Opinion

Highland Al Hujaz Co., Ltd.

Court
Armed Services Board of Contract Appeals
Filed
Jul 13, 2015
Status
Published
On the bench
Thrasher
Cited by
0 cases

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- )

)

Highland Al Hujaz Co., Ltd. ) ASBCA Nos. 59746, 59818

)

Under Contract No. W917PM-09-C-0049 )

APPEARANCES FOR THE APPELLANT: Herman M. Braude, Esq.

Edward D. Manchester, Esq.

Braude Law Group, P.C.

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney

Daniel B. McConnell, Esq.

Assistant Counsel

U.S. Army Engineer District, Middle East

Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE THRASHER

ON APPELLANT'S MOTION FOR AN ORDER DIRECTING THE

GOVERNMENT TO FILE THE COMPLAINT

This matter comes before the Board on appellant's motion for an order requiring

the government to file the complaint in this appeal. The government opposes the motion.

For the reasons that follow we grant the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The government awarded Contract No. W9 l 7PM-09-C-0049 (contract)

to Highland Al Hujaz Co., Ltd. (HLH), on 3 June 2009, for design and construction of

the Afghanistan National Army Corps Support Battalion, Camp Hero, Kandahar,

Afghanistan (R4, tab 11 ). • The government terminated the contract for default on

23 April 2012 (R4, tab 2). On 18 August 2012, the government issued an invitation

for bids to reprocure the uncompleted portion of the contract and to correct defects in the

work completed (R4, tab 903). Five bids were received and the government awarded

the reprocurement contract on 24 September 2012 (ASBCA No. 58243, R4, tab 841).

• The Rule 4 file in ASBCA Nos. 59746 and 59818 is consolidated with the Rule 4

file in ASBCA No. 58243, the appeal on the associated default termination

action giving rise to the demand for excess reprocurement costs.

The work under the reprocurement contract was completed and accepted by the

government on 31January2014 (R4, tab 904).

2. On 21 May 2014 the government issued HLH a demand letter to collect the

excess reprocurement costs in completing the work which was deficient and/or left

unfinished as of the date of termination for default of the contract. The demand letter

asserted the government's right to assess excess reprocurement costs, that the

reprocurement contract was competitively awarded, identified the reprocurement

contractor and described how the asserted amount of excess reprocurement costs were

calculated. (R4, tab 889) HLH responded on 23 May 2014 rejecting the government's

right to excess reprocurement costs (R4, tab 901 ). In addition to the issue of the

propriety of the underlying default termination being litigated in ASBCA No. 58243,

HLH's response asserted a number of reasons why the government's demand for

excess reprocurement costs was erroneous or questionable. Further, the letter asked

the government to confirm the demand letter was not a contracting officer's final

decision (COFD) (R4, tab 901).

3. Two years earlier, on 18 June 2012, the government issued HLH a demand

letter for reimbursement of $903,553.79 in overpayments to HLH during performance

of the contract (R4, tab 98). HLH responded disagreeing with the government's

assessment and requested further information (R4, tab 900). There is no record of a

request for a COFD, issuance of a COFD or an appeal to the Board on this issue.

4. The government issued HLH a second demand letter on 30 May 2014 that

mirrored the 21May2014 demand letter but also addressed each issue raised by HLH

in its response. However, the second demand letter did not address whether it was a

COFD. (R4, tab 893) Again on 4 June 2014, HLH rejected the government's

demands and repeated its arguments for the rejection of the assessment of excess costs

(R4, tab 902). On 20 June 2014 HLH requested issuance of a COFD on the

government's claim for excess reprocurement costs (R4, tab 921 at 2). Having not

received a COFD by 21 October 2014, HLH asked the government to confirm when it

would issue a COFD (R4, tab 922). No response or COFD was forthcoming so HLH

filed a notice of appeal with the Board on 15 December 2014 which was docketed as

ASBCA No. 59746. On 22 January 2015, the government issued a COFD repeating

its demand for excess reprocurement costs. The COFD referenced the overpayment

issue asserted on 18 June 2012 in a recitation of facts but did not appear to include the

amount of overpayment within the excess reprocurement calculations or otherwise

address entitlement to any amount for the overpayment issue in its decision. HLH

appealed the COFD to the Board on 5 February 2015 which was docketed as ASBCA

No. 59818. HLH' s notice of appeal only referenced excess reprocurement costs; there

was no reference to the overpayment demand.

2

5. On 20 February 2015, HLH filed a motion to extend time for filing the

complaint until 30 days after the government files the Rule 4 file. The motion was not

opposed by the government and was granted by the Board on 11 March 2015. The

Board received its copy of the Rule 4 file on 15 April 2015. On 23 April 2015, HLH

filed a motion for order directing the government to file the complaint in this appeal.

The government responded on 19 May 2015 opposing the motion asserting that both

the excess reprocurement cost and overpayment issues were before the Board in the

appeals, and HLH replied to the government's response on 2 June 2015.

DECISION

Under the unique procedural requirements of the Contract Disputes Act (CDA),

all claims, whether contractor or government claims, must be the subject of a COFD.

41 U.S.C. § 7103. The contractor, however, is the only party who may initiate

proceedings at the Board, 41 U.S.C. § 7104, and Board Rule 6(a) requires appellant to

file the complaint in an appeal. If the contractor appeals from a final decision on a

government claim, the contractor typically files a complaint with enough information

about the government claim to form a sufficient predicate for the government's answer

and allow for adequate framing of the issues. Therefore, the fact the appeal involves a

government claim alone, is not enough to compel the government to file the complaint.

Nonetheless, we have recognized that there may be situations when the

proceedings would be facilitated by the government filing the complaint or initial

pleading. E.g., Kellogg Brown & Root Services, Inc., ASBCA No. 59557, 15-1 BCA

ii 35,865; Beechcraft Defense Co., ASBCA No. 59173, 14-1BCAii35,592; RO. Vl.B.

Sri, ASBCA No. 56198, 09-1BCAii34,068. Ifwe determine that the proceeding

would not be facilitated, we do not order the government to file the initial pleading.

See, e.g., General Dynamics Corp., ASBCA No. 49339, 96-1BCAii28,244

(contractor in possession of information upon which government claim is based).

While ordinarily we might look with disfavor on the instant motion when

appellant has acknowledged its responsibility to file the complaint and requested an

extension to do so (SOF ii 5), the fact that it is unclear whether the appeals concern

excess reprocurement costs alone, or these costs plus an overpayment claim by the

government, present a unique situation. As near as we can determine on the present

record, the only issue before us is the government's affirmative claim for excess

reprocurement costs. However, a substantial portion of the government's 19 May

2015 response addresses a government demand for collection of overpayments during

performance of the contract. The government did assert a demand for overpayments

during performance (SOF ii 3) but there is no record of a COFD or an appeal to the

Board on this issue. Nonetheless, the government's response to the motion states

"Appellant does not address the Government's demand for overpayment in its

Motion. However, both the Government's demands for overpayment and assessed

3

reprocurement costs rely upon the same facts and therefore, both demands are

addressed herein." (Gov't resp. at 1) This statement is then followed by a page and a

half of discussion of the facts related to the overpayment (id. at 2-3). Then later in

summary, the government argues:

The information to accurately and fairly determine

the extent of both overpayments and excess reprocurement

costs caused by Appellant's non-conforming and

unfinished work resides with both the Government and

the Appellant, as both ultimately had equal access to the

information, albeit at different points in time. Therefore,

the proceedings would be not be facilitated by the

Government filing the initial pleading, and would be

better facilitated by Appellant setting forth the facts and

rationale as to its duty to perform as well as Appellant's

completion of the work under the original contract and

how it differs from the scope of work in the

reprocurement contract.

(Id. at 4)

These arguments seem to evidence a government belief that the overpayment

demand is included within the COFD, and is before the Board for decision, or that the

demand is somehow part of the excess reprocurement claim. The COFD does mention

the overpayment demand but the CO's calculations used to arrive at the excess

reprocurement costs do not appear to include the overpayment amounts demanded and

the CO does not address the overpayment issue in her decision (SOF ii 4 ). Likewise,

the overpayment demand has not been appealed to the Board; the only issue before us

in this appeal is the claim for excess reprocurement costs (id.). Consequently, it is

unclear how the overpayment issue relates to the government's theory of their case on

the excess reprocurement costs.

Given these circumstances, we conclude that the proceedings would be

facilitated by the government setting forth in an initial pleading, the facts and rationale

for its claim for excess reprocurement costs, and if claimed, overpayments.

4

CONCLUSION

The Board grants appellant's motion to direct the government to file the

complaint 30 days from the date of this opinion. Appellant's answer shall be due

30 days following receipt of the government's complaint.

Dated: 13 July 2015

of Contract Appeals

I concur

,//;-;? U-

~:~~Et«r~

Administrative Judge

RICHARD SHACKLEFORD

Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 59746, 59818, Appeals of

Highland Al Hujaz Co., Ltd., rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN

Recorder, Armed Services

Board of Contract Appeals

5

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.