Opinion

MSK Construction, Inc. v. Mayse Construction Company

Court
Court of Appeals of Tennessee
Filed
Sep 30, 2014
Status
Published
On the bench
Judge John W. McClarty
Cited by
0 cases
Authority
More cited than 33.3%

The opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT KNOXVILLE

August 26, 2014 Session

MSK CONSTRUCTION, INC. V.

MAYSE CONSTRUCTION COMPANY

Appeal from the Chancery Court for McMinn County

No. 2012CV246 Hon. Jerri S. Bryant, Chancellor

No. E2014-00139-COA-R3-CV-FILED-SEPTEMBER 30, 2014

This is a breach of an oral contract action in which MSK filed suit against Mayse for failure

to pay for the use of equipment and fuel used to fulfill a construction contract between Mayse

and the City of Athens. Mayse denied liability. Following a bench trial, the trial court ruled

in favor of MSK and awarded damages in the amount of $44,386.37 and prejudgment interest

in the amount of $1231.39. Mayse appeals. We affirm the decision of the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court

Affirmed; Case Remanded

J OHN W. M CC LARTY, J., delivered the opinion of the Court, in which D. M ICHAEL S WINEY,

and T HOMAS R. F RIERSON, II, JJ., joined.

Sam D. Elliott, Chattanooga, Tennessee, for the appellant, Mayse Construction Company.

William J. Brown, Cleveland, Tennessee, for the appellee, MSK Construction, Inc. d/b/a MC

Construction.

OPINION

I. BACKGROUND

Upon learning that the City of Athens (“the City”) intended to hire a contractor for a

sidewalk project, MSK Construction, Inc. d/b/a MC Construction (“MSK”) approached

Mayse Construction Company (“Mayse”) and offered to work as a subcontractor if Mayse

obtained the bid for the contract. MSK was owned by Mike Campbell (“Mike”) and Shane

Campbell (“Shane”), while Mayse was owned by William Preston Mayse (“William”) and

Richard Todd Mayse (“Todd”).1 At some point, the parties learned that MSK could not

proceed as the subcontractor because of the City’s specifications regarding the use of

subcontractors for such a large portion of the project. The parties came to an agreement in

which Mike and Shane (collectively “the Campbells”) would work as Mayse’s employees,

while MSK would serve as a vendor and provide some of the equipment to complete the

project.

Throughout the construction of the project, MSK submitted invoices for payment

regarding the equipment. In total, these invoices amounted to $95,092.78. Mayse remitted

payment in the amount of $50,755.91, leaving an outstanding balance of $44,386.37. MSK

made repeated demands for payment, which Mayse rejected. MSK filed suit. Mayse denied

that it owed any payment to MSK and asserted that the Campbells were individually liable

for negligent misrepresentation. Mayse claimed that it relied upon the Campbells’

computation regarding the cost of the project but that the Campbells were negligent by

failing to include the cost of concrete testing, which caused Mayse to submit a bid that was

not as profitable as originally anticipated.

The case proceeded to a bench trial at which several witnesses testified. Mike

testified that he had worked in the construction business since he was 13 years old. He

related that he became licensed in 1995 and that his son, Shane, started working for him

several years ago but had never obtained a license. He founded MSK, which operated as a

licensed general contractor and had completed numerous projects for the Tennessee

Department of Transportation (“TDOT”) as a subcontractor.

Mike related that he had worked with Mayse on other projects, specifically projects

involving concrete work. He testified that the project at issue in this case involved the

paving, striping, and construction of four and a half miles of sidewalk and handicap ramps.

He explained that the project was beyond MSK’s bonding capacity and that after reviewing

the line items in the overall project, he submitted a price estimate, dated October 30, 2009,

to Mayse in which MSK offered to complete several specific line items as a subcontractor.

He conceded that the estimate did not include a specific line item for the cost of the

equipment that would be used in the project. He explained that the cost of materials,

equipment, and labor was included in the overall estimate for each specific line item. He

opined that if MSK had been hired as a subcontractor, MSK would have assumed the risk in

the bidding process and would be required to absorb the costs beyond what was estimated

in the bidding documents. He related that he later learned that MSK could not complete the

line items as a subcontractor pursuant to the City’s specifications regarding the use of

1

In order to avoid confusion, we will refer to the parties involved by their respective first names.

-2-

subcontractors for such a large portion of the project. He asserted that he informed Mayse

of this fact before Mayse submitted the final bid to the City.

Mike testified that after learning that MSK could not work as a subcontractor, he and

Shane met with Mayse to discuss an alternative option. According to Mike, they came to an

agreement in which he and Shane would be hired as employees, MSK would serve as a

vendor and supply some equipment, and Mayse would recoup the added payroll costs by

increasing its percentage payment from 12 to 14 percent. He claimed that Mayse agreed to

reimburse MSK for the use of the equipment as an expense. He denied any discussion

regarding being paid for the equipment only when the project was recouping a profit. He

related that he was advised to charge everything he could, e.g., fuel and other expenses to

Mayse and that anything that could not be charged would be included in an invoice at the end

of each month as an expense. He explained that his portion of the project could not be

completed without the use of MSK’s equipment and that the charges contained in the invoice

were reasonable and necessary for completing the work. He conceded that he never entered

into a written contract with Mayse for the use of MSK’s equipment but that an oral

agreement was in place before the City awarded the bid to Mayse.

Relative to the issue of concrete testing, Mike recalled that he asserted at the pre-bid

and pre-construction meetings that TDOT would be responsible for the cost of the testing.

He acknowledged receipt of an addendum, dated October 23, 2009, advising everyone that

the cost of concrete testing was to be paid by the contractor, not TDOT. Despite the

addendum, he still believed that Mayse was not required to pay for the testing. He identified

a TDOT document in which it specified that concrete testing was to be performed by TDOT.

He acknowledged that while the project was built to TDOT’s specifications, it was the City’s

project. He conceded that he supplied his estimate after he received the addendum and that

he did not include the cost of concrete testing. He asserted that Mayse should have

performed its own research before submitting the final bid.

Mike testified that the contract for the project was signed on December 29, 2009, and

that construction began on January 8, 2010. He stated that MSK submitted numerous

invoices throughout construction and that the total payment requested for use of the

equipment was $95,092.78. He asserted that Defendant only remitted payment in the amount

of $50,755.91, leaving an outstanding balance of $44,336.87. He explained that Mayse

recouped its 14 percent before remitting any payments for expenses. He recalled advising

Mayse that it should not recoup its profit before paying expenses but that Mayse continued

in that manner throughout the project.

Mike identified an email in which he expressed concern that MSK would not receive

payment if the project was not profitable. He explained that at that point, Mayse had been

-3-

sporadically remitting payments. He conceded that the failure to account for concrete testing

was an added expense. He related that Mayse never blamed him for failing to include the

testing as an expense because everyone involved was confused and also believed that TDOT

was responsible for the testing. He claimed that he was simply an employee when Mayse

decided to accept responsibility for the concrete testing. He acknowledged that his price

estimates were also altered drastically by Mayse’s decision to increase its percentage

payment and by several change orders that were ultimately accepted by Mayse.

Shane testified that he learned of the project in a bid advertisement and that he

contacted Mayse to inquire whether MSK could serve as a subcontractor. He stated that

when they learned that MSK could not work as a subcontractor, he and Mike agreed to work

as employees instead. He claimed that they also agreed that MSK would serve as a vendor

by providing some equipment but that MSK would be reimbursed through monthly invoices.

He alleged that Mayse agreed to remit payment for the use of the equipment regardless of

whether the project was profitable.

Shane testified that he and Mike generated the initial estimate for the bidding process

but that Mayse supplied the final bidding documents well after everyone understood that he

and Mike were to work as employees, not subcontractors. He explained that the cost of

concrete testing was not included in his estimate because he believed that the testing would

be performed by TDOT. He acknowledged that they received an addendum concerning the

added expense of concrete testing prior to his submission of the final estimate. He claimed

that throughout his work on the project, he never received any complaints regarding the way

in which the bid had been constructed with the use of his estimate.

William testified that Mayse held an unlimited license as a utility contractor. He

related that he had worked with the Campbells and found that they had performed well and

were competent in the concrete business. He first learned of the project from Todd, who

informed him that MSK was to perform as a subcontractor. He later learned that they had

to hire Mike and Shane as employees. He believed that despite the change in MSK’s role,

their initial agreement remained in place, with the exception that Mayse would recoup an

additional 2 percent to compensate for the payroll expenses. He also believed that the

Campbells had included the cost of equipment in the initial price estimate. He asserted that

they did not discuss the issue of equipment until after they began work on the project. He

claimed that Mike requested money to pay insurance and that he informed Mike that he

would provide the funds to cover insurance if the job was profitable. He acknowledged that

several change orders were accepted throughout their work on the project and that these

changes affected the profit margin.

-4-

A portion of Todd’s deposition was read into the record in which he conceded that the

expenses requested by Plaintiff were reasonable and necessary but that they disagreed as to

whether the expenses should have been paid regardless of whether the job was profitable.

At trial, Todd testified that he was serving as the president of Mayse during the construction

of the project at issue. He related that he hired Plaintiff as a subcontractor for prior projects

and that they had performed well. He asserted that he contemplated the same arrangement

when he initially made plans with Plaintiff for the project at issue.

Todd testified that he relied on the Campbells’ estimate in preparing the bid for the

project. He acknowledged that the Campbells advised him that the estimate was “on the tight

side.” He asserted that they should have accounted for the concrete testing in the initial

estimate and that once the addendum was included in the contract, he was required to pay for

the testing in the amount of $25,139.05. He claimed that he learned that MSK could not

serve as a subcontractor after he had submitted the bid. He stated that he then agreed to hire

Mike and Shane as employees and that he increased his company’s percentage from 12 to 14

percent to account for payroll costs. He acknowledged that everyone understood that MSK

was not the subcontractor when the final contract with the City was signed. He provided that

Mike and Shane were paid for their work and that they even drew unemployment

compensation from his company. He asserted that the project was not as profitable as

anticipated and that he advised Mike and Shane that he could not fulfill the remainder of

MSK’s invoices. He claimed that he had already paid some of the invoices when the job was

making a profit and that according to their arrangement, MSK was responsible for bearing

the risk of loss as a vendor.

Following the presentation of the above evidence, the trial court found that MSK had

entered into an oral contract with Mayse to provide equipment for the project as a vendor and

that the parties recognized that the expenses were to be paid before any profit was

distributed. The court found that MSK was entitled to payment in the amount of $44,386.37

and prejudgment interest in the amount of $1231.39. The court denied Mayse’s counterclaim

for negligent misrepresentation, finding that Mayse accepted responsibility for the concrete

testing in the contract it formed with the City. This timely appeal followed.

II. ISSUES

We restate the issues raised on appeal by Mayse as follows:

A. Whether the trial court erred by finding in favor of MSK.

B. Whether the trial court erred in denying Mayse’s claim for negligent

misrepresentation.

-5-

MSK raised an issue for our consideration on appeal that we restate as follows:

C. Whether the trial court erred in setting the rate of prejudgment interest.

III. STANDARD OF REVIEW

We review the trial court’s findings of fact de novo on the record, presuming those

findings to be correct unless the evidence preponderates otherwise. Tenn. R. App. P. 13(d);

Bogan v. Bogan, 60 S.W.3d 721, 727 (Tenn. 2001); Wright v. City of Knoxville, 898 S.W.2d

177, 181 (Tenn. 1995). When the trial court’s factual determinations are based on its

assessment of witness credibility, we will not reevaluate that assessment absent clear and

convincing evidence to the contrary. See Jones v. Garrett, 92 S .W.3d 835, 838 (Tenn.

2002); Sullivan v. Sullivan, 107 S.W.3d 507, 510 (Tenn. Ct. App. 2002). We review a trial

court’s conclusions of law de novo, with no presumption of correctness. Whaley v. Perkins,

197 S.W.3d 665, 670 (Tenn. 2006); Taylor v. Fezell, 158 S.W.3d 352, 357 (Tenn. 2005).

The trial court’s award of prejudgment interest is reviewed under an abuse of

discretion standard. BankcorpSouth Bank, Inc. v. Hatchel, 223 S.W.3d 223, 230 (Tenn. Ct.

App. 2006); Franklin Capital Assocs., L.P. v. Almost Family, Inc., 194 S.W.3d 392, 405

(Tenn. Ct. App. 2005). “A trial court abuses its discretion only when it ‘applie[s] an

incorrect legal standard or reache[s] a decision which is against logic or reasoning that

cause[s] an injustice to the party complaining.’” Eldridge v. Eldridge, 42 S.W.3d 82, 85

(Tenn. 2001) (quoting State v. Shirley, 6 S.W.3d 243, 247 (Tenn. 1999)). If a discretionary

decision is within a range of acceptable alternatives, we will not substitute our judgment for

that of the trial court simply because we may have chosen a different alternative. White v.

Vanderbilt Univ., 21 S.W.3d 215, 223 (Tenn. Ct. App. 1999).

IV. DISCUSSION

A.

Mayse argues that the trial court found that there was no meeting of the minds

regarding the payment of expenses but then erroneously concluded that there was an oral

contract between the parties regarding the issue of expenses. Mayse asserts that the

preponderance of the evidence as demonstrated by the actions of the parties reflects that

MSK was only entitled to payment if there was a sufficient profit to cover the expenses.

MSK responds that the court did not err in finding that the parties entered into an oral

contract in which Mayse agreed to pay MSK’s expenses, regardless of whether the project

was profitable. MSK opines that there was ample evidence in the record to support the trial

court’s ultimate finding that an enforceable contract existed between the parties.

-6-

In finding that a contract existed regarding the payment of expenses, the trial court

stated, in pertinent part,

There was further no additional meeting of the mind and discussion on

[MSK’s] expenses. Exhibit 9, created by [MSK], shows that Mayse was

getting 14 percent and it did not reflect [MSK’s] expenses. Now, that

explanation [MSK] had for that document was that this was on a form as

requested by [Mayse]. Neither party in this case explained why they did not

go further and nail down these expenses as part of their agreement.

***

I don’t think either party talked about the risk of loss in this case. There was

no meeting of minds if this contract went over or if it couldn’t be done or what

was the risk; that the parties did not anticipate there was going to be a loss in

this case.

***

[MSK] is suing [Mayse] claiming that it was a salary plus expense contract.

Under [MSK’s] meaning of the agreement between the parties, this was very

basic and they were not responsible for their numbers being tight or any cost

overruns. [Mayse] says they would not have gotten into this job and accepted

this risk of loss, yet they did go on with the contract. [Mayse] says [MSK]

would not get paid for use of their own equipment if the job was not profitable.

That does not seem reasonable to this [c]ourt. The expenses of the job must

be paid before anyone gets paid out of profits.

The court ultimately held that the parties “recognized in this case that expenses were to be

paid before profits disbursed” and that Mayse breached its oral contract with MSK to pay for

the use of the equipment.

In order to prevail in a breach of contract case, Plaintiff first had to prove that an

enforceable contract existed between the parties. See Seramur v. Life Care Ctrs. of Am. Inc.,

No. E2008-01364-COA-R3-CV, 2009 WL 890885, at *2 (Tenn. Ct. App. Apr. 2, 2009)

(citing BankcorpSouth Bank, Inc. v. Hatchel, 223 S.W.3d 223, 227 (Tenn. Ct. App. 2006)).

A contract, either written or oral, “must result from a meeting of the minds of the parties in

mutual assent to the terms, must be based upon a sufficient consideration, free from fraud or

undue influence, not against public policy and sufficiently definite to be enforced.” Higgins

v. Oil, Chem. and Atomic Workers Int’l Union, 811 S.W.2d 875, 879 (Tenn. 1991) (internal

-7-

quotation and citation omitted). Tennessee courts have also defined a contract more simply

as “‘an agreement, upon sufficient consideration, to do or not to do a particular thing.’”

Calabro v. Calabro, 15 S.W.3d 873, 876 (Tenn. Ct. App. 1999) (quoting Smith v. Pickwick

Elec. Coop., 367 S.W.2d 775, 780 (Tenn. 1963) (internal citation omitted)). “‘For there to

be consideration in a contract between parties to the contract it is not necessary that

something concrete and tangible move from one to the other. Any benefit to one and

detriment to the other may be a sufficient consideration.’” GuestHouse Intern., LLC v.

Shoney’s North America Corp., 330 S.W.3d 166, 189 (Tenn. Ct. App. 2010) (quoting Walker

v. First State Bank, 849 S.W.2d 337, 342 (Tenn. Ct. App. 1992)). Indeed, “‘[a]ny

consideration, however small, will support a promise.”’ Id. (quoting Smith v. Riley, No.

E2001-00828-COA-R3-CV, 2002 WL 122917, at *3 (Tenn. Ct. App. Jan. 30, 2002)).

In this case, MSK and Mayse sought to obtain the bid for the City’s project. Upon

learning that MSK could not serve as a subcontractor, the parties agreed that the Campbells

would work for Mayse as employees and that MSK would provide some of the equipment

as a vendor. While the cost of the equipment was included in the initial estimate provided

by the Campbells when they sought to participate as a subcontractor, they never provided an

additional estimate reflecting their status as employees or MSK’s status as a vendor. This

oversight understandably caused confusion between the parties. Nevertheless, MSK

regularly submitted invoices for payment regarding the use of the equipment. Mayse paid

a number of these invoices and also regularly paid the Campbells as salaried employees.

While Mayse argued that it only remitted payment when the job was profitable, the testimony

presented at trial reflected that MSK objected to this arrangement and made repeated

demands for payment. Moreover, the trial court found that Mayse’s position that it was only

required to remit payment when there was a sufficient profit was unreasonable. We agree

with this finding. Indeed, we give great weight to the factual findings of the trial court which

rest on determinations of witness credibility. Randolph v. Randolph, 937 S.W.2d 815, 819

(Tenn. 1996). We will not reevaluate an assessment of witness credibility absent clear and

convincing evidence to the contrary. Wells v. Tenn. Bd. of Regents, 9 S.W.3d 779, 783

(Tenn. 1999). In consideration of these facts, we conclude that the parties assented to a

“handshake agreement” in which MSK agreed to provide equipment, while Mayse agreed

to pay for the use of the equipment in order to fulfill its contractual obligations with the City.

Accordingly, we further conclude that a valid oral contract had been formed between MSK

and Mayse and that Mayse breached the contract when it refused to remit the remainder of

the amount owed.

B.

Mayse argues that the trial court erred in dismissing its claim for negligent

misrepresentation relating to the Campbells’ failure to include the cost of concrete testing in

-8-

the initial estimate. Mayse notes that it justifiably relied upon the estimate. The Campbells

respond that the trial court did not err in denying the claim when the information regarding

the responsibility for concrete testing was also available to Mayse.

Persons asserting a negligent misrepresentation claim must establish:

One, who, in the course of his business, profession or employment, or in any

other transaction in which he has a pecuniary interest, supplies false

information for the guidance of others in their business transactions, is subject

to liability for pecuniary loss caused to them by their justifiable reliance upon

the information if he fails to exercise reasonable care or competence in

obtaining or communicating the information.

Restatement (Second) of Torts § 552(1) (1977); Robinson v. Omer, 952 S.W.2d 423, 427

(Tenn. 1997). An essential requirement for a claim of negligent misrepresentation is

“detrimental reliance on a false premise.” McNeil v. Nofal, 185 S.W.3d 402, 408 (Tenn. Ct.

App. 2005) (supporting citations omitted). To succeed on a claim of negligent

misrepresentation, the plaintiff must prove that he or she relied justifiably on the defendant’s

statements. See Lambdin v. Garland, 723 S.W.2d 953, 956 (Tenn. Ct. App. 1986). It is the

plaintiff’s burden to establish that his or her reliance on the defendant’s statements was

reasonable. Nofal, 185 S.W.3d at 409; see also Metro. Gov’t of Nashville and Davidson

Cnty. v. McKinney, 852 S.W.2d 233, 238 (Tenn. Ct. App. 1992).

The record reflects that the final bid was submitted after the parties received an

addendum providing that the contractor was responsible for the cost of the concrete testing.

This information was equally available to all parties. Additionally, the testimony presented

at trial also reflects that the parties discussed the issue of concrete testing on multiple

occasions and that Mayse, a sophisticated business, should have inquired further before

submitting its bid. Accordingly, we conclude that the trial court did not err in denying the

claim for negligent misrepresentation.

C.

MSK asserts that the trial court abused its discretion in setting the rate of prejudgment

interest at the statutory rate of 1 percent. Mayse responds that the court did not err.

The trial court may award prejudgment interest “as an element of, or in the nature of,

damages . . . in accordance with the principles of equity at any rate not in excess of a

maximum effective rate of ten percent (10%) per annum.” Tenn. Code Ann. § 47-14-123.

“The usual means of compensating for [loss of use of funds] is the allowance of interest.

-9-

Interest recovered in order to make the obligee whole is the relief usually sought, and the

allowance of prejudgment interest under such circumstances is ‘familiar and almost

commonplace.’” Mitchell v. Mitchell, 876 S.W.2d 830, 832 (Tenn. 1994) (quoting Deas v.

Deas, 774 S.W.2d 167, 170 (Tenn. 1989)). “The purpose of [prejudgment] interest is to fully

compensate a plaintiff for the loss of the use of funds to which he or she was legally entitled,

not to penalize a defendant for wrongdoing.” Hunter v. Ura, 163 S.W.3d 686, 706 (Tenn.

2005) (quoting Myint v. Allstate Ins. Co., 970 S.W.2d 920, 927 (Tenn. 1998)).

In determining whether to award prejudgment interest, courts should consider the

principles of equity and two additional factors. Mitchell, 876 S.W.2d at 830. First, an award

of interest is allowed when “the amount of the obligation is certain” or reasonably

ascertainable “by a proper accounting” and “is not disputed on reasonable grounds.” Myint,

970 S.W.2d at 927. Second, an award of interest is allowed when “the existence of the

obligation itself is not disputed on reasonable grounds.” Id. However, “[t]he uncertainty of

either the existence or amount of an obligation does not mandate a denial of prejudgment

interest, and a trial court’s grant of such interest is not automatically an abuse of discretion,

provided the decision was otherwise equitable.” Id. at 928.

Here, the amount of the obligation was certain, and the award of interest was equitable

because MSK lost the use of the funds while the case progressed in litigation. Moreover, the

court’s decision to award prejudgment interest at a statutory rate of 1 percent was wholly

within the court’s discretion. See Tenn. Code Ann. § 47-14-123. Following our review, we

conclude that the trial court did not abuse its discretion in setting the rate of prejudgment

interest.

V. CONCLUSION

The judgment of the trial court is affirmed, and this case is remanded to the trial court

for collection of costs below. Costs of the appeal are taxed to the appellant, Mayse

Construction Company.

______________________________________

JOHN W. McCLARTY, JUDGE

-10-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.