Opinion

Morton International, Inc. v. A.E. Staley Manufacturing Co.

  • 343 F.3d 669
  • 57 Fed. R. Serv. 3d 251
  • 33 Envtl. L. Rep. (Envtl. Law Inst.) 20270
  • 57 ERC (BNA) 1129
  • 2003 U.S. App. LEXIS 19152
Court
Court of Appeals for the Third Circuit
Filed
Sep 16, 2003
Status
Published
Author
Fuentes
On the bench
Fuentes, Smith, Greenberg
Cited by
1 cases
Authority
More cited than 44.7%

The opinion

Opinions of the United

2003 Decisions States Court of Appeals

for the Third Circuit

9-16-2003

Morton Intl Inc v. AE Staley Mfg Co

Precedential or Non-Precedential: Precedential

Docket No. 01-4259

Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2003

Recommended Citation

"Morton Intl Inc v. AE Staley Mfg Co" (2003). 2003 Decisions. Paper 233.

http://digitalcommons.law.villanova.edu/thirdcircuit_2003/233

This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova

University School of Law Digital Repository. It has been accepted for inclusion in 2003 Decisions by an authorized administrator of Villanova

University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.

PRECEDENTIAL

Filed September 16, 2003

UNITED STATES COURT OF APPEALS

FOR THE THIRD CIRCUIT

No. 01-4259

MORTON INTERNATIONAL, INC.; VELSICOL CHEMICAL

CORPORATION; NWI LAND MANAGEMENT CO.; FRUIT

OF THE LOOM, INCORPORATED,

v.

A.E. STALEY MANUFACTURING COMPANY; AIRCO

INDUSTRIAL GASES, a/k/a AIR REDUCTION COMPANY,

INC., f/k/a AIRCO, INC.; ALLIED CHEMICAL

CORPORATION; ALUMINUM COMPANY OF AMERICA

(ALCOA); AMERICAN CYANAMID COMPANY; ARMSTRONG

WORLD INDUSTRIES, INC.; ARSYNCO, INC.; BAILEY

CONTROLS CO., f/k/a BAILEY METER COMPANY;

BECTON-DICKINSON & CO., INC.; BELFORT

INSTRUMENT CO.; BELMONT METALS, INC., f/k/a

BELMONT SMELTING & REFINING WORKS, INC.;

CANADIAN GYPSUM COMPANY, LTD.; CANRAD, INC.,

(c/o Canrad Precision Industries, Inc.); CIBA-GEIGY

CORPORATION; COLUMBIA UNIVERSITY; CONOPCO,

INC., (Cheeseborough Ponds U.S.A. Co. Division); COSAN

CHEMICAL CORP.; CROUSE HINDS SEPCO

CORPORATION, f/k/a CONNECTICUT INTERNATIONAL;

CROWN ZELLERBACH CORP., a/k/a JAMES RIVER

CORPORATION OF NEVADA; CURTISS-WRIGHT; D.F.

GOLDSMITH CHEMICAL & METAL CORPORATION; DAY

& BALDWIN, f/k/a C-P PHARMACEUTICALS, INC.;

DIAMOND SHAMROCK CHEMICALS COMPANY, a/k/a

OCCIDENTAL ELECTROCHEMICALS CORPORATION;

DOW-CORNING CORPORATION; DURA ELECTRIC LAMP

CO., INC.; DURACELL, INC., (as successor to Mallory

Battery Co., Inc.); E.I. DUPONT DE NEMOURS & CO.;

2

EASTERN SMELTING & REFINING CORP.; EAGLEHARD

MINERALS AND CHEMICALS CORPORATION;

ENVIRONMENTAL CONTROL SYSTEMS; EXXON

CORPORATION; FEDERAL AVIATION ADMINISTRATION;

GARFIELD BARING CORPORATION, f/k/a GARFIELD

SMELTING & REFINING CO.; GENERAL ELECTRIC

COMPANY; GENERAL COLOR CO., INC.; GENERAL

SIGNAL CORPORATION; GILMARTIN INSTRUMENT CO.;

HARTFORD ELECTRIC SUPPLY COMPANY, INC.; HENKEL

CORPORATION; HOFFMAN-LAROUCHE, INC.; HUDSAR,

INCORPORATED; INMAR ASSOCIATES, INC.; INMAR

REALTY, INC.; INTERNATIONAL NICKEL, INC.; J.M. NEY

COMPANY; K.E.M. CHEMICAL COMPANY; KOPPERS,

a/k/a BEAZER EAST, INC.; MAGNESIUM ELEKTRON,

INC.; MARVIN H. MAHAN; MALLINCKRODT CHEMICAL,

INC.; MARISOL, INC.; MERCK & CO., INC.; MERCURY

ENTERPRISE, INC., f/k/a MERCURY INSTRUMENT

SERVICE; MINNESOTA MINING AND MANUFACTURING

COMPANY; MOBIL OIL CORPORATION; MT. UNION

COLLEGE; M.W. KELLOGG CO.; NATIONAL LEAD

COMPANY, (Goldsmith Brothers Division); NEPERA, INC.;

NEW ENGLAND LAMINATES CO., INC.; NEW JERSEY

INSTITUTE OF TECHNOLOGY, f/k/a NEWARK COLLEGE

OF ENGINEERING; NEW YORK CITY TRANSIT

AUTHORITY; NORTHEAST CHEMICAL CO., (Northeast

Chemical & Industrial Supply Co., Inc.); OCCIDENTAL

CHEMICAL CORPORATION, (as successor to Diamond

Shamrock Chemical Co., formerly Diamond Shamrock

Corporation); OLIN CORPORATION, f/k/a OLIN

MATHIESON CHEMICAL CORPORATION; PEASE &

CURREN, INC.; PFIZER, INC.; PSG INDUSTRIES, INC.,

f/k/a PHILADELPHIA SCIENTIFIC GLASS, INC.; PHILLIPS

& JACOBS, INC.; PUBLIC SERVICE ELECTRIC & GAS,

(PSE&G); PURE LAB OF AMERICA; RANDOLPH

PRODUCTS COMPANY; RAY-O-VAC DIVISION OF ESB,

INC., (ESB, INC.); REDLAND MINERALS LIMITED;

RHONE-POULENC, INC., f/k/a ALCOLAC CHEMICAL

COMPANY/GUARD CHEMICAL COMPANY; ROYCE

ASSOCIATES, f/k/a ROYCE CHEMICAL; RUTGERS, THE

STATE UNIVERSITY; SCIENTIFIC CHEMICAL

PROCESSING, INC.; SCIENTIFIC CHEMICAL TREATMENT

CO., INC.; SCIENTIFIC, INC.; SEAFORTH MINERAL &

ORE CO.; SPARROW REALTY, INC.; STATE UNIVERSITY

3

OF NEW YORK AT BUFFALO, (S.U.N.Y.A.B.);

SYLVANIA/GTE; TENNECO, INC.; TRANSTECH

INDUSTRIES, INC.; UEHLING INSTRUMENT CO., INC.;

UNION CARBIDE CORPORATION; UNIVERSAL OIL

PRODUCTS CO.; UNIVERSITY OF ILLINOIS; UNIVERSITY

OF MINNESOTA; VAR-LAC-OID CHEMICAL COMPANY,

INC.; W.A. BAUM CO., INC.; WAGNER ELECTRIC

COMPANY; WESTERN MICHIGAN UNIVERSITY;

WESTINGHOUSE ELECTRIC CORPORATION; JOHN DOE

1-100; GEROLD C. THOMPSON, ESQ.; GEORGE VAN

CLEVE, ESQ.; THE CONNECTICUT LIGHT AND POWER

COMPANY, f/k/a HARTFORD ELECTRIC LIGHT

COMPANY; GTE OPERATIONS SUPPORT INCORPORATED;

ALLIEDSIGNAL, INC.; BEAZER EAST, INC.; JERSEY CITY

MANAGEMENT, INC.; MICHAEL RODBURG, Site

Defendants Liasion Counsel; ASHLAND CHEMICAL CO., a

Division of Ashland Oil, Inc.; BASF CORPORATION, and

as successor to Wyandotte Chemical Corp., a/k/a

INMONT CORPORATION; FMC CORPORATION

Morton International, Inc.,

Appellant

On Appeal from the United States District Court

for the District of New Jersey

District Court Judge: Honorable Katherine S. Hayden

(D.C. No. 96-cv-03609)

Argued on July 7, 2003

Before: FUENTES, SMITH, and GREENBERG,

Circuit Judges.

(Opinion Filed: September 16, 2003)

4

Samuel P. Moulthrop

Riker, Danzig, Scherer, Hyland

& Peretti

One Speedwell Avenue

Headquarters Plaza

Morristown, NJ 07962

Joseph S. Justice

Thomas T. Terp

Taft, Stettinius & Hollister

425 Walnut Street

1800 Firstar Tower

Cincinnati, OH 45202

John G. Harkins, Jr. [ARGUED]

Steven A. Reed

Harkins Cunningham

2005 Market Street

2800 One Commerce Square

Philadelphia, PA 19103

Laurence S. Kirsch

Jonathan R. Stone

Frederick R. Anderson

Cadwalader, Wickersham & Taft

1210 F. Street, N.W.

Suite 1100

Washington, D.C. 20004

Attorneys for Appellant

David J. D’Aloia [ARGUED]

Robert B. Nussbaum

Michelle V. Fleishman

Saiber, Schlesinger, Satz &

Goldstein

One Gateway Center

Suite 1300

Newark, NJ 07102

Attorneys for Appellee

Tenneco, Inc.

5

OPINION OF THE COURT

FUENTES, Circuit Judge:

This appeal challenges the grant of summary judgment to

one defendant, Tennessee Gas Pipeline Co. (“Tenneco”), in

an action seeking contribution toward environmental

cleanup costs. These costs have been or will be incurred by

plaintiff-appellant Morton International, Inc. (“Morton”) in

regard to the Ventron/Velsicol Superfund Site in Wood

Ridge, New Jersey (the “Site” or “plant”). Morton and three

other plaintiffs, who are not parties to this appeal, sought

contribution under the Comprehensive Environmental

Response, Compensation, and Liability Act of 1980

(“CERCLA”), 42 U.S.C. § 9601 et seq., the New Jersey Spill

Compensation and Control Act (“Spill Act”), N.J.S.A. 58:10-

23.11 et seq., and common law.

Morton argues that Tenneco should be responsible,

under the “arranged for” provision of CERCLA Section

107(a)(3), for some of the cleanup costs because it arranged

for the processing of mercury at the facility for many years,

resulting in the release of hazardous waste into the

environment. Because we agree with Morton that material

factual issues remain with respect to whether Tenneco (1)

owned or possessed prime virgin mercury, (2) had

knowledge of the environmental hazards of mercury

processing at the plant, (3) had control over the hazardous

waste disposal practices at the plant, and (4) shipped its

own “dirty mercury” to the plant, we will remand for further

proceedings consistent with this opinion.

I. Background

A. Factual

The parties dispute many of the facts central to this

appeal, but the following facts are undisputed. From 1929

to 1974, a mercury processing plant was operated at the

Site. The plant was the largest domestic producer of

intermediate inorganic mercury compounds, including red

6

and yellow oxides of mercury (“ROM” and “YOM”). The

compounds were formulated, at least in part, using prime

virgin mercury (“PVM”). In addition, the plant cleaned

mercury that had been contaminated (“dirty mercury”) and

then converted it into intermediate compounds for some of

its customers. The plant released harmful waste into the

environment for decades.

The plant was owned by F.W. Berk & Company from

1929 to 1960. It was transferred to Wood Ridge Chemical

Corporation (its parent company is Velsicol Chemical

Corporation) in 1960, and then again to Ventron

Corporation in 1968. The plant was closed in 1974.

Sometime thereafter, Ventron merged into Thiokol, which

then merged into Morton-Thiokol, which eventually became

Morton.

The parties agree that Tenneco purchased ROM and YOM

from the plant from 1963 until the early 1970’s. The parties

disagree, however, as to the nature of the transactions

between Tenneco and the plant, Tenneco’s knowledge of

waste disposal by the plant, and whether Tenneco shipped

“dirty mercury” to the plant for processing.

B. Prior Litigation

In the 1970’s, the New Jersey Department of

Environmental Protection commenced an action against

Ventron, Velsicol, and other parties for cleanup and

removal of mercury at the Site. Eventually, Velsicol and

Morton were held strictly liable, jointly and severally, for

the cleanup of the Site, and that judgment was upheld

following numerous appeals and successive litigation. See

Morton International, Inc. v. General Acc. Ins. Co. of America,

629 A.2d 831, 880 (N.J. 1993) (concluding that Morton’s

predecessors had intentionally discharged pollutants over a

long period of time); State Department of Environmental

Protection v. Ventron Corp., 468 A.2d 150, 161-62 (N.J.

1983) (finding defendants violated statute prohibiting the

discharge of detrimental material into waters by

intentionally permitting mercury-laden effluent to escape

onto lands surrounding creek). After the enactment of

CERCLA in 1980, and the listing of the Site on the National

7

Priorities List, Morton, as the current owner of the Site,

Velsicol, and various other entities were required to perform

a remedial investigation/feasibility study for the Site. Since

then, Morton has been funding the environmental efforts

under various judicial orders.

C. The present litigation

Morton filed this action in 1996 seeking contribution

from Tenneco and numerous other defendants under

CERCLA, 42 U.S.C. § 9601 et seq., the Resource

Conservation and Recovery Act (“RCRA”), Pub. L. No. 94-

580, § 1, 90 Stat. 2795 (1976), as amended 42 U.S.C.

§ 6901 et seq., the Spill Act, N.J.S.A. 58:10-23.11 et seq.,

and common law.1 Morton argues that the “conversion” or

“toll” agreements, whereby the plant processed the

customers’ PVM into ROM and YOM, and the “dirty

mercury” processing agreements render the customer-

defendants subject to CERCLA liability as “arrangers”

under Section 107(a)(3), 42 U.S.C. § 9607(a)(3). Morton is

trying to recover from other allegedly responsible parties

some of the costs it has incurred and will continue to incur

to clean up the Site.

Tenneco and the other defendants refuse to share

responsibility for the cleanup costs. The defendants argue

that Morton’s characterization of the PVM transactions is

inaccurate; these transactions were nothing more than

straight purchases of finished products (ROM and YOM),

which do not expose them to CERCLA liability. On April 11,

2000, Tenneco and the other defendants moved for

summary judgment in an omnibus motion. The District

Court denied their motion with respect to the CERCLA,

Spill Act, and common law claims because of the varying,

complex fact patterns and material factual disputes with

1. Velsicol and its related entities were plaintiffs below, but have

withdrawn their appeal of the District Court’s order. Because they are no

longer parties to this appeal, we refer only to Morton’s pursuit of these

causes of action against the defendants.

8

respect to each defendant. The District Court granted the

defendants’ motion to dismiss Morton’s RCRA claim.2

Several months later, Tenneco filed a renewed motion for

summary judgment — this time on its own behalf. Morton

responded by incorporating by reference the briefings and

evidence it had submitted in response to the omnibus

summary judgment motion. After hearing oral argument on

Tenneco’s individual motion, the District Court ruled from

the bench and granted summary judgment to Tenneco on

all claims.

II. Jurisdiction

The District Court had jurisdiction over Morton’s federal

claims pursuant to 28 U.S.C. § 1331 and 42 U.S.C. § 9613.

The District Court exercised pendent jurisdiction over

Morton’s state law claim pursuant to 28 U.S.C. § 1367. We

have jurisdiction to hear this appeal from the final order of

the District Court pursuant to 28 U.S.C. § 1291.3

III. Analysis

The District Court has asked us to “definitively address”

the standard for “arranger liability” under CERCLA Section

107(a)(3) in this Circuit in order to properly resolve

2. The District Court’s grant of judgment to the defendants on Morton’s

RCRA claim is not before us on appeal.

3. The District Court granted the parties’ joint motion to certify the

dismissal of Tenneco from this action as a final, appealable order

pursuant to Federal Rule of Civil Procedure 54(b). Although the District

Court’s July 17, 2001 order disposed of Morton’s claims only against

Tenneco, leaving in place the claims against the other defendants, the

Court entered a final judgment with respect to Tenneco because: (a)

Morton’s claims against Tenneco are separable from the remaining

claims; (b) this Court will not be required to decide the same issues even

if there are subsequent appeals by other defendants; (c) the standard for

“arranger liability” under CERCLA has not been “definitively addressed”

by this Court; (d) the prospects for final resolution of Morton’s claims

will be improved by a ruling on the standard; and (e) certification of the

judgment in favor of Tenneco will not prejudice the remaining

defendants. (App. at 4-5).

9

Morton’s contribution claims against Tenneco and the other

defendants in this case.4

A. CERCLA “Arranger Liability” Standard

Congress enacted CERCLA in 1980 “in response to the

serious environmental and health risks posed by industrial

pollution.” United States v. Bestfoods, 524 U.S. 51, 55

(1998) (citation omitted).

As its name implies, CERCLA is a comprehensive

statute that grants the President broad power to

command government agencies and private parties to

clean up hazardous waste sites. Sections 104 and 106

provide the framework for federal abatement and

enforcement actions that the President, the EPA as his

delegated agent, or the Attorney General initiates. 42

U.S.C. § 9604, 9606. These actions typically require

private parties to incur substantial costs in removing

hazardous wastes and responding to hazardous

conditions. Section 107 sets forth the scope of the

liabilities that may be imposed on private parties and

the defenses that they may assert. 42 U.S.C. § 9607.

Key Tronic Corp. v. United States, 511 U.S. 809, 814 (1994).

In 1986, Congress amended CERCLA with the Superfund

Amendments and Reauthorization Act (“SARA”) and

included a provision — Section 113 — that expressly

created a cause of action for contribution. See 42 U.S.C.

4. We once came close to stating a standard for “arranger liability” under

CERCLA. In FMC Corporation v. United States Dep’t of Commerce, No. 92-

1945, 1993 WL 489133, at *11 (3d Cir. 1993), this Court adopted the

test for “arranger liability” articulated by the Eighth Circuit in United

States v. Aceto Agricultural Chems. Corp., 872 F.2d 1373, 1379-82 (8th

Cir. 1989). That decision was vacated, however, after the Court granted

rehearing en banc. See FMC Corp., 10 F.3d 1003 (3d Cir. 1994). In the

superseding en banc decision, the Court affirmed the district court’s

judgment holding the government liable as an arranger without

discussion because the Court was “equally divided on this point.” FMC.

Corp., 29 F.3d 833, 846 (3d Cir. 1994). Accordingly, this Court has

neither ruled on the validity of the Aceto test for “arranger liability,” nor

articulated its own test up to this point. See United States v. Occidental

Chem. Corp., 200 F.3d 143, 145 (3d Cir. 1999).

10

§ 9613(f). “A principal goal of Section 113 was to ‘clarif[y]

and confirm[ ] the right of a person held jointly and

severally liable under CERCLA to seek contribution from

other potentially liable parties, when the person believes

that it has assumed a share of the cleanup or cost that

may be greater than its equitable share under the

circumstances.’ ” New Castle County v. Halliburton NUS

Corp., 111 F.3d 1116, 1122 (3d Cir. 1997) (quoting

H.R.Rep. No. 99-253(I), at 79 (1985), reprinted in 1986

U.S.C.C.A.N. 2835, 2861; H.R. Conf. Rep. No. 99-962, at

221 (1986), reprinted in 1986 U.S.C.C.A.N. 3276, 3314).

Accordingly, CERCLA and SARA together create two legal

actions by which parties that have incurred costs

associated with cleanups can recover some or all of those

costs: (1) Section 107 cost recovery actions; and (2) Section

113 contribution actions. Section 113, the cause of action

Morton is pursuing against Tenneco, provides that “[a]ny

person may seek contribution from any other person who is

liable or potentially liable under [Section 107], during or

following any civil action under [Section 107]. . . .” 42

U.S.C. § 9613(f)(1).

Section 107 defines those who are “potentially

responsible persons” (“PRP’s”) as: (1) the current owner or

operator of a facility; (2) any person who owned or operated

the facility at the time of the disposal of any hazardous

substances; (3) “any person who by contract, agreement, or

otherwise arranged for disposal or treatment . . . of

hazardous substances owned or possessed by such person,

by any other party . . . at any facility;” and (4) any person

who accepts or accepted hazardous substances for

transport to sites selected by such person, “from which

there is a release, or a threatened release which causes the

incurrence of response costs . . . .” 42 U.S.C. § 9607(a).

Congress did not define the term “arranged for” in the

statute. Thus, our interpretation of the term begins with

the plain meaning. To repeat, Section 107(a)(3) holds

responsible those who “by contract, agreement, or

otherwise arranged for” the disposal or treatment of

hazardous substances. The verb “arrange” is defined (as

relevant to its usage in this section) as “to make

preparations for.” See Webster’s Third New International

11

Dictionary 120 (1993). The dictionary definition of “arrange”

does not shed much light on the proper scope of liability

under this section. However, by including “or otherwise”

after “by contract [or] agreement,” Congress expanded the

means by which a party could possibly “arrange for” the

treatment or disposal of hazardous substances in defining

this category of PRP. We think that this expansive list of

means indicates that Congress intended this category of

PRP to be broadly construed.

Our view that “arranged for” is to be broadly construed is

consistent with Congress’s overall purpose in enacting

CERCLA. Two of the main purposes of CERCLA are “prompt

cleanup of hazardous waste sites and imposition of all

cleanup costs on the responsible party.” General Electric Co.

v. Litton Ind. Auto. Sys., Inc., 920 F.2d 1415, 1422 (8th Cir.

1990), cert. denied, 499 U.S. 937 (1991), abrogated on other

grounds, Key Tronic, 511 U.S. at 814, 819. In enacting

CERCLA, Congress intended that “those actually

‘responsible for any damage, environmental harm, or injury

from chemical poisons [may be tagged with] the cost of their

actions.’ ” Bestfoods, 524 U.S. at 55-56 (quotations and

citations omitted). “The remedy that Congress felt it needed

in CERCLA is sweeping: everyone who is potentially

responsible for hazardous-waste contamination may be

forced to contribute to the costs of cleanup.” Pennsylvania

v. Union Gas Co., 491 U.S. 1, 21 (1989) (plurality op. of

Brennan, J.) (emphasis in original), overruled on other

grounds, Seminole Tribe of Florida v. Florida, 517 U.S. 44

(1996); see also Lansford-Coaldale Joint Water Auth. v.

Tonolli Corp., 4 F.3d 1209, 1221 (3d Cir. 1993).

Accordingly, we interpret the term “arranger liability”

broadly in keeping with the plain meaning of Section

107(a)(3) and the remedial statutory scheme of CERCLA.

Almost all of our sister circuit courts have adopted a

standard for “arranger liability,” but the standards adopted

vary. See Geraghty and Miller, Inc. v. Conoco Inc., 234 F.3d

917, 929 (5th Cir. 2001), cert. denied, 533 U.S. 950 (2001);

Freeman v. Glaxo Wellcome, Inc., 189 F.3d 160, 164 (2d Cir.

1999); Pneumo Abex Corp. v. High Point, Thomasville and

Denton R.R. Co., 142 F.3d 769, 775 (4th Cir. 1998); United

States v. Cello-Foil Products, Inc., 100 F.3d 1227, 1231-32

12

(6th Cir. 1996); South Florida Water Management District v.

Montalvo, 84 F.3d 402, 407 (11th Cir. 1996); Amcast

Industrial Corporation v. Detrex Corp., 2 F.3d 746, 751 (7th

Cir. 1993); Jones-Hamilton Co. v. Beazer Materials & Servs.,

Inc., 973 F.2d 688, 695 (9th Cir. 1992); United States v.

Aceto Agricultural Chems. Corp., 872 F.2d 1373, 1381-82

(8th Cir. 1989).

Our review of these decisions leads us to conclude that

the courts are virtually unanimous with respect to two

points. First, the determination of “arranger liability” is a

fact-sensitive inquiry that requires a multi-factor analysis.

Second, courts must look beyond the defendant’s

characterization of the transaction at issue in order to

determine whether the transaction, in fact, involves an

arrangement for the disposal or treatment of a hazardous

substance. We absolutely agree with both of these points.

However, there is not as much agreement among our

sister circuits as to which factors must be considered — or

what priority they should receive — in conducting the

multi-factor “arranger liability” analysis. In fact, some

courts require a showing of intent to dispose of or treat

hazardous substances, see Cello-Foil, 100 F.3d at 1232 (“in

the absence of a contract or agreement, a court must look

to the totality of the circumstances, including any

‘affirmative acts to dispose,’ to determine whether the

Defendants intended to enter into an arrangement for

disposal. . . . [A] party can be responsible for ‘arranging for’

disposal, even when it has no control over the process

leading to the release of substances.”); Amcast, 2 F.3d at

751 (“arranged for” . . . “impl[ies] intentional action.”); while

others require only a demonstration of control and/or

ownership over the hazardous substances that are being

disposed of or treated. See, e.g., Aceto, 872 F.2d at 1380

(rejecting reading of Section 107(a)(3) that requires proof

that defendant intended to dispose of a waste, and focusing

on defendant’s ownership of raw materials and control over

formulation process).

There has been some disagreement, too, as to whether

ownership or control over the material being processed is

the more critical factor in the “arranger liability” analysis.

C.f. United States v. Hercules, 247 F.3d 706, 720 (8th Cir.

13

2001) (implying that ownership without control would

suffice and stating that “[c]ontrol . . . is not a necessary

factor”) and Jones-Hamilton, 973 F.2d at 695 (liability based

on ownership without control); with United States v. Shell

Oil Co., 294 F.3d 1045, 1055-56 (9th Cir. 2002) (proof of

ownership not required because actual control is the

“crucial element”).

After carefully examining the language of the statute and

considering the standards adopted by other courts, we

conclude that the most important factors in determining

“arranger liability” are: (1) ownership or possession; and (2)

knowledge; or (3) control. Ownership or possession of the

hazardous substance must be demonstrated, but this factor

alone will not suffice to establish liability. A plaintiff must

also demonstrate either control over the process that

results in a release of hazardous waste or knowledge that

such a release will occur during the process.5 We note, too,

that in conducting this analysis a court should not lose

sight of the ultimate purpose of Section 113, which is to

determine whether a defendant was sufficiently responsible

for hazardous-waste contamination so that it can fairly be

forced to contribute to the costs of cleanup.

5. We do not mean to suggest that no other factors would be relevant to

this analysis. In Concrete Sales and Services, Inc. v. Blue Bird Body Co.,

the court compiled a comprehensive list of factors that courts have

considered in discussing “arranger liability,” including: “(1) whether a

sale involved the transfer of a ‘useful’ or ‘waste’ product; (2) whether the

party intended to dispose of a substance at the time of the transaction;

(3) whether the party made the ‘crucial decision’ to place hazardous

substances in the hands of a particular facility; (4) whether the party

had knowledge of the disposal; and (5) whether the party owned the

hazardous substances.” 211 F.3d 1333, 1336-37 (11th Cir. 2000). See

also State of New York v. Solvent Chem. Co., 225 F. Supp. 2d 270, 280-

81 (S.D.N.Y. 2002) (compiling list of factors considered by other courts).

Depending on the particular circumstances of a case, any of these

factors, and quite possibly others not mentioned here, could be helpful

in determining whether the defendant was sufficiently responsible for

hazardous-waste contamination so that it can fairly be forced to

contribute to the costs of cleanup. We think, though, that the factors we

have identified — ownership or possession, knowledge, and control —

are closely related to most or all of the other factors identified.

14

We believe that ownership or possession, knowledge, and

control are the most critical factors in this analysis for the

following reasons. First, proof of ownership, or at least

possession, of the hazardous substance is required by the

plain language of the statute. See 42 U.S.C. § 9607(a)(3)

(“any person who . . . arranged for disposal or treatment

. . . of hazardous substances owned or possessed by such

person . . . .) (emphasis added). This required factor is the

starting point in determining “arranger liability” because, of

course, with ownership comes responsibility. See Aceto, 872

F.2d at 1382 (imposing “arranger liability” upon defendant

that owned hazardous substance throughout formulation

process because finding otherwise “would allow defendants

to simply ‘close their eyes’ to the method of disposal of their

hazardous substances”).

As we said above, though, we do not think that proof of

ownership or possession alone is a sufficient basis upon

which to ground “arranger liability.” A rule stating that this

factor alone would suffice could broaden the sweep of

Section 107(a)(3) beyond the bounds of fairness. If, for

example, a defendant arranges for a plant to treat a

hazardous substance that it owns or possesses, but has

absolutely no control over the processing and no knowledge

(or even reason to know) that the processing will result in

the release of hazardous waste, it would be unfair to

require that defendant to contribute to the cost of cleanup.

Imposing liability on the defendant under those

circumstances would go beyond Congress’s intent to

require those “actually responsible for any damage,

environmental harm, or injury from chemical poisons” to

share in the cost of cleanup. Bestfoods, 524 U.S. at 55-56

(citations omitted).

Second, proof of a defendant’s knowledge that hazardous

waste can or will be released in the course of the process

it has arranged for, provides a good reason to hold a

defendant responsible because such proof demonstrates

that the defendant knowingly (if not personally) contributed

to the hazardous-waste contamination. Thus, general

knowledge that waste disposal is an inherent or inevitable

part of the process arranged for by the defendant may

suffice to establish liability. See Aceto, 872 F.2d at 1384.

15

This factor can be satisfied by proof of either actual

knowledge (e.g., a provision in an agreement estimating the

amount of environmentally harmful spillage inherent in the

processing of the defendant’s materials), or presumed

knowledge (e.g., the defendant is familiar with industry

custom, which is that the processing of the particular

material normally results in the release of harmful wastes).

See Cello-Foil Products, 100 F.3d at 1231 (concluding that

“intent need not be proven by direct evidence, but can be

inferred from the totality of the circumstances” when

evaluating “arranger liability”); Montalvo, 84 F.3d at 409

(indicating that inference that defendants had knowledge

that arranged for activity would entail spilling of pesticides

and draining of contaminated rinse water would expose

defendants to “arranger liability”).6

And third, proof that the defendant had control over the

process could establish that the defendant was responsible

for the resulting release of hazardous wastes. C.f. Shell Oil,

294 F.3d at 1055, 1057 (suggesting that “actual control”

rather than simply “authority to control” must be shown);

General Elec. Co. v. AAMCO Trans., Inc., 962 F.2d 281, 286-

87 (2d Cir. 1992) (implying that obligation to exercise

control alone satisfies “arranger liability” standard). In

many instances, proof of control could also create an

inference that the defendant had knowledge that the

process resulted in the release of hazardous wastes.

6. In Shell Oil, the Ninth Circuit distinguishes between “Direct Arranger

Liability” and “Broader Arranger Liability.” 294 F.3d at 1054-55. The

court describes the former as involving a transaction in which the “ ‘sole

purpose . . . is to arrange for the treatment or disposal of hazardous

wastes.’ ” Id. at 1054 (citation omitted). In other words, “[a] direct

arranger must have direct involvement in arrangements for the disposal

of waste.” Id. at 1055. The scienter required for “Direct Arranger

Liability” appears to be specific intent or at least specific knowledge of

the waste disposal. Either level of scienter is higher than the general

knowledge level that we require. Logically, though, if a plaintiff can prove

that a defendant had specific knowledge or specific intent, the plaintiff

can also prove the defendant had general knowledge. Accordingly, we see

no reason to draw a distinction between direct and broad (or indirect)

“arranger liability.” After all, there is only one category of “arranger

liability” under Section 107(a). We believe that only one set of factors is

required to analyze it.

16

Accordingly, we see these two factors as somewhat

interrelated.

In sum, we conclude that the analysis of “arranger

liability” under Section 107(a)(3) should focus on these

principal factors: (1) ownership or possession of a material

by the defendant; and (2) the defendant’s knowledge that

the processing of that material can or will result in the

release of hazardous waste; or (3) the defendant’s control

over the production process. A plaintiff is required to

demonstrate ownership or possession, but liability cannot

be imposed on that basis alone. A plaintiff is also required

to demonstrate either knowledge or control. We identify

these principal factors to establish the base-line for

analysis of “arranger liability” in this Circuit. It is certainly

possible that other factors could be relevant to this analysis

in a given case, and we encourage consideration of those as

well.

B. Disputed Material Facts With Respect to Morton’s

CERCLA Claims

Tenneco concedes that mercury is a hazardous substance

and that there was a release from the plant which has

caused Morton to incur response costs. Morton asserts that

Tenneco is liable because of two different types of

transactions — those involving PVM and those involving

“dirty mercury” — both of which comprise an arrangement

for the disposal of a hazardous substance under Section

107(a)(3). The District Court found, however, that there was

insufficient evidence supporting Morton’s claims to survive

Tenneco’s summary judgment motion. We will review each

of Morton’s claims under the “arranger liability” standard

articulated above to determine if the District Court correctly

granted judgment to Tenneco.

Our standard of review applicable to an order granting

summary judgment is plenary. See Curley v. Klem, 298

F.3d 271, 276-77 (3d Cir. 2002). We apply the same test

employed by the District Court under Federal Rule of Civil

Procedure 56(c). See Kelley v. TYK Refractories Co., 860

F.2d 1188, 1192 (3d Cir. 1988). Accordingly, the District

Court’s grant of summary judgment in favor of Tenneco was

17

proper only if it appears that “there is no genuine issue as

to any material fact and that [Tenneco] is entitled to a

judgment as a matter of law.” Fed. R. Civ. P. 56(c). In

evaluating the evidence, we “take the facts in the light most

favorable to the nonmoving party, [Morton], and draw all

reasonable inferences in [its] favor.” Doe v. County of

Centre, PA, 242 F.3d 437, 446 (3d Cir. 2001) (citation

omitted).

1. PVM Transactions

Morton alleges that Tenneco engaged in two types of “toll”

or “conversion” transactions with the plant involving PVM,

both of which comprise arrangements for the disposal of

hazardous substances owned by Tenneco under Section

107(a)(3). Basically, Morton contends that Tenneco

purchased the PVM either from the plant or some other

supplier and then paid a fee to the plant for the conversion

of the PVM into ROM or YOM. In either case, Morton

argues, Tenneco owned the PVM throughout the conversion

process, and was aware that the conversion process

inevitably resulted in the release of hazardous waste.

a. Ownership or Possession

The District Court addressed the issue of ownership or

possession, and found that “the record evidence shows”

that Tenneco did not own or possess the PVM that was

processed at the plant. (App. at 12-13). The Court based its

finding on two conclusions. First, the Court reasoned that

whether Tenneco purchased the PVM through a broker or

from the plant directly, the “ownership” alleged by Morton

was a bookkeeping function done solely for the purpose of

minimizing the plant’s financial risk in the volatile mercury

market. And second, the Court determined that there was

not a “showing that Tenneco was the necessary source of

the PVM,” or that “Tenneco was a manufacturer of PVM.”

Id. at 13.

We will look first at the District Court’s conclusion that

the “toll” or “conversion” transactions used by the plant

were solely for the purpose of minimizing the plant’s

financial risk in the volatile mercury market. One problem

18

with this conclusion is that it is an inference drawn in favor

of Tenneco rather than Morton, the party opposing the

motion. Another problem is that the conclusion

inappropriately resolves a material factual dispute.

Citing the plant brochure and the deposition testimony of

several former plant managers, Morton explains that the

plant customers, including Tenneco, had the option of

supplying their own PVM and storing it in the plant’s vault

or purchasing it directly from the plant. If the customer

chose the first option, the plant would charge for the

processing of the PVM into ROM or YOM and for insuring

the mercury while it was stored at the plant, but the

customer owned the mercury “at the beginning, middle,

and end of the process.” (Morton Brief at 13) (citing App. at

660, 881, 458). In fact, one plant manager testified that

when customers supplied PVM for processing, the

customers continued to hold title to it while it was at the

plant. Id. (citing App. at 238-240). Morton asserts that

Tenneco was “a major conversion customer” from at least

1963 to 1973, and that it supplied significant amounts of

PVM to the plant for processing. (Morton Brief at 13-14)

(citing, inter alia, numerous weekly Physical Inventories

and weekly Customer Ownership Reports documenting the

number of Tenneco-owned pounds of mercury stored at the

plant and converted into ROM and YOM).

To be sure, Tenneco disputes Morton’s contention that it

owned the PVM throughout the process. Tenneco contends

that the plant used certain billing methods (which look like

“conversion” or “toll” agreements) “to protect itself from the

price volatility of the mercury market and the associated

financial risk . . . .” (Tenneco Brief at 6). Tenneco also

asserts that the PVM it allegedly owned was never

segregated or labeled as belonging to it at any point in the

process. Id. at 21-22 (citing App. at 533-34). In fact,

Tenneco maintains that the customer-delivered PVM was

not the actual mercury used to manufacture that

customer’s ROM and YOM because mercury is

homogeneous; instead the mercury was added to the

plant’s inventory, like money in a bank. Id. at 22-23 (citing

App. at 635-38, 533-34, 472-73). (Thus, Tenneco’s

ownership of the PVM that was converted at the plant on

19

Tenneco’s behalf is very much in dispute. Morton has

submitted evidence, including plant records and the

testimony of former plant managers, from which it is fair to

infer that Tenneco owned the PVM (regardless of whether it

purchased it from the plant or a third party) throughout the

conversion process. Proof of ownership, of course, is one of

the principal factors in the “arranger liability” analysis.

Therefore, this evidence is sufficient to withstand Tenneco’s

motion for summary judgment.7

b. Knowledge

Although the District Court did not directly address the

knowledge factor, it discussed evidence that is relevant. The

Court referred to a memorandum from the United States

Environmental Protection Agency (“EPA”) cited by Morton

and concluded that the reference therein to Tenneco’s

disposal of mercury by-products was “just not enough”

evidence to survive a motion for summary judgment. (App.

at 14, 15).

Before we discuss the other evidence related to

7. Although we have already identified material disputed facts on the

issue of ownership that warrant remand for further consideration, we

pause to consider Tenneco’s argument that because mercury is

homogenous, it could not have been owned by any particular customer

throughout the oxide processing at the plant. See supra. Tenneco’s own

analogy to money in a bank suffices to demonstrate the

unreasonableness of its argument. When money is deposited in a bank

the depositor does not cease owning the money because the actual

dollars and cents it deposited are fungible and are used by other

customers. Whether the plant segregated each customer’s PVM or simply

added it all together is inconsequential. The ownership or possession

factor can be satisfied by proof that Tenneco owned or possessed the

amount of PVM that it paid to have processed into ROM and YOM. See

App. at 881 (Wood Ridge Chemical Corporation Balance Sheet and

Auditor’s Report, stating: “Since mercury is homogeneous, it is not

possible to physically identify owned from non-owned mercury, but

records are maintained to account for customer-owned quantities.”). Like

ownership of money in a bank, Tenneco’s ownership of a mercury is not

refuted by proof that other customers used the exact PVM it initially

deposited. Cf. Hercules, 247 F.3d at 721 (finding defendant owned

material despite intermingling with other materials during processing).

20

knowledge that was submitted by Morton, we will address

Tenneco’s argument that the EPA memorandum should not

be considered because it is not part of the record. Morton’s

counsel read a portion of the 1971 EPA memorandum

during the summary judgment oral argument, but

neglected to move its admission into the record. Id. at 80-

81. Prior to filing its appellate brief, Morton moved the

District Court to supplement the record with, among other

things, the EPA memorandum. The motion was denied, and

Morton has not appealed that decision. Because the

memorandum is not included in the certified record, even

after Morton’s motion to supplement the record, Tenneco

argues that we should not consider it at all. Tenneco

argues, too, that Morton’s counsel did not provide a copy of

the document to either the District Court or opposing

counsel. Morton asserts, however, that Tenneco produced

this document during discovery. And, because counsel read

the relevant portions of the memorandum into the record

during oral argument without objection from Tenneco and

because the District Court referred to the memorandum in

her ruling, the memorandum is part of the record.

According to Federal Rule of Appellate Procedure 10(a),

the record on appeal is comprised of (1) the original papers

and exhibits filed in the district court; (2) the transcript of

the proceedings; and (3) a certified copy of the docket

entries. “This definition not only includes items admitted

into evidence, but also includes items presented to the

district court and not admitted into evidence.” Waldorf v.

Shuta, 142 F.3d 601, 620 (3d Cir. 1998) (citation omitted).

Here, it is undisputed that the EPA memorandum was

never included in the record in its entirety. Given that the

memorandum does not appear to have been presented to

the District Court, we will not review it in its entirety (which

is not possible as a practical matter in any event because

the document was not included in the appendices). See

Waldorf, 142 F.3d at 620 (“The basic purpose behind the

rule is to prevent parties from supplementing the record on

appeal with items never presented to the district court.”)

The next question is whether we can appropriately consider

the portion of the memorandum that was read by Morton’s

counsel during oral argument and which is found in the

21

transcript. Because we conclude that Morton presented

evidence other than the portion of the EPA memorandum to

establish Tenneco’s knowledge, and because we think that

evidence created disputed facts, we do not need to decide

whether it is appropriate for us to consider the

memorandum on appeal. We leave it to the District Court

to evaluate the admissibility of the document on remand.

As we just mentioned, Morton presented evidence other

than the EPA memorandum to establish Tenneco’s

knowledge that the release of hazardous waste was an

inherent and inevitable aspect of mercury processing.

Specifically, Morton maintains that Tenneco was

knowledgeable about mercury processing because it used

ROM and YOM to manufacture products at its own

facilities, and because it had produced mercury oxide at its

Elizabeth facility in the past. (Morton Brief at 7-8, 9) (citing

App. at 855). Morton contends that Tenneco must have

been aware of the environmental risks inherent in mercury

processing because “the hazards of handling and

processing mercury were well known within the industry

generally,” and because “substantial mercury loss, as well

as known losses in dust and vapor, were an inherent part

of manufacturing mercury intermediates,” and that those

losses were “closely monitored by the Plant and its

customers who provided the mercury.” Id. at 9, 10 (citing

App. at 940, 942, 932-33, 796, 252-53).

Tenneco does not dispute that it used ROM and YOM to

manufacture its own products at its Elizabeth facility or

that it produced mercury oxide at the same facility in the

past. (Tenneco Brief at 24, 27). Instead, Tenneco accuses

Morton of improperly relying on general facts about the

plant’s relationship with its customers rather than facts

specific to the plant’s relationship with Tenneco in

attempting to prove Tenneco’s knowledge that waste was

released during mercury processing.

We think it is fair to infer from Tenneco’s involvement

with mercury oxides at its own facility that Tenneco had

some knowledge about the environmental hazards of

mercury processing. We also think it is fair to rely on

evidence provided by Morton about the plant customers

generally. While Morton did not present evidence showing

22

that Tenneco, specifically, was monitoring the mercury

losses during processing at the plant, it was not required to

do so in order to survive Tenneco’s motion for summary

judgment. After all, Tenneco was undisputably one of the

plant customers, and it is thus reasonable to infer (absent

proof to the contrary) that it had the same kind of

relationship with the plant as did the other customers.

Whether a jury would ultimately be persuaded by this

evidence is uncertain, but that is not the standard we apply

in evaluating a summary judgment motion. Accordingly, we

believe that there are disputed facts with respect to

Tenneco’s knowledge of hazardous waste releases during

the processing of PVM at the plant. Because knowledge is

one of the principal factors in the “arranger liability”

analysis, this evidence is sufficient to withstand Tenneco’s

motion for summary judgment.

c. Control

The District Court did not directly discuss this factor.

But, related to control, the Court observed that it would not

have mattered if Tenneco had shipped PVM directly to the

plant on a regular basis because “it is what happened [at

the plant] and [Tenneco’s] involvement . . . with respect to

what happened [at the plant] that’s important.” (App. at

12). We disagree with the Court’s suggestion that proof that

Tenneco shipped PVM directly to the plan would have been

irrelevant. Such proof could demonstrate Tenneco’s

ownership, or at least possession, of the PVM. More

importantly, though, the parties dispute Tenneco’s level of

control over “what happened” at the plant.

Morton states that “customers such as Tenneco played a

key role in shaping the Plant’s production processes and its

resulting emissions” by approving a new process for

mercury oxide manufacturing in the late 1960’s. (Morton

Brief at 11) (citing App. at 827-28, 923, 952, 953, 406-10).

Morton argues that the customer’s approval of the

production process amounted to some control over the

production process. Tenneco, however, disputes Morton’s

assertion that it had any control over the plant operations

or disposal practices. (Tenneco Brief at 12-13) (citing App.

at 504, 268, 340-42, 244-50).

23

Again, Morton’s evidence about the customers generally

is relevant — Tenneco was undisputably a customer of the

plant. Whether this evidence alone is sufficient to establish

control is another matter. Because we are remanding this

case to be analyzed under the standard articulated above,

we suggest that the District Court consider this evidence in

the subsequent proceedings.

d. Useful Product Defense

The District Court characterized the PVM transactions as

“sales transactions” and referred to the “useful product

defense” discussed in Pneumo Abex Corp. v. High Point,

Thomasville and Denton R.R. Co., 142 F.3d 769, 774 (4th

Cir. 1998). (App. at 13-14). Tenneco argued below, and

continues to argue on appeal, that this defense applies

because the transactions at issue were nothing more than

a sale of a useful product (PVM) and a purchase of finished

products (ROM and YOM). We believe that there are

disputed facts with respect to the critical elements of this

defense.‘’

In Pneumo Abex, the court concluded that “ ‘treatment

. . . of hazardous substances’ as used in CERCLA refers to

a party arranging for the processing of discarded hazardous

substances or processing resulting in the discard of

hazardous substances.” 142 F.3d at 774. Accordingly, the

sale of valuable materials to a processor alone does not

satisfy the requirements for “arranger liability.” See Glaxo

Wellcome, Inc., 189 F.3d at 164; Solvent Chemical Co., 225

F. Supp. 2d at 280.

We agree with Tenneco that the sale of PVM alone or the

purchase of ROM and YOM alone — without evidence of

ownership or possession, knowledge, and control — would

not be sufficient grounds on which to impose “arranger

liability.” Those transactions would either not meet the

standard we have articulated or would fall within the

“useful product defense.” It would be inappropriate at this

stage in the proceedings, however, to conclude that the

transactions between Tenneco and the plant were nothing

more than a sale of PVM or the purchase of ROM and YOM

because of the factual disputes we have described with

24

respect to the key elements of ownership or possession,

knowledge, and control.

2. “Dirty Mercury” Transactions

Morton asserts that Tenneco shipped its own “dirty

mercury” to the plant for processing into usable mercury, a

transaction which clearly qualifies Tenneco for “arranger

liability.” (Morton Brief at 15). Morton contends that it

submitted evidence sufficient to survive summary judgment

on this claim. Tenneco argues that Morton did not present

this claim to the District Court at all.

It is true that Morton did not include the “dirty mercury”

allegation in its Statement of Contested Facts for the

Pretrial Order. (Supp. App. at 2-3). As a general matter, the

pretrial order will “control the subsequent course of the

action unless modified by a subsequent order.” Fed. R. Civ.

P. 16(e). Moreover, the “finality of the pretrial order

contributes substantially to the orderly and efficient trial of

a case.” Petree v. Victor Fluid Power, Inc., 831 F.2d 1191,

1194 (3d Cir. 1987).

Nonetheless, “Rule 16 was not intended to function as an

inflexible straightjacket on the conduct of litigation . . .

instead, it was intended to insure the efficient resolution of

cases and, most importantly, minimize prejudicial

surprise.” Lamborn v. Dittmer, 873 F.2d 522, 527 (2d Cir.

1989) (citations omitted). Accordingly, Morton argues that

the issue is properly addressed on appeal because it raised

the issue in its brief opposing Tenneco’s motion for

summary judgment.

In response to Tenneco’s individual motion for summary

judgment, Morton incorporated its Statement of Material

Facts from the earlier summary judgment proceeding

involving all of the defendants. In paragraph 10 of that

Statement of Material Facts, Morton makes allegations

about PVM and “dirty mercury” transactions against “The

Customers” generally without specifying any customer by

name. (App. at 157). In paragraph 11, Morton asserts that

the “evidence confirming these transactions is

overwhelming” and cites numerous pages of deposition

testimony. Id. One of the cited portions of deposition

25

testimony indicates that Tenneco shipped “dirty mercury”

to the plant. Id. (deposition transcript of Joseph H.

Bernstein at 860).

The critical issue is whether Tenneco was on notice of

Morton’s “dirty mercury” claim during the summary

judgment proceedings despite the fact that the claim was

not included in the Pretrial Order. We find that Tenneco

was sufficiently aware of the claim. Tenneco was

presumably put on notice of Morton’s allegation at the time

of the Bernstein deposition given that Bernstein stated that

he believed that Tenneco shipped “dirty mercury” to the

plant. If not at the time of the deposition, Tenneco was

surely on notice as of the time it received Morton’s

Statement of Material Facts during the first summary

judgment proceeding. Finally, Tenneco was put on notice of

this claim a third time when Morton incorporated its

Statement of Material Facts into its response to Tenneco’s

individual motion for summary judgment. Thus, although

Morton’s failure to include this claim in the Pretrial Order

violates the letter of Rule 16(e), our consideration of this

claim on appeal does not violate the purpose of the rule,

which is primarily to “minimize prejudicial surprise.”

Lamborn, 873 F.2d at 527.

Assuming we would consider the “dirty mercury” claim,

Tenecco argues in the alternative that the District Court

properly granted summary judgment to Tenneco because,

quite simply,“Morton has absolutely no evidence to support

such a claim.” (Tenneco Brief at 57). We disagree.

Morton asserts that Tenneco shipped its own “dirty

mercury” to the plant for processing into usable mercury.

(Morton Brief at 15) (citing Bernstein Dep. at 40, 860).

Morton maintains that the plant’s standard operating

procedure was to store “dirty mercury” in separate flasks

labeled with the customer’s name and date received and

then to purify the mercury by a furnace-operated

distillation process, which produced environmentally

harmful residue. Id. (citing App. at 431-32, 443, 447, 461-

63, 868-69, 954). Morton contends that customers were

apprised of the fact that “a certain percentage of mercury

would be lost in the process.” Id. (citing App. at 963-65,

263). This evidence is sufficient to at least create a disputed

26

fact with respect to each of the principal “arranger liability”

factors — ownership or possession, knowledge, and control.

Therefore, under the standard we have just articulated, this

evidence suffices to survive summary judgment.

3. Spill Act and Common Law Claims

The District Court did not discuss Morton’s Spill Act

claim or its common law contribution claim, but it

nevertheless granted summary judgment to Tenneco on

both. Because the Spill Act is the “New Jersey analog to

CERCLA,” the standards for liability are the same. See SC

Holdings, Inc. v. A.A.A. Realty Co., 935 F. Supp. 1354, 1365

(D.N.J. 1996); State of New Jersey v. Gloucester

Environmental Management Servs., Inc., 821 F. Supp. 999,

1009 (D.N.J. 1993). Therefore, we vacate the District

Court’s grant of summary judgment on the Spill Act claim

for the same reasons that we vacate judgment on the

CERCLA claim. We conclude, however, that the District

Court’s grant of judgment to Tenneco on the common law

contribution claim was appropriate because that claim is

preempted by CERCLA Section 113(f). See In the Matter of

Reading Co., 115 F.3d 1111, 1117 (3d Cir. 1997) (holding

that CERCLA Section 113(f) preempts common law

contribution claim).

IV. Conclusion

Because there are disputed material facts with respect to

Morton’s CERCLA and Spill Act claims against Tenneco, we

will vacate the District Court’s grant of summary judgment

and remand those claims for further proceedings consistent

with this opinion. Because Morton’s common law

contribution claim is preempted by CERCLA, we will affirm

the District Court’s grant of summary judgment to Tenneco.

A True Copy:

Teste:

Clerk of the United States Court of Appeals

for the Third Circuit