Opinion

Framaco International, Inc. v. United States

  • 119 Fed. Cl. 311
  • 2014 WL 7800839
Court
United States Court of Federal Claims
Filed
Feb 11, 2015
Status
Published
Author
Horn
On the bench
Marian Blank Horn
Cited by
4 cases
Authority
More cited than 48.8%

understanding “at least” to indicate a minimum threshold

How later courts described this case

  • understanding “at least” to indicate a minimum threshold

Written by the judges who cited it.

The opinion

REDACTED OPINION

In the United States Court of Federal Claims

No. 14-713C

Filed: December 5, 2014

Redacted Version Issued for Publication: February 11, 20151

* * * * * * * * * * * * * *

FRAMACO INTERNATIONAL, INC., *

* Bid Protest; Omnibus Diplomatic

Protestor, * Security and Antiterrorism Act of

* 1986; Past Project Adjustment for

v. * Inflation.

*

UNITED STATES, *

*

Defendant, *

*

v. *

*

CADDELL CONSTRUCTION *

COMPANY,

*

Defendant-Intervenor. *

* * * * * * * * * * * * * *

Jonathan D. Shaffer, Smith Pachter McWhorter PLC, Tysons Corner, Virginia,

for protestor. With him were Mark E. Hanson, Mary Pat Buckenmeyer, Daniel R.

Rounds, Smith Pachter McWhorter PLC, Tysons Corner, Virginia.

Veronica N. Onyema, Trial Attorney, Commercial Litigation Branch, Civil

Division, United States Department of Justice, Washington, D.C., for defendant. With

her were Joyce R. Branda, Acting Assistant Attorney General, Civil Division, Robert E.

Kirschman, Jr., Director, Commercial Litigation. Of counsel, John W. Cox, Office of

the Legal Adviser, United States Department of State.

Dirk Haire, Fox Rothschild LLP, Washington D.C., for intervenor. With him were

Alexa Santora and Benjamin Kussman, Fox Rothschild LLP, Washington D.C.

1

This opinion was issued under seal on December 5, 2014. The parties were asked to

propose redactions prior to public release of the opinion. This opinion is issued with the

redactions that the parties proposed in response to the court’s request. Words which

are redacted are reflected with the following notation: “[redacted].”

OPINION

HORN, J.

Protestor, Framaco International, Inc., (Framaco) filed the above captioned bid

protest in this court against the United States, acting through the United States

Department of State (DOS), Bureau of Overseas Buildings Operations (OBO) Office of

Acquisitions, Acquisition Management. Protestor is “a construction management and

procurement firm providing turnkey overseas services to the U.S. government and

global construction companies.” Protestor challenges OBO’s decision not to prequalify

Framaco to compete under the Request for Proposals (RFP) in Solicitation No.

SAQMMA-14-R0115 to design and construct a new embassy compound (NEC) in

Harare, Zimbabwe (Harare, Zimbabwe project).

Protestor claims in its bid protest complaint that the “Harare, Zimbabwe

procurement is being conducted in two phases – the first for prequalification and the

second under which prequalified offerors are allowed to submit proposals in response to

the solicitation and to participate in site visits.” Protestor notes that “[i]n order to

prequalify, offerors needed to submit documentation to allow OBO to evaluate its

capabilities” and that “[d]uring Phase I, the agency declared Framaco ineligible to

compete in Phase II.” Framaco indicates, at the time the protest was filed, the agency

had not yet issued the RFPs under Phase II. Therefore, Framaco “seeks to participate

as a prequalified offeror in this procurement for construction of the NEC in Harare,

Zimbabwe.” Specifically, Framaco seeks a declaratory judgment that defendant violated

federal procurement law and regulation, as well as the terms of the Solicitation by failing

to prequalify Framaco for the Harare, Zimbabwe project. Protestor also seeks injunctive

relief directing defendant to reinstate or otherwise prequalify Framaco to compete under

the RFP for the Harare, Zimbabwe project.

FINDINGS OF FACT

On March 10, 2014, OBO issued a “Notice of Solicitation of Submissions for

Contractor Pre-Qualification” (the Notice of Solicitation) (emphasis in original) for a

design-build contract for the United States Embassy in Harare, Zimbabwe, RFP

SAQMMA-14-R0115. The Notice of Solicitation described the project as one for “the

design and construction of a New Embassy Compound to house U.S. Diplomatic

functions.” The Notice of Solicitation stated:

The New Embassy Compound) [sic] will be constructed on a US

Government owned site located on 16.5 acres of land adjacent to the

West Gate Shopping Center near Lorraine Drive in Harare, Zimbabwe.

Anticipated work and approximate sizes includes: New Chancery (NOB),

12,668 gross square meters (gsm); Maintenance Facilities and high-bay

Warehouse, 3185 gsm; Marine Security Guard Quarters, 1015 gsm;

Recreational Facilities,261 [sic] gsm; Vehicle and Pedestrian Access

Control Facilities, 528 gsm; ; [sic] Utility Building, 1015 gsm: Other Site

2

Work including Perimeter Security, Surface Vehicle Parking, Roadways,

Landscaped and Planted Areas. The site is rectangular with roads on

three sides and is approximately 16.5 acres. This project will be required

to achieve LEED® Silver certification, as a minimum.

The Notice of Solicitation set forth an approximate design-build cost of $165 to $210

million. The Notice of Solicitation also indicated that the Solicitation was to “consist of

two phases,” the first phase for prequalification and the second phase during which the

RFP would be released to the prequalified offerors, who then would be invited to submit

proposals in response and participate in site visits. The Notice of Solicitation provided:

Phase I – Pre-Qualification of Offerors

This announcement of solicitation of pre-qualification submissions is

Phase I. DOS will evaluate the pre-qualification submissions based on the

procedure and evaluation criteria set forth below.

...

Phase II – Requests for Proposals from Pre-Qualified Offerors

Those Offerors determined to be pre-qualified in accordance with this

notice will be issued a formal Request for Proposal (RFP) for the project

and invited to submit proposed pricing in Phase II.

(emphasis in original).

The Notice of Solicitation informed offerors that, with a single submission, they

could seek prequalification for the Harare, Zimbabwe project and four other projects:

United States Embassy Pristina, Kosovo, RFP SAQMMA-13-R0118; United States

Embassy/Consulate Ashgabat, Turkmenistan, RFP SAQMMA-14-R0108; United States

Consulate Nuevo Laredo, Mexico, RFP SAQMMA-14-R0117; and United States

Consulate Erbil, Iraq, RFP SAQMMA-14-R0101. The Notice of Solicitation instructed

that multiple submissions were not required for each project and that “[o]fferors seeking

multiple project qualifications must list all projects for which qualification is sought in the

cover letter.” The Notice of Solicitation indicated that “[t]he Government would evaluate

and consider the qualification package submitted in relation to the requirements for

qualification described in each separate project Notice of Solicitation of Submission for

which qualification is requested.”

The Notice of Solicitation provided that, “[f]irms submitting information for Phase I

qualification shall address the following criteria in the proposal to provide design and

construction services.” Under section “4. Mandatory Pre-Qualification Requirements”

(emphasis in original), the Notice of Solicitation indicated that, “[t]he Offeror shall submit

sufficient documentation to allow DOS to evaluate its capabilities with respect to the

factor(s) and qualification criteria listed. Submissions that are missing the required

information or otherwise do not comply with the submission requirements may be

eliminated from consideration at the Contracting Officer’s determination.” Moreover, of

3

particular relevance to the current protest, the Notice of Solicitation instructed:

To demonstrate performance of similar construction work for Omnibus

Diplomatic Security and Antiterrorism Act of 1986 purposes, the offeror

needs to provide information demonstrating that it has successfully

completed in the United States or at a U.S. diplomatic or consular mission

a construction contract or subcontract involving work of the same general

type and complexity as the solicited project and having a contract or

subcontract value of at least $124 million.

(emphasis added). The Notice of Solicitation required that “ALL SUBMISSIONS MUST

BE RECEIVED BY 3:00 P.M. Eastern Time on April 16, 2014” (capitalization in original),

and indicated “REQUESTS FOR CLARIFICATIONS must be submitted in writing to

Jillian Savage AND David Vivian by email SavageJM@state.gov AND Alt AQM

viviandw@state.gov.” (capitalization and emphasis in original). Under section “4.A.

Omnibus Diplomatic Security and Antiterrorism Act of 1986,” the Notice of Solicitation

further explained the application of the Omnibus Diplomatic Security and Antiterrorism

Act of 1986 (Diplomatic Security Act).2 The Notice of Solicitation provided:

2

Codified at 22 U.S.C. § 4852 (2012), the Diplomatic Security Act provides:

(a) Preference for United States contractors

Notwithstanding section 302 of this title, and where adequate competition

exists, only United States persons and qualified United States joint

venture persons may—

(1) bid on a diplomatic construction or design project which has an

estimated total project value exceeding $10,000,000; and

(2) bid on a diplomatic construction or design project which involves

technical security, unless the project involves low-level technology,

as determined by the Secretary of State.

...

(c) Definitions

For the purposes of this section—

...

(2) the term “United States person” means a person which—

...

4

Firms being considered for award under this acquisition are limited to

“United States Person” bidders as defined in the Act. The Offeror must

complete and submit as part of its pre-qualification package the pamphlet

“Certifications Relevant to Public Law 99-399, Statement of Qualifications

for Purpose of Section 402 of The Omnibus Diplomatic Security and

Antiterrorism Act of 1986.” (The pamphlet is attached to this

FEDBIZOPPS announcement and may be obtained from the DOS

Contract Specialist listed at the end of this notice.) . . . This is a pass/fail

evaluated area. Submissions from Offerors who do not receive a pass

rating in this area will not be further evaluated. Sufficient information

should be provided in the Certifications and attachments thereto to

determine eligibility under Public Law 99-399, but the Department

reserves the right to consider information available from other sources, or

to obtain clarifications or additional information from the Offeror.

(emphasis in original). A pamphlet titled: “CERTIFICATIONS RELEVANT TO PUBLIC

LAW 99-399 Statement of Qualifications for Purpose of Section 402 of the Omnibus

Diplomatic Security and Antiterrorism Act of 1986 (Public Law 99-399)” (capitalization in

original), was attached to the Notice of Solicitation. The pamphlet instructed prospective

offerors to “Use this Guide for All FY 2014 Project Submissions Include a copy in each

Qualification Submission.” (emphasis in original). The pamphlet explained that:

Section 402 of the Omnibus Diplomatic and Antiterrorism Act of 1986

provides that a “United States person” must meet certain requirements,

listed in subsections 402(c)(2) and (3) of the Act, to be eligible for the

statutory preference. To assist individuals to determine whether or not

they qualify as a U.S. person . . . entitled to preference under Section 402,

guidance is provided on this pre-qualification form.

For ease of reference, the statutory language will be quoted immediately

before the definitions that apply to it. Space for the information requested

is provided immediately following definitions. The Department of State

reserves the right, in its sole discretion, to interpret and apply the

definitions to the information provided by each prospective offeror.

(D) has performed within the United States or at a United States

diplomatic or consular establishment abroad administrative and

technical, professional, or construction services similar in

complexity, type of construction, and value to the project being

bid[.]

Omnibus Diplomatic Security and Antiterrorism Act of 1986, Pub. L. No. 99-399, § 402,

100 Stat. 853, 864 (1986) (as codified and amended at 22 U.S.C. § 4852) (emphasis to

word “value” added).

5

In relevant part, the pamphlet stated:

Section 402 (c) (2) (D): “The term ‘United States person’ means a person

which—has performed within the United States, or at a United States

diplomatic or consular establishment abroad administrative and

technical, professional, or construction services similar in complexity, type

of construction, and value to the project being bid.”

(emphasis in original). Following the quoted statutory language, the pamphlet defined

certain terms, including “VALUE” (capitalization and emphasis in original), which was

defined as follows:

“VALUE”—This term refers to the total contract price of the project, not to

the profit or loss to the contractor.

(capitalization and emphasis in original). The pamphlet then provided a space for the

prospective offeror to include a certification of its similar projects, as follows:

Certification #4: List on this page and an attachment if necessary, one or

more similar projects completed by the prospective offeror. For each

project, provide the following information:

Location:___________________________________(city and state)

Type of service:_____________________________(administrative, etc.)

Complexity:________________________________(office building, etc.)

Type of construction:_________________________

Value of project:_____________________________

If the prospective offeror’s participation was as a partner or co-venturer,

indicate the percentage of the project performed by the prospective

offeror:__________.

(emphasis in original).

On April 7, 2014, approximately nine days before the prequalification submission

deadline, and as instructed in the Notice of Solicitation regarding requests for

clarifications, President of Framaco Paul Kacha sent an email to DOS employee Jillian

Savage and to DOS contracting officer David Vivian,3 seeking clarification on the value

figure provided in the Notice of Solicitation. Mr. Kacha wrote:

3

The Administrative Record is unclear as to Jillian Savage’s job title at DOS.

Correspondence from counsel for Framaco addresses Ms. Savage as a “Contracting

Officer.” It is clear from the record that Mr. Vivian was a contracting officer.

6

We reviewed the pre-qualification Notice for the new Harare post.

The below Phase I requirements calls for a $124M completed US

diplomatic mission.

Kindly advise if we can apply using a $122M completed project that was

awarded in 2009 and if needed adjusting to inflation to meet the Harare

requirement?

Mr. Kacha copied into his email to the DOS the language from the Notice of Solicitation

regarding “Mandatory Pre-Qualification Requirements” (emphasis in original),

including the language setting forth the $124 million contract value threshold, which

stated:

To demonstrate performance of similar construction work for Omnibus

Diplomatic Security and Antiterrorism Act of 1986 purposes, the offeror

needs to provide information demonstrating that it has successfully

completed in the United States or at a U.S. diplomatic or consular mission

a construction contract or subcontract involving work of the same general

type and complexity as the solicited project and having a contract or

subcontract value of at least $124 million.

Later, on the morning of April 7, 2014, Mr. Vivian responded via email to Mr. Kacha’s

email, copying Ms. Savage and Michael Scott, 4 indicating: “The stated minimum is

$124. You may attempt to explain or justify why the Government should consider a

number less than the stated minimum but that is your decision and it may not be

successful.”

Protestor timely sent in a submission seeking prequalification for all five 2014

Design-Build Contracts: United States Embassy Pristina, Kosovo, RFP SAQMMA-13-

R0118; United States Embassy Harare, Zimbabwe, RFP SAQMMA-14-R0115; United

States Embassy/Consulate Ashgabat, Turkmenistan, RFP SAQMMA-14-R0108; United

States Consulate Nuevo Laredo, Mexico, RFP SAQMMA-14-R0117; and United States

Consulate Erbil, Iraq, RFP SAQMMA-14-R0101. In the cover letter to its prequalification

package, Framaco indicated “extensive experience of working successfully with the

Department of State, Bureau of Overseas Buildings Operations (DOS OBO) on several

embassy, consulate, and housing projects, often in challenging environments,” and that

it had “finished construction of the new 122M USD Design-Built [sic] US Embassy

Compound in Belgrade, Serbia successfully.”

As a reference project, Framaco submitted its contract for the Belgrade, Serbia

NEC performed by Framaco from February 2009 to October 2013. Framaco’s

prequalification package contained a section titled “Factor 4.0. Proof of Completion of

4

The Administrative Record is unclear regarding Michael Scott’s job title and

involvement in the procurement under consideration.

7

Project Approximately $120 million” (emphasis in original), in which Framaco sought

to demonstrate that it met the stated Solicitation requirements because the inflation-

adjusted contract value for the Belgrade, Serbia project exceeded $124 million.

Framaco “attached inflation adjusted calculations” and requested “OBO to take into

account the present value of Framaco’s historical work.” In its prequalification package,

Framaco stated:

With respect to the below requirement for all 5 above referenced projects:

To demonstrate performance of similar construction work for Omnibus

Diplomatic Security and Antiterrorism Act of 1986 purposes, the offeror

needs to provide information demonstrating that it has successfully

completed in the United States or at a U.S. diplomatic or consular mission

a construction contract or subcontract involving work of the same general

type and complexity as the solicited project and having a contract or

subcontract value of at least $.... million.

The magnitude of the 2014 minimum completion requirements is triggered

by an increased scope such as housing facilities. Framaco has already

successfully completed these type of facilities as part of its experience

(Ex. US$[redacted]+ [redacted] NEC, Housing Facilities).

Considering the successful completion of the Design Built US Embassy

NEC, Belgrade, Framaco would like to submit the attached inflation

adjusted calculations for your evaluation. Based on the 2009 awarded

price of $122,682,228 for the Belgrade Project and the present value of

the Serbia project would be $133,272,995 [sic]

The United States Congress and the Office of Federal Procurement Policy

have stated a clear policy preference for maximum competition through

the Competition in Contracting Act (“CICA”) and the Federal Acquisition

Regulation (“FAR”). OBO procurements remain subject to requirements of

CICA and the FAR. Accordingly, the qualification requirements of the

Omnibus Act must be interpreted in a manner that does not unduly and

impermissibly restrict competition. We understand that OBO in the past

has considered the present value of projects previously performed by a

contractor. We would appreciate OBO to take into account the present

value of Framaco’s historical work. If the Framaco projects and specifically

the NEC in Belgrade, Serbia was adjusted to reflect inflation and the

present value of money, Framaco’s project in the aggregate substantially

exceed the estimated value of the 2014 procurements. We hope that

OBO’s conclusion will be consistent with the letter or spirit of the Omnibus

Act requirements.

(emphasis and omission in original).

8

Framaco presented “Inflation Adjustment Calculations for the US Embassy

Belgrade Project” including a chart of “US Inflation per month” between February

2009 and March 2014 using inflation rates from the “US Bureau of Labor Statistics.”

(emphasis in original). Framaco also offered a timeline of events for the Belgrade,

Serbia project, which indicated Award on February 17, 2009, Substantial Completion on

March 29, 2013, Final Acceptance on October 31, 2013, and Prequalification

Submission on April 16, 2014. Framaco indicated that the “Contract Amount” at the

time of “award” was $117,137,704.00 and at the time of “s[ubstantial] completion”

was $122,682,229.00. (all emphasis in original). Framaco concluded “Average Inflation

per month between a& d” (emphasis in original) was 0.1358% and “Inflation adjust

Contract Completion Price based on the substantial completion date (61 terms)”

produced an “Inflation Adjusted Contract Value” of $133,272,995.00.5 (emphasis in

original). Also in support of Framaco’s Factor 4.0 submission, Framaco attached a

March 29, 2013 Certificate of Substantial Completion letter and an October 31, 2013

Final Acceptance letter for the Belgrade, Serbia project, both from the DOS.

In its prequalification package under a section titled “Factor 4.A. Omnibus

Diplomatic Security and Antiterrorism Act of 1986” (capitalization and emphasis in

original), Framaco also filled out and attached the pamphlet titled “CERTIFICATIONS

RELEVANT TO PUBLIC LAW 99-399 Statement of Qualifications for Purpose of

Section 402 of The Omnibus Diplomatic Security and Antiterrorism Act of 1986 (Public

Law 99-399).” (capitalization in original).

In accordance with Section 402(c)(2)(D) of the Diplomatic Security Act, and as

instructed in the pamphlet, Framaco responded to the request to comply with the term

“United States person” having “performed within the United States, or at a United

States diplomatic or consular establishment abroad administrative and technical,

professional, or construction services similar in complexity, type of construction, and

value to the project being bid.” (emphasis in original). In its submission, Framaco

indicated:

Certification #4: List on this page and an attachment if necessary, one or

more similar projects completed by the prospective offeror. For each

project, provide the following information:

Location: Please see the Attachment “Certification #4”(city and state)

Type of service:_____________________________(administrative, etc.)

Complexity:________________________________(office building, etc.)

Type of construction:_________________________

Value of project:_____________________________

If the prospective offeror’s participation was as a partner or co-venturer,

5

Framaco explained in its July 1, 2014 Agency Level Bid Protest that the chart “shows

the U.S. inflation by month for the years 2009 to 2014. Using the average inflation of

0.1358 percent, the inflation adjustment contract complete price based on the March 29,

2013 substantial completion date is $133,272,995.”

9

3) SAQMMA14R0115 NEC Harare, Zimbabwe ($165-210 million)

4) SAQMMA14R0118 NEC Pristina, Kosovo ($155-205 million)

5) SAQMMA14R0117 NCC Nuevo Laredo, Mexico ($68-95 million)

The May 12, 2014 Gallagher Memorandum provides that “[a]ll findings . . . are

based on the certifications and other prequalification materials submitted by the

prospective offerors and assume the truth of these representations unless otherwise

noted.” The May 12, 2014 Gallagher Memorandum notes:

there continues to be a good deal of uncertainty as to the application of

certain requirements of Section 402 of P.L. 99-399. In particular, there are

inconsistent decisions by the Court of Federal Claims and the Government

Accountability Office as to whether the business volume requirement may

be satisfied by cumulative business volume in 3 years of the 5 year period

prior to the solicitation exceeding the value of the project or whether

business volume in each of three years of the five year period is required.

For purposes of this review, I have applied the cumulative business

volume standard, but have notes [sic] instances in which the offeror would

not meet the standard articulated by GAO [Government Accountability

Office], in which the offeror must show business volume meeting or

exceeding the project value in each of 3 of the last five years.

The May 12, 2014 Gallagher Memorandum also states:

There has also been some uncertainty as to what project value should be

required for the construction services to be considered similar in value to

the project being solicited. To avoid uncertainty, each FedBizOpps

announcement provided that to meet the experience requirement a

potential offeror must have completed a construction contract involving

work of the same general type and complexity as the project for which it

seeks prequalification and having a contract or subcontract value

exceeding a specified amount as follows: 1) Erbil $187 million;

2) Ashgabat $135 million; 3) Harare $124 million; 4) Pristina $116 million;

5) Nuevo Laredo $51 million.

The May 12, 2014 Gallagher Memorandum proceeds to consider each of the

seventeen potential offerors7 ten of which sought to prequalify for the Harare, Zimbabwe

project. As reflected in the Administrative Record, in an undated DOS Internal Record of

Offerors, 8 eight of the ten potential offerors seeking prequalification for the Harare,

7

The May 12, 2014 Gallagher Memorandum did not fully consider Offeror #17, the offer

from the Weitz-Watts Joint Venture, because Mr. Gallagher indicated in the

memorandum that he was “unable to locate this volume” because it “either was not

submitted in the boxes for review or has been inadvertently misplaced.”

8

As reflected in the Administrative Record, the DOS Internal Record of Offerors

11

Zimbabwe project were prequalified by DOS and found eligible to bid on the Harare,

Zimbabwe project. These companies were: B.L. Harbert International, LLC; ECC

International, LLC; Caddell Construction Co., LLC, the intervenor in the protest currently

before the court, (Caddell); WATTS Constructors, Inc.; Perini Management Services;

KBR Federal Services, LLC; American International Contractors (Special Projects), Inc.;

and Pernix Group, Inc., bidding alone. 9 As reflected in the May 12, 2014 Gallagher

Memorandum and the DOS Internal Record of Offerors, two potential offerors were

found ineligible to compete and denied prequalification for the Harare, Zimbabwe

project: Framaco and ACC Construction Company, Inc. (ACC). Regarding Framaco,

also known as Offeror #2, which had sought prequalification for all five projects, the May

12, 2014 Gallagher Memorandum indicates, in relevant part:

Framaco’s reported business volume meets the COFC [United States

Court of Federal Claims] cumulative standard for all 5 projects but meets

the GAO 3 of 5 years standard only for Neuvo [sic] Laredo. Framaco’s

largest completed project is the Belgrade NEC ($122.6 million). This

meets the FedBizOpps thresholds only for Pristina and Nuevo Laredo.

Recommendation: Framaco should be deemed prequalified for Pristina

and Nuevo Laredo but not for the other three projects.

The May 12, 2014 Gallagher Memorandum does not specifically mention or discuss

Framaco’s request for DOS to utilize an inflation adjustment to reach the $124 million

threshold. Regarding the other potential offeror which was denied prequalification for

the Harare, Zimbabwe project, ACC, Offeror #15, the memorandum concluded that

ACC’s “largest projects are a [redacted] project and a [redacted] complex with contract

values of $[redacted] million and $[redacted] million respectively. This would meet the

contract value threshold only for Nuevo Laredo.” As reflected in the May 12, 2014

Gallagher Memorandum and the DOS Internal Record of Offerors, for the eight offerors

which were prequalified for the Harare, Zimbabwe project, all but Pernix Group, Offeror

#11, bidding alone, appear to have listed previous contracts that met the $124 million

contract value threshold. Regarding Pernix Group, Offeror #11, the May 12, 2014

Gallagher Memorandum recommended prequalification for the Pernix Group for the

provides the prequalification status of the potential offerors for the five projects, yet uses

some names for the companies different from those used in the May 12, 2014 Gallagher

Memorandum. For instance, the DOS Internal Record of Offerors refers to one company

as WATTS Construction, whereas the May 12, 2014 Gallagher Memorandum refers to

the company as WATTS Constructors, Inc.

9

The name Pernix appears three times in the May 12, 2014 Gallagher Memorandum:

first, as a joint venture proposer listed as Aecom/Pernix Joint Venture, Offeror #5;

second, as Pernix Group, Inc., Offeror #11; and third, as a joint venture proposer Pernix

Group/Aecom Government Services, Offeror #12. The joint venture proposers which

included Pernix, Offerors #5 and #12, sought prequalification only for the Nuevo Laredo,

Mexico project.

12

Harare, Zimbabwe project. The May 12, 2014 Gallagher Memorandum states:

Pernix lists business volumes for the three years from 2011 to 2013 that

exceeds $[redacted] million cumulatively. This would meet the COFC

cumulative business volume standard but would not meet the GAO

interpretation that the annual business volume for each of 3 years must

exceed the project value. For similar construction experience Pernix lists

one [redacted] office building construction project [redacted] whose value

is much less than the estimated value of the Harare or Pristina projects.

Pernix also lists a larger contract ($[redacted] million) for a variety of

construction work at the [redacted] that it performed as the majority

partner in a joint venture. This site is part of the [redacted] diplomatic

mission and the work at least in part appears similar in complexity and

type of construction to the Pristina and Harare projects and also meets the

contract value thresholds set for these two projects.

Recommendation: Pernix has demonstrated that it meets the

prequalification requirements for Harare and Pristina, and should be

deemed eligible to offer on those projects.

Although $[redacted] million is less than the $124 million contract value requirement for

prequalification for the Harare, Zimbabwe project, the May 12, 2014 Gallagher

Memorandum, nonetheless, prequalified the Pernix Group, Offeror #11, and

recommended it be allowed to proceed to Phase II of the competition.10

10

Upon reviewing the Administrative Record, including the May 12, 2014 Gallagher

Memorandum and the DOS Internal Record of Offerors, the court identified the

monetary disparity regarding the prequalification of Pernix Group, Offeror #11. The

court, therefore, issued an Order asking the parties to address why Pernix Group,

bidding alone as Offeror #11, had been recommended for prequalification for the

Harare, Zimbabwe project, although it had submitted a past project having a contract

value of only $[redacted] million, which was below the $124 million contract value

threshold requirement indicated to qualify for the Harare, Zimbabwe project. In

defendant’s reply in support of its motion for judgment on the Administrative Record,

defendant conceded that “DOS misapplied the $124 million threshold when it pre-

qualified offeror Pernix Group, Inc. (Pernix Group) for the Project, although it did not

consider inflation in doing so.” Defendant indicated that “DOS has since dis-qualified

Pernix Group.” Defendant attached a declaration from Dennis Gallagher, Assistant

Legal Adviser in the Office of the Legal Adviser to DOS and author of the May 12, 2014

memorandum. In his declaration, Mr. Gallagher acknowledges “Pernix Group listed a

contract of $[redacted] million for a construction project the [redacted] as evidence of

prior, similar work.” Mr. Gallagher explained that although he had “concluded that Pernix

Group met the pre-qualification requirement,” he had “reached this conclusion in error

because the threshold requirement contained in the Notice of Solicitation required a

contract or subcontract value of at least $124 million.” Mr. Gallagher indicated that he

had not considered inflation or other adjustments in the May 12, 2014 Gallagher

13

On June 3, 2014, contracting officer David Vivian notified Framaco of its

“Successful/Unsuccessful Prequalification” for the five projects. The letter indicated

Framaco did not qualify for the Harare, Zimbabwe project and, thus, would be ineligible

to submit a proposal for the project when the agency issues the Solicitation, although

Framaco did prequalify for the Pristina, Kosovo and Nuevo Laredo, Mexico projects.

The letter stated:

Based on the information provided in the prequalification package

submitted by Framaco International Inc., Framaco International Inc. did

not meet the technical requirements for prequalification for the 2014

Design-Build Construction Service for SAQMMA-14-R0101: Erbil, Iraq,

SAQMMA-14-R0108: Ashgabat, Turkmenistan and SAQMMA-14-R0115:

Harare, Zimbabwe projects.

However based on the information provided in the prequalification

package submitted by Framaco International Inc., Framaco International

Inc., has met all the requirements for prequalification for the 2014 Design-

Build Construction Service for SAQMMA-14-R0118: Pristina, Kosovo and

SAQMMA-14-R0117: Nuevo Laredo, Mexico projects.

The letter also provided instructions and timelines for the procurement process for

prequalified bidders:

Based on the current schedule, we plan to begin issuing the Request for

Proposal (RFP) for the prequalified referenced projects in late July 2014.

Once the RFP is released, a separate letter will be issued with the ProjNet

Key Codes to access the RFP.

Project and site specific discussions will be addressed during the site visit,

which will occur after release of the Request for Proposal (RFP)

Memorandum when he previously concluded that Pernix Group met the threshold.

Mr. Gallagher also indicated that, “[d]ue to this error, I have reviewed my May 12,

2014 memorandum to determine whether I made this same error when applying the

$124 million threshold to the other prospective offerors on the Project.” Mr. Gallagher

concluded he had not done so. Mr. Gallagher also “advised AQM [the Office of

Acquisition Management] at DOS that it should amend its prior notice to Pernix Group to

indicate that Pernix Group is not pre-qualified to participate in Phase II of the Project.” In

addition, defendant submitted a letter from contracting officer David Vivian to Pernix

Group, dated September 1, 2014, informing Pernix Group of the error and indicating

that, “[b]ased on the information provided in the prequalification package submitted by

Pernix Group, Inc., Pernix Group, Inc. does not meet all the requirements for

prequalification for the 2014 Design-Build Construction Service for the SAQMMA-14-

R0115 Harare, Zimbabwe.”

14

documents. Site visits usually take place approximately two weeks after

RFP issuance.

On June 9, 2014, Framaco requested a pre-award debriefing regarding the Erbil,

Iraq; Ashgabat, Turkmenistan; and Harare, Zimbabwe projects and received an oral

debriefing from the agency on June 12, 2014. During the debriefing, Framaco requested

the agency conduct a reconsideration of the determination on contract value. On June

13, 2014, Ms. Neal sent a DOS internal memorandum to Mr. Gallagher regarding

Framaco’s “Request for reconsideration of the Statement of Qualifications

Questionnaire” for the Harare, Zimbabwe project, as well as for the Erbil, Iraq and

Ashgabat, Turkmenistan projects. Ms. Neal’s June 13, 2014 Memorandum also

attached a blank form for Mr. Gallagher’s comments. Ms. Neal explained that during the

debriefing, Framaco “advised that the combined values of the project in Belgrade and

the present value of the Serbia project should have qualified them for the remaining 3

projects for which they are seeking prequalification. This information can be located on

page 1 of 3 under Factor 4.0.” On June 16, 2014, Mr. Gallagher responded to Ms. Neal

on the completed form:

Per telecon, Framaco seems to be arguing that the $122 million contract

value for Belgrade, Serbia NEC project should be adjusted upward. There

is nothing in the FedBizOpps announcement or in the law/regulation to

support such an adjustment, and no showing that such an adjustment is

warranted. I recommend that the prequalification determinations with

respect to Framaco not be changed.

On June 24, 2014, Ms. Neal responded by letter to Mr. Kacha. The letter stated:

During the debriefing conducted on June 12, 2014 a request for

reconsideration was made of the prequalification package submitted by

Framaco International Inc. The reconsideration request is based on the

position that Framaco International Inc. states that the $122 million

contract value for Belgrade and Serbia NEC projects should be adjusted

upward.

There is nothing in the FedBizOpps announcement or in the regulation/law

to support such an adjustment, and no showing of such and [sic]

adjustment is warranted. Therefore Framaco International Inc. remain s

[sic] not meeting the technical requirements for prequalification for the

2014 Design-Build Construction Service for SAQMMA-14-R0101: Erbil,

Iraq, SAQMMA-14-R0108: Ashgabat, Turkmenistan and SAQMMA-14-

R0115: Harare, Zimbabwe projects.

On July 1, 2014, counsel for Framaco filed an agency level protest with the

contracting officer, requesting a decision at a level above the contracting officer,

pursuant to FAR § 33.103(d)(4) (2013). Framaco indicated it was “not challenging the

OBO’s determination to disqualify Framaco for the OBO Erbil, Iraq and Ashgabat,

15

Turkmenistan projects” and it “understand[s] the agency’s analysis as to those larger

projects and only challenge[s] the agency’s decision with regard to the much smaller

Harare, Zimbabwe project.” Framaco stated:

OBO’s decision to disqualify Framaco is a violation of statute and

regulation. The agency should recommend that the contracting officer

determine Framaco prequalified for the 2014 NEC Harare, Zimbabwe

project. In the alternative, the agency should recommend that the

contracting officer conduct a new prequalification determination in

accordance with the requirements of the applicable statutes and

regulations and consistent with OBO’s practices.

Framaco argued that:

OBO’s determinations are not consistent with the applicable statutes and

regulations. Framaco has met the Section 402 subsection (D)

requirement. Framaco has performed similar construction services that

exceed the threshold required here. OBO’s interpretation treats Framaco

in an inconsistent and arbitrary manner. OBO found Framaco qualified

previously under almost identical situations. Moreover, OBO’s

disqualification relies on an unreasonable and unduly restrictive

interpretation of subsection (D) contrary to Section 402 and CICA. 41

U.S.C. § 3301.

Moreover, Framaco urged that:

Nothing in the Section 402 definitions limits the agency from adjusting past

projects for inflation. This makes logical sense. If Congress had intended

to limit competition solely to those offerors who had performed at least one

project with a dollar value equal to or greater than the project being bid

without any adjustments for inflation, Congress would have so specified.

Previously, OBO interpreted subsection (D) to allow for adjustments for

inflation. In the context of CICA and the overarching competition

requirements, and given the construction services of the type being

required here, especially where there are a limited number of potential

offerors, the rules must be interpreted to allow for adjustments for inflation.

Framaco attached to its request the same inflation adjustment calculations chart that it

had included in its prequalification package and stated:

Attachment A shows the U.S. inflation by month for the years 2009 to

2014. Using the average inflation of 0.1358%, the inflation adjustment

contract complete price based on the March 29, 2013 substantial

completion date is $133,272,995. This is the figure OBO should use in

determining the value of the Belgrade, Serbia project for the present

procurement. This present value of the Belgrade, Serbia project is

16

substantially more than the $124 million needed to prequalify for the

Harare, Zimbabwe NEC.

On July 21, 2014, Mr. Vivian responded to Framaco’s request by issuing a

“CONTRACTING OFFICER’S FINAL DECISION.” (capitalization in original). Mr. Vivian

denied Framaco’s protest, as follows:

On March 10, 2014 the Department of State issued the referenced

solicitation SAQMMA14R0115 for the Prequalification for the Design/Build

contract competition of a New Embassy Compound in Harare, Zimbabwe.

The solicitation announced that “Firms being considered for award under

this acquisition are limited to “United States Person” [sic] bidders as

defined in the Act.” In response to this solicitation, Framaco submitted a

Certification Relevant to Public Law 99-399, Statement of Qualifications

for Purpose of Section 402 of the Omnibus Diplomatic Security and

Antiterrorism Act of 1986 (hereafter (“the Act”),. [sic] Part of the Act

requires offerors to demonstrate completed projects that are considered

similar in value to the project being solicited. In Harare’s case, the range

of magnitude provided in the solicitation is $165 to 210 million. The largest

project submitted by Framaco to comply with this act was the Belgrade

NEC $122.6 million dollar project; which is nearly $42.5 million dollars less

than the minimum range for the Harare NEC project.

Furthermore, the announcement expressly indicates to all interest [sic]

parties that in order “To demonstrate performance of similar construction

work for Omnibus Diplomatic Security and Antiterrorism Act of 1986

purposes, the offeror needs to provide information demonstrating that it

has successfully completed in the United States or at a U.S. diplomatic or

consular mission a construction contract or subcontract involving work of

the same general type and complexity as the solicited project and having

a contract or subcontract value of at least $124 million.” This is a specific,

definite, and unequivocal reference to a mandatory threshold for

qualification. There is no allowance in the announcement for adjustment of

the stated threshold or to the value of the project that an interested party

may offer to demonstrate that it has successfully completed performance

of similar construction work. As indicated above, the project Framaco

offers to demonstrate compliance is the Belgrade NEC valued at $122.6

million: the project value is insufficient to meet the stated threshold.

The FedBizOpps announcement and the Act do not indicate that an

inflation adjustment to the project value is authorized or warranted;

therefore, it would be improper for the Government to apply such an

adjustment to any submission by any offeror. Please also note that the

announcement and prequalification evaluation criteria has been totally

revised and more clearly defined for 2014 so any allowance that may have

17

been appropriate in previous years cannot be brought forward into this

clearer unambiguous qualification process.

Wherefore, in light of the above facts, Framaco failed to display

completion of a project similar in value to the Harare NEC project as

required by the Act and solicitation, therefore Framaco’s protest is denied.

(emphasis in original). The contracting officer’s July 21, 2014 letter also indicated that

Framaco could seek review from the agency at a higher level than the contracting

officer by appealing to the Departmental Competition Advocate, Office of the

Procurement Executive (A/OPE), Department of State.

On July 23, 2014, Framaco submitted, what it referred to as, a “joint (a) request

for reconsideration of the U.S. Department of State, Bureau of Overseas Building

Operations’ . . . July 21, 2014 ‘Final Decision’ and (b) request that the agency protest

official Daniel J. Walt consider this additional submission in support of the protest.” In

the July 23, 2014 request, Framaco argued that “[t]he agency’s July 21, 2014 letter is

inconsistent with the solicitation and recent developments known to the agency” insofar

as it “inappropriately compares Framaco’s Belgrade project to an asserted range for the

total Harare project cost estimate of $165 to $210 million to claim that Framaco’s

Belgrade project is $42 million lower than required by the solicitation” because the

Solicitation does not require offers to be within the range of $165 to $210 million. In the

next line, however, the protestor acknowledged, through its attorney, that, “[t]he only

relevant threshold for qualification is the $124 million amount provided in the

FedBizOpps (‘FBO’) posting.” Framaco argued that the agency “cannot change the

ground rules in the middle of the procurement.” Framaco further stated that “the agency

analysis ignores the actual contract value for the Belgrade project.” Moreover, Framaco

asserted that “[a]ny reasonable analysis shows that the Belgrade project exceeds the

agency’s announced $124 million requirement.” Framaco once again urged that an

inflation adjustment should be used to reach “actual” value. Protestor also argued, “[i]n

any event, the actual contract value for the Belgrade project exceeds $124 million even

without an inflation adjustment” because of “approximately $[redacted] million in

Requests for Equitable Adjustments (‘REAs’) that are outstanding on the Belgrade,

Serbia project.” Framaco requested “that the agency determine Framaco to be

prequalified for the 2014 NEC Harare, Zimbabwe project” and stated, “[i]n the

alternative, Framaco is seeking the agency to recommend that the contracting officer

conduct a new prequalification determination in accordance with the requirements of the

applicable statutes and regulations and consistent with OBO’s previous practices.”

On August 5, 2014, Eric N. Moore, the DOS Departmental Competition

Advocate, sent a letter responding to Framaco, providing, “[a]s part of the independent

review of this agency protest, we reviewed all of the above materials plus the solicitation

and all other relevant supporting documentation.” The letter concluded:

Unfortunately, the solicitation does not include inflation adjustment as an

evaluation method. As such, applying it to your response would prejudice

18

other responses on which it was not applied. The Contracting Officer

therefore is unable to apply the inflation adjustment to any of the

responses, including yours. As such, we concur with the Contracting

Officer’s decision that based on your response to the solicitation; the

Department of State is unable to prequalify you to participate further in the

procurement.

Subsequently, the protestor filed the above captioned bid protest with this court,

asserting two claims: the first for “FAILURE TO EVALUATE IN ACCORDANCE WITH

SOLICITATION TERMS” and the second for “DISPARATE TREATMENT”

(capitalization in original), and requested the court to grant preliminary injunctive relief

precluding the defendant from continued pre-award activities under the Harare,

Zimbabwe project until after the court’s ruling on the merits. Framaco also requests that

the court grant “[a] judgment declaring that Defendant violated federal procurement law,

regulation and the terms of the RFP by failing to prequalify Framaco for the Harare,

Zimbabwe procurement.” The court granted Caddell’s motion to intervene in the

proceedings. The parties cross-moved for judgment on the Administrative Record.11

DISCUSSION

In its bid protest complaint, Framaco alleges two claims: the first for failure to

evaluate in accordance with Solicitation terms and the second for disparate treatment.

Regarding the first claim, protestor argues that to meet the Solicitation requirement of a

project “involving work of the same general type and complexity as the solicited project

and having a contract or subcontract value of at least $124 million,” Framaco submitted

its Belgrade, Serbia project, which according to Framaco, met the requirement, albeit

with an inflation adjusted contract value and/or an adjusted contract value for contract

modifications based on outstanding REAs. Protestor argues that “[t]he agency’s unduly

narrow and restrictive interpretation of the solicitation is arbitrary, capricious, an abuse

of discretion and otherwise contrary to statute and regulation.” Protestor also asserts

that the agency’s actions “constitute a clear and prejudicial violation of its obligations

under applicable law and regulation.” The protestor contends that the Harare,

Zimbabwe procurement is subject to the requirements of the Competition in Contracting

Act, 41 U.S.C. § 3301 (2012) (CICA) and that the “OBO’s present interpretation is anti-

competitive and contrary to the CICA and the FAR because [it] substantially limits

competition.”

Protestor also argues that the agency engaged in disparate treatment. Protestor

states it is “axiomatic that agencies must treat offerors on a fair and consistent basis”

and indicates that agencies are barred from treating offerors on a disparate basis.

11

Because DOS indicated that it intended to proceed to Phase II of the Solicitation on a

specified date, and after careful review of all of the parties’ submissions to the court, the

court denied the protest in a telephone conference with all parties and indicated this

written opinion would follow.

19

Protestor contends that “OBO has previously used inflation-adjusted contract values or

contract values that take into account modifications, REAs and other contract

adjustments in order to evaluate prequalification submissions.” Protestor argues that

“OBO has adopted an inconsistent and discriminatory interpretation of the Omnibus Act

in a manner that materially prejudices Framaco,” and that “[w]hen an agency departs

from its prior practice in an inconsistent fashion such action is arbitrary and capricious.”

Protestor contends such “impropriety is significantly heightened where, as here, it limits

competition, resulting in higher cost to the government.” In protestor’s motion for

judgment on the Administrative Record, protestor also alleges that “OBO erred as a

matter of law in determining that an inflation adjustment was barred by the terms of the

solicitation, statute and regulation” and “OBO’s improper exclusion of Framaco violated

material terms of the solicitation, the Federal Acquisition Regulation and the

Competition in Contracting Act . . . .”

The parties filed cross-motions for judgment on the Administrative Record.12 Rule

52.1(c) of the Rules of the United States Court of Federal Claims (2014) governs

motions for judgment on the Administrative Record. The court’s inquiry is directed to

“‘whether, given all the disputed and undisputed facts, a party has met its burden of

proof based on the evidence in the record.’” Mgmt. and Training Corp. v. United States,

115 Fed. Cl. 26, 40 (2014) (quoting A & D Fire Prot., Inc. v. United States, 72 Fed. Cl.

126, 131 (2006) (citing Bannum, Inc. v. United States, 404 F.3d 1346, 1356-57 (Fed.

Cir. 2005))); see also Eco Tour Adventures, Inc. v. United States, 114 Fed. Cl. 6, 21

(2013); DMS All-Star Joint Venture v. United States, 90 Fed. Cl. 653, 661 (2010).

12

Several documents not initially in the Administrative Record were offered to the court

during its review of Framaco’s bid protest. These documents included a declaration

from contracting officer David Vivian and a declaration from Framaco’s President Paul

Kacha. The United States Court of Appeals for the Federal Circuit has emphasized that,

on a motion for judgment on the Administrative Record, “‘the focal point for judicial

review should be the administrative record already in existence, not some new record

made initially in the reviewing court.’” Axiom Res. Mgmt., Inc. v. United States, 564 F.3d

1374, 1379-80 (Fed. Cir. 2009) (quoting Camp v. Pitts, 411 U.S. 138, 142 (1973)). The

Federal Circuit explained that supplementation of the record is not completely ruled out,

however, that “the parties’ ability to supplement the administrative record is limited.” Id.

at 1379. The record only should be supplemented to include documents that were not

before the agency at the time the decision was made in “cases in which ‘the omission of

extra-record evidence precludes effective judicial review.’” Id. at 1380 (quoting

Murakami v. United States, 46 Fed. Cl. 731, 735 (2000)). In the protest currently before

the court, the Administrative Record, without the additional declarations, is sufficient to

decide the case. The protestor’s Kacha declaration generally restates the protestor’s

arguments and although the defendant’s Vivian declaration may offer further rationale

for the agency’s decision, the record, without the Vivian declaration, is sufficient to

explain the agency rationale. Neither of the additional offerings are critical to the court’s

decision.

20

The Administrative Dispute Resolution Act of 1996 (ADRA), Pub. L. No. 104-320,

§§ 12(a), 12(b), 110 Stat. 3870, 3874 (1996) (codified at 28 U.S.C. § 1491(b)(1)-(4)

(2012)), amended the Tucker Act to establish a statutory basis for bid protests in the

United States Court of Federal Claims. See Impresa Construzioni Geom. Domenico

Garufi v. United States, 238 F.3d 1324, 1330-32 (Fed. Cir. 2001). The statute provides

that protests of agency procurement decisions are to be reviewed under Administrative

Procedure Act (APA) standards, making applicable the standards outlined in Scanwell

Laboratories, Inc. v. Shaffer, 424 F.2d 859 (D.C. Cir. 1970), and the line of cases

following that decision. See, e.g., Res. Conservation Grp., LLC v. United States, 597

F.3d 1238, 1242 (Fed. Cir.) (“Following passage of the APA in 1946, the District of

Columbia Circuit in Scanwell Labs., Inc. v. Shaffer, 424 F.2d 859 (D.C. Cir. 1970), held

that challenges to awards of government contracts were reviewable in federal district

courts pursuant to the judicial review provisions of the APA.”), aff’d, 432 F. App’x 975

(Fed. Cir. 2011); Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324, 1329 (Fed.

Cir.) (citing to Scanwell Laboratories, Inc. v. Shaffer, 424 F.2d at 864, 868, for its

“reasoning that suits challenging the award process are in the public interest and

disappointed bidders are the parties with an incentive to enforce the law”), reh’g denied

(Fed. Cir. 2004); Banknote Corp. of Am., Inc. v. United States, 365 F.3d 1345, 1351

(Fed. Cir. 2004) (“Under the APA standard as applied in the Scanwell line of cases, and

now in ADRA cases, ‘a bid award may be set aside if either (1) the procurement

official’s decision lacked a rational basis; or (2) the procurement procedure involved a

violation of regulation or procedure.’” (quoting Impresa Construzioni Geom. Domenico

Garufi v. United States, 238 F.3d at 1332)); Info. Tech. & Applications Corp. v. United

States, 316 F.3d 1312, 1319 (Fed. Cir.), reh’g and reh’g en banc denied (Fed. Cir.

2003). The United States Court of Appeals for the Federal Circuit has stated that the

Court of Federal Claims’ jurisdiction over “any alleged violation of statute or regulation in

connection with a procurement or a proposed procurement,” 28 U.S.C. § 1491(b)(1),

“provides a broad grant of jurisdiction because ‘[p]rocurement includes all stages of the

process of acquiring property or services, beginning with the process for determining a

need for property or services and ending with contract completion and closeout.’” Sys.

Application & Techs., Inc. v. United States, 691 F.3d 1374, 1381 (Fed. Cir. 2012)

(emphasis in original) (quoting Res. Conservation Grp., LLC v. United States, 597 F.3d

at 1244 (quoting 41 U.S.C. § 403(2))); see also Rockies Exp. Pipeline LLC v. Salazar,

730 F.3d 1330, 1336 (Fed. Cir. 2013), reh’g denied (Fed. Cir. 2014); Distrib. Solutions,

Inc. v. United States, 539 F.3d 1340, 1346 (Fed. Cir.) (“[T]he phrase, ‘in connection with

a procurement or proposed procurement,’ by definition involves a connection with any

stage of the federal contracting acquisition process, including ‘the process for

determining a need for property or services.’”), reh’g denied (Fed. Cir. 2008); RAMCOR

Servs. Grp., Inc. v. United States, 185 F.3d 1286, 1289 (Fed. Cir. 1999) (“The operative

phrase ‘in connection with’ is very sweeping in scope.”).

Agency procurement actions should be set aside when they are “arbitrary,

capricious, an abuse of discretion, or otherwise not in accordance with law,” or “without

21

observance of procedure required by law.” 5 U.S.C. § 706(2)(A), (2)(D) (2012);13 see

also Orion Tech., Inc. v. United States, 704 F.3d 1344, 1347 (Fed. Cir. 2013); COMINT

Sys. Corp. v. United States, 700 F.3d 1377, 1381 (Fed. Cir. 2012); Savantage Fin.

Servs. Inc., v. United States, 595 F.3d 1282, 1285-86 (Fed. Cir. 2010); Weeks Marine,

Inc. v. United States, 575 F.3d 1352, 1358 (Fed. Cir. 2009); Axiom Res. Mgmt., Inc. v.

United States, 564 F.3d 1374, 1381 (Fed. Cir. 2009) (noting arbitrary and capricious

standard set forth in 5 U.S.C. § 706(2)(A), and reaffirming the analysis of Impresa

Construzioni Geom. Domenico Garufi v. United States, 238 F.3d at 1332); Blue & Gold

Fleet, L.P. v. United States, 492 F.3d at 1312 (“‘[T]he inquiry is whether the

[government]’s procurement decision was “arbitrary, capricious, an abuse of discretion,

13

The language of 5 U.S.C. § 706 provides:

To the extent necessary to decision and when presented, the reviewing

court shall decide all relevant questions of law, interpret constitutional and

statutory provisions, and determine the meaning or applicability of the

terms of an agency action. The reviewing court shall—

(1) compel agency action unlawfully withheld or unreasonably delayed;

and

(2) hold unlawful and set aside agency action, findings, and

conclusions found to be—

(A) arbitrary, capricious, an abuse of discretion, or otherwise not in

accordance with law;

(B) contrary to constitutional right, power, privilege, or immunity;

(C) in excess of statutory jurisdiction, authority, or limitations, or

short of statutory right;

(D) without observance of procedure required by law;

(E) unsupported by substantial evidence in a case subject to

sections 556 and 557 of this title or otherwise reviewed on the

record of an agency hearing provided by statute; or

(F) unwarranted by the facts to the extent that the facts are subject

to trial de novo by the reviewing court.

In making the foregoing determinations, the court shall review the whole

record or those parts of it cited by a party, and due account shall be taken

of the rule of prejudicial error.

5 U.S.C. § 706.

22

or otherwise not in accordance with law.”’” (quoting Bannum, Inc. v. United States, 404

F.3d at 1351 (quoting 5 U.S.C. § 706(2)(A) (2000)))); Eco Tour Adventures, Inc. v.

United States, 114 Fed. Cl. at 22; Contracting, Consulting, Eng’g LLC v. United States,

104 Fed. Cl. at 340. “In a bid protest case, the agency’s award must be upheld unless it

is ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with

law.’” Turner Constr. Co. v. United States, 645 F.3d 1377, 1383 (Fed. Cir.) (quoting PAI

Corp. v. United States, 614 F.3d 1347, 1351 (Fed. Cir. 2010)), reh’g and reh’g en banc

denied (Fed. Cir. 2011); see also Glenn Defense Marine (ASIA), PTE Ltd. v. United

States, 720 F.3d 901, 907 (Fed. Cir.), reh’g en banc denied (Fed. Cir. 2013); McVey

Co., Inc. v. United States, 111 Fed. Cl. 387, 402 (2013) (“The first step is to

demonstrate error, that is, to show that the agency acted in an arbitrary and capricious

manner, without a rational basis or contrary to law.”); PlanetSpace, Inc. v. United

States, 92 Fed. Cl. 520, 531-32 (2010) (“Stated another way, a plaintiff must show that

the agency’s decision either lacked a rational basis or was contrary to law.” (citing

Weeks Marine, Inc. v. United States, 575 F.3d at 1358)).

In discussing the appropriate standard of review for bid protest cases, the United

States Court of Appeals for the Federal Circuit specifically addressed subsections (2)(A)

and (2)(D) of 5 U.S.C. § 706, see Impresa Construzioni Geom. Domenico Garufi v.

United States, 238 F.3d at 1332 n.5, but the Federal Circuit has focused its attention

primarily on subsection (2)(A). See COMINT Sys. Corp. v. United States, 700 F.3d at

1381 (“We evaluate agency actions according to the standards set forth in the

Administrative Procedure Act; namely, for whether they are ‘arbitrary, capricious, an

abuse of discretion, or otherwise not in accordance with law.’” (quoting 5 U.S.C.

§ 706(2)(A); Bannum, Inc. v. United States, 404 F.3d at 1351)); NVT Techs., Inc. v.

United States, 370 F.3d 1153, 1159 (Fed. Cir. 2004) (“Bid protest actions are subject to

the standard of review established under section 706 of title 5 of the Administrative

Procedure Act (‘APA’), 28 U.S.C. § 1491(b)(4) (2000), by which an agency’s decision is

to be set aside only if it is ‘arbitrary, capricious, an abuse of discretion, or otherwise not

in accordance with law,’ 5 U.S.C. § 706(2)(A) (2000).”) (citations omitted); Banknote

Corp. of Am., Inc. v. United States, 365 F.3d at 1350 (“Among the various APA

standards of review in section 706, the proper standard to be applied in bid protest

cases is provided by 5 U.S.C. § 706(2)(A): a reviewing court shall set aside the agency

action if it is ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance

with law.’” (quoting 5 U.S.C. § 706(2)(A) and citing Advanced Data Concepts, Inc. v.

United States, 216 F.3d 1054, 1057-58 (Fed. Cir.), reh’g denied (Fed. Cir. 2000))); Info.

Tech. & Applications Corp. v. United States, 316 F.3d at 1319 (“Consequently, our

inquiry is whether the Air Force’s procurement decision was ‘arbitrary, capricious, an

abuse of discretion, or otherwise not in accordance with law.’ 5 U.S.C. § 706(2)(A)

(2000).”).

The United States Supreme Court has identified sample grounds which can

constitute arbitrary or capricious agency action:

[W]e will not vacate an agency’s decision unless it “has relied on factors

which Congress has not intended it to consider, entirely failed to consider

23

an important aspect of the problem, offered an explanation for its decision

that runs counter to the evidence before the agency, or is so implausible

that it could not be ascribed to a difference in view or the product of

agency expertise.”

Nat’l Ass’n of Home Builders v. Defenders of Wildlife, 551 U.S. 644, 658 (2007) (quoting

Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983));

see also F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 552 (2009); Ala. Aircraft

Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009), reh’g

and reh’g en banc denied (Fed. Cir. 2010); In re Sang Su Lee, 277 F.3d 1338, 1342

(Fed. Cir. 2002) (“[T]he agency tribunal must present a full and reasoned explanation of

its decision. . . . The reviewing court is thus enabled to perform meaningful

review . . . .”), aff’d on subsequent appeal, 262 F. App’x 275 (Fed. Cir. 2008); Textron,

Inc. v. United States, 74 Fed. Cl. 277, 285-86 (2006), appeal dismissed sub nom.

Textron, Inc. v. Ocean Technical Servs., Inc., 222 F. App’x 996 (Fed. Cir.), and

dismissed per stipulation sub nom. Textron, Inc. v. Ocean Technical Servs., Inc., 223 F.

App’x 974 (Fed. Cir. 2007).

Moreover,

A bid protest proceeds in two steps. First . . . the trial court determines

whether the government acted without rational basis or contrary to law

when evaluating the bids and awarding the contract. Second . . . if the trial

court finds that the government’s conduct fails the APA review under 5

U.S.C. § 706(2)(A), then it proceeds to determine, as a factual matter, if

the bid protester was prejudiced by that conduct.

Bannum, Inc. v. United States, 404 F.3d at 1351; Eco Tour Adventures, Inc. v. United

States, 114 Fed. Cl. at 22; Archura LLC v. United States, 112 Fed. Cl. 487, 496 (2013).

A disappointed bidder has the burden of demonstrating the arbitrary and

capricious nature of the agency decision by a preponderance of the evidence. See

Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 995-96 (Fed. Cir. 1996); Davis Boat

Works, Inc. v. United States, 111 Fed. Cl. 342, 349 (2013); Contracting, Consulting,

Eng’g LLC v. United States, 104 Fed. Cl. at 340. The Federal Circuit has made clear

that “[t]his court will not overturn a contracting officer’s determination unless it is

arbitrary, capricious, or otherwise contrary to law. To demonstrate that such a

determination is arbitrary or capricious, a protester must identify ‘hard facts’; a mere

inference or suspicion . . . is not enough.” PAI Corp. v. United States, 614 F.3d at 1352

(citing John C. Grimberg Co. v. United States, 185 F.3d 1297, 1300 (Fed. Cir. 1999));

see also Turner Constr. Co., Inc. v. United States, 645 F.3d at 1387; Sierra Nevada

Corp. v. United States, 107 Fed. Cl. 735, 759 (2012); Filtration Dev. Co., LLC v. United

States, 60 Fed. Cl. 371, 380 (2004).

Under an arbitrary or capricious standard, the reviewing court should not

substitute its judgment for that of the agency, but should review the basis for the agency

24

decision to determine if it was legally permissible, reasonable, and supported by the

facts. See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. at 43

(“The scope of review under the ‘arbitrary and capricious’ standard is narrow and a

court is not to substitute its judgment for that of the agency.”); see also Turner Constr.

Co., Inc. v. United States, 645 F.3d at 1383; R & W Flammann GmbH v. United States,

339 F.3d 1320, 1322 (Fed. Cir. 2003) (citing Ray v. Lehman, 55 F.3d 606, 608 (Fed.

Cir.), cert. denied, 516 U.S. 916 (1995)). “‘“If the court finds a reasonable basis for the

agency’s action, the court should stay its hand even though it might, as an original

proposition, have reached a different conclusion as to the proper administration and

application of the procurement regulations.”’” Weeks Marine, Inc. v. United States, 575

F.3d at 1371 (quoting Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir.

1989) (quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C. Cir. 1971)));

Jordan Pond Co., LLC v. United States, 115 Fed. Cl. 623, 631 (2014); Davis Boat

Works, Inc. v. United States, 111 Fed. Cl. at 349; Norsat Int’l [America], Inc. v. United

States, 111 Fed. Cl. 483, 493 (2013); HP Enter. Servs., LLC v. United States, 104 Fed.

Cl. 230, 238 (2012); Vanguard Recovery Assistance v. United States, 101 Fed. Cl. 765,

780 (2011).

Stated otherwise by the United States Supreme Court:

Section 706(2)(A) requires a finding that the actual choice made was not

“arbitrary, capricious, an abuse of discretion, or otherwise not in

accordance with law.” To make this finding the court must consider

whether the decision was based on a consideration of the relevant factors

and whether there has been a clear error of judgment. Although this

inquiry into the facts is to be searching and careful, the ultimate standard

of review is a narrow one. The court is not empowered to substitute its

judgment for that of the agency.

Citizens to Pres. Overton Park, Inc. v. Volpe, 401 U.S. 402, 416 (1971), abrogated on

other grounds by Califano v. Sanders, 430 U.S. 99 (1977) (internal citations omitted);

see also U.S. Postal Serv. v. Gregory, 534 U.S. 1, 6-7 (2001); Bowman Transp., Inc. v.

Arkansas-Best Freight Sys., Inc., 419 U.S. 281, 285 (1974), reh’g denied, 420 U.S. 956

(1975); Co-Steel Raritan, Inc. v. Int’l Trade Comm’n, 357 F.3d 1294, 1309 (Fed. Cir.

2004) (In discussing the “arbitrary, capricious, and abuse of discretion, or otherwise not

in accordance with the law” standard, the Federal Circuit stated: “the ultimate standard

of review is a narrow one. The court is not empowered to substitute its judgment for that

of the agency.”); In re Sang Su Lee, 277 F.3d at 1342; Advanced Data Concepts, Inc. v.

United States, 216 F.3d at 1058 (“The arbitrary and capricious standard applicable here

is highly deferential. This standard requires a reviewing court to sustain an agency

action evincing rational reasoning and consideration of relevant factors.” (citing Bowman

Transp., Inc. v. Arkansas-Best Freight Sys., Inc., 419 U.S. at 285)); Lockheed Missiles

& Space Co. v. Bentsen, 4 F.3d 955, 959 (Fed. Cir. 1993); BCPeabody Constr. Servs.,

Inc. v. United States, 112 Fed. Cl. 502, 508 (2013) (“The court ‘is not empowered to

substitute its judgment for that of the agency,’ and it must uphold an agency’s decision

against a challenge if the ‘contracting agency provided a coherent and reasonable

25

explanation of its exercise of discretion.’” (quoting Keeton Corrs., Inc. v. United States,

59 Fed. Cl. 753, 755, recons. denied, 60 Fed. Cl. 251 (2004), and Axiom Res. Mgmt.,

Inc. v. United States, 564 F.3d at 1381)), appeal withdrawn, 559 F. App’x 1033 (Fed.

Cir. 2014) (internal citations omitted); Supreme Foodservice GmbH v. United States,

109 Fed. Cl. 369, 382 (2013); Alamo Travel Grp., LP v. United States, 108 Fed. Cl. 224,

231 (2012); ManTech Telecomms. & Info. Sys. Corp. v. United States, 49 Fed. Cl. 57,

63 (2001), aff’d, 30 F. App’x 995 (Fed. Cir. 2002); Ellsworth Assocs., Inc. v. United

States, 45 Fed. Cl. 388, 392 (1999) (“Courts must give great deference to agency

procurement decisions and will not lightly overturn them.” (citing Fla. Power & Light Co.

v. Lorion, 470 U.S. 729, 743-44 (1985))), appeal dismissed, 6 F. App’x 867 (Fed. Cir

2001), and superseded by regulation as recognized in MVS USA, Inc. v. United States,

111 Fed. Cl. 639 (2013).

According to the United States Court of Appeals for the Federal Circuit:

Effective contracting demands broad discretion. Burroughs Corp. v. United

States, 223 Ct. Cl. 53, 617 F.2d 590, 598 (1980); Sperry Flight Sys. Div. v.

United States, 548 F.2d 915, 921, 212 Ct. Cl. 329 (1977); see NKF Eng’g,

Inc. v. United States, 805 F.2d 372, 377 (Fed. Cir. 1986); Tidewater

Management Servs., Inc. v. United States, 573 F.2d 65, 73, 216 Ct. Cl. 69

(1978); RADVA Corp. v. United States, 17 Cl. Ct. 812, 819 (1989), aff’d,

914 F.2d 271 (Fed. Cir. 1990).

Lockheed Missiles & Space Co. v. Bentsen, 4 F.3d at 958-59. Therefore, as the Federal

Circuit further has indicated:

Contracting officers “are entitled to exercise discretion upon a broad range

of issues confronting them in the procurement process.” Impresa

Construzioni Geom. Domenico Garufi v. United States, 238 F.3d 1324,

1332 (Fed. Cir. 2001) (internal quotation marks omitted). Accordingly,

procurement decisions are subject to a “highly deferential rational basis

review.” CHE Consulting, Inc. v. United States, 552 F.3d 1351, 1354 (Fed.

Cir. 2008) (internal quotation marks omitted). Applying this highly

deferential standard, the court must sustain an agency action unless the

action does not “evince[ ] rational reasoning and consideration of relevant

factors.” Advanced Data Concepts, Inc. v. United States, 216 F.3d 1054,

1058 (Fed. Cir. 2000) (alterations added).

PAI Corp. v. United States, 614 F.3d at 1351; see also Weeks Marine, Inc. v. United

States, 575 F.3d at 1368-69 (“We have stated that procurement decisions ‘invoke[ ]

“highly deferential” rational basis review.’ Under that standard, we sustain an agency

action ‘evincing rational reasoning and consideration of relevant factors.’” (quoting CHE

Consulting, Inc. v. United States, 552 F.3d at 1354 (quoting Advanced Data Concepts,

Inc. v. United States, 216 F.3d at 1058))); Cohen Fin. Servs., Inc. v. United States, 112

Fed. Cl. 153, 162 (2013); McVey Co., Inc. v. United States, 111 Fed. Cl. at 402.

26

For example, “agencies ‘are entrusted with a good deal of discretion in

determining which bid is the most advantageous to the Government.’” Lockheed

Missiles & Space Co. v. Bentsen, 4 F.3d at 958-59 (quoting Tidewater Management

Servs., 573 F.2d at 73, 216 Ct. Cl. 69); see also Res-Care, Inc. v. United States, 735

F.3d 1384, 1390 (Fed. Cir.) (“DOL [Department of Labor], as a federal procurement

entity, has ‘broad discretion to determine what particular method of procurement will be

in the best interests of the United States in a particular situation.’” (quoting Tyler Constr.

Grp. v. United States, 570 F.3d 1329, 1334 (Fed. Cir. 2009))), reh’g en banc denied

(Fed. Cir. 2014); Grumman Data Sys. Corp. v. Dalton, 88 F.3d at 995; Kingdomware

Techs., Inc. v. United States, 107 Fed. Cl. 226, 231 (2012) (“‘Federal procurement

entities have “broad discretion to determine what particular method of procurement will

be in the best interests of the United States in a particular situation.”’” (quoting K-Lak

Corp. v. United States, 98 Fed. Cl. 1, 8 (2011) (quoting Tyler Constr. Grp. v. United

States, 570 F.3d at 1334)), aff’d, 754 F.3d 923 (Fed. Cir.), reh’g en banc denied (Fed.

Cir. 2014).

In addition, the court “assume[s] that the government acts in good faith while

contracting.” Galen Med. Assocs., Inc. v. United States, 56 Fed. Cl. 104, 108 (2003),

aff’d, 369 F.3d 1324 (Fed. Cir.), reh’g denied (Fed. Cir. 2004); Madison Servs., Inc. v.

United States, 92 Fed. Cl. 120, 129 (“The court’s review is thus guided by the ‘well-

established principle that contracting officials are presumed to act in good faith when

executing their procurement functions.’” (quoting Aero Corp. v. United States, 38 Fed.

Cl. 408, 413 (1997))), relief from judgment denied, 94 Fed. Cl. 501 (2010). A protestor

must show “‘well-nigh irrefragable proof’ that the government had an intent to injure it to

overcome this presumption.” Galen Med. Assocs., Inc. v. United States, 56 Fed. Cl. at

108 (quoting Knotts v. United States, 128 Ct. Cl. 489, 492, 121 F. Supp. 630, 631

(1954)); see also Caldwell & Santmyer, Inc. v. Glickman, 55 F.3d 1578, 1581 (Fed. Cir.

1995) (“We assume the government acts in good faith when contracting. Torncello [v.

United States], 681 F.2d [756,] 770 [(1982)]; Librach v. United States, 147 Ct. Cl. 605,

1959 WL 7633 (1959). A contractor can overcome this presumption only if it shows

through ‘well-nigh irrefragable proof’ that the government had a specific intent to injure

it. Torncello, 681 F.2d at 770.”); Madison Servs., Inc. v. United States, 92 Fed. Cl. at

129.

In the above captioned bid protest, Framaco states, “[s]ince the solicitation did

not preclude use of an inflation adjustment and the agency had regularly used inflation

adjustments in the past, Framaco reasonably assumed that an inflation adjustment

could and would be used here.” Framaco characterizes the agency decision not to apply

an inflation adjustment to its prequalification submission of the Belgrade, Serbia project

as “fundamental error of law” because, according to the protestor, the agency “believed

that it was legally prohibited from making an inflation adjustment.” During oral argument,

protestor focused heavily on a statement in the contracting officer’s July 21, 2014 final

decision in response to Framaco’s agency level protest, which stated: “The FedBizOpps

announcement and the Act do not indicate that an inflation adjustment to the project

value is authorized or warranted; therefore, it would be improper for the Government to

apply such an adjustment to any submission by any offeror.” Therefore, the protestor

27

asks this court to review the agency’s determination under a de novo standard of

review. Protestor alleges that the issue in the above captioned protest “is not one of

agency business judgment or a complex technical matter; it is a straightforward

question of law” and protestor “only challenges OBO’s legal error.” The Administrative

Record does not support protestor’s characterization that the agency acted because it

believed it was legally barred from using an inflation index, rather the agency chose not

to use an inflation adjustment for this solicitation, and the solicitation did not include any

indication that an inflation adjustment would be used.

Several documents in the Administrative Record bear on the discussion. First, a

handwritten note from DOS attorney Dennis Gallagher to DOS employee Donna Neal

states: “There is nothing in the FedBizOpps announcement or in the law/regulation to

support such an adjustment, and no showing that such an adjustment is warranted.” In

a June 24, 2014 letter to Framaco, signed by Ms. Neal as “Contracting Officer,” a nearly

identical statement appears: “There is nothing in the FedBizOpps announcement or in

the regulation/law to support such an adjustment, and no showing of such and [sic]

adjustment is warranted.” In response to Framaco’s agency level protest, an August 5,

2014 letter from DOS Departmental Competition Advocate Eric Moore, states: “the

solicitation does not include inflation adjustment as an evaluation method. As such,

applying it to your response would prejudice other responses on which it was not

applied. The Contracting Officer therefore is unable to apply the inflation adjustment to

any of the responses, including yours.”

Nothing in the Notice of Solicitation or the Diplomatic Security Act required the

agency evaluation and prequalification process to adjust for inflation or indicated that an

inflation adjustment would be applied when reviewing proposers’ evidence of prior,

similar work. The Notice of Solicitation did not include any indication that the

prequalification process would utilize an inflation adjustment, rather, the Notice of

Solicitation includes a clear, specific, and unequivocal statement that a $124 million

minimum qualification threshold would be utilized by the agency to review and

prequalify the proposals. Moreover, DOS did not use an inflation adjustment when

reviewing any of the submissions, and indicated in the August 5, 2014 letter to Framaco

that to apply an inflation index just for Framaco would result in prejudice to other

offerors. Defendant and the intervenor also correctly argue that Congress did not

include any reference to inflation adjustments in the Diplomatic Security Act and that the

implementing regulations likewise make no reference to an inflation adjustment. See

Diplomatic Security Act, § 402; 22 U.S.C. § 4852; 48 C.F.R. § 636.104-71 (2013); 48

C.F.R. § 652.236-72 (2013). In fact, the language of the Diplomatic Security Act and its

implementing regulations are silent on the subject, and neither preclude, nor require,

OBO to apply an inflation adjustment. Just because OBO used an inflation adjustment

when evaluating solicitations covered by the Diplomatic Security Act in the past, does

not alter the clear words of the solicitation currently under review and the clear $124

million contract value threshold stated in that solicitation.

Trying to turn the void to its advantage, protestor suggests that “nothing in the

Section 402 definitions [of the Diplomatic Security Act] limits the agency from adjusting

28

past projects for inflation, nor has the agency cited to any provision in support.”

Protestor contends that no regulation bars an inflation adjustment. (citing Caddell

Constr. Co., Inc., B-298949.2, 2007 WL 1893209, at *7-8 (Comp. Gen. June 15, 2007)).

Protestor, however cites only to general language noting overall guiding principles, for

example, that “[t]he agency’s position appears to be that, since the agency rules did not

address an inflation adjustment, it was barred.” Protestor argues this position is contrary

to the FAR § 1.102(d) (2013), Statement of guiding principles for the Federal Acquisition

System, which states: “In exercising initiative, Government members of the Acquisition

Team may assume if a specific strategy, practice, policy or procedure is in the best

interests of the Government and is not addressed in the FAR nor prohibited by law

(statute or case law), Executive order or other regulation, that the strategy, practice,

policy or procedure is a permissible exercise of authority.” FAR § 1.102(d).

The Notice of Solicitation at Section 4.A makes clear that the Diplomatic Security

Act applies to the procurement of the Harare, Zimbabwe project:

Firms being considered for award under this acquisition are limited to

“United States Person” bidders as defined in the Act.[14] The Offeror must

complete and submit as part of its pre-qualification package the pamphlet

“Certifications Relevant to Public Law 99-399, Statement of Qualifications

for Purpose of Section 402 of The Omnibus Diplomatic Security and

Antiterrorism Act of 1986.”

(emphasis in original). Under the Diplomatic Security Act, only “United States persons”

could bid on diplomatic design and construction work with an estimated total project

value exceeding $10,000,000.00 or more. See 22 U.S.C. § 4852(a)(1). As the total

project value for the Harare, Zimbabwe project is estimated between $165 million and

$210 million, the Diplomatic Security Act applies to the Harare, Zimbabwe project.

Therefore, the statute and implementing regulations do not preclude or require OBO to

apply an inflation adjustment when evaluating the solicitation at issue, and leaves the

decision as to whether to apply such an inflation adjustment within the agency’s

discretion.

The regulation at FAR § 1.102(d) also is silent on the possible application of an

inflation adjustment, and further supports the agency’s discretion to choose whether or

14

To be a United States person, a potential offeror must show, among other

requirements, that it “has performed within the United States or at a United States

diplomatic or consular establishment abroad administrative and technical, professional,

or construction services similar in complexity, type of construction, and value to the

project being bid.” 22 U.S.C. § 4852(c)(2)(D). The implementing regulations to the

Diplomatic Security Act define “value” as “mean[ing] the total contract price of the

project, not to the profit or loss to the bidder/offeror.” 48 C.F.R. § 652.236-72. There are

no allegations that Framaco was not a United States person for purposes of the

Diplomatic Security Act.

29

not to apply an inflation factor based on the best interests of the government. See FAR

§ 1.102(d) (“In exercising initiative, Government members of the Acquisition Team may

assume if a specific strategy, practice, policy or procedure is in the best interests of the

Government and is not addressed in the FAR nor prohibited by law (statute or case law),

Executive order or other regulation, that the strategy, practice, policy or procedure is a

permissible exercise of authority.”); see also Tyler Constr. Grp. v. United States, 570

F.3d at 1333 (“In other words, government officers are authorized, indeed, encouraged,

in exercising personal initiative in procurement matters, to assume that ‘a specific

strategy, practice, policy or procedure’ that is not ‘addressed in the FAR nor prohibited

by law (statute or case law), Executive order or other regulation’ and that ‘is in the best

interests of the Government,’ ‘is a permissible exercise of authority.’ . . . The Corps, like

other federal procurement entities, has broad discretion to determine what particular

method of procurement will be in the best interests of the United States in a particular

situation.” (quoting FAR § 1.102(d))); SEK Solutions, LLC v. United States, 117 Fed. Cl.

43, 49 (2014) (“In the absence of a violation of law, FAR 1.102(d) provides the agency

with a degree of flexibility in crafting its procurement.” (citing Tyler Constr. Grp. v. United

States, 570 F.3d at 1333)); FirstLine Transp. Sec., Inc. v. United States, 107 Fed. Cl.

189, 203-04 (2012) (An agency’s stated goal of 40 percent small business participation,

as measured by total contract price, was lawful when “nothing in the FAR affirmatively

prohibits an agency from establishing such goals in terms of total contract value” and

“FAR 1.102(d) expressly provides that contracting officers ‘may assume if a specific

strategy, practice, policy or procedure . . . is not addressed in the FAR, nor prohibited by

law (statute or case law), Executive order or other regulation, that the strategy, practice,

policy or procedure is a permissible exercise of authority.’” (quoting FAR § 1.102(d)))

(omission in original). The choice of whether or not to apply an inflation adjustment in

the protest currently before the court properly was left to the agency’s discretion.

As noted above, protestor relies on Caddell Construction Co., Inc., B-298949.2,

2007 WL 1893209, at *7-8 as “endors[ing] an agency evaluation under which the

agency adjusted an offeror’s previous work to reflect inflation under Section 402(d).”

Defendant also relies on Caddell Construction Co., but for the GAO’s finding that it

knew “‘of no statute or regulation that was violated by the agency’s decision to adjust for

inflation the price of the earlier project to determine its approximate current value,’” and

that as a result, the agency action was a proper exercise of discretion. (quoting Caddell

Constr. Co., B-298949.2, 2007 WL 1893209, at *7). Intervenor similarly argues,

“[n]othing in Caddell Construction provides that OBO is required to apply inflation

adjustments regardless of the Government’s best interests or language of the

solicitation documents” and states Caddell instead “merely provides that the

[Diplomatic] Security Act is silent regarding inflation adjustments and the decision of

whether or not to apply an adjustment ‘seems to fall within the reasonable exercise of

the agency’s discretion.’” (quoting Caddell Constr. Co., B-298949.2, 2007 WL 1893209,

at *8).

In Caddell, the GAO addressed a bid protest challenging an award under an RFP

issued by OBO for design and construction of a new United States embassy compound

pursuant to the Diplomatic Security Act. In Caddell, the awardee met the requirements

30

of the Diplomatic Security Act, in part, because for that procurement, “[t]he agency

determined that the value of the [awardee’s reference] project as adjusted for inflation

was $55 million and thus within the $50–$60 million estimate the government originally

prepared for the current . . . project.” Id. at *6. The GAO indicated “[o]n the question of

similar value, we know of no statute or regulation that was violated by the agency’s

decision to adjust for inflation the price of the earlier project to determine its

approximate current value.” Id. at *7. The GAO continued, “[i]n fact, the approach of

calculating such an adjustment for the purposes of determining a current value for the

earlier project seems to fall within the reasonable exercise of the agency’s discretion.”

Id. (citing OMNI Gov’t Servs., LP, B-297420.2 et al., 2006 WL 744276, at *2 (Comp.

Gen. Mar. 22, 2006)). Although not prohibiting use of an inflation adjustment, the

Caddell decision does not mandate its use and, instead, reemphasizes the discretionary

nature of whether or not to apply an inflation adjustment.

Nor is OBO’s decision not to apply inflation adjustments in the above captioned

protest inconsistent with the requirements in the CICA and part 6 of the FAR, that

agencies maximize competition. Protestor encourages the court to “take into account

the requirements of CICA and the FAR that agencies maximize competition,” and

argues that the CICA allows only a limited number of exceptions. Protestor requests the

court to “interpret the relevant statutory and regulatory provisions and case law in a

liberal manner that effectuates competition.” According to the protestor, “neither CICA,

nor the FAR . . . prohibit an inflation adjustment” and both “call for competition to the

maximum extent practicable.” Therefore, protestor argues that what it perceives to be

OBO’s interpretation that an inflation adjustment was precluded by the solicitation and

regulation “is anti-competitive and contrary to CICA and the FAR because OBO’s

interpretation substantially limits competition.” Protestor urges that “[i]nflation

adjustments are congruent with the policy and intent of CICA and the FAR competition

requirements,” and notes that the FAR encourages contracting officers to adopt liberal

interpretations, and such action is consistent with the mandates of the CICA to

maximize competition. Protestor indicates that “allowing an inflation adjustment is

reasonable given the construction services of the type being required here, especially

where there are a limited number of potential offerors.” Protestor indicates it is “not

asking OBO to remove the prequalification requirement, rather Framaco is asking that

OBO conduct its evaluation in accordance with the CICA requirements and on a non-

disparate basis,” so that the agency does not “unduly” restrict competition.

Intervenor asserts that OBO’s decision “does not impermissibly limit competition

under the Competition in Contracting Act, 41 U.S.C. § 3301 et seq.” Citing to the

Diplomatic Security Act and corresponding legislative history, intervenor argues that

“Congress, in its judgment and authority, found that some limit to competition is

necessary to protect the Government’s interests in diplomatic construction work.”

Specifically, regarding the Diplomatic Security Act, intervenor contends, “Congress

provided that an offeror’s performance of similarly valued work ‘will help ensure that a

firm is technically capable to carry out a given project.’” (quoting H.R. Rep. No. 99-494,

at 17 (1986), reprinted in 1986 U.S.C.C.A.N. 1865, 1883). Intervenor further argues,

“[t]his is a Congressionally-authorized protocol to prevent unqualified firms from

31

receiving contracts key to United States’ diplomacy and security – not an impermissible

restriction on competition.” Defendant adds that “[e]ach prospective offer was subject to

the same objective threshold of $124 million” and “as a result, each was provided an

equal opportunity to compete.” Defendant notes that the “CICA affords agencies the

discretion to ‘use the competitive procedure or combination of competitive procedures

that is best suited under the circumstances of the procurement.’” (citing 41 U.S.C.

§ 3301) (emphasis in original).

Although protestor may be correct that, in the past, on various solicitations for

DOS building contracts under the Diplomatic Security Act, the agency applied inflation

adjustments to calculate the value of projects previously performed, the decision in the

solicitation currently before the court to set a fixed contract value threshold at $124

million, or 75 percent of the minimum projected value of the contemplated project,

without considering an inflation index was permissible and there is no evidence that the

decision was unduly restrictive or applied in a disparate manner. As portrayed below in

chart form, the May 12, 2014, internal Gallagher Memorandum presented contract value

thresholds for each of the five projects that each represents 75 percent of the minimum

projected value of that project, rounded to the nearest million.

Project Name Minimum 75% of Minimum Contract Value

Approximate Approximate Threshold

Design-Build Cost Design-Build

of Project Cost

SAQMMA14R0101 $250 million $187.5 million $187 million

NCC Erbil, Iraq

SAQMMA14R0108 $180 million $135 million $135 million

NEC Ashgabat,

Turkmenistan

SAQMMA14R0115 $165 million $123.75 million $124 million

NEC Harare,

Zimbabwe

SAQMMA14R0118 $155 million $116.25 million $116 million

NEC Pristina,

Kosovo

SAQMMA14R0117 $68 million $51 million $51 million

NCC Nuevo

Laredo, Mexico

The decision to choose the 75 percent figure has not been demonstrated as arbitrary or

capricious. Moreover, the Administrative Record reflects that the agency’s use of a

specific contract value threshold in this solicitation sought to remove uncertainty from

the procurement prequalification process. The May 12, 2014 Gallagher Memorandum

explained:

There has also been some uncertainty as to what project value should be

required for the construction services to be considered similar in value to

32

the project being solicited. To avoid uncertainty, each FedBizOpps

announcement provided that to meet the experience requirement a

potential offeror must have completed a construction contract involving

work of the same general type and complexity as the project for which it

seeks prequalification and having a contract or subcontract value

exceeding a specified amount as follows: 1) Erbil $187 million;

2) Ashgabat $135 million; 3) Harare $124 million; 4) Pristina $116 million;

5) Nuevo Laredo $51 million.

The July 21, 2014 final decision issued by the contracting officer also explained

that the contract value threshold of $124 million was “a specific, definite, and

unequivocal reference to a mandatory threshold for qualification.” The contracting officer

further indicated: “Please also note that the announcement and prequalification

evaluation criteria has been totally revised and more clearly defined for 2014 so any

allowance that may have been appropriate in previous years cannot be brought forward

into this clearer unambiguous qualification process.” The August 5, 2014 letter from

DOS Departmental Competition Advocate Eric Moore also indicated to Framaco,

“[u]nfortunately, the solicitation does not include inflation adjustment as an evaluation

method. As such, applying it to your response would prejudice other responses on

which it was not applied. The Contracting Officer therefore is unable to apply the

inflation adjustment to any of the responses, including yours.”

Defendant and intervenor agree that, as stated by defendant, “[t]he Notice of

Solicitation expressly states that prospective offerors must demonstrate similar work as

evidence[d] by a ‘contract or subcontract value of at least $124 million.’” (emphasis in

original). Defendant further provides that OBO defines “value” as “the total contract

price of the project.” The contracting officer and DOS Departmental Competition

Advocate reference this amount as a “specific, definite, and unequivocal . . . mandatory

threshold for qualification.” The agency evaluated protestor’s prequalification

submission pursuant to the terms of the Notice of Solicitation.

The email exchange with the contracting officer for clarification also did not

obligate the agency to use an inflation index. Although suggesting to Framaco that it

could “attempt to explain or justify why the Government should consider a number less

than the stated minimum,” the email, in fact, gives notice to Framaco that the

explanation or justification “may not be successful.” (emphasis added). Moreover,

Framaco’s email to DOS and receipt of the contracting officer’s response demonstrate

that Framaco either understood or should have understood in advance of submitting its

proposal that the Notice of Solicitation did not contain any assurance that an inflation

adjustment would be utilized and that OBO had made no commitments to apply an

inflation adjustment when evaluating the prequalification submissions of proposers.

Moreover, intervenor points out that “Framaco does not allege that its prior experience

with OBO includes circumstances, such as here, where a minimum threshold (less than

the expected cost of the project being bid) was included in the Notice of Solicitation.”

Intervenor also states, “[a]s such, Framaco was put on notice that OBO’s prior practices

in applying inflation adjustments would be inapplicable here.”

33

Defendant further points out that “Framaco’s understanding of DOS’s prior

practices, as well as its expectations for this Project, are irrelevant to the issue here,

i.e., what the contracting officer considered or should have considered in evaluating

Framaco’s Pre-Qualification Submission for this Project.” (emphasis in original).

Defendant highlights that, “[n]otably, Framaco does not point to the language itself in

asserting that the Notice of Solicitation is ambiguous.” Moreover, Defendant argues

that, “Framaco’s contention that the contracting officer agreed to consider inflation is

factually inaccurate” and instead “Framaco was put on notice that it was taking a risk in

submitting evidence of prior work that was below the stated minimum threshold of $124

million.”

The agency’s decision not to apply an inflation or other adjustment to Framaco’s

prequalification submission was based on a rational interpretation and application of the

terms of the Notice of Solicitation. The May 12, 2014 Gallagher Memorandum, the

contracting officer’s final decision, and the DOS Departmental Competition Advocate’s

denial of Framaco’s request for reconsideration all reviewed and reiterated that the

$124 million figure was a clear and specific threshold for prequalification. Even protestor

concedes that “the solicitation was silent as to whether an inflation adjustment would be

used here,” and that “[t]he solicitation does not address whether contract value would

be adjusted for inflation to reflect the actual value of the project in 2014 dollars.” The

Notice of Solicitation clearly instructed that:

To demonstrate performance of similar construction work for Omnibus

Diplomatic Security and Antiterrorism Act of 1986 purposes, the offeror

needs to provide information demonstrating that it has successfully

completed in the United States or at a U.S. diplomatic or consular mission

a construction contract or subcontract involving work of the same general

type and complexity as the solicited project and having a contract or

subcontract value of at least $124 million.

(emphasis added). As noted above, nothing in the language of the Notice of Solicitation

requires the agency to apply an inflation adjustment. Under section “4. Mandatory Pre-

Qualification Requirements” (emphasis in original), the Notice of Solicitation provided:

“[t]he Offeror shall submit sufficient documentation to allow DOS to evaluate its

capabilities with respect to the factor(s) and qualification criteria listed. Submissions that

are missing the required information or otherwise do not comply with the submission

requirements may be eliminated from consideration at the Contracting Officer’s

determination.” The Notice of Solicitation required potential offerors to “complete and

submit as part of its pre-qualification package the pamphlet ‘Certifications Relevant to

Public Law 99-399, Statement of Qualifications for Purpose of Section 402 of The

Omnibus Diplomatic Security and Antiterrorism Act of 1986.’”

The pamphlet instructed prospective offerors to “Use this Guide for All FY 2014

Project Submissions Include a copy in each Qualification Submission.” (emphasis in

original). The pamphlet defined the term “VALUE” (capitalization in original) as follows:

34

“‘VALUE’—This term refers to the total contract price of the project, not to the profit or

loss to the contractor.” (capitalization and emphasis in original). Notably, the pamphlet

clearly and explicitly stated:

Section 402 of the Omnibus Diplomatic and Antiterrorism Act of 1986

provides that a “United States person” must meet certain requirements,

listed in subsections 402(c)(2) and (3) of the Act, to be eligible for the

statutory preference. To assist individuals to determine whether or not

they qualify as a U.S. person . . . entitled to preference under Section 402,

guidance is provided on this pre-qualification form.

For ease of reference, the statutory language will be quoted immediately

before the definitions that apply to it. Space for the information requested

is provided immediately following definitions. The Department of State

reserves the right, in its sole discretion, to interpret and apply the

definitions to the information provided by each prospective offeror.

(emphasis added).

Framaco’s inquiry by email to the contracting officer, Mr. Vivian, and also to Ms.

Savage, stated:

We reviewed the pre-qualification Notice for the new Harare post.

The below Phase I requirements calls for a $124M completed US

diplomatic mission.

Kindly advise if we can apply using a $122M completed project that was

awarded in 2009 and if needed adjusting to inflation to meet the Harare

requirement?

Based on the correspondence, protestor argues that “[t]he agency invited Framaco to

submit a response as to why an inflation adjustment was warranted but summarily

rejected that explanation in an arbitrary and capricious fashion, based on an erroneous

conclusion of law, and without any reasonable or consistent analysis.” Framaco argues

that, “[i]n accordance with CO’s [contracting officer’s] pre-proposal email, Framaco’s

prequalification proposal included a statement explaining why an inflation adjustment

was warranted,” but “OBO summarily rejected the inflation adjustment based on

erroneous conclusions of law.” (internal citation omitted).

The contracting officer’s April 7, 2014 response stated: “The stated minimum is

$124. You may attempt to explain or justify why the Government should consider a

number less than the stated minimum but that is your decision and it may not be

successful.” Although Framaco relies on this correspondence to argue “the agency

indicated that an adjustment would be considered” and that this “provided no indication

that an inflation adjustment was barred in any way by the solicitation or anything else,” it

35

is not correct for protestor to suggest that the DOS official’s indication that an

adjustment would be considered is equivalent to assuming that an inflation adjustment

would be applied. Although the contracting officer’s April 7, 2014 email provided that

Framaco “may” attempt to explain or justify an inflation adjustment, the email does not

bind OBO to apply an inflation adjustment or to consider Framaco’s proposal if a project

not meeting the $124 million threshold was offered by Framaco in its prequalification

submission. As the email plainly states, any attempts to “explain or justify” an amount

below $124 million “is your decision and it may not be successful.” The April 7, 2014

email correspondence between Framaco and the DOS did not alter the solicitation

requirements. The court finds the agency’s decision not to apply an inflation adjustment

to Framaco’s prequalification submission is in accordance with the terms of the Notice

of Solicitation. From the Notice of Solicitation, Framaco was put on notice and was

aware that, to prequalify, its proposal was required to demonstrate previous work having

a contract value of at least $124 million.

Framaco offers an additional argument in a footnote in its motion for judgment on

the Administrative Record that:

In addition, the true contract value for the Belgrade project exceeds $124

million even without an inflation adjustment. The agency has failed to take

into account the approximately $[redacted] million in REAs that are

outstanding on the Belgrade, Serbia project. The Belgrade project is not

subject to any liquidated damage assessment and any reasonable

analysis shows that the contract value exceeds $124 million. Even if only

a portion of the outstanding REAs are recognized by OBO, the total

project cost certainly exceeds the threshold and establishes that Framaco

meets this qualification requirement.

(internal citations omitted). In protestor’s reply brief, Framaco tries to rely on case law

that states: “Some information is too close at hand for the agency to ignore.” (citing

Wells v. United States, 46 Fed. Cl. 178, 182 (2000)). During oral argument, protestor

also indicated that the agency has formally acknowledged protestor is owed something

on the Belgrade, Serbia project. Framaco notes that although it claims a far greater

entitlement on the Belgrade, Serbia project REAs, the government had offered to settle

Framaco’s REAs in the amount of $[redacted] million. Even adding $[redacted] million to

$122.6 million, the total value is still shy of the $124 million contract value threshold.

Regardless, at the time of the prequalification evaluation, the parties all acknowledge

that the REA settlement was not yet final and, therefore, could not be considered as

part of the contract value of the Belgrade, Serbia project for the prequalification

evaluation.

Intervenor points out that under the implementing regulations for the Diplomatic

Security Act, value of a contract is defined as “the total contract price of the project . . .”

48 C.F.R. § 652.236-72, and that “the price of a contract is not increased until and

unless the Government grants a pending REA.” (emphasis in original). Intervenor also

notes that Framaco’s prequalification submission package listed the value of the

36

Belgrade, Serbia project as $122.6 million in value, made no mention of pending REAs,

and did not request OBO to take REAs into account. Moreover, because OBO did not

consider pending REAs for other prospective offerors for this solicitation, it would not

have been appropriate to do so when evaluating Framaco’s prequalification submission.

Therefore, the agency decision not to adjust for inflation or take into account

pending REAs was reasonable, not arbitrary or capricious, or a violation of the law.

OBO exercised its discretion reasonably and in accordance with the stated terms of the

Notice of Solicitation when it refused to apply unstated criteria to evaluate Framaco’s, or

any other offeror’s, submission. “It is hornbook law that agencies must evaluate

proposals and make awards based on the criteria stated in the solicitation . . . . It thus is

beyond peradventure that the government may not rely upon undisclosed evaluation

criteria in evaluating proposals . . . .” Banknote Corp. of Am., Inc. v. United States, 56

Fed. Cl. 377, 386 (2003), aff’d, 365 F.3d 1345 (Fed. Cir. 2004) (internal citations

omitted); see also PlanetSpace, Inc. v. United States, 92 Fed. Cl. at 536-37; NEQ, LLC

v. United States, 88 Fed. Cl. 38, 47-48 (2009). The $124 million figure included in the

Notice of Solicitation, which was approximately 75 percent of the minimum of the range

of the approximate design-build cost for the Harare, Zimbabwe project, provided a

definite threshold for determining compliance with the Diplomatic Security Act. Thus,

offerors which might not meet the minimum of the range for the approximate design-

build cost for the Harare, Zimbabwe project, nonetheless, could compete. Whether or

not OBO applied inflation adjustments in the past, but chose not to do so regarding the

solicitation at issue, is not controlling, given the clarity of the Notice of Solicitation, the

apparent uniformity by DOS not to apply an inflation adjustment to any offeror, and the

uniform enforcement of the $124 million prequalification threshold, once the Pernix

Group error was corrected.

Protestor also adds a claim of disparate treatment. Stating the obvious, protestor

contends it is “axiomatic that agencies must treat offerors on a fair and consistent basis”

and indicates that agencies are barred from treating offerors on a disparate basis.

Protestor tries to extend this axiom to its protest by stating: “OBO has previously used

inflation-adjusted contract values or contract values that take into account modifications,

REAs and other contract adjustments in order to evaluate prequalification submissions.”

Protestor argues that “OBO has adopted an inconsistent and discriminatory

interpretation of the Omnibus Act [Diplomatic Security Act] in a manner that materially

prejudices Framaco,” and that, “[w]hen an agency departs from its prior practice in an

inconsistent fashion such action is arbitrary and capricious.” Protestor also states that

defendant “has acted in an unfair and disparate manner by failing to prequalify Framaco

under the circumstances addressed here” and “has acted in an anti-competitive and

unlawful manner by excluding Framaco from the Harare competition based on an

unduly restrictive interpretation of the solicitation that is inconsistent with OBO’s past

actions and governing law.” According to the protestor, with the procurement for the

Harare, Zimbabwe project, OBO “dramatically shifted” its method and changed its

procurement practice regarding its interpretation of contract value by failing to allow for

application of an inflation factor. The protestor states:

37

OBO has previously used inflation-adjusted contract values to determine

whether an offeror is eligible for OBO procurements, including

procurements subject to the Omnibus Diplomatic Security and Anti-

Terrorism Act of 1986 (the ‘Omnibus Act’) (Public Law No. 99-399,

codified at 22 U.S.C. § 4852), the Percy Amendment and similar

thresholds involving past performance considerations.

Protestor points out that under previous solicitations, Framaco submitted projects to

OBO which OBO adjusted for inflation. Protestor provides two examples. Framaco

alleges it used a [redacted] construction project for prequalification on a 2008

solicitation and the OBO adjusted for inflation, in part, due to the increase in the price of

construction materials over four years. Framaco’s other example notes that OBO

prequalified Framaco in [redacted] for a project with an estimated design-build cost of

US$175 to $200 million, higher than the range established for the Harare, Zimbabwe

project, and for which Framaco assumed that the prequalification determination was

based in part on inflation adjustments. In support, protestor again points to the GAO

protest in Caddell Construction Company, Inc., B-298949.2, 2007 WL 1893209, to

suggest that the practice of applying adjustments was not limited to Framaco. Moreover,

protestor also asserts that “OBO’s previous interpretation is premised in and consistent

with OBO’s own recognition of the rising costs of construction” and protestor provides

examples of that recognition.

Protestor relies heavily on Redland Genstar, Inc. v. United States, 39 Fed. Cl.

220 (1997) and cites a number of other cases, contending that, under Redland “‘“an

agency action is arbitrary when the agency offer[s] insufficient reasons for treating

similar situations differently”’” and the agency must provide a rational basis for departing

from its previous procurement practice, even if those practices were based on non-

binding guidance. (quoting Redland Genstar, Inc. v. United States, 39 Fed. Cl. at 234-

35 (quoting Transactive Corp. v. United States, 91 F.3d 232, 237 (D.C. Cir. 1996))).

Protestor concludes “OBO has not and cannot provide a rational explanation for

refusing to consider inflation in this procurement” and for abandoning its previous

approach.

The protestor’s disparate treatment arguments fail under protestor’s own legal

standard. In Redland Genstar, Inc. v. United States, the United States Army Corps of

Engineer (Corps) issued a solicitation for the construction of a stone dike. See id. at

222. In Redland, a Judge of this court concluded that “some rational basis is needed to

explain the Corps’ decision to apply different abrasion tests” to one project and not the

project at issue in the protest, given the similarities of the two. See id. at 234 (citing

Transactive Corp. v. United States, 91 F.3d at 237). The court noted that the Corps in

the specific procurement at issue had departed from construction guidance in EM 1110–

2–2302, the Corps’ engineering manual for “Construction With Large Stone” that the

Corps had previously followed. See id. at 223, 227. The court in Redland found that

“[t]he Corps is certainly entitled to depart from previous practice and the nonbinding

engineering guidance contained in EM 1110–2–2302, but it must provide a rational

basis for doing so.” Id. at 234 (citing Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto.

38

Ins. Co., 463 U.S. at 57). Ultimately, the Redland court found that the agency had failed

to provide a rational connection between the agency decision and the facts associated

with the project, even though defendant was given an opportunity to present someone

at the agency involved with the project to “explain to the court and to plaintiff why the

conditions at Poplar Island provide a reasonable basis for the Corps’ choice of abrasion

tests” and the “[d]efendant declined to take this opportunity.” Id. at 233. In the above

captioned protest, protestor’s claim would fail even under Redland because, as the

Redland court stated, an agency is entitled to depart from previous practice if a rational

basis is provided. In the first place, no internal agency guidance previously governed

DOS procedures regarding whether or not to apply an inflation adjustment. Moreover,

the Administrative Record in the current protest under review reflects a rational basis for

the agency’s decision not to apply an inflation index, namely, to avoid uncertainty

regarding the requirements of the solicitation, changing the procurement method

announced in the Notice of Solicitation for the Harare, Zimbabwe project, as well as for

the other four projects referenced in the Notice of Solicitation.

Both defendant and intervenor contend that protestor’s disparate treatment

allegation must fail, and both note that nowhere in its complaint does Framaco allege

that OBO considered inflation or other adjustments for other prospective offerors for the

same procurement and declined to do so for Framaco. According to defendant and

intervenor, each procurement stands on its own and OBO’s potential consideration of

inflation and other adjustments in prior, unrelated procurements is not relevant to the

procurement in the above captioned protest. According to defendant, “[c]ase law makes

clear that an agency is not bound to act consistently across procurements” but is “free

to establish new methods for conducting their procurements.” (citing Griffy’s Landscape

Maint. LLC, v. United States, 51 Fed. Cl. 667, 671 (2001); Renic Corp., Gov’t Sys. Div.,

B-248100, 1992 WL 189192, at *3 (Comp. Gen. July 29, 1992)). Defendant also argues

that in accordance with G4S Technology CW LLC v. United States, 109 Fed. Cl. 708

(2013), an agency is afforded discretion to change its mind during the course of an

evaluation, and that if an agency can switch course mid-evaluation, it can certainly

change course between separate solicitations, conducted years apart. Intervenor states,

“‘“[e]ach procurement stands alone, and a selection decision made under another

procurement does not govern the selection under a different procurement.”’” (quoting

SDS Int’l, Inc. v. United States, 48 Fed. Cl. 759, 772 (2001) (quoting Renic Corp., Gov’t

Sys. Div., B-248100, 1992 WL 189192, at *3)).

As explained in the record before the court, including the May 12, 2014 Gallagher

Memorandum, the July 21, 2014 final decision letter from contracting officer David

Vivian to Framaco, and the August 5, 2014 letter from DOS Departmental Competition

Advocate Eric Moore to Framaco, OBO offered a rational explanation for the choice it

made regarding application of an inflation adjustment even though it had applied an

inflation adjustment in the past, and did not allow the practice for the Harare, Zimbabwe

project and the other four projects referenced in the Notice of Solicitation. As indicated

above, the May 12, 2014 Gallagher Memorandum indicated that a strict, minimum

contract value that was approximately 75 percent of the minimum design-build cost of

the project was set for each of the five different projects, including the Harare,

39

Zimbabwe project, to better avoid uncertainty regarding the solicitation requirements.

As intervenor and defendant identify, protestor did not at first argue that the

agency treated protestor’s prequalification submission disparately from other potential

offerors in the procurement at issue here, and such an allegation was not included in

Framaco’s bid protest complaint. Only after the court identified a potential issue with

prequalification of the Pernix Group, as recorded in the May 12, 2014 Gallagher

Memorandum, and requested the parties to address the prequalification of Pernix

Group, did protestor argue that OBO’s treatment of Pernix Group “is the hallmark of

disparate and unfair treatment contrary to CICA and the FAR.” Defendant responded to

the court that OBO’s conclusion to prequalify Pernix Group was in error and indicated

that OBO has since amended its decision and sent notice to Pernix Group that it is not

prequalified to bid on the Harare, Zimbabwe project. Defendant also stated that OBO

did not consider inflation or other adjustments in initially concluding that Pernix Group

met the threshold. Defendant further indicated that “[a]fter learning that this error was

made, Mr. Gallagher ‘reviewed [his] May 12, 2014 memorandum to determine whether

[he] made this same error when applying the $124 million threshold to the other

prospective offerors on the Project’” and determined he did not. (alterations in original).

Such a clear error, identified easily by the court upon review of the May 12, 2014

Gallagher Memorandum, causes the court to question the care with which Mr. Gallagher

arrived at his recommendations. There is no basis, however, given the record currently

before the court, that other prequalification errors occurred during the evaluation by

those who received the May 12, 2014 Gallagher Memorandum and the contracting

officer, who signed the final decision which denied Framaco prequalification for the

Harare, Zimbabwe project, nor has the protestor specifically so alleged or provided

evidence to suggest additional errors. Moreover, during oral argument, protestor

conceded that there was no disparate treatment within the boundaries of the particular

solicitation at issue in the above captioned protest because the agency has since

excluded Pernix Group.

CONCLUSION

The court concludes that the agency’s determination not to apply adjustments for

inflation and not to consider the yet unresolved REAs when deciding not to prequalify

Framaco for the Harare, Zimbabwe project complied with the terms of the solicitation,

applicable law, regulation, and was not arbitrary or capricious. Protestor’s motion for

judgment on the Administrative Record is DENIED. Defendant’s and intervenor’s cross-

motions for judgment on the Administrative Record are GRANTED. Protestor’s

complaint is DISMISSED. The Clerk of Court shall enter JUDGMENT consistent with

this opinion.

IT IS SO ORDERED.

s/Marian Blank Horn

MARIAN BLANK HORN

Judge

40