Opinion

Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.

  • 2016 Ohio 8580
Court
Ohio Court of Claims
Filed
Dec 13, 2016
Status
Published
On the bench
Crawford
Cited by
0 cases
Authority
More cited than 3.4%

The opinion

[Cite as Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm., 2016-Ohio-8580.]

JUTTE ELECTRIC, LTD., et al. Case No. 2014-00318

Plaintiffs/Counter Defendants Referee Dale A. Crawford

v. DECISION OF THE REFEREE

OHIO FACILITIES CONSTRUCTION

COMMISSION

Defendant/Counter

Plaintiff/Third-Party Plaintiff

v.

STEED HAMMOND PAUL, INC., etc.

Third-Party Defendant/Fourth Party

Plaintiff

v.

BERARDI PARTNERS, INC.

Fourth-Party Defendant

{¶1} This matter comes to be heard on a trial to the Court held on August 1-11,

2016. Post trial briefs and replies have been submitted. The action involves a

December 20, 2010 contract entered into between Ohio School Facilities Commission

(OSFC) as the “Owner” and Jutte Electric, Ltd. (Jutte), the electrical contractor (Ex. 11,

12, 13); TransAmerica Building Company, Inc. (TransAmerica), the general trades

contractor; Vaughn Industries, LLC (Vaughn), the mechanical and plumbing contractor;

Hall Aluminum Products, the exterior doors and windows contractor; TP Mechanical

Contractors, Inc., the fire protection contractor; Bovis Lend Lease, Inc. (Lend Lease),

the project construction manager; and, SHP Design (SHP), the lead architect for the

Case No. 2014-00318 -2- DECISION

project. (Ex. A). SHP contracted with Berardi + Partners, Inc. (Berardi) to do design

work and to prepare the finalized construction drawing. (Ex. SHP, E & D).

{¶2} The entire project was a campus wide construction of academic and

dormitory buildings for the Ohio School for the Deaf and Blind. Due to some political

and funding issues, it was decided that the project would be separated into two

components; the dormitories and the academic buildings. It was decided that the

dormitory contract would go first. The contract budget for the dormitories project was

$6,712,626 with the electrical portion being $786,892 with Jutte as the low bidder. The

original contract was for sixteen dorms, eight on each side. The number of buildings

was later changed to six on each side, a change that was anticipated in the bidding

process. The buildings were residential buildings made of wood framing. One model

was to be constructed for high school students, one model for middle and elementary

students.

{¶3} The Court agrees with Jutte’s counsel, and most witnesses, that the project

was a mess from beginning to the end. It was poorly planned, poorly scheduled, poorly

administered, and the Court will add, the contractors poorly performed. Plaintiffs, Jutte

and Southwest Marine and General Insurance Company (Surety) claim that because of

numerous problems encountered on the project attributed to the OSFC that they

incurred an uncompensated loss of $940,130.29. Shortly after the project commenced

in the spring of 2011, Jutte had significant financial difficulties and was unable to

complete the job. Jutte filed for bankruptcy in June 2011. The Surety on Jutte’s bid

came onto the project and in August 2011 agreed to complete the project by funding

Jutte to complete the work on the bid. The Surety claims that by funding Jutte to

complete the project it steps into the shoes of Jutte and has standing as a plaintiff and is

entitled to recover alleged loss incurred by Jutte.

{¶4} OSFC has denied it did anything wrong that proximately caused Jutte and/or

the Surety any damage. In addition, OSFC filed a third party claim against SHP alleging

Case No. 2014-00318 -3- DECISION

that if OSFC is liable to Jutte and/or the Surety for breach of contract or negligence on

behalf of SHP or its contractors, then SHP is liable to OSFC for the damages incurred.

SHP, in turn, has filed its third-party claim against its contractor, Berardi, alleging that if

it is liable to OSFC for any of the damages incurred by Jutte and/or the Surety, then

Berardi is liable to SHP for the damages it incurs.

I: Project Issues

{¶5} From the beginning the project was fraught with issues. The original project

manager for OSFC, Robert Grinch (Grinch depo, p. 60) testified there were political

issues with the project with a change of governors but they decided to go forward with

the dorms while they were waiting for funding for the academic buildings. The project

actually started in March 2011, months later than planned. The project drawings which

were required by R.C. 153.01 to be “full and accurate plans, suitable for the use of

mechanic’s and other builders * * *” were never done by Berardi. Berardi had been paid

its full contract price with SHP so it had no incentive to produce further drawings.

Weather was also an issue early on in the project. Requests for Information (RFI) were

answered on the average of 13 days late. Most of the project managers could not get

along with each other which created friction, especially between Jutte, Lend Lease,

TransAmerica, and SHP. Recovery Schedules 2, 3, and 4 were not realistic and fire

system ratings were changed mid project.

TransAmerica Project Issues

{¶6} As the general trades contractor, TransAmerica was responsible for

preparing the property and constructing the foundation; framing, roofing (AAA Roofing

was its subcontractor); and, drywall and painting. During the project, TransAmerica had

the following problems all impacting the timing and cost of the project:

1) The work was not in sequence (Ex. 91, 81);

2) Delays in laying the slabs which in turn causes delays in framing;

Case No. 2014-00318 -4- DECISION

3) The framing was done off-site which caused the framing to be inaccurate and

delayed up to six months;

4) Roofing was delayed and at times poorly done by AAA Roofing, which caused

the contractors (i.e. Jutte) to be behind in their work;

5) Not meeting recovery schedules – delaying the other contractors (Ex. 14).

6) Roofs not meeting specifications – not certified;

7) Walls not done properly caused delays in the electrical work (Ex. 282).

{¶7} As Madison Dowlen, OSFC’s Project Administrator, testified, TransAmerica

didn’t build the building in the way that they – in the way that the project was intended.

TransAmerica chose to panel these buildings and have them panelized and built off site.

(Dowlen depo., p. 55). Dowlen further testified that the drawings did not cause this

problem. He further testified that the walls weren’t straight. (Downlen depo., p. 133).

The core meeting minutes of July 21, 2011 (Ex. 184) stated that the “delays [in the

project] were due to weather, framing issues and the characteristics of the buildings

themselves as they are not typical houses.”

{¶8} The general overall performance of TransAmerica as testified to by Dowlen

(Dowlen depo., p. 194), and as set forth in Ex. 185-186, is that TransAmerica’s

personnel did not have the knowledge or skills to perform the job. “Their performance

was poor.”

{¶9} Kenneth Jutte, President of Jutte, testified as to the project issues,

especially with respect to TransAmerica as follows:

“The whole job was messed up. So, I mean that’s a tricky, tricky question for me.

[What did the State do to cause you damage?] It started off messed up right out

of the gate. It was like walking up on a train wreck. It never got really in line, as

far as I am concerned.”

(Jutte depo., p. 50)

***

Case No. 2014-00318 -5- DECISION

“Everybody in front of us, so it’s from the layout of the building to the concrete, to

the dirt work, to the wood framing. We’re not supposed to be in a building until

it’s dried up. That means the windows are in, the roof’s on, no water’s getting in.

Our stuff’s not allowed to get wet.”

(Jutte depo., p. 61)

{¶10} TransAmerica also had problems with its agent-architect SHP. SHP chose

to have an unlicensed architect manage the project. SHP’s subcontractor, Berardi, was

routinely dilatory in delivery of a buildable design. In fact, it never delivered one that

was acceptable to TransAmerica or Lend Lease.

Jutte Project Issues

{¶11} Ken Jutte and Jutte Electric started the project bankrupt. Even though it

officially ceased to exist as a legally recognized business entity as of December 31,

2012. (Ex. BB). According to Ken Jutte, his company ceased to exist at the time he filed

bankruptcy in June 2011 (Jutte depo., p. 9-10, 12). Jutte testified that he couldn’t

maintain payroll in late 2010-2011 (Jutte depo., p. 123); there was a hold on his

supplies as of June 23, 2011 (Jutte depo., p. 123); he owed his suppliers Edison

Electric and Loeb a lot of money and he couldn’t pay them (Jutte depo., p. 85); there

was a tax lien against his property in Mercer County (Jutte depo., p. 123); as of

June 23, 2011, Jutte’s employees on site hadn’t been paid for seven weeks (Jutte

depo., 85); and, the bank had foreclosed on the shop in spring of 2011 (Jutte depo., p.

125).

{¶12} As a result of all of these issues Jutte did not have the manpower to

perform its contracted job. Ditches necessary to carry the under foundation power

remained open and wet for months. (Ex. B). Temporary power, which Jutte was to

install in March, was not completed until August – with supplemental labor provided by

Accurate Electric (Accurate).

Case No. 2014-00318 -6- DECISION

{¶13} It is clear to the Court that Ken Jutte was oblivious of his financial position

and the contractual commitments he made on this project and the other projects he was

working on. While his company was doing practically nothing on the job from the spring

of 2011 to August of 2011, he denied he needed more manpower to complete the job.

(See five-day notice, Ex. G; July 19, 2011 email, Ex. SHP HH). He originally planned

on having four or six people on the two dorm sites which was clearly not enough

manpower. Ken Jutte received the August 3, 2011 Notice of Termination letter (Ex. G)

listing fifteen items that Jutte had not performed properly, his response was “* * * this is

the same old Lend Lease story. It’s hurry up and wait, and there was no need for

additional manpower.” (Jutte depo., p. 97). Jutte told Keith that he would bring in more

manpower “just to shut Clay up.” (Jutte depo., p. 80). Even after being advised orally,

in emails, in the August 3, 2011 letter of termination, and by his agreement in the

Memorandum of Understanding (MOU) completed in the Bankruptcy Court (Ex. 310),

Jutte continued to put his head in the sand and denied his company had done anything

wrong on this project and the work did not need to be supplemented by Accurate

Electric. (Jutte depo., p. 207). It appears to be the position of Plaintiffs that while Jutte

may not have been perfect on the job (Ben York testimony, Ken Jutte testimony, and

Plaintiff’s counsel closing argument), the delays and the cost overruns were the fault of

others – especially Berardi and SHP for not having workable drawings; SHP and Lend

Lease for not responding to RFI’s on a timely basis; and OSFC and Lend Lease for not

bidding the other phase of the project on a timely basis and by having unworkable

recovery schedules.

{¶14} While the Court finds that these issues impacted the project and are mostly

attributable to the OSFC, there is not sufficient evidence to prove that these issues were

a cause of Plaintiff’s damages. Quite the contrary. While the drawings were poor, late,

and never complied with R.C. 153.01, there is no evidence that the drawings, or lack

thereof, proximately causes any of Plaintiffs’ damages.

Case No. 2014-00318 -7- DECISION

{¶15} Ken Jutte testified he didn’t really rely on the schedules. (Jutte depo., p.

207). Ben York testified that the electrical drawings “were workable” but they did cause

additional time. Neither York, Jutte, nor Plaintiffs’ expert, Timothy Calvey, ever testified

as to the quantification of the time delay attributed to the drawings or schedules.

Joshua Predovich, project manager for SHP, testified that while the drawings were not

complete or accurate, Jutte was not affected. The posted drawings were sufficient for

the work Jutte was to perform. Clay Keith testified that the trades work (TransAmerica)

was out of sequence causing an impact on the electrical work (Ex. 81, 91). James

Smith, site superintendent for Lend Lease, testified that Jutte was far behind on the

project because of a lack of manpower and equipment. He did not believe that the lack

of proper drawings had an effect on Jutte’s lack of performance. Even Joshua Wilhelm,

project manager for TransAmerica,1 testified that while the drawings were not workable

for TransAmerica, Jutte could follow them.

{¶16} There is no doubt that the RFI’s submitted by Jutte and other contractors

were not answered in a timely fashion. In general, they were delayed on the average of

13 days. Plaintiffs allege that the delays in RFI’s caused it to be delayed. Ben York,

Jutte’s third project manager commencing in August 2012, testified that he believed

Jutte was delayed because of these late responses. (Ex’s. 232, 233, 234-240).

Mr. York’s testimony about delays attributable after he came on the project was

subjective as to the delays. He believed the late RFI’s caused delay but he did not

attribute any particular delay to any late RFI. (See Ex. 86). Mr. York also testified that

the drawings were “workable” and he attributed no delay or cost overruns to the poor

drawings.

1TransAmerica filed a separate action against OFSC claiming damages for its losses on the

project resulting from OSFC’s breach of contract.

Case No. 2014-00318 -8- DECISION

II: Plaintiff’s Expert Testimony

{¶17} As a background, this case needs to be considered in two different time

periods, before and after the execution of the MOU. (Ex. 310). Tim Calvey was

Plaintiffs’ expert. He testified and submitted a report with regard to Plaintiffs’ damages.

One of the major problems with Tim Calvey’s report and testimony is that he does not

separate these time periods. Upon the signing of the MOU, OSFC, Jutte, and the

Surety agreed to move forward with Jutte completing the project (funded by the Surety).

As further explained below, Jutte agreed to fix specifically enumerated problems that

happened before the MOU and complete the rest of the project pursuant to the

Contract. Therefore, all claims before August 31, 2011, were settled and should not

have been included as damages. OSFC had its chance to include all outstanding

issues in the MOU and agreed that what needed correcting was a specific number of

items listed in the August 2011 5-day notice. (Ex. H).

{¶18} Mr. Calvey uses the “measured mile” approach in calculating the alleged

damages suffered by Plaintiffs. This method may be appropriate in some

circumstances. See Wood Electric Inc. v. Ohio Facilities Construction Commission,

Court of Claims Case no. 2014-00987; J&H Reinforcing & Structural Erectors, Inc. v.

Ohio School Facilities Commission, Court of Claims Case no. 2010-07644. However, it

is not appropriate in all circumstances.

{¶19} In order to be an appropriate method, the work completed in different

portions of the project (used by the expert for comparison purposes) must be sufficiently

similar. Mr. Calvey used periods of time that were not sufficiently similar. He included

the period of time prior to the MOU. This period should not have been considered

because anything that happened during that time is effectively considered settled, as

the project was moving forward under a new agreement between OSFC and Jutte.

{¶20} Further, Mr. Calvey made absolutely no effort to distinguish the causes of

delays and cost overruns on the project. In fact, he took the position that Jutte was not

Case No. 2014-00318 -9- DECISION

responsible for any of the delays throughout the duration of the project. As to the time

leading up to the August 2011 5-day notice, he testified that Jutte’s actions did not lead

to cost overruns. This is clearly contrary to the facts, as OSFC was forced to bring in

additional manpower to supplement Jutte’s work. The Court does not find Mr. Calvey’s

testimony regarding Jutte’s lack of impact on delays to be credible. Ben York, Jutte’s

on-site supervisor, admitted that Jutte was not perfect on the site. He felt that other

contractors were also at fault for delays. Clearly, Mr. York is more credible regarding

Jutte’s impact.

{¶21} The Court finds that Jutte’s improper handling of the project is inextricably

connected to problems caused by other contractors. The differentiation of delays

attributable to particular parties is an integral part of the causation analysis and

Mr. Calvey completely ignored it. The fact that the damage calculation does not

attribute anything to Jutte’s own failings is highly suspect and realistically improbable. It

leads the Court to doubt the validity of Mr. Calvey’s findings.

{¶22} “A party seeking damages for breach of contract must present sufficient

evidence to show entitlement to damages in an amount which can be ascertained with

reasonable certainty.” Tri-State Asphalt Corp. v. Ohio Dept. of Transp., 10th Dist.

Franklin No. 94API07-986, 1995 Ohio App. LEXIS 1554 (Apr. 11, 1995), citing Kinetico,

Inc. v. Independent Ohio Nail Co., 19 Ohio App.3d 26, 30 (8th Dist.1984). “Contract

damages must be shown with certainty and not left to speculation.” Father’s House Int’l,

Inc. v. Kurguz, 10th Dist. Franklin No. 15AP-1046, 2016-Ohio-5945, citing Samson

Sales v. Honeywell, Inc., 8th Dist. Cuyahoga No. 51139, 1986 Ohio App. LEXIS 9341

(Dec. 18, 1986). In general, compensatory damages must be shown with certainty, and

damages that are merely speculative will not give rise to recovery. “Although lost profits

need not be proven with mathematical precision, the evidence and theory of the case

must provide the finder of fact with known, reliable factors that can guide the

computation of damages.” RAE Assocs. v. Nexus Communs., Inc., 2015-Ohio-2166, 36

Case No. 2014-00318 -10- DECISION

N.E.3d 757 (10th Dist.). The evidence in this case is lacking such known, reliable

factors.

{¶23} Plaintiffs have failed to prove by a reasonably degree of certainty that

OSFC, as opposed to another contractor or their own conduct, proximately caused their

damages. With no evidence attributing damages to particular parties, the Court is left to

speculate.

III: Surety and its Investigation

{¶24} Based upon Ken Jutte’s testimony, Jutte Electric was bankrupt when it

started the project in the spring of 2011. When it bid on the project in October 2010, it

filed a performance bond in the amount of its bid, $786,892. The bond was written by

Southwest Marine and General Insurance Company. The Surety’s bond is set forth in

Ex. 309. The Surety was notified of Jutte’s lack of performance and possible default on

the project sometime in June 2011. Counsel for the Surety, Anne Meyers was

responsible for investigating the claim and reporting her findings to the Surety so that it

could make a decision regarding how it wished to proceed on the claim. She worked

with Contractors Operation Planning (COP) to investigate the Surety’s option on the

performance bond. Raymond Zetts was the senior claims adjuster employed by COP to

work with Anne Meyers in choosing its method of proceeding.

{¶25} A surety has several options available to it when facing the possible default

of the contractor for which it issued the performance bond. Since the main purpose of

performance bonds is to assure owners that they will receive the performance that they

bargained for, courts interpreting the common-law rights of sureties have acknowledged

the rights of sureties to choose their means and methods so long as the owner is made

whole. See 4 Bruner & O’Conner on Construction Law § 12:77. “Performance bond

protects the [oblige/owner] by making sure that it is not left with a partially completed

project * * *.” Trinity Universal Ins. v. United States, 382 F.2d 317 (5th Cir.1967).

Another important function of performance bonds is to “assure that the government has

Case No. 2014-00318 -11- DECISION

a completed project for the agreed contract price.” Id. Sureties have a common law

right to choose to either complete performance or finance the obligee’s completion.

Aetna Cas. & Sur. Co. v. United States, 845 F2.d 971 (Fed. Cir. 1988). In effecting

these rights, the surety “may satisfy its obligations in various ways * * * the surety may

formally take over the project and contract for its completion, or it may allow the project

to be defaulted and let the government complete or contract for the completion of the

project, in which case the surety is responsible for reasonable costs in excess of the

contract price. A performing surety may also satisfy its obligation by providing funds to

an insolvent contractor to complete performance.” Id. at 975.

{¶26} A surety’s obligation to perform does not arise unless and until its principal

has materially defaulted with respect to its obligations. See L&A Contracting Company

v. Southern Concrete Service, Inc., 17 F.3d 106 (5th Cir.1994) (holding that, “although

the terms ‘breach’ and ‘default’ are sometimes used interchangeable, their meanings

are distinct in construction suretyship law. Not every breach of a construction contract

constitutes a default sufficient to require a surety to step in and remedy it. To constitute

a default, there must be (1) material breach or series of breaches (2) of such a

magnitude that the obligee is justified in terminating the contract.”)

{¶27} While the parties quibbled during trial about whether or not Jutte was

technically defaulted, giving rise to a situation wherein the Surety’s obligations arose,

the Court finds that Jutte did in fact default and the Surety’s rights and obligations arose

when it was made aware of Jutte’s issues on the site. Even if Jutte was not technically

defaulted, the parties agreed to the MOU. In the MOU, OSFC, the Surety, and Jutte

agreed that the Surety would step in to provide financing so that Jutte could finish the

job. Therefore, the Surety’s rights and duties were supplemented by this document.

What was not altered was the Surety’s duty to properly investigate the claim before

choosing which method to employ in order to ensure the project was completed as

originally agreed to by Jutte. There is little controlling case law regarding what a

Case No. 2014-00318 -12- DECISION

sufficient investigation should entail. However, there are a number of notable sources

available to sureties which provide information to a surety regarding the scope and

breadth of its inquiry.2 At the very least, the Surety should thoroughly investigate its

underwriting file, interview its principal (contractor) and review its files, and interview the

owner and review any materials which demonstrate any problems on the project.

Anne Meyers’ Investigation

{¶28} Anne Meyers was ultimately responsible for ensuring a thorough

investigation occurred, as the Surety relied on her recommendation in making its

decision. She testified that in conducting the investigation, and prior to making her

recommendation to the Surety, she did not do any of the following:

1) review the underwriting file;

2) visit the construction site;

3) personally evaluate the equipment Jutte had on site to ensure they were

properly equipped to finish the job, or evaluate the qualifications of the Jutte

employees;

4) see the photos of the open trenches (Ex. B);

5) hire an architect to review the project plans or a scheduling expert to evaluate

the quality of the schedules.

Further, she could not recall if she did the following:

6) review Ex. 321, the email from Clay Keith to Mr. Zetts explaining that Jutte

had already utilized 40% of its projected labor for the entire project by July,

2011;

7) review Ex. H, the email from Bob Beal, President of Accurate Electric,

regarding Accurate’s proposal to finish the job.

2See Bond Default Manual, Tort and Insurance Practice Section of the American Bar Association

(Duncan L. Clore, 2nd ed., 1995); Bruce King, Takeover and Completion of Bonded Contracts by the

Surety (1995); William H. Haug, Financing Your ‘Solvent’ Principal – Success of Failure (1996); The Law

of Performance Bonds, Tort and Insurance Practice Section of the American Bar Association (1999).

Case No. 2014-00318 -13- DECISION

{¶29} Number 7 is important, because she testified that one of the reasons she

decided to recommend that the Surety hire Jutte to complete the project, as opposed to

bringing on another contractor, was that it would take too long to get the other

contractor up and running on the job. However, it is clear that Accurate was ready,

willing, and able to get to work. In fact, they were already on site supplementing Jutte’s

work.

{¶30} It is clear that there were many aspects of the project that she was

unaware of prior to her recommendation to the Surety. In fact, she testified that there

were certain things about the project that she just didn’t know, because those particular

things were more the responsibility of Ray Zetts. Ultimately, as demonstrated by the

afore-mentioned list, she relied heavily on the Ray Zetts’ reporting on his findings of his

own investigation.

Raymond Zetts’ Investigation

{¶31} Based on the testimony of Raymond Zetts, one of the first steps in his

investigation involved reviewing the bid documents and obtaining completion bids from

the other contractors who originally bid the job to determine if Jutte’s bid was

reasonable. From this he learned that Jutte had substantially underbid the project. Yet,

he later determined, based in part on his investigation, that the Surety could possibly

“beat the spread,” that is, do the job for less than the next lowest bidder (Accurate

Electric). He first visited the construction site sometime in June 2011 and met

separately with Ken Jutte and Clay Keith. From his meetings he learned that there were

some issues with drawings on the site and that buildings were late coming out of the

ground. He personally witnessed the open trenches left unfinished by Jutte (Ex. B). He

was not aware of the specifics related to drawing issues, i.e. that full and accurate

drawings had not yet been rendered. He was aware of some scheduling issues, but

only to the extent that some of the buildings were not yet out of the ground, even though

they should have been by that day. No change to the completion date was discussed.

Case No. 2014-00318 -14- DECISION

He was not aware of any of the dimensional issues on site related to the walls which

were built incorrectly off-site. He was also not aware of any issues with RFI’s. Nor was

he aware of any issues related to casework – i.e. that the casework contractor had not

yet been identified. According to Ken Jutte, this project had all sorts of problems from

the very beginning. (Jutte depo., p. 26-27, 37, 50-51, 52, 93, and 142-143). Yet,

Mr. Zetts testified that he was only aware of minor issues with drawings and a slight

delay with buildings coming out of the ground. Had he thoroughly investigated, he

would have been aware of the issues that plagued the project from the beginning.

{¶32} Mr. Zetts did not investigate Ben York’s background to determine if he was

qualified to act as the project manager on a project of this magnitude. Rather, he

reviewed a short summary of his work history and relied on Ken Jutte’s representation

that Mr. York was his best employee for the job. Mr. Zetts was made aware of the fact

that Jutte had at least 3 other active projects besides the School for the Deaf and Blind,

and he expressed concerns to Ken Jutte about how that may impact Jutte’s available

manpower. He mistakenly relied on Mr. Jutte’s promise that Jutte had additional

manpower available to complete the job, a promise which never came to fruition.

Further, Mr. Keith informed Mr. Zetts that as of July 2011, Jutte had already expended

1,600 hours on the job, or approximately 40% of its estimated labor for the entire job.

(Ex. E). That is, he was aware in July 2011 that Ken Jutte had substantially

underestimated the total manpower necessary for completion. Mr. Zetts could not recall

reviewing the construction contract before he made the decision to recommend that the

Surety complete the contract by funding Jutte. Mr. Zetts relied on very little information

regarding Jutte’s internal accounting and financials. In an email to Ken Jutte at the very

beginning stages of his investigation, he asked Ken Jutte for a job cost breakdown.

(Ex. 321). However, he never received any such document, save for one page detailing

Jutte’s preliminary estimates for bidding purposes. Mr. Zetts never reviewed any

document detailing day-to-day operating expenses, and it seems that no such records

Case No. 2014-00318 -15- DECISION

were actually maintained by Jutte. Mr. Zetts also testified that he did not recall

reviewing the bankruptcy documents, in particular the summary of schedules (Ex. I)

detailing Jutte’s financial situation at the time of the project; however, these documents

were reviewed by Anne Meyers, counsel for the Surety.

{¶33} Mr. Zetts did testify that he was fully aware of the deficiencies laid out in

the five day notice (Ex. G) and that those deficiencies were incorporated into the MOU,

such that the Surety would be responsible for ensuring they were rectified. According to

Paragraph 1 of the MOU, “The Principal [Jutte] agrees to complete the Work in

accordance with the requirements of the Contract and to correct the issues raised by

Obligee [OSFC] in its 5 day notice of August 10, 2011.” (Ex. 310).

{¶34} He did not review the underwriting file nor did he know anything about the

underwriting process. He communicated, sparingly, with the underwriting department.

He was aware of the fact that Jutte had been bonded in the past, but that was the extent

of his knowledge as it relates to previously issued bonds, i.e. he did not know anything

about the nature or extent of the investigations performed by the Surety prior to issuing

bonds. It should also be noted that Mr. Zetts is not a licensed electrician nor has he

ever served as a project manager on this type of construction project. He is also not an

accountant, although he did testify that he took some accounting classes as part of his

bachelor’s degree. The Surety did not hire an expert (i.e. a forensic accountant, or a

construction and/or scheduling expert) prior to making the decision to fund Jutte nor did

it analyze the likelihood that Jutte could complete the project as bid.

{¶35} The Court finds that the investigation performed by the Surety, by way of

Mr. Zetts, assisted in part by Anne Meyers, was inadequate for a project of this

magnitude. In particular, the Surety was not aware of the day-to-day costs of the job to

date when it came onto the project. Rather, it relied on the pre-bid estimates produced

by Ken Jutte, and Mr. Jutte’s assurance that the numbers were still accurate. The

Surety, through Mr. Zetts, relied on Ken Jutte’s assurance that Jutte had enough

Case No. 2014-00318 -16- DECISION

manpower to finish the job as originally bid. Ms. Meyers testified that she recognized

from the beginning that Jutte’s representation as to its ability to produce adequate

manpower was not accurate. The Surety again relied solely on Ken Jutte’s

representation that Ben York was the best Jutte employee to run the job site. While the

evidence shows that Jutte’s performance dramatically increased after Mr. York took

over, the Surety did not take any steps to independently verify that the project manager

had the qualifications and experience to manage this type of project. Since Ken Jutte

was only on site a handful of times and Mr. Zetts was only on site frequently in the

beginning stages of the Sureties involvement, the Surety placed a great deal of trust in

a project manager that they knew very little about. Further, the Court finds there was a

lack of diligence by Mr. Zetts in failing to read and understand the original contract

between Jutte and OSFC. Especially, considering the fact that under the MOU

(Ex. 310), he was responsible for supervising and overseeing Jutte’s completion of the

job. The Surety mistakenly relied on Ken Jutte’s representation that Jutte (a company

which essentially existed only in name) could finish the job, pursuant to the contract,

within the original bid amount. Both Mr. Zetts and Ms. Meyers testified that they did not

believe Ken Jutte when he told them Jutte could finish the job and make a profit. They

recognized and testified that the project had been underbid. They decided not to

believe this bold claim as it had no basis in reality. However, for some reason, Mr. Zetts

decided he could rely on Ken Jutte’s opinion regarding Jutte’s ability to supply adequate

manpower and complete the job. Ultimately, a great deal of trust was placed in the

owner of Jutte Electric, even though it seems apparent to the Court that he had very

little interest in ensuring that his company completed the project as it agreed to.

{¶36} “The principal disadvantage of a takeover is the loss of protection of the

bond penalty. Once the surety agrees to complete the work [or agrees to fund the

principal], the surety’s obligation is not measured by the bond penalty but rather by its

contract with the owner/oblige to effect completion. The surety, therefore, assumes the

Case No. 2014-00318 -17- DECISION

risk of hidden conditions or other problems which might develop in the completion

process.” The Law of Performance Bonds, Tort and Insurance Practice Section of the

American Bar Association (1999), citing McWaters & Bartlett v. U.S, 272 F.2d 291 (10th

Cir.1959); Caron v. Andrews, 284 P.2d 544 (Cal. 1955); Klein v. J.D. & J.M. Collins, 106

So. 120 (1925). The Surety took a risk and it did not pay off. Had a proper investigation

been done, the maximum loss the Surety would have incurred would have been the full

bond amount, or $786,892.00; and, that would have been the Surety’s maximum

exposure.

{¶37} The Court finds that had a proper investigation been done the Surety would

have determined its least exposure would have been to pay the full bond amount of

$786,892. Had it paid the bond amount it would have been released of responsibility on

the project without further loss. It would then have its remedy to recover against its

principal, Jutte. The damages the Surety incurred were a direct and proximate cause of

its negligence in failing to properly investigate the project alternatives.

IV: Jutte and its Capacity to Sue

{¶38} OSFC raised the issue of whether or not the Surety has the legal capacity

to sue on behalf of Jutte, a bankrupt company. Pursuant to R.C. 1701.88, Jutte is

legally permitted to pursue its claim against OSFC.

{¶39} R.C. 1701.88(A) states that a corporation shall continue to exist for

purposes of bringing claims “for a period of five years from the dissolution, expiration, or

cancellation.”

{¶40} R.C. 1701.88(B) states in pertinent part:

{¶41} “The voluntary dissolution of a corporation, cancellation of the articles of

incorporation * * * shall not eliminate or impair any remedy to * * * its directors, officers,

or shareholders for any right or claim existing * * * prior to the dissolution.”

{¶42} Pursuant to R.C. 1701.88(C),

Case No. 2014-00318 -18- DECISION

{¶43} “Any claim * * * pending by * * * the corporation * * * may be prosecuted to

judgment, with the right of appeal as in other cases * * * the corporation shall, solely for

the purpose of such action, suit or proceeding [filed pursuant to R.C. 1701.88(B)] be

continued as a body corporate beyond the five year period and until any judgments * * *

are executed, without the necessity for any court order * * *.”

{¶44} Therefore, Jutte had the capacity to bring suit against OSFC for its

potential claims arising out of the project, even though Jutte stopped doing business

upon the filing of the bankruptcy and officially ceased to exist as of December 31, 2012.

(Ex. BB). Whether or not the Surety had the right to bring the suit on behalf of Jutte for

damages that Jutte incurred based on its contractual relationship with OSFC is not as

clear, as explained below.

V: Surety and its Rights

{¶45} In choosing to file a lawsuit as a co-plaintiff with a company that no longer

exists, the Surety must inherently assert certain rights of Jutte on behalf of Jutte. This is

due in part to Ken Jutte’s apparent disinterest in participating in this litigation based, in

part, on his failure to appear as a witness even though he was properly subpoenaed.

The claims stem from the underlying contract between Jutte and OSFC, and contract to

which the Surety was not a party. Therefore, it is imperative that the Surety either

assert its own damages or legally assert the damages on behalf of Jutte.

{¶46} The Court is not clear about exactly whose damages are being asserted in

this matter; the Surety’s or Jutte’s. In fact, it seems even the Surety is unclear who was

allegedly damaged by OSFC.3 The Surety representative, Ray Zetts’, testimony

conflicted with the position stated by counsel during closing arguments. What is clear is

that it is the Surety who paid for everything necessary in order for Jutte to complete the

project. It was the Surety who paid Jutte’s employees, including employment taxes

3Counsel for the Surety argues that the damages sought are those of Jutte’s and not the Surety.

Case No. 2014-00318 -19- DECISION

(except for one employee, Rachel, in Jutte’s “home office”). Likewise, the Surety paid

all of the temporary manpower agencies who supplied the bulk of the employees who

finished the job. The Surety paid the vendors their outstanding balances and continued

to pay them through the completion of the project. The Surety argues that it paid much

more than it should have to complete the project due to the conduct of OSFC in failing

to appropriately manage and schedule the project. Ultimately, it does not matter which

entity suffered the damages, because Plaintiffs’ have failed to prove by a

preponderance of the evidence that the alleged damages were proximately caused by

OSFC. What is clear, as stated above, is that the damages ultimately stem from the

contractually relationship between Jutte and OSFC. Therefore, the Court must

determine if the Surety has the ability to assert Jutte’s rights against OSFC.

{¶47} There are two ways that the Surety could properly assert damages on

behalf of Jutte: 1) the Surety obtains Jutte’s rights by stepping into the shoes of Jutte

based on general suretyship law, or 2) a legally binding assignment of Jutte’s rights to

the Surety.

Stepping into the Shoes of Jutte

{¶48} It is the position of the Surety, and its counsel, that it stepped into the

shoes of Jutte when it took over the site and funded Jutte to complete the work.

However, it is not clear that the well-established doctrine of a surety stepping into the

shoes of its principal applies to the particular facts of this case. Further, the Court finds

that the Surety’s characterization of what it means to step into the shoes of Jutte does

not comport with the general law of suretyship. In general, a surety steps into the shoes

of its principal by way of an equitable right of subrogation. This right entitles the surety

to recover from its principal any funds owed to it by the state. This right was, in fact,

memorialized in the General Indemnity Agreement. (Ex. M). Therefore, there is no

question that the Surety’s right of subrogation exists. However, the Surety seems to

believe that stepping into the shoes gives the Surety something more. The Court is

Case No. 2014-00318 -20- DECISION

aware of the fact that in some situations the surety agreement allows a surety to step

into the shoes of many parties, including its principal, some third parties

(i.e. vendors/subcontractors), and even into the shoes of the owner of the project.

However, the Surety has failed to demonstrate that any of the particular facts that give

rise to those scenarios exist in this case.

{¶49} Plaintiffs provided no authority (and the Court is not aware of any

controlling authority) that states that by virtue of the Surety’s decision to fund its

bankrupt principal, as opposed to formally taking over the project, it obtains the rights of

the principal under the original contract to bring claims against the owner. Rather, the

well-established law of suretyship is that the Surety’s rights come from the equitable

right of subrogation, which is inherently limited. There is a general principle of equitable

subrogation that “one cannot acquire by subrogation from another, rights which that

person did not have.” Ram Constr. Co., Inc. v. Am. States Ins. Co., 749 F.2d 1049,

1055 (3d Cir.1984), quoting United States v. Munsey Trust Co., 332 U.S. at 242, 76

S.Ct. 1599 (1947). Equitable subrogation exists to allocate proceeds of already-

established rights, not to create new ones.

{¶50} As further explained below, Jutte failed to give timely notice of its claims,

pursuant to Article 8 of the Contract. Therefore, it had no right to bring the claims it

asserts in either of its Article 8 claims. Consequently, the Surety has no right to bring

said claims.

{¶51} Even if Jutte did have a right to those claims, it had no right to claim some

of the damages which the Surety asserts, in particular the overruns the Surety incurred

to complete the project. Upon careful review of the Surety’s expenditures on the

project, the overruns were primarily caused by the Surety’s decision to employ

temporary employees at substantially higher rates than the Jutte employees. (Ex. J, K,

JJ). Under the terms of the original contract, Jutte had no right to use temporary

employees at a right higher than the agreed upon hourly rates submitted during the bid

Case No. 2014-00318 -21- DECISION

process. Therefore, the Surety, having no greater rights than Jutte, had no right to

expend additional funds on labor, in excess of the original contract amount. As

explained herein, it also failed to demonstrate that OSFC proximately caused these

overruns.

{¶52} The Court finds that there is no evidence to support the position that the

Surety obtained any rights of its principal, Jutte, save for its equitable right of

subrogation. Therefore, it does not have a right to assert of damages on behalf of Jutte

that Jutte could not itself assert.

Assignment of Jutte’s Right to the Surety

{¶53} The contract between Jutte and OSFC specifically prohibits an assignment

of Jutte’s rights without the consent of OSFC. (Ex. 12). There is no evidence of OSFC’s

consent to an assignment of Jutte’s rights found in the record. There is also no

evidence that the bankruptcy court assigned Jutte’s rights to the Surety. Plaintiffs argue

that this right is found in Ex. H, the September 1, 2011 Agreed Order Authorizing the

Debtor to Assume Executory with the State of Ohio, School Facilities Commission.

However, upon careful review, this order contains no such assignment of rights, i.e. the

order does not specifically give to the Surety the right to file a claim against OSFC on

behalf of Jutte. Ex. H merely gives Jutte the right to assume and complete the original

contract it had with OSFC (with funding from the Surety). It makes no mention of

assigning any of Jutte’s rights under the contract with OSFC to the Surety.

{¶54} The Surety also asserts that it obtained Jutte’s rights under the MOU (Ex.

310) which it argues incorporates the underlying contract. However, the Court does not

agree. The Court finds that the underlying contract was not replaced by the MOU, it

was merely supplemented such that payments from OSFC originally made to Jutte

under the contract could now be made to the Surety (consistent with the Surety’s right

of subrogation). The MOU did not change the underlying relationship between Jutte

Case No. 2014-00318 -22- DECISION

and OSFC. As with Ex. H, it makes no mention of assigning any of Jutte’s rights under

the contract to the Surety.

{¶55} The Surety also asserts that Jutte assigned its rights via a General

Indemnity Agreement (Ex. M). However, as explained above, this indemnity agreement

only affects the relationship between Jutte and the Surety it does not assign any of

Jutte’s rights under the contract to the Surety.

{¶56} The Court finds that there is no evidence to support the position that the

Surety was assigned of Jutte’s rights beyond those rights established by its equitable

right of subrogation.

VI: Article 8 Claims

{¶57} There is an issue regarding whether or not the Surety is bound by the

Article 8 process. The parties have not provided any authority which makes the rights

and responsibilities of the Surety related to an Article 8 claim any clearer. Assuming the

Surety did step into the shoes of Jutte, and therefore had all the rights and

responsibilities which Jutte had in this project, the Surety and/or Jutte failed to give

timely notice of its Article 8 claim. The Surety claims that it is not subject to the Article 8

process. It contends that only contractors are required to give timely notice of their

claims and proceed with the Article 8 dispute resolution process. If a contractor on a

project for OSFC believes that it has been negatively impacted on the project it must

give notice to the State within ten (10) days and substantiate its claim within thirty (30)

days. (General Conditions, Ex. 12). This is a non-waivable, statutory mandate. IPS

Elec. Srvs., LLC v. Univ. of Toledo, 10th Dist. Franklin No. 15AP-207, 2016-Ohio-361.

{¶58} On December 2, 2011, Anne Meyers, sent a letter to OSFC which did not

comply with the Article 8 requirements. OSFC replied and asked that she provide

additional information to substantiate the claim. On December 30, 2011, Anne Meyers

sent a follow up letter to OSFC which appears to be its first certified Article 8 claim. In

this letter, the Surety takes issue with the supplementation of Jutte’s work by Accurate

Case No. 2014-00318 -23- DECISION

Electric. The Surety claims that OSFC paid Accurate employees excessive hourly rates

and equipment charges; and, excessive trenching costs. It raises a concern about

OSFC including a 2% bond premium charge for retaining Accurate. It also complains

about allegedly missing and defective work completed by Accurate, as well as

preferential treatment of Accurate over Jutte. All of these issues relate to matters

before the MOU, and therefore, are effectively settled as the parties have agreed to

move forward under the new arrangement and Jutte promised to correct the mistakes

that occurred prior to the MOU. Even if this were not the case, the December 30, 2011

Article 8 claim is still late. Accurate’s supplementation work occurred several months

prior to this letter.

{¶59} On December 19, 2012, the second Article 8 claim was filed by Ronald

Friedberg on behalf of the Surety and Jutte. This Article 8 claim was clearly late as it

was received approximately four months after the project was substantially completed.

Conclusion

{¶60} Plaintiffs have failed to prove by a preponderance of the evidence within a

reasonable degree of certainty that their damages were proximately caused by OSFC.

{¶61} Even if Jutte was able to prove damages, the Surety failed to prove that it

is entitled to any of Jutte’s damages, or for that matter any of its own damages. The

Surety made a decision that it could possibly “beat the spread,” that is, it could finish the

project with Jutte and do so for less than it would have to pay another contractor (i.e.

Accurate). However, it made the decision to fund its principal (who essentially existed

in name only), after performing only a cursory investigation into said principal’s financial

health and the current state of the project. It then supplemented the vast majority of the

labor with temporary manpower at substantially higher hourly rates than the original bid,

causing massive cost overruns. The Surety failed to prove that it was the conduct of

OSFC that caused it to use this additional expensive labor.

Case No. 2014-00318 -24- DECISION

{¶62} Even if Plaintiffs proved that their damages were proximately caused by

OSFC, any damages related to the claims listed in the two Article 8 letters were not

timely submitted and therefore Plaintiffs have waived their right to receive compensation

for alleged losses incurred due to those claims.

{¶63} For the above-mentioned reasons, it is recommended that the Court find in

favor of Defendant, Ohio School Facilities Commission. Since the third-party claims

and counterclaims are based solely upon indemnity, the other claims, damages, and

costs should be denied as not supported by the greater weight of the evidence.

{¶64} A party may file written objections to the magistrate’s decision within 14

days of the filing of the decision, whether or not the court has adopted the decision

during that 14-day period as permitted by Civ.R. 53(D)(4)(e)(i). If any party timely files

objections, any other party may also file objections not later than ten days after the first

objections are filed. A party shall not assign as error on appeal the court’s adoption of

any factual finding or legal conclusion, whether or not specifically designated as a

finding of fact or conclusion of law under Civ.R. 53(D)(3)(a)(ii), unless the party timely

and specifically objects to that factual finding or legal conclusion within 14 days of the

filing of the decision, as required by Civ.R. 53(D)(3)(b).

DALE A. CRAWFORD

Referee

cc:

Craig D. Barclay Debra Jean Horn

David A. Beals Robert N. Guliano

William C. Becker Ronald P. Friedberg

Assistant Attorneys General 28601 Chagrin Boulevard, Suite 500

150 East Gay Street, 18th Floor Cleveland, Ohio 44122

Columbus, Ohio 43215-3130

Case No. 2014-00318 -25- DECISION

David M. Rickert Bradley J. Barmen

110 North Main Street, Suite 1000 1375 East 9th Street, 16th Floor

Dayton, Ohio 45402 Cleveland, Ohio 44114

Filed December 13, 2016

Sent to S.C. Reporter 1/17/17

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.