Opinion

Frank A. Putzu v. Department of the Navy

Court
Merit Systems Protection Board
Filed
Sep 2, 2015
Status
Unpublished
Cited by
0 cases
Authority
More cited than 35.1%

The opinion

UNITED STATES OF AMERICA

MERIT SYSTEMS PROTECTION BOARD

FRANK A. PUTZU, 1 DOCKET NUMBER

Appellant, DC-0752-13-5887-I-1

v.

DEPARTMENT OF THE NAVY, DATE: September 2, 2015

Agency.

THIS FINAL ORDER IS NONPRECEDENTIAL 2

Frank A. Putzu, Alexandria, Virginia, pro se.

Linda L. Tiller, John D. Norquist and Jeffrey A. Epstein, Esquire,

Washington, D.C., for the agency.

BEFORE

Susan Tsui Grundmann, Chairman

Mark A. Robbins, Member

FINAL ORDER

¶1 The appellant has filed a petition for review of the initial decision, which

affirmed the agency’s furlough action. Generally, we grant petitions such as this

one only when: the initial decision contains erroneous findings of material fact;

1

Pursuant to 5 C.F.R. § 1201.36(a), this appeal was part of a consolidation, NAVSEA v.

Department of the Navy, MSPB Docket No. DC-0752-14-0646-I-1.

2

A nonprecedential order is one that the Board has determined does not add

significantly to the body of MSPB case law. Parties may cite nonprecedential orders,

but such orders have no precedential value; the Board and administrative judges are not

required to follow or distinguish them in any future decisions. In contrast, a

precedential decision issued as an Opinion and Order has been identified by the Board

as significantly contributing to the Board’s case law. See 5 C.F.R. § 1201.117(c).

2

the initial decision is based on an erroneous interpretation of statute or regulation

or the erroneous application of the law to the facts of the case; the judge’s rulings

during either the course of the appeal or the initial decision were not consistent

with required procedures or involved an abuse of discretion, and the resulting

error affected the outcome of the case; or new and material evidence or legal

argument is available that, despite the petitioner’s due diligence, was not

available when the record closed. See Title 5 of the Code of Federal Regulations,

section 1201.115 (5 C.F.R. § 1201.115). After fully considering the filings in this

appeal, and based on the following points and authorities, we conclude that the

petitioner has not established any basis under section 1201.115 for granting the

petition for review. Therefore, we DENY the petition for review. Except as

expressly MODIFIED by this Final Order, which provides additional support for

the administrative judge’s finding that the appellant did not qualify for an

exception to the furlough, and clarifies that the burden is on the agency to prove

“cause” for the action, we AFFIRM the initial decision.

¶2 After a hearing, the administrative judge held that the agency proved that it

had to make significant spending cuts because of sequestration 3 and that the

furlough helped the agency avoid a deficit. NAVSEA v. Department of the Navy,

MSPB Docket No. DC-0752-14-0646-I-1, Consolidation Appeal File (CAF),

Tab 19, Initial Decision (ID) at 15-16. The administrative judge also found that

the furlough was a reasonable management solution to the financial issues facing

the agency and promoted the efficiency of the service. ID at 16. In this regard,

the administrative judge rejected the arguments that the agency could have taken

other measures to avoid the furlough, the budget cuts did not affect the ability of

the Department of the Navy (Navy) to protect national security, and funds could

not be reprogrammed, finding that these arguments were based on spending

3

The term “sequestration” refers to the cancellation of budgetary resources provided by

discretionary appropriations or direct spending law. See Salo v. Department of Defense,

122 M.S.P.R. 417, ¶ 2 (2015).

3

matters within the agency’s sound discretion. Id. The administrative judge also

held that the agency imposed the furloughs uniformly. Id.

¶3 The administrative judge held that, although the appellant asserted that he

should have been exempt from the furlough under an exemption for “Shipyard

Workers, Nuclear and Naval Reactors Staff,” see CAF, Tab 2; see also

Department of the Navy Administrative Record for FY 2013 Furlough Appeals,

Tab 12 at 105, 108-09, available at http://www.mspb.gov/furloughappeals/navy

2013.htm, because he serves as Counsel for the Office of Naval Reactors and was

therefore a member of the Naval Reactors staff, the appellant was actually an

employee of the Naval Sea Systems Command’s (NAVSEA’s) Office of General

Counsel (OGC), not the Office of Naval Reactors, which was one of his clients,

ID at 18-19. The administrative judge further concluded that the appellants did

not prove harmful error or a violation of their due process rights. ID at 19-20.

¶4 The appellant contends on review that the agency initially identified his

position as having met the criteria for an exception to the furlough, testimony and

his position description show that he qualified for the exception as “Naval

Reactors Staff,” the term “staff” does not only mean “employee,” and there is

nothing improper or unusual for a Navy employee to be on the staff of different

Navy organizations. Petition for Review (PFR) File, Tab 1 at 7, 10-11, 17. The

appellant asserts that “he is an employee of the Department of the Navy, a

member of OGC, paid from funds apportioned to NAVSEA (the same as Navy

employees assigned to NAVSEA 08), and works on the staff of Naval Reactors.”

Id. at 17. The agency asserts that the evidence shows that the appellant was not

an employee of the Office of Naval Reactors. PFR File, Tab 3 at 8.

¶5 An agency may furlough an employee for 30 days or less “only for such

cause as will promote the efficiency of the service.” 5 U.S.C. §§ 7512(5),

7513(a). The concept of “cause” in the context of a furlough appeal encompasses

whether the appellant met the criteria established by the agency for being subject

to, and not excepted from, the furlough. Dye v. Department of the

4

Army, 121 M.S.P.R. 142, ¶ 9 (2014). The agency has the burden of proof on this

issue. Id., ¶¶ 9-10; see In re Tinker AFSC/DP v. Department of the Air

Force, 121 M.S.P.R. 385, ¶¶ 14-15 (2014). Here, the administrative judge

correctly found that the agency met its burden of proof by preponderant

evidence. 4

¶6 In a May 14, 2013 memorandum, the Secretary of Defense set forth a list of

Department of Defense (DOD) Furlough Exceptions that included, for the Navy,

1,657 individuals identified only as “Shipyard Workers, Nuclear and Naval

Reactors Staff.” Department of the Navy Administrative Record for FY 2013

Furlough Appeals, Tab 12 at 105, 108-09.

¶7 The appellant’s position description indicates that his position of “Counsel,

Naval Reactors,” exists within the Navy’s OGC (first subdivision), Counsel,

NAVSEA (second subdivision), Office of Counsel (third subdivision). Initial

Appeal File (IAF), Tab 2 at 12. The position description further notes that the

position is “within the Office of Counsel, Naval Sea Systems Command,” and that

the NAVSEA Office of Counsel is responsible for providing legal advice,

services and representation, and giving necessary legal approvals, opinions, and

interpretations to NAVSEA and its field activities, affiliated Program Executive

Officers, Direct Reporting Program Managers, and the Director, Naval Reactors.

Id. at 13. In addition, the position description provides that the appellant’s

position “is a Section Head within the NAVSEA Office of Counsel, and the

primary legal subject matter expert and a senior advisor to the Director, Naval

Reactors.” Id. at 14. The appellant testified that his performance appraisals, at

least in part, as well as any disciplinary actions that would be taken against him,

were to be acted upon by individuals within OGC, not Naval Reactors. Hearing

Transcript (HT) at 111-13. He also testified that he considered Naval Reactors to

4

Preponderant evidence is the degree of relevant evidence that a reasonable person,

considering the record as a whole, would accept as sufficient to find that a contested

fact is more likely to be true than untrue. 5 C.F.R. § 1201.56(c)(2).

5

be his client in his capacity as an attorney. HT at 113-14. The fact that the

appellant’s position officially exists within OGC, not within Naval Reactors, and

provides legal advice, services, and representation to Naval Reactors, as well as

the involvement of OGC in matters affecting the appellant’s employment, all

support the administrative judge’s determination that the appellant’s position falls

within the staff of OGC, rather than “Naval Reactors Staff.”

¶8 In addition, the deciding official, who was the Executive Director of

NAVSEA, testified in a separate Board appeal that he interpreted the phrase

“Naval Reactors Staff” in the May 14, 2013 Secretary of Defense memorandum as

referring to the “C08 Headquarters department, of which I was not the deciding

official for those employees,” which referred to Naval Reactors. IAF, Tab 10

at 9, 12-13 (transcript pages 7-8, 21-22). He testified in the instant appeal that an

employee is either “bureaucratically coded” in Naval Reactors or not so coded.

HT at 53. He also testified that the appellant’s position was “a NAVSEA position

with counsel being assigned by NAVSEA to” Naval Reactors, and that the

appellant’s position was an “OOL code,” while employees in Naval Reactors had

an “08 code.” HT at 62-63. OOL is NAVSEA’s legal department, which is not a

part of 08, which in turn refers to Naval Nuclear Propulsion. HT at 78-79. The

deciding official testified that, because the appellant was not a NAVSEA 08

employee, the Deputy Director, Naval Reactors, did not have the authority to

advocate for an exemption for the appellant from the furlough. HT at 188-90.

¶9 The Deputy Director, Naval Reactors, testified that, when Naval Reactors

had initially recommended that the appellant be excepted from the furlough, it

was arguing for NAVSEA “on their behalf,” and that he believed he had the

authority to take that position on behalf of NAVSEA. IAF, Tab 15 at 13

(transcript page 31). He also indicated, however, that there was no guidance

provided to him specifically indicating that he could seek a waiver or attempt to

seek a waiver for the appellant. Id. at 28 (transcript page 91).

6

¶10 Further, in a June 19, 2013 email from NAVSEA to the Deputy Director,

Naval Reactors, in response to his request for an opinion regarding the term

“Naval Reactors Staff,” NAVSEA indicated that the term referred to the

106 positions at headquarters that were identified in an attached exemption

request for Naval Reactor employees. IAF, Tab 15 at 50. The email provides:

The Furlough exemption request was submitted by NR [Naval

Reactors] on 6 March 2013 and endorsed by the VCNO [Vice Chief,

Naval Operations] on 21 March. The request was for 1,657 NR

employees; 1,551 at the four shipyards, and 106 at NR headquarters.

The request regarding the HQ employees consisted of 103 Nuclear

Engineers, 1 Logistics Management Specialist, 1 Health Physicist,

and 1 Operations Manager. On 14 May 2013, SECDEF issued a

memorandum directing DoD activities to prepare for furlough. The

memorandum contains an attachment specifying the final

dispositions on furlough exemptions. The only language in the

attachment relative to this issue is the exemption of 1,657 “Shipyard

Workers, Nuclear and Naval Reactors Staff.” Presumably these are

the same 1,657 employees listed in the Navy’s March furlough

exemption request. Shipyard Workers refers to the 1,551 NR

Shipyard employees; Naval Reactors Staff refers to the 106

exempted employees at NR HQ.

I conferred with . . . [the] Assistant General Counsel for M&RA

[Manpower & Reserve Affairs]. He concurs that Naval Reactor Staff

refers to the 106 employees identified in the exemption request.

Id. All of this evidence further supports the administrative judge’s finding that

the appellant did not fall within the exception for “Naval Reactors Staff.”

¶11 Even assuming, however, that the Counsel, Naval Reactors position was a

part of “Naval Reactors Staff” for purposes of the furlough exception, the record

reflects that Naval Reactors determined, before the issuance of the Secretary of

Defense’s May 14, 2013 memorandum and the start of the furloughs, that the

appellant’s position would not be included among the 106 exceptions from Naval

Reactors headquarters. As suggested by the email quoted above, before the

issuance of the May 14, 2013 memorandum from the Secretary of Defense setting

forth the exceptions from the furlough, Naval Reactors requested on March 21,

2013, from the Office of the Secretary of Defense and had approved by DOD only

7

106 exceptions from the furlough for Naval Reactors Headquarters employees,

including 102 Nuclear Engineers, 1 Information Technology Specialist, 1 Health

Physicist, 1 Logistics Management Specialist, and 1 Operations Manager; this did

not include the position of Counsel, Naval Reactors, which was eliminated from

the request because the position was not critical to responding to a nuclear

emergency. CAF, Tab 8 at 20-31, 40-46. The Deputy Director, Naval Reactors,

testified in a deposition that, after Naval Reactors made a recommendation for

exemptions from the furlough that included the appellant, “we got some feedback

from someone in leadership that came back and requested that the number be

reduced [from 121] again [to] those folks only responsible for life and safety

requirements and work on a recallable basis.” IAF, Tab 15 at 13, 17 (transcript

pages 31, 46-47). He testified that the “waiver exception folks never worked to

our criteria,” but instead “had their own set of criteria which was very specific to

life and safety issues,” and that “I don’t think anyone within the secretariat ever

agreed with our three criteria as being something on which to base the waiver.”

Id. at 17 (transcript pages 47, 49). He further testified that he, along with several

other individuals, edited the list of 121 employees down to 106, eliminating the

appellant’s position based on guidance received indicating that Naval Reactors

should assume it could recall individuals from the furlough if necessary and

except from the furlough only those positions involved in “immediate health or

life and safety,” which did not include the appellant’s position. Id. at 27

(transcript pages 87-88). He further testified that no one specifically told him to

take the appellant off the list of exempt employees, but by position, “it didn’t fit

in the last set of criteria we had handed to us.” Id. at 29 (transcript page 97).

¶12 Based on the initial decision and the analysis set forth above, we find that

the administrative judge correctly determined that the agency proved by

preponderant evidence that the appellant was subject to, and not excepted from,

the furlough. See Dye, 121 M.S.P.R. 142, ¶ 9.

8

¶13 The appellant also asserts that the administrative judge improperly denied

his motion to compel the production of evidence, including his request to take the

depositions of the Vice Chief, Naval Operations, and the Assistant Secretary of

the Navy for Manpower and Reserve Affairs, that he claims would have shown

why the agency determined that he did not meet the “Naval Reactors Staff”

exception, and improperly prohibited him from submitting evidence from the

DOD official who handled that exception, as well as evidence showing that a

March 21, 2013 memorandum setting forth the exception criteria represented “the

binding position of the agency.” PFR File, Tab 1 at 11-14.

¶14 An administrative judge has wide discretion to exclude evidence and

witnesses when it has not been shown that such evidence and testimony would be

relevant, material, and nonrepetitious. Fox v. Department of the

Army, 120 M.S.P.R. 529, ¶ 42 (2014); see 5 C.F.R. § 1201.41(b)(10). The Board

will not reverse an administrative judge’s rulings on discovery matters, including

a motion to compel, absent an abuse of discretion. Fox, 120 M.S.P.R. 529, ¶ 42.

In an order denying the appellant’s motion to compel discovery, the

administrative judge found that “whether the appellant should have been included

on a list of excepted Naval Reactors employees is not relevant to this proceeding

because the appellant was not a Naval Reactors employee.” IAF, Tab 13 at 2. As

set forth above, the appellant has shown no error in that determination. Thus, the

appellant has shown no abuse of discretion in the denial of discovery.

¶15 The appellant contends that the deciding official failed to consider

documentation he attached to his reply to the proposal notice suggesting that he

met the exception to the furlough for “Naval Reactors Staff,” and that the

administrative judge improperly placed the burden of proving that there was

“cause” for the action on him, rather than on the agency. PFR File, Tab 1

at 19-23. Given our finding that the appellant did not constitute “Naval Reactors

Staff,” the deciding official correctly concluded that the documentation in

question was not relevant to his determination to furlough the appellant. See HT

9

at 42-43 (testimony of the deciding official that, when he received a written reply

that cited documents, “if I thought they were relevant, I would have probably

asked for them, but where it was very clear or there wasn’t a case to be made –

really, what I was looking for in the replies was if it fit into one of the categorical

exceptions. That is really the latitude I had as the deciding official.” “If it was

relevant to that, I would have asked for it. If it wasn’t, I was going to make a

final decision and move on.”). Moreover, the administrative judge did not

improperly place the burden of proving “cause” on the appellant. Although the

administrative judge’s analysis of this issue does fall under a subheading that

references affirmative defenses and includes a discussion of the appellants’

harmful error and due process claims, the administrative judge cited and applied

the correct standard in this case, i.e., that the agency bears the burden of proving

the factual basis for the furlough and that the furlough promoted the efficiency of

the service. ID at 14-17, 18-19, 21. In any event, to the extent that the initial

decision may be unclear on this issue, we find, as set forth above, that the agency

has met its burden of proof in this regard.

¶16 Finally, the appellant asserts that the agency provided on appeal to the

Board documentation in support of its action, such as a document entitled

“Department of the Navy Administrative Furlough Guidance for Proposing and

Deciding Officials,” that it did not make available to him when it proposed his

furlough. PFR File, Tab 1 at 4 n.1, 25-27. An agency’s proposal notice must

state the specific reasons for the proposed action and inform the employee of his

or her right to review the material relied on to support the reasons for the action

given in the notice. 5 C.F.R. § 752.404(b)(1). Here, the agency’s proposal notice

informed the appellant that supporting material for the action could be found at a

specified agency website. IAF, Tab 5 at 19. The appellant has not alleged that

the deciding official relied upon the above document in taking the furlough

action. Even assuming, however, that the appellant established a procedural error

by the agency in this regard, he has not shown that any error likely caused the

10

agency to reach a conclusion different from the one it would have reached in the

absence or cure of the error. See 5 C.F.R. § 1201.56(c)(3).

NOTICE TO THE APPELLANT REGARDING

YOUR FURTHER REVIEW RIGHTS

The initial decision, as supplemented by this Final Order, constitutes the

Board’s final decision in this matter. 5 C.F.R. § 1201.113. You have the right to

request the United States Court of Appeals for the Federal Circuit to review this

final decision. You must submit your request to the court at the following

address:

United States Court of Appeals

for the Federal Circuit

717 Madison Place, N.W.

Washington, DC 20439

The court must receive your request for review no later than 60 calendar

days after the date of this order. See 5 U.S.C. § 7703(b)(1)(A) (as rev. eff.

Dec. 27, 2012). If you choose to file, be very careful to file on time. The court

has held that normally it does not have the authority to waive this statutory

deadline and that filings that do not comply with the deadline must be dismissed.

See Pinat v. Office of Personnel Management, 931 F.2d 1544 (Fed. Cir. 1991).

If you need further information about your right to appeal this decision to

court, you should refer to the Federal law that gives you this right. It is found in

Title 5 of the United States Code, section 7703 (5 U.S.C. § 7703) (as rev. eff.

Dec. 27, 2012). You may read this law as well as other sections of the United

States Code, at our website, http://www.mspb.gov/appeals/uscode.htm.

Additional information is available at the court’s

website, www.cafc.uscourts.gov. Of particular relevance is the court’s “Guide

for Pro Se Petitioners and Appellants,” which is contained within the

court’s Rules of Practice, and Forms 5, 6, and 11.

11

If you are interested in securing pro bono representation for an appeal to the

United States Court of Appeals for the Federal Circuit, you may visit our website

at http://www.mspb.gov/probono for information regarding pro bono

representation for Merit Systems Protection Board appellants before the Federal

Circuit. The Merit Systems Protection Board neither endorses the services

provided by any attorney nor warrants that any attorney will accept representation

in a given case.

FOR THE BOARD: ______________________________

William D. Spencer

Clerk of the Board

Washington, D.C.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.