Opinion

Munilla Construction Management, LLC v. United States

  • 130 Fed. Cl. 131
  • 2016 U.S. Claims LEXIS 2026
  • 2016 WL 7666663
Court
United States Court of Federal Claims
Filed
Dec 23, 2016
Status
Published
Author
Kaplan
On the bench
Elaine D. Kaplan
Cited by
12 cases
Authority
More cited than 59.7%

finding the 18 balance of hardships weighs in favor of the Government and Intervenor when work under a contract has begun and it would prove disruptive to halt such work only to resume it at a subsequent time

How later courts described this case

  • finding the 18 balance of hardships weighs in favor of the Government and Intervenor when work under a contract has begun and it would prove disruptive to halt such work only to resume it at a subsequent time
  • “The standards for determining whether to grant a temporary restraining order are the same as those that apply to a motion for a preliminary injunction. They require the moving party to demonstrate that: (1) it is likely to succeed on the merits; (2

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

BID PROTEST

No. 16-1684C

(Filed Under Seal: December 23, 2016 | Reissued: January 10, 2017)*

)

MUNILLA CONSTRUCTION )

MANAGEMENT, LLC, )

) Keywords: Temporary Restraining Order;

Plaintiff, ) Likelihood of Success; Irreparable Harm;

) Bid Protest; 28 U.S.C. § 1491(b).

v. )

)

THE UNITED STATES OF AMERICA, )

)

Defendant, )

)

and )

)

SEAWARD SERVICES, INC., )

)

Defendant-Intervenor. )

)

Stephen Gregory Joy, Smith, Currie & Hancock LLP, Atlanta, GA, for Plaintiff. Karl Frederick

Dix, Smith, Currie & Hancock LLP, Atlanta, Georgia, and Alan I. Saltman, Smith, Currie &

Hancock LLP, Washington, DC, Of Counsel.

Amanda L. Tantum, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S.

Department of Justice, Washington, DC, for Defendant, with whom were Douglas K. Mickle,

Assistant Director, Robert E. Kirschman, Jr., Director, and Benjamin C. Mizer, Principal Deputy

Assistant Attorney General. Joe D. Baker, Navy Supply Systems Command, Fleet Logistics

Center Jacksonville, Department of the Navy, Of Counsel.

*

This Opinion was originally issued under seal on December 23, 2016, and the parties were

given the opportunity to request redactions. The parties disagree about the extent of redactions

appropriate for this public decision, but the Court agrees with Plaintiff that its prices are

proprietary, competition-sensitive information and should not be disclosed. However, the Court

will not redact the names of non-party offerors. This Opinion is now reissued with redactions

indicated by brackets. Additionally, the Court has corrected four typographical errors in citations

on pages two, four, six, and seven.

Shlomo D. Katz, Brown Rudnick LLP, Washington DC, for Defendant-Intervenor. Daniel B.

Abrahams, Brown Rudnick LLP, Washington, DC, and Tammy Hopkins, Brown Rudnick LLP,

Washington, DC, Of Counsel.

OPINION AND ORDER

KAPLAN, Judge.

Plaintiff Munilla Construction Management, LLC (Munilla) filed this post-award bid

protest on December 22, 2016. ECF No. 1. On the same day, Munilla also filed a motion for a

temporary restraining order and preliminary injunction. ECF No. 5. On December 23, 2016, the

Court heard oral argument on the motion. For the reasons discussed below, Munilla’s motion for

a temporary restraining order is hereby DENIED.

BACKGROUND1

Munilla is a construction company that has been in operation for more than thirty-two

years. Pl.’s Mem. of Law in Supp. of Its Mot. for TRO, Prelim. Inj., and Permanent Inj. (Pl.’s

Mem.) at 3, ECF No. 5. Munilla alleges that it (and its predecessor company) have provided

“port operations services at Guantanamo Bay Naval Station under contract with the Department

of the Navy since 1999.” Compl. ¶ 4.

In June 2016, the Navy issued Request for Proposal number N68836-16-R-0003 (the

RFP), a re-solicitation of the port services then being provided by Munilla. See id. ¶¶ 6, 9.

Munilla submitted a proposal in response. Id. ¶ 11.

The solicitation was for a firm fixed-price contract and contracting authority was based

upon FAR Part 12 and FAR Part 15. Def.’s Notice of Filing Solicitation, Approved Business

Clearance, and Decl. of Harm (Def.’s Notice) Ex. A at 158, ECF No. 22-1. The RFP provided for

award of the contract to the lowest-priced technically acceptable offeror. Pl.’s Mem. at 5; see

also Def.’s Notice Ex. A at 169 (“Government intends to award a contract . . . to the responsible

Offeror whose proposal conforming to the solicitation will be most advantageous to the

Government . . . and will be the Lowest Price Technically Acceptable (LPTA) Offer”). The RFP

stated as follows regarding the evaluation of price:

2. Reasonableness: Price is fully justified and supported and is

considered fair under current market conditions as well as

reasonable to both the Offeror and the Government. Reasonableness

may also be determined by comparing the proposed pricing with

Government estimates and/or other offers received. Unbalanced

pricing exists when, despite an acceptable total evaluated price, the

price of one or more contract line items is significantly over or

understated as indicated by the application of cost or price analysis

1

The facts in this section are based on the allegations in Munilla’s complaint as well as the

materials submitted by both Munilla and the government in connection with Munilla’s motion.

2

techniques. An offer may be rejected if the Contracting Officer

determines that the lack of balance proposes an unacceptable risk to

the Government. In accordance with FAR 15.404-1(g)(2) a price

analysis will be conducted on the individual CLINs to determine

whether unbalanced pricing occurred.

Def.’s Notice Ex. A at 171–72.

The Navy ultimately awarded the contract to Seaward Services, Inc. (Seaward) on

October 27, 2016. Pl.’s Mem. at 6; see also Compl. ¶ 12. Munilla requested a debriefing and on

November 1, 2016, the Navy informed Munilla that although Munilla’s proposal was technically

acceptable, it was not the lowest-priced; rather, Seaward had the lowest-priced technically

acceptable proposal. See Pl.’s Mem. at 6.

According to Munilla (and as reflected in the source selection documents), its base year

price was [***], while Seaward’s base year price was $3,539,749. Id. Munilla’s total price,

including option years, was [***], while Seaward’s was $20,475,969. Id. at 6–7.

Notwithstanding only a difference of [***] (or approximately [***]%) in overall contract price

between Munilla and Seaward, Munilla alleges that there are substantial differences between

Munilla’s and Seaward’s contract line item prices. See id. It highlights a number of line items

from both proposals which, according to Munilla, reflect differences between it and Seaward of

tens and hundreds of thousands of dollars on different line items. Id. at 7–8.

Munilla further alleges that some of Seaward’s line item pricing is “so low that it is

below cost” and also would not cover the cost of performance for its subcontractors. See id. at 8–

9. In contrast, Munilla states that other line items in Seward’s proposal are “substantially

overstated.” Id. at 9.

Munilla alleged in its complaint and in its Memorandum in support of its TRO Motion

that its proposal was the third lowest-priced, and that a second offeror’s proposal (that of

SoBran, Inc.) was priced lower than Munilla’s, but higher than Seaward’s. See id. at 10-11. It

claimed that “SoBran’s pricing was only [***] higher than Seaward’s” and that the Navy thus

also failed to assess whether SoBran’s pricing was “reasonable” and “fully justified and

supported and . . . considered fair under current market conditions.” Id. Documentation provided

by the government in response to Munilla’s motion, however, indicates that SoBran’s proposal

was found technically unacceptable. Def.’s Opp’n to Pl.’s Mot. for a TRO (Def.’s Opp’n) App.

at Appx248. It further shows that there was another technically-acceptable offeror whose overall

proposal was less expensive than Munilla’s: Crowley Government Services, Inc. (Crowley); its

proposal price (with government adjustments) was [***] (which is approximately [***] lower

than Munilla’s, reflecting a price difference of a little less than [***]%). Id. at Appx248–49.

After the contract award to Seaward, Munilla filed a protest at the Government

Accountability Office (GAO) on November 3, 2016, alleging that Seaward’s proposal was

“significantly understated and unbalanced” and “unreasonable,” and that the government failed

to perform a “proper price analysis.” Pl.’s Mem. at 11–12. On December 14, 2016, the GAO

dismissed Munilla’s protest on the ground that “the Navy was not required to perform a price

3

analysis to determine if the proposed prices were too low.” Id. at 12. Munilla then filed its bid

protest action in this Court. ECF No. 1.

In its complaint, Munilla alleges that both Seaward’s and SoBran’s prices were

“unreasonable to the Offeror and/or the Government” and that they were “significantly

understated and unbalanced.” Compl. ¶ 28. It argues that the Navy failed to engage in the proper

price analysis to determine price reasonableness as required by the RFP and the FAR. See id.

¶ 40. Specifically, Munilla argues, the Navy failed to comply with the RFP’s requirement, “in

accordance with FAR 15.404-1(g)(2)” to conduct a price analysis on the individual CLINs “to

determine whether unbalanced pricing occurred.” Further, according Munilla, the Navy failed to

conduct a proper analysis to determine whether Seaward’s price was “reasonable” and “fully

justified and supported and . . . fair under current market conditions.” See Pl.’s Mem. at 10. It

thus requests that the Court issue a temporary restraining order restraining the government from:

[E]xecuting a contract pursuant to the RFP with any proposer other

than [Munilla], from issuing a notice to proceed to Seaward, . . .

from taking any action toward implementing the contract award to

any proposer other than [Munilla], from directing any contractor

other than [Munilla] to perform work on the Project, [and] from

permitting any bidder other than [Munilla] to perform work on the

Project.”

Id. at 17. It also requests a preliminary and permanent injunction providing similar relief. See id.

at 17–18.

The Navy has extended Munilla’s contract through January 31, 2017. Compl. ¶ 35; see

also Def.’s Notice Ex. C ¶¶ 2, 4, ECF No. 22-3. The Navy indicates that one option period

remains on Munilla’s contract for the period February 1 through February 28, 2017. Def.’s

Notice Ex. C ¶ 2. The parties indicated at oral argument that the Navy and Seaward are moving

forward with contract transition, which resumed on December 15, 2016.

DISCUSSION

A temporary restraining order is an “extraordinary and drastic remedy, one that should

not be granted unless the movant, by a clear showing, carries the burden of persuasion.” Jones

Automation, Inc. v. United States, 92 Fed. Cl. 368, 370 (2010) (quoting Mazurek v. Armstrong,

520 U.S. 968, 972 (1997)). The standards for determining whether to grant a temporary

restraining order are the same as those that apply to a motion for a preliminary injunction. They

require the moving party to demonstrate that: (1) it is likely to succeed on the merits; (2) it will

be irreparably harmed without injunctive relief; (3) the balance of hardships tips in its favor and

(4) the public interest favors the grant of injunctive relief. Am. Signature, Inc. v. United States,

598 F.3d 816, 823 (Fed Cir. 2010) (citing Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 19

(2008)); see also Erico Int’l Corp. v. Vutec Corp., 516 F.3d 1350, 1353–54 (Fed. Cir. 2008)

(discussing injunctive relief in a patent context); FMC Corp. v. United States, 3 F.3d 424, 427

(Fed. Cir. 1993). “No single factor is determinative, and ‘the weakness of the showing regarding

one factor may be overborne by the strength of the others.’” Contracting Consulting Eng’g LLC

v. United States, 103 Fed. Cl. 706, 709 (2012) (quoting FMC Corp., 3 F.3d at 427). At the same

4

time, “the absence of an adequate showing with regard to any one factor may be sufficient, given

the weight or lack of it assigned the other factors, to justify . . . denial” of a preliminary

injunction or temporary restraining order. See Chrysler Motors Corp. v. Auto Body Panels of

Ohio, Inc., 908 F.2d 951, 953 (Fed. Cir. 1990). In this case, Munilla has failed persuade the

Court that the balance of the equities favors the extraordinary remedy of a TRO.

First, Munilla has not established a likelihood of success on the merits. Even assuming

that its legal challenge to the award to Seaward were likely to succeed (an issue upon which the

Court expresses no opinion at this point), it is not clear that Munilla possesses standing to bring

such a challenge. To possess standing to bring a bid protest, a plaintiff must be an interested

party within the meaning of 28 U.S.C. § 1491(b)(1), i.e., an actual or prospective bidder (or

offeror) who possesses a direct economic interest in the matter. Sys. Application & Techs., Inc.

v. United States, 691 F.3d 1374, 1382 (Fed. Cir. 2012) (citing Weeks Marine, Inc. v. United

States, 575 F.3d 1352, 1359 (Fed. Cir. 2009)); see also Orion Tech., Inc. v. United States, 704

F.3d 1344, 1348 (Fed. Cir. 2013). In post-award protests, a plaintiff is an interested party, and

thus has standing, where it would have had a “substantial chance” of winning the award “but for

the alleged error in the procurement process.” Info. Tech. & Applications Corp. v. United States,

316 F.3d 1312, 1319 (Fed. Cir. 2003); see also Weeks Marine, Inc., 575 F.3d at 1359; Rex Serv.

Corp. v. United States, 448 F.3d 1305, 1308 (Fed. Cir. 2006).

Here, Munilla has not established that it would have had a substantial chance of winning

the award but for the errors it alleges because—even if the award to Seaward were set aside—the

next lowest-priced technically acceptable offer after Seaward’s was made by another offeror,

Crowley. Def.’s Opp’n App. at Appx248–49; see also SOS Int’l LLC v. United States, 127 Fed.

Cl. 576, 587–88 (2016) (finding that plaintiff lacked standing because, inter alia, the record

indicated it would not have been next in line for the award if its allegations of error were

correct). Crowley’s offer was priced [***] lower than Munilla’s, and [***] higher than

Seaward’s. See Def.’s Opp’n App. at Appx248–49. Particularly given the fact that Crowley’s

total price is so close to Munilla’s the Court has no basis at this time for concluding, as counsel

suggested at oral argument, that an award to Crowley would be subject to the same legal defects

as are alleged with respect to the award to Seaward. Therefore Munilla has not shown a

likelihood of success on the merits and the first factor weighs against the granting of a temporary

restraining order.

Further, the second factor, whether the plaintiff will suffer irreparable harm absent

injunctive relief, also counsels against the issuance of a temporary restraining order. “To

demonstrate an irreparable injury, a plaintiff must show that without a preliminary injunction or

TRO it will suffer irreparable harm before a decision can be rendered on the merits.” OAO Corp.

v. United States, 49 Fed. Cl. 478, 480 (2001). Given the expedited briefing schedule the Court is

establishing (which will result in a final decision by January 31, 2017), this means that—to

justify a TRO—Munilla must show that it will suffer irreparable harm in the next month if the

transition activities that began last week continue.

In that regard, Munilla alleges that it will suffer such injury because Seaward “may begin

to hire MCM employees and MCM may not be able to replace or rehire those personnel given

restrictions on personnel who can travel to and work at the Guantanamo Bay Naval Station.”

Pl.’s Mem. at 25. “[A] turnover of MCM's employees,” Munilla further forecasts, “could lead to

5

the loss of personnel with expertise in work at the Guantanamo Bay [N]aval Station,” thereby

“disrupt[ing] MCM's ability to continue to provide services at the base.” Id. In addition,

according to Munilla, “if an injunction is not issued and another contractor begins work but

MCM is ultimately successful in its protest, there could be a second turnover which would result

in significant extra costs.” Id. Finally, Munilla expresses concern that its chances for securing

relief other than bid preparation costs would be adversely affected if the transition to Seaward

were permitted to move forward at this time. See id. at 24.

The Court finds these allegations insufficient to establish irreparable harm. First, the loss

of personnel by an incumbent contractor during a transition period generally does not constitute

irreparable injury. See, e.g., IBM Corp. v. United States, 118 Fed. Cl. 677, 684–85 (2014) (“the

mere fact that an incumbent's employees begin to move over to work for the awardee does not,

without more, constitute irreparable harm”); Eskridge Research Corp. v. United States, 92 Fed.

Cl. 88, 99 (2010) (stating that “the decision of [incumbent-protester's] employe[e]s to work for

[awardee] is not the kind of injury that constitutes irreparable harm”); Comput. Scis. Corp. v.

United States, 51 Fed. Cl. 297, 323 n.91 (2002) (“[A] potential loss of employees is not an

irreparable harm.”); PGBA, LLC v. United States, 60 Fed. Cl. 196, 221 (2004) (loss of

employees is “significant,” but not an irreparable injury, because the court would then be

required “to consider any incumbent contractor's loss of a successor contract to be irreparable

harm”), aff’d, 389 F.3d 1219 (Fed. Cir. 2004).

Further, and in any event, Munilla’s claims that it is likely to lose personnel over the next

month if a temporary restraining order is not granted appear to be supported by little more than

conjecture. See Pl.’s Mem. Ex. 1 ¶ 23 (observing that if another contractor is permitted to

mobilize “that contractor may begin to hire MCM employees and MCM may not be able to

replace or rehire those personnel given restrictions on personnel who can travel to and work at

the Guantanamo Bay Naval Station”). Indeed, it seems likely that even if the employees who are

currently performing the work at Guantanamo Bay Naval Station for Munilla accept job offers

from Seaward for work to begin on February 1, they would choose to remain as Munilla’s

employees if the Court enjoined the award of the contract to Seaward at the end of January.

The Court finds similarly unpersuasive Munilla’s other allegation of irreparable injury,

which is based on an argument that allowing a transition to begin now would impair its chances

of securing any relief other than bid protest costs even if it ultimately prevails in this litigation. A

“contention that without a preliminary injunction, [the awardee] will become so entrenched that

[the protester] will have lost its opportunity to compete does not demonstrate irreparable harm.”

Eskridge Research Corp., 92 Fed. Cl. at 99; see also Sierra Military Health Servs., Inc. v. United

States, 58 Fed. Cl. 573, 582 (2003) (noting that other courts have rejected the claim that the

contract awardee would become so entrenched during transition that the protester would be

irreparably harmed without an injunction).

Finally, given the lack of irreparable harm to Munilla, the balance of the hardships

weighs against a TRO. The transition process has already begun. Halting it now with the

possibility of having to resume it in February would be, if nothing else, disruptive to the

6

government and to Seaward.2 Nor does the public interest support the issuance of a temporary

restraining order. To be sure, the public has an interest “in honest, open, and fair competition in

the procurement process.” GEO Grp., Inc. v. United States, 100 Fed. Cl. 223, 230 (2011)

(quoting Software Testing Sols., Inc. v. United States, 58 Fed. Cl. 533, 538 (2003)). Nonetheless,

“[i]t is equally clear . . . that a procuring agency should be able to conduct procurements without

excessive judicial infringement upon the agency’s discretion.” Id. (quoting Aero Corp. S.A. v.

United States, 38 Fed. Cl. 237, 242 (1997)). In this case, given that Munilla has failed, at least at

this early stage, to demonstrate a likelihood of success on the merits, the Court concludes that the

latter interest should prevail.

CONCLUSION

For the reasons set forth above, Munilla’s motion for a temporary restraining order is

DENIED.

IT IS SO ORDERED.

s/ Elaine D. Kaplan

ELAINE D. KAPLAN

Judge

2

At oral argument on the motion, Munilla disputed the government’s contentions that the

government would incur additional costs if the transition were suspended. In fact, Munilla

argued that the government would save money if it continued to perform on its existing contract

through the end of February. Given the expedited nature of the proceedings, the Court has not

considered the government’s allegations of additional costs (or Munilla’s response) in

determining the balance of the hardships.

7

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.