The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

Bhate Environmental Associates, Inc. ) ASBCA No. 60903

)

Under Contract No. W912DY-11-D-0013 )

APPEARANCES FOR THE APPELLANT: Anna H. Browning, Esq.

Jack G. Kowalski, Esq.

Burr & Forman LLP

Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney

Kathryn R. Sommerkamp, Esq.

Margaret P. Simmons, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Huntsville

ORDER OF DISMISSAL

On 25 November 2016, the Board received the contractor's Notice of Appeal,

asserting that its "'request for equitable adjustment" was denied by the contracting

officer on 29 August 2016. This appeal was docketed as ASBCA No. 60903. The

government's motion to dismiss, which was predicated on Bhate's alleged failure to

state a proper claim, was received by the Board on 30 January 2017. In the conference

call of 27 July 2017, the Board discussed various options with the parties regarding the

next step. Bhate advised by correspondence dated 10 August 2017 that it was willing

to voluntarily withdraw this appeal without prejudice, subject to Bhate's right to

continue pursuit of the matters set forth in its Complaint against the government,

including the right, if necessary, to pursue subsequent appeal as appropriate.

By Order dated 14 August 2017, the Board informed the parties that it

intended to dismiss this appeal as requested by Bhate unless either party objected

within 14 days of the date of the Order. Although the Board received no objection

from the government, appellant requested that the order be revised further to remind

the government of its obligation to timely issue a contracting officer's final decision.

On 31 August 201 7, the Board advised the parties that it proposed to issue this

amended Order of Dismissal unless timely objections were received by 8 September

2017, which date was subsequently extended to 27 September 2017. A conference call

was convened on 18 September 2017. Accordingly, this appeal is dismissed without

prejudice. The parties are reminded of their relative obligations under the Contract

I

Disputes Act of 1978, 41 U.S.C. § 7103 including, without limitation, the

government's obligation to timely issue a contracting officer's final decision.

Dated: 19 September 2017

~~

~

REBAPAGE

Administrative Judge

Armed Services Board

of Contract Appeals

I certify that the foregoing is a true copy of the Order of Dismissal of the

Armed Services Board of Contract Appeals in ASBCA No. 60903, Appeal ofBhate

Environmental Associates, Inc., rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN

Recorder, Armed Services

Board of Contract Appeals

2

I

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.