Opinion

Ramsey v. Arizona Registrar of Contractors

  • 241 Ariz. 102
  • 751 Ariz. Adv. Rep. 34
  • 384 P.3d 316
  • 2016 Ariz. App. LEXIS 264
Court
Court of Appeals of Arizona
Filed
Nov 1, 2016
Status
Published
Author
Jones
On the bench
Jones, Howe, Kessler
Cited by
14 cases
Authority
More cited than 69.4%

“We will not set aside the trial court’s factual findings unless they are clearly erroneous.”

How later courts described this case

  • “We will not set aside the trial court’s factual findings unless they are clearly erroneous.”

Written by the judges who cited it.

The opinion

IN THE

ARIZONA COURT OF APPEALS

DIVISION ONE

JO ELLA RAMSEY, an individual, Plaintiff/Appellee,

v.

ARIZONA REGISTRAR OF CONTRACTORS, Defendant/Appellant.

No. 1 CA-CV 15-0355

FILED 11-1-2016

Appeal from the Superior Court in Maricopa County

No. CV2010-003331

The Honorable Katherine M. Cooper, Judge

VACATED AND REMANDED

COUNSEL

Sanders & Parks, P.C., Phoenix

By G. Gregory Eagleburger, Nicholas A. Bender

Counsel for Plaintiff/Appellee

Arizona Attorney General’s Office, Phoenix

By Michael Raine

Counsel for Defendant/Appellant

OPINION

Presiding Judge Kenton D. Jones delivered the Opinion of the Court, in

which Judge Randall M. Howe and Judge Donn Kessler joined.

RAMSEY v. AZROC

Opinion of the Court

J O N E S, Judge:

¶1 The Arizona Registrar of Contractors (ROC) appeals the trial

court’s order directing the ROC to issue payment from the Arizona

Residential Contractors’ Recovery Fund (the Fund), Ariz. Rev. Stat. (A.R.S.)

§§ 32-1131 to -1140,1 to Jo Ella Ramsey. The ROC argues the court erred by:

(1) granting Ramsey’s application for recovery when it did not contain

evidence required by Arizona Rule of Civil Procedure 56 to support a

motion for summary judgment; (2) interpreting the statutes governing

recovery from the Fund in a manner that did not account for the amount

left unpaid under the underlying contract; (3) declining to hold a hearing

on the ROC’s objection to Ramsey’s application; and (4) finding the ROC

had conceded a minimum amount Ramsey spent to complete the project at

issue.

¶2 For the following reasons, we hold that an application for

recovery from the Fund need not comply with Rule 56. We also adopt the

ROC’s interpretation of “actual damages” and hold that damages for

purposes of A.R.S. § 32-1132(A) are limited to the reasonable cost of

repairing the contractor’s defective work and completing the project, minus

any portion of the contract price still unpaid to the original contractor.

Additionally, we hold that a hearing is unnecessary when the ROC’s

objection presents a purely legal issue which it has had adequate

opportunity to brief, and that, in the immediate case, substantial evidence

supports the trial court’s determination that the ROC conceded Ramsey

spent at least $52,101.29 to complete her residential construction project.

Accordingly, we vacate the court’s order and remand for further

proceedings consistent with this Opinion.

FACTS AND PROCEDURAL HISTORY

¶3 In May 2010, Ramsey filed a complaint against Michael and

Barbara Edens and Edens Contracting, L.L.C. (collectively, the Edens),

seeking damages for deficiencies in the Edens’ performance of a contract to

build a residence for Ramsey (the Residence). The ROC timely intervened

to address whether Ramsey was eligible to recover from the Fund. See

A.R.S. § 32-1136(A). In June 2013, the trial court entered a $111,000

judgment in Ramsey’s favor against the Edens.

1 Absent material changes from the relevant date, we cite a statute’s

current version.

2

RAMSEY v. AZROC

Opinion of the Court

¶4 In August 2014, the ROC moved to dismiss the case, alleging

Ramsey was not eligible for compensation from the Fund because she had

not suffered any “actual damages” within the meaning of A.R.S. §§ 32-1132

and -1136(E) because the amount she spent to complete the Residence —

$52,101.29 — was significantly less than the approximate $130,000 balance

owed on her contract with the Edens. Ramsey objected to the request for

dismissal and applied for an order directing the ROC to compensate her

from the Fund.

¶5 The trial court treated the ROC’s motion as an objection to

Ramsey’s application and, after the matter was fully briefed, entered an

order directing the ROC to pay Ramsey $30,000, the maximum allowable

amount, from the Fund. See A.R.S. § 32-1132(A). The court rejected the

ROC’s interpretation of the applicable statutes and held no hearing was

necessary because the ROC had conceded Ramsey spent more than $30,000

to complete the Residence. The ROC timely appealed, and we have

jurisdiction pursuant to A.R.S. §§ 12-120.21(A)(1) and -2101(A)(1).

DISCUSSION

I. Arizona Rule of Civil Procedure 56 Does Not Apply to an

Application for Recovery from the Fund.

¶6 The ROC first argues the trial court erred in granting

Ramsey’s application without an evidentiary hearing because she did not

provide evidence within the application to prove the facts supporting her

entitlement to payment from the Fund. The interpretation and application

of statutes present questions of law, which we review de novo. See First Fin.

Bank, N.A. v. Claassen, 238 Ariz. 160, 162, ¶ 8 (App. 2015) (citing Schwarz v.

City of Glendale, 190 Ariz. 508, 510 (App. 1997)). When a statute is

unambiguous, we apply its terms as written. Berndt v. Ariz. Dep’t of Corr.,

238 Ariz. 524, 528, ¶ 11 (App. 2015) (quoting Fleming v. Dep’t of Pub. Safety,

237 Ariz. 414, 417, ¶ 12 (2015)).

¶7 Pursuant to A.R.S. § 32-1136(B), a homeowner who obtains a

valid judgment against a residential contractor for misconduct in violation

of Title 32, Chapter 10, of the Arizona Revised Statutes, may apply to the

trial court for an order directing payment out of the Fund for the amount

unpaid on the judgment, up to $30,000. The ROC contends summary

adjudication of a request for payment from the Fund is appropriate only if

the applicant complies with Arizona Rule of Civil Procedure 56(c)(3), which

requires a motion for summary judgment be accompanied by a statement

of the “specific facts relied upon in support of the motion” and “refer[ence]

3

RAMSEY v. AZROC

Opinion of the Court

to the specific portion of the record where the fact may be found.” No such

requirement appears in the statute. Instead, A.R.S. § 32-1136(B) provides

that the application for an order directing payment from the Fund should

be granted “either on receipt of a consent to payment . . . or, in the absence

of any written consent, after the notice period required by this subsection.”

If the ROC objects to payment, it is entitled to an opportunity to present and

support its objections. A.R.S. § 32-1136(B). Thus, the statute contemplates

the application will be granted — without any testimony, evidence, proof,

or hearing — if there is no objection.

¶8 It necessarily follows that testimony, documentary evidence,

or other proof is required only as to those portions of the application to

which the ROC has objected. This interpretation is consistent with the

direction that the application be addressed without delay. See A.R.S. § 32-

1136(D) (“The court shall proceed on an application [for recovery from the

Fund] in a summary manner . . . .”); Chaffin v. Comm’r of Ariz. Dep’t of Real

Estate, 164 Ariz. 474, 477 (App. 1990) (defining the phrase “summary

manner” within statutes governing the Real Estate Recovery Fund “to mean

that the court must proceed on the application without delay or formality

and in a short, concise and immediate proceeding”) (citation omitted).

Indeed, this Court has already determined the trial court may limit the

scope of a hearing on the applicant’s eligibility to recover from the Fund

after consideration of the ROC’s specific challenges and the need to

expedite its review. See Magness v. Ariz. Registrar of Contractors, 234 Ariz.

428, 433 n.3, ¶ 18 (App. 2014). Because the requirements of Arizona Rule of

Civil Procedure 56 do not apply to an application for recovery from the

Fund, there was no error in the procedure used by the court here.

II. The Proper Measure of Damages Under A.R.S. § 32-1132(A) is the

Cost of Completion of the Project Less the Unpaid Portion of the

Original Contract Price.

¶9 The ROC argues the trial court erred in interpreting the

governing statutes to prevent the ROC from offsetting the cost to complete

a project by the amount left unpaid to the original contractor, an issue we

review de novo. See supra ¶ 6.

¶10 By statute, “[a]n award from the [F]und is limited to the actual

damages suffered by the claimant as a direct result of the contractor’s

violation but shall not exceed an amount necessary to complete or repair a

4

RAMSEY v. AZROC

Opinion of the Court

residential structure.” A.R.S. § 32-1132(A).2 The phrase “actual damages”

is not defined; therefore, we defer to the implementing agency’s

interpretation so long as it is “based on a permissible construction of the

statute.” Kobold v. Aetna Life Ins., 239 Ariz. 259, 262, ¶ 9 (App. 2016) (quoting

Chevron, U.S.A., Inc. v. Nat. Res. Def. Council, Inc., 467 U.S. 837, 843 (1984)).

“The relevant inquiry is whether the agency’s interpretation is reasonable.”

Id. (citing United States v. Mead Corp., 533 U.S. 218, 229 (2001)). In addition,

if the literal interpretation of a statute would lead to an absurd result, it is

this Court’s duty to construe it, if possible, so it is readable and workable.

Pendergast v. Ariz. State Ret. Sys., 234 Ariz. 535, 541, ¶ 18 (App. 2014)

(quoting State Farm Auto Ins. v. Dressler, 153 Ariz. 527, 531 (App. 1987), and

citing A.R.S. § 1-211(B) (“Statutes shall be liberally construed to effect[uate]

their objects and to promote justice.”)).

¶11 The ROC interprets “actual damages” to mean the reasonable

cost of completing the contract and repairing the contractor’s defective

performance “less the part of the contract price still unpaid.”3 This

interpretation comports with both Arizona law and the Restatement of

Contracts. See Maricopa Cty. v. Walsh & Oberg Architects, Inc., 16 Ariz. App.

439, 441 (1972); Sorensen v. Robert N. Ewing, Gen. Contractor, 8 Ariz. App.

540, 544 (1968) (citing Green Manor Constr. Co. v. Highland Painting Serv., Inc.,

345 F.2d 657, 661 (1st Cir. 1965)); Restatement (First) of Contracts

§ 346(1)(a)(i), illus. 1, 4, 5 (1932) (“For a breach by one who has contracted

2 Although not applicable here, there is an exception to this rule when

“the claimant has paid a deposit or down payment and no actual work is

performed or materials are delivered.” A.R.S. § 32-1132(A). Under those

circumstances, the award from the Fund “shall not exceed the exact dollar

amount of the deposit or down payment plus interest at the rate of ten per

cent a year from the date the deposit or down payment is made or not more

than thirty thousand dollars, whichever is less.” Id.

3 The ROC also argues the amounts unpaid under the original contract

constitute recovery from an “other source,” which may be deducted from

the amount recovered from the Fund pursuant to A.R.S. § 32-1136(E).

Section 32-1136(E) states: “If the injured person has recovered a portion of

his loss from sources other than the fund, the registrar . . . or the court shall

deduct the amount recovered from other sources from the amount of actual

damages suffered pursuant to [A.R.S.] § 32-1132, subsection A.” Here,

however, the amount due under the original contract has not been

“recovered” by the homeowner and is not a “payment” within the plain

meaning of the word, but rather, as explained herein, a factor in

determining the homeowner’s actual damages under A.R.S. § 32-1132(A).

5

RAMSEY v. AZROC

Opinion of the Court

to construct a specified product, the other party[] can get judgment for

compensatory damages for all unavoidable harm that the builder had

reason to foresee when the contract was made, less such part of the contract

price as has not been paid and is not still payable . . . .”), adopted by Blecick

v. Sch. Dist. No. 18 of Cochise Cty., 2 Ariz. App. 115, 122-23 (1965), overruled

on other grounds by Donnelly Constr. Co. v. Oberg/Hunt/Gilleland, 139 Ariz.

184, 187 (1984); cf. Restatement (Second) of Contracts § 348(2), illus. 2 (1981)

(stating a party may recover damages from defective or unfinished

construction for the diminution in value, or, if difficult to ascertain, “the

reasonable cost of completing performance or of remedying the defects if

that cost is not clearly disproportionate to the probable loss in value to

him”).

¶12 This construction of the statute is also consistent with the

general purpose of making a homeowner who suffers from a contractor’s

misdeeds “whole.” This can be best understood based upon the principle

of expectation damages, which are intended to put the injured party “to the

extent possible . . . in as good a position as he would have been in had the

contract been performed.” Restatement (Second) of Contracts § 347 cmt. a,

cited favorably by AROK Constr. Co. v. Indian Constr. Servs., 174 Ariz. 291, 298

(App. 1993); cf. John Munic Enters., Inc. v. Laos, 235 Ariz. 12, 18, ¶ 18 (App.

2014) (“Enforcing the expectation interests of the parties is one of the

principal goals of remedying a breach of contract.”). The calculation of

expectation damages necessarily includes a deduction for “any cost or other

loss that [the injured party] has avoided by not having to perform.”

Restatement (Second) of Contracts § 347(c).

¶13 Two hypotheticals underscore this principle. For example,

consider a homeowner who agrees to pay $100,000 to contractor A to build

a garage. Contractor A then stops work and breaches the contract while

$90,000 of the original contract price remains unpaid. The homeowner then

agrees to pay contractor B $50,000 to both correct contractor A’s mistakes

and complete the garage, thereby obtaining the completed garage for

$40,000 less than it would have cost under the original contract. Under our

holding, the homeowner would not be eligible to collect from the Fund

because the amount remaining owed on the initial contract ($90,000)

exceeds the amount it ultimately costs the homeowner to complete the

garage ($60,000). In other words, she has not suffered any “loss” where she

has received a garage worth, to her, $100,000, after paying only $60,000 for

its construction. Allowing the homeowner additional recovery under the

Fund would exceed what is proper as expectation damages.

6

RAMSEY v. AZROC

Opinion of the Court

¶14 If, on the other hand, the initial cost of the contract remains

$100,000 and the amount paid to contractor A remains $10,000 but the

reasonable cost for contractor B to correct contractor A’s mistakes and

complete the garage is $120,000, the homeowner may be eligible to recover

from the Fund because, as a result of contractor A’s breach, homeowner has

to pay $130,000 for a garage worth $100,000. Under these circumstances,

the homeowner can recover the amount of the difference left owing on the

first contract ($90,000) and what it ultimately cost him to complete the

garage ($120,000), or $30,000. The homeowner requires additional funds to

be made “whole” because she has to pay more than originally anticipated

to obtain the contracted-for product.

¶15 Ramsey argues the ROC’s interpretation fails to account for

the unscrupulous contractor, who inflates the cost of completing a project,

performs poorly, and walks away. However, the Fund is not and was never

intended to serve as a panacea for every ill-advised construction contract.

To the extent a contractor breaches an unscrupulously inflated construction

contract, the homeowner is in no worse shape as to her contracted-for

expectations. Indeed, it can be argued the homeowner is actually in better

shape upon breach because she ultimately received the desired result for

less than anticipated, and further payout from the Fund is not required by

A.R.S. § 32-1232(A).

¶16 Moreover, the agency’s interpretation need not account for

every contingency, nor be the most reasonable construction, to warrant

deference. Kobold, 239 Ariz. at 262, ¶ 9 (citing Mead, 533 U.S. at 229, and

Entergy Corp. v. Riverkeeper, Inc., 556 U.S. 208, 218 (2009)). The ROC’s

interpretation of the statute eliminates the risk that a homeowner will

receive a windfall as a result of the residential contractor’s misconduct at

the expense of the licensed contractors who contribute to the Fund. See

A.R.S. § 32-1132(B). This notion is consistent with Arizona law, see A

Tumbling-T Ranches v. Flood Control Dist. of Maricopa Cty., 222 Ariz. 515, 535-

36, ¶ 61 (App. 2009) (approving a jury instruction on the available measure

of damages that “reflected the true economic loss” of the injured

landowners and rejecting an alternate theory that would result in a windfall

at the defendants’ expense) (citation omitted); Restatement (First) of

Contracts § 346 cmt. b (prohibiting an award of damages that would result

in economic waste, or “cost[s] that would be imprudent and

unreasonable”), and the statute’s own limiting language, see A.R.S. § 32-

1132(A) (“[D]amages . . . shall not exceed an amount necessary to complete

or repair a residential structure or appurtenance within residential property

lines.”).

7

RAMSEY v. AZROC

Opinion of the Court

¶17 We cannot say the agency’s interpretation is either incorrect

or unreasonable. Accordingly, we adopt the ROC’s interpretation of

“actual damages” under A.R.S. § 32-1132(A) and remand for

reconsideration of Ramsey’s application for recovery from the Fund.

III. Where the ROC’s Objection Presents a Purely Legal Question, No

Hearing Is Required.

¶18 The ROC also argues it is entitled to an evidentiary hearing

pursuant to A.R.S. § 32-1136(B) upon the lodging of any objection to a

homeowner’s application for recovery from the Fund. Resolution of this

question requires further consideration of the statute, which we again

undertake de novo. See supra ¶ 6.

¶19 Section 32-1136(B) states that upon “recei[pt of] written

objections by the registrar, the court shall not direct payment from the fund

without affording the registrar a reasonable opportunity to present and

support his objections.” This section establishes the ROC’s procedural

rights relative to a claim against the Fund — “notice and an opportunity to

be heard in a meaningful manner.” Magness, 234 Ariz. at 431, ¶ 11.

Although a reasonable opportunity to be heard is often equated with a

hearing, the terms are not synonymous; what is reasonable will depend

upon the circumstances of the case. See Mathews v. Eldridge, 424 U.S. 319,

333-34 (1976) (“Due process is flexible and calls for such procedural

protections as the particular situation demands.”) (quoting Morrissey v.

Brewer, 408 U.S. 471, 481 (1972)); see also Carlson v. Ariz. State Pers. Bd., 214

Ariz. 426, 430-31, ¶ 15 (App. 2007) (noting the flexible nature of due process

does not require elaborate administrative hearings as long as there is notice

and opportunity to be heard) (citing Cleveland Bd. of Educ. v. Loudermill, 470

U.S. 532, 545 (1985)).

¶20 Section 32-1136(B) does not, by its plain terms, require a

hearing, but rather an opportunity to be heard. Although the ROC relies

upon Magness in arguing an absolute right to a hearing, Magness is

distinguishable. There, this Court rejected the applicant’s argument that no

hearing was required because the ROC did not contest the eligibility

requirements outlined in A.R.S. § 32-1136(D), holding instead that a hearing

is required where the ROC challenges an applicant’s lack of compliance

with requirements set forth anywhere in the statutory scheme. Magness,

234 Ariz. at 432-33, ¶¶ 16-18. This principle is sound. However, when the

ROC’s objection presents a purely legal question, fully briefed before the

trial court, an evidentiary hearing would serve no purpose. See Bills v. Ariz.

State Bd. of Educ., 169 Ariz. 366, 370 (App. 1991) (concluding no remand was

8

RAMSEY v. AZROC

Opinion of the Court

necessary where issues could be disposed of through summary judgment

because they presented “only questions of law which we are able to resolve

by statutory interpretation”).

¶21 Forcing a hearing under such circumstances is contrary to

both principles of judicial efficiency and the legislature’s direction that

applications for recovery from the Fund be addressed without delay. See

Ariz. R. Civ. P. 7.1(c)(2) (“To expedite its business, the court may make

provision by rule or order for the submission and determination of motions

without oral hearing upon brief written statements of reasons in support

and opposition.”); Cristall v. Cristall, 225 Ariz. 591, 597, ¶ 29 (App. 2010)

(“[T]he trial court has discretion to grant or deny a request for oral

argument.”); see also supra ¶ 8 (discussing requirement that an application

for recovery from the Fund should be addressed in a summary manner).

We therefore hold the ROC’s opportunity to present and support its

objections identified with A.R.S. § 32-1136(B) may be satisfied without a

hearing if no factual matters are in dispute and the ROC’s objection presents

a legal matter appropriate for resolution by the trial court. Because the

ROC’s objection here was based upon the statutory definition of damages,

no hearing was required.

IV. Substantial Evidence Supports the Trial Court’s Finding that the

ROC Conceded the Amount Ramsey Spent to Complete the

Residence.

¶22 The ROC argues the trial court abused its discretion in finding

it had conceded Ramsey spent $52,101.29 to complete the Residence. We

will not set aside the trial court’s factual findings unless they are clearly

erroneous. Ariz. R. Civ. P. 52(a); see also Clark v. Anjackco Inc., 235 Ariz. 452,

456, ¶ 14 (App. 2014) (citing Phx. Newspapers Inc. v. Ariz. Dep’t of Corr., 188

Ariz. 237, 244 (App. 1997)). “A finding of fact is not clearly erroneous if

substantial evidence supports it, even if substantial conflicting evidence

exists.” Kocher v. Dep’t of Revenue of Ariz., 206 Ariz. 480, 482, ¶ 9 (App. 2003)

(citing Moore v. Title Ins. Co. of Minn., 148 Ariz. 408, 413 (App. 1985)).

¶23 The record reflects that, within its notice of rejection, the ROC

identifies the relevant figure, $52,101.29, as both “[t]he amount[] that

[Ramsey] established that she spent repairing or completing her residence,”

and “verified expenditures to complete [the] project.” In its response to

Ramsey’s application, the ROC admits Ramsey provided evidence to

support this figure. Although the ROC’s counsel indicated he “believe[d]

that the ROC still ha[d] some concerns about proofs offered in support of

some payments” and that its final decision would be “based on the

9

RAMSEY v. AZROC

Opinion of the Court

assumption those payments were proven,” these concerns were expressed

three weeks before formal notice of the ROC’s objection to Ramsey’s claim

and are not reflected either in the notice of rejection or the response to

Ramsey’s application. Nor did the ROC ever object to the $52,101.29 figure,

describe it as an approximation or demonstrative figure subject to further

proof, or otherwise express any specific intent to challenge it in this case,

even after Ramsey asserted the ROC made an “on-the-record

acknowledgment of her damages.” Instead, the ROC was clear that its sole

objection to Ramsey’s application was based upon its interpretation of

A.R.S. § 32-1132(A) and not the specific figures to be entered into the

calculation.

¶24 A party is bound by factual admissions or concessions made

in its pleadings. KCI Rest. Mgmt. L.L.C. v. Holm Wright Hyde & Hays P.L.C.,

236 Ariz. 485, 488, ¶ 12 (App. 2014) (citing Bank of Am. Nat’l Tr. & Sav. Ass’n

v. Maricopa Cty., 196 Ariz. 173, 176, ¶ 11 (App. 1999)). Substantial evidence

exists to support the trial court’s determination that the ROC conceded

Ramsey spent $52,101.29 to complete the Residence,4 and we find no abuse

of discretion.

CONCLUSION

¶25 We vacate the trial court’s order and remand for

reconsideration of Ramsey’s application for recovery from the Fund. We

leave to the trial court the issue of whether, under our interpretation of

A.R.S. § 32-1132(A), Ramsey’s application and the ROC’s objection present

questions of fact or law for which additional briefing, argument, or

evidence is required.

AMY M. WOOD • Clerk of the Court

FILED: AA

4 We take no position on the significance of this finding in light of the

principles articulated in Part II, supra, but note the trial court made no

finding regarding Ramsey’s assertion that she paid “well over $100,000” to

remedy the deficiencies in the Edens’ performance. Such a finding was

immaterial under the court’s erroneous interpretation of A.R.S. § 32-

1132(A). See supra ¶ 5. These and any remaining factual matters are best

handled on remand.

10

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.