Opinion

Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip

Court
Texas Court of Appeals, 1st District (Houston)
Filed
Aug 21, 2008
Status
Published
Cited by
0 cases
Authority
More cited than 35.2%

“A condition precedent is an event that must happen or be performed before a right can accrue to enforce an obligation.”

How later courts described this case

  • “A condition precedent is an event that must happen or be performed before a right can accrue to enforce an obligation.”
  • trial court may grant JNOV if there is not evidence to support jury finding on issue necessary to liability
  • enforcing unambiguous contract as written
  • distinguishing between breach of contract claim and breach of contractual warranty provision claim and applying outside Uniform Commercial Code

Written by the judges who cited it.

The opinion

Opinion issued August 21, 2008

In The

Court of Appeals

For The

First District of Texas

NO. 01-06-00535-CV

TENNESSEE GAS PIPELINE COMPANY, Appellant

V.

TECHNIP USA CORPORATION AND TECHNIP, S.A., Appellees

* * *

TECHNIP USA CORPORATION AND TECHNIP, S.A. , Appellants

V.

TENNESSEE GAS PIPELINE COMPANY , Appellee

On Appeal from the 165th District Court

Harris County, Texas

Trial Court Cause No. 2002-60134

MEMORANDUM OPINION ON REHEARING

This is a breach of contract dispute brought by Tennessee Gas Pipeline

Company (“TGP”) against Technip USA Corporation (“Technip USA”) and its

parent, Technip S.A. (collectively, “Technip”). TGP engaged Technip USA to

construct improvements along an interstate gas pipeline owned by TGP pursuant to

a “Lump Sum Turnkey, Engineering, Procurement and Construction Contract”

(“Contract”). After project delays occurred, TGP sued Technip to recoup its

additional expenses and for allegedly defective work. Technip counterclaimed to

recover sums owed under the Contract. A jury found that Technip had breached the

Contract and awarded delay damages and defective work damages to TGP.

Subsequently, on the motion of Technip, the trial court limited the jury award to

certain defective-work damages. Both TGP and Technip have appealed. TGP seeks

the total jury award; Technip seeks a holding that TGP take nothing on its claims.

In its appeal, TGP contends that the trial court erred by denying its Motion for

Judgment and by granting Technip USA’s Motions for Summary Judgment

Regarding TGP’s damages, Technip’s Motion to Disregard the Jury Findings, and

Technip’s Motion for Entry of Judgment Notwithstanding the Verdict because (1) the

total damages awarded by the jury constitute “direct damages” to which TGP is

entitled as a matter of law; (2) the evidence is legally sufficient to support the jury’s

finding of damages; and (3) Technip S.A. was required, pursuant to the guaranty it

executed, to pay all damages arising from Technip USA’s breach of the Contract

without limitation.

In its appeal, Technip contends that the trial court erroneously denied its

Motion for Judgment Notwithstanding the Verdict on TGP’s defective workmanship

claims because (1) such claims are barred by the exclusive remedy provisions of the

agreement; (2) the evidence is insufficient to support the damages awarded on certain

defective work claims; and (3) the trial court improperly applied the stipulated

retainage offset and improperly calculated interest and attorney’s fees.

On December 21, 2007, we reversed and rendered, in part, and affirmed as

modified, in part, the judgment of the trial court in this case. TGP moved for

rehearing. We grant the motion, withdraw the opinion dated December 21, 2007, and

issue this opinion in its stead. Our disposition and judgment remain unchanged.

We reverse and render, in part, and affirm as modified, in part.

FACTS AND PROCEDURAL HISTORY

TGP

owns and operates 14,200 miles of pipeline through which it transports

6.4 billion cubic feet of gas each day from Texas to the northeastern United States.

Technip USA is an engineering and construction contractor in the oil and gas

industry. TGP and Technip USA

have conducted business with one another since

the 1960s.

On August 6, 1999, TGP contracted with Technip USA for the replacement and

upgrade of six compressors

on one of TGP’s main transmission lines, known as the

“TGP 100 Line Horsepower Replacement Project” (“Project”), for a “lump sum, fixed

amount” of $86,740,000 (“Contract Price”).

Work on the Project commenced

immediately. TGP expected the Project to be completed within 17 months. Technip

contends that the schedule for completion was never formally finalized. Completion

of the Project took three years.

The Agreement

The progress and completion of the Project was formally governed by Article

5.2 of the Contract, which provides as follows, in pertinent part:

Project Schedule; Critical Path Schedule . [Technip USA] shall perform

the Work [its duties and obligations] in accordance with the schedule

and management plan set forth in Exhibit E (the “ Project Schedule ”).

Within twenty (20) days after the Effective Date, [Technip USA] shall

submit, for [TPG’s] review and approval, a critical path method

(“CPM”) schedule which conforms to the Project Schedule and which

sets forth the timing of all elements of the Work and the

interrelationship of such elements.

It is undisputed that there was never a Project Schedule “set forth in Exhibit E” of the

Contract, as contemplated by Article 5.2.

According to TGP, contemporaneous with the formation of the Contract, a

Project Schedule was formulated and was circulated at a meeting involving both

parties. The Project Schedule specified that Technip USA would complete the project

within 17 months of execution of the Contract. In addition, according to TGP, a CPM

schedule was created, also specifying that Technip USA would complete the Project

within 17 months . TGP contends that it remained in constant communication with

Technip USA and that all parties understood that the Project Schedule governed the

project. In addition, contends TGP, the Project Schedule was incorporated into the

Contract through Article 19.13, which provides that “[a]ll Exhibits, Schedules or

other attachments referenced in this Agreement shall be incorporated into this

Agreement by such reference and shall be deemed to be an integral part of this

Agreement.”

Article 5.2A of the Contract also provides that “[m]odifications to the critical

path of the Project Schedule shall only be made with the approval of [TGP]” and that

“[t]he Project Schedule shall be revised as required under Section 6.5.” Article 6.5

provides that “the Project Schedule may only be adjusted to the extent that [Technip

USA] can demonstrate that the change impacted the critical path of the Work” and

that Technip USA is required to attempt to accelerate the performance of work to

minimize the impact of any changes on the Project Schedule.

Pursuant to Article 5.2C, if Technip USA failed to achieve “Substantial

Completion within sixty (60) days following that Station’s Substantial Completion

Date, then the provisions of Section 13.2 shall apply.” Article 13.2 was a liquidated

damages provision that TGP agreed to remove from the Contract in exchange for a

$1.5 million decrease in the Contract Price. The balance of Article 13 provides that

“[t]ime is of the essence in the performance” of the Contract and that Technip USA

“guarantees that, subject to such adjustments as may be provided hereunder,

Substantial Completion shall occur not later than the Substantial Completion Date on

a station-by-station basis.”

Attached to the Contract is a parent guaranty executed by Technip S.A.,

guaranteeing the obligations of Technip USA under the Contract and agreeing to

indemnify TGP against damages arising from a breach of the Contract by Technip

USA.

The Dispute

During the course of the Project, numerous delays occurred that each party

attributed to various causes—including issues with the components being installed,

issues involving the new technology or new applications of technology being

employed, delays in change orders, shortages of skilled labor, and inclement weather.

Ultimately, the Project achieved substantial completion in April of 2002

— delays

having ranged from six to twenty months in the completion of five of the six

compressor stations. Specifically, Stations 47, 54, 63, 87, and 110 are the subject of

this dispute.

In May 2002, Technip USA requested an “equitable adjustment” to the

Contract Price based on increased costs incurred as a result of the extended work

periods. During October and November 2002, Technip filed $12.8 million in liens

against the Project. On November 22, 2002, TGP sued Technip to recover its

increased costs, alleging that Technip USA’s delays constituted a breach of the

Contract.

Technip moved for summary judgment on the grounds that TGP’s claims for

1. Project delay costs, sustained in the past

2. Excess gas use differential costs, sustained in the past

3. Excess lube oil costs, sustained in the past

4. Excess labor costs, sustained in the past

5. Extra power at Station 63 costs, sustained in the past

6. Backup generator costs, sustained in the past

7. Allowance for funds used during construction, sustained in the past

8. Premature energization costs at Station 54, sustained in the past

constituted claims for incidental or consequential damages and that such damages

were specifically excluded under Article 19.1 of the Contract, as follows:

Consequential Damages : Notwithstanding any other provisions of this

Agreement to the contrary, in no event shall Owner or Contractor be

liable to each other for any indirect, special, incidental or consequential

loss or damage including, but not limited to, loss of profits or revenue,

loss of opportunity or use incurred by either Party to the other, or like

items of loss or damage; and each Party hereby releases the other Party

therefrom.

In addition, Technip contended that TGP’s workmanship claims for

9. Realignment of compressor costs

10. Excessive blowdown costs, sustained in the past

11. Replacement and installation of operable oil fill system and repair costs for

air dryers, sustained in the past

12. Review “as-built” drawings, to be reasonably sustained in the future

were precluded because TGP failed to make written warranty claims as required

under the Contract. The trial court granted Technip’s motion, in part, holding that

claims 1–6, and 8 above were barred and that TGP take nothing on those claims.

TGP moved for a partial summary judgment “on the liability portion of its

claim that Technip USA breached the Contract by failing to complete the project

according to the Project Schedule,” which the trial court denied.

Subsequently, on November 19, 2004, The Honorable Reece Rondon of the

334th District Court of Harris County voluntarily recused himself. The case was

transferred to The Honorable Elizabeth Ray of the 165th District Court of Harris

County.

The case was tried to a jury beginning October 27, 2005. At a pre-trial hearing,

the trial court instructed the parties to place all of their evidence concerning damages

before the jury, that the jury would be instructed to determine whether a breach

occurred and, if so, to determine the award of damages applicable without regard to

whether such damages were precluded under the Contract, and that the trial court

would later determine which damages were barred as a matter of law.

The jury found that Technip USA breached the Contract by unreasonable delay

and awarded $18,468,361.73 in damages to TGP as follows:

1. Project delay costs, sustained in the past

$4,030,672.07

2. Excess gas use differential costs, sustained in the past

$4,617,717.00

3. Excess lube oil costs, sustained in the past

$ 233,933.04

4. Excess labor costs, sustained in the past

$ 950,560.94

5. Extra power at Station 63 costs, sustained in the past

$ 30,540.23

6. Backup generator costs, sustained in the past

$ 34,871.69

7. Allowance for funds used during construction, sustained

in the past

$6,427,535.70

8. Premature energization costs at Station 54, sustained in

the past

$ 452,368.13

9. Realignment of compressor costs

$ 964,170.02

10. Excessive blowdown costs, sustained in the past

$ 14,160.00

11. Replacement and installation of operable oil fill system

and repair costs for air dryers, sustained in the past

$ 156,292.91

12. Review “as-built” drawings, to be reasonably sustained

in the future

$ 555,540.00

In addition, the jury found that TGP did not breach the Contract.

Technip moved to disregard the jury findings and for judgment notwithstanding

the verdict on the grounds that (1) TGP’s delay-related damages were barred by the

consequential damages provision of the Contract; (2) TGP’s workmanship-related

claims were barred by the warranty and exclusive remedy provisions of the Contract;

(3) there was no evidence of causation as to TGP’s delay-related damages; and (4)

there was no evidence that Technip breached the Contract by unreasonably delaying

beyond any deadline fixed by the Contract. TGP moved for judgment on the verdict

on the grounds that its damages were “direct damages” caused solely by Technip

USA’s delay.

The trial court granted each motion in part. The trial court limited the jury

award to certain defective work claims—awarding TGP damages for “Realignment

of compressor costs,” “Replacement and installation of operable oil fill systems,” and

“Review ‘as-built’ drawings.” In addition, the trial court awarded to TGP pre- and

post-judgment interest and, as the parties had stipulated, $1.1 million in attorney’s

fees. The trial court held that Technip was entitled to a credit against the judgment

of the $1,650,000 retainage held by TGP, “as stipulated by the parties.” The trial

court held Technip S.A. jointly and severally liable as guarantor for payment of the

judgment.

Technip USA moved to modify the judgment and for a new trial, which were

overruled by operation of law. TGP and Technip have appealed. TGP seeks to

recover the entire jury award; Technip seeks a holding that TGP take nothing on its

claims. I. TGP’s Appeal In its appeal, TGP contends that the trial court erred by denying its Motion for

Judgment and by granting Technip USA’s Motions for Summary Judgment

Regarding TGP’s damages, Technip’s Motion to Disregard the Jury Findings, and

Technip’s Motion for Entry of Judgment Notwithstanding the Verdict because (1) the

total damages awarded by the jury constitute “direct damages” to which TGP is

entitled as a matter of law; (2) the evidence is legally sufficient to support the jury’s

finding of damages; and (3) Technip S.A. was required, pursuant to the guaranty it

executed, to pay all damages arising from Technip USA’s failure to perform under

the Contract. The Jury Award

In its first issue, TGP contends that the trial court erred by granting Technip’s

Motion for Judgment Notwithstanding the Verdict because the total damages awarded

by the jury constituted “direct damages” to which TGP is entitled as a matter of law.

TGP contends that it is entitled to recover the total damages awarded by the jury

because (A.) it is entitled, as a matter of Texas contract law, to recover its “benefit-of-the-bargain,” namely, “to have efficient compressors in place in seventeen months,”

and (B.) the plain language of the Contract’s damages provision does not limit

recovery for “direct damages.”

Standard of Review

A trial court may disregard a jury finding and enter a judgment notwithstanding

the verdict (“JNOV”) if the finding is immaterial or if there is no evidence to support

the finding. Tiller v. McClure , 121 S.W.3d 709, 713 (Tex. 2003); Spencer v. Eagle

Star Ins. Co. of Am. , 876 S.W.2d 154, 157 (Tex. 1994); Williams v. Briscoe , 137

S.W.3d 120, 124 (Tex. App.—Houston [1st Dist.] 2004, no pet.). A question is

“immaterial” when it should not have been submitted to the jury, it calls for a finding

beyond the province of the jury, such as a question of law, or when it was properly

submitted but has been rendered immaterial by other findings. Se. Pipe Line Co. v.

Tichacek, 997 S.W.2d 166, 172 (Tex. 1999); Spencer , 876 S.W.2d at 157 .

A. Benefit of the Bargain

The objective in awarding damages for a breach of contract is to provide just

compensation for the loss actually sustained by the complaining party. Phillips v.

Phillips , 820 S.W.2d 785, 788 (Tex. 1991). Damages for breach of contract protect

three interests: a restitution interest, a reliance interest, and an expectation interest.

See O’Farrill Avila v. Gonzalez , 974 S.W.2d 237, 247 (Tex. App.—San Antonio

1998, pet. denied). The general measure of damages in a common-law breach of

contract claim is just compensation for the loss or damage actually sustained,

commonly referred to as the “benefit-of-the-bargain.” Bowen v. Robinson , 227

S.W.3d 86, 96 (Tex. App.—Houston [1st Dist.] 2006, pet. denied). The “benefit-of-the-bargain” measure represents the difference between the value expected from the

contract and the value actually received by the non-breaching party. Frost Nat’l Bank

v. Heafner , 12 S.W.3d 104 , 111 n.5 (Tex. App.—Houston [1st Dist.] 1999, pet.

denied). The proper measure of damages is a question of law for the court, and the

court’s charge should limit the jury’s consideration to facts that are properly a part of

the damages allowable. Allied Vista, Inc. v. Holt , 987 S.W.2d 138, 141 (Tex.

App.—Houston [14th Dist.] 1999, pet. denied).

Actual damages are either “direct” or “consequential.” Arthur Andersen & Co.

v. Perry Equip. Corp. , 945 S.W.2d 812, 816 (Tex. 1997). Direct damages are those

that flow naturally and necessarily from the breach. Id . “Direct damages compensate

for the loss, damage, or injury that is conclusively presumed to have been foreseen

or contemplated by the party as a consequence of his breach of contract or wrongful

act.” Id. “Consequential damages” are those which result naturally, but not

necessarily, from the breach. Id . Consequential damages must be foreseeable and

must be directly traceable to the wrongful act and result from it. Id.

A general measure of damages is subject to any agreement that the parties

might have made with respect to damages because parties to a contract are free to

limit or modify the remedies available in the event of a breach of the contract. GT &

MC, Inc. v. Tex. City Refining, Inc. , 822 S.W.2d 252, 256 (Tex. App.—Houston [1st

Dist.] 1991, writ denied); see also Heafner , 12 S.W.3d at 110–11 (reversing award

of consequential damages when contract excluded liability for consequential

damages).

Here, the Contract reflects that TGP and Technip agreed to limit the remedies

available in the event of a breach of the Contract. Hence, TGP’s ability to recover its

full expectancy interest, or the full benefit of its bargain, is subject to limitations. We

consider the nature of the contractual limitations and whether they apply to the

damages at issue in this case.

B. Contractual Limitations

The parties agreed at Article 19.1 of the Contract to limit the remedies

available, as follows:

Consequential Damages : Notwithstanding any other provisions of this

Agreement to the contrary, in no event shall Owner or Contractor be

liable to each other for any indirect, special, incidental or consequential

loss or damage including, but not limited to, loss of profits or revenue,

loss of opportunity or use incurred by either Party to the other, or like

items of loss or damage; and each Party hereby releases the other Party

therefrom.The parties do not dispute that Article 19.1 precludes recovery for incidental or

consequential damages. Rather, TGP contends that its claims constitute “direct

damages” and therefore are not precluded by Article 19.1. Technip contends that all

of TGP’s claims are for incidental, indirect, and consequential damages and thus are

barred by Article 19.1.

It is a basic premise of contract interpretation that unambiguous contracts are

construed as a matter of law. Coker v. Coker , 650 S.W.2d 391 , 393–94 (Tex. 1983).

The parties have stipulated that Article 19.1 is unambiguous. When a contract is

unambiguous, “the court must enforce it as written.” Transcon. Gas Pipeline Corp.

v. Texaco, Inc. , 35 S.W.3d 658, 665 (Tex. App.—Houston [1st Dist.] 2000, pet.

denied) . In construing the contract, we attempt to ascertain the parties’ true intent “as

expressed in the instrument.” Nat’l Union Fire Ins. Co. v. CBI Indus. , 907 S.W.2d

517, 520 (Tex. 1995). We presume that the parties intended for every clause to have

some effect. Heritage Res., Inc. v. NationsBank , 939 S.W.2d 118, 121 (Tex. 1996).

We give terms their plain, ordinary and generally accepted meaning unless the

instrument shows that the parties used them in a technical or different sense. Id.

Here, we apply these rules of construction to determine whether Article 19.1

precludes TGP’s claims. By its plain language, Article 19.1, entitled “Consequential

Damages,” provides that, without regard to any other provision of the Contract, the

parties agreed to release each from any liability for any “indirect, special, incidental

or consequential loss or damage.” The parties defined such damages within this

provision as including “loss of profits or revenue, loss of opportunity or use” and

“like items of loss or damage.”

TGP contends that Article 19.1 has no bearing on its direct damages. TGP

contends that, to the degree its damages could be characterized as lost profits or loss

of use, Article 19.1 “excludes only ‘lost profits’ and ‘loss of use’ that also qualify as

consequential” and does not preclude it from recovering its lost profits and loss of use

that constitute direct damages arising from Technip USA’s breach.

Technip contends that the language of Article 19.1 reflects that the parties “set

out general categories of damages that would be excluded—“indirect, special,

incidental and consequential—and then they set out a non-exclusive list of damage

claims that are specifically excluded—loss of opportunity, loss of use, lost profits,

lost revenue, and ‘like items of loss or damage.’” Technip contends that the parties

defined damages for loss of use, opportunity, and profits as being wholly within the

categories of “indirect, special, incidental or consequential damages.” Hence,

contends Technip all claims for loss of use, opportunity, or profits are necessarily

barred under Article 19.1.

In addition, Technip contends that the parties’ removal of the liquidated

damages provision (which specified damages for delay) demonstrates that the parties

did not intend to place the risk of lost use, opportunity, or profits on Technip USA.

Technip contends that the Contract, as drafted, left TGP without a remedy for its

delay claims, but that this was negotiated up front and TGP enjoyed a $1.5 million

decrease in the Contract price to assume the risks of delay. TGP contends that the

removal of the liquidated damages provision simply left TGP’s claims unliquidated,

not defunct.

In attempting to harmonize Article 19.1 with the other terms of the Contract,

we note that Article 2.5 of the Contract indicates that Technip USA assumed certain

risks—including “all risk related to and any right to claim any adjustment in the

Project Schedule or Contract Price for (i) topography or soil conditions, (ii)

availability of laborers and Subcontractors, (iii) adequate availability and

transportation of Equipment, and (iv) and [sic] breakdown or other failure of

Equipment under the control of or provided by [Technip USA].” In addition,

pursuant to Article 13, Technip USA guaranteed that Substantial Completion would

not be delayed beyond the “Substantial Completion Date on a Station-by-station

basis.” Further, Article 19.2 provides, as follows, in pertinent part:

19.2 Limitation of Liability . Except for [Technip USA’s] liability

arising out of or relating to Articles 12 (warranties), 13 (guarantee of

timely completion), . . . , 5.2C (Substantial Completion Date), . . .

[Technip USA’s] liability arising out of or relating to this [Contract]

shall be limited to 50% of the Contract Price, regardless of whether the

liability arises out of contract, . . . or any other legal or equitable theory.

Hence, Technip USA agreed to assume certain risks and extended a guarantee

with regard to completion. In addition, subject to certain exceptions, the parties

agreed to cap at 50% of the Contract Price any liability of Technip USA arising from

violations of the provisions of the Contract, regardless of the theory of liability.

Notably, the exceptions include liability concerning warranties and timely

completion, which are not capped.

Considering the Contract as a whole, we conclude that Article 19.1, as written,

does not preclude any and all liability that arises from delay under the Contract. Had

all such liability been precluded at Article 19.1, Article 19.2 would be rendered

meaningless. We conclude that Article 19.1, “Consequential Damages,” does not

preclude the recovery of direct damages involving loss of use, opportunity, or profits.

We next consider whether the specific claims at issue constitute claims for

direct or consequential damage:

1. “ Project delay costs”

TGP contends that it is entitled to the jury award for its “project delay costs”

because the Project took longer to complete than agreed and TGP incurred substantial

expenses for the extended administration. Specifically, TGP asserts that it incurred

extended expenses for labor, travel, environmental contractors, TGP inspectors,

purchase and supply of additional construction consumables, costs for hauling

wastewater from the site, and services and utilities. TGP contends that these expenses

constitute “direct damages” because they naturally and necessarily flow directly from

the breach in that the expenses would not have been incurred but for the breach of the

Contract by Technip.

Article 4 of the Contract, “Owner’s Responsibilities,” provides that TGP is

required to provide: permits; construction and permanent power; incoming high

power transmission lines; storage and lay down areas at the Sites; space at the Sites

for construction trailers; water; potable water; fire water; hydrotest media; and

operation personnel for commissioning.” Hence, the parties clearly contemplated that

TGP would incur these costs throughout the Project and a breach of the Contract by

delay naturally and necessarily would cause these costs to be extended over a longer

period of time.

We conclude that these damages that resulted from the delay represent direct

damages because they clearly flow naturally and necessarily from the breach. See

Arthur Andersen & Co. , 945 S.W.2d at 816 . Because TGP is expressly responsible

for these costs under the Contract, it can be conclusively presumed to have been

foreseen or contemplated by Technip that, as a consequence of its breach of the

Contract by delay, TGP would have to continue paying these ongoing costs. See id.

TGP is not precluded from receiving these damages under Article 19.1 of the

Contract.

2.–4. Loss of efficiency–excess gas, oil, and labor

TGP characterizes its claims for “excess gas use,” “excess lube oil,” and

“excess labor cost” as damages for “loss of efficiency caused by the delay” and “lost

value.” TGP compared the cost of gas and oil used in the old compressors with what

it anticipates it would have expended had the new, more efficient compressors been

timely installed. As to labor, TGP compared the level of labor costs expended to run

the old equipment during the delay with the labor costs it anticipates it would have

incurred once the highly automated compressors were installed. TGP contends that

these claims represent direct damages because “the entire reason for the Project [was]

to obtain the new compressors on a timely basis.”

Technip contends that TGP’s claims of lost efficiency constitute claims of

consequential “loss of use” damages and are precluded under Article 19.1. We agree

that the loss of anticipated savings on the projected efficiency of the new compressor

components is not a direct damage because it is too remote to be “conclusively

presumed to have been foreseen or contemplated” by Technip USA as a consequence

of its breach. See Arthur Andersen & Co. , 945 S.W.2d at 816 ; Wade and Sons Inc.

v. Am. Standard, Inc. , 127 S.W.3d 814, 823 (Tex. App.—San Antonio 2003, pet.

denied).

5. “Power at Station 63”

TGP contends that it is entitled to damages for providing extended “Power at

Station 63” separately from its “Project delay costs” above. As we concluded in our

analysis of the “Project delay costs,” because TGP is expressly responsible for

providing power under the Contract, it can be conclusively presumed to have been

foreseen or contemplated by Technip that, as a consequence of its breach of the

Contract by delay, TGP would have to continue paying these ongoing costs. See id.

We conclude that these damages resulting from the delay also represent “direct

damages” because they clearly flow naturally and necessarily from the breach. See

Arthur Andersen & Co. , 945 S.W.2d at 816 . Hence, these damages are likewise not

precluded under the Contract.

6. Backup generator at Station 47

TGP contends that, pursuant to Article 3 of the Contract, Technip was required

to perform its work according to “Good Engineering and Construction Practices” and

to ensure that its work did not “unreasonably interfere with the operation of the

Facilities.” In addition, TGP points to the “Scope of Work” that it contends the

parties agreed on that stated that “[r]etirement of existing equipment shall not begin

until the replacement horsepower is in service without permission of the Company.”

TGP complains that Technip USA dismantled an existing backup generator at Station

47 before the new backup generator was fully functional. When a power outage

occurred, TGP was forced to rent a backup generator to ensure continuing operations

and to comply with regulations. TGP contends that it is entitled to recover its costs.

Technip contends without discussion that this cost represents an indirect

damage “clearly ancillary to the progress of the Project.”

We cannot conclude that a power outage and the necessity of a rented backup

generator could have been “conclusively presumed to have been foreseen or

contemplated” by Technip USA at the time the Contract was formed “as a

consequence of [its] breach of contract or wrongful act.” See Arthur Andersen & Co. ,

945 S.W.2d at 816 . Hence, we cannot conclude that the damages are “direct.” We

conclude that the damages resulted naturally, but not necessarily, from the breach.

See id. Hence, these damages are “consequential.” Because Article 19.1 of the

Contract precludes recovery for consequential damages, the trial court did not err by

excluding them.

7. Allowance for funds used during construction

TGP contends that it paid for the project out of its own funds and that it is

entitled to damages for the interest that accrued “on the total amount TGP had

invested in the Project during the delay period.” Although this claim does not involve

any actual payment to a third party, TGP characterizes this claim as a “a loss of

borrowing power” because it represents interest TGP theoretically could have earned

on its money—generally “ranging from five to six percent”—had it invested the funds

it spent on this project in other investments during the delay period.

“Interest is an element of damages suffered by the ‘loss of use’ of money.”

Sherrill v. Phillips , 405 S.W.2d 627, 633 (Tex. Civ. App.—Austin 1966, writ ref’d

n.r.e.); see Marrs and Smith P’ship v. D.K. Boyd Oil and Gas Co., 223 S.W.3d 1 ,

24–5 (Tex. App.—El Paso 2005, pet. denied) (explaining that “interest as interest (eo

nomine) is compensation for the use or detention of money” and “interest as damages

is compensation for lost use of money”). Here, the record shows that Bert Pineda,

TGP’s project manager, testified that “the imputed interest claim is a claim for the

loss of use of those funds.”

The lost use of money represents an indirect loss to TGP because any return

that might be attributable to theoretical investments TGP might have made falls

outside its Contract with Technip. See Cont’l Holdings, Ltd. v. Leahy , 132 S.W.3d

471, 475 (Tex. App.—Eastland, 2003, no pet.) (explaining that profits lost on other

contracts or relationships resulting from the breach are “indirect” or “consequential

damages”). Hence, TGP’s interest claim is a consequential “loss of use” claim that

is precluded by Article 19.1 of the Contract.

8. Premature energy costs at Station 54

TGP contends that it is entitled to damages for premature energy costs at

Station 54 because, asserts TGP, Technip prematurely requested permanent electricity

to Station 54. TGP contracted with the utility company to bring in large transmission

lines to get electricity to the new motors being installed at the compressor stations.

Pursuant to TGP’s contract with the utility company, TGP was to pay for a specified

amount of electric use to compensate the utility company for laying the transmission

lines. TGP was given a three-month grace period, after which time TGP either had

to begin the use of electricity at the anticipated demand rate or to pay a penalty of

50% of the anticipated demand for each month it did not use any electricity. TGP

contends that Technip USA reported that it was ready for electricity in April 2001 and

that TGP had the power turned on in May 2001, but that it was not until nine months

later that Technip commissioned the units and used the electricity.

We conclude that the trial court did not err by excluding this claim from TGP’s

recovery. TGP has not directed us to any provision in the Contract governing this

claim. However, even if Technip’s conduct constituted a breach of the Contract, we

conclude that TGP’s damage is indirect or consequential because it involves a

relationship outside of the Contract between TGP and Technip; namely, this claim

involves a penalty TGP owes under its contract with its utility company. See Leahy ,

132 S.W.3d at 475 . As an incidental or consequential damage, it is barred by Article

19.1 and the trial court did not err by excluding it.

(Claim 10.) Excessive blowdown

TGP contends that it is entitled to damages as a result of excessive blowdown.

TGP asserts that Technip failed to store certain components properly on the job sites,

which caused rust to form inside the mechanisms. Subsequently, when gas was

introduced into the new facilities, the seals were damaged and certain elements were

not tightened properly. TGP asserts that it was forced to vent gas into the atmosphere

and perform emergency shutdowns that wasted its gas product. TGP contends that

the vented gas represents gas product that TGP was then not able to sell to its gas

customers. We construe TGP’s claim to be for lost profits.

Lost profits can take the form of direct or consequential damages. Id . Profits

lost on the breached contract itself are classified as “direct damages.” Id. ; Hedley

Feedlot, Inc. v. Weatherly Trust , 855 S.W.2d 826, 834 (Tex. App.—Amarillo 1993,

no writ) (holding lost profits from breach of cattle purchase contract to be direct

damage). If a party’s expectation of profit is incidental to the performance of the

contract, the loss of that expectancy is consequential. Naegeli Transp. v. Gulf

Electroquip Inc. , 853 S.W.2d 737, 739 (Tex. App.—Houston [14th Dist.] 1993, writ

denied) (holding profits lost as result of inability to use electricity transformer not

delivered in breach of contract to be consequential damage).

Here, TGP’s expectation of profit through the sale of gas to its customers is

incidental to the performance of TGP’s Contract with Technip USA concerning the

installation of new equipment. We conclude that excessive blowdown damages are

incidental or consequential and, as such, the trial court did not err by excluding this

damage claim.

In sum, we conclude that all of TGP’s challenged damages under this issue

were precluded under the terms of the Contract, as a matter of law, except those

damages awarded for “Project delay costs” and “Power at Station 63.” Thus, the

question of damages on all but these two claims should not have been submitted to

the jury and the trial court did not err in disregarding the jury’s findings of damages

on these claims. See Tichacek , 997 S.W.2d at 172 .

Accordingly, we sustain TGP’s first issue insofar as it concerns TGP’s claims

for “Project delay costs” and “Power at Station 63.” We overrule TGP’s first issue

in all other respects.

Sufficiency of the Evidence Supporting the Damages

In its second issue, TGP contends that the trial court erred by limiting the jury

award because there was legally sufficient evidence to support the jury findings of

damages. We consider only those categories of damages that we determined above

are not precluded under the terms of the Contract—those remaining damages are for

“Project delay costs” and for “Power at Station 63.”

We review a JNOV under a legal sufficiency standard, viewing the evidence

and inferences in the light most favorable to the jury’s finding. City of Keller v.

Wilson , 168 S.W.3d 802, 807 (Tex. 2005) (stating that “the test for legal sufficiency

should be the same for summary judgments, directed verdicts, judgments

notwithstanding the verdict, and appellate no-evidence review”). We will sustain the

granting of a JNOV based on “no evidence” when the record discloses one of the

following: (1) a complete absence of evidence of a vital fact; (2) the trial court is

barred by the rules of law or evidence from giving weight to the only evidence

offered to prove a vital fact; (3) the evidence offered to prove a vital fact is not more

than a scintilla; or (4) the evidence establishes conclusively the opposite of a vital

fact. Id. at 810 ; Tiller , 121 S.W.3d at 713 (trial court may grant JNOV if there is not

evidence to support jury finding on issue necessary to liability). More than a scintilla

of evidence exists if the evidence supporting the finding “rises to a level that would

enable reasonable and fair-minded people to differ in their conclusions.” Burroughs

Wellcome Co. v. Crye , 907 S.W.2d 497, 499 (Tex. 1995). With regard to damages

awards, the granting of a JNOV is proper if there is no evidence to support the jury’s

damages finding and if the evidence establishes the trial court’s damage award as a

matter of law. Cont’l Coffee Prods. Co. v. Cazarez , 937 S.W.2d 444, 450 (Tex.

1996).

TGP contends that “[i]t was not incumbent on TGP to prove what ‘caused’ the

delay or prove that Technip USA was culpable in the delay”; rather, that “the delay

by itself was a breach of contract and caused substantial damage.” We disagree that

TGP bears no burden to prove causation. Recovery under a breach of contract claim

requires proof of four elements: (1) the existence of a valid contract, (2) performance

or tendered peformance by the plaintiff, (3) breach of the contract by the defendant,

and (4) damages sustained by the plaintiff as a result of the breach. Crowder v.

Sheirman , 186 S.W.3d 116 , 118–19 (Tex. App.—Houston [1st Dist.] 2005, no pet.).

TGP contends that the record is replete with evidence supporting the jury’s

award of damages for project delay costs and for power at Station 63.

The record shows that TGP submitted evidence of its project delay damages in

the form of a chart summary of the expenses it incurred by station for each category

of costs during the delay or schedule “slip.” In addition, to support the chart

summary, TGP submitted a breakdown of expenses per station, listing individual

payments made on particular dates within each category of expenses.

In addition, Winston Johnson, El Paso’s Senior Vice President of Engineering,

testified that he met with Technip USA in July 2000 regarding Technip USA being

behind schedule. Concrete at Station 47 had been poured incorrectly by Technip

USA and had to be redone. Johnson testified that he met with Technip USA again in

November 2000 and discussed the lack of progress. Johnson testified that Technip

USA never asked for schedule adjustments or submitted change orders regarding the

schedule. Johnson also testified that Stations 47, 63, and 87 all had “significant

changes to the scope of work” by TGP. However, Johnson also testified that the

project involved state-of-the-art technology and that TGP’s engineers concluded that

there were issues with the design of the new units, namely, vibration problems and

alignment issues.

Dewey McLain, Vice President of Construction for Technip, testified that the

engineering was not on schedule, which he attributed, in part, to delays in the

document flow between Technip USA and Wartsila (the manufacturer of the

components).

William Ellison, Vice President of Engineered Product Sales for CSI (third

party that assembles the compressors on skids), testified that the Project involved

cutting-edge technology and that there were a number of change orders. Ellison

testified that there were problems with vibration in the units. Ellison testified that his

company was forced to cease work internally on some occasions because it would

receive requests or instructions to change scope without written authorization or

assurances that CSI would be paid for the changes.

Mike Hanson, an engineering and construction consultant testifying on behalf

of TGP, testified that Technip USA installed equipment improperly and wiring had

to be redone. Hanson also testified that certain components were not stored properly,

which caused rust problems and subsequent leaks, and that Technip USA was at fault

because it was in charge of the work site and storing the machines. Hanson also

testified that some of the delays that occurred were not the fault of Technip USA and

that he did not do a critical path analysis to determine whether any certain delay was

attributable to Technip USA or to TGP.

Bert Pineda, TGP’s project manager for the Project, testified that Technip USA

was 100 percent at fault for the delay. Pineda testified that he met with Technip USA

personnel to determine the cause of the delays. Technip USA had labor problems at

Station 63. There were commissioning problems at Stations 47, 63, and 87 that were

attributable to Technip USA having improperly stored the engines. Rust formed in

the engines, which caused broken seals and leaks in water pumps. Pineda testified

that there were delays at TGP in approving change orders, but that this was

attributable to Technip USA’s submission of orders that contained errors in the

structure and pricing.

Pineda also testified regarding his methodology to determine the delay

damages. Pineda testified that he added up all of the time between what was

apparently the first day after the date of demobilization and the date of actual

substantial completion, and then attributed 100% of the delay in this period to

Technip USA. Pineda testified that he did not determine if, within each delay period,

Technip USA actually caused the delay. Pineda stated that he did not identify

whether any of the issues he believed Technip USA did wrong were associated with

any particular period of delay. Pineda testified, for instance, that there were

permitting delays as Stations 47, 63, and 87, but that these delays were not taken into

account. Pineda also testified that there were numerous alignment issues, but that

delays attributable to modifications were not taken into account. Pineda testified that

he did not consider what percentage of the delay issues were attributable to TGP and

what percentage could be attributed to Technip USA.

We conclude that this evidence constitutes more than a scintilla because it

“rises to a level that would enable reasonable and fair-minded people to differ in their

conclusions.” Crye , 907 S.W.2d at 499 . We hold that, having reviewed all of the

evidence in the light most favorable to the jury’s finding, the trial court’s granting of

a JNOV as to the damages was improper because there is evidence to support the

jury’s damages finding. See Wilson , 168 S.W.3d at 807 ; Cazarez , 937 S.W.2d at 450 .

Accordingly, we sustain TGP’s second issue insofar as it relates to its damages

for “Project delay costs” and “Power at Station 63.” We overrule TGP’s second issue

in all other respects.

Parent Guaranty

In its third issue, TGP contends that the trial court erred by limiting the jury

award because Technip S.A. was required, pursuant to the guaranty it executed

(“Guaranty”), to pay all of TGP’s damages arising from Technip USA’s breach of the

Contract.

A guarantor’s liability is measured by the principal’s liability unless a more

extensive or more limited liability is expressly provided for in the guaranty. W. Bank-Downtown v. Carline , 757 S.W.2d 111, 113 (Tex. App.—Houston [1st Dist.] 1988,

writ denied). To determine the extent of the guarantor’s liability, we look to the

language of the guaranty agreement. Id. If the guaranty agreement is so worded that

it can be given a certain or definite legal meaning or interpretation, it is not

ambiguous, and we construe the contract as a matter of law. Id. at 114 . If uncertainty

exists as to the meaning of the guaranty contract, and if two reasonable interpretations

may be made, we apply the construction most favorable to the guarantor. Coker , 650

S.W.2d at 394 n.1 (explaining that “guarantor is entitled to have his agreement strictly

construed so that it is limited to his undertakings, and it will not be extended by

construction or implication”); Clarke v. Walker-Kurth Lumber Co. , 689 S.W.2d 275,

278 (Tex. App.—Houston [1st Dist.] 1985, writ ref’d n.r.e.).

Here, the Guaranty provides as follows, in pertinent part:

1. GUARANTY

a. On the terms and subject to the conditions contained herein,

[Technip S.A.] hereby irrevocably and unconditionally

guarantees, to and for the benefit of [TGP], the performance of all

[Technip USA’s] obligations contained in the [Contract] in

accordance with the terms hereof. . . .

b. If, for any reason, [Technip USA] shall fail or be unable to duly,

punctually, or fully perform the Guaranteed Obligations or

commits any breach thereof, then upon [TGP’s] request to that

effect, [Technip S.A.] shall forthwith perform or shall cause a

third party acceptable to [TGP] to perform such obligations and

shall indemnify and keep indemnified [TGP] against any loss,

damages, costs and expenses arising from the said failure or

breach for which [Technip USA] may be liable in accordance

with the [Contract], as if it was the primary obligor. c.[Technip S.A.’s] obligations and liability under this Guaranty

shall in no event exceed [Technip USA’s] obligations and liability

under the [Contract].

2. OBLIGATIONS

[Technip S.A.] agrees that the obligations of [Techip S.A.] set

forth in this Guaranty shall be absolute and unconditional, shall

not be subject to any counterclaim, set-off-deduction, . . .

reduction, or defense (other than full and strict compliance by

[Technip S.A.] with its obligations hereunder) based upon any

claim [Technip S.A.] may have against [Technip USA] . . . .

The trial court held Technip S.A. jointly and severally liable as a guarantor for

payment of the judgment. The parties do not dispute that Technip S.A. is liable to

TGP under the Guaranty; rather, the parties dispute the extent of that liability.

TGP contends that the Guaranty required Technip S.A. to “keep TGP whole for

any breach of the Contract by Technip USA” and that the “evidence conclusively

established that Technip failed to do so.” Specifically, to support its position, TGP

directs us to paragraph 1b of the Guaranty which provides that “[i]f, for any reason,

[Technip USA] shall fail or be unable to duly, punctually, or fully perform the

Guaranteed Obligations or commits any breach thereof” Technip S.A. is required to

“indemnify and keep indemnified [TGP] against any loss, damages, costs and

expenses arising from the said failure or breach for which [Technip USA] may be

liable in accordance with the [Contract].” TGP contends that, according to the terms

of the Guaranty, Technip S.A. must reimburse TGP for any loss, damages, or costs

arising from Technip USA’s breach.

Technip contends that Technip S.A. is liable to the same degree that Technip

USA is liable and no more. Technip contends, and we agree, that the Guaranty

clearly provides that “[Technip S.A.’s] obligations and liability under this Guaranty

shall in no event exceed [Technip USA’s] obligations and liability under the

[Contract].” This language means that Technip S.A. is not liable to TGP beyond the

level of liability imposed on Technip USA. See Carline , 757 S.W.2d at 113–14.

TGP contends that Technip’s focus on this language “ignores the rules of

contract construction, which require a court to read the agreement in its entirety and

to harmonize its provisions.” TGP points us to paragraph 1a, which states that:

“[Technip S.A.] hereby irrevocably and unconditionally guarantees, to and for the

benefit of [TGP], the performance of all [Technip USA’s] obligations contained in

the [Contract].”

Reading paragraph 1a in its entirety, as we must, we note that TGP omits

significant language from this provision, emphasized as follows:

On the terms and subject to the conditions contained herein, [Technip

S.A.] hereby irrevocably and unconditionally guarantees, to and for the

benefit of [TGP], the performance of all [Technip USA’s] obligations

contained in the [Contract] in accordance with the terms hereof . . .

(Emphasis added.) By its plain language, Technip S.A.’s guarantee of Technip

USA’s obligations is subject to the terms and conditions contained in the Guaranty.

As noted above, those terms include that “[Technip S.A.’s] obligations and liability

under this Guaranty shall in no event exceed [Technip USA’s] obligations and

liability under the [Contract].”

In addition, TGP contends that it is entitled to a judgment against Technip S.A.

for the total jury award because the Guaranty prohibits Technip S.A. from claiming

any set-off or defense. TGP contends that, pursuant to the express terms of paragraph

2, Technip S.A.’s obligations are not “subject to any counterclaim, set-off-deduction,

. . . reduction or defense” and therefore Technip S.A. cannot apply any reduction to

the jury award for the retainage at issue and cannot apply the consequential damages

defense asserted by Technip USA.

A closer reading of paragraph 2 indicates that Technip S.A.’s obligations under

the Contract are “not subject to any counterclaim, set-off-deduction, . . . reduction,

or defense (other than full and strict compliance by [Technip S.A.] with its

obligations hereunder) based upon any claim the Guarantor [Technip S.A.] may have

against Contractor [Technip USA] .” (Emphasis added.) Thus, Technip S.A. is

precluded from claiming that any set-off, reduction, or defense Technip S.A. might

have against Technip USA reduces its liability to TGP. There are not any claims at

issue between Technip USA and Technip S.A. in this case.

Finally, TGP contends that the Contract required Technip USA to obtain a

guaranty from its parent, Technip S.A., that was to be in the form of Exhibit “T” to

the Contract. TGP contends that the guaranty was to have “no limitation of liability.”

TGP contends that, because Technip USA failed to execute a guaranty in the form of

Exhibit “T,” and instead executed a different form of guaranty, TGP was prevented

from receiving the benefit of the “intended Technip guaranty, and TGP is entitled to

recover that benefit from Technip USA.” We must enforce a contract as written, not

as one party contends that, in hindsight, it intended for to have been written. See CBI

Indus., Inc. , 907 S.W.2d at 520 (ascertaining intent of parties “as expressed in the

instrument”); Texaco, Inc. , 35 S.W.3d at 665 (enforcing unambiguous contract as

written).

We conclude that the trial court did not err in limiting Technip S.A.’s liability

as guarantor to the liability imposed on Technip USA.

Accordingly, TGP’s third issue is overruled.

II. Technip’s Appeal

In its appeal, Technip contends that the trial court erroneously denied its

Motion for Judgment Notwithstanding the Verdict on the issue of TGP’s

workmanship-related damages because (1) such claims are barred by the exclusive

remedy provisions of the agreement; (2) the evidence is insufficient to support the

damages awarded on the realignment and as-built drawings claims; and (3) the trial

court improperly applied the stipulated retainage offset and improperly calculated

interest and attorney’s fees.

Defective Workmanship Claims

In its first issue, Technip contends that the trial court erroneously denied its

Motion for Judgment Notwithstanding the Verdict on the issue of TGP’s

workmanship-related damages because such claims are barred by the exclusive

remedy provisions of the agreement. Specifically, the trial court granted damages to

TGP as awarded by the jury on the following workmanship-related claims:

“Realignment of compressor costs,” “Replacement and installation of operable oil fill

systems,” and “Review of ‘as-built’ drawings.” Technip contends that there is no

evidence that TGP gave notice of the alleged defects to Technip USA, as required

under the Contract.

B. Standard of Review

We review the denial of this portion of Technip’s Motion for Judgment

Notwithstanding the Verdict under a legal sufficiency standard. See Brown v. Bank

of Galveston , 963 S.W.2d 511, 513 (Tex. 1998); CDB Software, Inc. v. Kroll , 992

S.W.2d 31, 35 (Tex. App.—Houston [1st Dist.] 1998, pet. denied). A JNOV should

be entered on “no evidence” when the evidence offered to prove a vital fact is no

more than a scintilla. Wilson , 168 S.W.3d at 823 . We view the evidence and

inferences in the light most favorable to the jury’s finding. Id. at 807 . With regard

to damages awards, the granting of a JNOV is proper if there is no evidence to

support the jury’s damages finding and if the evidence establishes the trial court’s

damage award as a matter of law. Cazarez , 937 S.W.2d at 450 .

C. Relevant Contractual Provisions

The Contract provides, at Article 1, that “‘Defect’ or ‘Defective’ shall have the

meaning set forth in Section 12.1 .”

Article 12.1 defines what constitutes a “defect” and includes issues with quality

of equipment and workmanship. Generally, “[a]ny Work that does not meet the

standards set forth in this Section 12.1 is ‘Defective’ or contains a ‘Defect.’”

Article 12.2, “Owner’s Right to Inspect,” provides, in relevant part, as follows:

A. General Rights . All work shall be subject to inspection by [TGP]

at all times to determine whether the Work conforms to the requirements

of the Agreement. [Technip USA] shall furnish [TGP] with access to all

locations where work is in progress . . . . If, in the judgment of [TGP],

any Work is Defective, then [Technip USA] shall, at its expense,

promptly repair or replace the Defective Work. Subject to [Technip

USA’s] right to pursue a dispute under Article 18 (“Dispute

Resolution”), the decision of [TGP] shall be conclusive as to whether

the Work is conforming or Defective, and [Technip USA] shall comply

with the instructions of [TGP] in all such matters while pursuing any

dispute. If it is later determined that the Work was not defective, then

[TGP] shall reimburse [Technip USA] for all costs incurred in

connection with such repair or replacement and a Change Order shall

be issued for such amount and shall address any impact the repair or

replacement may have had on the Project Schedule. If [Technip USA]

fails, after a reasonable period of time not to exceed one (1) week, to

repair or replace any Defective Work, or to commence to repair or

replace any Defective Work and thereafter continue to proceed

diligently to complete the same, then [TGP] may repair or replace such

Defective Work and the expense thereof shall be paid by [Technip

USA].

(Emphasis added.)

Article 12.3, “Warranty of Defects,” provides, in relevant part, as follows: A. Defect Period . Except as provided in Section 12.1.D

(“Subcontractor Warranties”), [Technip USA] shall promptly repair or

replace, at no cost to [TGP], any Defective Work, if the Defect appears

or occurs during the twelve (12) month period commencing on

Substantial Completion of the Facilities (the “Defect Period”).

. . . . C. Remedy . [TGP] shall provide notice to [Technip USA] of the

discovery or any Defective Work as soon as practicable after such

discovery.

D. Repair by Owner . If, after notification of a breach of warranty

under Section 12.3.C., [Technip USA] delays in commencing,

continuing or completing curative action, then [TGP], by written notice

to [Technip USA], may correct such Defect(s) in accordance with this

Contract, and [Technip USA] shall be liable for all reasonable direct

costs, charges and expenses incurred by [TGP] in connection with such

repair or replacement and shall pay to [TGP] an amount equal to such

costs, charges and expenses upon receipt of an invoice from [TGP].

Article 12.5 of the Contract provides that

[t]he warranties provided under this [Contract] are the sole and

exclusive warranties provided by [Technip USA]. No other warranties,

express or implied, are provided by [Technip USA] hereunder. Owner’s

remedies are limited to those described herein.

D. Analysis

Technip USA contends that Article 12.3C required TGP to give notice to

Technip USA of any work it deemed defective and that Article 12.3D required that,

after such notice, if Technip USA failed to cure the defect, TGP was required to give

written notice that it would correct the defect and then Technip USA would be liable

for such costs. Technip USA contends that there is no evidence that TGP provided

the required written notice of the defects at issue, that TGP gave Technip USA a

chance to cure the defects, or that TGP gave written notice that it would repair the

defects at Technip USA’s expense. Technip USA contends that, as such, TGP did not

avail itself of the warranty provision in the Contract, which, pursuant to Article 12.5,

was its exclusive remedy.

On the other hand, TGP contends that it was not required to give written notice

of defects under the Contract. TGP contends that “[t]he ‘Defect Period’ for Warranty

claims under Article 12.3 does not begin until after substantial completion and after

all of the Work required by the Contract has been completed.” TGP contends that

Article 12.2 governs because the workmanship issues first arose while work was in

progress (prior to substantial completion) and that nothing in Article 12.2 required

TGP to give notice to Technip USA concerning such defects.

Article 12.2 provides that TGP has a right to inspect the work “at all times” to

determine whether work conforms to the Contract; that “ Contractor [Technip USA]

shall furnish Owner [TGP] with access to all locations where work is in progress ”;

that if, in TGP’s judgment, any work is defective, then Technip USA will promptly

repair or replace the defective work; and that, if it is subsequently determined that

work was not defective, then TGP will reimburse Technip USA for costs and that “ a

Change Order shall be issued for such amount and shall address any impact the

repair or replacement may have had on the Project Schedule. ” (Emphasis added.)

Based on the emphasized language, Article 12.2 clearly contemplates that it applies

while work is in progress .

The record shows that, concerning TGP’s claim for “Review of ‘as-built’

drawings,” this claim arose in 2004, when TGP went out to Station 54 and discovered

an error in the as-built drawing of that station. The certificate of substantial

completion was executed on Station 54 on April 19, 2002. Hence, this claim arose

after substantial completion.

Concerning TGP’s claim for “Replacement and installation of operable oil fill

systems,” the record shows that TGP discovered that, when it came time to service

the engines, it took three to four days to refill the oil. The delay caused significant

interruptions in TGP’s use of their stations. According to Pineda, TGP re designed

the “existing system” by bypassing the tank that sat on top of the building and

attaching a larger line to transfer oil faster. Hence, TGP discovered that it had a

design problem after the stations were in use and after the time came to service the

engines.

TGP contends that its issue of “Realignment of compressor costs,” which it

also characterizes as an issue with the “anchor bolts” that held equipment to the floor,

began prior to substantial completion of the project (while work was in progress) and

that the issues were never rectified. TGP argues that the anchor bolts were “never

finished,” as evidenced by their inclusion on various punch lists,

and that they could

not have constituted a warranty issue. However, TGP also characterizes the issue as

follows:

• “During construction an issue arose regarding the torque value (or tension)

that had been applied to the bolts. . . .” (Emphasis added.)

• “Technip agreed to remove and reinstall the equipment and each of the

anchor bolts.” (Emphasis added.)

• “To remove the anchor bolts[,] all of the equipment had to be removed then

reassembled and realigned .” (Emphasis added.)

• “Technip failed to properly align ten (10) HP replacement units . . . .

Because of this misalignment, TGP has had to institute immediate

corrective measures to rectify this situation.”

The emphasized language demonstrates that TGP’s claims were for work that

had been performed , but allegedly had been performed improperly and needed to be

removed and re installed. Thus, TGP’s claims are not, as TGP urges, for a simple

breach of contract that arose through a failure to perform the work at all. See Sw. Bell

Tel. Co. v. FDP Corp ., 811 S.W.2d 572 , 574–76 (Tex. 1991) (distinguishing between

breach of contract claim and breach of contractual warranty provision claim and

applying outside Uniform Commercial Code).

According to the record, by April 19, 2002, certificates of substantial

completion had been executed on all of the stations at issue in this appeal. Article

12.3A provides that Article 12.3 governs any defect that “appears or occurs during

the twelve (12) month period commencing on Substantial Completion.” Hence, at the

point of substantial completion, any “defective work” that arose or existed necessarily

became a warranty issue because there is no other provision in the Contract that

governs defects in workmanship that exist after substantial completion occurs.

Article 12.2, which speaks of access to locations where work is in progress, change

orders, and impact on project schedules, logically, is of no effect once the project is

substantially completed. Hence, we conclude that Article 12.3 governs.

Even if we concluded that Article 12.2 governs, we could not construe Article

12.2 in the manner that TGP advances, namely, that no notice is required under

Article 12.2. First, as a practical matter, Technip could not know that, “in the

judgment of [TGP],” certain work is defective unless TGP gives notice to Technip of

those defects. Second, Article 12.2 allows Technip “one week” to repair or replace

defective work. Without notice from TGP as to the existence of a defect, it is not

possible for Technip to calculate when that “one week” period begins or ends.

Finally, Article 12.2 provides that, should Technip fail within that week to repair or

replace any defective work, “then [TGP] may repair or replace such Defective Work

and the expense thereof shall be paid by [Technip].” We cannot logically construe

Article 12.2 to require Technip to bear the cost of rectifying any work that TGP

deems is defective, without notice.

TGP contends that Technip had actual notice of defects and that actual notice

was sufficient under Article 12.2. However, pursuant to Article 19.7: “Any notice,

demand, offer, or other written instrument required or permitted to be given pursuant

to this Contract shall be in writing signed by the Party giving such notice . . . .”

We conclude that Article 12.3 governs and that written notice of defects was

required.

TGP contends that it gave written notice of defective work. On the realignment

claim, TGP directs us to an email concerning a suggested way to rectify the

alignment; a letter from CSI to Technip USA concerning measures taken to realign

the skids; and punch lists from Station 47 and 87. As to the oil fill systems, TGP

directs us to what appear to be internal emails concerning the issue. As to the “as

built” drawings, TGP direct us to the testimony of Pineda, who stated that he

“believe[d] there was a letter sent to Technip” on this claim. These items do not

constitute evidence that TGP gave notice of defects to Technip USA pursuant to the

warranty provision in the Contract or that, after Technip USA failed to take curative

action, TGP submitted written notice that it would repair the defects at the expense

of Technip USA.

TGP asserts in its motion for rehearing that it “provided notice of default

related to the failure to complete the anchor bolt/alignment issues on June 26, 2003,

after suit was filed but before all of the work related to this claim was completed.”

The record shows that, on June 26, 2003, TGP gave Technip written “notice of

default and defect due to Technip’s failure to properly complete portions of the scope

of work,” pursuant to Article 12.3C. TGP asserted, in part, that Technip had “failed

to properly align the ten (10) HP relacement units at Stations 47, 54, 63, 87 and 96,”

and that “[b]ecause of this misalignment, TGP has had to institute immediate

corrective measures to rectify this situtation.” In its letter, TGP also asserted that

Technip had “failed to remedy past punch list items and other construction defect

items.”

This letter indicates that TGP considered its defective workmanship claims to

be Article 12.3 warranty issues. However, even if TGP’s letter of June 26, 2003

could have provided the required notice under Article 12.3, it came too late.

Substantial Completion on the final station at issue occurred on April 19, 2002. The

12-month warranty period commenced on that same date, pursuant to Article 12.3A.

Hence, the 12-month period expired on April 19, 2003. TGP’s letter of June 26, 2003

came three months too late. We conclude that this is not evidence that TGP gave

written notice of defects within the “Defect Period,” as required under the Contract.

Article 12.5 provides that “the warranties provided under this [Contract] are the

sole and exclusive warranties provided by the Contractor. No other warranties,

express or implied, are provided by the Contractor hereunder. Owner’s remedies are

limited to those described herein.” Therefore, when TGP failed to give notice as

required, it failed to invoke Article 12, and it failed to avail itself of its exclusive

remedy under the Contract.

E. Waiver

TGP asserts that Technip USA waived this issue on appeal because it failed to

plead lack of notice as an affirmative defense. Texas Rule of Civil Procedure 94

requires the affirmative pleading of certain specified defenses and of “any other

matter constituting an avoidance or affirmative defense.” Tex. R. Civ. P. 94.

Generally, if an affirmative defense is not pleaded or tried by consent, it is waived.

Tacon Mech. Contractors, Inc. v. Grant Sheet Metal, Inc. , 889 S.W.2d 666, 671 (Tex.

App.—Houston [14th Dist.] 1994, writ denied). A general denial is insufficient

because it fails to place the plaintiff on notice that defendant intends to bring in

evidence of an independent reason why plaintiff is barred from recovery, even if the

plaintiff proves the elements of his cause of action. Id.

Here, lack of notice required under the Contract goes directly to TGP’s cause

of action. Performance of any condition precedent is an essential element of a

plaintiff’s breach of contract case. See Assoc. Indem. Corp. v. CAT Contracting, Inc. ,

964 S.W.2d 276, 283 (Tex. 1998); see also Centex Corp. v. Dalton , 840 S.W.2d 952,

956 (Tex. 1992) (“A condition precedent is an event that must happen or be

performed before a right can accrue to enforce an obligation.”); Emerald Forest Util.

Dist. v. Simonsen Constr. Co. , 679 S.W.2d 51, 54 (Tex. App.—Houston [14th Dist.]

1984, writ ref’d n.r.e.) (“When a contract provides for a particular form of notice,

compliance with such provisions is a condition precedent to invoking the contract

rights which are conditioned on the notice.”). Here, TGP was required to plead that

it performed all conditions precedent, which then gave rise to Technip USA’s burden

to specifically deny the performance of any condition precedent. See Tex. R. Civ. P.

54; Beard Family P’ship v. Commercial Indem. Ins. Co. , 116 S.W.3d 839, 852 (Tex.

App.—Austin 2003, no pet.).

The record shows that, in its answer, Technip USA “specifically denied that

TGP satisfied the conditions precedent for its claims, including adherence to the

contractual procedures for asserting warranty-type claims relating to alleged defects.”

As Technip USA contends, this plea was verified pursuant to Rule 93(12), which

addresses whether “notice and proof of loss or claim for damage has not been given

as alleged.” See Tex. R. Civ. P. 93(12). We conclude that Technip USA did not

waive this issue on this basis.

In its motion for rehearing, TGP contends that Technip failed to use the words

“condition precedent” in its initial brief on appeal and, as such, the issue is waived.

TGP argues that it was not afforded an opportunity to respond to the applicability of

any “condition precedent” because these words were not used until Technip’s reply

brief.

In its brief, Technip complained that “[t]here is no legally or factually sufficient

evidence that TGP followed the warranty provisions of the Agreement. . . . Articles

12.3 and 12.5 of the Contract provide that if TGP determines that work is defective,

it must give Technip prompt notice of the defect as soon as practicable, and Technip

will repair or replace that work at its own cost. . . . TGP did not avail itself of the

warranty provisions of the Agreement, which provided its exclusive remedy for

workmanship issues. . . .” In its reply, Technip more specifically referred to this lack

of notice as the failure of a “condition precedent.”

First, we are required to construe the briefs liberally. See Tex. R. App. P.

38.1(e). Second, as TGP points out its own brief on rehearing, Technip “raised

conditions precedent in its Supplement to its Motion for JNOV” in the trial court. In

addition, in its answer, Technip specifically denied that TGP satisfied the “conditions

precedent” for its claims, including adherence to the procedural requirements in the

warranty provision. The substance of the complaint did not change on appeal. See

Hohenberg Bros. Co. v. George E. Gibbons & Co. , 537 S.W.2d 1, 3 (Tex. 1976)

(stating that no particular words are necessary for existence of condition, but terms

such as “if,” “provided that,” “on condition that,” or some similar phrase of

conditional language create condition); Emerald Forest Util. Dist. v. Simonsen

Constr. Co. , 679 S.W.2d 51, 54 (Tex. App.—Houston [14th Dist.] 1984, writ ref’d

n.r.e.) (noting that, when contract provides for particular form of notice, compliance

with form is “a condition precedent” to invoking contract rights conditioned on such

notice).

Finally, TGP contends that Technip breached the Contract and that such breach

excused TGP from having to comply with contractual notice provisions. Generally,

it is a fundamental principle of contract law that when one party commits a material

breach of mutually dependent, reciprocal promises in a contract, the other party is

discharged or excused from further performance. Mustang Pipeline Co. v. Driver

Pipeline Co. , 134 S.W.3d 195, 196 (Tex. 2004); see also Joseph v. PPG Indus., Inc. ,

674 S.W.2d 862, 867 (Tex. App.—Austin 1984, writ ref’d n.r.e.) (recognizing that

one who breaches contract may not then recover on it). However, if the non-breaching party elects to treat the contract as continuing and insists that the party in

default continue its performance, the previous breach constitutes no excuse for non-performance on the part of the non-breaching party, and the contract continues in

force for the benefit of both parties. Hanks v. GAB Bus. Servs., Inc. , 644 S.W.2d 707,

708 (Tex. 1982); Gupta v. E. Idaho Tumor Inst., Inc. , 140 S.W.3d 747 , 756–57 (Tex.

App.—Houston [14th Dist.] 2004, pet. denied); Chilton Ins. Co. v. Pate & Pate

Enters., Inc. , 930 S.W.2d 877 , 887–88 (Tex. App.—San Antonio 1996, writ denied).

Here, TGP and Technip sued each other for breach of contract. Technip lost

on its claim and did not appeal that ruling . TGP won on its claim and the trial court

awarded damages. On appeal, Technip contends that the trial court erred by awarding

damages to TGP. Hence, Technip is not “relying on the notice provisions” in a

breach of contract suit against TGP. Nor is Technip applying lack of notice as an

affirmative defense (as an independent reason that it should prevail). Rather, Technip

complains that the evidence is legally insufficient to support the verdict because TGP

failed to show evidence of an element of its own claim . See Assoc. Indem. Corp. v.

CAT Contracting, Inc. , 964 S.W.2d 276, 283 (Tex. 1998). Most importantly, the

record shows that, at all times during the dispute, TGP treated the Contract as

continuing and TGP continued to demand performance of its terms. Even after TGP

sued on the Contract, it sent a letter to Technip demanding performance under Article

12.3 of the Contract.

We conclude that Technip conclusively proved it is entitled to the JNOV on

these claims. See Wilson , 168 S.W.3d at 823 (stating that JNOV should be entered

on “no evidence” when evidence offered to prove vital fact is no more than scintilla).

Accordingly, we sustain Technip’s first issue. We do not reach its second

issue, that the evidence was insufficient to support the jury’s damages findings on

these claims.

Interest and Attorney’s Fees

In its third issue, Technip contends that the trial court improperly (1) applied

the stipulated retainage offset, (2) calculated interest, and (3) applied attorney’s fees.

1. Stipulated retainage offset

Over the course of the Project, TGP withheld a ten percent retainage from its

progress payments. The record shows that, at trial, the parties stipulated that “the

amount of the retainage at issue between the parties will be $1,650,000.” In addition,

the parties stipulated that “should TGP prevail in this case and be awarded damages

that this $1,650,000 retainage amount would be an offset against their damage

award.”

On appeal, Technip contends that the trial court erred by failing to provide “for

prejudgment interest on [the retainage] at the rate specified in section 7.7 of the

[Contract] for late payments.” The stipulation is a binding contract between the

parties and the court. Houston Lighting & Power Co. v. City of Wharton , 101 S.W.3d

633, 641 (Tex. App.—Houston [1st Dist.] 2003, pet. denied). A stipulation is

conclusive on the issue, and the parties are estopped from claiming otherwise. Id.

Hence, having stipulated to the amount of the retainage at trial, Technip cannot be

heard to complain of that amount on appeal.

In addition, Technip contends that the trial court erred by failing to subtract the

stipulated retainage prior to calculating prejudgment interest on the judgment. We

agree. The judgment reflects that damages and interest were calculated, and then

$1,650,000 retainage was subtracted. The retainage should be subtracted from the

principal amount of the judgment prior to the calculation of pre-judgment interest.

See Pringle v. Moon , 158 S.W.3d 607, 611 (Tex. App.—Fort Worth 2005, no pet.)

(applying offset to damage award prior to calculation of pre-judgment interest).

2. Interest

Technip contends that the trial court erred by awarding pre-judgment interest

on the defective workmanship damages because these damages constitute future

damages. Having determined that the trial court erred by denying Technip’s motion

for judgment notwithstanding the verdict as to TGP’s claims of “Realignment of

compressor costs,” “Replacement and installation of operable oil fill systems,” and

“Review of ‘as-built’ drawings,” and thereby determining that TGP take nothing on

these claims, we do not reach the issue of whether the interest on these claims

constitutes interest on future damages.

As to TGP’s remaining claims, Technip contends that the trial court generally

applied an incorrect rate of interest in its judgment. Specifically, Technip contends

that the trial court erred by calculating pre-judgment interest at a rate of nine percent,

which is the rate of interest provided in the Contract that is applicable only to any late

payments made to Technip by TGP under the Contract. Technip contends that the

nine percent rate does not apply to pre-judgment interest, nor does the Contract

provide for any specific rate in the event of a breach. Technip contends that when the

interest rate is not specified in a contract, pre-judgment interest should be calculated

based on the statutory rate provided in Texas Finance Code section 304.003(c)(1).

See Tex. Fin. Code Ann. 304.003(c)(1) (Vernon Supp. 2007).

There are two legal sources for an award of pre-judgment interest: (1) common

law equitable principles and (2) an enabling statute. Johnson & Higgins, Inc. v.

Kenneco Energy , 962 S.W.2d 507, 528 (Tex. 1998). However, in Johnson , the Texas

Supreme Court harmonized the common law pre-judgment interest accrual scheme

with that under the Finance Code. Id. The court held that pre-judgment interest is

calculated as simple interest and is based on the post-judgment interest rate applicable

at the time of the judgment. Id. at 532 ; Tex. Fin. Code Ann. § 304.103.

When the interest rate is not specified in a contract, pre-judgment interest

should be calculated based on the statutory rate provided in Texas Finance Code

section 304.003. See Tex. Fin. Code Ann. 304.003; ExxonMobil Corp. v. Valence

Op. Co. , 174 S.W.3d 303, 319 (Tex. App.—Houston [1st Dist.] 2005, pet. denied)

(applying section 304.003 in breach of contract claim). Although section 304.003

expressly applies to post -judgment rates, pre-judgment interest is computed at the

same statutory rate. See Tips. v. Hartland Developers, Inc. , 961 S.W.2d 618, 624

(Tex. App.—San Antonio 1998, no pet.).

Here, the record shows that the Contract provides for interest on any late

payments due under the Contract from TGP (as the annual prime plus two percent),

but it does not provide for any rate of interest on damages resulting from a breach of

the Contract by either party. Because an applicable interest rate is not specified in the

Contract, pre-judgment interest is calculated based on the statutory rate provided in

Texas Finance Code section 304.003. See Tex. Fin. Code Ann. 304.003;

ExxonMobil Corp. , 174 S.W.3d at 319 .

Section 304.003(b) provides that “[o]n the 15th day of each month, the

consumer credit commissioner shall determine the postjudgment interest rate to be

applied to a money judgment rendered during the succeeding calendar month.” Tex.

Fin. Code Ann. 304.003(c)(1). Section 304.003(c)(1) provides that, with exceptions

not applicable here, “the postjudgment interest rate is the prime rate as published by

the Board of Governors of the Federal Reserve System on the date of computation.”

Id. § 304.003(c)(1). That rate is published in the Texas Register by the Secretary of

State. Id. § 304.004. This court may take judicial notice of the correct, published rate

on appeal. Office of Pub. Util. Counsel v. Pub. Util. Comm’n of Tex ., 878 S.W.2d 598,

600 (Tex. 1994).

Here, when the trial court entered its final judgment on May 18, 2006, the

judgment interest rate as determined by the consumer credit commissioner was 7.75

percent. See Judgment Rate Summary, http:// www.occc.state.tx.us / pages/int_rates/

Index.html (last visited Nov. 15, 2007). Thus, the trial court’s judgment should have

reflected pre-judgment interest at the rate of 7.75 percent, rather than 9 percent.

Accordingly, we sustain Technip’s third issue as it concerns the pre-judgment

interest rate stated in the judgment.

3. Attorney’s fees

As to attorney’s fees, Technip contends that, although the parties stipulated to

$1.1 million as reasonable attorney’s fees for the prevailing party, if TGP’s recovery

is reduced in this appeal, the attorney’s fees should likewise be reduced. As TGP

contends, the stipulation is a binding contract between the parties and the court. City

of Wharton , 101 S.W.3d at 641 . A stipulation is conclusive on the issue, and the

parties are estopped from claiming otherwise. Id.

Accordingly, we overrule Technip’s third issue as it concerns attorney’s fees.

CONCLUSION We conclude that the trial court erred by granting judgment notwithstanding

the verdict on TGP’s claims for “Project delay costs” and “Power at Station 63.” We

reverse the trial court’s judgment as to these claims and render judgment that TGP is

entitled to the principal damages awarded by the jury on these claims. We modify the

judgment to reflect that the $1,650,000 retainage is subtracted from the principal

amount of the judgment prior to the calculation of pre-judgment interest. In addition,

we modify that portion of the trial court’s judgment awarding pre-judgment interest

at the rate of 9% per year to an award of pre-judgment interest at the rate of 7.75%

per year. See Tex. R. App. P. 43.2(b). Further, we conclude that the trial court erred

by denying Technip’s motion for judgment notwithstanding the verdict on TGP’s

claims for “Realignment of compressor costs,” “Replacement and installation of

operable oil fill systems,” and “Review of ‘as-built’ drawings.” We reverse the trial

court’s judgment as to these claims and render judgment that TGP take nothing on

these claims.

The trial court’s judgment is affirmed in all other respects.

Laura Carter Higley

Justice

Panel consists of Justices Taft, Hanks, and Higley.