ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

Environmental Safety Consultants, Inc. ) ASBCA No. 58343

)

Under Contract No. N62470-95-C-2399 )

APPEARANCE FOR THE APPELLANT: Peter C. Nwogu, Ph.D.

President/CEO

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq.

Navy Chief Trial Attorney

Ellen M. Evans, Esq.

Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE FREEMAN ON THE

GOVERNMENT'S MOTION FOR RECONSIDERATION OF THE

PARTIAL DISMISSAL FOR LACK OF JURISDICTION

In our decision dated 25 July 2014, the Board granted in part the government's

motion to dismiss the appeal for lack of jurisdiction. We granted the motion to the

extent of the contractor's claimed amount of $897,082.62 in costs incurred in

performance of the contract that exceeded the contract price of $561, 873 .25 at the time

the contract was terminated. See Environmental Safety Consultants, Inc., ASBCA

No. 58343, 14-1 BCA ii 35,681. Familiarity with that decision is assumed.

The government moves for reconsideration of two alleged "mistakes" in the

Statement of Facts (SOFs) of the 25 July 2014 opinion. The "Board's First Mistake"

alleged by the government is that:

The first sentence in [SOF] ii 11 of the decision

states, " ... the termination settlement exclusive of the

termination settlement expenses, cannot exceed the total

contract price as reduced by... the amount of 'payments

previously made' ..." (emphasis added). But the last

sentence in [SOF] ii 11 indicates the board did not reduce

the total contract price by any amount before subtracting it

from the total claim amount.

(Mot. at 2)

The last sentence in SOF ,-i 11 determined that the total amount of the

termination settlement claim (excluding the settlement expenses) exceeded the total

contract price at termination by $897,082.62. The government contends that for

purposes of calculating the claimed costs exceeding the contract price, the contract

price at termination ($561,873.25) should be reduced by the prior payments by the

government ($465,919.67). As so reduced, the contract price at termination would be

$95,953.58 and the excess of the claimed costs over the contract price would be

$1,363,002.29. (Mot. at 3)

At this stage of the appeal, we are not determining the net termination

settlement due ESCI, if any, but the jurisdictional limit on the maximum amount it can

claim. The last sentence in SOF ,-i 11 was not a mistake. When and if appellant proves

its incurred costs, a reasonable profit on those costs and its termination expenses, we

will then apply the reduction for payments previously made by the government, in

determining the net settlement amount due ESCI.

The "Board's Second Mistake" alleged by the government is the sentence in

SOF ,-i 15 stating that "all of the events fixing the liability of the government...were

known or should have been known by ESCI no later than the date the contract was

terminated for default on 12 June 1998." The government contends that: "This

finding is not supported by the facts and it directly conflicts with specific findings in

prior published decisions in which this board and the Court of Federal Claims fixed the

point in time at which all events giving rise to claims under this contract for alleged

increased costs accrued no later than the Summer of 1997." (Mot. at 1)

The prior decisions referred to by the government in its motion are

Environmental Safety Consultants, Inc., ASBCA No. 54615, 07-1 BCA ,-i 33,483,

issued by the Board on 31 January 2007, and Environmental Safety Consultants, Inc.

v. United States, 97 Fed. Cl. 190 (2011), issued by the Court of Federal Claims

(COFC) on 11 February 2011. Both decisions dealt with CDA claims by ESCI

submitted to the contracting officer on 22 October 2003. The total amounts of

those claims were $457,000 for additional work and $1,000,000 for "injuries to

appellant's business reputation, credit damages and conspiracy to injure appellant

and its owner, negligence .. .in the administration of the contract, and bad faith of

the part of the ROICC against appellant and its owner." 07-1 BCA ,-i 33,483 at

165,967-68; 97 Fed. Cl. at 194 ($457,011.02 as final amount due as of June, 1998).

Both the Board decision and the COFC decision held that the 22 October 2003 claims

accrued prior to 22 October 1997, outside the CDA statute of limitations and

accordingly outside the jurisdiction of the forum. 07-1BCA,-i33,483 at 165,983-86;

97 Fed. Cl. at 200.

The termination settlement claim now before the Board is in the total amount of

$1,458,955.87 (exclusive of settlement expenses) for alleged total incurred costs, profit

2

on those costs and settlements with subcontractors. The alleged amount for total

incurred costs includes among other items an amount of $123,000 under the heading

"ESCI Incurred Costs from July 1997 thru June 12, 1998" (app. supp. R4, tab 1, vol. 1,

Table 1 at 3). For purposes of determining the jurisdictional limit of the 5 July 2012

termination settlement claim, the "no later than" accrual date of 12 June 1998 for the

latest claimed amount in the termination settlement claim was not a mistake, and does

not change the earlier accrual date found by the Board and COFC for the 22 October

2003 claim that was before those forums in the cited decisions. The government has

not cited any authority, and we are not aware of any, that requires all claims or parts

thereof to have identical accrual dates.

On reconsideration, we find no error in the SOFs cited by the government. Our

decision of 25 July 2014 is affirmed.

Dated: 22 October 2014

I concur I concur

«~~

Administrative Judge

·(\~~----...

~N

Administrative Judge

Acting Chairman Acting Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 58343, Appeal of

Environmental Safety Consultants, Inc., rendered in conformance with the Board's

Charter.

Dated:

JEFFREY D. GARDIN

Recorder, Armed Services

Board of Contract Appeals

3

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.