Opinion

Precision Standard, Inc v. United States

Court
United States Court of Federal Claims
Filed
Jun 9, 2016
Status
Unpublished
Cited by
0 cases
Authority
More cited than 43.6%

“[T]the party opposing the motion for summary judgment . . . must point to an evidentiary conflict created on the record, at least by a counter-statement of a fact set forth in detail in an affidavit by a knowledgeable affiant.”

How later courts described this case

  • “[T]the party opposing the motion for summary judgment . . . must point to an evidentiary conflict created on the record, at least by a counter-statement of a fact set forth in detail in an affidavit by a knowledgeable affiant.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 11-558C

(Filed: June 9, 2016)

**********************************

PRECISION STANDARD, INC.,

Contract Disputes Act, 41

U.S.C. § 609(a) (2012);

Plaintiff,

Defense Priorities and

Allocations Systems;

v.

waiver of delivery dates;

e q u i t abl e adj ust m ent ;

conditional approval

THE UNITED STATES,

Defendant.

*********************************

_____________

OPINION

_______________

BRUGGINK, Judge.

Plaintiff, Precision Standard, Inc. (“PSI”), brings this case pursuant to

the Contract Disputes Act, 41 U.S.C. § 609(a) (2012) and the Tucker Act, 28

U.S.C. § 1491(a) (2012) against the United States seeking equitable adjustment

and damages arising under various contracts between it and the Defense

Logistics Agency (“DLA” or “the Agency”), formerly known as the Defense

Supply Center Richmond (“DSCR”). Pending is defendant’s motion for partial

summary judgment on Counts 2 through 9 of the complaint.1 The motion is

fully briefed, and oral argument was held on April 6, 2016. For the reasons

stated below, we grant in part and deny in part defendant’s motion for

summary judgment.

1

The complaint contains nine counts. Count 1, however, is not included in this

motion.

BACKGROUND2

There are 28 contracts at issue in Counts 2 through 9 of the complaint.

These contracts, each of which was for a particular aircraft part, were entered

into between April 2006 and January 2009. The majority of the contracts

required first article testing to be performed at Warner Robins Air Force Base

(“Warner Robins”). The remainder required first article testing at Hill Air

Force Base (“Hill”). They are listed as follows:

Count Contract No. Contract Date Part

2 SPM4A7-07- March 23, 2007 Upper Thrust

0105 Reverser Fan

Cowlers

3 SP0407-06-M- April 18, 2006 Structural

9684 Aircraft Panels

4 SPM4A7-08-M- March 31, 2008 Access Covers

5689

5 SP0407-05-C- March 28, 2005 Trailing Edge

2028 Panels

6 SPM4A7-09-D- July 2009 Bundle Covers

5547

7 SPM4A7-08-D- July 30, 2008 Coupling

0316 Adapter Sleeves

8(A) SPM4A7-07-D- March 6, 2007 Lower Left

3180 Panel Aircraft

Assemblies

8(B) SPM4A5-08-M- February 22, Access Covers

2072 2008

8(C) SPM4A7-07-M- April 12, 2007 Fairing

6269 Assemblies

2

The facts are drawn from the appendices filed with the parties’ briefing.

2

8(D) SPM4A7-08-C- June 6, 2008 Aircraft Fairings

0387

8(E) SPM4A7-08-D- June 23, 2008 Fuselage Fairing

0274 Panels

8(F) SPM4A7-07-M- August 6, 2007 Aircraft Fairings

A678

8(G) SPM4A7-07-M- September 14, Aileron Trailing

C357 2007 Edge

Assemblies

8(H) SPM4A7-08-C- August 16, 2008 Aircraft Access

0481 Doors

9(A) SPM4A7-08-M- November 29, Trailing Edge

2238 2007 Wing

Assemblies

9(B) SPM4A7-08-M- January 17, Insulation

4809 2008 Panels

9(C) SPM4A7-08-M- February 25, Lower Bunk

6942 2008 Panels

9(D) SPM4A7-08-M- March 14, 2008 Aircraft Floor

7318 Panels

9(E) SPM4A7-08-M- April 1, 2008 Aircraft Fairings

8566

9(F) SPM4A7-08-M- May 16, 2008 Wheel Panel

A725 Assemblies

9(G) SPM4A7-08-M- May 31, 2008 Aircraft

A912 Retainer

Assemblies

9(H) SPM4A7-08-M- June 10, 2008 Aircraft Floor

B771 Panels

9(I) SPM4A7-08-M- July 23, 2008 Aircraft Panel

D715 Assembly

3

9(J) SPM4A7-08-M- August 25, 2008 Helicopter

F252 Access Covers

9(K) SPM4A7-09-M- January 30, Aircraft Access

3933 2009 Doors

9(L) SPM4A7-07-M- October 26, Cowlings

0637 2006

9(M) SPM4A7-08-M- March 5, 2008 Panel

7193 Assemblies

9(N) SPM4A7-08-M- March 21, 2008 Bulkhead Clips

7646

The parties set forth arguments which pertain to every contract,

arguments which pertain to a specific group of contracts, and arguments that

pertain to individual contracts. Before discussing these arguments, we will

detail the facts that led to the dispute for each contract individually.

Count 2

DLA awarded contract number SPM4A7-07-0105 to PSI on March 23,

2007. The contract was for 33 upper thrust reverser fan cowling covers for a

total price of $154, 300. The first article was due for testing 120 days later, on

July 21, 2007. Defendant claims that the Agency received the first article in

September 2007. After receiving and testing the first article, DLA rejected it

on January 11, 2008. In its correspondence with PSI, the Agency stated that the

first article did not conform to the procurement specifications and pointed out

nine specific defects. The letter also stated that PSI had the opportunity to

correct the nonconformance and resubmit two first articles for testing, at a cost

to PSI of $5,880.20. PSI challenged the rejection on February 14, 2008, and

requested conditional approval. In its May 7, 2008 response, DLA denied the

request for conditional approval and informed PSI the first article was not

manufactured in accordance with the drawings.

PSI submitted a second first article to Warner Robins for testing in

September 2008. Contracting Officer (“CO”) Carl Hudson sent PSI a letter on

April 15, 2009 informing PSI that the second first article failed inspection. The

letter identified 10 different defects, and offered PSI the option of submitting

another first article for testing or cancelling the contract. According to the

4

letter, the third re-test would cost PSI $6,062.47. In August 2009, DLA

returned the second first article to PSI. In November 2009, DLA send PSI an

email requesting that PSI inform the Agency whether it would submit another

first article and requesting a revised delivery schedule or cancellation request

by December 3, 2009. PSI did not respond to this email.

On January 4, 2010, the contracting officer issued a unilateral

modification P00002 cancelling the contract “at no cost or obligation to either

party.” Def.’s App. 19A. On April 30, 2010, PSI responded with an inventory

schedule and advised DLA that it would be submitting is termination

settlement proposal. Id. at 19C. DLA responded on May 4, 2010 with a show

cause notice, which stated that modification P00002 should not have been

issued as a unilateral no-cost modification and was therefore rescinded.

However, the letter informed PSI that it was delinquent on the contract and

that DLA was considering cancelling for default.

PSI responded to the show cause notice on May 11, 2010, asserting that

the Agency illegally imposed a requirement that the parts conform exactly to

the product-part specifications and arguing that the government had no valid

basis for a termination for default. It also stated that, on June 1, 2007, PSI had

written the government asking for assistance and cooperation in checking

PSI’s drill bit template, but that the government never responded.

PSI sent a supplemental letter on June 30, 2010, asserting that the part

it sent as its second first article was actually the same part as the initial first

article, with the identified defects corrected, yet Warner Robins had found

completely new defects in the second first article. The letter went on to state

that the fact that Warner Robins is a manufacturing competitor of PSI created

a conflict of interest that should disqualify Warner Robins as a first article

tester.

On August 17, 2010, the contracting officer issued a termination for

default for “failure to comply with the essential requirements of the contract.”

Id. at 26. Notice of the termination was sent to PSI on September 3, 2010.

Count 3

DLA awarded contract number SP0407-06-M-9684 for the manufacture

of 10 structural aircraft panels to PSI on April 18, 2006. The contract required

that PSI send its first article to Hill within 90 days (by July 17, 2006). The

5

parties disagree about when the first article was shipped to Hill–PSI claims

May 2008, while the Agency claims June 2008. In any event, it was after the

90 day period required by the contract.

On October 7, 2008, Hill reported to the agency that the first article

failed testing, identifying 9 discrepancies. PSI was informed by letter on

October 21, 2008. DLA offered PSI the opportunity to resubmit a first article

and requested that PSI submit a revised delivery schedule by November 4,

2008. PSI responded, contesting the rejection of the first article, requesting its

return, and requesting conditional approval. The parties disagree as to whether

the first article was returned to PSI. The parties executed a bilateral contract

modification on March 31, 2010, setting the deadline for first article

resubmission as May 7, 2010.

As of November 2010, PSI had not delivered a second first article. The

contracting officer sent PSI a show cause notice requesting a response by

November 18, 2010. PSI responded, through counsel, on November 26, 2010.

In the response letter, PSI claimed that the Agency was precluded from

terminating the contract for default because it had not returned the initial first

article to PSI and because it never gave PSI a decision on its request for

conditional approval. PSI indicated to the Agency that it believed DLA used

the first article but refused to pay for it. PSI also made a claim for equitable

adjustment for its rejected first article, consisting of $3,000 for the unreturned

first article, $254.32 for time spend researching and analyzing the show cause

notice, $806.89 in delay costs, and proposal preparation fees of $800. PSI

informed DLA that it would work with the Government to establish a new

discovery schedule after the Government returned the first article and ruled on

the request for conditional approval.

In response to PSI’s request for equitable adjustment, DLA issued a

termination for default on December 6, 2010. DLA stated that it would pay

$3,000 for the unreturned first article, but it denied the other components of

PSI’s request for equitable adjustment.

Count 4

Contract number SPM4A7-08-M-5689 was awarded to PSI on March

31, 2008, for the production of 38 access covers for $44,800. It required a first

article to be delivered at Hill within 180 days (by November 3, 2008). DLA

inquired about the status of the first article on January 22, 2009. PSI responded

6

that the delinquency was due to DX-rated contracts.3 PSI shipped the first

article in May 2009.

On November 23, 2009, DLA sent a letter disapproving of the first

article. Attached to the letter was a list of 14 discrepancies. The letter went on

to state that a no-cost termination for convenience would be issued and that

“[n]o further submission is requested or authorized.” Def.’s App. 99. On

December 2, 2009, DLA sent PSI a proposed bilateral modification to

terminate the contract at no cost to either party. PSI refused to agree to the

modification. DLA then informed PSI that the contract would be terminated

for default.

PSI responded on November 19, 2010 with a claim for equitable

adjustment in the amount of $16,144.62. Contracting Officer Sally Gorby sent

DLA a response letter on December 14, 2010, stating that PSI’s request for

equitable adjustment was based on the mistaken belief that the contract had

been terminated for convenience. It further asked PSI to show cause why the

contract should not be terminated for default. In the alternative, the letter

offered a no cost termination in lieu of termination for default. PSI responded

through counsel on December 23, 2010, asserting that the government had

constructively terminated the contract. PSI therefore purported to convert its

request for equitable adjustment into a claim for equitable adjustment pursuant

to the termination clause of the contract. PSI further requested a termination

for convenience. DLA thereafter issued a termination for default.

Count 5

Contract number SP0407-05-C-2028 was awarded on March 28, 2005.

The first article was due by July 26, 2005. DLA received the first article on

June 22, 2006. It was rejected on February 27, 2007. PSI subsequently

submitted a second first article on July 20, 2007, and DLA conditionally

approved it on December 18, 2007. PSI was notified of the conditional

approval on January 10, 2008. Thus, pursuant to the contract, the parts were

3

Under the Defense Priorities and Allocations Systems (“DPAS”), which is

used to prioritize performance, defense contracts are identified by rating the

symbols “DO” and “DX.” Contractors are required to prioritize DX-rated

orders over DO-rated orders and unrated orders.

7

due 293 days later, by October 30, 2008. PSI did not deliver any parts by this

date.

By email dated November 25, 2008, Milan Reeder, Vice President of

PSI, advised DLA that PSI would be shipping a minimum of five or more units

the following week. He also indicated that PSI “ha[d] DX rated contracts

which took priority.” Def.’s App. 162. A modification was then issued by DLA

to ship the first five parts by December 5, 2008 and the remaining 50 by the

end of December in exchange for $350 consideration. PSI objected to this

modification by letter on December 6, 2008, asserting that delivery of 50

panels by the end of December was “arbitrary, unrealistic, and nonfeasible.”

Pl.’s App. 493. The letter also accused DLA of causing delays of

approximately 17 months, and requested modification to reflect the

government delays. PSI shipped the first five panels that month, but did not

submit the remainder.

On January 22, 2009, DLA sent PSI an email informing it that the

contract had become delinquent and requesting a status update. DLA again

contacted PSI on March 23, 2010m offering a no-cost termination for

convenience. PSI responded, refusing the termination for convenience, stating

that it had to interrupt production due to DX-rated contracts and that it

expected to resume production within six weeks. DLA wrote back, stating that

it would issue a modification changing the delivery date to May 14, 2010. PSI

responded by email on April 2, 2010, advising that it expected to complete

delivery of the remaining parts by July 30, 2010.

DLA sent a show cause notice on November 14, 2010. PSI responded

by requesting equitable adjustment in the amount of $6,252.64 for the

government’s delay of its testing decision for both first articles and delay in

returning the first article to PSI upon PSI’s request.

On December 2, 2010, DLA issued a contract modification requiring

the remaining units to be delivered by January 31, 2011. It subsequently denied

PSI’s request for equitable adjustment on December 8, 2010. PSI responded

with a letter expressing concern over DLA’s and the contracting officer’s

course of conduct. It subsequently shipped the remaining parts between

December 2010 and March 2011.

8

Count 6

DLA awarded contract number SPM4A7-09-D-5547 to PSI in July

2009 for an indefinite quantity purchase order for bundle covers. On July 24,

2009, DLA issued Delivery Order 0001 for 24 covers to be delivered by

November 30, 2009. On October 3, 2009, DLA issued Delivery Order 0002 for

29 covers for delivery by February 5, 2010. On January 29, 2010, DLA issued

Delivery Order 0003 for 48 covers to be delivered by June 30, 2010. PSI

delivered a portion of the covers for Delivery Order 0001 on June 12, 2010,

and the remainder on July 11, 2010. On July 14, 2010, PSI delivered the covers

for Delivery Order 0002.

DLA issued a show cause notice on January 25, 2011, regarding PSI’s

failure to deliver under Delivery Order 0003. PSI responded that it had never

received Delivery Order 0003, but that it was prepared to complete all orders

under the contract, including Delivery Order 0003, within the five year period

of the contract with the date of Delivery Order 0003 running from the date of

the letter announcing its existence. On February 10, 2011, the contracting

officer issued a termination for default as to Delivery Order 0003.

Count 7

Count 7 concerns contract number SPM4A7-08-D-0316. This indefinite

delivery, indefinite quantity contract for coupling adapter sleeves was awarded

to PSI on July 30, 2008. It provided that delivery of orders was due 111 days

after receipt of each order. DLA issued the following delivery orders:

1. Delivery Order 0001: 111 units due November 18, 2008

2. Delivery Order 0002: 74 units due February 22, 2010

3. Delivery Order 0003: 81 units due April 27, 2010

4. Delivery Order 0004: 80 units due June 28, 2010

5. Delivery Order 0005: 79 units due July 28, 2010

6. Delivery Order 0006: 283 units due January 5, 2011

On February 12, 2010, PSI delivered two of the units owed under Delivery

Order 0002. Between June 2010 and August 2010, it delivered all but 14 of the

units owed under Delivery Order 0001.

On November 16, 2010, DLA sent PSI a letter notifying PSI that all of

the orders except Delivery Order 006 were delinquent and informing PSI that

9

it was considering terminating for default. The letter also provided that PSI

would need to provide monetary consideration before the agency would accept

any more shipments. It requested a response by November 19, 2010. PSI

responded, claiming that the agency had overwhelmed it with orders. It also

stated that it had 97 parts ready to ship but would stop delivery because it

viewed DLA’s demand for consideration as a stop work order.

PSI subsequently shipped the 97 parts. It then submitted a claim for

equitable adjustment on November 26, 2010, demanding $23,012. PSI also

objected to DLA’s assertion that PSI had repudiated the contract, and

countered that there was no longer a delivery schedule in place. On December

8, 2010, DLA sent a letter denying PSI’s request for equitable adjustment. In

this letter, DLA also stated that it had not waived delivery or the delivery

schedule and that it expected PSI to deliver Delivery Order 0006 by the

January 5, 2011 due date. The letter further invited PSI to provide reasonable

revised delivery dates for Delivery Orders 0003, 0004 and 0005. Otherwise,

the letter provided, the agency would terminate for default. PSI did not

respond. The agency thereafter terminated the contract for default on February

4, 2011.

Count 8

Count 8 pertains to eight contracts which are further divided into

Counts 8(A) through 8(H). The specific facts of each contract are detailed

below. As of February 22, 2011, PSI had not shipped the required parts for any

of the eight contracts. DLA therefore wrote PSI offering a no cost, no liability

termination for all of the contracts and providing that it would terminate them

for default if PSI did not respond by March 15, 2011. PSI sent a letter to DLA

on February 28, 2011, challenging the authority of the contracting officer to

“continually issue demands and threats with arbitrarily and capriciously set

response-date demands.” Def.’s App. 357.

PSI responded to DLA’s letter again, through counsel, on April 7, 2011.

It contended that the government had waived its right to terminate for default,

and that the only action that DLA could take was to issue formal terminations

for convenience. The letter also noted that the government had, in the past,

typically allowed PSI to prioritize its DX-rated contracts over DLA’s DO-rated

contracts and that the government never set new dates for these contracts

because it no longer had a need for the products. Thereafter, DLA terminated

the contracts for default.

10

Count 8(A)

Count 8(A) pertains to contract number SPM4A7-07-D-3180. This

indefinite delivery, indefinite quantity contract for lower left panel aircraft

assemblies was awarded to PSI on March 6, 2007. The first article was due at

Warner Robins 250 days after award on November 5, 2007. On March 20,

2007, DLA issued Delivery Order 001 for six panels. On March 21, 2007,

DLA issued Delivery Order 0002 for another six panels. Both orders were

placed before DLA received the first article for testing.

On February 5, 2008, in response to a request for clarification, DLA’s

contract administrator sent an email to PSI, informing it that the first article

should be shipped against Delivery Order 0001. If approved, the first article

requirement for Delivery Order 0002 would be deemed satisfied. The email

also provided that delivery would be due 242 days after first article approval.

PSI responded, informing DLA that it would have the first article

complete by March 7, 2008. It followed up via email on March 6, 2008,

informing PSI that the first article would be ready by March 21, 2008 or

earlier. On March 14, 2008, DLA issued modifications to Delivery Orders

0001 and 0002 to revise first article shipment to March 31, 2008. However,

PSI did not ship the first article by March 31, 2008. DLA inquired into the

status of the first article on February 26, 2009. PSI did not respond.

On June 1, 2009, DLA issued Delivery Order 0003 for another six

panels. It again inquired into the status of the first article on November 30,

2009. PSI advised the agency that it was planning on submitting its first article

by December 18, 2009. As of March 29, 2010, PSI still had not delivered the

first article. In communications with DLA through the Defense Contract

Management Agency (“DCMA”), PSI indicated that it would ship the first

article by the middle of April 2010. Nevertheless, the first article was never

shipped, and on April 27, 2011, DLA terminated the contract for default.

Count 8(B)

Contract number SPM4A5-08-M-2072 for 162 aircraft access covers

was awarded on February 22, 2008. The first article was due at Hill 240 days

after award. On May 15, 2008, PSI shipped the first article, and on September

26, 2008, the agency informed PSI that the first article had failed testing. The

11

rejection letter invited PSI to submit another first article, submit a rebuttal

letter, or request cancellation of the contract. The letter requested a response

within 15 days, and warned that the contracts might be cancelled or terminated

if PSI did not respond.

PSI did not respond. On May 4, 2009, DLA again contacted PSI

requesting a status update within 15 days. DLA contacted PSI again on May

21, 2009, informing PSI that the contracts might be cancelled if a response was

not received by May 22, 2009.

As of February 22, 2011, PSI still had not submitted another first

article, and DLA issued a show cause notice. The only response was the April

7, 2011 letter, mentioned above, which expressed discontentment with DLA’s

course of action regarding the contracts in general but did not provide

responses as to each specific contract. DLA terminated the contract for default

on April 29, 2011.

Count 8(C)

Contract number SPM4A7-07-M-6269 for 34 fairing assemblies was

awarded on April 12, 2007. The contract required the first article in 90 days,

but it also provided that a first article which PSI had previously submitted for

a contract not at issue in this case would suffice if it was approved. On

February 14, 2008, and again on October 10, 2009, however, PSI’s first article

submissions were rejected.

On March 30, 2010, DLA sent PSI an email offering a no cost

termination and requesting a response by April 1, 2010. On May 5, 2010, DLA

sent an email attaching a proposed modification to the contract to terminate it

at no cost. PSI refused to agree to the no-cost termination.

As of February 22, 2011, PSI still had not submitted another first

article, and a show cause notice was issued. PSI responded only via the April

7, 2011 letter. DLA terminated the contract for default on April 29, 2011.

Count 8(D)

Contract number SPM4A7-08-C-0387 for 30 aircraft fairings was

awarded on June 6, 2008. The first article was due on December 13, 2008. On

April 21, 2010, a representative of DCMA sent a message to DLA, indicating

12

that PSI had made no progress toward the completion of the order. On June 8,

2010, DLA contacted PSI warning that no progress was being made and

therefore the contract would be cancelled at no cost to the government.

PSI responded on June 10, 2010, stating that progress had been made

and that it did not assent to a termination for convenience. DLA emailed back

that day, asking “where do we stand on this contract?” Def.’s App. 434. PSI

did not respond.

As of February 22, 2011, PSI still had not submitted a first article, and

DLA issued a show cause notice. PSI only responded via the April 7, 2011

letter. DLA terminated the contract for default on May 6, 2011.

Count 8(E)

On June 23, 2008, DLA awarded PSI contract number SPM4A7-08-D-

0274, an indefinite delivery, indefinite quantity contract for wing to fuselage

fairing panels. The first article was due by November 5, 2008. DLA issued the

following delivery orders: Delivery Order 0001 on September 19, 2008 for 15

panels, and Delivery Order 0002 on December 5, 2008 for 17 panels.

On March 13, 2009, PSI told the agency that it had not yet shipped a

first article or begun production. DLA then issued a modification to Delivery

Order 0001, adding a requirement of a first article to be delivered by July 6,

2009. As of February 3, 2010, PSI still had not delivered the first article. DLA

informed PSI that the item was over-procured and offered a partial

cancellation, to which PSI agreed. Thus, DLA issued a modification to

Delivery Order 0002 decreasing it to 6 panels.

As of February 22, 2011, PSI still had not submitted a first article, and

DLA issued a show cause notice. PSI responded only via the April 7, 2011

letter. DLA terminated the contract for default on May 10, 2011.

Count 8(F)

DLA awarded contract number SPM4A7-07-M-A678 for 19 aircraft

fairings to PSI on August 6, 2007. The first article was due February 2, 2008.

On March 3, 2008, PSI requested a mylar that it needed for the part from DLA.

It requested the mylar again on June 17, 2009. A 2010 letter from PSI to DLA

indicated that the mylar was provided to PSI on July 2, 2010.

13

On August 8, 2010, DLA issued a modification revising the delivery

date to January 30, 2011. As of February 22, 2011, PSI still had not submitted

a first article, and thus a show cause notice was issued. PSI responded only via

the April 7, 2011 letter. DLA terminated the contract for default on April 29,

2011.

Count 8(G)

This contract, number SPM4A7-07-M-C357, for 50 aileron trailing

edge assemblies was awarded to PSI on September 14, 2007. The first article

was due in 180 days, by March 12, 2008. DLA contacted PSI on June 11,

2009, to report that the government had a critical need for the parts and to ask

if the first article had shipped. PSI responded on June 16, 2009, advising that

the first article was complete and ready for spot welding, and would ship by

August 19, 2009.

The first article did not ship by August 19, 2009. On July 12, 2010, PSI

informed DLA that the reason for the delay was spot welding issues and that

the first article was expected to ship by July 31, 2010. The first article was not

shipped by this date. In February 2011, PSI indicated that it would ship the

first article by the end of March 2011.

As of February 22, 2011, PSI still had not submitted a first article, and

a show cause notice was issued. PSI responded only via the April 7, 2011

letter. DLA terminated the contract for default on April 29, 2011.

Count 8(H)

On August 16, 2008, this contract, number SPM4A7-08-C-048, for 38

aircraft access doors was awarded to PSI. The first article was due by February

12, 2009. As of July 1, 2009, PSI had not shipped the first article, and DLA

requested a status update. In response, PSI indicated that it expected to ship

the first article by September 15, 2009.

As of June 3, 2010, PSI had still not shipped the part, and DLA

requested a status update. PSI responded that it intended to ship the part. On

October 7, 2010, DLA contacted PSI to request a reduction of the quantity by

four. PSI did not respond, and DLA contacted PSI again on November 8, 2010

to request a response.

14

On December 15, 2010, DLA was notified by DCMA that PSI had not

yet begun production because it was awaiting approval from DLA on a similar

part. On January 21, 2011, DLA contacted PSI again asking for the status of

the part. On January 31, 2011, DLA repeated its request for a status update

and its request to reduce the total contract amount by four parts. DLA renewed

this request for the last time on February 7, 2011.

As of February 22, 2011, PSI still had not submitted a first article, and

DLA issued a show cause notice. PSI responded via the April 7, 2011 letter.

DLA terminated the contract for default on May 6, 2011.

Count 9

Count 9 pertains to 14 additional contracts, which are divided into

Count 9(A) through 9(N). Defendant has made a prima facie case that it is

entitled to summary judgment as to Counts 9(A) through 9(N) because PSI

either failed to deliver the products or failed to submit second first articles

after its initial submissions were rejected. As discussed more fully below,

plaintiff has failed to set forth any meaningful response to defendant’s motion

as to Counts 9(A) through 9(K). Therefore, for the purpose of brevity, we will

only provide the facts for Counts 9(L) through 9(M).

Count 9(L)

Contract number SPM4A7-07-M-0637 for 12 cowlings was awarded

on October 25, 2006. The first article was due in 120 days, by February 22,

2007. On February 9, 2007, PSI submitted a request for copies of three

drawings that it needed to complete the part. DLA responded, recommending

that PSI contact Lockheed Martin for the drawings. PSI again requested the

drawings on April 25, 2007, and they were provided to PSI by DLA on May

30, 2007.

On July 26, 2007, the contracting officer issued a modification,

changing the deadline for first article submission to September 15, 2007. This

modification also changed the product delivery date to May 13, 2008. On

October 22, 2007, PSI shipped the first article.

The first article was rejected on May 20, 2008 because it failed a form,

fit, and function test and because the spot welds did not conform to the

drawings. PSI was given the opportunity to submit another first article, with

15

PSI to bear the costs. PSI subsequently requested that DLA return the rejected

first article and asked that DLA send a full copy of the test report. In

November 2008, PSI submitted five samples to an independent company to

test the spot welds. The testing company determined that all five samples had

spot weld failures.

On January 6, 2009, PSI reported to DLA that it would ship a new first

article by the end of the month. On January 30, 2009, DLA contacted PSI to

inform it that the contract was delinquent and demanded monetary

consideration and an explanation for the delay. PSI responded that the first

article had not shipped because it was still waiting for the rejected first article

to be returned.

On February 11, 2009, PSI received the initial first article back from

DLA. On March 16, 2009, PSI stated that it would submit a new first article

by April 15, 2009. As of May 29, 2009, PSI had yet to ship the second first

article, and DLA contacted PSI to request an updated delivery date.

On June 10, 2009, PSI shipped the second first article. On December

17, 2009, PSI was notified that its second first article was rejected, again due

to spot weld failures and improper fit.

DLA issued a show cause notice for this contract and two others on July

8, 2011, offering PSI a no-cost termination or the opportunity to provide

another first article for testing. PSI responded that the government’s charges

of delinquency were themselves untimely and argued that there was no

effective schedule in place.

DLA terminated the contract for default on September 1, 2011. Four

months later, PSI submitted a claim for equitable adjustment seeking

$84,421.55 attributable to government-caused delay. This claim was rejected

on February 13, 2012.

Counts 9(M) and 9(N)

Count 9(M) pertains to contract number SPM4A7-08-M-7193 for 20

panel assemblies awarded to PSI on March 5, 2008. The first article was due

by August 22, 2008. PSI submitted a first article, which was rejected by

Warner Robins on April 30, 2010. The memorandum explaining the rejection

provided that the panel had the wrong contour and several disbonds were

16

found along the edge of the panel. On May 24, 2010, DLA informed PSI of the

rejection, and invited PSI to submit a new first article. PSI did not respond to

this letter and did not submit a new first article.

Count 9(N) pertains to contract number SPM4A7-08-M-7646 for 300

bulkhead clips which was awarded to PSI on March 21, 2008. The first article

was due on October 22, 2008. PSI submitted a first article, which was rejected

by Hill on January 20, 2009 due to dimensional discrepancies and an improper

bend. On February 4, 2009, DLA informed PSI that it could submit a new first

article or request a no-cost cancellation. PSI did not respond. DLA contacted

PSI two more times requesting a response. On April 2, 2010, PSI responded,

providing that it would submit its first article within 30 days. However, PSI

never submitted a new first article.

Both contracts were included in the July 8, 2011 show cause notice

mentioned above, to which PSI responded by claiming that the government’s

charges of delinquency were themselves untimely, and that there was no

effective schedule in place. The contracts were terminated for default on

September 1, 2011.

DISCUSSION

The government argues that it is entitled to summary judgment with

respect to Counts 6, 7, 8(A), 8(C) through 8(H), and 9(A) through 9(K)

because PSI failed to deliver the required products. Each of the 19 contracts

associated with Counts 8 and 9 incorporates either FAR 52.209-3(d) or FAR

52.209-4(d), which both state that if “the Contractor fails to deliver any first

article on time, or the Contracting Officer disapproves of any first article, the

Contractor shall be deemed to have failed to make delivery within the meaning

of the Default clause of this contract.” 48 C.F.R. §§ 52.209-3(d), 52.209-4(d)

(2015). Although the contracts underlying Counts 6 and 7 did not have first

article requirements, PSI failed to deliver all of the parts ordered. The default

clause in these contracts states that the government may terminate a contract

for default “if the Contractor fails to - (i) Deliver the supplies or to perform the

services within the time specified in this contract or any extension.” Id. §

52.249-8(a)(1). Defendant therefore argues that the agency was entitled to

terminate these contracts for default pursuant to their respective default

clauses.

17

For Counts 2-4, 8(B), and 9(L) through 9(N), the government contends

that it is entitled to summary judgment because PSI’s first articles failed

inspection and PSI never submitted second first articles. Defendant claims that,

because successful first article submissions were required under these

contracts, DLA was entitled to terminate for default upon PSI’s failure to

submit acceptable first articles. In response to PSI’s allegation that Warner

Robins improperly rejected PSI’s first articles in order to purchase the same

parts from its own internal manufacturing facility, defendant points out that

this argument fails because the first articles for Counts 3, 4, 8(B) and 9(N)

were submitted to Hill, not Warner Robins, and PSI has offered no evidence

that Warner Robins even manufactured the same parts required by the

contracts in Counts 2, 9(L), and 9(M). Rather, defendant argues, PSI is

engaging in mere speculation.

For Count 5, PSI’s appeal of the denial of its request for equitable

adjustment, defendant argues that it is entitled to summary judgment because

PSI did not make a timely request for equitable adjustment. Rather, it raised

the issue nearly four years after receiving notice that its first article was

rejected and nearly three years after receiving notice that its second first article

was conditionally approved. In addition, PSI was provided additional time

within which to deliver the remaining parts, but PSI failed to meet those

deadlines and therefore is entitled to no more from the government.

In response, plaintiff argues that, for all of the contracts, DLA waived

delivery dates through its course of dealing with PSI over the years. According

to plaintiff, PSI and DLA had an informal working relationship whereby

delivery schedules were not strictly enforced and DLA regularly allowed

deadlines to pass. Plaintiff contends that it relied on this waiver by accepting

contracts based on the understanding that DLA would continue to be flexible

with delivery schedules.

Plaintiff also argues that for all of the contracts at issue in this motion,

DLA abused its discretion by failing to consider the impact of DX-rated orders

when terminating PSI’s contracts for default. Plaintiff contends that under the

Defense Priorities and Allocations Systems (“DPAS”), which is used to

prioritize the performance of defense contracts, contractors are required to

prioritize DX-rated orders over DO-rated orders and unrated orders. All of the

contracts listed in the complaint were DO-rated or unrated. However, during

the relevant time period, PSI had a number of DX-rated orders with Sikorsky

Aircraft Corporation. Plaintiff argues that the law required it to reschedule and

18

delay its lower-rated orders with DLA in order to accomodate the DX-rated

orders. Further, plaintiff contends that the government was aware of PSI’s DX-

rated contracts and therefore should have considered them when determining

whether to terminate for default.

Regarding Counts 2, 3, 4, 8(B), 9(L), 9(M), and 9(M), the contracts for

which PSI’s initial first article was rejected and it did not submit second first

articles, PSI argues that DLA abused its discretion because it failed to grant

conditional approval for first articles with easily correctable defects. Plaintiff

provides the affidavit of Jeremy Wilczewski, the Chief Operating Officer of

PSI, explaining how PSI could have easily corrected the defects that DLA

identified in its first article rejections.

PSI concludes by arguing that DLA was obligated by law to equitably

adjust the contract associated with Count 5. PSI contends that FAR 52.209-4(f)

requires the government to pay the contractor for delays in first article

approval if timely written request is made and that, here, a timely request was

made–four days after the agency issued a modification extending the delivery

date.

Defendant replies that, having met its burden of establishing that PSI

did not meet the performance deadlines, the burden shifts to PSI to excuse the

failure to deliver. Defendant claims that plaintiff’s argument that the

government waived delivery deadlines is without support because it fails to

establish the elements necessary to prove a waiver: (1) failure to terminate

within a reasonable time after default under circumstances indicating

forbearance and (2) reliance by the contractor on the failure to terminate.

DeVito v. United States, 413 F.2d 1147, 1154 (Ct. Cl. 1969). According to

defendant, PSI offers no evidence that it performed on the contracts, or that it

continued to perform after the expiration of the delivery dates. Defendant also

contends that plaintiff has failed to sufficiently explain why its obligations to

complete DX-rated contracts precluded it from fulfilling its obligations under

the contracts with DLA and argues that plaintiff’s conditional approval

argument is unsupported by the evidence.

We begin by addressing plaintiff’s general arguments that DLA waived

the delivery deadlines through its course of dealing and that DLA abused its

discretion in failing to consider the impact of PSI’s DX-rated contracts when

it terminated several of the contracts for default. As we discuss in detail below,

we agree with defendant. Plaintiff has failed to establish waiver as to any of

19

the contracts or that DLA was required to consider PSI’s DX-rated contracts

when terminating for default.4

Plaintiff argues that, for all of the contracts at issue and for past

contracts, DLA routinely allowed delivery dates to pass and generally made it

clear to PSI that time was not of the essence. Thus, according to plaintiff, it

accepted the contracts with the expectation that DLA would continue not to

strictly enforce delivery dates. Plaintiff points out that, in 2009, DLA went

through a reorganization that involved a restructuring of its post-award branch.

According to plaintiff, the agency thereafter abruptly changed its course of

dealing, resulting in DLA suddenly demanding performance for all contracts

at once. This argument, however, does not explain why DLA’s decision to

terminate any specific contract was unreasonable. What we would need from

plaintiff to accept its waiver argument are contract-specific facts showing

“failure to terminate within a reasonable time after default under circumstances

indicating forbearance.” DeVito, 413 F.2d at 1154. The broad approach which

plaintiff takes in arguing waiver by DLA is not sufficient. Only the

circumstances surrounding each individual contract determine whether the

agency was within its rights in terminating that contract for default.

Counts 2, 3, and 4 all had first article submissions which were rejected.

In Count 2, a second first article was submitted and also rejected. The agency

therefore informed PSI that it could either submit another first article or cancel

the contract. PSI, however, failed to inform the agency whether it would

submit a new first article or agree to a cancellation. As to Count 3, after the

first article was rejected, the parties bilaterally set a new date for first article

resubmission. However, that date passed without PSI submitting a new first

article. In Count 4, after the first article was rejected, the agency sent a

proposed bilateral termination for convenience. PSI refused to sign it, but did

not indicate that it planned to submit another first article. The agency

ultimately issued show cause notices for each of these contracts. These facts

cannot be construed as showing waiver by DLA. PSI was given the option to

either resubmit a first article or cancel the contract–neither option is indicative

of forebearance by DLA.

4

Plaintiff makes these arguments as to all of the contracts, but Counts 7, 8(A),

8(C) through 8(H), and 9(A) through 9(K) rest entirely on these arguments.

20

Count 7 pertains to an indefinite delivery, indefinite quantity contract

consisting of six separate orders. The first five had delivery dates spanning

from November 2008 through July 2010. Nevertheless, as of November 2010,

PSI had only shipped a portion of the first two orders. DLA thus notified PSI

that the contract was delinquent and that consideration was required before it

would accept any more shipments. PSI, however, did not take any steps

towards providing consideration and establishing new delivery dates. Instead,

it submitted a claim for equitable adjustment, which DLA subsequently denied.

In its denial letter, DLA reiterated that it expected delivery for the final order

and that if PSI did not provide revised delivery dates for the earlier orders,

DLA would terminate for default. These facts do not indicate forbearance by

DLA. Moreover, PSI has not shown “reliance by the contractor on the failure

to terminate and continued performance by him under the contract, with the

Government’s knowledge and implied or express consent.” DeVito, 188 Ct. Cl.

at 1154. While PSI shipped some parts after it was notified of its

delinquencies, this was not done with the government’s consent, as DLA had

informed PSI that it would require consideration before accepting late

shipments. Def.’s App. 248-49. Thereafter, PSI never informed the agency

whether it was working on the remaining parts. Nor did it ship them.

The contracts in Counts 8(A), 8(C) through 8(H), and 9(A) through

9(K) had first article requirements, but PSI failed to provide a first article.

Count 8(C)’s first article requirement was tied to another contract. If the other

first article was accepted, PSI would receive a first article waiver for this

contract. However, the first article submission for the other contract was

rejected twice, and PSI did not indicate whether it would submit another first

article. DLA therefore offered PSI a no-cost termination, which PSI refused

to sign. PSI did not, however, indicate that it would submit another first article

and never delivered one. This course of conduct again fails to show reliance

by PSI on the failure to terminate or continued performance under the contract

and thus fails to meet the requirements for waiver.

Counts 8(D), 8(F), and 9(A) through 9(K) transpired similarly–PSI

failed to deliver the first article on time and, for several of the counts, declined

to agree to the government’s proposed no-cost cancellation. However, PSI

never indicated to DLA that it was working on a first article and planned to

21

complete performance.5 Thus, DLA terminated the contracts for default. As

stated above, this course of conduct does not establish reliance by PSI on the

failure to terminate or continued performance under the contract, and therefore

it fails to meet the requirements for waiver.

For Counts 8(A), 8(E), 8(G), and 8(H), the agency requested several

status updates after the first article deadlines passed. Each time, PSI advised

that it was working on the first article or otherwise gave a new shipment date.

However, PSI never delivered the first articles and therefore DLA issued show

cause notices. These contracts can be differentiated from those discussed

above, however, because there is evidence that PSI told the agency that it was

working on the first articles and would ship them soon, which is indicative of

reliance. DLA’s failure to terminate when PSI indicated that it would ship the

first article late therefore could be construed as a waiver of the delivery date.

Thus, we are unable to grant summary judgment as to these contracts.

Next, we find no abuse of discretion in DLA’s failure to consider the

impact of PSI’s DX-rated contracts when it terminated several of PSI’s

contracts for default. Plaintiff is correct that it was required to give DX-rated

orders preference over DO-rated and unrated orders. 15 C.F.R. § 700.14(b)

(2015). However, PSI has not alleged that it was forced into accepting DO-

rated and unrated orders from DLA. In fact, the regulations provide that a

contractor shall not accept a rated order for delivery if it cannot fill the order

by the required date, or if it will interfere with previously accepted DO or DX-

rated orders. Id. § 700.13(b). PSI, however, never declined any contracts

because of performance issues stemming from other rated contracts. See Def.’s

App. 1065 (deposition of Jeremy Wilczewski). Thus, PSI was not acting under

duress and the blame cannot be shifted to the agency for failing to consider

5

For Counts 8(D) and 9(K), PSI was asked where it stood on the contract but

did not respond. Plaintiff contends that it was customary for PSI to

communicate with DLA through DCMA and thus DLA was given status

updates through DCMA, but does not provide any evidence that PSI gave DLA

specific updates as to the progress of these contracts. For Count 9(A), the

government warned PSI that, if it did not propose a new delivery date, the

contract would be terminated for default. PSI responded, but did not propose

a new delivery date. For Counts 9(D), 9(G), and 9(J), PSI provided a new ship

date but did not ship by this date and did not otherwise indicate that it was

working on the first article.

22

PSI’s higher-rated orders. PSI simply should not have accepted orders which

it was unable to fill or which interfered with earlier higher-rated orders.

PSI attempts to argue that the burden to rearrange the delivery schedule

can be shifted to the agency because it was on notice of PSI’s DX-rated

contracts. There is no merit to this argument, however, because the agency was

not given proper notice. The regulation dealing with the notice requirement

provides that

[i]f a person has accepted a rated order and subsequently finds

that shipment or performance will be delayed, the person must

notify the customer immediately, give the reasons for the delay,

and advise of a new shipment or performance date. If

notification is given verbally, written (hard copy) or electronic

confirmation must be provided within one working day of the

verbal notice.

Id. § 700.13(d)(3). There is no indication in the record that PSI provided notice

to the agency. As to all of the contracts pertaining to Count 8, PSI first

mentioned its DX-rated contracts in its response to DLA’s show cause notice,

well after it had failed to meet delivery deadlines. This reference by PSI to its

DX-rated contracts simply refers to an “understanding” that PSI would

prioritize DX-rated contracts. Def.’s App. 297, 316. This is unspecific and

does not suffice to provide the notice required by the regulations. In fact, the

only contracts for which PSI explicitly informed the agency that delivery

would be delayed due to DX-rated contracts were those underlying Counts 4

and 5. However, rather than notifying the agency immediately and providing

reasons for the delay, as required by the regulations, PSI waited until the

agency inquired about the late shipment before it mentioned that it had

interrupted production due to DX-rated contracts. See Pl.’s App. 398; Def.’s

App 162-64. DLA therefore had no obligation to allow PSI to extend delivery

dates due to conflicts with higher-rated contracts. Accordingly, we reject the

argument, as to all contracts, that DLA abused its discretion in failing to

consider the impact of PSI’s DX-rated contracts when it terminated several of

PSI’s contracts for default.

Thus, we are left with plaintiff’s remaining arguments as to Counts 2,

3, 4, 5, 6, 8(B), 9(L), 9(N), and 9(M). Regarding Count 5, plaintiff’s remaining

argument is that it was entitled to equitable adjustment because the

government delayed first article approval. We reject this argument because the

23

government did equitably adjust the contract. The relevant FAR provision

provides that if the government delays completion of first article disapproval

or conditional approval, it “shall, upon timely written request from the

Contractor, equitably adjust under the Changes clause of this contract the

delivery or performance dates and/or the contract price, and any other

contractual term affected by the delay.” 48 C.F.R. § 52.209–4(f) (2015). The

parts were originally due in October 2008. DLA issued several modifications

extending the due date, which ultimately resulted in a January 2011 due date.

Thus, if DLA delayed performance, it remedied its delay by equitably

adjusting the performance dates of the contract. We therefore grant summary

judgment as to Count 5.

As to Count 6, plaintiff argues that DLA’s decision to terminate the

contract for default based on PSI’s failure to deliver Delivery Order 0003 was

arbitrary and capricious because PSI never received the third order. Defendant

contends that the order was sent to the email address provided by PSI. Plaintiff

responds that DLA has not verified whether the order actually went through.

The contracting officer stated in her deposition that Delivery Order 0003 was

sent by the same means as Delivery Orders 0001 and 0002, and that it was

posted to DLA’s computerized ordering system. However, she could not recall

if she checked her electronic contract file to see if the notice had actually been

sent to PSI. We find that this information presents fact issues which we cannot

resolve on summary judgment, and therefore deny summary judgment as to

Count 6.

The remaining issue is whether the first articles for the contracts

associated with Counts 2, 3, 4, 8(B), 9(L), 9(N), and 9(M) should have been

granted conditional approval because their defects were easily correctable.

Plaintiff points to a number of Armed Services Board of Contract Appeals

(“ASBCA”) decisions in which termination for default of a contract which

provides for conditional approval was reversed where the first article with

easily correctable defects was rejected. See, e.g., Marvin Engineering

Company, Inc., ASBCA No. 27016, 84-2 BCA ¶ 17,401; Harco Manufacturing

Company, ASBCA No. 27567, 85-1 DCA ¶ 17,926. Forfeiture is inappropriate

where the only basis for rejection of the first article is defects that could be

easily corrected during production.

To support its argument that the defects were easily correctable,

plaintiff provides the affidavit of its Chief Operating Officer. In this affidavit,

Mr. Wilczewski notes the discrepancies identified in the notices of first article

24

rejections as to the relevant contracts and explains how each defect could have

been corrected during production. The contract underlying Count 3, for

example, was rejected due to dimensional discrepancies, because a strap was

off-center, because the part was the wrong shade of gray, and because two

certifications were missing. Wilczewski explains in his affidavit that the

dimensional variations could have been easily corrected by adjusting the trim

fixture, and the strap could have been easily corrected by adjusting its location.

Wilczewski Affidavit ¶ 39. Moreover, he states that the color could have been

easily changed, and the missing certifications could have been easily remedied

by giving the government the correct paperwork. Id.

We find that the Wilczewski affidavit is sufficient to defeat the

government’s motion for summary judgment as to these counts. See

TechSearch, LLC v. Intel Corp., 286 F.3d 1360, 1372 (Fed. Cir. 2002) (“[T]the

party opposing the motion for summary judgment . . . must point to an

evidentiary conflict created on the record, at least by a counter-statement of a

fact set forth in detail in an affidavit by a knowledgeable affiant.”). The

affidavit has set forth facts which create a genuine issue as to whether these

defects were easily correctable and thus whether PSI was entitled to

conditional approval of its initial first articles. Therefore, we deny summary

judgment as to Counts 2, 3, 4, 8(B), 9(L), 9(N), and 9(M).6

CONCLUSION

For the reasons stated herein, we grant in part and deny in part

defendant’s motion for summary judgment. The clerk is directed to enter

judgment for defendant as to Counts 5, 7, 8(C), 8(D), 8(F), and 9(A) through

9(K). The parties are directed to consult and jointly propose a trial schedule by

June 30, 2016.

s/ Eric G. Bruggink

ERIC G. BRUGGINK

Senior Judge

6

Plaintiff also makes additional count-specific arguments as to Count 2, 3, 4, and

9(L). However, because plaintiff has already defeated summary judgment as to

these counts with its conditional approval argument, there is no need to address

these arguments.

25

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.