Opinion

Green Valley Landowners Ass'n v. City of Vallejo

  • 241 Cal. App. 4th 425
  • 194 Cal. Rptr. 3d 19
  • 2015 Cal. App. LEXIS 912
Court
California Court of Appeal
Filed
Oct 16, 2015
Status
Published
Author
Dondero
On the bench
Dondero, Margulies, Banke
Cited by
45 cases
Authority
More cited than 77.2%

discussing public entity immunity in the context of a Bane Act claim

How later courts described this case

  • discussing public entity immunity in the context of a Bane Act claim
  • “There are no separate causes of action for specific performance or injunctive relief, 18 which are instead remedies.”
  • “The 17 essential elements of a claim of breach of contract, whether express or implied, are the 18 contract, the plaintiff’s performance or excuse for nonperformance, the defendant’s breach, 19 and the resulting damages to the plaintiff.”
  • “It is a well-settled rule that there is no common law governmental tort liability in California.”

Written by the judges who cited it.

The opinion

Filed 10/16/15

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION ONE

GREEN VALLEY LANDOWNERS

ASSOCIATION,

Plaintiff and Appellant, A142808

v. (Solano County

CITY OF VALLEJO, Super. Ct. No. FCS042938)

Defendant and Respondent.

In this class action comprised of nonresident water customers, plaintiff Green

Valley Landowners Association filed a complaint seeking to preserve its alleged right to

continue receiving water at reasonable rates from an historical water delivery system

owned and operated by defendant City of Vallejo (City). The trial court sustained the

City’s demurrer as to all 12 causes of action contained in the complaint without leave to

amend. Plaintiff contends the court’s rulings are legally erroneous. We affirm.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY

I. Factual Background1

The Lakes Water System (LWS) was created in the late 1800’s through the early

1900’s to provide the City with potable water. The City first constructed a diversion dam

coupled with a 14-inch transmission pipeline, which brought water from Solano County’s

Green Valley to the City (the Green Line). After completing the dam, the City created

1

We take the facts from the allegations in the complaint.

two reservoirs, Lake Frey (completed in 1894) and Lake Madigan (completed in 1908).

The LWS was one of the first municipal water projects in California.

Lake Frey and Lake Madigan were soon insufficient to meet the demands of the

City’s rapidly growing population. The City then applied for a permit to store 37,000

acre-feet of water in the hills above Napa County’s Gordon Valley. Subsequently, the

City constructed a dam and reservoir in Napa County known as Lake Curry (completed in

1925), along with a 24-inch transmission line to transport water from Lake Curry to the

City (the Gordon Line). Upon completion, the LWS consisted of three large reservoirs,

two dams, thousands of acres of land and watershed, and dozens of miles of municipal-

sized pipes, which conveyed needed water to the City.

In order to transport the water from the three reservoirs, the City acquired

easements from some of the property owners along the Green Line, the Gordon Line, and

elsewhere within the LWS service area. In exchange for these easements, the City agreed

in writing to provide a certain quantity of “free water” to the owners of the servient

estates.2 In addition, the City agreed in writing to provide certain quantities of “free

water” to other nonresident customers in exchange for riparian water rights. Over the

decades, the City agreed to provide potable water to other nonresident customers. These

connections were made without a master plan.

From 1893 through the 1950’s, the City’s municipal water needs were met

exclusively by the LWS. In the 1950’s, the City obtained water rights from the

Sacramento River Delta and contracted for water from the Solano Project.

In 1992, water quality from Lake Curry ceased to meet water treatment standards

adopted by the California Department of Health Services. The City elected to stop using

Lake Curry as a water source, closing a valve on the Gordon Line and stopping the flow

2

In other instances, the City condemned by eminent domain the property needed for the

easements.

2

of LWS water to the City. The City then passed an ordinance (the 1992 Ordinance)

shifting 100 percent of the cost of operating the LWS to its approximately 809

nonresident customers. Prior to 1991, these nonresidents had shared the cost of the LWS

with approximately 30,000 metered connections within the City. As a result of the 1992

Ordinance, water rates for the nonresident customers increased by over 230 percent.

The City passed additional water rate increases by ordinances enacted in 1995 (the

1995 Ordinance) and 2009 (the 2009 Ordinance). In addition to increasing water

consumption charges, the ordinances increased the fixed service charges to the

nonresident customers of the LWS. Plaintiff alleges in its complaint that current water

rates within the LWS are among the highest in the state.3

On June 9, 2009, plaintiff, on behalf of the purported class of nonresident LWS

customers (the Class), entered into a tolling agreement with the City (Tolling

Agreement). The Tolling Agreement tolls “any applicable statutes of limitations

regarding a potential challenge to the rate increase [which occurred in 2009].” The

Tolling Agreement has been extended 10 times, and expired on December 31, 2013.

According to plaintiff, the City has grossly mismanaged and neglected the LWS,

placing the burden on the Class to fund a deteriorating, inefficient, and costly water

system that is spread over an “incoherent service area.” In addition to water treatment

plant improvements made between 1997 and 2005 that cost almost $8 million,

replacement cost for a 10-mile section of the Gordon Line and a six-mile section of the

Green Line are expected to be over $12 million. All of these costs have been, or will be,

passed on to the LWS’s nonresident customers. Plaintiff did not become aware of these

unfunded liabilities until June 2013. Previously, the City had represented that the LWS

3

According to plaintiff’s opening brief, the average bimonthly water bill for residential

members of the Class is now over $400, or approximately 400 percent more than the

average City customer water bill.

3

was free of liabilities and debt, even though it performed “virtually no capital

improvements to or replacements of the infrastructure” between 1894 and 1992.

Plaintiff also alleges that the City had engaged in negotiations with a private

investor-owned utility to purchase the LWS. Reportedly, the City will only consider

selling the LWS to plaintiff (or to a water district or service district created by plaintiff)

for a sum that is almost $3 million over its “already flawed appraised value of the LWS.”

The extra sum reportedly represents a loan or subsidy that the City claims it extended to

LWS customers prior to 2009. Additionally, plaintiff complains that certain fees paid by

Class members have not been earmarked for LWS improvements as required by City

ordinances, but instead have been improperly used by the City for other unrelated

purposes.

II. Procedural History

On December 3, 2013, plaintiff filed and served a claim pursuant to Government

Code section 910 on behalf of itself and the Class.4

On January 23, 2013, plaintiff filed the operative complaint against the City. The

class action complaint states 12 causes of action, comprised of claims for breach of

implied contract, breach of implied covenant of good faith and fair dealing, breach of

contract (third party beneficiary), breach of duty to charge reasonable water rates, breach

of fiduciary duty, specific performance, declaratory relief, and accounting, along with

four separate claims for injunctive relief.

On February 24, 2014, the City filed a general demurrer to the complaint.

On June 11, 2014, the trial court issued a tentative ruling sustaining the City’s

demurrer without leave to amend.

4

All further statutory references are to the Government Code except as otherwise

indicated.

4

On August 21, 2014, plaintiff filed its notice of appeal.5

On August 22, 2014, the trial court filed its order affirming its tentative ruling,

granting the demurrer without leave to amend.

On October 1, 2014, the trial court filed its order dismissing the lawsuit and

entered final judgment for the City.

DISCUSSION

I. Standard of Review

“Because this case comes to us on a demurrer for failure to state a cause of action,

we accept as true the well-pleaded allegations in plaintiff’s . . . complaint. ‘ “We treat the

demurrer as admitting all material facts properly pleaded, but not contentions, deductions

or conclusions of fact or law. [Citation.] We also consider matters which may be

judicially noticed.” [Citation.] Further, we give the complaint a reasonable

interpretation, reading it as a whole and its parts in their context.’ ” (Evans v. City of

Berkeley (2006) 38 Cal.4th 1, 6.)

“While the decision to sustain or overrule a demurrer is a legal ruling subject to de

novo review on appeal, the granting of leave to amend involves an exercise of the trial

court’s discretion. [Citations.] When the trial court sustains a demurrer without leave to

amend, we must also consider whether the complaint might state a cause of action if a

defect could reasonably be cured by amendment. If the defect can be cured, then the

judgment of dismissal must be reversed to allow the plaintiff an opportunity to do so.

The plaintiff bears the burden of demonstrating a reasonable possibility to cure any defect

5

Although plaintiff’s appeal was premature because it was taken from the nonappealable

order sustaining the demurrer without leave to amend, we treat it as being from the

subsequently entered final judgment of dismissal. (See, e.g., Maxwell v. Dolezal (2014)

231 Cal.App.4th 93, 96, fn. 1 [“We deem appellant’s premature appeal, filed after the

nonappealable order sustaining the demurrer without leave to amend and before the

judgment of dismissal was entered, to be an appeal from the subsequent judgment of

dismissal.”].)

5

by amendment. [Citations.] A trial court abuses its discretion if it sustains a demurrer

without leave to amend when the plaintiff shows a reasonable possibility to cure any

defect by amendment. [Citations.] If the plaintiff cannot show an abuse of discretion, the

trial court’s order sustaining the demurrer without leave to amend must be affirmed.”

(Trader Sports, Inc. v. City of San Leandro (2001) 93 Cal.App.4th 37, 43–44.)

The plaintiff’s “burden of demonstrating a reasonable possibility to cure any

defect” (Trader Sports, Inc. v. City of San Leandro, supra, 93 Cal.App.4th at p. 43) is not

pro forma. “ ‘To satisfy that burden on appeal, a plaintiff “must show in what manner he

can amend his complaint and how that amendment will change the legal effect of his

pleading.” [Citation.] . . . The plaintiff must clearly and specifically set forth . . . factual

allegations that sufficiently state all required elements of that cause of action. [Citations.]

Allegations must be factual and specific, not vague or conclusionary.’ ” (Rossberg v.

Bank of America, N.A. (2013) 219 Cal.App.4th 1481, 1491, quoting Rakestraw v.

California Physicians’ Service (2000) 81 Cal.App.4th 39, 43–44.)

II. The Demurrer Was Properly Sustained as to the Implied Contract Claims

A. Causes of Action

Plaintiff represents that its implied contract claims, which it identifies as the first

(breach of implied contract), second (breach of implied covenant of good faith and fair

dealing) and 10th (specific performance) causes of action, are based on its theory that the

City is contractually obligated to share in the cost of the LWS pursuant to what plaintiff

refers to as the “Historic[al] Cost Sharing Ratio.”6 The gist of these claims is that the

City made an implied promise that it would “indefinitely share in the cost of operating,

maintaining and improving the LWS and that the costs would be shared according to the

6

In the complaint, the “Historic[al] Cost Sharing Ratio” is identified as the percentage of

LWS costs paid by City residents (at least 98 percent), as compared to nonresident LWS

customers (less than 2 percent) up until 1992.

6

Historic[al] Cost Sharing Ratio,” a promise that it allegedly breached when it passed the

1992, 1995, and 2009 Ordinances.

As the City notes, plaintiff’s third cause of action is also based on an implied

contract theory.7 The City also correctly observes that the complaint’s 10th claim, which

is for specific performance of the alleged implied agreement, actually constitutes a

remedy and is not itself a cause of action.8

B. Implied Contracts

“The terms of an express contract are stated in words. [Citation.] The existence

and terms of an implied contract are manifested by conduct. [Citation.] The distinction

reflects no difference in legal effect but merely in the mode of manifesting assent.”

(Retired Employees Assn. of Orange County, Inc. v. County of Orange (2011) 52 Cal.4th

1171, 1178.) The essential elements of a claim of breach of contract, whether express or

implied, are the contract, the plaintiff’s performance or excuse for nonperformance, the

defendant’s breach, and the resulting damages to the plaintiff. (Reichert v. General Ins.

Co. (1968) 68 Cal.2d 822, 830; Habitat Trust for Wildlife, Inc. v. City of Rancho

Cucamonga (2009) 175 Cal.App.4th 1306, 1332.) The prerequisite for any action for

breach of the implied covenant of good faith and fair dealing is the existence of a

contractual relationship between the parties, since the covenant is an implied term in the

contract. (See Foley v. Interactive Data Corp. (1988) 47 Cal.3d 654, 683–684, 690;

7

The third cause of action for breach of contract (third party beneficiary) focuses on the

LWS’s easements and asserts the City “breached its obligation to the Class when it

divested itself of any obligation to pay for the LWS and forced the members of the Class

to pay for and subsidize the provision of free water to the servient property owners. In

essence, [the City] transferred its contractual obligation to provide and pay for the free

water and has improperly shifted that obligation to the class.”

8

There are no separate causes of action for specific performance or injunctive relief,

which are instead remedies. (See, e.g., Wong v. Jing (2010) 189 Cal.App.4th 1354, 1360,

fn. 2 [specific performance and injunctive relief are equitable remedies and not causes of

action for injuries]; Marlin v. Aimco Venezia, LLC (2007) 154 Cal.App.4th 154, 162

[injunctive relief].)

7

Gruenberg v. Aetna Ins. Co. (1973) 9 Cal.3d 566, 576 [since noninsurer defendants in

bad faith case were not parties to the insurance contracts, they were not subject to an

implied duty of good faith and fair dealing].)

The trial court found the City could not be subjected to liability under an implied

contract theory, first noting the City’s charter does not contain any provisions specifically

addressing contract formation. As the charter is silent, the court concluded the City’s

contracting procedures are governed by the general law provision found in section 40602.

That section applies to the manner of contract formation and provides, in part, “[t]he

mayor shall sign . . . [¶] . . . [¶] [a]ll written contracts and conveyances made or entered

into by the city.” (Italics added.)

The trial court also cited to G.L. Mezzetta, Inc. v. City of American Canyon (2000)

78 Cal.App.4th 1087 (Mezzetta). In Mezzetta, the appellate court concluded that certain

municipal code provisions together with section 40602 precluded the general law city of

American Canyon from entering into an oral agreement. The agreement had allegedly

obligated the city to provide the plaintiff with wastewater discharge services. The court

reasoned: “[I]mplicit in the relevant statutes, when read together, is the requirement that

contracts with the City be in writing, approved by the city council, approved as to form

by the city attorney, and signed by either the mayor or the city manager. [Citations.]”

(Mezzetta, at p. 1093, italics added.) The court held that the alleged oral agreement was

void because it failed to comply with this requirement: “[B]ecause the statutes in question

specifically set forth the ways in which the City may enter into contracts, any other

methods of contract formation—even though not explicitly prohibited by the statutes—

are invalid. [Citations.] . . . To conclude otherwise would undermine the City’s clear

intent to ‘ “ensure that expensive decisions are not hastily made.” ’ ” (Id. at pp. 1093–

1094, fn. omitted.)

Plaintiff does not dispute that the City’s charter is silent with respect to the manner

of contracting. It also concedes the “implied agreement to share in the cost of the LWS

8

was never memorialized in writing.” It contends section 40602 does not apply because

charter cities “are independent of the general laws of the State on all matters of municipal

affairs.” This is true, according to plaintiff, even as to matters on which the charter is

silent. In so arguing, plaintiff construes cases that favor charter city ordinances over

conflicting general law provisions as standing for the proposition that general laws have

no application to charter cities in the absence of ordinances or charter provisions that

expressly invoke those general laws. This construction is not supported by case law.

C. General Law and Charter Cities

“ ‘The Government Code classifies cities as either “general law cities” (cities

organized under the general law of California) or “chartered cities” (cities organized

under a charter).’ ” (City of Orange v. San Diego County Employees Retirement Assn.

(2002) 103 Cal.App.4th 45, 52.) It is well settled that the method by which a city has

power to enter into a contract may be controlled by its charter. (Loop Lumber Co. v. Van

Loben Sels (1916) 173 Cal. 228, 232; First Street Plaza Partners v. City of Los Angeles

(1998) 65 Cal.App.4th 650, 661 (First Street).) Further, unless the city charter authorizes

such, no implied contract rights can arise. (Reams v. Cooley (1915) 171 Cal. 150, 153–

154; First Street, at p. 667.)

Section 201 of the City’s charter states: “The City shall have the power to act

pursuant to procedure established by any law of the State unless a different procedure is

required by this Charter.”9 The court below correctly noted that the manner in which a

city may form a contract is a municipal affair, and that the City’s charter, which could

have validly included contract formation provisions, “does not specifically prescribe how

its contracts must be executed.” The court concluded the City could thus rely on section

40602 for guidance. Plaintiff contends charter cities are never subject to general laws,

9

The City adopted its charter in 1970.

9

including section 40602, even if their charters are silent on the subject matter. We are not

persuaded.

Charter cities are specifically authorized by our state Constitution to govern

themselves, free of state legislative intrusion, as to those matters deemed municipal

affairs. Article XI, section 5, subdivision (a) of the California Constitution provides: “It

shall be competent in any city charter to provide that the city governed thereunder may

make and enforce all ordinances and regulations in respect to municipal affairs, subject

only to restrictions and limitations provided in their several charters and in respect to

other matters they shall be subject to general laws. City charters adopted pursuant to this

Constitution shall supersede any existing charter, and with respect to municipal affairs

shall supersede all laws inconsistent therewith.” (Italics added.) As the italicized

provisions indicate, chartered cities are permitted, but not required, to make and enforce

laws governing municipal affairs. If a city’s charter is silent as to a particular matter,

even one concerning a municipal affair, courts have opined that the matter will be subject

to the general laws of this state. (See, e.g., McLeod v. Board of Pension Commissioners

(1970) 14 Cal.App.3d 23, 29–30 (McLeod) [“[a] city, such as Los Angeles, which

operates under a freeholders’ charter is exempt from the operation of general laws with

respect to all ‘municipal affairs’ covered by the charter. [Citation.] . . . However, where

the charter contains no special procedure concerning a municipal subject, the general

laws govern.”] (Italics added, fn. omitted.))

As noted in section 201 of the Vallejo Charter, the City is permitted to follow the

laws of California regarding contract formation, i.e., section 40602, unless “a different

procedure is required by this Charter.” And section 200 of the Vallejo charter expressly

permits the City to “exercise any and all rights [and powers] . . . established, granted or

prescribed by the general laws of the State.” Thus, as the trial court below concluded, the

Vallejo Charter has effectively adopted the procedures set forth in section 40602 over any

10

other municipal-based approach to government contracts. Simply stated, the City has not

opted to create a different contracting procedure under its Charter.10

We concur with the holding of McLeod, supra, 14 Cal.App.3d 23. That decision

follows established principles in addressing charter cities and the effect of state statutes

on such municipalities when their charter does not provide specific guidance on a matter

of municipal concern. We disagree with plaintiff’s characterization of McLeod as an

isolated decision. (See Civic Center Assn. v. Railroad Comm. (1917) 175 Cal. 441, 445

[“With respect to matters not municipal, or municipal affairs upon which the charter [is]

silent, the provisions of any general law [i.e. state statute] pertaining thereto would

control the subject.”]; Armas v. City of Oakland (1960) 183 Cal.App.2d 137, 138–139

[“Although Oakland is a charter city, plaintiffs concede that its charter and ordinances

prescribe no procedure for street closing and that thus the procedural provisions of state

law must be followed, even if the function be municipal in character”]; Hyde v. Wilde

(1921) 51 Cal.App. 82, 86 [“Where no particular provisions are made covering a matter

falling within the classification of a ‘municipal affair,’ the state law controls.”])

In arguing otherwise, plaintiff relies on Butterworth v. Boyd (1938) 12 Cal.2d 140

(Butterworth) for the proposition that charter cities are not bound by the general laws of

this state with respect to municipal affairs, even as to matters that the charter does not

address. In Butterworth, a proposed charter amendment to the charter of the City and

10

The Vallejo charter contains express language dealing with contracting that is

compatible with section 40602. These charter provisions ensure City taxpayers are

protected from implied obligations. Charter section 716 prohibits any City expenditures

without the approval of the city council. Also, section 717 allows the city manager to

make contracts only with the approval of the council and an appropriation. The

Municipal Code of Vallejo has similar express restrictions. Section 3.20.045 allows

particular officials of the City to make contracts in stated dollar amounts. Written bids

and proposals in contracting are required under section 3.20.222. Additionally, section

3.22.010 mandates chapter 3.22 of the Vallejo Municipal Code applies to all government

contracts. These charter provisions and municipal ordinances facilitate the operation of

section 40602 and its requirements for express contracts.

11

County of San Francisco was approved by the electorate, and became effective by

concurrent resolution of the Legislature. The amendment called for a “ ‘health [care]

system’ ” for municipal employees. (Id. at p. 143.)

In deciding whether the establishment of a health care system qualified as a

“ ‘municipal affair,’ ” the Supreme Court observed, “In the early stages of municipal

home rule in California, the charter prevailed only where it expressly covered the

particular power exercised. Under the liberalizing constitutional amendment of 1914, the

charter is not a grant of power but a restriction only, and the municipality is supreme in

the field of municipal affairs even as to matters on which the charter is silent.”

(Butterworth, supra, 12 Cal.2d at p. 146, italics added.) As is apparent, the language

plaintiff relies on from Butterworth simply states the well-established principle that

chartered cities may act independent of general law with respect to matters deemed

“municipal affairs,” regardless of whether their charters address the specific municipal

affair that is at issue. It does not stand for the proposition that general laws never apply

to chartered cities, particularly in the absence of conflicting municipal ordinances or

regulations.

As the Butterworth court stated: “The purpose of the constitutional provisions was

to make municipalities self-governing and free from legislative interference with respect

to matters of local or internal concern. ‘It was to enable municipalities to conduct their

own business and control their own affairs, to the fullest possible extent in their own way.

It was enacted upon the principle that the municipality itself knew better what it wanted

and needed than the state at large, and to give that municipality the exclusive privilege

and right to enact direct legislation which would carry out and satisfy its wants and

needs.’ ” (Butterworth, supra, 12 Cal.2d at p. 147, italics added.) Thus, Butterworth

merely stands for the proposition that a chartered city has the power to enact regulations

regarding contract formation that differ from those contained in section 40602, something

the City has evidently chosen not to do. Simply stated, in Butterworth, the court held the

12

general law (state law) could not preempt a charter amendment passed by the voters of

San Francisco specifically addressing the topic of city employee health insurance

practices.

D. Cities Cannot Be Sued Under An Implied Contract Theory

Even if plaintiff is correct that section 40602 does not apply to this case, as

explained by the Court of Appeal in Katsura v. City of San Buenaventura (2007)

155 Cal.App.4th 104 (Katsura), “[i]t is settled that ‘a private party cannot sue a public

entity on an implied-in-law or quasi-contract theory, because such a theory is based on

quantum meruit or restitution considerations which are outweighed by the need to protect

and limit a public entity’s contractual obligations.’ [Citations.] [¶] . . . The reason is

simple: ‘ “The law never implies an agreement against its own restrictions and

prohibitions, or [expressed differently], ‘the law never implies an obligation to do that

which it forbids the party to agree to do.’ ” ’ [Citation.] In other words, contracts that

disregard applicable code provisions are beyond the power of the city to make.” (Id. at

pp. 109–110.)

The principle set forth in Katsura, supra, 155 Cal.App.4th 104, is well established

(see, e.g., Janis v. California State Lottery Com. (1998) 68 Cal.App.4th 824, 830; see

also Seymour v. State of California (1984) 156 Cal.App.3d 200, 204–205.) Limitations

on a municipality’s power to contract should be strictly construed because such

restrictions are designed to protect the public, not those who contract with the

municipality. (10 McQuillin, Municipal Corporations (3d ed. 2009 rev.) § 29:6, p. 336.)

Plaintiff seeks to distinguish Katsura, supra, 155 Cal.App.4th 104, because the

operative charter in that case expressly required all city contracts to be in writing.

Plaintiff asserts that if the City had “wanted the benefit of the Katsura rule, it could have

adopted similar charter language.” However, the holding in Katsura was that all implied

contracts against public entities are barred because, by definition, they have not formally

13

been approved by the entity. The court in that case did not limit its holding to cities with

charters that expressly require all contracts to be in writing.

In sum, we agree with the City that the demurrer as to the first, second, third and

10th causes of action was properly sustained.

III. Proposition 218

The trial court sustained the City’s demurrer to the fourth, fifth, and 11th causes of

action, finding them barred under Proposition 218. “Adopted by California voters in

November 1996, Proposition 218 added articles XIII C and XIII D to the California

Constitution. Proposition 218 generally prohibits local governments from imposing taxes

without voter approval.” (Owens v. County of Los Angeles (2013) 220 Cal.App.4th 107,

128.) “ ‘Article XIII C concerns voter approval for local government general taxes and

special taxes. Article XIII D sets forth procedures, requirements and voter approval

mechanisms for local government assessments, fees and charges.’ ” (City of Palmdale v.

Palmdale Water Dist. (2011) 198 Cal.App.4th 926, 931.)

Plaintiff’s fourth cause of action is for “Breach of Duty to Charge a Reasonable

Water Rate.”11 In its claim, it asserts the City “breached its obligation to provide water at

a reasonable rate” when it passed the 1992, 1995, and 2009 Ordinances in contravention

of the Historical Cost Sharing Ratio, causing Class members to pay rates almost five

times higher than rates paid by City residents. It claims the Class has suffered damages

in excess of $11 million, equal to the difference between what the Class paid under the

2009 Ordinance and what it would have paid had the City “honored the contractual

Historic[al] Cost Sharing Ratio.” Similarly, the fifth cause of action for breach of

fiduciary duty claims that the City owes the Class a duty to treat residents and

nonresidents equally with respect to the LWS. The 11th cause of action for declaratory

11

Our research has not uncovered any reported cases in any jurisdiction in the United

States identifying this claim as a cause of action.

14

relief alleges that the City presently intends to sell the LWS to a private utility and claims

the July 2014 rates “will continue to violate the Historical Cost Sharing Ratio by forcing

the non-resident customers of the LWS to pay 100% of the cost of operating, maintaining

and improving the LWS.”

The trial court found what it referred to as the “ ‘pooled-rate’ structure” proposed

by plaintiff in these claims to be prohibited by article XIII D, section 6, subdivision (b) of

the California Constitution, which provides that “[a] fee or charge shall not be extended,

imposed, or increased by any agency unless it meets all of the following requirements:

[¶] (1) Revenues derived from the fee or charge shall not exceed the funds required to

provide the property-related service. [¶] (2) Revenues derived from the fee or charge

shall not be used for any purpose other than that for which the fee or charge was imposed.

[¶] (3) The amount of a fee or charge imposed upon any parcel or person as an incident

of property ownership shall not exceed the proportional cost of the service attributable to

the parcel.” (Italics added.) The court cited to Griffith v. Pajaro Valley Water

Management Agency (2013) 220 Cal.App.4th 586 (Griffith) in support of its ruling,

concluding that Proposition 218 “prohibits a rate structure as alleged in Plaintiff’s

complaint that requires one group of customers to essentially subsidize another . . . .”

In Griffith, the objectors appealed from judgments in favor of a water management

agency challenging an ordinance enacted by the agency that increased groundwater

augmentation charges for the operation of wells within the agency’s jurisdiction. The

Court of Appeal held that the augmentation charges were expressly exempt from

Proposition 218’s fee/charge voting requirement. “Given that Proposition 218 prescribes

no particular method for apportioning a fee or charge other than that the amount shall not

exceed the proportional cost of the service attributable to the parcel, defendant’s method

of grouping similar users together for the same augmentation rate and charging the users

according to usage is a reasonable way to apportion the cost of service.” (Griffith, supra,

220 Cal.App.4th at p. 601.)

15

Plaintiff asserts Proposition 218 is irrelevant to this dispute because the complaint

does not specify how the City is to satisfy its obligation to pay monetary damages equal

to the difference between a “reasonable rate” and the rates the City actually charged

members of the putative class. However, the “Historical Cost Sharing Ratio” theory is

not viable in light of Proposition 218. Manifestly, an apportionment that would place 98

percent of the burden of LWS on City residents while giving them zero services in return

is unreasonable. Plaintiff also briefly asserts it should be granted leave to amend to

allege a federal equal protection cause of action. However, the case that it relies on—

Hansen v. City of San Buenaventura (1986) 42 Cal.3d 1172, 1189–1190 (Hansen)—does

not assist plaintiff, as it was decided before the passage of Proposition 218.

IV. Injunctive Relief Against Sale

Plaintiff’s sixth and seventh causes of action are for injunctive relief against the

alleged proposed sale of the LWS. The sixth cause of action is against the sale of the

system, and the seventh is against the sale of the system without land. The complaint

alleges that the City intends to sell the LWS to a private investor-owned utility that would

thereafter “be allowed to pass the full cost of operating, maintaining and improving the

LWS onto the Class.” In the seventh cause of action, plaintiff asserts the city intends to

sell the physical structure of the LWS, while retaining the excess real property for the

benefit of its general municipal fund without investing any of the proceeds into the LWS.

The trial court concluded that it could not legally prevent the execution of a public

sale, noting that both the California Constitution12 and Public Utilities Code section

12

California Constitution article XI, section 9, subdivision (a) provides: “A municipal

corporation may establish, purchase, and operate public works to furnish its inhabitants

with light, water, power, heat, transportation, or means of communication. It may furnish

those services outside its boundaries, except within another municipal corporation which

furnishes the same service and does not consent.”

16

1005113 grant the City the power to operate and to sell its public utility assets. (See

Leach v. City of San Marcos (1989) 213 Cal.App.3d 648, 660–661 [“Under Code of Civil

Procedure section 526 . . . and Civil Code section 3423 an injunction cannot be granted to

prevent execution of a public statute. Nonetheless an injunction may issue where the

statute or ordinance is invalid and a showing is made of irreparable injury to property or

business.”].) Here, plaintiff offers nothing persuasive to show that Public Utilities Code

section 10051 is invalid.14 Accordingly, the two claims for injunctive relief fail.

V. Injunctive Relief Against Surcharge Fee and Future Rate Structures

Plaintiff’s eighth cause of action asked for an injunction to stop the City from

continuing a surcharge fee enacted as a part of the 1995 Ordinance after September 30,

2015, when it is set to expire. In the ninth cause of action it seeks to stop the City from

imposing future rate structures that do not require it to share in the cost of operating and

maintaining the LWS pursuant to the Historical Cost Sharing Ratio.

As the trial court correctly found, the speculative allegation that the City may

violate the provision that discontinues the surcharge fee after September 30, 2015, was

premature. Additionally, the court noted that under Water Replenishment Dist. of

Southern California v. City of Cerritos (2013) 220 Cal.App.4th 1450, 1469–1470, water

assessments are subject to the “ ‘pay first, litigate later’ ” rule. Plaintiff challenges this

ruling. Regardless, the injunction claims are based on the same implied contract theory

that we have already found lacking in merit.

13

Public Utility Code section 10051 provides: “Any municipal corporation incorporated

under the laws of this State may as provided in this article sell and dispose of any public

utility that it owns.”

14

Plaintiff claims that the sale would violate Public Utilities Code sections 10061

[prohibiting the acquiring entity from unreasonably discriminating against existing

customers] and 789.1 [proceeds from sale of public utility land by a “water corporation”

must be invested in “necessary or useful” water infrastructure]. The claims are

premature, as there are no allegations in the complaint that the City has approved a sale to

an identified buyer on known terms.

17

VI. Breach of Fiduciary Duty and Accounting

Plaintiff’s fifth cause of action is for breach of fiduciary duty. The 12th cause of

action is for accounting. The trial court agreed with the City that the two claims fail

because there is no common law tort liability for public entities in California. Instead,

liability must be based on statute per section 815, subdivision (a). We agree.

“The elements of a cause of action for breach of fiduciary duty are the existence of

a fiduciary relationship, its breach, and damage proximately caused by that breach.

[Citation.] Whether a fiduciary duty exists is generally a question of law. [Citation.]

Whether the defendant breached that duty towards the plaintiff is a question of fact.”

(Amtower v. Photon Dynamics, Inc. (2008) 158 Cal.App.4th 1582, 1599.)

It is a well-settled rule that “[t]here is no common law governmental tort liability

in California; and except as otherwise provided by statute, there is no liability on the part

of a public entity for any act or omission of itself, a public employee, or any other

person.” (Cowing v. City of Torrance (1976) 60 Cal.App.3d 757, 761.) Section 815,

subdivision (a) states: “Except as otherwise provided by statute: [¶] (a) A public entity is

not liable for an injury, whether such injury arises out of an act or omission of the public

entity or a public employee or any other person.” The legislative committee comment to

section 815 states: “This section abolishes all common law or judicially declared forms

of liability for public entities, except for such liability as may be required by the state or

federal constitution . . . .” (Italics added.)

Plaintiff relies on South Pasadena v. Pasadena Land Etc. Co. (1908) 152 Cal. 579,

594 (South Pasadena) and other cases stating that a city holding title to a water system

outside of its boundaries acts “as a mere trustee, bound to apply it to the use of those

beneficially interested.” These cases are not controlling, however. For example, in

Hansen, supra, 42 Cal.3d 1172, the Supreme Court reversed the Court of Appeal and

upheld the lower court’s ruling that a 70 percent surcharge on nonresident water

customers was reasonable. (Id. at p. 1176.) That case is distinguishable because it, like

18

South Pasadena, at pp. 587–588, is founded on the following principle: “A city which

acquires the water system of another community incurs an obligation to deal fairly with

its customers in that community and to provide them with service at reasonable rates.”

(Hansen, at p. 1180, italics added.) Here, the City did not acquire the LWS from plaintiff

or plaintiff’s predecessors. Again, Hansen is also distinguishable because it was decided

prior to the passage of Proposition 218. Additionally, none of the cases cited by plaintiff

in this regard discuss section 815, subdivision (a).

Finally, the accounting cause of action seeks an accounting of the surcharge and

connection fees levied by the City upon the LWS customers based on the allegation that

the fees were not placed in dedicated accounts and were not used exclusively for

constructing capital improvements to the LWS, as required by City regulations.

“An accounting is an equitable proceeding which is proper where there is an

unliquidated and unascertained amount owing that cannot be determined without an

examination of the debits and credits on the books to determine what is due and owing.

[Citations.] Equitable principles govern, and the plaintiff must show the legal remedy is

inadequate. . . . Generally, an underlying fiduciary relationship, such as a partnership,

will support an accounting, but the action does not lie merely because the books and

records are complex. [Citations.] Some underlying misconduct on the part of the

defendant must be shown to invoke the right to this equitable remedy.” (Prakashpalan v.

Engstrom, Lipscomb & Lack (2014) 223 Cal.App.4th 1105, 1136–1137.) As we have

already concluded plaintiff cannot state any viable claims alleging misconduct on the part

of the City, the cause of action for an accounting fails.

19

VII. Trial Court Did Not Abuse Its Discretion in Denying Leave to Amend

Plaintiff fails to set forth in sufficient detail how it would amend its complaint to

correct the multiple defects noted above. We conclude the trial court did not abuse its

discretion in denying plaintiff leave to amend.15

DISPOSITION

The judgment is affirmed.

15

In light of our above conclusions, we need not address the parties’ remaining

arguments.

20

_________________________

DONDERO, J.

We concur:

_________________________

MARGULIES, Acting P.J.

_________________________

BANKE, J.

A142808

21

Trial Court: Solano County Superior Court

Trial Judge: Hon. W. Arvid S. Johnson

Counsel for Appellant Law Offices of Stephen M. Flynn

Stephen M. Flynn

Counsel for Respondent Claudia M. Quintana, Vallejo City

Attorney; Donna R. Moody, Chief

Assistant Vallejo City Attorney

Colantuono, Highsmith & Whatley, PC

Michael G. Colantuono

Amy C. Sparrow

Leonard P. Aslanian

Jennifer L. Pancake

22