Opinion

Reliant Energy, Incorporated and American Electric Power Company v. Public Utility Commission of Texas

Court
Texas Court of Appeals, 3rd District (Austin)
Filed
Feb 6, 2003
Status
Published
Cited by
0 cases
Authority
More cited than 36.0%

The opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-02-00001-CV

Reliant Energy, Incorporated and American Electric Power Company, Appellants

v.

Public Utility Commission of Texas, Appellee

DIRECT APPEAL FROM THE PUBLIC UTILITY COMMISSION OF TEXAS

O P I N I O N

In this direct appeal, we must determine whether the Public Utility Commission erred

in promulgating a rule governing stranded-cost recovery for formerly regulated electric utilities. See

Tex. Util. Code Ann. § 39.001 (e), (f) (West Supp. 2003). Stranded costs represent prudently

incurred expenditures made by the utilities during regulation--previously recoverable over time

through regulated rates--that have become unrecoverable in a deregulated market. Utilities are

permitted to recover their stranded costs as part of the transition to competition in Texas. Reliant

Energy, Incorporated and American Electric Power Company ("AEP") argue that the Public Utility

Commission (1) exceeded its authority by promulgating portions of substantive rule 25.263, which

governs the proceeding where the Commission is to determine whether a utility actually has stranded

costs and to reconcile a utility's actual stranded costs with amounts already recovered based on

previous estimates. We hold that the Commission exceeded its authority in promulgating some of

the challenged portions of its rule and reverse and remand those portions to the Commission for

further proceedings in accordance with this opinion. See Tex. Util. Code Ann. § 39.001 (f). We

affirm the remaining portions of the rule as enacted. See id.

BACKGROUND

In 1975, the legislature enacted the Public Utility Regulatory Act (PURA) creating

the Public Utility Commission and establishing a comprehensive regulatory regime for electric

utilities. At that time, it was thought that electric utilities were natural monopolies, immune from

the normal forces of competition. Under the regulatory regime created by PURA, each utility was

allowed to operate as a monopoly in the area it served but was prohibited from charging monopoly

prices. The Commission was authorized to set rates for each utility at a level that would allow it to

recoup its prudently incurred costs and to earn a reasonable return on its investments. (2) See 16 Tex.

Admin. Code §§ 25.231 , .235(a) (2002); see also Central Power & Light Co. v. Public Util.

Comm'n , 36 S.W.3d. 547, 553 (Tex. App.-- Austin 2000, pet. denied) (describing utility ratemaking

procedure under regulation).

When the legislature enacted PURA most electric utilities were large vertically

integrated companies that produced, transported, and retailed electricity. In truth, only one

component of a vertically integrated electric utility immunizes it from the normal forces of

competition --its transmission and distribution infrastructure. Recognizing this, the legislature

amended PURA in 1999 and partially deregulated the industry. Among its "policies and purposes,"

the legislature found that:

[T]he production and sale of electricity is not a monopoly warranting regulation of

rates, operations, and services and that the public interest in competitive electric

markets requires that, except for transmission and distribution services and for the

recovery of stranded costs, electric services and their prices should be determined by

customer choices and the normal forces of competition.

Tex. Util. Code Ann. § 39.001 (a) (West Supp. 2003).

Chapter thirty-nine of PURA governs the restructuring of the electric-utility industry.

As of January 1, 2000, each privately owned electric utility was required to "unbundle" or separate

into the following entities: a power generation company, a retail electric provider, and a transmission

and distribution utility. See id. § 39.051(b) (West Supp. 2003). The former vertically integrated

utilities can now operate as holding companies that own affiliated unbundled entities. See id.

§ 39.051(c) (West Supp. 2003). Under deregulation, the power generation and retail markets are to

be governed by "customer choices and the normal forces of competition," while the Commission is

to continue to regulate transmission and distribution utilities. See i d . § 39.001(a). The Commission

is also charged with facilitating stranded-cost recovery for the formerly regulated utilities. See id.

Chapter thirty-nine defines stranded costs as "the positive excess of the net book

value of generation assets over the market value of those assets. . . ." See id. § 39.251(7) (West

Supp. 2003). The basic concept of stranded costs is straightforward. Under regulation, a utility

could recover over time its prudently incurred costs of acquiring power-generation assets through

rates approved by the Commission and paid by captive customers. See Central Power & Light Co. ,

36 S.W.3d at 552-53. The Commission facilitated this cost recovery by incorporating depreciation

expenses into approved rates. See id. at 53. But in a deregulated environment, it was thought that

competition might drive rates to levels so low that a formerly regulated utility would be unable to

recoup its investments. Stranded costs represent that portion of the net book value of a utility's

generation assets not yet recovered through depreciation that has become unrecoverable in a

deregulated environment. See City of Corpus Christi v. Public Util. Comm'n , 51 S.W.3d 231, 237-38 (Tex. 2001); Tex. Util. Code Ann. § 39.251 (7).

Chapter thirty-nine sets out a three-stage program for the recovery of stranded costs.

In the first stage, from September 1999 to December 2001, the Commission froze retail electric rates.

See Tex. Util. Code Ann. §§ 39.052 (a), .254-.256 (West Supp. 2003). During this stage, utilities

identified as having probable stranded costs (3) were required to "mitigate" them through various

measures intended to reduce the book value of their generation assets. See id. They could shift

depreciation from transmission and distribution assets to generation assets, id. § 39.256; they could

keep earnings in excess of the allowed rate of return, id. § 39.254. These utilities were also allowed

to "securitize" a portion of their estimated stranded costs by selling transition bonds and using the

proceeds to reduce the book value of their generation assets. See id. §§ 39.301-.313 (West Supp.

2003). The costs of issuing and servicing transition bonds are borne by all retail customers in a

utility's service area through a nonbypassable "transition charge." See id. §§ 39.302(7), .303(b), (c);

City of Corpus Christi , 51 S.W.3d at 239 . Because the Commission estimated in 1998 that the

appellant utilities would have significant stranded costs in a deregulated environment, each utility

used the available mitigation procedures and securitization to reduce the book value of their

generation assets during this stage of PURA's stranded-cost recovery program. (4)

The second stage began on January 1, 2002, the first day of competition. See Tex.

Util. Code Ann. §§ 39.001 (b)(1), .201 (West Supp. 2003). During this stage, the Commission was

authorized to set a nonbypassable "competition transition charge" to allow utilities to recover any

stranded costs remaining after the mitigation procedures and securitization utilized in stage one . See

generally id. § 39.201. Any competition transition charge was to be included in the tariffs of a

utility's affiliated unbundled transmission and distribution utility. See id. § 39.201(b)(3). In

determining whether to set such a charge, the Commission was required to revise its previous

stranded-cost estimates using "updated company-specific inputs." See id. § 39.201(h).

In preparation for the rate hearings for the transmission and distribution utilities to

be held in 2001, the stranded cost estimates were updated. The Commission's updated estimates

unexpectedly reflected that the utilities would have no stranded costs. (5) A substantial increase in

natural gas prices in 2000 had driven the market value of the utilities' generation assets well above

their book value. These new estimates therefore indicated that some utilities had been

overcompensated by their earlier mitigation procedures and securitization.

In light of these revised estimates, the Commission issued orders requiring the

utilities to discontinue all mitigation efforts, to reassign the depreciation transferred from

transmission and distribution assets back to those assets, and to return monthly "excess mitigation

credits" to retail providers and their ratepayers. The Commission did not, however, require the

utilities to refund the amounts they had received from selling transition bonds, and by statute it could

not alter the transition charge that had been imposed on ratepayers to service the bonds. See id.

§ 39.303(d) (Transition charge authorized in financing order is "irrevocable and not subject to

reduction, impairment, or adjustment by further action of the commission . . . ."). Utilities that had

sold transition bonds to recover stranded costs no longer anticipated would seem to have received

a windfall at the ratepayers' expense.

The third and final stage of stranded-cost recovery is yet to occur. This stage requires

the Commission to conduct a "true-up proceeding" sometime after January 10, 2004, to determine

whether a utility actually has remaining stranded costs. See id. §§ 39.201(l), .262(c) (West Supp.

2003). The challenged rule governs the conduct of this true-up proceeding. See 16 Tex. Admin.

Code § 25.263 (2002). The goal of the true-up proceeding in this third stage is to determine the

utility's actual stranded costs and to reconcile or true up this determination with its previous

estimates. See Tex. Util. Code Ann. §§ 39.201 (l), .262(c). This final determination is to be based

on a new calculation of the value of a utility's generation assets made under actual competitive

conditions. See id. The Commission is required to subtract the market value of a utility's generation

assets from the book value of those assets. (6) See id. §§ 39.251(7), .252(a), .262(c), (h), (i) (West

Supp. 2003). If the calculation yields a positive number, i.e. , if the book value of the assets exceeds

their market value, then the utility has stranded costs it is entitled to recover. If the calculation yields

a negative number, i.e. , if the market value of the assets exceeds their book value, the utility has no

stranded costs--and chapter thirty-nine does not provide for any return to ratepayers of so called

"negative stranded costs." If this true-up proceeding reveals that the utilities over-recovered

estimated stranded costs through their earlier mitigation efforts, the Commission can make

appropriate adjustments by, among other things, reducing the unbundled transmission and

distribution utility's rates. See id. § 39.201(l). The Commission cannot, however, reduce the

transition charge imposed on ratepayers to service transition bonds. See id . § 39.303(d).

In addition to finalizing stranded costs, chapter thirty-nine also requires that the

Commission make several other "true-up" calculations in the 2004 proceeding that could affect

customer rates. See id. § 39.262(d)-(g) (West Supp. 2003). These calculations reconcile previous

estimates with known values in various areas and result in either credits or bills to the transmission

and distribution utility from its affiliated power generation company or retail electric provider. See

generally id . Based on these credits or bills, the transmission and distribution utility is to make

adjustments to its nonbypassable delivery rates. See id. § 39.262(g).

One of these several other true-up calculations involves the determination of a

utility's final fuel balance. See id. §§ 39.202(c), .262(d)(1) (West Supp. 2003). In the 2004

proceeding, the Commission must true up the actual cost of fuel incurred by the utility against the

prior estimate used to set the "fuel factor" component of regulated rates during the final period of

traditional regulation. See id. A positive fuel balance represents money owed to the utility for

under-recovered fuel costs. (7) See id . The challenged portion of rule 25.263 would reduce this

positive fuel balance owed to the utility by any negative stranded-cost calculation--regardless of

whether the negative calculation was caused by market forces or by previous over-recovery through

securitization. See 16 Tex. Admin. Code § 25.263 (l).

The utilities argue that there is no such thing as negative stranded costs. They also

complain that the fuel balance is not a stranded cost and therefore cannot be "netted" against a

negative stranded-cost calculation. In other words, according to the utilities, the true-up proceeding

was never intended to reconcile a negative stranded-cost calculation against a positive fuel-balance

calculation to reduce the amount due to the utility for under-recovered fuel costs. The Commission

insists that it has a mandate to prevent a utility from receiving an over-recovery of stranded costs and

that offsetting sums due for a positive fuel balance is a permissible means of reversing an over-recovery of stranded costs achieved through securitization. We begin our analysis by examining how

the rule works.

THE RULE

Rule 25.263 requires the relevant portion of the true-up proceeding to be conducted

in four steps. First, the Commission subtracts the newly calculated market value (8) of the utility's

generation assets from the net book value of those assets. According to the statute, if this number

is positive, the utility has recoverable stranded costs; if it is negative, the utility has no stranded

costs. (9) See Tex. Util. Code. Ann. §§ 39.251(3), (7), .252(a) (West Supp. 2003). A negative number

may be due to over-recovery of stranded costs that reduced the book value of assets during the first

stage, but it may also result from unrelated market conditions that increased the market value of the

assets.

Second, the Commission calculates the utility's final fuel balance, which is the

difference--positive or negative--between the estimated cost of fuel that was used to set the utility's

rates for the final period of regulation and the actual cost of fuel for that period. Under the prior

regulatory regime, this amount would have been included--as a credit or charge--in the rates set at

the utility's next ratemaking proceeding. Under the challenged section of rule 25.263, this final fuel

balance is netted against the actual stranded costs determined in step one. Thus, a negative stranded

cost calculation could reduce or eliminate a positive fuel balance owed to the utility.

Third, the Commission calculates a "capacity-auction true-up" amount, which is the

difference between the price the utility, or its unbundled power generation affiliate, was estimated

to obtain for its power on the wholesale market in the second stage and the price the utility actually

received during the first two years of competition. See 16 Tex. Admin. Code §§ 25.263 (i), (l)

(2002). The actual market price is reflected in "capacity auctions" in which the utility sold its

entitlements to generation capacity to reduce its market share as a part of the transition to

competition. See Tex. Util. Code Ann. §§ 39.153 , .156 (West Supp. 2003). The capacity-auction

true-up amount must then be netted against the amount reached in step two by netting the stranded

costs determined in step one with the fuel balance.

Fourth, and finally, the Commission will conduct a prudence review of regulatory

assets (10) not previously approved in a prior Commission rate order but being recovered through

securitization in the form of a transition charge or through a competition transition charge imposed

during the second stage of stranded-cost recovery. See 16 Tex. Admin. Code § 25.263 (l) (2002).

If the Commission determines that these assets were not prudently incurred, it will subtract them

from the true-up balance as determined in steps one through three. If the resulting final true-up

balance is positive, the utility will be entitled to recover that amount through a competition transition

charge assessed to its transmission and distribution customers. See id. § 25.263(l)(2)(A). If

negative, the Commission will (1) reverse any existing competition transition charge, then (2)

reverse any remaining mitigation proceeds, then (3) impose on utilities that have sold transition

bonds a negative competition transition charge based on the lesser of the absolute value of the

remaining negative true-up balance or the amount the utility has securitized. See id.

§ 25.263(l)(2)(C).

DISCUSSION

This is a direct challenge to the validity of a chapter thirty-nine competition rule. See

Tex. Util. Code Ann. § 39.001 (e). The utilities allege that certain portions of the rule exceed the

Commission's statutory authority. (11) See id. ; see generally City Pub. Serv. Bd. v. Public Util.

Comm'n , No. 3-00-007-CV, slip op. at 8, 2002 Tex. App. LEXIS 2059 , at *12 (Tex. App.

Austin--Mar. 21, 2002, no pet.). An administrative agency has only those powers conferred upon

it by clear and unmistakable language. Public Util. Comm'n v. City Pub. Serv. Bd. , 53 S.W.3d 310,

315-16 (Tex. 2001). When the legislature expressly confers a power on an agency, it also impliedly

intends that the agency have whatever powers are reasonably necessary to fulfill its express functions

or duties. Public Util. Comm'n v. GTE-Southwest, Inc. , 901 S.W.2d 401, 407 (Tex. 1995). An

agency may not, however, exercise what is effectively a new power on the theory that such exercise

is expedient for the agency's purposes. Id. at 407 . We must therefore determine whether the

Commission had either the express or implied authority to promulgate the challenged aspects of its

rule that will govern the 2004 true-up proceedings.

Netting

PURA provides that "[a]n electric utility is allowed to recover all of its net, verifiable,

nonmitigable stranded costs incurred in purchasing power and providing electric generation service."

Tex. Util. Code Ann. § 39.252 (a). The utilities challenge the Commission's authority to net a

utility's final stranded-cost calculation with other true-up items such as a utility's final-fuel balance.

The Commission defends its rule arguing that (1) these other true-up items are themselves potential

stranded costs and, (2) even if they are not, netting is a permissible means of preventing over-recovery of stranded costs by those utilities that received a windfall through securitization.

PURA defines stranded costs as follows:

"Stranded costs" means the positive excess of the net book value of generation assets

over the market value of those assets, taking into account all of the electric utility's

generation assets, any above market purchased power costs, and any deferred debit

related to a utility's discontinuance of the application of Statement of Financial

Accounting Standards No. 71 [ i.e. , unrecovered regulatory assets].

Tex. Util. Code Ann. § 39.251 (7). PURA further defines generation assets as follows:

"Generation assets" means all assets associated with the production of electricity,

including generation plants, electrical interconnections of the generation plant to the

transmission system, fuel contracts, fuel transportation contracts, water contracts,

lands, surface or subsurface water rights, emissions-related allowances, and gas

pipeline interconnections.

Id. § 39.251(3).

As described above, at the true-up proceeding, the Commission is required to

calculate a utility's actual stranded costs by subtracting the market value of its generation assets from

their book value. If this number is negative, i.e. , if the market value of those assets exceed their book

value, it is undisputed that the utilities are not required to refund this negative amount to the

ratepayers. Under chapter thirty-nine, there is simply no concept of negative stranded costs and no

consequence of a negative calculation.

Chapter thirty-nine defines stranded costs as "the positive excess of net book value

of generation assets over the market value of the assets." See id. § 39.252(7) (emphasis added).

Because we presume that each word in a statute has meaning, the word "positive" must be given

effect. See Southwestern Life Ins. Co. v. Montemayor , 24 S.W.3d 581, 584 (Tex. App.--Austin

2000, pet. denied). Stranded costs therefore exist only when the book value of a utility's generation

assets exceeds their market value. If book value is equal to or less than market value, then there are

no stranded costs. The term "negative stranded costs" appears nowhere in chapter thirty-nine, and

there are no statutory provisions providing for recovery by ratepayers of the excess market value over

cost.

The fact that chapter thirty-nine does not recognize the concept of negative stranded

costs motivates the Commission's argument that all the true-up items represent stranded costs and

that the netting required under its rule will determine actual stranded costs. The utilities protest that

the other true-up items do not comprise stranded costs as they are defined in chapter thirty-nine and

cannot be offset by a negative stranded-cost calculation. They focus particularly on showing that the

final-fuel balance has nothing to do with stranded costs. The Commission responds by arguing that

because coal, gas, nuclear, and other types of fuel are "indisputably assets associated with the

production of electricity," they constitute generation assets that could become stranded. We reject

the Commission's attempt to define these items as stranded costs.

Under the prior regulatory regime, the approved rates for a utility always included a

"fixed fuel factor," which was based on a projection of future fuel costs. 16 Tex. Admin. Code

§ 25.237 (2002). The Commission periodically adjusted this fuel factor, and at least every three

years the fuel revenues the utility received under the factor were "reconciled" with the fuel costs the

utility actually incurred. See Tex. Util. Code § 36.203 (West 1998); 16 Tex. Admin. Code § 25.236

(2002); see also Nucor Steel v. Pub. Util. Comm'n , 26 S.W.3d 742, 744-45 (Tex. App.--Austin

2001, pet. denied). Chapter thirty-nine, section 36.202(c) simply postpones the fuel reconciliation

for the final period of regulation until the 2004 true-up proceeding, at which time any under-recovered fuel balances will be surcharged.

The statutory structure of chapter thirty-nine also indicates that the legislature did not

consider a final fuel balance to be a stranded cost. Stranded costs and the final fuel balance are

determined and recovered under separate sections of chapter thirty-nine.

Stranded costs are determined and recovered under sections 39.201(l) and 39.262(c).

Section 39.201(l) provides: "[t]wo years after customer choice is introduced, the stranded cost

estimate under this section [ i.e. , the stage-two stranded-cost estimate] shall be reviewed and, if

necessary, adjusted to reflect a final, actual valuation in the true-up proceeding under Section

39.262." Tex. Util. Code Ann. § 39.201 (l). Section 39.262(c) provides:

After January 10, 2004 . . . each transmission and distribution utility, its affiliated

retail electric provider, and its affiliated power generation company shall jointly file

to finalize stranded costs under Subsections (h) and (i) and reconcile those costs with

the estimated stranded costs used to develop the competition transition charge in the

proceeding held under Section 39.201.

Id. § 39.262(c). Subsections (h) and (i) set out methods for quantifying the market value of a utility's

generation assets and calculating its stranded costs. Significantly, the final fuel balance does not

figure into this calculation.

Under-recovered fuel costs are determined and recovered under section 39.202(c) and

39.262(d)(1). Section 39.202(c) provides: "[a]fter the date of customer choice, each affiliated power

generation company shall file a final fuel reconciliation for the period ending the day before the date

customer choice is introduced . . . [which will be] included in the true-up proceeding." Id.

§ 39.202(c). Section 39.262(d)(1) provides "the affiliated power generation company shall reconcile,

and either credit or bill to the transmission and distribution utility, the net sum of . . . the former

electric utility's final fuel balance . . . and [the capacity-auction true-up amount]." Id. § 39.262(c).

Stranded costs and the final fuel balance are distinct concepts treated separately in

the statute. If the legislature wanted to define an under-recovered fuel balance as a stranded cost it

could have done so explicitly, or it could have easily included the impact of the final fuel

reconciliation in the market valuation of a utility's generation assets under section 39.262(c), (h), and

(i). The fact that the legislature treated the fuel balance separately shows that it did not intend it to

be a component of a stranded-cost calculation.

The same is true of the other true-up items. The capacity-auction true-up amount is

the difference between the price the utility, or its unbundled power generation affiliate, was

estimated to obtain for its power on the wholesale market in the second stage of stranded-cost

recovery and the price the utility actually received during the first two years of competition.

Although there is a closer nexus between this true-up item and the final determination of stranded

costs, the legislature chose not to include this item in its definition of stranded costs or to incorporate

it into the methods it prescribes for calculating stranded costs. Moreover, the legislature specifically

mandated that this item be netted with the final fuel balance. Id. § 39.262(d).

Chapter thirty-nine seems to contemplate two parallel true-up tracks--one for

stranded costs and one for the several other true-up items. Separate portions of chapter thirty-nine

govern the effects that the calculations under each track are to have on rates. Compare id.

§ 39.262(c), with id. § 39.262(g). Although the calculation under each track can be applied to adjust

the transmission and distribution utility's nonbypassable rates, the utilities are authorized to

securitize any remaining stranded costs but not positive balances associated with the other true-up

items. Id § 39.262(c). In some circumstances, performing two parallel true-up calculations, as the

statute provides, and performing a single true-up calculation that nets stranded costs against all the

true-up items, as the rule requires, would result in identical adjustments to rates. However, netting

the stranded-cost calculation with the other true-up items can cause an impermissible offset of

amounts due a utility whenever the market value of its generation assets exceed their book value, i.e. ,

when it has no stranded costs. See generally id. §§ 39.252(a) (a utility is allowed to recover all its

net verifiable stranded costs), .262(c)-(i) (contemplating two parallel true-up tracks).

We thus reject the Commission's argument that the other true-up items represent

stranded costs. We agree with the utilities that the statute does not contemplate a negative stranded-cost calculation and does not contemplate any consequence to ratepayers if the stranded-cost

calculation produces a negative number. The rule that would net a negative stranded-cost calculation

against a positive balance produced from the other true-up items is not authorized by the statute.

Indeed, it directly contradicts the legislature's intent that a positive stranded-cost calculation has

significance while a negative calculation simply means that a utility is not entitled to recovery of

stranded costs. By collapsing two parallel true-up tracks into a combined calculation, the rule

impermissibly allows a negative stranded-cost calculation to offset positive balances due from other

true-up items. The statute does not require a utility to refund a negative calculation of stranded costs

to ratepayers and the Commission may not require such a refund by calling these other true-up items

stranded costs.

Reversing Securitization Over-Recoveries

We now turn to the Commission's claim that even so, netting the calculations is a

permissible means of preventing over-recovery of stranded costs by those utilities that received a

windfall through securitization. When the legislature provided for mitigation and securitization of

estimated stranded costs, it did so with the proviso that the Commission must ensure that no utility

over-recover its stranded costs. See id. § 39.262(a). The utilities that were estimated in the first

stage to have stranded costs received substantial sums of money or its equivalent through mitigation

and securitization proceeds. When the revised stranded-cost estimate showed that these utilities

were likely to have no stranded costs, the Commission required the utilities to disgorge their

mitigation proceeds through excess mitigation credits. As previously noted, however, the

Commission could not reverse the transition charge imposed on ratepayers to finance the bonds that

the utilities had sold. See id . §§ 39.201(l)(1), .303(d).

When the legislature expressly confers a power on an agency, it also impliedly intends

that the agency have whatever powers are reasonably necessary to fulfill its express functions or

duties. Public Util. Comm'n , 53 S.W.3d at 316 . Chapter thirty-nine requires the Commission to see

that utilities do not over-recover their stranded costs. The Commission argues that netting the

various true-up items is a permissible way to prevent over-recovery--effectively forcing the utilities

that sold transition bonds based on earlier invalid stranded-cost estimates to disgorge amounts to

which they are not entitled.

While we agree with the Commission that it has the implied power to attempt to

reverse over-recovery of stranded costs through netting, we find its rule to be overbroad. An agency

may not exercise what is effectively a new power on the theory that such exercise is expedient for

the agency's purposes. GTE-Southwest, Inc ., 901 S.W.2d at 407 . The Commission's rule does not

limit the amount by which a negative stranded-cost calculation can offset other positive true-up

balances to a utility's previous over-recovery. See 16 Tex. Admin. Code. § 25.263(l). We hold that

the Commission has the discretion to net a negative stranded-cost calculation against the other true-up items only to the extent that the utility over-recovered stranded costs through securitization.

For example, a utility that entered the first stage of stranded-cost recovery with

generation assets having a book value of 3x and an estimated market value of 1x would have been

required to mitigate or securitize estimated stranded costs of 2x. Assume that this utility sold

transition bonds and removed 2x from its books, reducing its book value to 1x. If the market value

of this utility's generation assets has risen to 3x at the time of the true-up proceeding, the updated

stranded-cost calculation will yield a negative 2x indicating that it has no actual stranded costs. But

to the extent the book value was reduced by the proceeds of securitization, the utility appears to have

over-recovered 2x when it received its bond proceeds. This is true because the original book value

of 3x would not have exceeded the increased market value of 3x, even had the utility never received

bond proceeds of 2x. The full 2x would represent an over-recovery of stranded costs that the utility

did not have. This amount, but no more, may be netted against other sums to prevent over-recovery.

The Commission must conduct parallel true-up calculations for stranded costs and

the other true-up items. Only in those limited circumstances where a negative calculation of stranded

costs results from the reduction of book value by securitization may the Commission devise a rule

to offset any windfall received through securitization against the positive balance due the utility for

the other true-up items. If a utility's stranded-cost calculation would have been negative even if it

had never sold transition bonds, then the full amount of its bond proceeds represents an over-recovery which can be netted against the other true-up items. On the other hand, if a utility would

have had a positive stranded-cost calculation but for the fact that it sold the bonds, i.e. , if it would

be entitled to recover stranded costs had it never reduced its book value through securitization, the

Commission is limited to netting the amount by which the bond proceeds exceeded the actual

stranded costs it would have recovered. (12)

Reliant argues that it should not be required to disgorge any over-recovery it may

have received through securitization. Its basic complaint seems to be that the Commission's rule

does not account for the fact that securitization substantially reduces the book value of a utility's

generation assets. We believe that our formulation--requiring the Commission to consider what a

utility's stranded-cost calculation would have been absent securitization--addresses this concern. (13)

In no circumstances may a negative stranded-cost calculation attributable to market

conditions be netted against a positive fuel balance or other such true-up calculation. We sustain the

challenge to the rule because it does not limit the netting of negative stranded-cost calculations to

prevent over-recovery attributable to securitization. The Commission has the statutory authority to

prevent over-recovery of stranded costs through securitization. It has no statutory authority to net

negative stranded costs attributable to market forces. (14)

Partial Stock Valuation Method

One of the Commission's most important responsibilities during the true-up

proceeding is to calculate the market value of a utility's generation assets. See generally Tex. Util.

Code Ann. § 39.262 (h). Chapter thirty-nine sets out several different methods that the Commission

may use to make this calculation. See id . The utilities claim that the Commission exceeded its

authority in promulgating portions of its rule that implement "the partial stock valuation method."

See generally id. § 39.262(h)(3); 16 Tex. Admin. Code § 25.263 (f)(1)(C) (2002).

The Commission is authorized to use the partial stock valuation method to establish

the value of generation assets when a utility has transferred some or all of those assets to affiliated

or nonaffiliated corporations and between nineteen and fifty-one percent of the common stock of

each such corporation is spun off and sold to public investors through a national stock exchange and

traded for one year or more. See Tex. Util. Code Ann. § 39.262 (h)(3). The Commission is

authorized to calculate the value of the assets held by the transferee corporation, presumably an

unbundled power generation company, by adding the market value of its common stock to the book

value of its preferred stock and its debt. See id. ; see generally 16 Tex. Admin. Code

§ 25.263 (f)(1)(C)(viii).

A. Control Premium

The average daily closing price over thirty consecutive trading days, chosen by the

Commission, with some constraints, is generally presumed to establish the market value of the

common stock. See Tex. Util. Code Ann. § 39.262 (h)(3). The Commission, however, is also

authorized to convene a panel of financial experts to determine whether a control premium exists

for the retained common stock. Id . A control premium is the additional value that a block of shares

obtains by virtue of the fact that it carries with it the power to control the corporation. See Black's

Law Dictionary 1200 (7th ed. 1999). "The control premium is often computed by comparing the

aggregate value of the controlling block of shares with the cost that would be incurred if the shares

could be acquired at the going market price per share." Id .

The utilities challenge the way that the control premium is calculated under the

Commission's rule.

Section 39.262(h)(3) of PURA specifically provides:

The [C]ommission may accept the market valuation to conclusively establish the

value of the common stock equity in each transferee corporation or convene a

valuation panel of three independent financial experts to determine whether the

percentage of common stock sold is fairly representative of the total common stock

equity or whether a control premium exists for the retained interest . . . . If the panel

determines that a control premium exists for the retained interest , the panel shall

determine the amount of the control premium, and the [C]ommission shall adopt the

determination but may not increase the market value by a control premium greater

than 10 percent .

Tex. Util. Code Ann. § 39.262 (h)(3) (emphasis added). The Commission's rule, however, provides:

If the panel determines that a control premium exists for the retained interest, the

panel shall determine the amount of the control premium, and the [C]ommission

shall adopt the determination, but may not use the control premium to increase the

value of the assets by more than 10%.

16 Tex. Admin. Code § 25.263 (f)(1)(C)(v) (emphasis added). The utilities argue that the statute only

allows the Commission to apply the control premium to increase the value of the retained common

stock equity by up to ten percent. They claim that the rule is invalid because it instead allows the

Commission to apply the control premium to increase by up to ten percent the value of all the

corporation's assets. (15) The Commission responds that while the statute prohibits it from

"increas[ing] the market value by a control premium greater than 10 percent," see Tex. Util. Code

Ann. § 39.262 (h)(3), the statute does not specify "[ten] percent" of what and that we should defer

to its interpretation.

We may not add words to a statute unless necessary to give effect to legislative intent.

Southwestern Life Ins. , 24 S.W.3d at 583 . The Commission essentially asks us to add the words "of

all the corporation's assets" to the end of the statutory phrase "by a control premium no greater than

10 percent." But the meaning of the phrase is unmistakable without such an addition. Because a

control premium represents value added to a retained block of shares, a "control premium of ten

percent" would naturally increase the value of the retained block of shares by ten percent. Similarly

the phrase "by a control premium no greater than 10 percent" is limited to increasing the value of

the retained block of shares by no more than ten percent. We agree with the utilities that the

Commission exceeded its authority by enacting the portion of its rule that would apply the control-premium cap to all of the corporation's assets.

B. "Other Admitted Evidence "

Reliant also complains that the rule impermissibly allows the Commission to second-guess the findings of the valuation panel. Chapter thirty-nine , section 39.262(h)(3) requires a

valuation panel consisting of three financial experts chosen from the top ten nationally recognized

investment banks with demonstrated experience in the electric industry of the United States. Tex.

Util. Code Ann. § 39.262 (h)(3). It then provides, "[i]f the panel determines that a control premium

exists for the retained interest, the panel shall determine the amount of the control premium, and the

commission shall adopt the determination [subject to the ten-percent cap]." Id. (emphasis added).

The statute further provides that "the determination of the commission based on the finding of the

panel conclusively establishes the value of the common stock in each transferee corporation." Id.

Rule 25.263, however, states that the Commission is to determine the value of the common stock

of the transferee corporation "based on the findings of the Commission and other admitted

evidence ." See 16 Tex. Admin. Code 25.263(f)(1)(C)(vii) (2002) (emphasis added).

The Commission argues that the language "other admitted evidence" was intended

only to allow for consideration of evidence relating to issues other than the panel's substantive

finding, such as the Commission's obligation to reduce any control premium by ten percent, or to

ensure that the panel was properly constituted in accordance with the statute. See Tex. Util. Code

Ann. § 39.262 (h)(3). It claims that if the rule is applied in a way that fails to respect the panel's

determination, the proper place to challenge it is at the true-up proceeding.

By requiring that the Commission "shall adopt" the panel's control-premium

determination, the legislature signaled its intent that the valuation of the panel be conclusive. The

extra-statutory language of the rule, as written , allows the Commission to consider whatever

evidence it chooses to increase the value of the common stock. The Commission cannot simply

confer this authority on itself without legislative approval. See Ford Motor Co. v. Motor Vehicle Bd.

21 S.W.3d 744, 764 (Tex. App.--Austin 2000, pet. denied) (an agency "may not, on a theory of

necessary implication from a specific power, function, or duty expressly delegated, erect and exercise

a new or additional power or a power that contradicts the statute").

The Commission is also wrong to contend that Reliant's complaint is not properly

brought as a validity challenge. It cannot promulgate a rule granting to itself a power in

contradiction of its legislative mandate, and then claim that because it intends to interpret the rule

narrowly that the issue is somehow one of application and not validity. We sustain the challenge to

this portion of the rule. (16)

Interest

A utility found to have stranded costs at the true-up proceeding must either securitize

those costs or recover them over time through nonbypassable rates. See Tex. Util. Code Ann.

§ 39.262 (c) ; 16 Tex. Admin. Code § 25.263 (l)(2)(A) (2002). For a utility that does not securitize

its stranded costs, full recovery may take a number of years. Rule 25.263 provides that if a utility

is found to have stranded costs at the true-up proceeding, then its unbundled transmission and

distribution affiliate "shall be allowed to recover . . . carrying costs [ i.e. , interest] on the true-up

balance." See 16 Tex. Admin. Code § 25.263 (l)(3) (2002). Because of the time value of money, this

interest represents a portion of the "net, verifiable, nonmitigable stranded costs" that the utility is

entitled to recover under chapter thirty-nine. See generally Tex. Util. Code Ann. § 39.252 (a). The

rule further provides that interest shall be calculated from the date that the final true-up order is

issued until stranded costs are fully recovered. See 16 Tex. Admin. Code § 25.263 (l)(3).

The utilities argue that the rule's provision for interest is deficient. They claim that

interest should be calculated to accrue from January 1, 2002, the first day of competition, because

this is when costs became "stranded." The Commission rejoins that stranded costs do not magically

arise on the first day of competition, but, for purposes of stranded-cost recovery under chapter thirty-nine, come into existence only after the true-up proceeding. We agree with the Commission.

The true-up proceeding determines whether a utility has any actual stranded costs.

See Tex. Util. Code Ann. § 39.201 (l), .262(c). At that time, the Commission is to determine a

utility's stranded costs by comparing the market value of the utility's generation assets with their

book value. The utilities attach some significance to the fact that the stranded-cost calculation is to

use the book value of December 31, 2001--the last day of regulation. See Tex. Util. Code Ann. §

39.251 (7). They contend that this indicates that the true-up proceeding actually determines the

amount of stranded costs that existed on the first day of competition. This contention is false. While

the book value to be used by the Commission at the true-up proceeding is to be determined as of

December 31, 2001, its calculations are to be based on the market value as determined in the

proceeding. See id . § 39.262(h). This market value may fluctuate widely between the first day of

competition and the date of the true-up proceeding. Moreover, a formerly regulated utility enters the

first day of competition with its preexisting customer base intact, i.e. , the utility's affiliated retail

electric provider inherits the retail customers in the former utility's service area. In the first few

years of competition--before the 2004 true-up proceeding--a utility can take steps to increase the

market value of its generation assets by simply participating in the market. (17)

That the legislature chose the last day of regulation as the day for measuring book

value is inconsequential. After competition is introduced, a utility no longer accrues "book value,"

because such a concept is meaningless outside of the former regulatory system. We reject the

utilities' argument that their actual stranded costs all accrued on the first day of competition.

Reliant makes an additional argument that interest on at least a portion of its

recoverable stranded costs should accrue from the first day of competition. It claims that "[t]o the

extent Reliant . . . has stranded costs in 2004, the Commission's 2001 stranded-cost estimates [which

resulted in reversal of Reliant's earlier mitigation efforts] will have been incorrect" and Reliant will

have been deprived of the opportunity to recover its stranded costs through early mitigation. See

generally Tex. Util. Code Ann. §§ 39.201 (d)-(l), .254, .256. It therefore contends that interest on

any stranded costs attributable to reversed mitigation should accrue from the time that it is required

to issue excess mitigation credits. This argument lacks merit. The duty to utilize the statute's

mitigation procedures was predicated on stranded-cost estimates , see id. , and a utility's right to fully

recover its stranded costs does not encompass a right to early mitigation . (18) See id. 39 .252(a).

AEP also argues that providing for interest to accrue only from the date of the final

order is arbitrary and capricious because orders affecting different utilities will likely be issued on

different dates. This argument also lacks merit. Normal "regulatory lag" is considered to be an

element of risk borne by a utility. See State v. Public Util. Comm'n , 883 S.W.2d. 190, 196 (Tex.

1994). The utilities therefore are not entitled to revenues lost due to the time it takes to conduct the

true-up proceeding.

We overrule the utilities' issues challenging section 25.236(l)(3) of the Commission's

competition rule and hold that the Commission's provision for interest is adequate to provide the

utilities with full recovery of their stranded costs.

Failure to Reduce Potential Stranded Costs

Because recoverable stranded costs are determined according to the market value of

generation assets as measured in the 2004 true-up proceeding, any move that increases the market

value of these assets before the true-up proceeding will potentially reduce a utility's stranded-cost

recovery. For utilities with significant unrecovered book value there will be no competitive-market

incentive to maintain or increase the market value of their assets until after the true-up proceeding.

Chapter thirty-nine addresses this lack of market incentive by creating a statutory

incentive. It provides that utilities are only allowed to recover stranded costs that are

"nonmitigable," see Tex. Util. Code Ann. § 39.252 (a), and requires "an electric utility . . . [to] pursue

commercially reasonable means to reduce its potential stranded costs, including good faith attempts

to renegotiate above-cost fuel and purchased power contracts or the exercise of normal business

practices to protect the value of its assets." See id. § 39.252(d). To enforce this requirement the

legislature mandated that "the [C]ommission shall consider the utility's efforts under this subsection

when determining the amount of the utility's stranded costs; provided, however, that nothing in this

section authorizes the [C]ommission to substitute its judgment for a market valuation of generation

assets determined under Sections 39.262(h) and (i)." Id.

Rule 25.263(e)(4) implements this section. It provides that the Commission will

determine at the true-up proceeding whether the utility, through its unbundled successor affiliates,

has pursued commercially reasonable means to reduce its stranded costs. It further provides that if

the [C]ommission finds that a utility's successor affiliates "have failed, individually or in

combination, to fully comply with their obligations under PURA § 39.252(d), the [C]ommission may

reduce the net book value of the . . . [affiliated power generation company's] generation assets or

take other measures it deems appropriate in the true-up proceeding filed under this section." See 16

Tex. Admin. Code § 25.263 (e)(4) (2002).

AEP and Reliant each challenge this portion of the rule, but on different grounds.

AEP claims that a utility's duty to reduce its potential stranded costs ended once it unbundled into

successor affiliates, while Reliant argues that the Commission lacks the authority to reduce the book

value of generation assets. We reject both arguments.

AEP claims that unbundled power generation companies and retail electric providers

are not required to reduce their potential stranded costs. It argues that these successor affiliates have

no such duty because section 39.252(d) imposes the duty on "[a]n electric utility" and PURA's

general definition of electric utility specifically excludes power generation companies and retail

electric providers. See Tex. Util. Code Ann. § 31.002 (6). This argument cannot survive close

scrutiny because it requires us to construe portions of the statute in isolation and would lead to

absurd results. See Southwestern Life Ins., 24 S.W.3d at 583-85 .

Section 39.252(a) grants the right to recover stranded costs to "an electric utility."

Tex. Util. Code Ann. § 39.252 (a). Section 39.252(d) imposes the duty to pursue commercially

reasonable means to reduce potential stranded costs on "an electric utility," and requires the

commission to consider "the utility's" efforts when determining the amount of stranded costs, i.e. ,

when conducting the true-up proceeding. Id. § 39.252(d). These subsections all affect the stranded-cost calculation to take place at the true-up proceeding. Yet at the true-up proceeding, "an electric

utility" is to collect its stranded costs through its successor affiliates. See id. § 39.262(c) (". . . each

transmission and distribution utility, its affiliated retail electric provider, and its affiliated power

generation company shall jointly file to finalize stranded costs . . . ."). The "electric utility's"

stranded costs are calculated according to the market value of the generation assets owned by its

successor power generation company. See id. § 39.262(h), (i). It is apparent from these sections that

when the legislature was discussing stranded-cost recovery it sometimes used the term "electric

utility" to refer to an integrated utility's successor affiliates.

Moreover, AEP's reading would lead to absurd results. As discussed above, section

39.252(d) imposes on an electric utility the statutory duty to try to reduce stranded costs as a

substitute for market incentive. As discussed above, until the true-up proceeding, no utility with

significant book value will have any market incentive to increase or maintain the value of its

generation assets because any move to do so will correspondingly reduce its stranded-cost recovery.

The unbundling of a utility into successor affiliates does not affect this lack of incentive. We decline

to attribute to the legislature the intent to make such an arbitrary distinction.

Reliant attacks the rule on another basis. The rule allows the Commission to reduce

the book value of a utility's generation assets if its successor affiliates have not pursued

commercially reasonable means to reduce potential stranded costs. See 16 Tex. Admin. Code

§ 25.263 (e)(4) (2002). According to Reliant, the legislature's "obvious purpose" in prohibiting the

Commission from substituting its judgment for the market valuation of generation assets is to ensure

that the true-up calculation yields an accurate stranded-cost number. Reliant argues that by allowing

the Commission to adjust book value, the rule circumvents the statutory goal of calculating an

accurate stranded-cost amount. We disagree.

We note initially that the relevant statutory goal is not calculating an accurate

stranded-cost amount, but calculating an accurate "verifiable, non-mitigable stranded cost[]" amount.

Tex. Util. Code Ann. § 39.252 (a) (emphasis added). Compliance with the duty to pursue

commercially reasonable means to mitigate its potential stranded costs is part of what makes

stranded costs non-mitigable. See id. § 39.252(a), (d). Reliant's interpretation is likely to yield

inaccurate determinations of non-mitigable stranded costs.

Nothing in the statute explicitly prohibits the Commission from reducing a utility's

book value if it finds that it or its successor affiliates have failed to comply with their obligation to

attempt to reduce stranded costs. In fact, the statute implies that just such an adjustment should take

place. As noted, section 39.252, subsection (d) requires the Commission to consider a utility's

attempts to comply with this obligation when determining a utility's stranded costs at the true-up

proceeding. See id. § 39.252(d). Because this same subsection further provides that the Commission

is prohibited from adjusting the market value of the generation assets as determined under section

39.262(h) and (i), see id , it impliedly contemplates some sort of adjustment to book value--the only

other component of stranded costs. We overrule the utilities' challenge to section 25.263(e)(4) of

the Commission's rule.

CONCLUSION

The Commission erred in promulgating that portion of its rule which unqualifiedly

allows a negative stranded-cost calculation to offset other amounts a utility may become entitled to

at the true-up proceeding. The statutory duty to see that a utility does not over-recover its stranded

costs justifies netting a negative stranded-cost number against the other true-up amounts only to the

extent that it reverses an actual over-recovery due to securitization. The Commission also erred in

promulgating those portions of its rule which, in setting out the partial stock valuation method, (1)

allow it to apply the ten-percent control-premium cap to the value of all corporate assets, and (2)

allow it to second-guess the valuation of the panel by considering other admitted evidence. We

reverse these portions of the rule and remand them to the Commission for further proceedings

consistent with this opinion. We find the other challenged portions of the rule to be valid and uphold

them as enacted.

ON REHEARING

The utilities filed motions for rehearing asking that we clarify certain portions of our

opinion and substantively change other portions. We grant the motions for purposes of clarification

only and substitute modified pages. We overrule the motions insofar as they request that we change

our holding. Our opinion and holding remain substantively unchanged.

Bea Ann Smith, Justice

Before Justices Kidd, B. A. Smith and Yeakel

Affirmed in Part; Reversed and Remanded in Part

Filed: February 6, 2003

1. In addition to the Commission, several intervenors

argue in support of the rule. They

include the Office of Public Utility Counsel (OPUC), the Steering Committee for Cities Served by

TXU Electric and Central Power and Light Company (SCC), Texas Industrial Energy Consumers

(TIEC), the State of Texas, and the Alliance for Retail Markets (ARM). TXU Electric Company was

also a party to this appeal but it has since settled with the Commission and filed a motion to dismiss.

We have granted TXU's motion and dismissed its claims.

2. The utilities could recoup, among other things, the following expenses if reasonably

incurred:

•operation and maintenance costs incurred in furnishing normal service and

in maintaining plants

•assessed taxes

•fuel and purchased power costs

•ordinary advertising costs

•post-retirement benefit-plan costs

•costs of certain assets through depreciation

See 16 Tex. Admin. Code §§ 25.231 , .235(a) (2002).

3. These utilities were identified in an April 1998 Commission Report to the Texas Senate

Interim Committee on Electric Utility Restructuring. In making these estimates, the Commission

utilized an "Excess Cost Over Market" computer model (ECOM model).

4. See generally Tex. Pub. Util. Comm'n, Application of Reliant Energy, Incorporated for

Financing Order to Securitize Regulatory Assets and Other Qualified Costs , Docket No. 21655

(2000); Tex. Pub Util. Comm'n, Application of Central Power and Light Company for Financing

Order to Securitize Regulatory Assets and Other Qualified Costs , Docket No. 21528 (2000); Tex.

Pub. Util. Comm'n, Application of Reliant Energy for Approval of Unbundled Cost of Service Rate

Pursuant to PURA § 39.201 and Public Utility Commission Substantive Rule § 25.344 , Docket No.

22355 (2001); Tex. Pub. Util. Comm'n, Application of Central Power and Light Company for

Approval of Unbundled Cost of Service Rate Pursuant to PURA § 39.201 and Public Utility

Commission Substantive Rule § 25.344 , Docket No. 22352 (2001).

5. See generally Tex. Pub. Util. Comm'n, Application of Reliant Energy for Approval of

Unbundled Cost of Service Rate Pursuant to PURA § 39.201 and Public Utility Commission

Substantive Rule § 25.344 , Docket No. 22355, p. 139; Tex. Pub. Util. Comm'n, Application of

Central Power and Light Company for Approval of Unbundled Cost of Service Rate Pursuant to

PURA § 39.201 and Public Utility Commission Substantive Rule § 25.344 , Docket No. 22352,

p. 120.

6. The ECOM model remains applicable in 2004 only to the extent that a utility has nuclear

assets that are not susceptible to market valuation under the methods described in PURA section

39.263(h). See Tex. Util. Code Ann. § 39.262 (i) (West Supp. 2003).

7.

§§

8. - '

" " §

§

9.

- §

§

10. Regulatory assets are a subset of generation-related costs incurred by a utility. See City

of Corpus Christi v. Public Util. Comm'n , 51 S.W.3d 231, 238 (Tex. 2001)

. They arise when the

regulatory regime requires that a utility's right to recover an expenditure be deferred over several

years. See id. The right to recover this income stream in future years is carried on the utility's books

as a regulatory asset. See id. Regulatory assets therefore have no market value absent a regulatory

regime that assures their recovery. See id.

11.

We reject the Commission's contention that the utilities' complaints are not properly

brought as validity challenges because there may exist some hypothetical set of facts where the type

of harm that the utilities predict might not actually occur. The utilities properly challenge the rule's

validity by arguing that several of its mandatory provisions were promulgated without statutory

authority. City Pub. Serv. Bd. v. Public Util. Comm'n , No. 3-00-007-CV, slip op. at 8, 2002 Tex.

App. LEXIS 2059 , at *12 (Tex. App. Austin--Mar. 21, 2002, no pet.). ("In order to be invalid, the

1999 Rule must, on its face, contravene the legislative grant of power.")

12.

- -

-

-

13. Reliant claims that failure to take this reduction of book value into account causes the

Commission to inaccurately catagorize the bond proceeds as an over-recovery. Reliant also argues

that by netting the amounts that a utility received when it sold securitization bonds against other

amounts it is due, the Commission accomplishes indirectly what it is directly prohibited from doing

by statute. This argument is misconceived. Chapter thirty-nine makes securitization financing

orders irrevocable and prohibits the Commission from adjusting the transition charges in order to

assure payment to bondholders and allow the bonds to be issued on more favorable terms. See Tex.

Util. Code. Ann. §§ 39.301, .304, .306, .307 (West Supp. 2003). Transition charges flow to the

bondholders to retire the transition bonds by paying all the principal and interest. See id .; City of

Corpus Christi , 51 S.W.3d at 239 . Nothing in chapter thirty-nine guarantees that a utility can keep

bond proceeds to which it is not entitled.

14. In view of our disposition of this issue, we need not address the utilities' equal-protection

arguments. See Tex. R. App. P. 47.1 (opinions must be as brief as practicable). Similarly, we do

not specifically reference the arguments of the several intervenors on this issue because they do not

differ materially from those of the Commission. See id . Throughout our opinion, we discuss the

arguments of the intervenors only when they differ materially from those of the Commission.

15. As explained above, under the partial stock valuation method a corporation's common

stock represents only a portion of the total value of its assets. See Tex. Util. Code Ann.

§ 39.262 (h)(3); 16 Tex. Admin. Code § 25.263 (f)(1)(C). Of course, the retained portion of that stock

represents an even smaller portion of the total value of its assets. See id.

16. Intervenors TIEC, SCC, and OPUC argue that the challenged portion of the rule is valid

because the Commission can choose not to convene a valuation panel at all, in which case it must

consider "other admitted evidence" in order to determine market value. They argue that, in light of

this discretion, the statutory requirement that the Commission's determination be "based on the

finding of the panel" means only that the panel's determination is to provide a basis, but not

necessarily the sole basis, for the Commission's interpretation. We disagree. The challenged portion

of the rule only applies if the Commission chooses to convene a valuation panel. Moreover, the

statute is clear that when a panel is convened, its determination is to be conclusive. See Tex. Util.

Code. Ann. § 39.262(h)(3). On the intervenors' interpretation, the requirement that the

Commission's determination be "based on the findings of the panel" would be superfluous given the

fact that it follows a requirement that the Commission "shall adopt" the panel's determination. See

Texas Workers' Compensation Ins. Fund v. Del Industrial, Inc. , 35 S.W.3d. 591, 593 (Tex. 2000)

("A cardinal rule of statutory construction is that each sentence, clause and word is to be given effect

if reasonable and possible.").

17. For example a utility may upgrade a plant or successfully renegotiate an above-cost fuel

contract. Cf. Tex. Util. Code Ann. § 39.251 (7) (requiring that "above market purchased power

costs" be considered in any stranded-cost calculation).

18. We also reject Reliant's claim that interest on the capacity auction true-up amount should

accrue from the first day of competition. We have held that the capacity auction true-up amount is

not a component of stranded costs.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.