Opinion

Hunt Construction Group, Inc., Desert Plains, Inc., Way Engineering, Ltd., and Way Engineering Service, Ltd. v. Kevin Konecny

Court
Texas Court of Appeals, 1st District (Houston)
Filed
Dec 4, 2008
Status
Published
Cited by
0 cases
Authority
More cited than 35.2%

The opinion

Opinion issued December 4, 2008

In The

Court of Appeals

For The

First District of Texas

NO. 01-06-01155-CV

____________

HUNT CONSTRUCTION GROUP, INC., DESERT PLAINS, INC., WAY

ENGINEERING, LTD., AND WAY ENGINEERING SERVICE, LTD.,

Appellants

V.

KEVIN KONECNY, Appellee

On Appeal from the 125th Judicial District Court of

Harris County, Texas

Trial Court Cause No. 2004-21023

O P I N I O N

This appeal concerns the exclusive remedy of coverage under the Texas

Workers’ Compensation Act (the “Act”). See Tex. Lab. Code §§ 401.001–451.003

(Vernon 2006 & Supp. 2008). Appellants, Hunt Construction Group, Inc. (“Hunt”),

Desert Plains, Inc. (“Desert Plains”), Way Engineering, Ltd., and Way Engineering

Service, Ltd. (collectively “Way”), appeal from a judgment finding that they

negligently contributed to the injuries of Kevin Konecny, appellee. In two issues,

appellants assert that (1) the Act bars Konecny’s claims because he recovered

workers’ compensation benefits for his injury and those benefits were the exclusive

compensation he could receive, and (2) the evidence is legally insufficient to show

that either Hunt or Way is liable for Konecny’s injury. We conclude that Konecny’s

recovery of workers’ compensation benefits bars any other recovery from appellants .

We reverse the judgment of the trial court and render judgment in favor of appellants. Background

The Harris County Houston Sports Authority (“the Sports Authority”) owned

the property where the Houston Multipurpose Arena was constructed. The Arena is

now called the Toyota Center. The Sports Authority hired Hunt as the general

contractor for the project. Hunt subcontracted the ventilation and air conditioning

work to Way, who subcontracted the sheet metal and duct work to Superior Air

Handling Corporation (“Superior”). Konecny was a foreman for Superior. Hunt

subcontracted the application of fireproofing material to Desert Plains.

The Sports Authority implemented an owner-controlled insurance program

(OCIP) to provide workers’ compensation, general and excess liability, and builders’

risk insurance coverage for the entire Toyota Center project. At the Toyota Center

project, the subcontractors were required to participate in the OCIP, with its

requirements included in every subcontract. The costs for the OCIP were paid through

a credit against each subcontractor’s contract price.

According to the OCIP manual, the OCIP was “for the benefit of the Owner,

Construction Manager, contractor and eligible subcontractors of all tiers who have on-site employees.” The manual defined “eligible contractor” to include “all

subcontractors providing direct labor on Houston Multipurpose Arena site . . . .

Temporary labor services and leasing companies are to be treated as a subcontractor

[sic].” The manual defined “ineligible contractor” to include “consultants, suppliers

(that do not perform subcontract installation), vendors, materials dealers, guard

services, or janitorial services, truckers . . . , and other temporary project services.”

The list describing ineligible contractors was illustrative, not exclusive.

The OCIP coverage obtained by the Sports Authority applied to “Hunt, all

employees of Hunt, all subcontractors of Hunt, and all subcontractors of

subcontractors.” The subcontract between Hunt and Way had a credit to pay for the

workers’ compensation coverage under the OCIP. Similarly, the subcontract between

Way and Superior had a credit to pay for the workers’ compensation coverage under

the OCIP. The total contract price for Superior’s work included an $81,000 deduction

for “OCIP deduct.” Way and Superior each subscribed to the workers’ compensation

insurance coverage provided to them through the Sports Authority’s OCIP.

The OCIP was described in what was called “Attachment V,” which was

attached to the contract between Hunt and Way and the contract between Hunt and

Desert Plains. The contract between Hunt and Desert Plains required Desert Plains to

“purchase and maintain in force the insurance coverages set forth in Attachment V.”

The contract between Hunt and Way imposed the same requirement on Way.

Attachment V stated,

ATTACHMENT V

INSURANCE REQUIREMENTS

OWNER CONTROLLED INSURANCE PROGRAM

Harris County-Houston Sports Authority hereinafter collectively called

the Owner has elected to implement an Owner Controlled Insurance

Program (OCIP) that will provide Workers’ Compensation, Employer’s

Liability, General Liability, Excess Liability and Builder’s Risk for the

Construction Manager, contractors and subcontractors of every tier

providing direct labor to The Houston Multipurpose Arena Project,

hereinafter called The Project. The Owner agrees to pay all premiums

associated with the OCIP including deductibles or self-insured retention

subject to adjustment of the Contract Sum as provided in paragraph

11.1.7 below, unless otherwise stated in the contract documents.

. . . .

APPLICABILITY OF THE OWNER CONTROLLED INSURANCE

PROGRAM

Participation in the OCIP is mandatory but not automatic.

Eligible Contractor includes all subcontractors providing direct labor on

the Project site . . . .

. . . .

Unless otherwise directed by The Owner, Contractors/subcontractors not

enrolled in the OCIP shall be required to maintain their own insurance.

Coverage types and limits are set forth in Article 11 of the General

Conditions of the contractor. Contractor shall promptly furnish The

Owner, or their designated representative, certificates of insurance giving

evidence that all required insurance is in force.

. . . .

CONTRACTOR’S RESPONSIBILITY FOR ITS SUBCONTRACTORS

The Contractor shall require that all subcontractors of every tier shall

complete and submit Form 2, and shall also provide a copy of the

declaration page(s) and premium rate page(s) for each policy, at least ten

(10) days after notice to proceed is granted. TI shall be the Contractor’s

responsibility to submit to The Owner and its designated representative,

changes to the cost of the subcontractor’s insurance resulting from any

adjustments to its program. Contractor shall include all of the provisions

of this Article 11 in every subcontract so that such provisions will be

binding upon each of its subcontractors.

. . . .

CERTIFICATES AND POLICIES

Each Contractor and all tiers of subcontractors will receive a separate

Workers’ Compensation policy.

. . . .

SUBCONTRACTOR PARTICIPATION

Upon execution of a subcontract, the Contractor will immediately report

all new subcontractors to the OCIP Program Administrator for

enrollment in the OCIP. The subcontractor shall incorporate all the

provisions in any subcontractor agreement and shall cause its

subcontractors to cooperate fully with the Owner, the OCIP Program

Administrator and insurance companies for the Project, in the

administration of the OCIP. . . . Contractor shall not permit any

subcontractor to enter the Project Site prior to enrollment in the OCIP

unless they are ineligible to participate in the OCIP and covered by their

own insurance. Failure to do so shall negate the afforded coverage(s).

. . . .

ADMINISTRATION OF THE OCIP

Administration is an integral part of the success of the OCIP. All

Contractors MUST be properly enrolled in the OCIP before access to the

Project site is allowed.

On May 23, 2003, crews from Superior and Desert Plains found themselves

working on the same level of the Toyota Center project. The Superior crew, with

Konecny as foreman, was installing perimeter air ducts while the Desert Plains crew

was spraying fireproofing material on support beams. As the Desert Plains crew

gradually got closer to the Superior crew, so did overspray from the slippery

fireproofing material. For safety reasons, Konecny instructed his crew to clean up and

leave the area. As he was leaving, Konecny slipped on fireproofing overspray, falling

and injuring his back.

Konecny filed a workers’ compensation claim and received benefits totaling

$282,321.30. Konecny then initiated this suit. The jury found that comparative

responsibility for Konecny’s workplace injury belonged 20% to Konecny, 20% to

Hunt, 20% to Way Engineering, and 40% to Desert Plains. After reducing the jury

award by the amount of medical expenses paid through workers’ compensation

insurance in accordance with the prior agreement of the parties, the trial court awarded

Konecny $181,342.96 in damages, excluding interest and court costs.

Workers’ Compensation Coverage

In their first issue, appellants assert it was error for the trial court to deny their

motion for directed verdict and judgment notwithstanding the verdict. Appellants

contend that Konecny’s suit is barred by the Texas Workers’ Compensation Act

because the Sports Authority and Hunt provided workers’ compensation insurance to

all contractors, subcontractors, and employees working on the Toyota Center project

grounds.

A. Standard of Review

A motion for directed verdict or motion for judgment notwithstanding the

verdict preserves a legal-sufficiency challenge. See Cecil v. Smith , 804 S.W.2d 509 ,

510–11 (Tex. 1991). To preserve a complaint for review on appeal, a party must

present to the trial court a timely request, motion, or objection that states the specific

grounds for the ruling requested and conforms to the requirements of the Rules of

Procedure and Evidence. See Wal-Mart Stores, Inc. v. McKenzie , 997 S.W.2d 278,

280 (Tex. 1999); Tex. R. App. P . 33.1(a)(1)(A)-(B). The complaining party must also

show that the trial court ruled on the request, objection, or motion “either expressly

or implicitly.” Tex. R. App. P . 33.1(a)(2)(A).

“The final test for legal sufficiency must always be whether the evidence at trial

would enable reasonable and fair-minded people to reach the verdict under review.”

City of Keller v. Wilson , 168 S.W.3d 802, 827 (Tex. 2005). Legal-sufficiency review

in the proper light must credit favorable evidence if reasonable jurors could, and

disregard contrary evidence unless reasonable jurors could not. Id. If the evidence

would enable reasonable and fair-minded people to differ in their conclusions, then

jurors must be allowed to do so. Id. at 822 . A reviewing court cannot substitute its

judgment for that of the trier-of-fact, so long as the evidence falls within this zone of

reasonable disagreement. Id. Although the reviewing court must consider evidence

in the light most favorable to the verdict, and indulge every reasonable inference that

would support it, if the evidence allows only one inference, neither jurors nor the

reviewing court may disregard it. Id.

B. Texas Workers’ Compensation Act

A Texas employer has the option of participating in the workers’ compensation

system. Tex. Lab. Code Ann. § 406.002 (Vernon 2006) . If the employer chooses not

to participate, the employer may not assert common-law defenses against an employee

in a negligence suit. Id. § 406.033. If the employer does participate, the employer and

the employer’s employees are protected from an employee’s common-law claims for

injuries or death occurring during the course and scope of the employee’s work

responsibilities, except those claims involving the death of an employee caused by an

employer’s intentional or grossly negligent conduct. Id. § 408.001. “Recovery of

workers’ compensation benefits is the exclusive remedy of an employee covered by

workers’ compensation insurance coverage . . . for the death of or a work-related

injury sustained by the employee.” Id . § 408.001(a). Employees may have more than

one employer within the meaning of the Act, and each employer may raise the

exclusive remedy provision as a bar to the employee’s claims. See Wingfoot Enters.

v. Alvarado , 111 S.W.3d 134, 143 (Tex. 2003); Etie v. Walsh & Albert Co., Ltd. , 135

S.W.3d 764, 768 (Tex. App.—Houston [1st Dist.] 2004, pet. denied) .

For purposes of the Act, a general contractor is deemed the employer of a

subcontractor and the subcontractor’s employees if the general contractor provides,

in accordance with a written agreement, workers’ compensation insurance coverage

to the subcontractor and its employees. Tex. Lab. Code Ann. § 406.123(e) (Vernon

2006). A general contractor is “a person who undertakes to procure the performance

of work or a service, either separately or through the use of subcontractors.” Id. §

406.121(1). A subcontractor is a person who “contracts with a general contractor to

perform all or part of the work or services that the general contractor has undertaken

to perform.” Id. § 406.121(5). Since a general contractor is deemed the employer of

a subcontractor’s employees when the general contractor provides workers’

compensation insurance to them, id. § 406.123(e), the subcontractor’s employees who

do not opt out of the workers’ compensation coverage waive their right to sue the

general contractor for claims not covered by the Act. See id. § 408.001(a).

C. The Evidence

Konecny asserts that appellants presented no evidence at trial to show that they

are entitled to the protections of the Act. Specifically, Konecny claims that sections

referring to workers’ compensation in the contracts between the Sports Authority and

Hunt, Hunt and Way, Hunt and Desert Plains, and Way and Superior are not in

evidence. However, Sue Millican, comptroller of the Sports Authority, did testify to

the agreement between the Sports Authority and Hunt. Millican stated that the Sports

Authority obtained and paid premiums for the OCIP, which provided workers’

compensation coverage to “Hunt, all employees of Hunt, all subcontractors of Hunt,

and all subcontractors.” She also testified that “Hunt was responsible for

implementing the policy.”

Konecny is correct that the contract sections relating to workers’ compensation

coverage were not presented as evidence for the jury. However, both parties agreed

the issue of workers’ compensation coverage as an exclusive remedy would not be

presented to the jury because the matter of whether the Act barred the negligence suit

was a legal issue for the court.

Although the contracts were not before the jury, the relevant sections of the

contracts were presented to the court. Konecny attached unredacted copies of the

contracts between Hunt and Way, Hunt and Desert Plains, and Way and Superior to

its reply to appellants’ motion for summary judgment. In his reply to appellants’

motion for JNOV, Konecny relied on and referred to language in the contracts without

questioning the authenticity of the documents or whether the contracts were in

evidence for the court’s consideration. In rendering its decision on appellants’ motion

for JNOV, “[w]e presume the trial court took judicial notice of its files.” Holley v.

Holley , 864 S.W.2d 703, 706 (Tex. App.—Houston [1st Dist.] 1993, writ denied); see

also Attorney Gen. of Tex. v. Duncan , 929 S.W.2d 567, 571 (Tex. App.—Fort Worth

1996, no writ) (“[T]he trial court may take judicial notice of its file at any stage of

proceedings and is presumed to have done so with or without a request from a party.”) .

Because the contracts were presented as evidence for the trial court’s consideration,

and because we assume the trial court took judicial notice of its files, appellants did

present evidence supporting their motion for JNOV.

D. The Sports Authority

The parties do not dispute that Hunt was a general contractor for the Toyota

Center project. The parties dispute only whether the Sports Authority was also a

general contractor, in addition to being the owner of the project. However, we do not

reach the merits of that dispute concerning whether the Sports Authority was a general

contractor because that contention was never made to the trial court. On appeal,

appellants contend that the Sports Authority was both the owner and a general

contractor, citing Entergy Gulf States, Inc. v. Summers , in which the Texas Supreme

Court held that “the Labor Code’s definition of ‘general contractor’ does not prohibit

a premises owner who ‘undertakes to procure the performance of work or a service’

from also being a general contractor.” 50 Tex. Sup. Ct. J. 1140 , 2007 WL 2458027 ,

at *2 (Tex. Aug. 31, 2007) . Konecny correctly responds that appellants did not

present this argument to the trial court. In its motion for judgment notwithstanding the

verdict, appellants stated that “Hunt Construction provided workers’ compensation

insurance to Plaintiff’s employer—through the contracts and subcontracts with Way

Engineering and Superior Air Handling—that covered Plaintiff at the time of this

accident. Hunt Construction was therefore, for purposes of the Labor Code, Plaintiff’s

employer.” Appellants never asserted at trial that the Sports Authority was a general

contractor. We hold the argument that the Sports Authority was a general contractor

is waived on appeal because it was never made to the trial court. See Tex. R. App. P .

33.1(a)(1)(A)-(B) .

E. Hunt

Appellants contend that Hunt, acting as the general contractor, provided

workers’ compensation insurance to all subcontractors and employees on the site, so

all subcontractors and employees became employees of Hunt for purposes of the Act.

See Tex. Lab. Code Ann. § 406.123(e). Konecny replies that Hunt did not provide

coverage because the Sports Authority, not Hunt, obtained the policy and paid the

premiums. In asserting that the Sports Authority, not Hunt, provided workers’

compensation insurance for the Toyota Center project site, Konecny argues that we

should interpret “provide” to mean “purchase.” The parties dispute, therefore, is over

the meaning of the term “provides,” as that term is used in the Act.

“Our primary objective” in construing statutes “is to determine the Legislature’s

intent.” State v. Shumake , 199 S.W.3d 279, 284 (Tex. 2006). If the statute’s language

is not ambiguous, we must seek the Legislature’s intent in the plain meaning of the

words and terms used and not look to extraneous matters for an intent the statute does

not state. Nat’l Liab. & Fire Ins. Co. v. Allen , 15 S.W.3d 525, 527 (Tex. 2000).

Generally, we accept the ordinary meaning of words used unless the Legislature

provides a specific statutory definition. Cities of Austin, Dallas, Fort Worth &

Hereford v. Sw . Bell Tel. Co. , 92 S.W.3d 434, 442 (Tex. 2002). We read every word

in a statute as if it were deliberately chosen and presume that omitted words were

excluded purposely. Cameron v. Terrell & Garrett, Inc. , 618 S.W.2d 535, 540 (Tex.

1981). We begin with the plain language of section 406.123(a) before resorting to the

rules of construction because we assume the Legislature said what it meant. Segal v.

Emmes Capital, L.L.C. , 155 S.W.3d 267, 286 (Tex. App.—Houston [1st Dist.] 2004,

pet. dism’d). Only if we find that the Act’s plain language is susceptible of two or

more reasonable interpretations will we hold that section 406.123(a) is ambiguous.

See id.

The relevant section states, “A general contractor and a subcontractor may enter

into a written agreement under which the general contractor provides workers’

compensation insurance coverage to the subcontractor and the employees of the

subcontractor.” Tex. Lab. Code Ann . § 406.123(a). Considering each section and

word in connection with chapter 406, we conclude that the statute is unambiguous on

its face. Therefore, we must construe the statute in light of its plain meaning. The

ordinary meaning of the word “provide” is “to supply or make available.” See

Webster’s Ninth New Collegiate Dictionary 948 (1990); see Funes v. Eldridge

Elec. Co. , No. 04-08-00006-CV, 2008 WL 4426058, at *4 (Tex. App.—San Antonio

Oct. 1, 2008, no pet. h.).

Because we must give effect to every word in the statute, we conclude that the

Legislature used the word “provides” intentionally. Had the Legislature intended for

“provide” to mean “purchase,” it could simply have used the word “purchase” instead.

Alternatively, the Legislature could have defined “provide” to mean “purchase” in the

statute’s definition section. The Legislature chose neither of these options. We

presume that the Legislature deliberately chose “provide” instead of “purchase” in

writing the Act, choosing not to limit the deemed-employee relationship of section

406.123 to only those general contractors who purchase workers’ compensation

insurance. See Funes , 2008 WL 4426058, at *4 (“To hold to the contrary . . . the

general contractor would be required to procure a second compensation insurance

program in order to qualify under the statute as an ‘employer’ who ‘provides’

insurance, and thereby obtain the Act’s protection. . . . The resulting ‘double cover’

for, in effect, single protection is superfluous, and outside any reasonable intent of the

Legislature.”); see also Williams v. Razor Enters., Inc ., 70 S.W.3d 274 , 277 n.6 (Tex.

App.—San Antonio 2002, no pet.) ( “Courts have consistently enforced provisions

permitting an employer to benefit from workers’ compensation coverage even though

the coverage was paid for by a third entity.”); Williams v. Brown & Root, Inc ., 947

S.W.2d 673, 678 (Tex. App.—Texarkana 1997, no pet.) (“[T]he statute does not

require the general contractor to ‘pay’ for the insurance. It is incumbent upon the

general contractor only to ‘provide’ the insurance.”).

Konecny cites Rice in asserting that the contracts in this case merely required

subcontractors to purchase workers’ compensation coverage but did not provide that

coverage. See Rice v. HCBeck, Ltd. , No. 02-05-00239-CV, 2006 WL 908761, at *4

(Tex. App.—Fort Worth Apr. 6, 2006, pet. granted) (mem. op.). In Rice , an owner

created an OCIP, an employee was injured on the site, and after recovering workers’

compensation benefits under the OCIP, the employee sued the general contractor for

negligence. Id. at *1–2. The contract between the owner and the general contractor

in Rice only required subcontractors to apply for enrollment in the OCIP. See id. at

*4.

The Rice decision is distinguishable because the insurance coverage here was

provided by Hunt through the OCIP. See id . Here, the contract language makes clear

that eligible subcontractors are automatically covered by the OCIP. Since all

appellants were eligible subcontractors, they were automatically provided with

workers’ compensation coverage through the OCIP. Unlike in Rice , the general

contractor did not merely require participation in the OCIP but provided insurance

coverage through the OCIP. See id .

“[W]e construe subsection 406.123(a) to mean the following: where a general

contractor and a subcontractor enter into a written agreement under which the general

contractor supplies or makes available workers’ compensation insurance coverage to

the subcontractor and its employees, the general contractor is the employer of the

subcontractor and its employees for purposes of the Workers’ Compensation Act, as

provided under subsection 406.123(e).” Funes , 2008 WL 4426058, at *4 . Because

Hunt supplied or made available workers’ compensation insurance to Desert Plains,

Way, Superior, and all of their employees, Hunt did “provide” workers’ compensation

insurance . Hunt is therefore considered the employer of Desert Plains, Way, Superior,

and their employees for purposes of the Act.

F. The Subcontractors

Having determined the general contractor, Hunt, provided the OCIP workers’

compensation coverage, we must next determine how that coverage affected the

subcontractor. When a general contractor provides workers’ compensation insurance

that covers all workers on a site, the subcontractors are “deemed employees” and

immune from suit by injured workers. Etie , 135 S.W.3d at 768 . In Etie v. Walsh &

Albert Co., Ltd. , Clark Construction Group, Inc. entered into a contract with Enron

Corp. for the construction of Enron building 2. Clark subcontracted part of the work

to Way Engineering Company, Inc., who subcontracted part of its work to Walsh &

Albert, Ltd. Clark purchased a workers’ compensation policy covering all

subcontractors and employees working on the Enron building 2 site. Etie, an

employee of Way, was injured on the site by the negligence of a Walsh & Albert

employee. Etie sought and recovered workers’ compensation benefits then sued

Walsh & Albert for negligence. Walsh & Albert moved for, and the trial court

granted, summary judgment. On appeal, we affirmed the trial court’s decision,

holding that Walsh & Albert was immune from suit as a “deemed employee.” We

explained:

Clark Construction provided workers’ compensation coverage to

all of the employees who worked at the site as part of its contract with

Way Engineering. Way Engineering’s contract with Walsh & Albert

incorporated by reference all of the provisions of the contract between

Clark Construction and Way Engineering. Consequently, Walsh &

Albert and its employees were also covered by the workers’

compensation insurance policy that Clark Construction purchased.

Therefore, as a general contractor who provided workers’ compensation

coverage, Way Engineering became Walsh & Albert’s “employer” for

purposes of the workers’ compensation statute. Walsh & Albert, and its

employees, became Way Engineering’s “employees.”

Id. at 767 (internal citations omitted).

As we stated in Etie , the purposes of the Act are best served by deeming

immune from suit all subcontractors and lower-tier subcontractors who are collectively

covered by workers’ compensation insurance. Id. at 768 . The Texas legislature’s

purpose in passing the Act was to ensure injured workers could obtain reimbursement

for medical expenses related to workplace injuries without the time, money, and

difficulty of a negligence lawsuit. See Lawrence v. CDB Servs., Inc. , 44 S.W.3d 544,

555 (Tex. 2001) (Baker, J., dissenting). Another purpose of the Act is to encourage

employers to participate in workers’ compensation by precluding nonsubscribing

employers from relying on common-law defenses to negligence in defending against

their employees’ personal-injury actions. Kroger Co. v. Keng , 23 S.W.3d 347, 350

(Tex. 2000).

Under the terms of the OCIP, coverage applied to contractors as well as

subcontractors who provided direct labor, as each of appellants did here. Although

the OCIP deemed some contractors to be ineligible for coverage under the OCIP, none

of those categories applied to appellants.

We conclude that appellants are deemed employees for purposes of the Act. See

Tex. Lab. Code Ann. § 406.123(e). We hold that Konecny’s sole remedy was

workers’ compensation coverage. We sustain the first issue in the appeal and do not

reach the second issue.

Conclusion

We reverse the judgment of the trial court and render judgment in favor of

appellants.

Elsa Alcala

Justice

Panel consists of Justices Taft, Keyes, and Alcala.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.