to the greatest

number that will permit an efficient competition . . . .” FAR 15.306(c)(2).

FAR 15.306(c) notably does not require the agency to perform any

tradeoff between price and other non-cost factors when establishing a

competitive range. Comp. FAR 15.101, 15.101-1 (best value tradeoff), with

FAR 15.306(c) (competitive range). The contracting officer likewise is not

required to redo the technical evaluators’ work in setting the range; instead

the range is based on “the ratings of each proposal against all evaluation

criteria.” FAR 15.306(c)(1). The agency is authorized to limit the range

beyond the most highly rated proposals to “the greatest number that will

permit an efficient competition.” FAR 15.306(c)(2). The FAR does not

specify how the agency must decide how many proposals will create efficient

competition.

Contracting officers have “broad discretion in determining

competitive range,” and the court will not disturb that determination “unless

clearly unreasonable.” Birch & Davis Int’l, Inc. v. Christopher, 4 F.3d 970,

973 (Fed. Cir. 1993). It is not this court’s role to substitute our judgment for

that of the agency, and “the agency does not have to include all technically

acceptable proposals that have a low price in the competitive range.” Red

River Computer Co., Inc. v. United States, 120 Fed. Cl. 227, 239 (2015). The

court is concerned with whether the agency took proposals’ ratings into

15

account in setting the range and explained the reasoning underlying which

proposals were included and excluded.

First, there is no dispute that the Army thoroughly evaluated all three

factors—Technical, Past Performance, and Price—before setting the

competitive range. It assigned ratings on the Technical and Past Performance

factors. As to Price, it determined the total evaluated price of each offer and

compared it to the Independent Government Cost Estimate. The only step the

Army saved for after discussions was the price reasonableness analysis,

which would be used as part of the best value tradeoff.

Second, the Army considered the ratings on all three factors when

deciding how to set the competitive range. At the beginning of the

competitive range determination, the SSA stated that the competitive range

was based on the “merits of each offer” and “the merits of each offer were

determined on the basis of” all three evaluation components. AR 2207. The

competitive range determination incorporated the SSEB’s evaluation of all

offerors on each of the three factors. Furthermore, in the analysis following

the repetition of the SSEB’s ratings, the SSA stated that, except [ ], the

agency planned to address price concerns for each offeror in the competitive

range, showing that the Army in fact accounted for prices when deciding how

to shape the competitive range. The Army likewise acknowledged that one

offeror in the range, [ ], had a lower Past Performance rating than others,

but because it had an “Acceptable” Technical rating coupled with its price,

the Army chose to include it in the range. The Army also stated that the

offerors included in the range were included based on Technical and Past

Performance “coupled with” price. AR 2268. Even if the Army could have

been more detailed, the competitive range determination reflects

consideration of all three factors.

Finally, to winnow the number of most highly rated proposals for

efficient competition, the SSA prioritized the most important factor:

Technical. This was the part of the proposals that told the Army how the

offerors would produce parts of military vehicle weapons systems. The SSA

chose to include not only the one offer that had a “Good” Technical rating

but to expand the range to include those four offers rated “Acceptable” on

Technical. He excluded only those offerors whose Technical rating meant

they had a high risk of unsuccessful performance. The SSA explained the

reasoning behind why each offeror would be included or excluded based on

the Army’s understanding of its ability to manufacture the needed parts.

16

We find that the Army reasonably decided to prioritize the Technical

factor in creating the competitive range. The Army was not clearly

unreasonable in deciding that discussions should be reserved for those

offerors who either had a low or moderate risk of unsuccessful performance.

It was not required to include all low-priced offerors in the competitive range,

particularly not at the expense of lowering its expectations for the Technical

proposal. The SSA had the authority to limit the range for efficient

competition and chose a perfectly logical cutoff point for inclusion or

exclusion.

Loc ultimately argues that the SSA should have included a lengthier

discussion of specifically how Past Performance and Price entered into the

SSA’s decision to exclude Loc. See AR 2267. The agency could have

included more detail in its discussion of why it excluded five offerors from

the competitive range. The comparison that Loc demands, however, goes

beyond what was required of the Army. Even if the SSA had included more

explanation discussing Loc’s Past Performance and Price evaluation, Loc has

not demonstrated that the outcome would be different given its technical

inferiority. We need not disturb the competitive range determination.

III. Even if the Army’s Evaluation of [ ] was Flawed, Loc is not

Prejudiced.

Loc also argues that [ ] was not eligible for award because it is

not a responsible contractor and its Past Performance rating was inflated due

to misrepresentations. Loc seeks to supplement the administrative record

with a Department of Justice press release that may call into question [

] representations and the responsibility determination.

We do not need to consider the issue. Even if [

], Loc’s position would not be improved and the Army

would not be required to redo the procurement. The solicitation stated that

the Army could award up to three contracts. It awarded two. [

] and the Army only awarded an additional

contract for increased competition and production capacity. Alternatively,

even if the Army needed to select a second contractor, it properly excluded

Loc from the competitive range and, thus, Loc would not have a chance of

being awarded a contract. Because Loc would not have a substantial chance

of being awarded a contract if we found the Army’s responsibility

determination was made in error or that [

], we need not address that argument further. The court denies Loc’s

17

motion to supplement the administrative record because the submitted press

release is not necessary to effective judicial review.

CONCLUSION

In sum, because the Army rationally evaluated Loc’s proposal and

excluded it from the competitive range, we deny plaintiff’s motion for

judgment on the administrative record and grant the government’s motion.

The Clerk is directed to enter judgment for defendant. No costs.

s/Eric G. Bruggink

ERIC G. BRUGGINK

Senior Judge

18