Opinion

City of San Antonio v. Valemas, Inc.

Court
Texas Court of Appeals, 4th District (San Antonio)
Filed
Jun 13, 2012
Status
Published
Cited by
0 cases
Authority
More cited than 42.2%

holding fact that lease was not assignable did not prevent valid assignment of overcharge claim arising from lease

How later courts described this case

  • holding fact that lease was not assignable did not prevent valid assignment of overcharge claim arising from lease

Written by the judges who cited it.

The opinion

MEMORANDUM OPINION

No. 04-11-00768-CV

CITY OF SAN ANTONIO,

Appellant

v.

VALEMAS, INC.,

Appellee

From the 166th Judicial District Court, Bexar County, Texas

Trial Court No. 2007-CI-15772

Honorable David A. Berchelmann, Jr., Judge Presiding

Opinion by: Marialyn Barnard, Justice

Sitting: Karen Angelini, Justice

Phylis J. Speedlin, Justice

Marialyn Barnard, Justice

Delivered and Filed: June 13, 2012

AFFIRMED

This is an interlocutory appeal from the trial court’s order denying a plea to the

jurisdiction filed by appellant City of San Antonio (“the City”). On appeal, the City raises two

issues challenging the trial court’s denial. We affirm.

BACKGROUND

In 2005, the City entered into a contract with Valemas, Inc. (“Valemas”). Pursuant to the

contract, Valemas was to provide extensive landscaping renovation in Brackenridge Park.

04-11-00768-CV

Valemas was to provide all machinery, labor, materials, and supervision for the project.

Valemas entered into subcontracts with numerous subcontractors and suppliers to perform work

on the Brackenridge Park project. The subcontractors included L. Payne Constructors (“Payne”).

Valemas began work on the project on January 27, 2005. According to Valemas, during

the course of the project, the City, among other things, delayed in obtaining necessary approvals

and permits, was slow in obtaining necessary amended drawings, mandated the use of specific

suppliers, and altered the scope of the project and increased the amount of work to be done.

Valemas claimed that as a result of the City’s acts and omissions, the contract price increased to

$2,552,200.17 and the contractual completion date of 250 days was impossible. The project

concluded on December 30, 2006. According to Valemas, the City’s actions resulted in

increased costs not only to Valemas, but to its subcontractors, including Payne. Valemas

claimed it and the subcontractors incurred damages for extra work, delay, downtime, additional

equipment charges, etc.

Valemas claimed the City refused to pay not only for the additional balance due because

of the delays and changes, but also refused to pay the balance on the original contract price. As a

result, Valemas was unable to pay Payne. In 2007, Valemas filed suit against the City alleging

breach of contract. In May 2010, Payne filed a plea in intervention and a cross-action, seeking

damages for breach of contract, or in the alternative quantum meruit or promissory estoppel.

The cross-action was originally against Valemas, but Payne then amended its intervention and

cross-action to include the City as a cross-defendant. The amendment of the cross-action came

after Valemas and Payne entered into a pass through agreement, which allows a contracting party

to assert a claim against the party with whom it contracted on behalf of another party who was

-2-

04-11-00768-CV

not a party to the contract. However, in January 2011, Payne filed a notice of nonsuit as to the

City.

The matter then proceeded between Valemas and the City. After answering and asserting

numerous affirmative defenses, the City filed a plea to the jurisdiction. In its plea to the

jurisdiction, the City asserted Valemas’s suit had to be dismissed for lack of jurisdiction because

it was asserting a claim not on its own behalf, but on behalf of Payne under a “pass through

agreement,” 1 and there is no statutory waiver of immunity for such a claim.

The trial court held a hearing on the City’s plea. At that hearing, the City conceded that

under section 271.152 of the Texas Local Government Code, the City “waives sovereign

immunity to suit for adjudicating a claim for breach of contract subject to the terms and

conditions of Chapter 271.” The City asserted, however, that waiver was not applicable here

because even though Valemas brought the breach of contract suit, it was not, in actuality, seeking

to recover under its contract with the City, but was pursuing claims on behalf of Payne, who was

not a party to the contract, through a pass through agreement. Because Payne has no written

contract with the City, the City argued immunity was not waived under section 271.152 and the

trial court was without jurisdiction. Alternatively, the City argued the anti-assignment clause in

the contract precluded Valemas from asserting Payne’s breach of contract claim.

At the conclusion of the hearing, the trial court took the matter under advisement. On

October 24, 2011, the trial court signed an order denying the City’s plea to the jurisdiction. The

City then perfected this appeal.

1

Under a “pass through agreement,” a party agrees to pursue another party’s claim or claims against a third party.

See Interstate Contracting Corp. v. City of Dallas, 135 S.W.3d 605, 610 (Tex. 2004). Such claims are referred to as

pass through claims, which are claims (1) by a party who has suffered damages, (2) against a responsible party with

whom it has no contract, and presented through an intervening party who has a contractual relationship with both.

Id. Typically, the contractor remains liable to the subcontractor, but only to the extent the contractor receives

payment from the owner. Id.

-3-

04-11-00768-CV

ANALYSIS

On appeal, the City raises two issues challenging the trial court’s order. The City first

contends the trial court erred in denying its plea to the jurisdiction because there is no express

waiver of immunity in section 271.152 of the Local Government Code for a subcontractor’s pass

through claim. Alternatively, the City argues that dismissal was required because of the anti-

assignment clause in the contract between Valemas and the City. We consider each issue in turn.

Waiver of Sovereign Immunity & Pass through Claims

The City first contends the trial court erred in refusing to dismiss Valemas’s suit for lack

of jurisdiction because Valemas was asserting a claim not on its own behalf, but on behalf of

Payne under a “pass through agreement,” and there is no statutory waiver of immunity for such a

claim. As noted above, under a “pass through agreement,” a party agrees to pursue another

party’s claim or claims against a third party. See Interstate Contracting Corp., 135 S.W.3d at

610. These “pass through claims” are claims by a party (here, a subcontractor) who has suffered

damages against a responsible party (here, the City) with whom it has no contract, presented

through an intervening party (here, a contractor) who has a contractual relationship with both.

Id.

Although the City concedes that under section 271.152 of the Texas Local Government

Code, sovereign immunity is waived for suits adjudicating a claim for breach of contract

between the City and parties it contracts with, waiver is not applicable here. The City asserts

that even though Valemas brought the breach of contract suit, it was pursuing claims on behalf of

Payne, who was not a party to the contract, by way of a pass through agreement between

Valemas and Payne. Thus, the question is whether section 271.152 of the Local Government

Code waives the City’s immunity for a breach of contract suit brought by a contracting party

-4-

04-11-00768-CV

when the contracting party is seeking recovery based on a pass through agreement with a party

that did not contract with the City.

Standard of Review

A plea to the jurisdiction based on governmental immunity2 challenges a trial court’s

subject matter jurisdiction. State v. Holland, 221 S.W.3d 639, 642 (Tex. 2007). Because the

existence or absence of subject matter jurisdiction is a question of law, we must review a trial

court’s ruling on a plea to the jurisdiction under a de novo standard of review. Tex. Dep’t of

Parks & Wildlife v. Miranda, 133 S.W.3d 217, 224-26 (Tex. 2004); Univ. of Tex. Health Sci. Ctr.

at San Antonio v. Stevens, 330 S.W.3d 335, 337 (Tex. App.—San Antonio 2010, no pet.). In

conducting our de novo review, we look to the plaintiff’s petition to determine whether the facts

as pled affirmatively demonstrate that jurisdiction exists. Holland, 221 S.W.3d at 642-43. We

must accept the allegations in the petition as true, construe them in favor of the pleading party,

and examine the pleader’s intent. Stevens, 330 S.W.3d at 337. We also consider any evidence

relevant to jurisdiction without considering the merits of the claim beyond the extent necessary

to determine jurisdiction. Miranda, 133 S.W.3d at 226-27. However, if the relevant evidence is

undisputed or fails to raise a fact question on the jurisdiction issue, the trial court rules on the

plea as a matter of law. Id. at 228. Here, we find the evidence presented is not probative of the

existence of any disputed jurisdictional facts, and therefore, we must decide the existence of

jurisdiction as a matter of law.

2

Although the phrases “sovereign immunity” and “governmental immunity” are often used interchangeably, the

phrase “sovereign immunity” technically applies to various divisions of state government, e.g., agencies, boards,

hospitals, and universities. Wight Realty Interests, Ltd. v. City of Friendswood, 333 S.W.3d 792, 796 (Tex. App.—

Houston [1st Dist.] 2010, no pet.). The phrase “governmental immunity,” on the other hand, protects political

subdivisions of the state, e.g., counties, cities, and school districts. Id. As the City is the relevant party in this

appeal, the phrase governmental immunity is proper. See id.

-5-

04-11-00768-CV

Application

We begin our analysis by noting that Texas recognizes the validity of pass through claims. See

Interstate Contracting Corp., 135 S.W.3d at 619; Alamo Cmty. Coll. Dist. v. Browning Constr.

Co., 131 S.W.3d 145, 159-60 (Tex. App.—San Antonio 2004, pet. denied). In Interstate

Contracting, the supreme court was presented with a certified question from the Fifth Circuit,

asking whether Texas recognized pass through claims, that is, whether a contractor could assert a

claim against an owner on a subcontractor’s behalf when there is no privity of contract between

the subcontractor and the owner. Id. at 607. The supreme court concluded Texas would allow

pass through claims, but it did not answer the question that is now posed to this court for review,

i.e., whether governmental immunity is waived under section 271.152 for suit based on such

claims. Id. at 620. The supreme court explained why it specifically chose not to address the

issue of sovereign immunity in Interstate Contracting, stating:

Although the questions certified do not limit our answers, we decline to extend

our answers in this case to the issue of sovereign immunity, which is well beyond

the scope of the questions certified. Doing so would require us to venture into the

facts of this particular case and analyze the merits of the parties’ claims at issue

before the Fifth Circuit Court of Appeals, rather than provide answers solely as to

the status of the Texas law on the questions asked. How our answer is to be

applied to the facts of this case is the province of the certifying court. See

Amberboy v. Societe de Banque Privee, 831 S.W.2d 793, 798 (Tex.1992).

Id. 3 The supreme court did not want to venture into the facts of the case and analyze the merits

of the issue before the federal appellate court. Id. However, the applicability of sovereign

immunity to pass through claims is now squarely before this court.

Here, it is undisputed that immunity is waived for any contract claims brought by

Valemas on its own behalf, assuming the damages sought are within the statutory limitations.

3

Although the Fifth Circuit applied the Texas Supreme Court’s answer to the certified question in Interstate

Contracting, allowing a contractor to sue the City of Dallas on behalf of a subcontractor based on a pass through

agreement, the issue of sovereign immunity was not raised. See Interstate Contracting Corp. v. City of Dallas,

Texas, 407 F.3d 708 (5th Cir. 2005).

-6-

04-11-00768-CV

See id. § 271.153. It is also undisputed that Payne does not have a written contract with the City,

and therefore could not assert a breach of contract action against the City on its own due to lack

of privity. See Sanders v. Total Heat & Air, Inc., 248 S.W.3d 907, 912 (Tex. App.—Dallas

2008, no pet.) (holding privity between injured party and party to be held liable is generally

essential element for recovery in breach of contract action). Given that Texas recognizes the

validity of pass through claims, the question is whether Valemas, as a party who has a contract

with the City, can assert a pass through claim on Payne’s behalf against the City based on section

271.152, or whether the City has immunity from such a claim.

Sovereign and governmental immunity protect the State and its political subdivisions

from suits for money damages. See Reata Constr. Corp. v. City of Dallas, 197 S.W.3d 371, 374

(Tex. 2006). The Texas Legislature has mandated that statutes should not be construed to waive

immunity unless the waiver is stated in clear and unambiguous language. City of Galveston v.

State, 217 S.W.3d 466, 469; see TEX. GOV’T CODE ANN. § 311.034 (West Supp. 2011) (stating

statute shall not be construed as waiver of sovereign immunity unless waiver is effected in clear

and unambiguous language). Generally, any ambiguity as to the existence of waiver is resolved

in favor of immunity. Harris Cnty. Hosp. Dist. v. Tomball Reg’l Hosp., 283 S.W.3d 838, 844

(Tex. 2009); City of San Antonio v. Caruso, 350 S.W.3d 247, 250 (Tex. App.—San Antonio

2011, pet. denied).

In 2005, the Texas Legislature passed HB 2039, enacting sections 271.151-.160 of the

Texas Local Government Code. Act of May 23, 2005, 79th Leg., R.S., ch. 604, § 1, 2005 Tex.

Gen. Laws 1548 (codified at TEX. LOC. GOV’T CODE ANN. § 271.151-.160 (West 2005); Tooke v.

City of Mexia, 197 S.W.3d 325, 342 (Tex. 2006). These provisions were enacted to waive local

governmental entities’ immunity from suit for breach of contract under certain circumstances.

-7-

04-11-00768-CV

See id. Valemas contends its suit, which is based on the pass through agreement with Payne,

falls within these provisions. The City counters that it does not fall within the statute because

waiver based on a pass through agreement was not stated in clear and unambiguous language.

The resolution of this issue requires this court to interpret section 271.152 and the companion

provisions thereto.

It is well-settled that statutory construction is a question of law. City of Rockwall v.

Hughes, 246 S.W.3d 621, 625 (Tex. 2008); Caruso, 350 S.W.3d at 250. Our objective in

interpreting any statute is to determine the Legislature’s intent. Hughes, 246 S.W.3d at 625;

Mid-Century Ins. Co. v. Ademaj, 243 S.W.3d 618, 621 (Tex. 2007). We look to the plain

meaning of the statute, construing it as a whole to give effect to every part, unless such a

construction would lead to absurd or nonsensical results. Hughes, 246 S.W.3d at 625-26;

Ademaj, 243 S.W.3d at 621. We may consider the object of the statute, legislative history, and

the consequences of a proposed construction. TEX. GOV’T CODE ANN. § 311.023(1), (3), (5)

(West 2005); see Caruso, 350 S.W.3d at 250; First-Citizens Bank & Trust Co. v. Great Austin

Area Telecomm. Network, 318 S.W.3d 560, 567 (Tex. App.—Austin 2010, no pet.). We may

consider these things whether or not the statute is ambiguous. TEX. GOV’T CODE ANN.

§ 311.023. With these principles in mind, we turn to section 271.152 to determine whether the

Legislature waived immunity for breach of contract actions brought as a pass through claim.

The relevant statute in this appeal, section 271.152, sets forth under what circumstances

local governmental entities waive immunity in breach of contract actions:

A local governmental entity that is authorized by statute or the constitution to

enter into a contract and that enters into a contract subject to this subchapter

waives sovereign immunity to suit for the purpose of adjudicating a claim for

breach of contract, subject to the terms and conditions of this subchapter.

-8-

04-11-00768-CV

TEX. LOC. GOV’T CODE ANN. § 271.152. Although we have found no cases directly addressing

this provision’s applicability to pass through claims, the Austin Court of Appeals has considered

the statute with regard to assignments, and we find its analysis of the statute compelling, despite

the City’s protestations to the contrary, and adopt it here. First-Citizens Bank & Trust Co. v.

Great Austin Area Telecomm. Network, 318 S.W.3d at 567-69; see also Galveston Indep. Sch.

Dist. v. Clear Lake Rehab. Hosp., L.L.C., 324 S.W.3d 802, 810 (Tex. App.—Houston [14th

Dist.] 2010, no pet.) (citing First-Citizens Bank & Trust Co. to support holding that when

governmental entity and contracting party enter into contract under subchapter I and denominate

third-party beneficiary to contract, third-party beneficiary’s claim falls within waiver of

immunity authorized by section 271.152).

We begin with the plain language of section 271.152. Reviewing this language, we hold

the waiver set forth in section 271.152 is not limited to suits brought by contract signatories for

claims belonging solely to the signatories. Rather, “section 271.152 waives immunity for a class

of suits–suits for the purpose of adjudicating a claim for breach of a contract subject to

subchapter I.” See First-Citizens Bank & Trust Co., 318 S.W.3d at 567. In other words, section

271.152 waives immunity when a breach of contract action is brought against a governmental

entity based on a contract subject to subchapter I. Id. Therefore, we must review the entirety of

subchapter I to determine if the waiver stated in section 271.152 was intended to apply to pass

through claims. Id. at 567-68.

As noted above, subchapter I includes sections 271.151 through 271.160, which:

• define the terms used in the subchapter, see TEX. LOC. GOV’T CODE ANN.

§ 271.151;

• provide for waiver, see id. § 271.152;

• limit damages that may be awarded, see id § 271.153;

-9-

04-11-00768-CV

• provide that adjudication procedures, e.g., notice requirements or alternate

dispute resolution requirements, stated or incorporated in a contract are

enforceable, see id § 271.154;

• provide that other available contract defenses are not waived, see id

§ 271.155;

• provide there is no waiver of immunity to suit in federal court, see id

§ 271.156;

• provide there is no waiver of immunity to suits for a negligent or intentional

tort, see id § 271.157;

• note the subchapter is not a grant of immunity to suit to a local governmental

entity, see id § 271.158;

• prohibit recovery of attorney’s fees absent a contractual provision allowing

recovery of such fees to the prevailing party, see id § 271.159; and

• note that a contract entered into by a local government entity is not a joint

enterprise for purposes of liability, see id § 271.160.

We find nothing in any of these sections to show the Legislature intended to exclude pass

through claims from the waiver provision in section 271.152. See id. §§ 271.152-.160.

Moreover, when we review the legislative history, it strongly suggests the Texas

Legislature intended to enact a broad waiver for local governmental entities in the contractual

setting. The Texas Supreme Court agrees. Quoting the bill analysis of the House Committee on

Civil Practices, the supreme court stated, “by enacting section 271.152, the Legislature intended

to loosen the immunity bar so ‘that all local government entities that have been given or are

given the statutory authority to enter into contracts shall not be immune from suits arising from

those contracts.’” Ben Bolt-Palito Blanco Consol. Indep. Sch. Dist. v. Tex. Political

Subdivisions Prop./Cas. Joint Self-Ins. Fund, 212 S.W.3d 320, 327 (Tex. 2006) (quoting House

Comm. on Civil Practices, Bill Analysis, Tex. H.B. 2039, 79th Leg., R.S. (2005)). Thus, the

Legislature clearly intended the waiver to apply not only to signatories, not only to claims based

- 10 -

04-11-00768-CV

on the contracts themselves, but to claims “arising from” those contracts. Payne’s pass through

claim, as asserted by Valemas, clearly “arises from” the contract between the City and Valemas.

Further, the bill analysis suggests the enactment of section 271.152 was based on the

Legislature’s recognition of the inherent unfairness in allowing governmental entities to enter

into contracts, but then avoid its obligations under such contracts by claiming immunity. See

First-Citizens Bank & Trust Co., 318 S.W.3d at 568; see House Comm. on Civil Practices, Bill

Analysis, Tex. H.B. 2039, 79th Leg., R.S. (2005). As noted by supporters of the bill, because of

the threat of immunity, many qualified contractors declined to bid on local government projects,

considering it too risky. House Comm. on Civil Practices, Bill Analysis, Tex. H.B. 2039, 79th

Leg., R.S. (2005). This was especially true for small businesses which generally did not bid at

all. Id. The bill was enacted to “encourage a broader, more qualified, and more diverse range of

bidders for local government contracts.” First-Citizens Bank & Trust Co., 318 S.W.3d at 568

(citing House Comm. on Civil Practices, Bill Analysis, Tex. H.B. 2039, 79th Leg., R.S. (2005).

In the context of this case, the “inherent unfairness” is obvious should the statute be

interpreted as to permit immunity for pass through claims. It is common knowledge that when a

local governmental entity enters into a contract for extensive renovations or construction, the

general contractor with whom it contracts will subcontract with others. If a local governmental

entity is immune from pass through claims, requiring subcontractors to sue the general contractor

to recover rather than rely on the general contractor to pursue such claims, smaller

subcontractors will be less likely to risk entering such agreements–knowing that in the event the

contractor is unable to pay because of non-payment by the governmental entity they will be

forced to engage in expensive litigation, the cost of which they may not be able to bear, or

simply write the matter off as a loss. This puts subcontractors into the same position as

- 11 -

04-11-00768-CV

contractors, and as recognized by the supporters of the bill that proposed section 271.152 in the

context of general contractors, will make many highly qualified subcontractors, especially small

businesses, hesitant to enter into such contracts. This will discourage and disadvantage a diverse

range of bidding subcontractors and limit the choices of general contractors in direct opposition

to what the bill was intended to do.

Accordingly, we hold that just as it is inconsistent with the purpose of section 271.152 to

construe it to deny waiver to assignees of those who enter into contracts subject to subchapter I,

so is it inconsistent to deny waiver to pass through claims brought by a contractor against a

local governmental entity on a subcontractor’s behalf. To hold otherwise would subject

subcontractors to the same risk of non-redressable breach the statue sought to eliminate, resulting

in subcontractors suffering the same problems once suffered by general contractors prior to the

enactment of section 271.152.

Our interpretation does not, as the City suggests, extend liability beyond what the statute

contemplates. Section 271.153 defines the limits of liability and specifically provides that

recovery under subchapter I is limited to the balance due and owed under the contract, any

amount owed for change orders or additional work the contractor is directed to perform by the

local governmental entity, and interest as allowed by law. TEX. LOC. GOV’T CODE ANN.

§ 271.153. Thus, Valemas can only recover what is owed on the contract–the fact that any

recovery may be payable to Payne does not extend the City’s liability. This is borne out by a

close review of Valemas’s pleadings in which it seeks recovery based on its contract with the

City.

Based on the foregoing, we hold the trial court did not err in denying the City’s plea to

the jurisdiction based on an absence of immunity. The doctrine of governmental immunity does

- 12 -

04-11-00768-CV

not preclude Valemas from asserting a pass through claim on Payne’s behalf. We therefore

overrule the City’s first issue.

Sovereign Immunity & Anti-Assignment Clauses

In the alternative, the City contends that even if this court determines there is waiver of

immunity for the pass through claims, the anti-assignment clause in the City’s contract precludes

Valemas from asserting Payne’s claims. Although the City did not mention the concept of

standing, we find that given this issue was raised in the plea to the jurisdiction, it appears the

City is arguing Valemas lacks standing to assert Payne’s claims based on the anti-assignment

clause. Assuming without deciding that Valemas’s suit even involves an assignment, we

disagree with the City’s argument.

Standard of Review

Standing is a prerequisite to subject matter jurisdiction, and subject matter jurisdiction is

essential to a court’s power to decide a case. Bland Indep. Sch. Dist. v. Blue, 34 S.W.3d 547,

553-54 (Tex. 2000). A plaintiff may not maintain a cause of action unless he has standing to

litigate the matters that are the basis of the lawsuit. RDG P’ship v. Long, 350 S.W.3d 262, 271

(Tex. App.—San Antonio 2011, no pet.). A claim that a party lacks standing may be raised by a

plea to the jurisdiction. Bland Indep. Sch. Dist., 34 S.W.3d at 553-54. A party’s standing to see

relief is a question of law we review de novo. Tex. Dep’t of Transp. v. City of Sunset Valley, 146

S.W.3d 637, 646 (Tex. 2004); Long, 350 S.W.3d at 271.

Application

In their contract, the City and Valemas agreed that:

[Valemas] shall not assign, transfer, convey, sub-let or otherwise dispose of this

contract, or any portion thereof, or any right, title, or interest in, to or under the

same, without previous consent in writing of the City.

- 13 -

04-11-00768-CV

The City contends this anti-assignment clause precluded Valemas from asserting a breach of

contract claim on behalf of Payne, i.e., that by suing the City to recover for Payne, Valemas had

assigned Payne rights under the contract. However, Texas law distinguishes between a

contracting party’s ability to assign rights under a contract containing an anti-assignment clause

and that same party’s ability to assign causes of action arising from the breach of that contract.

E.g., Dearborn Stove Co. v. Caples, 149 Tex. 563, 236 S.W.2d 486-490 (1951) (holding fact that

lease was not assignable did not prevent valid assignment of overcharge claim arising from

lease); City of Brownsville ex. rel. Pub. Utils. Bd. v. AEP Tex. Cent. Co., 348 S.W.3d 348, 358

(Tex. App.—Dallas 2011, no pet.) (holding anti-assignment clause that precluded assignment of

rights and duties under contract did not preclude assignment of cause of action for breach of the

contract); Pagosa Oil & Gas, L.L.C. v. Marrs and Smith P’ship, 323 S.W.3d 203, 211–12 (Tex.

App.—El Paso 2010, pet. denied) (holding mineral lessee was not precluded from assigning

cause of action for breach of lease to another despite language in assignment clause requiring

consent to assignment); Lindsay ex rel. Lindsay v. S. San Antonio Indep. Sch. Dist., 983 S.W.2d

778, 779-80 (Tex. App.—San Antonio 1998, no pet.) (recognizing assignability of decedent’s

cause of action for alleged breach of employment contract despite estate’s inability to assign

contract itself). Absent specific circumstances not present in this case, causes of action in Texas

are freely assignable. See State Farm Fire & Cas. Co., v. Gandy, 925 S.W.2d 696, 705-07 (Tex.

1996).

In the agreement between the City and Valemas, Valemas agreed not to “assign, transfer,

convey, sub-let or otherwise dispose of this contract, or any portion thereof, or any right, title, or

interest in, to or under the same” without the City’s consent. We look to the plain wording of the

anti-assignment clause to determine whether it prohibited Valemas from assigning its breach of

- 14 -

04-11-00768-CV

contract action to Payne. See AEP Tex. Cent. Co., 348 S.W.3d at 358; Pagosa Oil & Gas, 323

S.W.3d at 212. We hold it does not. The clause merely states Valemas’s rights and interests

under the agreement were not assignable without written consent of the City. The provision does

not indicate an intent to limit Valemas’s ability to assign causes of action arising from an alleged

breach of the contract. Because Valemas maintained its common law rights to assign its causes

of action arising from the contract, it would have standing to assert Payne’s claims by virtue of

the assignment. See id.

This anti-assignment clause in this case is similar to the one reviewed in AEP Tex. Centr.

Co. In that case, AEP Texas Central Company (“AEP”), the appellee, raised a cross-point

contending the City of Brownsville lacked standing to assert the causes of action at issue in the

case based on an anti-assignment clause in the purchase and sale agreement between AEP and

OMPA. AEP Tex. Cent. Co., 348 S.W.3d at 358. The anti-assignment clause stated: “The rights

under this Agreement shall not be assignable or transferable nor the duties delegable by either

Party without the prior written consent of the other Party, which consent may be granted or

withheld in such other Party’s sole discretion.” Id. The Dallas Court of Appeals held this clause

did not preclude OMPA from assigning its breach of contract action against AEP to the City. Id.

Rather, the clause merely precluded the assignment of rights and duties under the contract. Id.

As noted above, the same is true with regard to the anti-assignment clause in the contract

between the City and Valemas. The contract merely precludes Valemas from assigning its rights

and interests under the contract to another without the City’s consent. A breach of contract claim

is not a right or interest identified in the contract. Accordingly, we resolve this issue against the

City.

- 15 -

04-11-00768-CV

CONCLUSION

Based on our analysis of the issues and our interpretation of the law, the trial court did

not err in denying the City’s plea to the jurisdiction. The City is not entitled to immunity from

Valemas’s breach of contract action and Valemas is not precluded from asserting the breach of

contract claim by the anti-assignment clause in the contract. We therefore affirm the trial court’s

judgment.

Marialyn Barnard, Justice

- 16 -

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.