Filed 12/10/15

IN THE SUPREME COURT OF CALIFORNIA

RANDALL KEITH HAMPTON et al., )

)

Plaintiffs and Appellants, )

) S213132

v. )

) Ct.App. 4/1 D061509

COUNTY OF SAN DIEGO, )

) San Diego County

Defendant and Respondent. ) Super. Ct. No. 37-2010-00101299-

) CU-PA-CTL

___________________________________ )

A public entity may be liable for injuries caused by dangerous conditions of public

property. (Gov. Code, §§ 830, 835.)1 An entity may avoid liability, however, through

the affirmative defense of design immunity. (§ 830.6.) “A public entity claiming design

immunity must establish three elements: (1) a causal relationship between the plan or

design and the accident; (2) discretionary approval of the plan or design prior to

construction; and (3) substantial evidence supporting the reasonableness of the plan or

design.” (Cornette v. Department of Transportation (2001) 26 Cal.4th 63, 66

(Cornette).) The present case concerns the second element of design immunity set out in

section 830.6 — discretionary approval.

In their petition for review, plaintiffs framed the issues as follows: “(1) Does a

public official‟s approval of a design constitute an „exercis[e] of discretionary authority‟

under []section 830.6 if, at the time he [or she] approved the design, the official did not

1

Statutory references are to the Government Code unless otherwise indicated.

1

realize the design deviated from governing standards? [¶] (2) Where a design deviates

from governing standards, must the public entity show that the official who approved the

design had the authority to disregard those standards?”

We conclude that the discretionary approval element of section 830.6 does not

implicate the question whether the employee who approved the plans was aware of

design standards or was aware that the design deviated from those standards. The issue

of the adequacy of the deliberative process with respect to design standards may be

considered in connection with the court‟s determination whether there is substantial

evidence that the design was reasonable. In addition, the discretionary approval element

does not require the entity to demonstrate in its prima facie case that the employee who

had authority to and did approve the plans also had authority to disregard applicable

standards.

We affirm the judgment of the Court of Appeal affirming the trial court‟s order

granting the County of San Diego‟s motion for summary judgment.

I. FACTUAL AND PROCEDURAL BACKGROUND

Before dawn on a day in early November 2009, plaintiff Randall Keith Hampton

was seriously injured in a collision between his vehicle and another that occurred at the

intersection of Miller and Cole Grade Roads in San Diego County. Hampton alleged that

the accident occurred when, attempting a left turn, he pulled forward from Miller Road, a

rural side road, onto Cole Grade Road, a rural two-lane thoroughfare that had paved

shoulders in addition to marked lanes of traffic.

Hampton and his wife sued defendant Robert Cullen, the other driver, alleging his

negligence caused the accident. Hampton suffered brain injuries and was unable to recall

whether he had stopped at the stop sign at the intersection. Cullen stated that Hampton‟s

vehicle entered the intersection “right in front of him, leaving too little time to stop before

the collision.” The on-scene accident report prepared by an officer of the California

2

Highway Patrol concluded that plaintiff had caused the accident by failing to stop at the

stop sign on Miller Road before proceeding into the intersection.

At issue in the present matter is not the question of driver negligence, however,

but the Hamptons‟ additional cause of action against the County of San Diego (County)

for maintaining an allegedly dangerous condition of public property. (§ 835 et seq.) The

Hamptons‟ principal claim against the County was that the design and construction of the

intersection where the accident occurred afforded inadequate visibility under applicable

County design standards for a driver turning left from Miller Road onto Cole Grade

Road. They presented evidence that a high embankment covered with vegetation

substantially impaired visibility for drivers turning left from Miller Road onto Cole Grade

Road. They alleged that the County‟s design drawings for the intersection did not

describe or depict the embankment or take it into account as an impediment to visibility,

nor did the design plan identify the sight distance a driver in plaintiff Hampton‟s position

would have, nor, significantly, did the design afford the visibility required by County

standards.

The County moved for summary judgment or summary adjudication of issues,

claiming design immunity under section 830.6. In support, it proffered reports that traffic

studies had suggested that visibility from Miller Road at the intersection had been

impaired because of the grade of Cole Grade Road. The County proffered design plans

and other evidence indicating that County engineers accordingly set out to improve

visibility by lowering the grade on that thoroughfare — along with installing some

warning signs and other measures. In fact, as shown by County road studies and plans

and an expert‟s declaration, the grade successfully was lowered and the warning signs

were installed along with a stop sign on Miller Road in preference to a stop light.

The County‟s principal expert, Robert Goralka, was employed as the County

Traffic Engineer for the County of San Diego. In addition to outlining the dangers

addressed by the County‟s road studies, and the improvements accomplished by its

3

design plans as executed, Goralka‟s declaration described the approval process for the

plans. It explained that prior to construction the plans were “signed by David Solomon, a

licensed civil engineer and traffic engineer who served as Deputy County Engineer and

was in charge of the County of San Diego Design Engineering Section. As the person in

charge of the County‟s Design Engineering Section, Solomon had been delegated by the

County Board of Supervisors, through the Director of the Department of Public Works,

[the] discretion and authority to approve plans such as [the improvement plan]. After the

project was completed, „as-built‟ plans were approved and signed by John Bidwell, a

licensed civil engineer who served as senior Civil Engineer of the County‟s Design

Engineering section on April 13, 1998.”

Goralka‟s declaration averred that at the time of the accident, the intersection was

substantially as called for in the design plans and that there had been no significant

changes since the plans were approved. Goralka went on to opine that the design plan

was reasonable because it provided adequate visibility for a driver on Miller Road who

could “creep forward” from the stop sign toward the edge of the lane of oncoming traffic

on Cole Grade Road. He added that the plan was a reasonable improvement in light of

design constraints “including roadways already in place that are near the crest of a hill

and an embankment with existing utilities.”

The Hamptons opposed the motion for summary judgment, stating that disputed

issues of fact remained concerning two elements of the County‟s immunity defense;

namely, whether there had been discretionary approval of the intersection design within

the meaning of the statute and whether the County had proffered substantial evidence that

such a design was reasonable. They also argued that through changed conditions of the

intersection, of which the County had notice, the County lost whatever design immunity

it had ever possessed. We are concerned here solely with the discretionary approval

element.

4

A principal point made by the Hamptons‟ opposition and evidence was that the

design plans proffered by the County did not show a geographic feature — the high,

raised embankment covered with shrubs — that allegedly would seriously impede the

visibility or “sight distance” available to a motorist who stopped at the stop sign on

Miller Road and sought to turn left onto Cole Grade Road. Plaintiffs measured visibility

from a certain vantage point that they asserted, with some support in documentary

evidence and expert declarations, was the point required by County standards. They

argued that the embankment rendered visibility plainly inadequate under applicable

County standards.

There was a conflict in the evidence concerning the vantage point from which

visibility should be measured under County standards. Plaintiffs presented evidence that

county design standards required that visibility be measured from behind the “limit line,”

referred to variously as a point a certain distance behind the curb or edge of pavement of

the cross street. It was undisputed that from that vantage point, visibility would be

impaired by the embankment and would not meet County standards. The County, by

contrast, presented evidence that County design standards called for a different vantage

point when work on existing as opposed to new roads was involved. According to the

County‟s expert, for existing roads, visibility was to be measured a few feet behind the

painted edge of the lane of oncoming traffic. Design standards contemplated, in other

words, that drivers would stop at the stop sign on Miller Road and then “creep forward”

onto Cole Grade Road to a point a few feet back from the edge of the lane of oncoming

traffic. From that vantage point, the embankment, albeit concededly absent from the

design drawings, would present no barrier to visibility and, in fact, visibility would meet

or exceed County standards.

The trial court granted summary judgment in the County‟s favor on the basis of

design immunity. The trial court concluded there was substantial evidence supporting

each of the three elements of design immunity. First, it pointed out that plaintiffs had

5

conceded the first element, causation. Second, it determined that Solomon‟s position as

the director of the County‟s design engineering section, meant that “he had been

delegated by the County Board of Supervisors, through the Director of the Department of

Public Works, to have discretion and authority to approve such plans[, and] [t]his

bespeaks sufficient discretion to entitle the County to invoke design immunity as a matter

of law. The court finds that the Goralka declaration is of solid evidentiary value and

inspires confidence in the conclusions expressed.” In addition, the trial court said, “the

as-built plan drawing was signed off on by John Bidwell, Senior Engineer in the Design

Engineering Section. This was all that was required.”

Third, the court also found substantial evidence upon which a reasonable public

employee could have adopted the plan, adding that typically the opinion of one engineer

in the public entity‟s favor is sufficient, and that because substantial evidence is all that

was required, the contrary opinion expressed by plaintiff‟s expert did not create a triable

issue of fact. Finally, the court also determined that there were no material triable issues

of fact concerning whether changed conditions rendered the intersection dangerous or

whether the County had notice of such changes.

The Court of Appeal agreed with the trial court that the County had established the

defense of design immunity for the purpose of summary judgment. With respect to the

second element of design immunity — discretionary approval — it concluded that “the

trial court properly determined that in presenting undisputed evidence that a licensed civil

and traffic engineer employed by the County approved the Plans prior to construction,

that this engineer had the discretionary authority to approve the Plans, and that another

licensed engineer employed by the County approved and signed the „as built‟ plans after

construction of the improvements, the County demonstrated the discretionary approval

element of its design immunity defense as a matter of law.”

In the view of the Court of Appeal, evidence of the County‟s deviation from its

own design standards was not a consideration that would preclude the grant of summary

6

judgment in the County‟s favor. The court declined to follow contrary language in Levin

v. State of California (1983) 146 Cal.App.3d 410 (Levin) and Hernandez v. Department

of Transportation (2003) 114 Cal.App.4th 376 (Hernandez). Plaintiffs‟ petition for

review was limited to the discretionary approval element of design immunity. Plaintiffs

did not challenge the trial and appellate courts‟ decision concerning the reasonableness of

the plan or their conclusion that the County did not lose design immunity due to changed

circumstances.

II. DISCUSSION

A. Standard of review

“A trial court properly grants a motion for summary judgment where „all the

papers submitted show that there is no triable issue as to any material fact and that the

moving party is entitled to a judgment as a matter of law.‟ (Code Civ. Proc., § 437c,

subd. (c).) „Because this case comes before us after the trial court granted a motion for

summary judgment, we take the facts from the record that was before the trial court when

it ruled on that motion. [Citation.] “ „We review the trial court‟s decision de novo,

considering all the evidence set forth in the moving and opposing papers except that to

which objections were made and sustained.‟ ” [Citation.] We liberally construe the

evidence in support of the party opposing summary judgment and resolve doubts

concerning the evidence in favor of that party.‟ ” (Hartford Casualty Ins. Co. v. Swift

Distribution, Inc. (2014) 59 Cal.4th 277, 286.)

B. General principles governing government tort claims and design immunity

Under the Government Claims Act, “[a] public entity is not liable for an injury,”

“[e]xcept as otherwise provided by statute.” (§ 815, subd. (a); see Guzman v. County of

Monterey (2009) 46 Cal.4th 887, 897 [“there is no common law tort liability for public

entities in California”]; Eastburn v. Regional Fire Protection Authority (2003) 31 Cal.4th

1175, 1179 [“the intent of the Tort Claims Act is to confine potential governmental

liability, not expand it”].)

7

The Government Claims Act (Act) provides for direct liability on the part of

public entities for injuries caused by maintaining dangerous conditions on their property

when the condition “created a reasonably foreseeable risk of the kind of injury which was

incurred” and either an employee‟s negligence or wrongful act or omission caused the

dangerous condition or the entity was on “actual or constructive notice” of the condition

in time to have taken preventive measures. (§ 835; see Cornette, supra, 26 Cal.4th at

p. 66.) A dangerous condition is one that “creates a substantial risk of injury” when the

property is “used with due care in a manner in which it is reasonably foreseeable that it

will be used.” (§ 830, subd. (a).)

If a dangerous condition is demonstrated, the public entity may still prevail against

a claim by means of an affirmative defense of immunity. Various types of public sector

immunity have been established by statute (see, e.g., §§ 830.8 [immunity for “failure to

provide traffic or warning signals” except when necessary to avoid a trap for drivers

exercising due care], 831.2 [immunity for natural condition of unimproved public

property]), but the present case concerns solely the affirmative defense of design

immunity under section 830.6.

Section 830.6 provides in pertinent part: “Neither a public entity nor a public

employee is liable under this chapter for an injury caused by the plan or design of a

construction of, or an improvement to, public property where such plan or design has

been approved in advance of the construction or improvement by the legislative body of

the public entity or by some other body or employee exercising discretionary authority to

give such approval or where such plan or design is prepared in conformity with standards

previously so approved, if the trial or appellate court determines that there is any

substantial evidence upon the basis of which (a) a reasonable public employee could have

adopted the plan or design or the standards therefor or (b) a reasonable legislative body or

other body or employee could have approved the plan or design or the standards

therefor.” Additional language governs circumstances under which design immunity

8

may be lost when the danger arises out of a change in physical conditions of which the

entity had notice and as to which it had time to obtain funding for and perform remedial

work or provide appropriate warnings. (Ibid., see Cornette, supra, 26 Cal.4th at p. 66.)

C. Discretionary approval element

Plaintiffs contend that “approv[al]” by one “exercising discretionary authority”

(§ 830.6), requires an exercise of discretion in the sense of an exercise of judgment or

choice, and that, in their words, “one cannot truly exercise judgment or make a choice

without an awareness of what is to be judged or chosen.” According to plaintiffs, “only

an engineer who realizes a design does not conform to governing standards can truly

make a discretionary decision to approve the design despite its nonconformity. By

contrast, an engineer who approves a nonconforming design on the mistaken belief it

conformed to governing standards has acted through inadvertence, not discretion.”

We disagree. Plaintiffs‟ claim essentially is that there was an abuse of discretion.

As we shall demonstrate, however, such claims are considered under the reasonableness

element of the statute.

As always, “our fundamental task is to ascertain the intent of the lawmakers so as

to effectuate the purpose of the statute.” (Estate of Griswold (2001) 25 Cal.4th 904, 910.)

The Act, including the design immunity statute, was adopted in 1963 (as the Tort

Claims Act) in response to judicial decisions abrogating principles of sovereign

immunity. The language governing the element of discretionary authority is unchanged

to this day. The Law Revision Commission (Commission) comment regarding section

830.6 describes the provision as “provid[ing] immunity where a governmental body

exercises the discretion given to it under the laws of the State in the planning and

designing of public construction and improvements. . . . [¶] The immunity provided by

Section 830.6 is similar to an immunity that has been granted by judicial decision to

public entities in New York. See Weiss v. Fote, 7 N.Y.2d 579, 200 N.Y.S.2d 409, 167

N.E.2d 63 (1960).” (Recommendation Relating to Sovereign Immunity (Jan. 1963)

9

Proposed Legislation, com. foll. § 830.6, 4 Cal. Law Rev. Com. Rep. (1963) p. 851, com.

reprinted in West‟s Ann. Gov. Code (2012 ed.) foll. § 830.6, p. 40.)

A statement by the Commission suggests that the discretionary approval element

of section 830.6 does not call for a jury to examine whether the employee who approved

a plan realized that the plan deviated from applicable standards. Rather, the statement

indicates that the law‟s purpose is to avoid the dangers involved in permitting re-

examination and second-guessing of governmental design decisions in the context of a

trial: “While it is proper to hold public entities liable for injuries caused by arbitrary

abuses of discretionary authority in planning improvements, to permit reexamination in

tort litigation of particular discretionary decisions where reasonable men may differ as to

how the discretion should be exercised would create too great a danger of impolitic

interference with the freedom of decision-making by those public officials in whom the

function of making such decisions has been vested.” (Recommendation Relating to

Sovereign Immunity, supra, 4 Cal. Law Revision Com. Rep. at p. 823.) We have

recognized that this statement reflects legislative intent. (Cornette, supra, 26 Cal.4th at

p. 69; Cameron v. State of California (1972) 7 Cal.3d 318, 326 (Cameron).) Plaintiffs‟

interpretation of the statute, however, would implicate the adequacy of the deliberative

process at the discretionary approval stage and would lead a jury into just the sort of

second-guessing concerning the wisdom of the design that the statute was intended to

avoid.

Moreover, the text of the statute does not suggest that a triable issue on the

discretionary approval element occurs whenever there is a conflict in the evidence

concerning applicable design standards and the plaintiff raises the question whether the

designated employee realized the design deviated from applicable standards. Ordinarily

we are not free to add text to the language selected by the Legislature. (Code Civ. Proc.,

§ 1858; Los Angeles County Metropolitan Transportation Authority v. Alameda Produce

Market, LLC (2011) 52 Cal.4th 1100, 1108.) Rather, as the Court of Appeal in the

10

present case observed, such an interpretation actually conflicts with statutory language.

According to the Court of Appeal: “On the contrary, the statute provides that the

discretionary element may be established either by evidence of appropriate discretionary

approval or evidence that the plan conformed with previously approved standards.

(§ 830.6 [„Neither a public entity nor a public employee is liable under this chapter for an

injury caused by the plan or design . . . where such plan or design has been approved . . .

by some . . . employee exercising discretionary authority to give such approval or where

such plan or design is prepared in conformity with standards previously so

approved . . . . ‟ (italics added)].)” That the statute permits, as one alternative, that the

discretionary approval element may be established through proof that the design complies

with discretionarily approved standards suggests that the other alternative, that is,

discretionary approval by the appropriate employee, does not require evidence of the

employee‟s awareness of and compliance with standards.

The structure of the provision as a whole also supports our interpretation. Under

the statute, once causation and approval by an authorized employee or compliance with

appropriately adopted standards is established, there is immunity so long as “the trial or

appellate court determines that there is any substantial evidence upon the basis of which

(a) a reasonable public employee could have adopted the plan or design or the standards

therefor or (b) a reasonable legislative body or other body or employee could have

approved the plan or design or the standards therefor.” (§ 830.6.) This three-part

structure implies that the wisdom of the design is evaluated — by the court — under the

reasonableness element of the immunity statute, and not under the element asking a jury

to decide whether an employee vested with discretion to approve the plans actually

approved them.

Indeed the Commission‟s comments make plain that it is the reasonableness

element of section 830.6 that supplies the statutory bulwark against arbitrary abuse of

discretion in the initial planning decision. As the Commission declared: “There should

11

be immunity from liability for the plan or design of public construction and

improvements where the plan or design has been approved by a governmental agency

exercising discretionary authority, unless there is no reasonable basis for such approval.”

(Recommendation Relating to Sovereign Immunity, supra, 4 Cal. Law Revision Com.

Rep. at p. 823, italics added.)

Thus, considered as a whole, it appears plain that section 830.6 was intended to

avoid second-guessing the initial design decision adopted by an employee vested with

authority to approve it, except to the extent the court determines that the employee‟s

approval of the design was unreasonable. It is at the reasonableness stage that the court

would consider whether an employee, in either knowingly or unknowingly approving a

design that deviates from applicable standards, adopted a design that a “reasonable

legislative body or other body or employee could have approved.” (§ 830.6.) Plaintiffs‟

contrary interpretation would undermine the function of the statute‟s reasonableness

element, a result that would be inconsistent with our duty to read the elements of the

statute together, harmonizing and giving effect to them all. (Los Angeles Unified School

Dist. v. Garcia (2013) 58 Cal.4th 175, 186; City of Huntington Beach v. Board of

Administration (1992) 4 Cal.4th 462, 468.)

We also note practical problems with plaintiffs‟ interpretation. Although objective

proof of the fact of approval by an employee with authority to approve the plan may be

readily available, evidence of the standards actually considered by the decision makers,

as well as the reasoning and motivation of those employees, will be much more scarce

with the passage of time. Plaintiffs‟ interpretation could produce the anomaly of different

immunity outcomes for identical designs depending simply upon the recordkeeping

ability of the public entities involved, or the availability of employees who are able to

remember the decisionmaking process of the persons involved — a process that may

have occurred long before the lawsuit.

12

Our understanding of the statute finds support in the New York high court‟s

decision in Weiss v. Fote, supra, 167 N.E.2d 63 (Weiss) — the decision to which the

Commission referred as a source of our own law. In Weiss, a pedestrian brought suit

after a car that had crashed into another car in an intersection veered into the pedestrian,

injuring her. She argued that the car accident was caused by a traffic signal that had

improper timing intervals pursuant to a local entity‟s design. Although the state and its

subdivisions owed a duty to keep streets in a reasonably safe condition, the decision

declared that courts “would not go behind the ordinary performance of planning functions

by the officials to whom those functions were entrusted.” ( Id. at p. 65.) In other words,

it was not for courts to take “ „administration of municipal affairs out of the hands to

which it has been entrusted by law.‟ ” (Ibid.) When the power over design of public

improvements such as streets rests with public officials or entities, “ „the duty to make

them is quasi judicial or discretionary, involving a determination as to their necessity,

requisite capacity, location, etc., and for a failure to exercise this power or an erroneous

estimate of public needs, no civil action may be maintained.‟ [. . . .] „[To permit such

actions] would be to take the administration of municipal affairs out of the hands to

which it has been entrusted by law. ‟ ” (Ibid.) Similarly, design “immunity [rests] on the

policy of maintaining the administration of municipal affairs in the hands of state or

municipal executive officers as against the incursion of courts and juries.” (Ibid.)

The New York court explained further: “Lawfully authorized planning by

governmental bodies has a unique character deserving of special treatment as regards the

extent to which it may give rise to tort liability. It is proper and necessary to hold

municipalities and the State liable for injuries arising out of the day-by-day operations of

government, . . . but to submit to a jury the reasonableness of the lawfully authorized

deliberations of executive bodies presents a different question. [Citations.] To accept a

jury‟s verdict as to the reasonableness and safety of a plan of governmental services and

prefer it over the judgment of the governmental body which originally considered and

13

passed on the matter would be to obstruct normal governmental operations and to place in

inexpert hands what the Legislature has seen fit to entrust to experts.” (Weiss, supra, 167

N.E.2d at pp. 65-66.)

We acknowledge that the Weiss court referred both to the reasonableness of the

design decision and the care or study with which it was adopted. The court pointed to

evidence that the city council, through its agent the board of safety, had made an

extensive study of traffic conditions at the intersection and had reached “considered

judgment” based on the studies before it regarding a “reasonably safe” timing interval for

the traffic lights. (Weiss, supra, 167 N.E.2d at p. 66.) The court, noting these studies,

found that there was no evidence to suggest that the local entity‟s decision was “either

arbitrary or unreasonable.” (Ibid., italics added.) “[A]bsent some indication that due

care was not exercised in the preparation of the design or that no reasonable official

could have adopted it — and there is no indication of either here — we perceive no basis

for preferring the jury verdict, as to the reasonableness of the „clearance interval,‟ to that

of the legally authorized body which made the determination in the first instance.” (Ibid.,

italics added.) In sum, the court concluded: “We are of the opinion that the traditional

reliance on a jury verdict to assess fault and general tort liability is misplaced where a

duly authorized public planning body has entertained and passed on the very same

question of risk as would ordinarily go to the jury. . . . For this reason, liability for injury

arising out of the operation of a duly executed highway safety plan may only be

predicated on proof that the plan either was evolved without adequate study or lacked

reasonable basis.” (Id. at pp. 67-68, italics added.)

In our view, however, the court‟s alternating references to decisions made without

adequate study and those lacking a reasonable basis for approval appear to be simply

components of a broader reasonableness inquiry. These comments fail to give significant

support to plaintiffs‟ interpretation of our own statute. Indeed, the Weiss court made it

plain that it was following long-established authority recognizing the importance of

14

leaving design decisions — including the design‟s necessity, wisdom, completeness, and

capacity — in the hands of the political branches. (Weiss, supra, 167 N.E.2d at pp. 65-

67; see Alexander v. Eldred (N.Y. 1984) 472 N.E.2d 996 [suggesting that under New

York law, arbitrary or uninformed decisionmaking should be analyzed under the

reasonableness element of design immunity].) Similarly, the Weiss court recognized

authority establishing that mere design error should not defeat immunity. (Weiss, supra,

167 N.E.2d at pp. 66, 67.) These considerations would be defeated if the trier of fact

were to reevaluate, in connection with the discretionary authority element of design

immunity, whether the employee who approved the design was adequately informed

regarding and actually considered all potentially relevant entity standards.

Plaintiffs cite a footnote in Johnson v. State of California (1968) 69 Cal.2d 782 in

support of their interpretation of what “exercising discretionary authority” (§ 830.6)

means. In that case we interpreted a statute providing immunity for public employees for

injuries resulting from an act or omission that “was the result of the exercise of the

discretion vested in him, whether or not such discretion be abused.” (§ 820.2.) Our

principal task in that case was to distinguish discretionary from ministerial acts, as the

latter carried no immunity. We declined to be drawn into debate concerning a literal or

mechanical definition of an exercise of discretion. (Johnson, supra, at pp. 788-789.)

Rather, we looked to the policy basis for governmental immunity for discretionary as

opposed to ministerial acts, locating the policy in “concern for the court‟s role in the

governmental structure” (id. at p. 794), and, more specifically, in avoiding placing courts

in “the unseemly position of determining the propriety of decisions expressly entrusted to

a coordinate branch of government.” (Id. at p. 793.) In a footnote we agreed with the

plaintiff‟s argument that the statute required the state to prove “that the employee, in

deciding to perform the act that led to plaintiff‟s injury, consciously exercised discretion

in the sense of assuming certain risks in order to gain other policy objectives.” (Id. at

p. 794, fn. 8.) We further agreed with plaintiffs that to obtain immunity for discretionary

15

or policy decisions, “the state must make a showing that such a policy decision,

consciously balancing risks and advantages, took place. The fact that an employee

normally engages in „discretionary activity‟ is irrelevant if, in a given case, the employee

did not render a considered decision.” (Ibid.)

Johnson interpreted a different statute employing different language from that

found in section 830.6, and, as noted, our principal task in that case was to distinguish

discretionary from ministerial acts, a distinction that plaintiffs‟ argument does not rest on

in this case. Moreover, the question of whether discretion has been exercised at all is

different from the question of how well it was exercised. We have since explained that in

the context of section 820.2 itself, we did not mean to suggest in Johnson that the public

entity must demonstrate a “strictly careful, thorough, formal, or correct evaluation. Such

a standard would swallow an immunity designed to protect against claims of

carelessness, malice, bad judgment, or abuse of discretion in the formulation of policy.”

(Caldwell v. Montoya (1995) 10 Cal.4th 972, 983-984 (Caldwell), italics omitted.)

In the Caldwell case, the question was whether the decision of school board

members not to renew a school superintendent‟s employment contract was a

discretionary policy decision subject to immunity under section 820.2. The allegations of

the complaint indicated that the board members “made an actual, conscious, and

considered collective policy decision to replace plaintiff as superintendent. The

complaint admits of no theory that the Board acted unconsciously or failed to weigh pros

and cons. On the contrary, [the complaint] asserts that Board members did purposely

employ standards they deemed relevant, but that [according to the plaintiffs] the

standards employed were wrong and impermissible. For reasons already stated, claims of

improper evaluation cannot divest a discretionary policy decision of its immunity.”

(Caldwell, supra, 10 Cal.4th at p. 984, fn. omitted, final italics added.)

Just as in Caldwell, plaintiffs do not allege that the responsible engineers failed to

exercise their discretion or judgment at all. Rather, plaintiffs allege in essence that the

16

engineers applied the wrong design standards and erred in their exercise of judgment

because they were unaware of the correct standards. These allegations simply claim an

“improper evaluation,” that is, carelessness, bad judgment, or abuse of discretion. But

under Caldwell, such a claim “cannot divest a discretionary policy decision of its

immunity.” (Caldwell, supra, 10 Cal.3d at p. 984; and see id. at p. 984, fn. 6.)

We acknowledge that the decisions in Levin, supra, 146 Cal.App.3d 410, and

Hernandez, supra, 114 Cal.App.4th 376, support plaintiffs‟ interpretation of the statute.

In Levin, a driver who veered to avoid an oncoming car that had crossed into her lane was

killed when her vehicle went over an embankment into a channel filled with water. The

plaintiffs‟ complaint alleged a dangerous condition in that the highway design omitted

adequate shoulders or a guardrail near the steeply sloped embankment. There was

evidence that the design violated state guardrail standards. The reviewing court, having

already identified a triable issue of fact on the causation element of design immunity, also

found a triable issue of fact with respect to the discretionary approval element. Its

analysis was brief: “As our Supreme Court pointed out in Cameron [, supra,] 7 Cal.3d

318, 326, the rationale of the design immunity defense is to prevent a jury from simply

reweighing the same factors considered by the governmental entity which approved the

design. An actual informed exercise of discretion is required. The defense does not exist

to immunize decisions that have not been made. Here, as in Cameron, supra, the design

plan contained no mention of the steep slope of the embankment. The state made no

showing that [the engineer], who alone had the discretionary authority, decided to ignore

the standards or considered the consequences of the elimination of the eight feet shoulder.

It follows that the state also failed to establish the second element of the defense.”

(Levin, supra, 146 Cal.App.3d at p. 418.)

In Hernandez, supra, 114 Cal.App.4th 376, the family of a decedent and persons

injured in an accident on a freeway off-ramp sued the state Department of Transportation,

alleging that the absence of a guardrail on the off-ramp constituted a dangerous condition

17

of public property that caused the injuries and death. Plaintiffs presented evidence that

the off-ramp design violated state guardrail standards and that state rules required that

formal approval of any deviation from standards be recorded in the project approval

document. (Id. at pp. 380-381.) The principal question before the Court of Appeal was

whether the discretionary approval element is one of fact for the jury or of law for the

court, and having appropriately concluded that the element is for the jury (Cornette,

supra, 26 Cal.4th at pp. 66, 74-75 & fn. 3; Laab v. City of Victorville (2008) 163

Cal.App.4th 1242, 1264), the Court of Appeal appeared to rely on Levin for the

proposition that summary judgment was inappropriate so long as there was a dispute in

the evidence concerning the factual questions whether the design violated applicable

standards and whether deviation from standards had been knowingly approved by the

responsible officials. (Hernandez, supra, 114 Cal.App.4th at p. 386, see also id. at

p. 388.) Hernandez relied on Levin, and Levin, in turn — with little analysis — relied on

our decision in Cameron, supra, 7 Cal.3d 318, as the principal authority for its decision.

Our decision in Cameron, supra, 7 Cal.3d 318, however, does not supply the

necessary authority in support. In that case the plaintiffs sustained injury when they lost

control of their car on a highway. Their complaint alleged that the injuries were caused

by a dangerous condition on the highway, namely uneven banking, also referred to as

“superelevation,” on a curve in the road. (Id. at p. 323) The state countered that although

the uneven banking or superelevation on the highway constituted a dangerous condition

of its property, the state was immune from liability under section 830.6 because the

uneven banking “was part of a duly approved design or plan of the highway.” (Cameron,

supra, 7 Cal.3d at p. 324.) The plaintiffs responded that even if plans for the highway

were approved by the appropriate entity, “such plans did not contain any design for or

mention of superelevation, and that therefore the design immunity provided for by

section 830.6 is inapplicable.” (Ibid.)

18

We reversed the trial court‟s entry of a judgment of nonsuit in favor of the state,

finding that the state had failed to meet its burden of establishing all the elements of

design immunity as a matter of law. We summarized the state‟s evidence that the

highway plans were prepared by appropriate county employees and had been approved

by the county board of supervisors, adding that the board of supervisors “was the proper

body to exercise the discretionary authority referred to in section 830.6. The record also

contains a declaration by . . . a civil engineer employed by the state, to the effect that the

design contained in the plan was in accordance with mid-1920 standards of design and

was reasonable.” (Cameron, supra, 7 Cal.3d at p. 325, fn. omitted.) We said these items

of evidence clearly were “sufficient to establish the initial applicability of an immunity

under section 830.6.” (Ibid.)

We observed that the plaintiffs had produced evidence that the superelevation did

not appear in the plan. (Cameron, supra, 7 Cal.3d at p. 325.) There was evidence from a

state highway engineer who reviewed the design plans and acknowledged that they did

not show any superelevations or cross sections and that “ „that was an omission on the

plans.‟ ” (Id. at p. 325, fn. 9, italics omitted.) A civil engineer called by the plaintiffs

testified regarding the design plans that “[t]hey do not give you any grades or elevations

other than the center line profile.‟ ” (Ibid.) The plaintiffs therefor urged that “there is no

evidence showing that the uneven superelevation was the result of a design or plan

approved by the . . . Board of Supervisors.” (Id. at pp. 325-326.)

Recalling that the rationale behind design immunity is to prevent a jury from

reweighing the same factors the public entity already considered during its discretionary

approval of the design, we said there would be no such reexamination in the case before

us: “Here the state has presented no evidence that the superelevation which was actually

constructed on the curve in question . . . was the result of or conformed to a design

approved by the public entity vested with discretionary authority. Thus, there would be

no reexamination of a discretionary decision in contravention of the design immunity

19

policy because there has been no such decision proved. The state merely showed that the

. . . Board of Supervisors approved a design showing the course of the right of way and

the elevation above sea level of the white center stripe for the road. The design plan

contained no mention of the superelevation intended or recommended. Therefore such

superelevation as was constructed did not result from the design or plan introduced into

evidence and there was no basis for concluding that any liability for injuries caused by

this uneven superelevation was immunized by section 830.6.” (Cameron, supra, 7 Cal.3d

at p. 326, fn. omitted.)

The above account shows that Cameron, supra, 7 Cal.3d 318, is not authority for

the interpretation of section 830.6 suggested by Levin, supra, 146 Cal.App.3d 410 and

Hernandez, supra, 114 Cal.App.4th 376. Cameron, unlike Levin and Hernandez (and

unlike the present case), did not concern the question whether a design deviated from

applicable standards or whether the approving employee was aware of a deviation from

standards and nonetheless decided to approve the plan. Our discussion in Cameron of the

rationale of design immunity — to prevent a jury from “ „simply reweighing the same

factors considered by the governmental entity which approved the design,‟ ” — along

with our comment that there had been no discretionary decision on the superelevation

(Cameron, supra, 7 Cal.3d at p. 326), were not intended to and did not suggest that, under

the discretionary approval element of section 830.6, the public entity bears the burden of

demonstrating that its employee considered all potentially applicable standards. Indeed,

such a requirement would constitute a surprising retreat from the basic understanding that

the discretionary approval element of design immunity asks whether a person vested with

discretion to approve the plan did approve the plan or design that was built, and that the

question whether it was wise to approve the plan is judged under the reasonableness

element of the statute.

Nor did our recitation in Cameron, supra, 7 Cal.3d 318, of various facts that we

believed amply demonstrated a prima facie showing of entitlement to design immunity

20

under all the elements of section 830.6 — including the reasonableness element —

indicate that each of the factors we mentioned was part of the required prima facie

showing for the discretionary approval element. Plaintiffs are correct that in Cameron we

stated that the state‟s engineer declared that “the design contained in the plans was in

accordance with mid-1920 standards of design and was reasonable” (id. at p. 325), but

nothing in our statement suggests that, as opposed to being a circumstance that was

relevant to the reasonableness of the plans at the time they were adopted in 1920,

evidence concerning the approving employee‟s awareness of applicable standards was

necessary to the prima facie showing for discretionary approval element. Because they

conflict with our interpretation of the statute and find no support in Cameron, supra, 7

Cal.3d 318, we disapprove Levin v. State of California, supra, 146 Cal.App.3d 410 and

Hernandez v. Department of Transportation, supra, 114 Cal.App.4th 376, to the extent

they are inconsistent with today‟s opinion.

As noted at the outset, plaintiffs made a subsidiary claim that the public entity, in

order to establish a prima facie case in support of the discretionary approval element of

section 830.6, was required to establish that the employees who approved the plans had

authority to deviate from applicable visibility standards. They offer no persuasive

authority in support. As the trial court found, the County‟s evidence was uncontradicted

that Solomon and Bidwell had authority to approve the designs. Plaintiffs presented no

evidence that these employees lacked authority to approve designs that deviated in any

respect from county standards. Plaintiffs did not create a conflict in the evidence on the

question of the employees‟ authority merely because they proffered evidence at trial that

the designs failed to comply with county standards.

Even the Levin and Hernandez decisions themselves do not support plaintiffs‟

claim on this point. We acknowledge that the Levin decision noted the absence of

evidence that the employee who approved the plans had authority to disregard applicable

guardrail standards. (Levin, supra, 146 Cal.App.3d at p. 418; see also Hernandez, supra,

21

114 Cal.App.4th at p. 543.) But neither Levin nor Hernandez held that, in the absence of

evidence proffered by the plaintiff that the employee lacked such authority, the public

entity must establish in its prima facie case that the approving employee‟s authority to

approve the plan included the authority to deviate from any possibly relevant standards.

Indeed, we note that in Hernandez, supra, 114 Cal.App.4th 376, it was the plaintiff who

presented evidence that the approving employees lacked authority to approve a deviation

from standards. (Id. at pp. 380-381.)

Nor did our decision in Cameron, supra, 7 Cal.3d 318, suggest that an employee‟s

authority to deviate from applicable standards is part of the public entity‟s prima facie

burden with respect to the discretionary approval element of design immunity. As we

have seen, Cameron did not turn on compliance with design standards, let alone on the

presence or absence of authority to deviate from those standards. The fact that we

observed in Cameron that the plans in that case had been prepared in accordance with

governing design standards did not establish that an approving employee‟s authority to

deviate from standards was part of the public entity‟s prima facie case.

22

III. CONCLUSION

For the foregoing reasons the decision of the Court of Appeal is affirmed.

CANTIL-SAKAUYE, C. J.

WE CONCUR:

WERDEGAR, J.

CHIN, J.

CORRIGAN, J.

LIU, J.

CUÉLLAR, J.

KRUGER, J.

23

See next page for addresses and telephone numbers for counsel who argued in Supreme Court.

Name of Opinion Hampton v. County of San Diego

__________________________________________________________________________________

Unpublished Opinion

Original Appeal

Original Proceeding

Review Granted XXX 218 Cal.App.4th 286

Rehearing Granted

__________________________________________________________________________________

Opinion No. S213132

Date Filed: December 10, 2015

__________________________________________________________________________________

Court: Superior

County: San Diego

Judge: Timothy B. Taylor

__________________________________________________________________________________

Counsel:

Thorsnes Bartolotta McGuire, John F. McGuire, Ian C. Fusselman and Benjamin I. Siminou for Plaintiffs

and Appellants.

Law Offices of Thor O. Emblem and Thor O. Emblem for Consumer Attorneys of California as Amicus

Curiae on behalf of Plaintiffs and Appellants.

Thomas E. Montgomery, County Counsel, and Christopher J. Welsh, Deputy County Counsel, for

Defendant and Respondent.

Ronald W. Beals, David Gossage, Lucille Y. Baca, Karl Schmidt and Derek S. Van Hoften for California

Department of Transportation as Amicus Curiae on behalf of Defendant and Respondent.

Pollak, Vida & Fisher and Daniel P. Barer for League of California Cities and California State Association

of Counties as Amicus Curiae on behalf of Defendant and Respondent.

1

Counsel who argued in Supreme Court (not intended for publication with opinion):

Benjamin I. Siminou

Thorsnes Bartolotta McGuire

2550 Fifth Avenue, 11th Floor

San Diego, CA 92103

(619) 236-9363

Christopher J. Welsh

Deputy County Counsel

1600 Pacific Highway, Room 355

San Diego, CA 92101-2469

(619) 557-4039

2

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.