Opinion

Fortis Networks, Inc. v. United States

Court
United States Court of Federal Claims
Filed
May 9, 2019
Status
Published
On the bench
Thomas C. Wheeler
Cited by
0 cases
Authority
More cited than 7.6%

The opinion

In the United States Court of Federal Claims

No. 19-531C

(Filed: May 9, 2019)

*************************************

*

FORTIS NETWORKS, INC. *

* Motion to Dismiss; Subject Matter

* Jurisdiction; RCFC 12(b)(1);

* Contract Disputes Act; Election

* Doctrine

Plaintiff, *

*

v. *

*

THE UNITED STATES, *

*

Defendant. *

*************************************

David A. Rose, Rose Consulting Law Firm, Valdosta, Georgia, for Plaintiff.

Joseph A. Pixley, Trial Attorney, with whom were Joseph P. Hunt, Assistant Attorney

General, Robert A. Kirschman, Jr., Director, Deborah A. Bynum, Assistant Director,

Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington,

D.C., and Lauren M. Williams, Assistant District Counsel, U.S. Army Corps of Engineers,

Tulsa District, Tulsa, Oklahoma, for Defendant.

OPINION AND ORDER

WHEELER, Judge.

On April 10, 2019, Plaintiff Fortis Networks, Inc. filed an emergency motion for a

temporary restraining order and a preliminary injunction, asking this Court to stop the U.S.

Army Corps of Engineers (USACE) from using offsets to collect a debt. The Government

responded with a Motion to Dismiss the complaint under RCFC 12(b)(1), arguing that

Plaintiff is currently challenging the disputed debt before the Armed Services Board of

Contract Appeals (ASBCA) and therefore this Court is without subject matter jurisdiction

to rule on this matter. The case is now fully briefed and ready for decision.

As explained below, the Court agrees with Defendant and GRANTS Defendant’s

Motion to Dismiss this case. The Court also DENIES Plaintiff’s motion for a temporary

restraining order and preliminary injunction.

Background

Fortis entered into Contract No. W912BV-14-D-0005, Task Order 2, FY14 Multiple

Mechanical Repairs, with the USACE, to perform repair work at Fort Sill, Oklahoma.

Compl. 4. On November 7, 2018, the Contracting Officer issued a final decision giving

notice to Fortis of the assessment of liquidated damages for late performance, in the amount

of $578,445.00. This debt was partly satisfied by retaining the $82,000 balance remaining

to be paid to Plaintiff, which left a balance of about $496,000 still due to the Government.

Dkt. No. 6-1. On December 18, 2018, the USACE Finance Center sent to Fortis a demand

letter to repay the debt and included a blank “voluntary installment repayment agreement”

(VIRA) to repay over time. Dkt. No. 6-2. Plaintiff apparently had free choice in filling

out the repayment terms and returned the signed VIRA, promising to pay $1,000 per month

towards the debt. Dkt. No. 6-3. Fortis has made at least three monthly payments to

USACE. Compl. 14. Plaintiff subsequently filed a notice of appeal of the Contracting

Officer’s liquidated damages assessment with the ASBCA on January 16, 2019. A

complaint and answer have now been filed in that case, ASBCA No. 61941. Dkt. Nos. 11-

1, 11-2, 11-3.

While the appeal is pending, Government collection efforts have not stopped. The

USACE-Tulsa District Counsel found the VIRA executed by Fortis to be unacceptable in

that it lacked a repayment schedule and did not address maturity, interest, or other terms

relating to the debt. For those reasons, Tulsa District Counsel requested that the ACE

Finance Center continue offset collection against other payments due to Fortis under other

government contracts it is performing. Dkt. 7-3 at 2. Fortis has now filed this action in

this Court in an effort to stop the offset collection, arguing that without such relief, Fortis

faces financial ruin.

Discussion

A. Jurisdiction

Whether the Court has jurisdiction to decide the merits of a case is a threshold

matter. See PODS, Inc. v. Porta Stor, Inc., 484 F.3d 1359, 1365 (Fed. Cir. 2007). When

deciding a Rule 12(b)(1) motion to dismiss, a court must assume all the undisputed facts

in the complaint are true and draw reasonable inferences in the non-movant’s favor.

Acevedo v. United States, 824 F.3d 1365, 1368 (Fed. Cir. 2016). Further, the plaintiff

2

bears the burden of establishing facts sufficient to invoke this Court’s jurisdiction by a

preponderance of the evidence. Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746,

748 (Fed. Cir. 1988). In determining whether a plaintiff has met this burden, courts may

look “beyond the pleadings and ‘inquire into jurisdictional facts’ in order to determine

whether jurisdiction exists.” Lechliter v. United States, 70 Fed. Cl. 536, 543 (2006)

(quoting Rocovich v. United States, 933 F.2d 991, 993 (Fed. Cir. 1991)).

In support of its Motion to Dismiss, the Government argues that jurisdiction in this

case is barred by the “Election Doctrine.” This is a “body of jurisprudence” developed by

this Court under the Contract Disputes Act, 41 U.S.C. § 601 et. seq., which provides a

choice of forums in which to contest a contracting officer’s decision. National Neighbors,

Inc. v. U.S., 839 F.2d 1539, 1541-42 (Fed. Cir. 1988). The Election Doctrine holds that,

once a contractor makes a binding election to appeal an adverse decision to a board of

contract appeals, he cannot pursue his claim in this Court. “The Election Doctrine controls,

as a matter of law.” Id. at 1541.

Plaintiff counters that the Election Doctrine does not apply here because Fortis is

challenging the Government’s breach of the VIRA, not the merits of the Contracting

Officer’s final decision, which is the subject of the ASBCA appeal. Plaintiff maintains

that, since the USACE Finance Center provided the installment agreement form and

accepted several monthly payments, a binding contract was created, and a challenge to that

contract confers jurisdiction in this Court over a matter separate from the underlying

contract under challenge at the ASBCA.

As discussed, the Plaintiff has the burden of proof to show facts sufficient to invoke

this Court’s jurisdiction. If the Government’s collection actions were to be seen as

sufficiently separate from the underlying contract so as to avoid the Election Doctrine,

Fortis would still have to establish jurisdiction in this Court. Pursuant to the Tucker Act,

28 U.S.C. § 1491(a)(1), this Court has subject matter jurisdiction to hear claims against the

Government “founded . . . upon any express or implied contract with the United States.”

Where a plaintiff alleges that he entered into a contract with the Government, the plaintiff

need only make a “non-frivolous allegation of a contract with the government.” Mendez

v. United States, 121 Fed. Cl. 370, 378 (2015) (quoting Engage Learning, Inc. v. Salazar,

660 F.3d 1346, 1353 (Fed. Cir. 2011) (emphasis in original)). Accordingly, to show

jurisdiction, a plaintiff must plead the elements of a government contract: “(1) mutuality

of intent to contract; (2) consideration; (3) an unambiguous offer and acceptance; and (4)

actual authority on the part of the government’s representative to bind the government.”

Biltmore Forest Broad. FM, Inc. v. United States, 555 F.3d 1375, 1380 (Fed. Cir. 2009)

(citations omitted).

3

It is a far reach to characterize the VIRA in this case as a contract of any sort, and

Plaintiff did not plead facts sufficient to show the required elements. For example, Plaintiff

did not meet its burden of showing consideration, intent, or authority on the part of the

Government. Therefore, the Court holds that Plaintiff’s claim of breach of the VIRA is

insufficient to establish jurisdiction in this Court separate from the challenge to the

Contracting Officer’s final decision currently pending before the ASBCA. The Court

further holds that the Election Doctrine bars this Court from jurisdiction over the debt

collection practices related to that decision, which should be challenged as part of that

appeal.

For these reasons, the Court GRANTS the Defendant’s Motion to Dismiss and

DENIES Plaintiff Fortis’ Motion for a Temporary Restraining Order and Motion for

Preliminary Injunction. The Clerk of Court shall enter judgment accordingly.

IT IS SO ORDERED.

s/ Thomas C. Wheeler

THOMAS C. WHEELER

Judge

4

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.