Opinion

Bradley B. Ware v. Texas Commission on Environmental Quality

Court
Texas Court of Appeals, 3rd District (Austin)
Filed
May 7, 2015
Status
Published
Cited by
0 cases
Authority
More cited than 3.0%

The opinion

ACCEPTED

03-14-00416-CV

5197870

THIRD COURT OF APPEALS

AUSTIN, TEXAS

5/7/2015 3:28:51 PM

JEFFREY D. KYLE

CLERK

Case No. 03-14-00416-CV

IN THE FILED IN

3rd COURT OF APPEALS

THIRD COURT OF APPEALS AUSTIN, TEXAS

AT AUSTIN, TEXAS 5/7/2015 3:28:51 PM

JEFFREY D. KYLE

Clerk

BRADLEY B. WARE,

Appellant,

v.

TEXAS COMMISSION ON ENVIROMENTAL QUALITY,

Appellee.

ON APPEAL FROM THE 53RD JUDICIAL DISTRICT COURT OF TRAVIS

COUNTY, TEXAS

APPELLANT’S REPLY BRIEF

Stephen P. Webb

Bar No. 21033800

s.p.webb@webbwebblaw.com

Gwendolyn Hill Webb

Bar No. 21026300

g.hill.webb@webbwebblaw.com

Attorneys for Appellant

Webb & Webb, Attorneys at Law

211 East Seventh Street

Austin, Texas 78701

Phone: 512-472-9990

APPELLANT REQUESTS ORAL ARGUMENT

Case No. 03-14-00416-CV

BRADLEY B. WARE,

Appellant,

v.

TEXAS COMMISSION ON ENVIRONMENTAL QUALITY,

Appellee.

REQUEST FOR ORAL ARGUMENT

Appellant, Bradley B. Ware, requests an oral argument in this case.

i

TABLE OF CONTENTS

Request for Oral Argument .........................................................................................i

Index of Authorities ................................................................................................. iii

Appellant’s Reply Brief ............................................................................................. 1

Additional Procedural History ................................................................................... 1

Restatement and Update of Standard of Review ....................................................... 2

Introduction and Summary ........................................................................................ 7

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to All of Ware’s Points of

Error ............................................................................................................... 11

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to Ware’s Point of Error

Number 1. ...................................................................................................... 19

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to Ware’s Point of Error

Numbers 2 and 5 ............................................................................................ 21

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to Ware’s Point of Error

Number 3. ...................................................................................................... 23

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to Ware’s Point of Error

Number 4. ...................................................................................................... 24

Ware’s Reply to Appellee TCEQ’s Brief Pertaining to Ware’s Point of Error

Number 6. ...................................................................................................... 25

Conclusion ............................................................................................................... 26

Prayer for Relief ....................................................................................................... 29

Certificate of Compliance ........................................................................................ 30

Certificate of Service ............................................................................................... 31

Appendix .................................................................................................................. 31

ii

INDEX OF AUTHORITIES

CASES

City of Dallas v. Stewart, 361 S.W. 3d 562 (Tex. 2012) ........................................ 22

Lower Colorado River Authority, et al, v. Texas Department of Water Resources,

689 S.W. 2d 873 (Tex. 1984) ....................................................................... 12

Madden v. Tex. Bd. of Chiropractic Examiners, 663 S.W.2d 622 (Tex. App. Austin

1985) ................................................................................................................ 8

McWatt v. Mattax, 03-133-00332-CV (Tex. App. – Austin 3-18-2015) ............... 4, 5

Oncor Electric Delivery Co. v. Public Utility Commission, 406 S. W. 3d 253 (Tex.

App. Austin 2013) .......................................................................................... 8

TCEQ v. Texas Farm Bureau, et al, Cause No. 13-13-00415-CV (13th Court of

Appeals, Corpus Christi-Edinburg, April 2, 2015) ....................................... 10

Texas State Bd. Of Examiners of Marriage and Family Therapists v. Texas

Medical Assn, No. 03-13-00077-CV, November 21, 2014 ........................... 23

PUC v. City of Austin, 728 S.W.2d 907 (Tex. App. Austin 1987) .......................... 22

Railroad Commission of Texas v. Citizens for a Safe Future & Clean Water, 336

S.W.3d 619 (Tex. 2011) .................................................................................. 6

TEXAS GOVERNMENT CODE

§2001.174 ................................................................................................................ 3,4

TEXAS WATER CODE

§11.021 ................................................................................................................. 9, 20

§11.022 ....................................................................................................................... 9

§11.025 ................................................................................................................ 9, 12

§11.026 ....................................................................................................................... 9

§11.027 ................................................................................................................. 9, 11

§11.046 ...........................................................................................................9, 15, 16

§11.121 ....................................................................................................................... 9

iii

§11.134 ....................................................................................................................... 9

§11.1381 .........................................................................................................9, 13, 14

§11.141 ....................................................................................................................... 9

iv

Case No. 03-14-00416-CV

BRADLEY B. WARE,

Appellant,

v.

TEXAS COMMISSION ON ENVIRONMENTAL QUALITY,

Appellee.

APPELLANT’S REPLY BRIEF

TO THE HONORABLE THIRD COURT OF CIVIL APPEALS:

Appellant, Bradley B. Ware, submits this Reply Brief in appeal of the Order

of the Texas State District Court on administrative appeal affirming the decision of

the Texas Commission on Environmental Quality1 (“TCEQ,” “Commission,” or

“Agency”). This Appeal is from the District Court of Travis County, Texas, 53 rd

Judicial District, the Honorable John Dietz presiding, in which Appellant was the

Plaintiff and Appellee was the Defendant. Appellant Bradley B. Ware may be

referred to in this Reply Brief as “Plaintiff,” “Appellant,” “Ware,” or “Mr. Ware;”

1

To avoid unnecessary confusion in this Reply Brief, the Texas Commission on Environmental

Quality refers to the Texas Commission on Environmental Quality and any of its predecessor

agencies, including the Texas Water Rights Commission, the Texas Department of Water

Resources, the Texas Water Commission, and the Texas Natural Resources Conservation

Commission.

and Appellee, the Texas Commission on Environmental Quality may be referred to

as “Defendant,” “Appellee,” “TCEQ,” “Commission,” or “Agency.”

I. ADDITIONAL PROCEDURAL HISTORY

The prior procedural history of this case is set out in full Appellant’s Brief,

pp. 5-6, in the Statement of Facts. The additional procedural history is set out

below.

1. On January 15, 2015, Ware filed his Appellant’s Brief, wherein he requested

oral argument.

2. On February 13, 2015, TCEQ filed its Unopposed Motion for Extension of

Time for Appellee Texas Commission on Environmental Quality to File

Brief.

3. On February 13, 2015, the Court issued correspondence granting Appellee’s

Unopposed Motion for Extension of Time for Appellee to File Reply Brief.

4. On April 17, 2015, TCEQ filed its Appellee’s Brief.

II. RESTATEMENT AND UPDATE OF STANDARD OF REVIEW

Appellee TCEQ faults Appellant’s brief for not including a Standard of

Review. In light of Appellee’s comment, Appellee restates the Standard of Review

details set out in Appellant’s Brief, pp.2-4, under the heading “Statement of the

APPELLANT’S REPLY BRIEF PAGE 2

Case,” and updated by recent applicable case law. The Standard of Review is Tex.

Gov’t Code, §2001.174, which states:

Sec. 2001.174. REVIEW UNDER SUBSTANTIAL

EVIDENCE RULE OR UNDEFINED SCOPE OF REVIEW.

If the law authorizes review of a decision in a contested case

under the substantial evidence rule or if the law does not define

the scope of judicial review, a court may not substitute its

judgment for the judgment of the state agency on the weight of

the evidence on questions committed to agency discretion but:

(1) may affirm the agency decision in whole or in part; and

(2) shall reverse or remand the case for further proceedings

if substantial rights of the appellant have been prejudiced

because the administrative findings, inferences, conclusions,

or decisions are:

(A) in violation of a constitutional or statutory provision;

(B) in excess of the agency's statutory authority;

(C) made through unlawful procedure;

(D) affected by other error of law;

(E) not reasonably supported by substantial evidence

considering the reliable and probative evidence in the record as

a whole; or

(F) arbitrary or capricious or characterized by abuse of

discretion or clearly unwarranted exercise of discretion.

Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1,

1993.

Plaintiff, Bradley B. Ware appeals from the 53rd Judicial District Court of

Travis County, Texas for its failure to overturn the final order of the TCEQ which

denied Plaintiff the right to continue to divert and use water under Permit to

Appropriate State Water No. 5594 (“Permit No. 5594”), attached hereto as Exhibit

A. Appellant asserts that the Commission’s April 20, 2010 Final Order of the

APPELLANT’S REPLY BRIEF PAGE 3

TCEQ (“Order”) violates extant provisions of the Texas Water Code (“TWC”),

and contains reversible legal error.

Generally, as argued below, the Commission’s order is in violation of the

fundamental precepts of the Constitution of the United States (5 th and 14th

Amendments) and the Texas Constitution (Art. 1, Bill of Rights, Sections 3 and

19), the Texas Water Code and the Texas Government Code; is in excess of the

Commission’s statutory authority; is made through unlawful procedure; is affected

by numerous other errors of law; is not reasonably supported by substantial

evidence when considering the record as a whole; and is on its face arbitrary,

capricious, and characterized by abuse of discretion, or clearly unwarranted

exercise of discretion. The Commission’s final order is not entitled to the deference

that agency decisions are afforded in a simple substantial evidence factual review.

Put simply, the Commission’s April 20, 2010 TCEQ Order is subject to

reversal because it finds and concludes that there is State water available for

appropriation in the Brazos River Basin in the form of return flows, but reserves

the available water to a pending Applicant Brazos River Authority (“BRA”) -- not

an existing or senior appropriator-- and denies water availability as to Ware’s

application against the substantial evidence of record and contrary to the prior

appropriation doctrine. The trial court erred in failing to recognize these

APPELLANT’S REPLY BRIEF PAGE 4

deficiencies in the Commission’s April 20, 2010 Order and erred in rendering its

June 11, 2014 order which denied Plaintiff’s appeal.

The legal standard for a court’s consideration on appeal of the actions of

administrative agencies in contested case hearings was enunciated by this Court

very recently (March 18, 2015). The opinion in McWatt v. Mattax, 03-133-00332-

CV (Tex. App. – Austin 3-18-2015) is very clear on the role of the judiciary where

questions similar to those urged by Appellant in this case, are involved. The

McWatt v. Mattax, id., opinion states the requirements of Tex. Gov’t Code,

2001.174:

Section 2001.174 of the Texas Government Code provides the

standard for judicial review of the ALJ’s and the

Commissioner’s orders. See id2. §2001.174. Under this standard

we may not, with respect to questions committed to its

discretion, substitute our judgment on the weight of the

evidence for that of the agency. Id. We must, however, reverse

an order if it prejudices substantial rights because its findings,

inferences, conclusions, or decisions

(1) violate a constitutional or statutory provision;

(2) exceed statutory authority;

(3) were made through unlawful procedure;

(4) were affected by other error of law;

(5) are not reasonably supported by substantial evidence

considering the reliable and probative evidence in the record as

a whole; or

(6) are arbitrary or capricious or characterized by an abuse of

discretion or a clearly unwarranted exercise of discretion. Id.

McWatt v. Mattax, at p. 7

2

All “id.” references in the quote from McWatt v. Mattax refer to Texas Gov’t Code, § 2001.174(2) (setting forth

circumstances requiring reversal of agency’s decision in contested case). McWatt v. Mattax, p. 6.

APPELLANT’S REPLY BRIEF PAGE 5

Appellant contends that under the extant legal standard of review, Mr. Ware is

entitled to a reversal of the April 20, 2010 TCEQ Order and remand of his

amendment application for consideration in accordance with applicable facts and

full access to water available in the Brazos River Basin on the basis of his senior

appropriation under the prior appropriation doctrine.

The statutory legal standard is especially important in this case, where

Appellee TCEQ clings to its experts’ versions of the facts, attempting to remove

the Court’s focus from the TCEQ’s violations of constitutional and statutory

provisions, exceedance of statutory authority, unlawful procedures, errors of law,

and abuse of and clearly unwarranted exercise of discretion. Therefore, the TCEQ

should not be allowed to justify its legal missteps in the law by asserting that it has

broad discretion to construe the facts in this case under the protection of substantial

evidence review. It is well settled that the resolution of constitutional questions

such as due process, statutory construction and any other question of law is to

reviewed de novo by a court. [See, Railroad Commission of Texas v. Citizens for a

Safe Future & Clean Water, 336 S.W. 3rd 619, 624 (Tex 2011)] The case is about

the adoption by the TCEQ of a regulatory scheme regarding return State water,

flows, water availability, and water rights permitting which does not appear in its

regulations and is contrary to the statutory directives of the Texas Water Code.

The Agency’s abuse of discretion and its clearly unwarranted exercise of discretion

APPELLANT’S REPLY BRIEF PAGE 6

are demonstrated in its failure to announce regulations concerning the

appropriation of State water in the form of return flows; the implementation of the

unwritten regulations first by TCEQ staff during the contested case hearing and

then by the Commission without full notice and comment; and the implementation

of the unwritten regulations based on the TCEQ’s previously unannounced

interpretations of the Texas Water Code which are directly contrary to the Texas

Water Code’s statutory directives.

III. INTRODUCTION AND SUMMARY

Citizens of Texas, regardless of their occupation or financial circumstance,

have every reason to expect to be treated fairly by their state government and in

accordance with applicable law. In Texas, where water resources are often in short

supply, the Texas Legislature adopted the prior appropriation system and, over

time, organized a variety of state agencies to implement the doctrine of prior

appropriation in accordance with the specific mandates of the Texas Water Code,

the general guidelines of our Texas Constitution and applicable laws, and

especially in this instance, the substantive and procedural due process mandates of

the Texas Administrative Procedures Act. In this case, the staff and Commissioners

of the Texas Commission on Environmental Quality substituted their own

unwritten scheme of water rights permitting and administration for the legal

APPELLANT’S REPLY BRIEF PAGE 7

mandates of the Texas Legislature and the prior appropriation doctrine. In this

case, contrary to the legal mandates of the Texas Legislature, Commission staff

developed and implemented a system whereby later applications of some would-be

junior appropriators were entitled to consideration based on a complete and full

analysis of water availability under the Texas Water Code, and other senior water

rights holders, independent of their priority dates, were not entitled to

consideration of their applications based on a comprehensive determination of

water availability. The courts have held that it is a denial of due process for an

agency to fail to adopt any written statements of agency policy regarding such

issues as priority dates in existing permits so as to provide notice to an applicant of

the burden of proof. [See, Madden v. Tex. Bd. of Chiropractic Examiners, 663

S.W. 2d 622,626 (Tex. App. Austin 1985); and Oncor Electric Delivery Co. v.

Public Utility Commission, 406 S. W. 3d 253, 269 (Tex. App. Austin 2013).

This appeal involves a case of first impression. Rather than adhere to the

legal mandates of the Texas Water Code, which are set out below for ease of

reference, Appellee TCEQ asks this court to accept and to validate its own water

rights permitting and administration system, which it has yet to codify in Agency

regulations. The most important and applicable provisions which TCEQ seeks to

reinterpret to Appellant’s detriment are in the following sections of Texas Water

Code, Chapter 11:

APPELLANT’S REPLY BRIEF PAGE 8

§ 11.021, State Water - Asserts State sovereignty over the surface

waters of the State in watercourses

§ 11.022, Acquisition of Right to Use State Water - Provides for the

use of State water by authorized appropriators;

§ 11.025, Scope of Appropriative Right - Sets forth the limitations of

the appropriative rights;

§ 11.026, Perfection of an Appropriation - Provides for perfection of

an appropriation by beneficial use in accordance with the permit;

§ 11.027, Rights Between Appropriators - Provides for resolution of

conflict between appropriators on the basis of “first in time is first in

right;”

§ 11.046, Return Surplus Water - Provides that water authorized to

be appropriated but not needed for the authorized use be returned to

the watercourse for further appropriation and for other uses;

§ 11.121, Permit Required - Requires the issuance of water rights

permits to authorize appropriation

§ 11.134, Action on Application - Specifies the conditions under

which the Commission may grant a water rights permit;

§ 11.1381, Term Permits - Establishes a means for issuance of term

permits; and

§ 11.141, Date of Priority - Establishes the priority date for water

rights permits as the date the application was filed.

Taken as whole, the provisions of the Texas Water Code establish the regulatory

framework for the administration of Texas water rights.

APPELLANT’S REPLY BRIEF PAGE 9

At the same time, the water rights program which TCEQ now informs the

Court that it is implementing through the factual assertions of its water rights

permitting staff cannot be allowed to substitute for the legal mandates and

fundamental fairness of the “first in time, first in right” principles of Texas water

law which have withstood the test of generations of continued economic growth

and must continue to be the legal basis of water rights administration by the TCEQ.

The Texas Legislature has not authorized the TCEQ to determine water availability

based on which applicants it would like to grant rights in State water to, regardless

of priority dates. Generally, in its Reply Brief, the TCEQ informs the Court that

“this is how we administer water rights at the TCEQ,” in a manner which is

contrary to law, has no statutory support, and is contrary to the plain terms and

conditions of the Commission’s Final Orders and the Permit to Appropriate State

Water No. 5594 issued by the Commission. This Court of Appeals, as the Corpus

Christi-Edinburg Court of Appeals did recently in TCEQ v. Texas Farm Bureau, et

al, Cause No. 13-13-00415-CV (13th Court of Appeals, Corpus Christi-Edinburg,

April 2, 2015) can honor the doctrine of separation of powers and inform the

TCEQ that it must follow the doctrine of prior appropriation for all water rights

holders.

Appellant TCEQ’s brief contains no case law, statutory basis, or

Commission regulation in support of its contention that it can grant or deny water

APPELLANT’S REPLY BRIEF PAGE 10

rights without reference to the priority dates included in the permits. Consequently,

the standards of substantial evidence review require a result in favor of Appellant.

The actions of the TCEQ in denying Mr. Ware’s renewal of his term permit are

arbitrary, capricious, founded upon unlawful procedure, and constitute an

unreasonable denial of Appellant’s property right in State water.

IV. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

ALL OF WARE’S POINTS OF ERROR

The main contention of TCEQ in this appeal relating all Appellant’s Points

of Error is that the Commission is entitled to implement a policy of water rights

permitting and administration whereby some State water in the form of return

flows is reserved for later applicants, as opposed to being considered available for

appropriation in accordance with the first in time, first in right principle of the prior

appropriation doctrine set forth in Tex. Water Code §11.027, which states:

RIGHTS BETWEEN APPROPRIATORS. As between appropriators,

the first in time is the first in right.

Amended by Acts 1977, 65th Leg., p. 2207, ch. 870, Sec. 1, eff. Sept.

1, 1977.

TCEQ staff contends that term permit holders are not appropriators, or are a

separate class of appropriators with a floating priority date.

APPELLANT’S REPLY BRIEF PAGE 11

As both Appellant and Appellee have stated, the statutory authorization to

issue term permits came about because the Texas Supreme Court specifically

found that the Commission practice of issuing permits based on streamflows and

assuming that not all permitted water would be put to beneficial use by existing

permittee was unlawful double permitting of already appropriated water. See,

Lower Colorado River Authority v. Texas Department of Water Resources, 689

S.W. 2d 873 (Tex. 1984), sometimes referred to as the Stacy Dam Decision. In

that case, the Texas Supreme Court stated:

Under the law, the Department [of Water Resources] may not grant permits

when its own records show that the supply must come from an existing

downstream permittee’s water that the Department speculates he will not

actually need. [TWC] Section 11.0253 places a limit on the amount of

water that can be used beneficially or the amount the senior holders can

claim, even though the face amount of their permits may be more.

* * * * *

The Water District [LCRA] and the Department have a remedy expressly

granted by the Legislature. If there exists recorded permits, filings and

certificate of adjudication that will not reasonably be used in the future, the

Department or another interested party may seek total or partial

cancellation of those rights. Only after sufficient cancellations have freed

that water from its commitment, may the Department again grant a permit

to appropriate it. Id., at p. 882.

3

Tex. Water Code, Sec. 11.025. SCOPE OF APPROPRIATIVE RIGHT. A right to use state

water under a permit or a certified filing is limited not only to the amount specifically

appropriated but also to the amount which is being or can be beneficially used for the purposes

specified in the appropriation, and all water not so used is considered not appropriated.

APPELLANT’S REPLY BRIEF PAGE 12

As a result of the Stacy Dam Decision, the Commission was temporarily prohibited

from issuing new water rights based on permitted water not being put to beneficial

use.

Appellee TCEQ’s assertions regarding the nature of term permits as not

being permanent water rights and subject to full access to water availability is

inconsistent with written Agency policy and the water code. Specifically, Tex.

Water Code, §11.1381 establishes the TCEQ’s right to issue term permits as

follows:

Sec. 11.1381. TERM PERMITS. (a) Until a water right is

perfected to the full extent provided by Section 11.026 of this

code, the commission may issue permits for a term of years for

use of state water to which a senior water right has not been

perfected.

(b) The commission shall refuse to grant an application for a

permit under this section if the commission finds that there is a

substantial likelihood that the issuance of the permit will

jeopardize financial commitments made for water projects that

have been built or that are being built to optimally develop the

water resources of the area.

(c) The commission shall refuse to grant an application for a

term permit if the holder of the senior appropriative water right

can demonstrate that the issuance of the term permit would

prohibit the senior appropriative water right holder from

beneficially using the senior rights during the term of the term

permit. Such demonstration will be made using reasonable

projections based on accepted methods.

(d) A permit issued under this section is subordinate to any

senior appropriative water rights.

Added by Acts 1987, 70th Leg., ch. 405, Sec. 1, eff. Sept. 1,

1987.

APPELLANT’S REPLY BRIEF PAGE 13

Effective September 1, 1987, the Commission was authorized to issue water rights

for unspecified terms to allow for the use of state water not being put to beneficial

use. Read together, the Stacy Dam Decision and TWC, §11.1381 authorized the

Commission to issue permits for available streamflows not needed by senior

downstream water rights holders4 until such time as water became available as

permits were cancelled for total or partial nonuse under the Texas Water Code’s

cancellation provisions in TWC, Ch. 11, Subch. E, §§11.171-11.186. Term

Permits are specifically subject to the same requirements of all permits under

TWC, §11.134(b), Action on Application, and those same requirements are

clarified and emphasized in TWC, §13.1381 specifically identifying public interest

concerns of the financial viability of water projects (§11.1381(b), and the specific

opportunity for a demonstration of harm by a senior appropriator (§11.1381(b).

But, the limitation of TWC, §11.1381(d), that “A permit issued under this section

is subordinate to any senior appropriative water rights” is no different from the

general limitations of the doctrine of prior appropriation. Every single water rights

permit issued by the Commission for any purpose or for any length of time

contains the proviso: “This permit [or amendment] is issued subject to senior and

superior water rights in the _________ River Basin.” This proviso is not unique to

term permits. Even if it were, there is no seniority or superiority as between an

4

Note that this refers to senior downstream water rights holders, not applicants, perspective

water rights holders or junior water rights holders.

APPELLANT’S REPLY BRIEF PAGE 14

authorized appropriator and an applicant. As between appropriators, first in time

is first in right; Appellant does not claim or request a water right to divert and use

water already permitted to senior appropriators.

In addition to authorizing the issuance of term permits for permitted but

unused water in TWC, §11.1381, however, the Texas Legislature made additional

water available for appropriation under TWC, §11.046. In many ways, TWC,

§11.046 is a codification of the previous Commission analysis of permits being

limited to the water actually being beneficially used by the permittee; and allowing

the Commission to authorize new appropriations for water returned to the stream

after its permitted use. TWC, §11.046 states as follows:

Sec. 11.046. RETURN SURPLUS WATER. (a) A person who

takes or diverts water from a watercourse or stream for the

purposes authorized by this code shall conduct surplus water

back to the watercourse or stream from which it was taken if the

water can be returned by gravity flow and it is reasonably

practicable to do so.

(b) In granting an application for a water right, the commission

may include conditions in the water right providing for the

return of surplus water, in a specific amount or percentage of

water diverted, and the return point on a watercourse or stream

as necessary to protect senior downstream permits, certified

filings, or certificates of adjudication or to provide flows for

instream uses or bays and estuaries.

(c) Except as specifically provided otherwise in the water right,

water appropriated under a permit, certified filing, or certificate

of adjudication may, prior to its release into a watercourse or

stream, be beneficially used and reused by the holder of a

permit, certified filing, or certificate of adjudication for the

purposes and locations of use provided in the permit, certified

filing, or certificate of adjudication. Once water has been

APPELLANT’S REPLY BRIEF PAGE 15

diverted under a permit, certified filing, or certificate of

adjudication and then returned to a watercourse or stream,

however, it is considered surplus water and therefore

subject to reservation for instream uses or beneficial inflows

or to appropriation by others unless expressly provided

otherwise in the permit, certified filing, or certificate of

adjudication.

(d) Water appropriated under a permit, certified filing, or

certificate of adjudication which is recirculated within a

reservoir for cooling purposes shall not be considered to be

surplus for purposes of this chapter.

Amended by Acts 1977, 65th Leg., p. 2207, ch. 870, Sec. 1, eff.

Sept. 1, 1977; Acts 1997, 75th Leg., ch. 1010, Sec. 2.07, eff.

Sept. 1, 1997.

The additional water—return flows—referred to in TWC, §11.046(c) is

specifically water which is returned to a stream after use, such as a municipal

discharge, for example, and the water becomes available for environmental

purposes “or to appropriation by others.” Nothing in TWC, §11.046(c) authorizes

the TCEQ to treat the appropriation of return flows in manner other than on a first

in time, first in right basis.

In Appellee’s Brief, TCEQ attempts to convince the Court that Ware’s water

right was a not a permanent water right and that Permit to Appropriate State Water

No. 5594 had no priority date, expired by its own terms, and was part of a separate

class of water rights not entitled to consideration under the prior appropriation

doctrine. The TCEQ’s argument rests entirely on its own policy of expedience;

TCEQ has offered no basis beyond its non-lawyer expert staff assertions in favor

APPELLANT’S REPLY BRIEF PAGE 16

of these “unwritten rules” and statutory interpretations which fall outside of the

Agency’s historical practice and factual determinations of water available for

appropriation. Simply put, there is no law which supports the TCEQ’s position in

this case; the doctrine of prior appropriation favors Appellant.

Not only do these TCEQ assertions have no basis in statute, but they are

directly contrary to the plain language of Ware’s Permit No. 5594. Permit No.

5594 grants a water right with a priority date for a term of years, and states

explicitly:

3. SPECIAL CONDITIONS

The authorization to divert and use 130 acre-feet of water per

year shall expire and become null and void on November 7,

2007 unless prior to such date permittee applies for an

extension hereof and such application is subsequently granted

for an additional term or in perpetuity. The priority date of

this permit and all extensions hereof shall be July 1, 1997.

It is undisputed that Appellant filed his application prior to November 7, 2007; that

the TCEQ found the application to be administratively complete on March 20,

2006; and that the TCEQ issued notice of the application stating that Ware:

“has applied for an amendment to its existing Water Use Permit

on the Lampasas River, Brazos River Basin, in Bell County to

extend or delete the expiration date of November 7, 2007,

add an additional 31 acres for irrigation, and to divert and use

an additional 20 acre-feet of water5.”

5

See TCEQ Interoffice Memorandum dated March 20, 2006, SUBJECT: Bradley B. Ware;

CN601474224, RN102842416; Application No. 5594A to Amend Water Use Permit No. 5594;

APPELLANT’S REPLY BRIEF PAGE 17

It is simply not true, as TCEQ asserts in Appellee’s Brief, that water rights issued

for a term of years were not issued with priority dates and were not therefore

subject to periodic review and consideration of water availability during that

review.

More importantly, TCEQ’s assertion goes against the evidence in the case

which establishes that the TCEQ policy on amendment of term permit water rights

holders was to grant permanent water rights when, upon review of the amendment

applications, it was found that water was available for appropriation in the

requested source of supply. The undisputed evidence in this case establishes that

Samuel W. Jones, P. E. a former TCEQ employee and part owner of water rights

Permit No. 4166, as amended, was granted a permit for diversion and use of 120

acre-feet of water from Brushy Creek in Williamson County for a term of years on

December 18, 1984 with a July 31, 1984 priority date. He applied for an

amendment similar to Appellant’s (increase in irrigation acreage) in 2000 and was

granted a perpetual water right with an April 26, 1984 priority date. 6 The simple

truth is that in this case, the TCEQ, in reviewing water availability in the Brazos

TWC §11.122, Requiring Mailed and Published Notice; Lampasas River, Brazos River Basin;

Bell County, attached hereto as Exhibit C.

6

This priority date which appears in the preamble of Permit No. 4166A appears to be an error,

and the use of the date Application No. 4470 for Permit No. 4166 was received, rather than the

date it was filed, which was correctly set out in the Special Condition 3. (b), of Permit No. 4166,

which stated: The priority date for this permit and all extension hereof shall be July 31, 1984.

APPELLANT’S REPLY BRIEF PAGE 18

River Basin, found that it was only available for BRA and that the same State

water which flowed past Appellant’s diversion point associated with his earlier

priority, should not be made available to Mr. Ware.

IV. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

WARE’S POINT OF ERROR NO. 1

Ware’s Point of Error One:

The District Court erred in failing to find that the Commission’s April 20, 2010

Order unlawfully ignores the evidence of record regarding the water available for

appropriation by Plaintiff; therefore, the Commission’s action in adopting the April

20, 2010 Order was arbitrary and capricious, and was characterized by an abuse of

discretion.

In Appellee’s Brief, the TCEQ’s claim that return flows are not available to

Appellant, rests on an unauthorized and unlawful attempt to create a separate class

of State water, return flows, to be administered by the TCEQ under some basis

other than first in time, first in right, priority system of property rights in State

water. Again, the TCEQ’s brief presents no Agency rule or statute which supports

the TCEQ staff factual assertions. There is no legitimate factual issue as to

whether return flows are available for appropriation throughout the Brazos River

Basin—Appellant’s contested case hearing Exhibit No. 50, attached hereto as

Exhibit B, a November 25, 2008 Water Availability Analysis regarding

Application No. 5851 by Brazos River Authority specifically details the points of

APPELLANT’S REPLY BRIEF PAGE 19

discharge of over 100 million gallons per day in authorized discharges of treated

domestic wastewater effluent—return flows—which remain unappropriated.

There is no legal justification for reserving these return flows for a junior

applicant, while at the same time acting to terminate the water use of senior

appropriators on the basis that no water is available for appropriation throughout

the Brazos River Basin.7

Texas Water Code, §11.021 defines State water as follows:

Sec. 11.021. STATE WATER. (a) The water of the ordinary

flow, underflow, and tides of every flowing river, natural

stream, and lake, and of every bay or arm of the Gulf of

Mexico, and the storm water, floodwater, and rainwater of

every river, natural stream, canyon, ravine, depression, and

watershed in the state is the property of the state.

(b) Water imported from any source outside the boundaries of

the state for use in the state and which is transported through

the beds and banks of any navigable stream within the state or

by utilizing any facilities owned or operated by the state is the

property of the state.

Texas Water Code, §11.046 defines return flows, treated effluent wastewater

discharges, and makes them available for appropriation as stated above.

Return flows are State water, subject to appropriation in accordance with the

prior appropriation doctrine. There is no statutory basis which allows TCEQ to

reserve the use of State water in the form of return flows for potential junior

appropriators. The hearing testimony of TCEQ staff members regarding the TCEQ

7

TCEQ’s Finding of Fact No. 44-52.

APPELLANT’S REPLY BRIEF PAGE 20

uncodified policy to develop and apply certain water availability analyses for

certain applicants produces an unlawful reservation of State water which runs

counter to the prior appropriation doctrine principle of “first in time, first in right.”

The water availability analysis of the full amount of State water available for

appropriation throughout the Brazos River Basin, Appellant’s contested case

hearing Exhibit No. 50, showed that there are at least 580 acre-feet/year of

unappropriated return flows from the City of Lampasas which flow past

Appellant’s Ware Farm diversion point. Appellant TCEQ can point to no statutory

or regulatory authority which authorizes the TCEQ to withhold those return flows

from Appellant, and attempt to award them to BRA.

V. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

WARE’S POINT OF ERROR NO. 2 AND 5

Ware’s Point of Error Two:

The Commission’s April 20, 2010 Order violates the directives and requirements

of Texas Water Code, §11.134(b), regarding Commission action on water rights

applications.

Ware’s Point of Error Five:

The District Court erred in failing to find that the Commission acted arbitrarily and

capriciously to deprive Plaintiff of any continued right to divert and use any water

at any time for Ware Farm under Permit No. 5594, an authorized appropriation, on

the stated basis of no water available for appropriation, while at the same time

granting water rights for new appropriations and issuing statements of water

availability for other Plaintiffs, new permittees, and other water rights holders.

APPELLANT’S REPLY BRIEF PAGE 21

In Appellee’s Brief, the TCEQ again puts forward the assertions of TCEQ

non-lawyer experts as dispositive of the legality of the TCEQ’s unwritten law of

water rights permitting and administration concerning the availability of State

water in the form of return flows on a basis other than the prior appropriation

doctrine. TCEQ even goes so far as to say that the statutory framework set out in

the Texas Water Code regarding the availability of return flows for appropriation is

not significant. TCEQ staff’s and Commission’s erroneous construction of the

Texas Water Code is not controlling is this court in the guise of a substantial

evidence review. It is well settled that the court is the ultimate arbiter of statutory

construction, even though State agencies are allowed to construe enabling statutes

as they perform their duties. [See, City of Dallas v. Stewart, 361 S.W. 3d 562,579

(Tex. 2012); and PUC v. City of Austin, 728 S.W. 2d 907, 910 (Tex. App. Austin

1987)] Agencies and Staff are simply not legally authorized to develop and

implement policies which are directly contrary to or even unsupported by statutory

mandates.

The text of Texas Water Code, §11.027; §11.135(b); §11.1381; and §11.046

is plain and unambiguous. Therefore, the tortured statutory interpretations of the

TCEQ non-lawyer staff which run counter to the prior appropriation doctrine

should be disregarded. It simply is not the case that the statutes do not mean what

they plainly state and that water available for appropriation can be reserved for

APPELLANT’S REPLY BRIEF PAGE 22

what could only be a junior appropriator while senior appropriators are denied

access to those return flows.

Therefore, the Agency’s construction of the Texas Water Code, §11.027;

§11.135(b); §11.1381; and §11.046 are not entitled to judicial deference because

the subject sections are completely unambiguous. This court has recently held that

deference should be given to an agency’s interpretation of statutes only when the

statutory authority is ambiguous. Texas State Bd. Of Examiners of Marriage and

Family Therapists v. Texas Medical Assn, No. 03-13-00077-CV, November 21,

2014, citing Entergy Gulf States, Inc. v. Summers, 282 S.W. 3d 433, 437 (Tex.

2009).

VI. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

WARE’S POINT OF ERROR NO. 3

Ware’s Point of Error Three:

The District Court erred in failing to find that the Commission’s April 20, 2010

Order is in violation of the requirements of Texas Water Code, §11.1381,

regarding the consideration and granting of water rights permits for a term of

years.

In Appellee’s Brief, TCEQ attempts to convince the Court that specifically

quantified return flows shown to be available from various sources throughout the

Brazos River Basin and passing downstream to the authorized diversion point for

APPELLANT’S REPLY BRIEF PAGE 23

Permit No. 5594 should not be available to Appellant, but should be made

available to a later applicant, BRA.

TCEQ’s contention that the water is available only at the mouth of the

Brazos River directly contradicts the water availability analysis of Application No.

5851, Appellant’s contested case hearing Exhibit No. 50, which identifies not only

the specific locations, but also the specific amounts of return flows available

upstream of Ware Farm. TCEQ’s contention that State water is available in the

Brazos River Basin to BRA, a later applicant, but not to Ware, an earlier

appropriator makes no sense, and is not factually correct. It is simply not true that

State water is available in large quantities for a later applicant, but a much smaller

quantity of water is not available for a senior appropriator. And, any policy of the

TCEQ which provides for that result is unlawful.

VII. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

WARE’S POINT OF ERROR NO. 4

Point of Error Four:

The District Court in failing to find that the Commission’s April 20, 2010 Order

violates the fundamental doctrine of water rights law of “first in time, first in

right,” as set forth in the Texas Water Code, Section 11.027.

In Appellee’s Brief, TCEQ asserts that Permit No. 5549’s 1997 priority date

is meaningless and should be given no consideration as compared to later

applicants for water rights. Again, other than the assertions of TCEQ staff, and

APPELLANT’S REPLY BRIEF PAGE 24

Appellee TCEQ in its Brief, TCEQ offers no applicable law in support of this

contention. Not a single written or adopted rule of the TCEQ or statutory

interpretation authorizes the TCEQ’s position. Moreover, for the TCEQ staff in

the context of a contested case hearing to assert this “revision” of a water rights

permit issued by the Agency pursuant to a final order over which the Agency has

long lost jurisdiction, amounts to the Staff unlawfully collaterally attacking the

validity of its own final order.

TCEQ’s continual assertion that Ware’s priority date is meaningless

contradicts the terms of the Final Order of the Commission, which is set forth in 3.

Special Condition (b) of Permit No. 5499, and has no legal support.

VIII. WARE’S REPLY TO APPELLEE TCEQ’S BRIEF PERTAINING TO

WARE’S POINT OF ERROR NO. 6

Point of Error Six:

The District Court erred in failing to find that the Commission’s April 20, 2010

Order adopted Findings of Fact pertaining to a pending non-party applicant;

Moreover, the details of said Plaintiff’s pending application and proposed

appropriation were unlawfully used as a basis to deny Plaintiff’s water right

application.

In Appellee’s Brief, TCEQ asserts that findings regarding BRA were made

necessary by Applicant’s use of the Brazos River Basin Water Availability

Analysis applied to the BRA application. TCEQ also asserts that the Brazos River

APPELLANT’S REPLY BRIEF PAGE 25

Basin Water Availability Analysis contained in Appellant’s contested case hearing

Exhibit No. 50 is “irrelevant.” TCEQ’s assertion that the Brazos River Basin water

availability analysis related to Application No. 5851 by BRA and detailing the

availability of yet to be appropriated return flows is directly contrary to the first in

time first in right doctrine of prior appropriation, and has no legal support. More

importantly, TCEQ’s reliance on staff testimony in a contested case hearing to

explain away the relevance of water available for appropriation under TWC,

§11.046 only highlights the Commission’s lack of regulatory support for its

implementation of an unauthorized and unwritten water rights permitting and

administration system regarding return flows.

IX. CONCLUSION

As discussed above, the Commission’s April 20, 2010 Order denying

Appellant’s water rights Amendment Application No. 5594 to continue to divert

and use his authorized appropriation of 130 acre-feet of water per year from the

Lampasas River, Brazos River Basin, should be reversed and remanded to the

TCEQ in accordance with Tex. Gov’t Code, §2001.174. The TCEQ’s April 20,

2010 Order violates the Texas Water Code, the Texas Constitution, and the

Constitution of the United States and is voidable and reversible for the following

reasons:

APPELLANT’S REPLY BRIEF PAGE 26

(1) In this case, the TCEQ created an unwritten parallel system of water

rights related, at Commission Staff discretion, only to term permits,

which deprived those permits and the authorizations to appropriate

State water of their legal priority;

(2) The TCEQ, contrary to the plain terms and conditions of Appellant’s

Permit to Appropriate State Water No. 5594, stated that Appellant’s

July 1, 1997 priority date did not apply to this amendment Application

No. 5594A;

(3) The TCEQ Water Availability Analysis of the Brazos River Basin

dated November 28, 2008, details the location and extent of over 100

million gallons per day in return flows available for appropriation

throughout the Brazos River Basin;

(4) In this case, the TCEQ staff and Commissioners have implemented an

unwritten water rights permitting and administration program related

to State Water in the form of return flows;

(5) In their final order in this case, the TCEQ has refused to recognize the

presence of State Water in the form of return flows shown to be

available at Appellant’s diversion point in its Brazos River Basin

Water Availability Analysis Model as available for appropriation

pursuant to Tex. Water Code, §11.046(c); and

APPELLANT’S REPLY BRIEF PAGE 27

(6) The unwritten TCEQ policies and procedures regarding State water in

the form of return flows do not provide for allocation of return flows

on a first in time, first in right basis.

The tacit adoption of these unlawful and statutorily inconsistent policies in the

Findings of Fact and Conclusions of Law in the TCEQ’s April 20, 2010 Order

render the action of the TCEQ voidable as a matter of law pursuant to Tex. Gov’t

Code, §2001.174.

Apart from being unlawful, the Commission’s role in administering water

rights is called into question when it denies a family farmer access to water

available for appropriation in the Brazos River Basin for continued diversion and

use of water for any term at all on the one hand, and yet supports the issuance of

perpetual permits for the use of State water in the form of return flows and based

on updated streamflow conditions and data sets for other, later water rights

applicants on the other hand.

APPELLANT’S REPLY BRIEF PAGE 28

X. PRAYER FOR RELIEF

WHEREFORE, CONSIDERING THE FOREGOING, Plaintiff asks this

Court to:

A. Reverse the Texas Commission on Environmental Quality’s unlawful

April 20, 2010 Order denying the Application of Bradley B. Ware to

Amend his Permit to Appropriate State Water No. 5594;

B. Remand Appellant’s water rights Amendment Application No. 5594A

to the TCEQ for further and lawful consideration of Appellant’s

application based on the evidence of record of State Water available

for appropriation in the Brazos River Basin in the form of return

flows;

C. Require the consideration of Appellant’s water rights Amendment

Application No. 5594A to be consistent with the Texas Water Code

and all applicable law, and not subject to any unwritten, unlawful and

statutorily inconsistent policies for permitting and administration of

State water; and

D. Provide such other and further relief that Appellant may show himself

to be justly entitled.

APPELLANT’S REPLY BRIEF PAGE 29

Respectfully Submitted,

WEBB & WEBB

Attorneys at Law

712 Southwest Towers

211 East i h Street

Austin, Texas 78701

(512) 472-9990 Telephone

(512) 472-3183 Facsimile

~~

g.hill.webb@webbwebblaw.com

State Bar No. 21026300

STEPHENP. WEBB

s.p.webb@webbwebblaw.com

State Bar No. 21033800

ATTORNEY FOR APPELLANT,

BRADLEY B. WARE

CERTIFICATE OF COMPLIANCE

Pursuant to Texas Rule of Appellate Procedure 9.4(i)(3), I hereby certifY that

this reply brief contains 6,767 words (excluding the caption, table of contents, table

of authorities, signature, proof of service, certification, and certificate of

compliance). This is a computer generated document created in Microsoft Word,

using 14-point typeface for all text, except for footnotes which are 12-point

typeface. In making this certificate of compliance, I am relying on the word count

provided by the software used to prepare the document.

ApPELLANT'S REPLY BRIEF PAGE 30

CERTIFICATE OF SERVICE

I hereby certify that I have this 7th day of May, 2015, served copies of the

foregoing instrument upon the parties to this proceeding, who's full and complete

names and addresses appear below, by certified mail, facsimile, hand delivery, or

regular u.s. mail.

Linda Secord, Asst. Attorney General

Office of the Attorney General

P.O. Box 12548-MC015

Austin, Texas 78711-2548

Phone: 512-475-4002

Fax: 512-320-0911

Linda.secord@texasattorneygeneral.gov

~

Gwendolyn II We b

APPENDIX

Exhibit A. Permit to Appropriate State Water No. 5594

Exhibit B. November 25, 2008 Interoffice Memorandum regarding Water

Availability Analysis for BRA's Application No. 5851

Exhibit C. March 20, 20016 Interoffice Memorandum Requiring Mailed and

Published Notice

ApPELLANT'S REPLY BRIEF PAGE 31

i'

TEXAS NATURAL RESOURCE CONSERVATION COMMISSION

PERMITTO APPROPRIATE

AND USE STATE WATER

APPLICATION NO. 5594 PERMIT NO. 5594 TYFE:.Section 11.121

Name: Bradley B. Ware Address: Rte~ 3, Box 211

Killeen, TX 76542

;

Filed: . July 1, 1997 Granted: HOY 0 7 1997

Purposes: Irrigation County: Bell

Watercourse: Lampasas River, tributary Watershed: Brazos River Basin .

of the Little River, tributary

'of the Brazos River

.:'.

--WHBREAS:-Bradlei"i3::WareIas -requestedatithorizatlon- to'divei:iand use- noTio exceed -130

acre-feet of water per annum to irrigate' 100 acres of'land owned by the: applicant in Bell County

approximately

..

15 miles southwest of Killeen,

..

Texas; and

.,

WHEREAS, the Texas Natural Conservation Commission fmds that jurisdiction over the

application is establishe~; and

WHEREAS, no person protested the granting'ofthis application; and

WHEREAS, the Commission has complied with the requirements of the Texas Water Code

and Rules . ofthe

.,' '.

Texas Natural

..'

',,'

Resource

.

Conservation Cominission

. ' ~ . .

in- issiIiIi.g this' permit. .'

' . '

. . .

NOW, THEREFORE, this permit to appropriate and use State Water' IS issued to 'Bradley B.

Ware, subject to the following terms and conditions: '.

. _ ."'._.-

Permittee is authorized to divert and use neit to exceed 130 acre-feet of water per

:. anilUni. from the Lampasas River to irrigate 100 acres of-land out of 261"acres in

the W. Brown Survey, Abstract No. 67, the D.G. Van Vicheton (Vecheton)

1

I-

Survey, Abstract No. 851, and the C. Edwards Survey, Abstract No. 291 in Bell

County, Texas approximately 15 miles southwest of Killeen,' Texas. This land 'is

conveyed. to permittee in a deed recqrded in Volume 1524, page 671 of the Bell .

County Deed Records.'

2. . DIVERSION

a. Diversion Area: Permitte is authorized to divert water from any point

on the left or east· bank' of the Lampasas River, between a point

N60.6°W 2,050 feet from the southeast corner of the aforesaid Van

Vicheton Survey and a point . located S37"E 4,200 feet from the

aforesaid sutvey comer in Bell Courity. This downstream point is

located at Latitude 31.032°N, Longitude 97.~92°W. .

b. Maximum Diversion Rate: 2.67 cfs (1200 gpm).

3. SPECIAL CONDITIONS

a. In order to protect instream uses, biological habitats and water quality,

perinittee is authorized to divert water hereunder ·during. the months of

Apr.il through ·June only when the flow of the Lampasas River at

U.S.G.S .. Gaging Station No. 08103800 near Kempner; Texas equals

- ...- - _........ ',:-on~xceeds38 cfs'!uid 'dlitihgthe"otliei'" fiionths brilY::WhelntequalS' or

exceeds 12 cfs.. _. ... - . ........-

b. The authorization to divert and use 130 acre-feet of water per year shall

expire and become null and void on :November. .7., 2007 unless'

prior to such date permittee applies for an extension hereof and such

application is suhsequently granted for an additional term or' in .

perpetuity, The priority date of this permit apd l!ll ex~ensions hereof

shall be July 1, 1997. .. " .

4, WATER CONSERVATION .. . . ;.:. '-:.

-" ' ':'.

Permitee shall' unplement a .water' conServation' plan that provides fbr the

utiliz~tion of tho;epraciices, tecIriques, ';~d'tecb;;oi;ii;s 'th~tr~d~c~ the

consumption of water, prevent or reduce the: l(jss _or waste of water, maintain or

improve the efficiency.in the use of water, or increase the recycling and reuse

of water so that a water supply is made avaiiablefor future or alternative uses .

. . 'Thls permit is

o •

issueds~bject t~ all sup~rior and senio~ ~~t~; .ri~hts in.the B;azos River Basin,

• • •

2

"

Permittee agrees to be bound by the terms, conditions and provisions contained hereih and such

agreement is a condition precedent to the granting of this permit. .

All other matters requested in the application which are not specifically granted by thi~ permit

are denied.

This pennit is issued subject to the Rules of the Texas Natural Resource Conservation

Commission and to the right of continuing supervision of State water resources exercised by the·

Commission.

TEXAS NATURAL ~OURCE

CONSERVATION COMMISSION

For _.....'"'"

DATE ISSUED: NOV 0 7 1997

ATTEST:

b--)··fd . . .:.

. I\,.~

Eugenia K. Brumm, Ph.D.,ChIef Clerk

. ,

3

App. Exh. _--'S""~,,-.,:__

Texas Commission on Environmental Quality

INTEROFFICE MEMORANDUM

To: Ron Ellis, Application Manager November 25, 2008

Water Rights Permitting Team

ThroUgh:.fS Lann Bookout, Team Leader

6~ Surface Water Availability & Interstate Compacts Team

From: Kathy Alexander, Hydrologist

Surface Water Availability & Interstate Compacts Team

Subject: Brazos River Authority

Application 585 I

CN600506794

Brazos River, Brazos River Basin

WATER AVAILABILITY ANALYSIS

Application Summary

The Brazos River Authority (BRA or the Authority) has applied for a pelmit, designated its "System

Operation Pelmit". The BRA owns the following water rights, which comprise BRA's system of

reservoirs: Certificate No. 12-5155 (Possum Kingdom Lake), Certificate No. 12-5156 (Lake GranbUlY),

Certificate No. 12-5165 (Lake Limestone), Celtificate No. 12-5157 (Lake Whitney), Certificate No. 12-

5160 (Lake Belton), Celtificat~ No. 12-5159 (Lake Proctor), Certificate No. 12-5164 (Lake Somerville),

Celtificate No. 12-5161 (Lake Still house Hollow), Celtificate No.1 2-5163 (Lake Granger), Celtificate

No. 12-5162 (Lake Georgetown) and Celtificate No. 12-5158 (Lake Aquilla). The BRA, along with the

Texas Water Development Board and the City of Houston, owns Water Use Pennit 2925A (Aliens Creek

Reservoir). The BRA also owns Celtificate Nos. 12-5166 and 12-5167, which authorize various uses of

water within the applicant's other certificates and penn its. The applicant is cutTently authorized, pursuant

to a TCEQ order, to manage and operate its tributalY reservoirs as elements of a system, coordinating

releases and diversions from the tributalY reservoirs with releases and diversions from the applicant's

main-stem reservoirs to conserve water.

BRA seeks a Water Use Permit to authorize:

• A new appropriation of state water in the amount of 421 ,449 acre-feet per year for mUltiple use

purposes on a firm basis in the Brazos River Basin. Out of the 421,449 acre-feet per year of

unappropriated water being requested, the maximum amount of unappropriated water that will be

available if such water is divelted upstream at USGS gage No. 08091000 near Glen Rose. Texas

is 150,538 acre-feet per year of firm water, and if such unappropriated water is divelted upstream

at USGS gage No. 08098290 near Highbank, Texas, the maximum amount of unappropriated

water that will be available at that location is 144.306 acre-feet per year offirm water.

• Diversion of the water from: (i) the existing diversion points authorized b) BRA's existing water

rights: (iiJ the Brazos River at the USGS gage No. 08091000 near G len Rose, Texas: (iii) the

Brazos River at USGS gage No. 0809S~90 near Highbank. Texas: (i,,) the Brazos " ~. . .

Bra;os Ri\'(!r Authority

Pel'm{f 5851

Page 2 of 14

Gulf of Mexico; and (v) at such other diversion points that may be identified and included in

BRA's proposed Water Management Plan (WMP), which is subject to TCEQ's approval.

• Use of up to 90,000 acre-feet of water per year of the firm supply to produce, along with other

unappropriated flows, an interruptible water supply of 670,000 acre-feet pel' yeai' and the

appropriation of that interruptible water supply. Out of the 1.001.449 acre-feet of firm and

interruptible water being requested, the maximum amount offirm and interruptible water that will

be available if such water is diverted upstream at USGS Gage No. 08091000 near Glen Rose,

Texas is 60,538 acre-feet of firm water pel' year and 157,000 acre-feet of intelTuptible water pel'

year and if such water is diverted upstream at USGS Gage No. 08098290 neal' Highbank, Texas,

the maximum amount of firm water is 54,306 acre-feet of water per year and 303,000 acre-feet of

interruptible water pel' year.

• An exempt interbasin transfer authorization to use, on a film and interruptible basis, the

appropriated water in the adjoining San Jacinto-Brazos Coastal Basin and the Brazos-Colorado

Coastal Basin.

• An appropriation of cUlTent and future retum flows (treated sewage effluent and brine

bypass/return) to the extent that such retum flows continue to be discharged 01' returned into the

bed and banks of the Brazos River, its tributaries, and BRA's reservoirs. BRA indicates that such

appropriation of return flows would be subject to interruption by direct use 01' indirect use within

I the discharging entity's city limits, extratelTitorial jurisdiction, or contiguous water celtificate of

I convenience and necessity boundary. Specified discharge points and amounts of water will be

accounted for on a monthly basis as part of BRA's WMP, which is subj ect to TCEQ's approval.

• Operational flexibility to (i) use any source of water available to BRA to satisfy the diversion

requirements of senior water rights to the same extent that those water rights would have been

satisfied by passing inflows through the BRA's reservoirs on a priority basis; and (ii) release,

pump and transport water from any ofthe BRA's reservoirs for subsequent storage, diversion and

use throughout the BRA's service area.

• Recognition that the System Operation Permit will prevail over inconsistent provisions in the

BRA's existing water rights regarding system operation.

• Use of the· bed and banks of the Brazos River, its tributaries and BRA's reservoirs for the

conveyance. storage, and subsequent diversion of (i) water appropriated under this application;

(ii) waters that are being conveyed via pipelines and subsequently discharged into the Brazos

River, its tributaries or stored in the BRA's reservoirs; (iii) surface water impOlted from areas

located outside the Brazos River Basin for subsequent use: (iv) in-basin surface water and

groundwater subject to BRA's control;(v) waters developed frol11 future projects; and (vi) current

and future reuse of surface and groundwater based e'ftluent requested by this application. This bed

and banks authorization is subject to BRA. after identifYing specific points of discharge and

diversion and conveyance and other losses, obtaining future authorizations to satisfy the

requirements ofTWC § 11.042. Such points of discharge and diversion and conveyance and other

losses may also be identified and included in BRA's proposed WMP, which is subject to TCEQ's

approval.

(

Bra=as R,ver Authority

Permit 5851

I>uge 3 of 14

Until the construction of Aliens Creek Reservoir is completed, the BRA requests that the System

Operation Pennit include special conditions which authorize:

• Appropriation of state water in the amount of 425,099 acre-feet per year for mUltiple use purposes

on a firm basis in the Brazos River Basin. Out ofthe 425,099 acre-feet per year of unappropriated

water being requested, the maximum amount of unappropriated water that will be available if

such water is diverted upstream at USGS Gage 08091000 near Glen Rose, Texas is 150,538 acre-

reet per year of firm water and if such unappropriated water is diverted upstream at USGS Gage

08098290 near Highbank, Texas the maximum amount of unappropriated water that will be

available is, at that location, 175,306 acre-feet per year finn water.

• Use of up to 90,000 acre-feet of water pel' year of BRA's finn supply to produce, along with other

unappropriated flows, an interruptible water supply of 869,000 acre-feet per year. Out of the

1,204,099 acre-feet of firm and intefl'uptible water being requested, the maximum amount of finn

and interruptible water that will be available if such water is divClted upstream at USGS Gage

No. 08091000 near Glen Rose, Texas, will be 60,538 acre-feet of firm water per year and 190,000

acre-feet of interruptible water per year and if such water is divClted'upstream at USGS Gage No.

08098290 neal' Highbal\k, Texas the maximum amount of finn water will be 85,306 acre-feet of

water pel' year and 284,000 acre-feet of interruptible water pel' year.

• Exempt interbasin transfer authorization to use, on a firm and interruptible basis, the appropriated

water in the adjoining San Jacinto-Brazos Coastal Basin and the Brazos-Colorado Coastal Basin

I and to transfer such water to any county, municipality or the municipality's retail service area that

is partially i'n the Brazos River Basin for use in that part of the county or municipality's retail

service area not within the Brazos River Basin.

Water Availability Analysis

The Commission's Water Availability Model (W AM) for the Brazos River Basin protects existing water

rights based on the prior appropriation doctrine. The period of record for the Brazos WAM is 1940

through 1997. The application was declared administratively complete on October 15, 2004. TCEQ

Resource Protection Staff recommends that the application be subject to special conditions to protect

aquatic habitat and the environment, including the following (For specific numeric values for the flow

requirements below, refer to the Resource Protection Staff memo dated November 25, 2008):

I. Total storage in Permittee's system reservoirs is the trigger for determining hydrologic

condition, which, in tUI'll, determines instream flow requirements.

2. Interim instream flow requirements apply at six USGS gaging stations. The instream

flow requirements are applicable at all times.

3. The level of flow (i.e., Subsistence, Dry, Average, or Wet) is determined seasonally

based on hydrologic condition.

4. Permittee shall meet a seasonal schedule of individual high flow pulses. The

magnitude, duration. timing and frequency and measurement location for the pulses

are included as special conditions in Resource Protection Staffs memo (Additional

discussion of how these high flow pulses were included in the availability analysis is

included in Section C.2 (Unappropl'iated Watel') of this memo).

5. In addition to the above requirements. Permittee is prohibited from divelting and

!

Bra;os River Authority

Peril/II 5851

Page 4 of 14

storing water authorized by this permit unless streamflow meets or exceeds the 7Q2

value at additional gages located below Pennittee's reservoirs as specified in Resource

Protection Staff s memo.

A. Interbasin Transfer and Bed and Banks

Pursuant to TWC § 11.085(v)(3) and (v)(4), the request for an exempt interbasin transfer does not require

a water availability analysis. For the request to use the bed and banks of the Brazos River and its

tributaries, the application indicates that although specific locations, quantities and diversion rates for the

bed and banks request are unknown at this time, potential diversion locations include the perimeter of a\l

existing and proposed BRA reservoirs. The application also indicates that potential diversion locations

include the following stream reaches:

• Brazos River from the confluence of the Salt and Double Mountain Forks to the Gulf of

Mexico,

• Double Mountain Fork of the Brazos River below Lake Alan Henry to its confluence

with the Brazos River,

• Leon River from Lake Proctor to the confluence with the Little River,

• Lampasas River from Lake Stillhouse Hollow to the confluence with the Little River,

• Little River from the junction of Leon and Lampasas Rivers to the confluence with the

Brazos River,

( • Yegua Creek from Lake Somerville to the confluence with the Brazos River,

• Navasota River from Lake Limestone to the confluence with the Brazos River,

• Allens Creek from below Allens Creek Reservoir to confluence with the Brazos River,

• Any other tributary of the Brazos River into which water appropriated under this

application (groundwater or surface water under the control of BRA) is discharged.

With the exception of Pennit 2925 (Aliens Creek Reservoir), BRA's cunent rights authorize use of the

bed and banks of the Brazos River and its tributaries below the Authority's reservoirs to deliver water to

downstl'eam customers. The application indicates that the location of specific amounts, rates, releases and

loss infonnation will be detailed in BRA's Management Plan once the specific amount of unappropl'iated

water and retul11 flows available to BRA is detel·mined. Staff is of the opinion that accounting for the bed

and banks transfer of water through a delivery plan will mitigate any effects on basin water rights. The

accounting/delivel)' plan should be included in BRA's Water Management Plan (WMP).

B. Return Flows

The application requests appropriation of current and future I'eturn flows in the Brazos Basin discharged

from 136 locations by various entities. These dischal'ges includ.e surface and groundwater based retul11

flows. The surface water based retul11 flow includes discharges from BRA facilities, discharges of water

originating from BRA's water rights, as well as discharges from facilities owned by other entities and

originating from non-BRA sources of supply.

A review of water rights in the Brazos River Basin indicates that Permit 4218 (diversion of 172 acre-feet

of water from South Nolan Creek): Permit 5088 (diversion of 37 acre-feet of water from South Nolan

Creek): and Permil 5089 (diversion of 60 acre-feet of waleI' from South Nolan Creek) were explicitly

granted based on the presence of retul11 flows now being claimed as palt of this application. Staff

Bra:o:. River Al/thoriI)'

Parrl/if 5851

Page 5 ofl4

recognizes the possibility that other basin rights were granted based on the presence of the requested

return flows. Because of this, a priority date of October 15,2004 is assigned to the applicant's diversions

of historically discharged return flows. To evaluate the request for reuse of return flows, staff identified

those return flows discharged fi'om BRA facilities, 01' originating from diversions authorized by BRA's

existing water rights, that have not been previously appropriated by other water rights as indicated in

Table I. below. BRA also requested reuse of return flows generated by foul' power plants that receive

contract water from BRA's water rights. These return flows result from once through cooling water, or

other power plant operations, and are thus highly variable. The application did not provide sufficient

information to evaluate this request and these return flows were not included in the analysis.

The Current Conditions data set was updated with the amount of current return flows as indicated in the

application (74,387 acre-feet which is the sum of the maximum repolted annual discharge amounts for

each plant). The request to reuse return flows was modeled at the most downstream point in the basin to

detennine the volume of return flows available to BRA on a basin-wide basis. Results indicate that 100%

and 75% of the return flows were available in 45% and 81 % of the years in the period of record,

respectively and the monthly amount of discharged return flows was available in 87% ofthe months.

Table 1. Return Flows Available to BRA

Current Current

Percent Surface Ground-

TPDES Permitted

Current BRA ofSW Water water

Name Permit Discharge

Source from Returns Returns

Number (mgd)

BRA (ac- (ac-

ftlyr) ftlyr)

Sportsmans World

MUDWTP 02461000 0.01 Possum Kingdom 100% 11.2 0

Double Diamond 02789000 0.06 Possum Kingdom 100% 67 0

Authoritv SWATS . 02889000 2.5 Granbury System 100% 730 0

City of Copperas

Cove 10045003 2.5 .Lake Belton 100% 923 0

City of Copperas

Cove 10045004 2.5 Lake Belton 100% 1.375 0

City of Copperas

Cove 10045005 4.0 Lake Belton 100% 1.600 0

City of DeLeon 10078001 0.3 Lake Proctor 100% 192 0

City of Marlin 10110002 ~.O Whitney System 16% 159.4 0

Cit)' of Harker

Heights 10155001 3.0 Lake Belton 100% 2.780 0

City of Gatesville 10176002 2.2 Lake Belton 100% 1.731 0

City of Gatesville 10176004 1.0 Lake Bellon 100% 703 0

City of Granbury 10178002 2.0 Granhury System 100% 1313 0

Bl'a:oJ, River Allthority

Pel'll/if 5851

Page}6 0 r 14

Current Current

Percent Surface Ground-

TPDES Permitted

Current BRA ofSW Water water

Name Permit Discharge

Source from Returns Returns

Number (mgd)

BRA (ac- (ac-

ftlyr) ft/yr)

Lake Stillhouse

City of Lampasas 10205002 1.5 Hollow 100% 580 0

City of McGregor

(South WWTP) 10219002 ·0.99 Lake Belton 95% 651.7 0

City of Moody 10225001 0.2, Lake Belton 100% 157 0

Authority/LCRA Georgetown/Still

BCRWSS West 10264001 3.0 -house System 100% 2.402 1-657

Authority/LCRA Georgetown/Still

BCRWSS East 10264002 21.5 -house System 100% 16.767 0

City ofTaylor 10299001 4.0 Granger System 100% 2.220 0

Bell County

WCIDIII 10351001 0.9 Lake Belton 100% 983 0

Bell County

WCID#I 10351002 18.0 Lake Belton 100% 14.123 0

Bell County

WCID#I 10351003 6.0 Lake Belton 100% 5,389 0

City of Brenham 10388001 3.55 Lake Somerville 100% 2.485 0

City of Dublin 10405001 0.45 Lake Proctor 100% 325 0

Georgetown/Still

City of Georgetown 10489002 2.5 -house System 100% 1,815 0

Georgetown/Still

City of Georg~town 10489003 2.5 -house System 100% 1,423 0

Georgetown/Still

Gity of Georgetown 10489005 1.5 -house System 100% 1.389 0

City of Hamilton 10492002 0.44 Lake Proctor 100% 392 0

City of Hillsboro 10630001 1.81 Lake Aquilla 100% 1,440 0

Lake Stillhouse

Citv of Rosebud 10731001 0.25 Hollow 100% 194 0

Bell County

WClD#3 10797001 0.675 Lake Belton 100% 360 0

Lake Stillhouse

City of Holland 10897001 0.2 Hollow 100% 93 0

Bell County

WClD#2 11090001 0.094 Lake Belton 100% 63 0

Bell Count)'

WClD#2 11091001 0.08 Lake Belton 100% 70 0

Authority TBRSS 11318001 10.0 Lake Belton 100% 8.523 0

Hra;os River Authority

Perl/II ( 585 J

Paoe 7 of 14

~

Current Current

Percent Surface Ground-

TPDES Permitted

Current BRA ofSW Water water

Name Permit Discharge

Source from Returns Returns

Number (mgd)

BRA (ac- (ac-

ftfvr) ftfyr)

Acton MUD 14211001 0.6 Granburv System 100% 366 0

Acton MUD 14212001 0.49 Granbury S)'stem 100% 268 0

City of Comanche 14445001 0.6 Lake Proctor 100% 324 0

C. Unappropriated Walel'

The request for unappropriated water was incorporated into the TCEQ WAM as follows:

1) The Dual Simulation 1 approach was used. For each existing BRA authorization:

a) Water rights activated only in the initial simulation represent existing diversions and storage

authorized by the BRA's senior rights. These water rights calculate the total depletions and

storage. .

b) Water rights activated during the second simulation calculate the depletion for the senior rights

limited by the streamflow depletion in the preceding step.

c) The final depletions are stored at a viltual control point until the priority date of the System

Operation Pennit application (October IS, 2004), and

d) BRA's reservoirs are refilled using a priority date of October 15, 2004, with the stored final

depletions. Any remaining water is returned to the stream at the control points of the BRA's

existing water rights.

2) TCEQ Resource Protection Staff recommendations for in stream flow protection were incorporated

into the Brazos WAM at the priority date of the application as follows:

a) Seasonal flow requirements were converted to monthly values in acre-feet.

b) The instream flow requirements were subtracted from the seasonal pulse values to determine the

incremental HFP (high flow pulse).

c) The incremental HFP was multiplied by the seasonal pulse frequency to determine the total pulse

va lume for each season.

d) The total pulse volume for each season was distributed by month

e) The monthly pulse volume was added to the monthly instream flow volume for each flow regime

to determine the WAM in stream flow constraint for each month for each flow regime. and

f) 7Q2 flows for the additional control points were convelted to an annual value in acre-feet and

added to the model. .

g) Based on a distribution of the annual diversion amount to a monthly value in '1v'AM and

conversion of that value to a daily diversion in cfs, staff determined that the diversion rate for

BRA's diversions would be below 7,535 cfs at USGS Gage 08114000. Brazos River near

Richmond.

3) After applying the instream flow constraints. the new appropriation of water was then included in the

1 For additional explanation of Dual Simulation. see \\\lrb~. Ralph A. 2(J07 Wafer Rlgh,.\ Anulysl,l Package (Wu"/PJ .\Iode/JIl1/ System {"ler,1

:\falllrai Tl{~256. Texa!> Water Resource$ in.'Hitllle. College Station. Texa~. Pp. lJ4-lJ6

Bra:os River Allthority

Permi! 585/

Pag.e 8 of 14

second simulation (which generated the final results) as follows:

a) All BRA reservoirs are refilled with any unappropriated water at the priority date of this

application.

b) Diversions are made, backed up by system storage in all BRA reservoirs, and

c) All BRA reservoirs are then refilled again to ensure that all water potentially available under the

permit application is impounded.

To determine the amount of water available for appropriation, Staff first evaluated the applicant's request

for finn water, i.e., that amount of water that would be available 100% of the time during the period of

record. The request for finn water was modeled using the TCEQ Full Authorization simulation, which

does not include return flows. Staff evaluated the requests for firm yield water at the three points

requested in the application; from upstream to downstream being Glen Rose, Highbank and the Gulf of

Mexico. The most downstream point for measurement of instream flow requirements is the Richmond

gage. Staff calculated the amount of flow available to BRA at the Gulf of Mexico by determining the

amount of flow available at the Richmond gage and applying a drainage area ratio relationship between

the Richmond gage and the WAM control point representing the basin outlet at the Gulf of Mexico.

The analysis was conducted for two scenarios. The first simulation included Allens Creek Reservoir at its

fully authorized amounts for storage and diversion, and was used to detennine the amount of water

available for appropriation after considering all water rights at their fully authorized amounts. The second

simulation was conducted to deternline if the water appropriated for Allens Creek Reservoir could be

I

used more efficiently by the BRA, in conjunction with other water rights requested by this application,

(

until such time as Allens Creek Reservoir is constructed. The amount of firm water available to BRA is

indicated in Table 2. below. To the extent that removal .of the requirement for wet season pulses at

Richmond resulted in additional unappropriated water, staff recommended the additional amount.

The application requested an amount of additional water that would be available on a reasonably

dependable basis. The application states that this water would be available if 90,000 acre-feet of firm

water was used, along with other sources available to the applicant, to produce the additional supply;

Pursuant to 30T AC §297.42(d), Staff may recommend granting applications that are not based upon the

continuous availability of historic, normal stream flow on a case-by-case basis. A system operation in

conjunction with other water rights is an application that may not be required to be based on the

continuous availability of historic, normal streamflow. The applicant has requested that the additional

amount of water be evaluated using the criteria in 30TAC §297.42(c). that is, 75% of the water is

available 75% of the time when distributed on a monthly basis (75175 criteria). Staff modeled this request

using the Full Authorization simulation and included the applicant's estimated CUITent return flows.

Model results (Table 3.) indicate that additional amounts of water are available to the applicant using the

7517 5 criteria.

T a bl e 2 N ew Aqlpl'oprmtlOn 0 fW ater ('mc Iudes All ens C ree {)

Volume in acre-feet

Location Firm Non-Firm

Glen Rose 131.363 157.000

Highbank 144,306 303.000

Richmond 188.470 670.000

Gulf of Mexico 191.516 670.000

Bra=os RIl'el' Authority

Permit j8jJ

Page 9 of 14

Table 3. New Appropriation of Water (does not include Aliens Creek)

Volume in acre-feet

Location Firm Non-Firm

Glen Rose 131,363 190,000

Highbank 175,306 284,000

Richmond 237,920 869,000

Gulf of Mexico 241,765 869.000

No InjUJ'Y Review

The application requests authorization for operational flexibility to use any sOUrce of water available to

BRA to satisfY the diversion requirements of senior water rights to the same extent that those water rights

would have been satisfied by passing inflows through the BRA's reservoirs on a priority basis. The new

authorization requested in this pennit has a priority date junior to most basin water rights. Although

changes in operations for BRA's existing water rights resulting from additional operational flexibility

have the potential to affect river flows in the Brazos River and its tributaries, Staff is of the opinion that

implementation of accounting measures should mitigate any impacts to senior and superior water rights.

These accounting measures should be part of the accounting/delivery plan, which should be included in

theWMP.

The application requests authorization to release, pump and transport water from any of the BRA's

reservoirs for subsequent storage, diversion and use throughout the BRA's service area. The request to

release, pump and transport stored water should have no effect on other basin rights so long as BRA

obtains the appropriate bed and banks authorizations as needed. In addition, special conditions requiring

BRA to maintain an accounting of water in storage by priority date should mitigate any impacts to

downstream senior and superior water rights.

The application requests that the Commission recognize that the System Operation Permit will prevail

over inconsistent provisions in the BRA's existing water rights regarding system operation. This would

include existing limitations on the percentage of reservoir storage allowed to be used in system operations

and identification of sources of supply. Specifically, the existing system operation order requires the BRA

to exclude tributary reservoirs from operation of the system during any period of time in which BRA's

permitted storage space is less than 30% full. The application states that the Commission's review and

approval of the BRA's Management Plan will provide equivalent safeguards and, at the same time, allow

the BRA greater operational flexibility. Staff agrees that there may be inconsistent provisions and

recommends special conditions to clarify inconsistencies while protecting other basin water rights.

Conclusion

Based on the revie,," and analysis of this application. staff can support granting the application provided

the permit contains the special conditions proposed by Resource Protection staff and additional special

conditions as indicated below.

A. inte"hasin Transfer and Bed and Banks

The water requested for exempt interbasin transfer will be authorized with a priorit) date of October IS.

2004 and as such will be among the most junior rights in the Brazos River Basin. Therefore. there can be

Bra:os River Authol'Il)'

Bm;os Rive,.lJm';II

Page 10 oflS

no effects on existing water rights and staff can recommend granting this request.

Staff can recommend authorization for the use of the bed and banks of streams already authorized in

BRA's cun'ent permits, certificates and amendments, subject to identification of specific losses. Staff

recommends that the permit contain the following special conditions:

1. The lise of the bed and banks of Aliens Creek from below Aliens Creek Reservoi I' to the Brazos

River is not authorized until Pennittee applies for and is granted an amendment to Permit 2925A.

2. Permittee is authorized to use the following reaches, authorized in Permittee's celtificates and

amendments, for conveyance of water, previously appropriated to the Pennittee and water

authorized by this pennit, downstream for diversion at Glen Rose, Highbank and the Gulf of

Mexico and any of the Pennittee's currently authorized diversion points within these reaches:

A. Brazos River from below Possum Kingdom Reservoir to the Gulf of Mexico

B. Leon River from Lake Proctor to the confluence with the Little River

C. Lampasas River from Lake Stillhouse Hollow to the confluence with the Little River

D. Little River from the junction of Leon and Lampasas Rivers to the confluence with the

Brazos River .

E. Yegua Creek from Lake Somerville to the confluence with the Brazos River

F. Navasota River from Lake Limestone to the confluence with the Brazos River

3. Prior to use of the bed and banks identified in Special 'Condition A.2. above, Pennittee must

submit to and have approved by the Executive Director, as part of its accounting/delivery plan, a

procedure to estimate daily deliveries of water. This procedure should be in electronic fonnat and

detail by source, type and priority date, the amounts to be conveyed and delivered, losses

associated with the conveyance, specific points of diversion, associated travel times, and times of

commencement and termination of transit for conveyed waters. Documentation of actual

deliveries as well as the accounting/delivery plan shall be maintained by the Permittee in

electronic fonnat and made available to the general public during normal business hours and to

the Executive Dil'ector upon request. Modifications or changes to the accounting/delivery plan

must be approved by the Executive Director.

4. The use of the bed and banks of additional streams and tributaries in the Brazos River Basin for

conveyance of water appropriated under this permit, or other sources available to the Permittee, is

subject to Permittee, after identifying specific sources and types of water, specific points of

discharge and diversion, and conveyance and other losses. obtaining future authorizations to

satisfy the requirements ofTWC § 11.042.

5. The use of additional points of diversion within the reaches specified in Special Condition A.2.

above is subject to Permittee, obtaining authorization to use those diversion points. The points of

diversion may also be identified and included in Permittee's proposed WMP which is subject to

Commission approval.

B. Reuse of Return Flows

Staff can recommend granting BRA authorization to reuse retul"ll flows discharged from BRA facilities or

originatin" from dive;sions ~nder BRA's water rights. as indicated in Table-I. above. subject to the

folrowing~pecial conditions to protect water rights gran'ted based on the presence or those retu;'11 flows as

Bra:os RiveI' AurhoriT;l'

Bro:os Rh'er Basin

Page 11 oriS

well as other senior water rights:

I. Prior to the diversion of return flows authorized by this permit, Permittee must submit to and

have approved by the Executive Director, a reuse accounting plan. The reuse accounting plan

must be in electronic fonnat and account, by source, for all return flows discharged and

subsequently diverted. The reuse accounting plan should include amounts discharged by outfall.

amounts of return flows used by permits gl'anted based on the presence of these retum flows, and

estimated travel times and conveyance losses from discharge point to diversion point(s). If the

return flows will be stored in Permittee's reservoirs, the reuse accounting plan should include any

evaporative losses associated with the storage. Pennittee shall maintain the approved reuse

accounting plan in electronic fonnat and make it available to the general public during normal

business hours and to the Executive Director upon request. Modifications or changes to the reuse

accounting plan must be approved by the Executive Director. The reuse accounting plan shall be

included as part of Permittee's accounting/delivery plan.

2. The right to divert discharged retum flows from plants owned by the City of Granbury (TPDES

Pennit No. 10178002), Acton MUD (TPDES Pennit Nos. 14211001 and 14212001), Bell County

WCID #2 (TPDES Pelmit No. 1109000 I), City of Georgetown (TPDES Permit Nos. 10489002

and 10489003) and the City of Holland (TPDES Pennit No. 10897001) is limited to the amount

of surface water based return flows discharged from those plants that originates from water rights

owned by the Permittee. Pennittee is not authorized to diveli groundwater based retum flows

\ discharged from these plants, except as may be authorized by Special Condition B.4 .. Pennittee

( must include in the reuse accounting plan the total amount discharged from the plants and the

percentage of that water that is divertable undel' this permit.

3. Permittee is authorized to divert historically discharged groundwater based retulll flows from the

Brazos River Authority/LCRA BCRWSS West (TPDES Permit No. 10264001).

4. FutUl'e discharges of groundwater based retum flows may be diverted if those retum flows

originate from groundwater owned by Pelmittee or are discharged from treatment plants owned

by the Permittee. Prior to diversion, Permittee must apply for and be granted an amendment to

this permit authorizing these diversions and shall submit for approval by the Executive Director, a

revised accounting/delivery plan addressing such new groundwater based discharges ...

5. Pennittee is authorized to diveli only that water discharged by the City of Marlin (TPDES Permit

No. 10 II 0002) originating from water rights owned by the Permittee. Permittee shall calculate

the divertable amount of the City's discharge and include this information in the reuse accounting

plan.

6. Permittee shall only divelt the actual annual amount of return flows discharged from the Bell

County WClD #1 (TPDES Permit Nos. 10351001 and 10351002) and the City of Harker Heights

(TPDES Permit No. 10155001) less up to 172 acre-feet as authorized by Permit 4218.37 acre-

feet as authorized by Pel111it 5088 and 60 acre-feet as authorized by Permit 5089 when the

aforementioned permits are being used.

7. Diversions and storage of retum flows shall not occur at rates or in amounts higher than the actual

daily amount of ret~rn flows discharged into watercourses in the Brazos 'River Basin. after

accounting for the calculated losses and travel time from the discharge point(s) to the diversion

point(s) in accordance with the accounting/delivery plan.

Bra;Q5: Rm:r Aufhorily

Bra:os R,ver Basin

Page 12 of 15

8. Prior to diversion of the water authorized herein, if sufficiently accurate measuring devices are

not available, Permittee shall install and maintain measuring device(s) capable of measuring

within plus 01' minus 5% accUl'acy, at the discharge point of each wastewater treatment plant

(WWTP) to record the amount of return flows discharged into the Brazos River or its tributaries

on a daily basis.

9. The priority date for diversion of up to 116,434 acre-feet (103.899 mgd) of return flows is

October 15,2004.

10. The priority date for diversion of future return flows in excess of 116,434 acre-feet (103.899

mgd) of discharged return flows is October 15, 2004 but is not subject to call by senior and

superior pelmit holders in the basin and is not subject to instream flow limitations.

11. Prior to diversion of any return flows in excess of the individual TPDES Permit limits indicated

in the Table 1. Retul'l1 Flows Available to BRA, Permittee must apply for and be granted the right

to reuse those return flows. Permittee must amend the reuse accounting plan to include future

return flows prior to diverting sa id return flows.

12. The diversion of up to 116,434 acre-feet (103.899 mgd) of water is dependant upon potentially

intenl.lptible return flows 01' discharges and is conditioned on the availability of those discharges.

The right to divert the discharged return flows is subject to revocation if discharges become

permanently unavailable for diversion and may be subject to reduction if the return flows are not

available in quantities and qualities sufficient to satisfy the pennit. Should any of the discharges

become permanently unavailable for divel'sion, Pelmittee shall immediately cease diversion of

those return flows and reflect such reductions in the reuse accounting plan.

13. Pel1l1ittee's diversion and use of return flows is subject to interruption by direct use or indirect

use within the discharging entity's corporate limits, extraterritorial jurisdiction, or contiguous

water certificate of convenience and necessity boundary, provided the discharging entit), has

applied for and been granted authorization to reuse the retul'll flows.

C. Unappropriated Water

Staff can recommend granting reduced amounts of unappropriated water as follows:

Table 4. New Anoro dation of Water

Volume in acre-feet

Location Firm Water Non-Firm 'Vater

Glen Rose 131,363 157,000

Highbank 144306 303.000

Richmond 188.470 670.000

Gulf of Mexico 191.516 670.000

!Jra:o,t Rlvcr Authority

!Jra:o,1 n;1'cr Basill

P(lJ!,1! 13 of I;

Table 5N ew A , I ude A lens Creel<)

.ppropnatton of Water (does not mc

Volume in acre-feet

Location Firm Non-Firm

Olen Rose 131.363 190,000

Highbank 175,306 284,000

Richmond 237,920 869,000

Oulf of Mexico 241.765 869,000

In order to ensure that existing basin rights are protected, the following special conditions should be

included in the pennit:

1. Prior to diversion or storage of the additional water authorized by this pelTIlit, Pennittee shall

provide to and have approved by the Executive Director, a daily accounting/delivery plan that

includes, at minimum, the following:

a. The accounting/delivery plan shall address reservoir storage and withdrawal plans for

each system reservoir and account by priority date and amounts for any inflows,

evaporation, water in storage and diversions from the reservoirs under all o{ Permittee's

priority dates and authorizations including reuse.

b. A method to account for inflows to system reservoirs for .purposes of compliance with

special conditions requiring passage of pulse flows and estimation of those inflows.

c. An accounting of instream flow and pulse requirements to include total system storage,

I gage flows at the measurement points, high flow pulse volume impounded and the release

( schedule for the impounded high flow pulse, and timing, magnitude and duration of pulse

flows.

d. The accounting/delivery plan must detail how measurements will be taken to detennine if

impoundment or diversions under either Permittee's senior orjunior rights can be made.

e. The accounting/delivery plan must identify, accou;lt for, and distinguish between finn

and non-firm water supplied or delivered from Permittee's system of reservoirs. In

addition, the accounting/delivery plan must specify diversion points for this water if those

diversion points are not specifically identified in this pennit. Any additional diversion

points must be within the reaches where use of the bed and banks is authorized. Any

diversion points outside those reaches will require an amendment to this pennit.

f. Permittee shall maintain the approved daily accounting/delivery plan in electronic format

and make it available to the general public during normal business hours and to the

Executive Director upon request. Modifications or changes to the plan must be approved

by the Executive Director.

') If the total amounts of firm water indicated above are divelted at Glen Rose or Highbank. the

additional amount of firm water available below those points is reduced accordingly. Permittee

shall include the amount of that reduction in the accounting/delivery plan.

3. The full additional amount of non-firm water is only available when the amount of firm water is

reduced by 90.000 acre-feet at Glen Rose, Highbank and the Gulf of Mexico. If less than the full

amount of non-firm water is used, the amount of the finn water reduction shall be adjusted

propOltionately.

4. The non-firm water authorized above includes 74.387 acre-feet of historically discharged return

flows. A reduction in firm yield waler is not required in order to divelt these retul1l flows

\' Bl'a:os River Allthorit),

8l'a:os RIver Basin

Page 14 of 15

5. The remaining 42,047 acre-feet of retul11 flows out of the total amount of 116,434 acre-feet of

return flows (Table I.) may be divelted by the Permittee so long as the total diversions under this

permit for all of the authorizations do not exceed the amounts of firm water and non-finn water

indicated in Tables 4. and 5., above unless Permittee applies for and is granted the authorization

to divert additional amounts of water.

6. Permittee may not exercise a priority call on water rights in the Brazos River Basin with priority

dates seniOr to October 15, 2004 for purposes of increasing storage in and/or diversion from

Permittee's system reservoirs where drawdown of Permittee's system reservoirs is caused by

compliance with the terms and conditions of this pelmit.

7. The request for operational flexibility to use any source of water available to Pelmittee to satisfy

the diversion requirements of senior water rights to the same extent that those water rights would

have been satisfied by passing inflows through the Permittee's system reservoirs on a priority

basis is limited as follows:

a. To water previously stored in Pennittee's reservoirs as documented in the

accounting/delivery plan required in Special Condition C.I. above.

b. Use of this option shall not cause Permittee to be out of compliance with Special

Condition C.1. and Special Condition C.6.

I 8. Pelmittee may divelt water from storage in its pel1nitted reservoirs and store that water in

( Pennittee's other reservoirs for use within the Pennittee's service area so long as all diversions

and storage are included in and comply with the provisions of the accounting/delivery plan and

Special Condition C.1. above.

9. The total amount of water divelted and released from Permittee's system reservoirs in any year

for each authorized purpose of use may not exceed the cumulative authorized total for each

purpose until Pennittee applies for and is granted amendments to the underlying authorizations.

10. Pennittee is required to comply with the existing System Operation Order and certificates of

adjudication requiring Pennittee to exclude tribut81Y reservoirs from operation of the system

during any period of time in which Permittee's pel1nitted storage space in that reservoir is less

than 30% full (until all system reservoirs al'e below 30% capacity, at which time the reservoir can

resume system opel'ation), until such time as Permittee submits, and the Commission approves. a

WM P for the Brazos River Basin which details how such limitations will be altered. Any

alterations to the limitations must be in compliance with the accounting provisions required in

Special Condition C.I above.

11. Until such time as the POlts are closed on the dam impounding Allens Creek Reservoir,

authorized by Permit 2925, Permittee may impound and divert additional unappropriated water as

specified in Table 5. subject to Special Conditions C.l. through C.l O. above.

12. Permittee shall prepare and submit to the Commission. a Water Management Plan (WMP) which

shall include such studies and other information as may be required by the Commission to

demonstrate Permittee's compliance with and its ability to comply with all of the Special

Conditions included in this permit.

, .

Bra;os River All/hority

Bra:os Rivet Basil!

Page 15 of 15

13. The initial p)'oceedings to consider the adoption of the WMP, and any major amendment thereof,

shaH be pursuant to contested case procedures. Any proceeding to consider the adoption or major

amendment of the WMP shal1 be preceded by notice and 0ppOltunity to request a hearing, in

accordance with the Commission's regulations applicable to water rights permitting proceedings.

The WMP shaH provide an adaptive management strategy for water supply and thus may be

amended from time to time upon the request of Pennittee or on the Commission's own motion,

The initial accounting/delivery plan shall be submitted as pm1 of the WMP.

TEXAS COMMISSION ON ENVIRONMENTAL OUALITY

INTEROFFICE MEMORANDUM

TO: Office of the Chief Clerk DATE: March 20, 2006

Texas Commission on EnvirOllllental Quality t~ ..~

r; E'

:c w~!

CJ

THRU: Kellye Rila \LJl-- E8

0 ...

:;~

:J'"'"

,T

~~~~Q}

Team Leader 0

:;;0

i

"0

CJ (':;0[;-,',;

FROM: Kathy C. Hopkins, Project Manager =If;'~i~~i>

~

Water Rights Permitting Team 0

~. ~r

,',

." :; I

-n ."'

,-

SUBJECT: Bradley B. Ware 0rn 1..;JJ

CN60l474224,RN1028424l6

Application No. 5594A to Amend Water Use Pennit No. 5594

TWC § 11.122, Requiring Mailed and Published Notice

Lampasas River, Brazos River Basin

Bell County

The application was received on November 17, 2005. Additional infonnation and fees were,

received on February 8, 2006. The application was declared administratively complete and

accepted for filing on March 20, 2006. Notice is being published and mailed pursuant to TAC

§295.l58 to the water rights holders of record in the Brazos River Basin.

Bradley B. Ware has applied fo,' an amendment to its existing Water Use Permit on the

Lampasas River, Brazos River Basin, in Bell County to extend or delete the expiration date of

November 7,2007, add an additional 31 acres for in'igation, and to divert and use an additional

.W'"

20 acre-feet of water .

,,,';,,tio., ;, _""", fm fill ,g.

Kathy C. Ho~ins '

Water Rights Permitting Team