Opinion

in Re BHP Billiton Petroleum (Americas) Inc.

Court
Texas Court of Appeals, 1st District (Houston)
Filed
Dec 4, 2009
Status
Published
Cited by
0 cases
Authority
More cited than 35.3%

“[W]hen cases involving the same subject matter are brought in different courts, the court with the first-filed case has dominant jurisdiction and should proceed, and the other cases should abate.”

How later courts described this case

  • “[W]hen cases involving the same subject matter are brought in different courts, the court with the first-filed case has dominant jurisdiction and should proceed, and the other cases should abate.”

Written by the judges who cited it.

The opinion

Opinion issued December 4, 2009

In The

Court of Appeals

For The

First District of Texas

NO. 01-09-00509-CV & 01-09-00647-CV

__________

BHP BILLITON PETROLEUM (AMERICAS) INC., Appellant

V.

ATLANTIA OFFSHORE LIMITED, Appellee

On Appeal from the 215th District Court

Harris County, Texas

Trial Court Cause No. 2009-16355

O P I N I O N

In this interlocutory appeal,

appellant, BHP Billiton Petroleum (Americas)

Inc., challenges the trial court’s temporary injunction enjoining it from pursuing a

“second-filed arbitration” on its claim for breach of a construction contract against

appellee, Atlantia Offshore Limited. Concluding that the arbitration involved “the

same parties and same disputes” subject to an already pending arbitration proceeding,

the trial court stayed and abated this “second-filed arbitration.” BHP also challenges

the trial court’s order by petition for writ of mandamus.

In three issues, BHP

contends that the trial court abused its discretion in enjoining it “from pursuing its

contractual right to arbitrate its $67 million construction defect claim before

arbitrators selected pursuant to the arbitration agreement,” in staying the arbitration

initiated by BHP and allowing the other “special purpose arbitration panel to extend

its jurisdiction to matters not submitted” to it, and in “refusing to enjoin the limited

purpose arbitration panel from arbitrating disputes not submitted” to it. In its petition

for writ of mandamus, BHP also contends that it does not have an adequate remedy

by appeal.

We dismiss the interlocutory appeal and deny the petition.

Factual and Procedural Background

In July 2005, Atlantia entered into an Engineering and Construction Services

Agreement (the “Agreement”) with BHP to engineer and construct an offshore

platform to be erected in the Gulf of Mexico. Schedule 1 of the Agreement, entitled

“Dispute Resolution,” contains the following dispute resolution procedures:

1. SETTLEMENT OF DISPUTES

The Parties agree that any dispute, which arises hereunder, shall

be resolved in accordance with the dispute resolution procedures

(“Procedure”) set forth in this Schedule 1. This Procedure shall apply

to any claim or dispute arising under or related to any of the Contract

Documents (whether arising in contract, tort or otherwise, and whether

arising at law or in equity), including (a) any dispute regarding the

construction, interpretation, performance, validity or enforceability of

any provision of the Contract Documents or whether either Party is in

compliance with, or breach of, any provisions of the Contract

Documents, and (b) the applicability of this Procedure to a particular

dispute (a “Dispute”). The provisions of this Procedure shall be the

exclusive method of resolving Disputes.

Section 1.1 of Schedule 1, entitled “Negotiation to Resolve Disputes,” provides

that, “[i]f a Dispute arises, the Parties shall attempt to resolve such Dispute” through

senior management negotiations conducted promptly and in good faith and, if

unsuccessful, twenty days later, “then either Party may submit such Dispute to

binding arbitration under this Procedure by giving written notice to the other Party

(an “Arbitration Notice”).” Schedule 1 further provides,

1.2 Selection of Arbitrators

a. Any arbitration conducted under this Procedure shall be heard by

three (3) arbitrators (the “Arbitrators”), each qualified by his or

her education, experience and training to resolve the disputed

matters, selected in accordance with Clause 1.2. . . .

b. Each party shall appoint one (1) arbitrator within (30) days of the

filing of the arbitration, and the two arbitrators so appointed shall

select the presiding arbitrator within thirty (30) days after the

latter of the two arbitrators has been appointed by the Parties to

the Dispute. If a Party to the Dispute fails to appoint its Party-appointed arbitrator or the two Party-appointed arbitrators cannot

reach an agreement on the presiding arbitrator . . . , then the

American Arbitration Association . . . shall serve as the

appointing authority and shall appoint the remaining of the three

arbitrators not yet appointed in accordance with its then-current

Commercial Arbitration Rules (“Rules”) . . .

1.3 Conduct of Arbitration

The Arbitrators shall expeditiously (if possible, within 90 days after its

selection) hear and decide all matters concerning the Dispute. . . . The

Arbitration shall be governed by the U.S. Federal Arbitration Act and

conducted in accordance with the Rules (excluding rules governing the

payment of arbitration, administrative or other fees or expenses to the

Arbitrators or the AAA), to the extent that such Rules do not conflict

with the terms of this Contract. The Arbitrators shall have the power .

. . (b) to grant injunctive relief and enforce specific performance. . . .

The decision of the Arbitrators (which shall be rendered in writing) shall

be final, not subject to appeal, binding upon the Parties, and may be

enforced in any court of competent jurisdiction. . . .

On March 18, 2008, BHP sent Atlantia a notice of breach of the Agreement

based upon alleged defects in the platform, and BHP demanded that Atlantia perform

remedial or warranty work. On October 14, 2008, BHP sent Atlantia another letter,

referencing its prior notice of breach and asserting that it had incurred $28 million in

costs for certain services associated with the warranty work performed by Atlantia as

well as other damages attributable to the delays in the work, and BHP demanded that

Atlantia reimburse it for its costs. BHP stated that its demand also triggered the

parties’ obligations to commence senior management negotiations under the

Agreement.

Pursuant to BHP’s letter and the Agreement, the parties commenced senior

management negotiations, but the negotiations were unsuccessful. On March 16,

2009, BHP sent a letter to Atlantia acknowledging that the parties had not been able

to resolve their dispute, and BHP stated its intent to “instruct external counsel to

proceed with drawing upon” a letter of credit (the “LOC”) and “to commence

arbitration proceedings” under the Agreement.

On March 17, 2009, Atlantia filed an application for a temporary restraining

order and temporary injunction in the trial court. In this application, Atlantia stated

that it had been obligated by the Agreement to furnish a $9 million LOC to secure its

performance. Atlantia acknowledged that a dispute had arisen between the parties

over payment of expenses incurred by BHP during the course of Atlantia’s warranty

work, but Atlantia contended that BHP’s threat to immediately draw on the LOC,

prior to a decision on the merits of the contractual dispute, violated the Agreement

or was based upon fraud. Atlantia further contended that, although the merits of this

dispute were subject to arbitration under the rules of the AAA, it would take at least

thirty days to constitute a tribunal, which Atlantia averred would be too late “to

address the matter at hand.”

Atlantia stated that the “issues to be determined in the arbitration” would be to

what extent Atlantia was responsible for BHP’s costs and whether BHP had the right

to draw on the LOC before Atlantia’s liability for the costs had been established.

Atlantia asserted that, to draw on the LOC, BHP would be required to certify

Atlantia’s failure to perform its obligations, such a certification would be false and

fraudulent, and such action would cause Atlantia immediate and irreparable harm.

Thus, Atlantia requested injunctive relief enjoining BHP from presenting the LOC

“until 30 days after an arbitral tribunal capable of addressing this issue is further

constituted.”

On the same day that Atlantia filed its application, the trial court conducted a

hearing and entered an “Agreed Standstill Order” (the “ASO”), which was signed by

both BHP and Atlantia. The trial court ordered the parties to use their “best efforts”

through March 25, 2009 “to constitute an arbitral tribunal pursuant to the Agreement”

to “determine the issue of whether [BHP] may draw on the LOC.” It also ordered

Atlantia not to appeal “any decision by the arbitral tribunal on the issue of whether

[BHP] may draw on the LOC.” The trial court further ordered that, if a tribunal could

not be constituted or could not determine “the issue” before March 25, 2009, the trial

court would rule on Atlantia’s application for a temporary restraining order on March

25, 2009 or would further extend the ASO. The trial court prohibited BHP from

presenting the LOC to the bank until March 26, 2009 and both parties from filing any

other proceeding, except arbitration, “with respect to the matters at issue” in

Atlantia’s application for a temporary restraining order, “and, specifically [BHP’s]

ability to draw down on the LOC,” prior to April 30, 2009. Finally, the trial court

mandated that Atlantia would extend the LOC to a new expiration date of April 30,

2009.

On March 19, 2009, BHP sent Atlantia a letter designating, pursuant to section

1.2 of Schedule 1 of the Agreement and in accordance with the ASO , William

Andrews as an arbitrator. In this letter, BHP cited Andrews’s “extensive experience

in construction disputes, both onshore and offshore” as being “valuable in resolving

the captioned matter,” which referred to Atlantia’s application for injunctive relief.

Atlantia also designated its arbitrator, and he, along with Andrews, selected the

presiding arbitrator.

On March 23, 2009, after appointing its arbitrator under the ASO, BHP filed

a response to Atlantia’s application in the trial court, asserting that Atlantia’s

discussion of the merits of the contractual dispute was irrelevant to the discrete issue

of the enforcement of the LOC. On March 24, 2009, the arbitration panel, consisting

of the arbitrators appointed by the parties and the presiding arbitrator (the “private

arbitration” panel), conducted a hearing, and, on March 25, 2009, issued an order

denying Atlantia’s application for a temporary restraining order. However, the

private arbitration panel further stated in its order that it determined that it had

“jurisdiction over the disputes arising out of and related to the [Agreement]” and that

“a prompt hearing on the merits of the parties’ dispute should be arranged.” The

panel set a scheduling hearing for March 30, 2009, and noted that it intended to

provide an “expeditious arbitration.”

On March 27, 2009, BHP sent the panel a letter stating that it had not formally

submitted the merits of its contractual dispute to arbitration and had not submitted its

arbitration demand to the AAA. BHP further asserted that the private arbitration

panel had been expeditiously convened only to handle the limited issue of the LOC

and that, although the panel might ultimately be designated to arbitrate the merits of

the contractual dispute, the parties had not designated the panel to handle the

contractual dispute at that time. On March 30, 2009, at the scheduling hearing, BHP

again objected to the private arbitration panel’s jurisdiction to rule on the contractual

disputes or any other claims other than Atlantia’s application for a temporary

restraining order regarding the LOC. The private arbitration panel denied BHP’s

objection, and then set various deadlines for the arbitration. On April 13, 2009, BHP

filed a formal objection to the private arbitration panel’s jurisdiction and, subject to

its objection, its affirmative claims. The panel again denied BHP’s jurisdictional

objection, stating that it had determined that it had jurisdiction to decide the current

disputes between the parties, “including those for which Atlantia’s LOC was called

following” its order denying Atlantia a temporary restraining order.

On April 8, 2009, BHP filed a separate demand for arbitration against Atlantia

with the AAA (the “AAA arbitration”) for its affirmative claims concerning the

alleged defective and negligent design of the platform, and BHP sought damages for

reimbursement of costs and deferred production in the amount of $67 million.

Atlantia filed an objection with the AAA to stop this separate arbitration proceeding,

but, on April 21, 2009, the AAA issued a letter stating that BHP met the filing

requirements and that, absent an agreement by the parties or a court order, the AAA

arbitration would proceed.

On April 22, 2009, Atlantia filed another application for a temporary

restraining order and temporary injunction in the trial court, this time seeking an order

enjoining BHP from pursuing the AAA arbitration and staying that arbitration

“because the matters in controversy” were “already the subject of a previously filed”

private arbitration and that the private arbitration panel had “already issued a binding

decision that it has jurisdiction over such matters.”

The trial court granted Atlantia

a temporary restraining order. BHP then filed in the trial court an answer and

“counterclaim for permanent injunctive relief” in which it asked the trial court to find

that the private arbitration panel did not have jurisdiction to hear the merits of the

contractual dispute and that BHP may continue with the AAA arbitration. BHP also

requested injunctive relief to enjoin the private arbitration on the basis that it was

being deprived of its right to arbitrate the dispute under the procedures set forth in the

Agreement. BHP cited the provisions in the Agreement that allowed a certain number

of days to select an arbitrator qualified by education, experience, and training. BHP

complained that it did not have the opportunity to evaluate and select an arbitrator

based upon his knowledge of maritime law, vessel charter agreements, the

remediation operation, and deferred production, all of which BHP contended were

important parts of its $67 million claims.

After a hearing, the trial court issued a temporary injunction enjoining BHP

from pursuing its AAA arbitration and staying the AAA arbitration. In the order, the

trial court stated that the Agreement requires “all disputes (including disputes over

whether the dispute resolution procedure applies to a particular dispute) be submitted

to binding arbitration,” “[a]n arbitral panel has been constituted and has determined

that it has jurisdiction to decide the merits of the disputes between the parties,” the

panel’s decision is binding on the parties, BHP’s “second-filed” AAA arbitration

involves the same parties and subjects of dispute as the private arbitration and is

unauthorized, and that, without injunctive relief, Atlantia would be irreparably

harmed by being forced to arbitrate in a manner inconsistent with the Agreement and

being subjected to a significant risk of inconsistent outcomes.

Jurisdiction

BHP has filed both an interlocutory appeal and a petition for writ of

mandamus. In its appeal, BHP asserts that we have jurisdiction to determine whether

the trial court erred in enjoining BHP from pursuing the AAA arbitration, staying the

AAA arbitration, and not enjoining the private arbitration. See Tex. Civ. Prac. &

Rem. Code Ann. § 51.014(a)(4) (Vernon 2008) (providing for interlocutory appeal

from order granting or refusing to grant temporary injunction). BHP also asserts that

we have jurisdiction to consider its challenges to the trial court’s order, as well as the

trial court’s “implicit” refusal to enjoin the private arbitration, through its petition for

writ of mandamus.

Atlantia agrees that BHP’s interlocutory appeal of the temporary injunction is

proper. Atlantia also agrees that BHP may seek mandamus relief to challenge the trial

court’s order enjoining BHP from pursuing the AAA arbitration and staying that

arbitration. However, Atlantia disputes that BHP can appeal the trial court’s implicit

refusal to grant a temporary injunction because it argues that BHP only pleaded for

permanent injunctive relief.

The Federal Arbitration Act (“FAA”)

applies to the Agreement in this case.

See W. Dow Hamm III Corp. v. Millennium Income Fund, L.L.C. , 237 S.W.3d 745,

751 (Tex. App.—Houston [1st Dist.] 2007, no pet.) (noting that arbitration agreement

provided that FAA would apply to dispute and stating that “[p]arties may validly

agree to arbitrate under the FAA”). Although both parties agree that we have dual

bases for jurisdiction to review the trial court’s express order enjoining BHP from

pursuing the AAA arbitration and staying that arbitration, we conclude that the actual

order issued by the trial court is one staying the AAA arbitration.

Texas courts have

held that a party, like BHP, seeking relief pursuant to the FAA from an order staying

arbitration should pursue relief by way of petition for writ of mandamus. See

Haddock v. Quinn , 287 S.W.3d 158, 168 (Tex. App.—Fort Worth 2009, pet. filed)

(citing In re D. Wilson Constr. Co. , 196 S.W.3d 774, 780 (Tex. 2006) (orig.

proceeding); In re Valero Energy Corp. , 968 S.W.2d 916, 917 (Tex. 1998) (orig.

proceeding); Jack B. Anglin Co. v. Tipps , 842 S.W.2d 266, 272 (Tex. 1992) (orig.

proceeding)). Our Court has also recently stated that generally “no interlocutory

appeal lies from the order staying arbitration proceedings.” W. Dow Hamm III Corp. ,

237 S.W.3d at 752 . Therefore, we dismiss for want of jurisdiction BHP’s

interlocutory appeal of the trial court’s order prohibiting it from pursuing the AAA

arbitration and staying that arbitration, and we proceed to determine whether BHP is

entitled to mandamus relief from the trial court’s order staying the AAA arbitration.

See Haddock , 287 S.W.3d at 168 .

Mandamus is an extraordinary remedy, which will issue only to correct a clear

abuse of discretion or a violation of a duty imposed by law when there is no adequate

remedy by appeal. In re Ford Motor Co. , 165 S.W.3d 315, 317 (Tex. 2005) (citing

In re Prudential Ins. Co. of Am. , 148 S.W.3d 124 , 135–36 (Tex. 2004)); Walker v.

Packer , 827 S.W.2d 833 , 839–40 (Tex. 1992). A trial court abuses its discretion

when it errs in determining what the law is or in applying the law to the facts. In re

Bruce Terminix Co. , 988 S.W.2d 702, 703 (Tex. 1998).

Order Staying the AAA Arbitration

In its first two issues, BHP argues that the trial court abused its discretion in

enjoining it “from pursuing its contractual right to arbitrate its $67 million

construction defect claim before arbitrators selected pursuant to the arbitration

agreement” and in staying the AAA arbitration, because the Agreement contains

procedures requiring that disputes be presented to arbitrators with the necessary

education, experience, and training, and the trial court has denied it the right to

arbitrate its claims in accordance with the Agreement. BHP asserts that the trial court

has allowed the private arbitration panel “to extend its jurisdiction to matters not

submitted” to it.

The issues presented here are atypical of those present in most appeals and

mandamus actions related to arbitration. First, both BHP and Atlantia agree that all

the matters in contention, including the LOC and the merits of the contractual dispute,

are subject to arbitration under the Agreement. Second, after Atlantia filed its first

application for injunctive relief, both Atlantia and BHP entered into the ASO, which

expressly referred to the Agreement and instructed the parties “to constitute an

arbitral tribunal pursuant to the Agreement” on an expedited basis. We conduct our

review of the trial court’s order staying the AAA arbitration with these unique

procedural characteristics in mind.

The parties essentially ask us to consider whether the trial court was authorized

to stay the AAA arbitration based upon its findings that the AAA arbitration was an

unauthorized second-filed arbitration involving the same parties and subjects of

dispute as the private arbitration and that the private arbitration panel made a binding

decision that it had jurisdiction to hear the contractual merits dispute. The parties

refer us to no Texas authority which would allow a trial court to enter an order

staying an arbitration based upon the argument that it is duplicative of a previously

filed, competing arbitration. However, other federal courts applying the FAA have

concluded that a trial court possesses the power, in certain circumstances, to stay a

competing arbitration. In L.F. Rothschild & Co. v. Katz , the plaintiff, citing 9 U.S.C.

§ 4 of the FAA , moved for an order compelling the defendants to proceed with an

arbitration before the New York Stock Exchange (“NYSE”) and staying a competing

arbitration that the defendants had commenced with the Chicago Board Options

Exchange (“CBOE”). 702 F. Supp. 464, 465 (S.D.N.Y. 1988) . The parties agreed

that the plaintiff’s claims were subject to arbitration, and both the NYSE and the

CBOE were authorized to arbitrate the dispute. Id . at 466. The court stated,

Here, each party has commenced an arbitration proceeding that, standing

alone, would be valid under the Arbitration Agreement. However, to

permit both proceedings to continue would require the parties to pursue

the same claims or defenses in two separate forums, resulting in the

duplication of the arbitrators' efforts and risking inconsistent outcomes.

To avoid these problems, only one of these proceedings should go

forward. As a general rule, the forum where an action is first filed takes

priority over the forum where a subsequent action arising out of the

same facts is filed.

Id . at 466–67.

Applying the “first-filed” principle, the court determined that the NYSE was

the appropriate arbitrator because the plaintiff had commenced that proceeding first

and the defendants had commenced the CBOE arbitration only after learning of the

competing proceeding. Id .

After determining that the NYSE would be appropriate arbitrator, the court

then examined its authority to stay the competing, second filed arbitration. Id . The

court recognized that “[a]lthough the Federal Arbitration Act authorizes a district

court to stay litigation, it remains silent regarding a court’s authority to stay

arbitration.” Id . (citing 9 U.S.C. § 3 ). However, the court concluded that this

“silence” did not leave district courts without such power. Id . The court, quoting

persuasive authority, stated,

The Act expressly provides federal courts with the power to order

parties to a dispute to proceed to arbitration where arbitration is called

for by the contract. 9 U.S.C. § [4]. To allow a federal court to enjoin an

arbitration proceeding which is not called for by the contract interferes

with neither the letter nor the spirit of this law. Rather, to enjoin a party

from arbitrating where an agreement to arbitrate is absent is the

concomitant of the power to compel arbitration where it is present. . . .

In fact, were the law read to prevent a court from enjoining an

arbitration proceeding it might actually interfere with arbitration— in the

unusual case, arguably present here, where one such arbitration

proceeding may interfere with another.

Id . at 467 (quoting Societe Generale de Surveillance, S.A. v. Raytheon European

Mgmt. & Sys. Co. , 643 F.2d 863 (1st Cir. 1981)). Based upon this authority, the court

concluded that when the parties contracted to arbitrate a dispute “surely they did not

anticipate two-or perhaps more-rival arbitrations arising out of the same controversy”

and that, after the first arbitration proceeding was already in place, the second-filed

arbitration “was not authorized by the contract.” Id . at 468. The court stated that, i n

these circumstances, section 4 of the FAA empowered a court to stay the

unauthorized arbitration. Id .

No Texas court has yet applied the first-filed principles articulated in Katz to

stay competing arbitration proceedings, but Texas courts recognize the first-filed

principles in the litigation context. See Perry v. Del Rio , 66 S.W.3d 239, 252 (Tex.

2001) (“[W]hen cases involving the same subject matter are brought in different

courts, the court with the first-filed case has dominant jurisdiction and should

proceed, and the other cases should abate.”). Here, it is undisputed that all of the

matters in dispute between BHP and Atlantia are governed by the FAA and are

subject to arbitration under the Agreement. The instant circumstances are comparable

to those in Katz , and the analysis in Katz persuasive. Accordingly, we conclude that

the trial court, under section 4 of the FAA, was authorized to enter an order staying

the AAA arbitration.

We now turn to consider whether the trial court properly determined that the

AAA arbitration was a competing, duplicative arbitration that involved the same

subject matter and controversy as the private arbitration.

In its March 18, 2008 letter to Atlantia, BHP claimed that Atlantia had

breached the Agreement, and BHP demanded that Atlantia perform warranty work.

In its October 14, 2008 letter, BHP claimed $28 million in reimbursable costs that it

had allegedly incurred, and it demanded that Atlantia reimburse it for these costs. It

also indicated that there were additional damages associated with the resulting delay.

Thus, BHP expressly triggered the parties’ obligations under the Agreement to

commence senior management negotiations to resolve this Dispute. The record

before us conclusively shows that the Dispute, as that term is used in the Agreement ,

that was being submitted for senior management negotiations prescribed for by the

parties involved the merits of the parties’ entire contractual dispute; the LOC dispute

had not yet arisen.

Following the parties’ unsuccessful senior management negotiations of this

Dispute, which was conducted pursuant to the Agreement, BHP notified Atlantia of

its intent “to commence arbitration proceedings” under the Agreement. Although the

letter also expressed BHP’s intent to “instruct external counsel” to draw upon the

LOC to recover at least some of its damages associated with this Dispute, the letter

unequivocally indicated BHP’s intent to commence arbitration of the entire Dispute.

In response, Atlantia filed its first application for injunctive relief, in which it

specifically referenced not only the LOC but also the merits of the contractual

dispute. It also specifically stated that the “issues to be determined in the arbitration”

would be both the contractual dispute and the LOC dispute. Atlantia took the

position that the LOC dispute and the contractual merits dispute could not be

separated, and Atlantia requested injunctive relief enjoining BHP from presenting the

LOC “until 30 days after an arbitral tribunal capable of addressing this issue is further

constituted.” Because Atlantia contended that the LOC dispute and the contractual

merits dispute could not be separated, Atlantia did not merely seek injunctive relief

prior to any expedited arbitral consideration of the LOC issue, but also injunctive

relief prior to any decision of the contractual merits dispute.

BHP was not obligated to enter into the ASO. However, in paragraph 2 of the

ASO, both BHP and Atlantia agreed to, between March 17, 2009 and March 25,

2009, use their best efforts “ to constitute an arbitral tribunal pursuant to the

Agreement and to have the arbitration tribunal determine the issue of whether [BHP]

may draw on the LOC.” (Emphasis added). Thus, paragraph 2 obligated BHP to

make efforts to both constitute a panel under the Agreement and to have the panel

make a determination on the LOC issue by March 25. Although most of the

paragraphs of the ASO refer to the LOC, nothing in the ASO indicated that the

private arbitration panel constituted thereunder, and pursuant to the Agreement,

would be dissolved following the determination of the LOC dispute or that the private

arbitration panel would be voided if the panel could not come to a determination of

the LOC issue by March 25. Instead, the parties simply agreed that, in that instance,

the trial court would rule on Atlantia’s application for a temporary restraining order

or would further extend the ASO as necessary.

BHP’s March 19, 2009 letter designating William Andrews pursuant to section

1.2 of Schedule 1 of the Agreement and in accordance with the ASO belies BHP’s

contention that it designated Andrews solely to consider the LOC issue. In its letter,

BHP stated that Andrews was being appointed to resolve “the captioned matter,”

which was Atlantia’s application for injunctive relief. By its plain terms, this

application related both to the LOC and the contractual merits dispute. The bottom

line is that, at the time the private arbitration panel was constituted by the parties

pursuant to both the Agreement and the ASO, the parties had already conducted

senior management negotiations under the Agreement regarding the contractual

merits dispute, BHP had expressed its intent to instruct its counsel to commence

arbitration of the contractual merits dispute, and Atlantia had filed an application for

injunctive relief, which included its contention that the LOC could not be resolved

without a determination of the merits of the contractual dispute. The Agreement does

not contemplate the setting up of a special or limited purpose arbitration panel that

would terminate upon March 25 or immediately after a determination of the LOC

issue. Instead, it contemplates a panel constituted under the Agreement, which by the

Agreement’s terms, is set up to consider and address the Dispute. At the time the

panel was constituted, the Dispute was not limited to the LOC.

BHP’s demand in the AAA arbitration reflects that BHP seeks to arbitrate the

same matters at issue in the private arbitration. This is, of course, why BHP sought

injunctive relief to stay the private arbitration. But, we have concluded that trial court

did not err in determining that the private arbitration panel had jurisdiction to hear the

contractual merits dispute. Because the contractual merits dispute was already the

subject of the pending private arbitration, we hold that the trial court did not abuse

its discretion in entering an order staying the AAA arbitration.

In so holding, we note that BHP has not been denied its contractual right to

arbitrate its $67 million construction defect claim before arbitrators selected pursuant

to the Agreement . BHP complains that the trial court’s order has the effect of

denying its contractual rights to have sufficient time to vet any potential arbitrators

and ensure that they possess specialized knowledge regarding the types of claims it

seeks to bring. Although Schedule 1 provides that the appointed arbitrators shall be

qualified by education, experience, and training to resolve the disputed matters,

nothing in the ASO affected this provision. As discussed above, at the time the

parties signed the ASO and appointed their arbitrators on an expedited basis, the

disputed matters were the LOC and the related contractual merits dispute.

Furthermore, although Schedule 1 provides parties with thirty days to appoint their

arbitrators, BHP signed the ASO and appointed its arbitrator on an expedited basis.

BHP’s argument that it is being deprived of certain contractual rights is unavailing.

We overrule BHP’s first two issues.

Conclusion

We dismiss the interlocutory appeal and deny BHP’s petition for writ of

mandamus.

Terry Jennings

Justice

Panel consists of Justices Jennings, Higley, and Sharp.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.