The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

Dawson-Alamo 1 JV, LLC ) ASBCA No. 60590

)

Under Contract No. FA3047-10-D-OOI2 )

APPEARANCES FOR THE APPELLANT: Johnathan M. Bailey, Esq.

Kristin E. Zachman, Esq.

Bailey and Bailey, P.C.

San Antonio, TX

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.

Air Force Deputy Chief Trial Attorney

Erika L. Whalen Retta, Esq.

Justin D. Haselden, Esq.

Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WILSON

ON THE GOVERNMENT'S MOTION TO DISMISS COUNT TWO

OF APPELLANT'S AMENDED COMPLAINT

Dawson-Alamo I JV, LLC (DAI or appellant) has appealed the contracting

officer's (CO's) deemed denial of its certified claim for work performed, allegedly

outside the statement of work (SOW). The Air Force (AF or government) has moved

to dismiss count two of appellant's amended complaint, in which appellant raised the

allegation of mutual mistake for the first time.

ST A TEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On July 12, 2010, the AF awarded Contract No. FA3047-10-D-OOI2 to DAI

for miscellaneous construction projects on Lackland Air Force Base, San Antonio, Texas,

and related installations. This was a fixed-price, indefinite-delivery, indefinite-quantity

requirements contract. (R4, tab 3 at 2, 5-10)

2. On September 22, 2011, DAI was awarded Delivery Order (D035) for

repair of the interior rooms at Lackland Air Force Base Building 150, valued at

$2,500.000 (R4, tab 10 at 1-2).

3. The parties executed Modification No. 01, effective September 30, 2011,

adding repairs and increasing the price of D035 by $500,000 to $3,000,000 (R4,

tab 12 at 1-3). Bilateral Modification No. 03, effective March 25, 2013, incorporated a

revised comprehensive SOW and estimate. This revised SOW added repairs to the

understructure of Building 150 and increased the price ofD035 by $347,335.14 to

$3,347,335.14. (R4, tab 15 at 1-4)

4. Appellant submitted a letter, dated October 29, 2012, to the CO outlining

costs related to "the extensive changes to this project that has [sic] been established by

[the government] and DAI JV. All items and tasks are needed to give the end user a

useable/workable facility." (Supp. R4, tab 53 at 1) The government, by memorandum

dated January 11, 2013, stated "your request is being returned without action. [The

Civilian Engineering Center] feels that your letter does not state the facts clearly."

(App. supp. R4, tab 145)

5. Appellant submitted a request for equitable adjustment (REA) to the AF,

dated January 16, 2013, requesting payment of $465,521.98 for extra materials and

work performed under the contract as well as a contract time extension of 210 days

(R4, tab 21 at 1). Appellant's REA stated:

As you review the E4-Clicksf*l cost estimate and compare

to the original SOW, you will find that all of the additional

work was not included in the original scope of work or

awarded task order, but all was coordinated and performed

per [the government]'s direction .... Per [two government

offices], all items were deemed necessary .... Additional

items include, but are not limited to, electrical

infrastructure, bracing for the TV's [sic], emergency exit

corridor, and communications infrastructure, all of which

were not part of the original SOW and E4Clicks cost

estimate. Unfortunately several needed items were

overlooked in the mechanical portion of the project as

well. The original SOW and MOD#l called for 10 RTU's

when the true requirement was for 12 units in this area of

the construction including all necessary components.

(Id. at 1-2) Appellant then submitted a certified claim, dated August 8, 2013, to the

CO requesting the same amount, arguing its performance of "additional work outside

the scope of the awarded task order is a binding change under the Changes clause"

(R4, tab 24 at 4). Appellant further noted:

During the performance of the Project the Government

directed DA 1 to perform additional work that was beyond

the scope of the agreed E4click [sic] estimate presented by

• E4Clicks appears to be a system for producing estimates of project costs.

2

the Government and accepted by DAI as the scope of the

work for the project at the beginning of the project...the

Government directed work amounted to $462,521.98.

(Id.) DA I attached its REA to its claim (R4, tab 24 at 65-80).

6. By email dated May 17, 2016, appellant appealed the deemed denial of its

claim to the Board.

7. Appellant asserted in its June 28, 2016 complaint that the government

directed it to perform work beyond the scope of the SOW. causing it to incur the extra

mat~rials and work expenses, and argues that such changes were pursuant to the

Changes clause (com pl. , 13 ). However, appellant later amended its complaint to

include count two, alleging in the alternative mutual mistake (amended compl., 16).

This legal argument was developed further in appellant's pre-hearing brief, in which

appellant requested reformation of D03 5 on the basis of mutual mistake, though no

longer in the alternative (app. pre-hearing br. at 53-59).

DECISION

The AF moves to dismiss appellant's mutual mistake allegation, asserting it is a

new claim not submitted to the CO, and thus not within the Board's jurisdiction. In its

motion, the AF argues mutual mistake requires proof of different elements and

requests different relief than the constructive change theory, and that both of these

issues indicate the mutual mistake count is a separate claim. As this separate claim

was not submitted to the CO for a final decision, the AF posits that the Board lacks

jurisdiction over it, and it must be dismissed.

In its response, appellant argues that the operative facts of its original claim

provided for mutual mistake and the addition of this new legal theory does not alter the

nature of the claim. Thus, it is not a new claim and the Board retains jurisdiction.

The Contract Disputes Act requires all claims by a contractor be submitted to

the CO for decision. 41 U.S.C. § 7103(a)(l ). "We lack jurisdiction over claims raised

for the first time on appeal, in a complaint or otherwise." Optimum Servs., Inc.,

ASBCA No. 57575, 13 BCA, 35,412 at 173,726 (citing Versar, Inc., ASBCA

No. 56857, 10-1 BCA, 34,437 at 169,957). However, the Board possesses

jurisdiction to entertain claims that arise from the same operative facts as those

presented to the CO, seek essentially the same relief, and merely assert differing legal

theories for that recovery. ABC Data Entry Sys., Inc., ASBCA No. 59865, 16-1 BCA

, 36,557 at 178,048 (citing King Aerospace, Inc., ASBCA No. 57057, 16-1 BCA

, 36,451 at 177,651). "Matching the elements of [the original legal theory] against the

elements of the new legal theories [appellant] posed does not resolve the question

3

whether the claim before us in the amended complaint is the same one presented to the

CO.'" Public Warehousing Co., ASBCA No. 56022, 11-2 BCA, 34,788 at 171,228

(citing URN Indus., Inc. v. United States, 962 F.2d 1013, 1024 (Fed. Cir. 1992)). "The

introduction of additional facts which do not alter the nature of the original claim ... or

the assertion of a new legal theory of recovery, when based upon the same operative

facts as included in the original claim, do not constitute new claims." Trepte Constr.

Co., ASBCA No. 38555, 90-1 BCA, 22,595 at 113,385-86. "In determining a claim's

scope, we are not limited to the claim document but can examine the totality of the

circumstances. No particular wording is necessary to express it, but the CO must have

'adequate notice' of the basis and amount of the claim." Sauer, Inc., ASBCA

No. 60366, 16-1 BCA, 36,565 at 178.101.

In Todd Pacific Shipyards Corp., ASBCA No. 55126, 06-2 BCA, 33,421, the

contractor (Todd) had signed a contract for, inter alia, servicing various Navy ships in

dry dock, including the U.S.S. Sacramento. Though Todd incurred expenses to

maintain a dry dock large enough to service the Sacramento, the Navy decided to

decommission the ship early and transfer two vessels which would likely have been

serviced at Todd's dry dock to another fleet. In seeking to recover the incurred costs

for certification and upkeep, Todd advanced several legal theories, ranging from

constructive change to an effective partial termination for convenience and equitable

reimbursement under FAR Part 50. In its claim, Todd alleged the Navy had engaged

in actions. which altered the amount of work Todd could receive under the contract by

moving some of the vessels to be serviced to a different fleet. Todd then advanced

two new legal theories for the first time in its complaint: provisions for an equitable

adjustment allowed in the Cost Accounting Standards, and the Navy's delay in or

elimination of the contract's work requirements. Id. at 165,684-86. Despite the range

of elements and proof the theories would require, we allowed Todd to proceed under

the new legal theories as "appellant essentially alleged the operative facts necessary to

those theories in its ... claim" as well as supporting documents to which the claim

·referred. Id. at 165,688.

We must look at the elements required to prove mutual mistake in order to

determine whether the theory springs from the same operative facts alleged in

appellant's claim. To prove mutual mistake, appellant must show:

1) the parties to the contract were mistaken in their belief

regarding a fact;

2) that mistaken belief constituted a basic assumption

underlying the contract;

3) the mistake had a material effect on the bargain; and

4

4) the contract did not put the risk of the mistake on the

party seeking reformation.

SKE Base Servs. GmbH, ASBCA No. 60101, 18-1 BCA ,r 37,159 at 180,901 (citing

National Australia Bank v. United States, 452 F.3d 1321, 1329 (Fed. Cir. 2006)).

Rather than prove these elements, at this stage, appellant's claim must merely allege

facts that could plausibly support each ele"ment. Ashcroft v. Iqbal, 556. U.S. 662, 678

(2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). Next, we

inspect the operative facts alleged to see if they plausibly support each element of

mutual mistake.

Similar to Todd Pacific Shipyards, we find that it does. The claim and prior

documents to which it referred alleged the government had directed appellant to

perform additional work beyond the government's SOW, which detailed what work

needed to be done to Building 150 at the time of award to achieve the government's

desired ends (SOF ,i 5). This is sufficient to allege, though not prove, that the parties

had a different understanding of the work required to complete D035 and thus were

both mistaken. As performance of the SOW was the entire point of D035, the scope

of the SOW qualifies as a basic assumption underlying the contract (SOF ,i 2). The

alleged mistake had a material effect on the bargain as it involved appellant allegedly

incurring significant costs it had not accounted for (SOF ,i 5). Finally, appellant

alleges the risk was not on it as to the cost of additional work, as evidenced by the

filing of their REA and certified claim (id.). The government was certainly on notice

that appellant believed it did not bear any risk of loss for the amount asserted. The

government cannot reasonably claim to have lacked notice of the matters alleged and

they do not differ materially from the essential nature of and operative facts in

appellant's claim to the CO.

Appellant's claim of mutual mistake also requests essentially the same relief as

that for constructive change. As the work at issue is already completed, should

appellant prevail on its theory of mutual mistake. reformation of 003 5 would afford

appellant practically the same relief as its original claim. Neither theory would create

any new obligations for either party at this point beyond the entitlement to the payment

appellant sought in its original claim. See Envtl. Chem. Corp., ASBCA No. 58871,

15-1 BCA ,i 36,110 at 176,288. We hold count two is not a new claim.

5

CONCLUSION

For the reasons stated above, the government's motion to dismiss is denied.

Dated: May 30, 2019

OWEN C. WILSON

Administrative Judge

Vice Chairman

Armed Services Board

of Contract Appeals

I concur

inistrative Judge Administrative Judge

Chairman Armed Services Board

Armed Services Board of Contract Appeals

of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 60590, Appeal of

Dawson-Alamo I JV, LLC, rendered in conformance with the Board's Charter.

Dated:

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

6