The opinion

NO.

12-05-00217-CV

IN THE COURT OF APPEALS

TWELFTH COURT OF APPEALS DISTRICT

TYLER, TEXAS

OLYMPIC WASTE SERVICES,

A DIVISION OF ALLIED

WASTE

INDUSTRIES, INC., § APPEAL

FROM THE 294TH

APPELLANT

V. § JUDICIAL

DISTRICT COURT OF

THE CITY OF GRAND

SALINE, TEXAS,

APPELLEE § VAN

ZANDT COUNTY, TEXAS

OPINION

Olympic

Waste Services, a division of Allied Waste Industries, Inc., appeals from the

trial court’s orders granting the City of Grand Saline’s plea to the

jurisdiction and motion for summary judgment and the trial court’s order

denying Olympic’s motion for partial summary judgment. In five issues, Olympic contends the City is

not immune from suit for breach of contract and the trial court made erroneous

rulings regarding its claim for violations of the Texas Open Meetings Act. 1 We

affirm in part and reverse and render in part.

Background

Beginning

in February 1989, Olympic contracted with the City to provide solid waste

removal services. The contract had an

initial five year term and renewed automatically for successive five year

terms. However, either party could

terminate with notice at least sixty days prior to the end of the five year

term. On February 10, 2004, the Grand

Saline city council awarded a “garbage contract” to Easley Sanitation, to be

effective April 1, 2004. Olympic

received a letter from the City dated February 17, 2004, stating that its

contract with the City was “breached and terminated” on the grounds that

Olympic had failed to provide certificates of insurance and surety bonds. The letter stated that Olympic would no

longer receive payment from the City.

Olympic

filed suit to have the contract between Easley and the City declared void due

to violations of the Texas Open Meetings Act and the Local Government Code’s

competitive bidding requirements and to have the contract between Olympic and

the City declared to be in full force.

Alternatively, Olympic asserted a cause of action against the City for

breach of contract. Olympic also alleged

that Easley committed tortious interference with its contract with the City and

conspired with unknown others to interfere with Olympic’s contractual relations

with the City.

Claiming

immunity to suit, the City filed a plea to the jurisdiction arguing that the

trial court did not have jurisdiction over Olympic’s causes of action based on

its contract with the City, that is, the request for declaratory judgment on

the contract termination and the breach of contract claim. The City filed a motion for summary judgment

on the cause of action for violation of competitive bidding, relying on an

exception to the statute, and on the cause of action for violations of the Open

Meetings Act based on statutory authority to consult with the city attorney in

executive session. Olympic filed a

partial motion for summary judgment addressing the alleged open meetings violations. The trial court denied Olympic’s motion and

granted the City’s plea to the jurisdiction and its motion for summary

judgment. Later, Olympic nonsuited

Easley, dropping its tortious interference and conspiracy claims.

Plea to the

Jurisdiction

In

its first issue, Olympic contends the trial court erred in granting the City’s

plea to the jurisdiction. Relying on the

Local Government Code, which states that a municipality may sue and be sued, it

argues that the City is subject to a legislative waiver of immunity for its

contract claim.

Standard of Review

Immunity

from suit bars an action against the State unless the State expressly consents

to the suit. Texas Dep’t of

Transp. v. Jones , 8 S.W.3d 636, 638 (Tex. 1999). Since as early as 1847, the law in Texas has

been that absent the State’s consent to suit, a trial court lacks subject

matter jurisdiction. Id . The absence of subject matter jurisdiction

may be raised by a plea to the jurisdiction.

Bland Indep. Sch. Dist. v. Blue , 34 S.W.3d 547, 554 (Tex.

2000). Because subject matter jurisdiction

presents a question of law, we review the trial court’s decision to grant a

plea to the jurisdiction de novo. Mayhew

v. Town of Sunnyvale , 964 S.W.2d 922, 928 (Tex. 1998). In

reviewing a plea to the jurisdiction, we review the pleadings and any evidence

relevant to the jurisdictional issue. Texas

Dep’t of Crim. Justice v. Miller , 51 S.W.3d 583, 587 (Tex. 2001). The party suing the governmental entity must

establish the State’s consent, which may be alleged either by reference to a

statute or to express legislative permission.

Jones , 8 S.W.3d at 638 .

In considering the jurisdictional allegations contained in a petition,

they are to be construed liberally in the plaintiff’s favor. Texas Ass’n of Bus. v. Texas Air

Control Bd. , 852 S.W.2d 440, 446 (Tex. 1993).

Discussion

The

Local Government Code provides that Type A general law municipalities “may sue

and be sued, implead and be impleaded, and answer and be answered in any matter

in any court or other place.” Tex. Loc. Gov’t Code Ann. § 51.013

(Vernon 1999). In 1970, the Texas

Supreme Court determined that the effect of the phrase “sue and be sued” in a

statute is a waiver of sovereign immunity giving general consent for the entity

to be sued in the courts of Texas in the same manner as other defendants. Missouri Pac. R.R., Co. v. Brownsville

Navigation Dist. , 453 S.W.2d 812, 813 (Tex. 1970). However, the supreme court recently

reconsidered this exact issue in Tooke v. City of Mexia , 197

S.W.3d 325 (Tex. 2006). After reviewing

legislative use of the phrases “sue and be sued,” “implead and be impleaded,”

and “answer and be answered”since 1858, the court overruled Missouri

Pacific . Tooke ,

197 S.W.3d at 342 . The court explained

that, because immunity is waived only by clear and unambiguous language, and

because the meaning of these phrases cannot be ascertained apart from the

context in which they occur, they do not, in and of themselves, waive immunity

from suit. Id . at 342.

Further,

and more to the point, the Legislature, in 2005, passed Sections 271.152 to

271.160 of the Local Government Code, which waive local governmental entities’

immunity from suit for breach of contract under certain circumstances and limit

damages. Tex. Loc. Gov’t Code Ann. §§ 271.151-.160 (Vernon

2005). Although the effective date of

the new statutes was September 1, 2005, the new law applies to claims arising

under a contract executed before the effective date if sovereign immunity has

not been waived with respect to the claim before the effective date. Act of May 23, 2005, 79th Leg., R.S., ch.

604, §§ 2-3, 2005 Tex. Gen. Laws 1548 , 1549.

Just as the supreme court determined in Tooke that the

phrase “plead and be impleaded” in the context of Local Government Code Section

51.075 reveals nothing about an intent to waive immunity, we determine that the

phrase “sue and be sued” in Section 51.013 does not unambiguously waive

immunity. See City of Houston v. Boyer, Inc. ,

197 S.W.3d 393, 393 (Tex. 2006) (Neither Local Government Code Section 51.075

nor city charter provision authorizing it to “sue and be sued, . . . contract

and be contracted with, implead and be impleaded in all courts and places and

in all matters whatever” contains a clear and unambiguous waiver of immunity

from suit.).

Olympic’s

claim for breach of contract arose under a contract executed before September

1, 2005, and the City was immune from suit on Olympic’s claim. Therefore, Section 271.152 applies to waive

immunity only to the extent provided by that statute. That is, the City’s immunity to suit is

waived for the purpose of adjudicating a claim for breach of contract. See Tex.

Loc. Gov’t Code Ann . § 271.152.

Damages are limited by Section 271.153 to include the balance due and

owed by the local governmental entity under the contract, the amount owed for

change orders in connection with the contract, and interest. Tex.

Loc. Gov’t Code Ann . § 271.153(a).

The statute specifically provides that damages awarded under this

subchapter may not include consequential damages. Id . § 271.153(b)(1). As did the plaintiffs in Tooke ,

Olympic attempted to recover lost profits, which under the facts of this case,

are consequential damages excluded from recovery under the statute. See id . ; Tooke ,

197 S.W.3d at 346 . Consequently, the City’s immunity from suit

on Olympic’s breach of contract claim has not been waived. See Tooke , 197 S.W.3d at

346 .

Section

271.152 specifically applies to breach of contract claims. Tex.

Loc. Gov’t Code Ann. § 271.152.

It does not mention claims for declaratory relief. Olympic also pleaded for declaratory judgment

on the validity of its contract with the City in light of the City’s attempted

termination. The City claimed immunity

to suit on this claim. As explained

above, the “sue and be sued” language relied on by Olympic does not constitute a

clear and unambiguous waiver of immunity by the City. See Tooke , 197 S.W.3d at

342 . Therefore, the trial court lacked

jurisdiction to give declaratory relief regarding the termination issue. Accordingly, the trial court did not err in

granting the City’s plea to the jurisdiction.

We overrule Olympic’s first issue.

Summary Judgment

In

its remaining issues, Olympic complains of the trial court’s rulings on the

City’s motion for summary judgment and Olympic’s motion for partial summary

judgment regarding Olympic’s claims of Open Meetings Act violations. 2 In its second issue, Olympic argues that the

City’s motion should not have been granted because fact issues exist with

respect to violations of the Open Meetings Act.

In its third issue, Olympic argues that its motion should not have been

denied because the City violated the Open Meetings Act by taking action to

terminate its contract in executive session and by evaluating, considering, and

discussing the award of a contract to an independent contractor in executive

session. In its fifth issue, Olympic

asserts that the trial court erred in denying its motion because the City

illegally used the statutory authorization for private consultation with the

governmental entity’s attorney found in Section 551.071 of the Act.

Applicable Law

To

obtain a summary judgment, the movant has the burden of showing that there is

no genuine issue of material fact and that he is entitled to judgment as a

matter of law. Tex. R. Civ. P. 166a(c).

In deciding whether there is a disputed material fact issue precluding

summary judgment, evidence favorable to the nonmovant will be taken as

true. Nixon v. Mr. Prop. Mgmt. Co. ,

690 S.W.2d 546, 548-49 (Tex. 1985).

Every reasonable inference must be indulged in favor of the nonmovant

and any doubts resolved in its favor. Id.

at 549 . Summary judgment for a defendant

is proper when the summary judgment evidence negates an essential element of

the plaintiff’s cause of action as a matter of law or conclusively establishes

all elements of an affirmative defense as a matter of law. See Black v. Victoria Lloyds Ins. Co. ,

797 S.W.2d 20, 27 (Tex. 1990). Once the

defendant produces sufficient evidence to establish the right to summary

judgment, the burden shifts to the nonmovant to produce controverting evidence

raising a fact issue as to the elements negated. Torres v. Western Cas.

& Sur. Co. , 457 S.W.2d 50, 52 (Tex. 1970); Owen Elec. Supply,

Inc. v. Brite Day Constr. Inc. , 821 S.W.2d 283, 286 (Tex. App.–Houston

[1st Dist.] 1991, writ denied).

A

plaintiff, as movant, must conclusively prove all essential elements of his

claim. MMP, Ltd. v. Jones ,

710 S.W.2d 59, 60 (Tex. 1986). Once a

movant has established the right to a summary judgment on the issues presented,

the nonmovant has the burden of introducing evidence that raises issues of

fact. Mott v. Montgomery County ,

882 S.W.2d 635, 640 (Tex. App.– Beaumont

1994, writ denied). The nonmovant’s

evidence must be of probative force. Id.

When

both parties move for summary judgment, each party bears the burden of

establishing that it is entitled to judgment as a matter of law, and neither

party can prevail because of the other’s failure to discharge his burden. Guynes v. Galveston County , 861

S.W.2d 861, 862 (Tex. 1993); State Farm Lloyds, Inc. v. Willliams ,

791 S.W.2d 542, 549-50 (Tex. App.–Dallas 1990, writ denied). When reviewing competing motions for summary

judgment, we consider all the evidence accompanying both motions. Dallas County Appraisal Dist. v.

Institute for Aerobics Research , 766 S.W.2d 318, 319 (Tex. App.–Dallas

1989, writ denied) (op. on reh’g). We

must indulge all reasonable inferences and resolve all doubts in favor of the

losing party. University of Tex.

Health Sci. Ctr. v. Big Train Carpet of El Campo, Inc. , 739 S.W.2d 792,

792 (Tex. 1987). If the trial court grants

one motion and denies the other, the appellate court should determine all

questions presented and may render the judgment the trial court should have

rendered. Jones v. Strauss ,

745 S.W.2d 898, 900 (Tex. 1988) (orig. proceeding).

When

the order granting summary judgment does not specify the particular grounds the

trial court sustained, on appeal, the summary judgment opponent must defeat

each summary judgment ground argued by the movant. Carr v. Brasher , 776 S.W.2d

567, 569 (Tex. 1989). Otherwise, an

appellate court must uphold the summary judgment on any ground that is

supported by the evidence and pleadings.

Id.

The

Texas Open Meetings Act requires every regular, special, or called meeting of a

governmental body to be open to the public, with certain narrowly drawn

exceptions. Tex. Gov’t Code Ann. §§ 551.002, 551.071-.088. A governmental body may conduct a private

consultation with its attorney when the governmental body seeks the advice of

its attorney about pending or contemplated litigation or a settlement offer, or

on a matter in which the duty of the attorney to the governmental body under

the Texas Disciplinary Rules of Professional Conduct of the State Bar of Texas

clearly conflicts with Chapter 551 of the Government Code. Tex.

Gov’t Code Ann. § 551.071.

This provision incorporates the attorney-client privilege, an attorney’s

duty to preserve the confidences of a client.

Op. Tex. Att’y Gen. No. JC-0233 (2000).

A governmental entity may consult with its attorney in executive session

to receive advice on legal issues raised by a proposed contract. Id . However, the entity may not discuss the

merits of a proposed contract, financial considerations, or other nonlegal

matters related to the contract simply because its attorney is present. Id . Neither can the entity engage in a general

discussion of policy unrelated to legal matters. Op. Tex. Att’y Gen. No. JM-100 (1983).

Motions and Evidence

In

response to Olympic’s allegation that the City violated the Open Meetings Act

when it met in executive session during the February 10, 2004 meeting, the City

asserted that the exception allowing consultation with legal counsel applied

because the council met with the city attorney regarding its contract with

Olympic. Relying on the affidavit of

Grand Saline Mayor Terry Tolar, the City argued that the council, in executive

session, discussed the ramifications of terminating the contract, the

contractual options the City would have following termination, and the

financial ramifications of continuing to do business with Olympic under the

existing contract. Mayor Tolar stated in

his affidavit:

The City Council did convene in executive

session and consulted with City Attorney, Joel Elliott, regarding the existing

contract with Plaintiff, the consequences of terminating the contract, legal

ramifications of terminating the contract, and contractual options in the event

the contract was terminated with Plaintiff.

These were all legal matters that required the expertise and counsel

from our City Attorney. As part of this

discussion regarding the contractual issues previously mentioned, entering into

a contract with Easley Sanitation was discussed as one of our options in the

event the contract with Plaintiff was terminated.

Olympic

filed a single document containing both a response to the City’s motion and its

own motion for partial summary judgment on the alleged violations of the Open

Meetings Act. In response to the City’s

motion and in support of its motion, Olympic filed the contract at issue, a

letter sent by the City dated February 17, 2004, the agenda and minutes for the

February 10, 2004 council meeting, and excerpts from the depositions of Mayor

Tolar and Gene Putman, Grand Saline’s Public Works Director.

Olympic

received a letter from Virginia Shafer, Grand Saline’s City Administrator,

dated February 17, 2004, informing Olympic that the City “hereby deems the

contract, whereby you have been collecting the city’s solid waste, breached and

terminated.” The letter went on to

explain that the City had not received all required certificates of insurance

or the surety bond and its accompanying certificate.

The

agenda for the council meeting reflects that “garbage bids” were to be

discussed at the workshop immediately prior to the public hearing. “Garbage bids” were also listed under item

six, which listed topics to be discussed, accepted/rejected, or tabled for

further study. Under the title “EXECUTIVE

SESSION” is the explanation that the City reserves the right to adjourn into

closed session to discuss any of the matters listed in the agenda as authorized

by Sections 551.071, 551.072, 551.073, 551.074, 551.076, or 551.087 of the

Texas Government Code.

The

topic of “garbage bids” is not listed among the items named in the minutes as

having been discussed during the workshop on February 10. According to the minutes, early in the

regular meeting, the council decided that “GARBAGE BIDS WILL BE DISCUSSED IN

EXECUTIVE SESSION.” The minutes further

reflect that “AT 9:55 PM WENT INTO EXECUTIVE SESSION PER TX. GOV. CODE SEC.

551.071, FOR CONSULTATION WITH ATTORNEY ON GARBAGE BIDS.” The next entry states: “COUNCIL RECONVENED

INTO REGULAR SESSION AT 10:12 PM. LOGAN

COSTILOE MADE A MOTION TO AWARD GARBAGE CONTRACT TO EASLEY SANITATION TO BE

EFFECTIVE 4-1-04. SECOND BY JERRY

BOLIN. ALL VOTED YES. MOTION CARRIED.”

In

his deposition testimony, Mayor Tolar said the council considered bids for

garbage contracts at the February 10 meeting.

He said that, at that time, there was an existing garbage contract

between Olympic and the City and no one had threatened the City with litigation

regarding garbage bids. Tolar testified

that there were no severe service problems at that time and the City had not

given Olympic notice of any severe service problem as of that date. He agreed with Olympic’s counsel that the

reason the “garbage issue” came up is because the city council was trying to

save money. Predominantly, it was an

economic issue, rather than a public safety or welfare issue. Tolar testified that before February 17,

Olympic had a valid solid waste contract with the City and there were no major

service problems with the contract. He

explained that termination of the Olympic contract was done without the city council’s

authorization. He said it was not posted

on an agenda or in any of the meetings.

He agreed that proper termination of the contract required council

action. He also agreed that it would be

difficult for the administrator who signed the letter to know whether the

insurance certificates had been provided to the City because she signed the

letter, which was drafted by the city attorney, on her second day on the

job. Tolar also stated that the City did

not send notice by certified letter sixty days ahead of the contract

termination.

Public

Works Director Gene Putman testified that, on February 10, 2004, he had no

reason to believe there would be a court case between Olympic and the

City. He agreed that the reason the City

wanted a new garbage contract was to save money. He also agreed that, on February 10, 2004,

the City did not need a new garbage contract in order to preserve or protect

the public health or safety of the citizens of Grand Saline.

Legal Counsel Exception

Tolar

explained that the city council, in executive session, consulted with the city

attorney about the “consequences” and “legal ramifications” of terminating

Olympic’s contract. This discussion

falls in the category of legal advice and is appropriate for executive

session. See Op. Tex. Att’y Gen.

No. JC-0233. However, the discussion of “resulting

contractual options” including entering into a contract with Easley Sanitation

is a topic not to be discussed in executive session. See id . The minutes seem to indicate that,

immediately upon reconvening into regular session, the city council voted,

without discussion, to award a garbage contract to Easley Sanitation. Indulging reasonable inferences in favor of

Olympic, this evidence supports a finding that the city council discussed the

relative merits of awarding the contract to Olympic or Easley while in

executive session in violation of the Open Meetings Act. See id . ; University

of Tex. Health Sci. Ctr. , 739 S.W.2d at 792 . The evidence simultaneously shows that the

City did not conclusively establish the affirmative defense provided by the

statutory exception allowing the governmental entity to avoid an open meeting

by consulting with its attorney and the City actually violated the Open

Meetings Act. See Black ,

797 S.W.2d at 27 ; Jones , 710 S.W.2d at 60 . Therefore, the trial court erred in granting

the City’s motion for summary judgment and in denying Olympic’s partial motion

for summary judgment. We sustain Olympic’s

second issue. To the extent Olympic

complains of the executive session discussion of the merits of the proposed

Easley contract, and because that discussion is not allowed by the statutory

exception for legal advice, we sustain Olympic’s third and fifth issues. We need not reach Olympic’s fourth

issue. See Tex. R. App. P. 47.1.

Easley Contract

In

its petition, Olympic asked the trial court to void the contract awarded to

Easley on the basis of Open Meetings Act violations. In its brief, Olympic mentioned the existence

of alleged fact questions precluding the City’s summary judgment, stating that “[t]ermination

of Appellant’s contract in closed Executive Session would clearly violate the

Act and void the Council action awarding the Easley contract.” Other than this statement, Olympic provided

no argument in support of its theory that it is entitled to have the contract

voided.

Section

551.141 provides that an action taken by a governmental body in violation of

the Open Meetings Act is voidable. Tex. Gov’t Code Ann. § 551.141. Here, while the discussion that took place in

executive session was in violation of the Act, voiding the Easley contract does

not follow. The vote awarding the

contract to Easley took place in open session, after the violation

occurred. The vote was not taken in violation

of the Act. Therefore, Olympic is not

entitled to the remedy of voiding the Easley contract. See United Indep. Sch. Dist. v.

Gonzalez , 911 S.W.2d 118, 128 (Tex. App. –San Antonio 1995, writ

denied) (op. on reh’g).

Conclusion

Due

to application of the new statutory scheme for adjudication of claims arising

under contracts with local governmental entities, we determine that the City’s

immunity from suit was not waived as to Olympic’s breach of contract

claim. Neither was the City’s immunity

waived as to Olympic’s claim for a declaration regarding the continued validity

of the contract. We affirm

the trial court’s order granting the City’s plea to the jurisdiction. Because the evidence shows the City violated

the Open Meetings Act, we reverse the trial court rulings on the

City’s motion for summary judgment and Olympic’s motion for partial summary

judgment and render judgment for Olympic on its Open Meetings Act

claim.

JAMES T. WORTHEN

Chief Justice

Opinion delivered September 29, 2006.

Panel

consisted of Worthen, C.J., Griffith, J., and Hoyle, J .

(PUBLISH)

[1]

COURT OF APPEALS

TWELFTH COURT OF APPEALS

DISTRICT OF TEXAS

JUDGMENT

SEPTEMBER 29, 2006

NO. 12-05-00217-CV

OLYMPIC WASTE SERVICES, A

DIVISION

OF ALLIED WASTE INDUSTRIES,

INC.,

Appellant

V.

THE CITY OF GRAND SALINE,

TEXAS,

Appellee

Appeal from the 294th Judicial District Court

of Van Zandt County, Texas. (Tr.Ct.No.

05-00021)

THIS

CAUSE came to be heard on the appellate record and briefs filed herein, and the

same being inspected, it is the opinion of this Court that there was error in

the judgment as entered by the trial court, and that the same should

be Affirmed in part, and Reversed and Rendered in part.

It is therefore ORDERED,

ADJUDGED and DECREED that that portion of the trial court's ruling on the City

of Grand Saline’s Motion for Summary Judgment and Olympic Waste Services, A

Division of Allied Waste Industries, Inc.’s Motion for Partial Summary Judgment

is Reversed and Judgment is Rendered for Olympic Waste Services, A Division of

Allied Waste Industries, Inc., on its Open Meetings Act Claim . The trial court’s order granting the City of Grand Saline’s Plea to the Jurisdiction is Affirmed ; all costs of court are

taxed against the party incurring same; and that this decision be certified to

the court below for observance.

James T. Worthen, Chief

Justice.

Panel

consisted of Worthen, C.J., Griffith, J., and Hoyle, J.

THE STATE OF TEXAS

M A N D A

T E

*********************************************

TO THE 294TH JUDICIAL DISTRICT COURT

OF VAN ZANDT COUNTY, GREETINGS:

Before

our Court of Appeals for the 12th Court of Appeals District of Texas, on the 29

day of September, 2006, the cause upon appeal to revise or reverse your

judgment between

OLYMPIC

WASTE SERVICES, A DIVISION OF

ALLIED

WASTE INDUSTRIES, INC., Appellant

NO.

12-05-00217-CV; Trial Court No. 05-00021

Opinion by

James T. Worthen, Chief Justice.

THE CITY OF GRAND SALINE, TEXAS, Appellee

was

determined; and therein our said Court made its order in these words:

“ THIS CAUSE came

to be heard on the appellate record and briefs filed herein, and the same being

inspected, it is the opinion of this Court that there was error in the judgment

as entered by the trial court, and that the same should be Affirmed in part, and Reversed and Rendered in part.

It is therefore ORDERED, ADJUDGED and DECREED

that that portion of the trial court's ruling on the City of Grand Saline’s

Motion for Summary Judgment and Olympic Waste Services, A Division of Allied

Waste Industries, Inc.’s Motion for Partial Summary Judgment is Reversed and

Judgment is Rendered for Olympic Waste Services, A Division of Allied Waste

Industries, Inc., on its Open Meetings Act Claim . The trial court’s order granting the City of Grand Saline’s Plea to the

Jurisdiction is Affirmed ;

all costs of court are taxed against the party incurring same; and that this

decision be certified to the court below for observance.”

WHEREAS, WE COMMAND YOU to observe the

order of our said Court of Appeals for the Twelfth Court of Appeals District of

Texas in this behalf, and in all things have it duly recognized, obeyed, and

executed.

WITNESS, THE HONORABLE JAMES T. WORTHEN ,

Chief Justice of our Court of Appeals for the Twelfth Court of Appeals

District, with the Seal thereof affixed, at the City of Tyler, this the ______

day of __________________, 200____.

CATHY

S. LUSK, CLERK

By:_______________________________

Deputy Clerk

1 See Tex.

Gov’t Code Ann. §§ 551.001-.146 ( Vernon

2004 & Supp. 2006).

2 Although the trial court’s ruling also granted

the City’s request for summary judgment on the claim for competitive bidding

violations, Olympic has not appealed from that ruling.

[1] J.9 AFFIRMED in part, REVERSED & RENDERED

in part