Opinion

Commonwealth Edison Co. v. Illinois Commerce Comm'n

  • 2014 IL App (1st) 130544
Court
Appellate Court of Illinois
Filed
Sep 26, 2014
Status
Published
Cited by
1 cases
Authority
More cited than 45.4%

The opinion

Illinois Official Reports

Appellate Court

Commonwealth Edison Co. v. Illinois Commerce Comm’n, 2014 IL App (1st) 130544

Appellate Court COMMONWEALTH EDISON COMPANY, Petitioner, v. ILLINOIS

Caption COMMERCE COMMISSION; AMEREN ILLINOIS COMPANY;

C3, INC.; COALITION OF ENERGY SUPPLIERS (Interstate Gas

Supply, Inc.; MidAmerican Energy Company; and North American

Power and Gas, LLC); CONSTELLATION NEWENERGY, INC.;

ENVIRONMENTAL LAW AND POLICY CENTER; EXELON

GENERATION COMPANY, LLC; FUTUREGEN INDUSTRIAL

ALLIANCE, INC.; ILLINOIS COALITION TO ADVANCE

RENEWABLE ENERGY (ACCIONA Energy North America

Corporation; EDP Renewables North America LLC; Iberdrola

Renewables, LLC; Invenergy LLC; and NextEra Energy Resources,

LLC); ILLINOIS COMPETITIVE ENERGY ASSOCIATION

(Ameren Energy Marketing Company; Champion Energy, LLC;

Constellation NewEnergy, Inc.; Direct Energy Services, LLC; Exelon

Energy Company; Integrys Energy Services, Inc.; MC Squared

Energy Services, LLC; FirstEnergy Solutions Corporation; Nordic

Energy Services, LLC; and Reliant); ILLINOIS INDUSTRIAL

ENERGY CONSUMERS; ILLINOIS POWER AGENCY;

NATIONAL RESOURCES DEFENSE COUNCIL; RETAIL

ENERGY SUPPLY ASSOCIATION (Champion Energy Services,

LLC; ConEdison Solutions; Constellation NewEnergy, Inc.; Direct

Energy Services, LLC; Energetix, Inc.; Energy Plus Holdings, LLC;

Exelon Energy Company; GDF Suez Energy Resources NA, Inc.;

Green Mountain Energy Company; Hess Corporation; Integrys

Energy Services, Inc.; Just Energy; Liberty Power; MC Squared

Energy Services, LLC; Mint Energy LLC; NextEra Energy Services;

Noble American Energy Solutions LLC; PPL EnergyPlus, LLC;

Reliant; Stream Energy; TransCanada Power Marketing Ltd.; and

TriEagle Energy, L.P.); WIND ON THE WIRES, Respondents.

District & No. First District, Second Division

Docket Nos. 1-13-0544, 1-13-0632, 1-13-0653, 1-13-1063, 1-13-1120

cons.

Filed July 22, 2014

Held An order of the Illinois Commerce Commission requiring petitioner to

(Note: This syllabus enter into a sourcing agreement to procure electricity for the retail

constitutes no part of the customers of alternative retail electric suppliers and recoup the costs

opinion of the court but through a “competitively neutral” charge, rather than requiring each

has been prepared by the alternative retail electric supplier to enter into its own sourcing

Reporter of Decisions agreement, was upheld on appeal over petitioner’s contentions that the

for the convenience of Commission made the decision without support from the record and

the reader.) violated the Rate Relief Law by requiring petitioner to enter into a

sourcing agreement to procure electricity for customers other than its

own “eligible retail customers,” since the Commission was entitled to

substantial deference with respect to its interpretation of the statute it

administers and the approach adopted by the Commission in the

instant case was within its statutory authority and was a cost-effective

alternative to administering the nearly 70 individual sourcing

agreements that would result from requiring each alternative retail

electric supplier to have its own agreement.

Decision Under Petition for review of order of Illinois Commerce Commission, No.

Review 1-13-0544.

Judgment Affirmed.

Counsel on Rooney Rippie & Ratnaswamy LLP (E. Glenn Rippie, of counsel),

Appeal and Jenner & Block LLP (Barry Levenstam and Irina Dmitrieva, of

counsel), both of Chicago, and Jenner & Block LLP, of Washington,

D.C. (David W. Debruin and Matthew E. Price, of counsel), for

petitioner.

Shefsky & Froelich Ltd., (John F. Kennedy, Jonathan B. Amarillo,

Barton J. O’Brien, Rachel L. Schaller, and Cary E. Donham, of

counsel), Quarles & Brady LLP (Christopher J. Townsend,

Christopher N. Skey, and Adam T. Margolin, of counsel), Law Offices

of Gerald T. Fox (Gerald T. Fox, of counsel), Husch Blackwell LLP

(Douglas F. McMeyer, of counsel), Lisa Madigan, Attorney General

(Clifford W. Berlow, Assistant Attorney General, of counsel), and

Citizens Utility Board (Julie Soderman and Orijit Ghoshal, of

counsel), all of Chicago, Lueders Robertson and Konzen LLC, of

Granite City (Eric Robertson, Ryan Robertson, and Drew Rankin, of

counsel), and Husch Blackwell LLP, of St. Louis, Missouri (Kyle C.

Barry and JoAnn T. Sandifer, of counsel), for respondents.

-2-

Panel PRESIDING JUSTICE HARRIS delivered the judgment of the court,

with opinion.

Justice Pierce concurred in the judgment and opinion.

Justice Pucinski dissented, with opinion.

OPINION

¶1 Petitioner Commonwealth Edison Company (ComEd), Illinois Competitive Energy

Association (ICEA), and Illinois Industrial Energy Consumers (IIEC) appeal the order of the

Illinois Commerce Commission (Commission) that requires ComEd to enter into a sourcing

agreement to procure electricity for the retail customers of alternative retail electric suppliers

(ARES) and recoup the costs through a “competitively neutral” charge. On appeal, appellants

contend that the Commission violated section 16-111.5 of the Public Utilities Act (220 ILCS

5/16-111.5 (West 2012)) when it ordered ComEd to enter into a sourcing agreement to

procure electricity for customers other than its own “eligible retail customers” and rendered

its decision without substantial support from the record.

¶2 JURISDICTION

¶3 The Commission issued its final order on December 19, 2012. ComEd filed a timely

application for rehearing on January 22, 2013, and a joint motion for clarification of the final

order. On January 29, 2013, the Commission denied the application for rehearing but granted

the motion for clarification and, on the same day, issued an amendatory order. On February

22, 2013, ComEd filed a notice of appeal. Accordingly, this court has jurisdiction pursuant to

Illinois Supreme Court Rule 335(a) governing direct review of administrative orders by the

appellate court. Ill. S. Ct. R. 335(a) (eff. Feb. 1, 1994).

¶4 BACKGROUND

¶5 Under the Public Utilities Act, article XVI (titled Electric Service Customer Choice and

Rate Relief Law of 1997) (Rate Relief Law) sought to restructure the electricity industry in

order to create competition and introduce customer choice in the supply of electricity. 220

ILCS 5/16-101A(b) (West 2012). Prior to the passage of this article, electric utilities like

ComEd both sold electricity to customers and delivered that electricity through its

distribution network. Article XVI separated the two components so that ARES could now

compete with one another to sell electricity to consumers. 220 ILCS 5/16-115 (West 2012).

Before an ARES can serve any retail customer, it must first obtain a certificate of service

authority from the Commission in accordance with section 16-115. As part of its

certification, subsection (d)(5) requires an ARES applicant to source some electricity from

clean coal facilities, and further provides that “the required sourcing of electricity generated

-3-

by clean coal facilities, other than the initial clean coal facility, 1 shall be limited to the

amount of electricity that can be procured or sourced at a price at or below the benchmarks

*** in accordance with item (1) of subsection (c) and items (1) and (5) of subsection (d) of

Section 1-75 of the Illinois Power Agency Act.” 220 ILCS 5/16-115(d)(5)(iii) (West 2012).

ComEd, however, remains responsible for delivering electricity to ARES customers over its

distribution network. 220 ILCS 5/16-108 (West 2012).

¶6 Article XVI also requires ComEd to continue supplying electricity to residential and

small commercial customers within their service territory who have not chosen an ARES and

who purchase power from the utility “under fixed-price bundled service tariffs.” 220 ILCS

5/16-111.5(a) (West 2012). The statute refers to these customers as “eligible retail

customers.” Id. To guide ComEd’s procurement of electricity, the General Assembly passed

the Illinois Power Agency Act (20 ILCS 3855/1-5(1) (West 2012)), which created the Illinois

Power Agency (IPA). The IPA has the powers and duties enumerated in the Illinois Power

Agency Act. 20 ILCS 3855/1-15(a) (West 2012).

¶7 The goal of the Illinois Power Agency Act is to protect “[t]he health, welfare, and

prosperity of all Illinois citizens” in the “provision of adequate, reliable, affordable, efficient,

and environmentally sustainable electric services at the lowest total cost over time.” 20 ILCS

3855/1-5(1) (West 2012). To accomplish this goal, the General Assembly declared it

“necessary to improve the process of procuring electricity to serve Illinois residents, to

promote investment in energy efficiency ***, and to support development of clean coal

technologies and renewable resources.” 20 ILCS 3855/1-5(4) (West 2012). The legislature

established that by January 1, 2025, “25% of the electricity used in the State shall be

generated by cost-effective clean coal facilities.” 20 ILCS 3855/1-75(d)(1) (West 2012). It

also determined that “[p]rocuring a diverse electricity supply portfolio will ensure the lowest

total cost over time for adequate, reliable, efficient, and environmentally sustainable electric

service.” 20 ILCS 3855/1-5(5) (West 2012).

¶8 Pursuant to the Illinois Power Agency Act, the Illinois Power Agency is tasked with

procuring electricity for ComEd and Ameren Illinois Company (Ameren).2 To this end, the

Illinois Power Agency develops annual electricity procurement plans for the utilities and

submits the plans for final approval by the Commission. 220 ILCS 5/16-111.5(b) (West

2012) (“[a] procurement plan shall be prepared for each electric utility consistent with the

applicable requirements of the Illinois Power Agency Act”). Relevant to this appeal, the

clean coal portfolio standard contained in the Illinois Power Agency Act states that the IPA’s

“procurement plans shall include electricity generated using clean coal.” 20 ILCS

3855/1-75(d) (West 2012).

¶9 On September 28, 2013, the Illinois Power Agency filed a proposed procurement plan

with the Commission. The plan required ComEd and ARES to enter into sourcing

agreements with FutureGen 2.0, a project of the FutureGen Industrial Alliance, Inc.

(FutureGen Alliance). The FutureGen Alliance is a nonprofit corporation “formed to create

1

The parties agree that an initial clean coal facility has never been established by the legislature and

therefore the statutory provisions dealing with the initial clean coal facility are not relevant in this

appeal.

2

Ameren is not a party to this consolidated appeal.

-4-

the world’s first coal-fueled, near-zero emissions electric power plant.” The FutureGen 2.0

project consists of the retrofitting of Ameren’s facility in Meredosia, Illinois, to utilize

clean-coal technology. The Illinois Power Agency determined that the utilities and ARES

should purchase the facility’s output in an amount consistent with their proportional share, or

in a “competitively neutral” manner.

¶ 10 The Commission found that, pursuant to section 1-75(d)(5) of the Illinois Power Agency

Act, it had the authority to compel both the utilities and ARES to enter into sourcing

agreements with retrofitted clean coal facilities approved by the Commission. However,

Commission staff expressed concern that, given the number of ARES involved

(approximately 70), requiring each ARES to enter into a sourcing agreement with FutureGen

2.0 would present an administrative burden.3 The staff suggested an alternate approach

whereby FutureGen 2.0 would contract only with ComEd and Ameren, and each utility

would purchase FutureGen 2.0 power for its own eligible retail customers as well as the retail

customers of ARES. The utilities would then recover the additional costs through a

competitively neutral charge assessed to ARES’ customers for their share of the output.

¶ 11 On December 19, 2012, the Commission issued its final order approving the Illinois

Power Agency’s procurement plan, but modified the plan to reflect the staff’s alternate

approach regarding sourcing agreements with FutureGen 2.0. It concluded that the staff’s

proposal was “quite reasonable in light of the administrative burden that would be placed on

FutureGen, the Commission, Staff and ARES if a separate sourcing agreement were required

for each and every ARES as well as ComEd and Ameren.” Illinois Power Agency, Ill. Com.

Comm’n Docket 12-0544, at 236 (Order Dec. 19, 2012). The Commission found that while

sections 1-75(d)(5) of the Illinois Power Agency Act and 16-115 of the Public Utilities Act

did not explicitly sanction the alternate approach, “the intent of the Legislature that all

customers equally bear the costs and benefits of the State’s clean coal portfolio standard is

consistent with the alternative proposal.” Id. Upon a motion for clarification, the Commission

entered an amendatory order on January 29, 2013, stating that under the alternate approach,

ComEd would be able to recover its costs incurred under the FutureGen 2.0 sourcing

agreement through a competitively neutral charge that is not a delivery services charge.

Illinois Power Agency, Ill. Com. Comm’n Docket 12-0544 (Amend. Order Jan. 29, 2013).

After denial of the petitions for rehearing filed on January 29, 2013, ComEd, ICEA, and IIEC

initiated this action for administrative review. This court consolidated the appeals.

¶ 12 ANALYSIS

¶ 13 Initially, we address a preliminary issue raised by the Commission. The Commission

contends that this court should disregard and strike the brief of Coalition of Energy Suppliers

(CES), and strike portions of ComEd’s brief in response to ICEA/IIEC’s appellant brief. It

argues that CES is an appellee, but CES’s brief attacks the Commission’s order. The

Commission contends that if CES seeks reversal or modification of the order, it must file its

own appeal or cross-appeal. The Commission also argues that this court should strike the

portion of ComEd’s response brief raising the dormant commerce clause argument, because

ComEd did not present the issue as a ground for error in its application for rehearing as

3

The majority of customers in ComEd’s service territory receive their electricity from ARES, not

ComEd.

-5-

required, nor did it raise the issue in its main brief. The striking of a brief, in whole or in part,

is a harsh sanction and is proper only in cases where the alleged violations interfere with or

preclude our review. In re Detention of Powell, 217 Ill. 2d 123, 132 (2005). This consolidated

appeal involves numerous parties presenting, and responding to, arguments on complex

issues regarding the regulation of the electricity industry. The fact that this court ordered a

specific briefing schedule, pursuant to an agreement by the parties, underscores the unique

nature of this appeal. The briefs before us sufficiently set forth the issues, and we find that

the alleged violations identified by the Commission do not preclude meaningful review of the

merits of this case. Therefore, in the exercise of our discretion, we deny the Commission’s

request to strike and will address the arguments briefed in this appeal. Id.

¶ 14 On appeal, ComEd and ICEA/IIEC challenge the Commission’s order. Courts give

substantial deference to the Commission’s decisions for it is an administrative body with

expertise in the area of public utilities, and thus is qualified to interpret highly technical

evidence. United Cities Gas Co. v. Illinois Commerce Comm’n, 163 Ill. 2d 1, 12 (1994). The

Commission’s findings are considered prima facie reasonable and the burden of proof is on

the appellant on all issues raised in the appeal. 220 ILCS 5/10-201(d) (West 2012). In

reviewing the Commission’s orders, a court is limited to determining whether (1) the

Commission acted within its authority; (2) it made adequate findings to support its decision;

(3) substantial evidence supports its decision; and (4) any constitutional rights were violated.

Commonwealth Edison Co. v. Illinois Commerce Comm’n, 322 Ill. App. 3d 846, 849 (2001).

¶ 15 ComEd and ICEA/IIEC contend that the Commission’s approval of the procurement

plan, which compels ComEd to enter into a sourcing agreement with FutureGen 2.0 on behalf

of ARES, exceeded its statutory authority. The scope of the Commission’s authority is a

question of law, which we review de novo. City of Chicago v. Illinois Commerce Comm’n,

294 Ill. App. 3d 129, 134-35 (1997).

¶ 16 An administrative agency derives its authority to act solely from the statute creating the

agency. Resource Technology Corp. v. Commonwealth Edison Co., 343 Ill. App. 3d 36, 44

(2003). Therefore, the issue before this court is one involving statutory interpretation. In

interpreting a statute, a court’s primary objective is to ascertain and give effect to legislative

intent as indicated by the plain and ordinary meaning of the statutory language.

Commonwealth Edison Co. v. Illinois Commerce Comm’n, 328 Ill. App. 3d 937, 942 (2002).

However, courts appreciate an agency’s experience and expertise in a given area and

therefore will give substantial deference to its interpretation of an ambiguous statute it

administers and enforces. Illinois Consolidated Telephone Co. v. Illinois Commerce Comm’n,

95 Ill. 2d 142, 152-53 (1983). While not binding on the courts, an agency’s interpretations

are an informed source for ascertaining the legislature’s intent in enacting the statute. Id. at

153.

¶ 17 In construing a statute, courts must “ascertain and give effect to the overall intent of the

drafters.” Knolls Condominium Ass’n v. Harms, 202 Ill. 2d 450, 458 (2002). The Rate Relief

Law of the Public Utilities Act sought to restructure the electricity industry so as to create

competition and introduce customer choice in the supply of electricity. 220 ILCS

5/16-101A(b) (West 2012). Accordingly, section 16-111.5(a) of the Public Utilities Act sets

forth ComEd’s procurement of electricity for its customers. It states that an electric utility

“shall procure power and energy for its eligible retail customers in accordance with the

applicable provisions set forth in Section 1-75 of the Illinois Power Agency Act and this

-6-

Section.” 220 ILCS 5/16-111.5(a) (West 2012). “Those customers that are excluded from the

definition of ‘eligible retail customers’ shall not be included in the procurement plan load

requirements ***.” Id. The Rate Relief Law further provides that utilities shall procure power

pursuant to procurement plans approved by the Commission. 220 ILCS 5/16-111.5(b) (West

2012).

¶ 18 Section 1-75 of the Illinois Power Agency Act grants the Illinois Power Agency authority

to “develop procurement plans and conduct competitive procurement processes in

accordance with the requirements of Section 16-111.5 of the Public Utilities Act for the

eligible retail customers of electric utilities.” 20 ILCS 3855/1-75(a) (West 2012). It also sets

forth specific provisions relating to the procurement plan requirements. Relevant to this

appeal, section 1-75(d)(1) provides that such procurement plans “shall include electricity

generated using clean coal.” 20 ILCS 3855/1-75(d)(1) (West 2012). This section is referred

to as the clean coal portfolio standard.

¶ 19 Section 1-75(d)(5) provides that the Illinois Power Agency shall also “consider sourcing

agreements covering electricity generated by power plants” previously owned by Illinois

utilities “that have been or will be converted into clean coal facilities.” 20 ILCS

3855/1-75(d)(5) (West 2012). As part of the procurement planning process, owners of these

retrofitted facilities “may propose to the [Illinois Power] Agency sourcing agreements with

utilities and alternative retail electric suppliers required to comply with subsection (d) of this

Section and item (5) of subsection (d) of Section 16-115 of the Public Utilities Act.” Id.

¶ 20 The legislature included a corresponding clean coal electricity requirement in the

certification of ARES. Before servicing any customer in Illinois, an ARES “must obtain a

certificate of service authority from the Commission in accordance with this Section.” 220

ILCS 5/16-115(a) (West 2012). As part of the certification process, an ARES applicant must

source some of its electricity from clean coal facilities including retrofitted facilities. 220

ILCS 5/16-115(d)(5)(iii) (West 2012). This section provides:

“(d) The Commission shall grant the application for a certificate of service

authority if it makes the findings set forth in this subsection based on the verified

application and such other information as the applicant may submit:

***

(5) That the applicant will procure renewable energy resources in accordance

with Section 16-115D of this Act, and will source electricity from clean coal

facilities, as defined in Section 1-10 of the Illinois Power Agency Act, in amounts

at least equal to the percentages set forth in subsections (c) and (d) of Section 1-75

of the Illinois Power Agency Act. For purposes of this Section:

***

(iii) the required sourcing of electricity generated by clean coal facilities,

other than the initial clean coal facility, shall be limited to the amount of

electricity that can be procured or sourced at a price at or below the benchmarks

approved by the Commission each year in accordance with item (1) of

subsection (c) and items (1) and (5) of subsection (d) of Section 1-75 of the

Illinois Power Agency Act[.]” 220 ILCS 5/16-115(d)(5)(iii) (West 2012).

¶ 21 Appellants agree that these statutory provisions allow the Illinois Power Agency to

develop a procurement plan that compels ComEd to enter a sourcing agreement with a

retrofitted clean coal facility on behalf of ComEd’s eligible retail customers. However, they

-7-

argue for a strict reading of the statutory provisions. ComEd and ICEA/IIEC contend that the

plain words of the procurement plan provisions of the Rate Relief Law and the Illinois Power

Agency Act refer only to ComEd’s eligible retail customers, which by definition excludes

ARES customers. Therefore, the IPA has no power to propose, and the Commission has no

power to approve, procurement plans requiring ComEd to procure electricity for ARES

customers. At most, the Commission can compel each ARES to enter into a sourcing

agreement with FutureGen 2.0, but it cannot compel ComEd to enter such agreements on

behalf of ARES.

¶ 22 We disagree. While the general statutory provisions relating to procurement plans for

utilities refer only to ComEd’s eligible retail customers, the specific provisions setting forth

ComEd’s required procurement of electricity from retrofitted clean coal sources make no

mention of eligible retail customers. We will not place undue emphasis on the statutory

construction rule that the inclusion of one term necessarily excludes other possible terms. See

Knolls, 202 Ill. 2d at 459. Instead, courts must construe statutes relating to the same subject

with reference to one another in order to give effect to all the provisions if possible. Henrich

v. Libertyville High School, 186 Ill. 2d 381, 392 (1998). If it appears a conflict exists between

the statutes, courts will try to construe the provisions harmoniously. United Citizens of

Chicago & Illinois v. Coalition to Let the People Decide in 1989, 125 Ill. 2d 332, 339 (1988).

The intent of the legislature is most significant. Id. at 338-39.

¶ 23 The legislature clearly found the use of electricity generated by clean coal facilities

important for both utilities and ARES. Both parties must utilize such electricity in their

supply to customers, and when the electricity comes from retrofitted clean coal facilities,

procurement by utilities and ARES must meet the same benchmarks set forth in section

1-75(d)(5). This legislative intent is reflected in the clean coal portfolio standard which, by

its terms, grants the Illinois Power Agency and the Commission more authority in the

procurement of electricity from such sources. See Knolls, 202 Ill. 2d at 459 (where both a

general statutory provision and a specific statutory provision address the same subject, “the

specific provision controls and should be applied”).

¶ 24 The question is whether these provisions authorize the Illinois Power Agency to compel

ARES to enter into a sourcing agreement with FutureGen 2.0. ICEA/IIEC argue that the

statutes grant no such authority. The statutory procurement planning process, after all, is

aimed at the utilities and not at ARES. Also, the statutes do not expressly state that ARES

can be compelled to enter into a sourcing agreement with a retrofitted clean coal facility.

¶ 25 However, as part of the certification process ARES must source electricity from clean

coal facilities in amounts at least equal to those set forth in section 1-75(c)(1) and (d)(5) of

the Illinois Power Agency Act. Subsection (d)(5) provides that pursuant to the procurement

planning process, owners of qualified retrofitted clean coal facilities “may propose to the

[Illinois Power] Agency sourcing agreements with utilities and alternative retail electric

suppliers required to comply with” subsection (d) and section 16-115(d)(5) of the Public

Utilities Act. (Emphasis added.) 20 ILCS 3855/1-75(d)(5) (West 2012). The statute clearly

contemplates, at the very least, that the Illinois Power Agency can consider such sourcing

agreements with ARES in the procurement planning process. If the Illinois Power Agency

can consider such agreements, it is reasonable to presume that the Illinois Power Agency can

compel ARES to enter into sourcing agreements with such facilities as part of the

procurement planning process if doing so furthers statutory goals. The Commission contends

-8-

that it has such authority where compelling ARES to enter into sourcing agreements with

retrofitted clean coal facilities furthers the goals of supporting the development of clean coal

technologies, and providing electricity at the lowest total cost. We acknowledge the

Commission’s experience and expertise in this area and give substantial deference to its

interpretation of an ambiguous statute it administers and enforces. Illinois Consolidated

Telephone Co., 95 Ill. 2d at 152-53.

¶ 26 The Commission, however, adopted the alternate approach suggested by its staff. The

alternate approach requires only ComEd and Ameren to enter into sourcing agreements with

FutureGen 2.0 to purchase a pro rata share of the output based on the amount of electricity

the utilities deliver to its distribution customers (including ARES customers). ComEd and

Ameren then could recover the costs associated with procurement through a competitively

neutral charge assessed to all of their retail distribution customers (including ARES

customers). The Commission reasoned that this approach was a cost-effective alternative to

the burdensome process of administering and monitoring approximately 70 individual

sourcing agreements.

¶ 27 We find that the Commission acted within its statutory authority. Pursuant to the Rate

Relief Law of the Public Utilities Act and the Illinois Power Agency Act, both the utilities

and ARES must source some of their electricity from clean coal or retrofitted facilities. As

discussed above, the Commission has the authority to compel both the utilities and ARES to

enter into sourcing agreements with retrofitted clean coal facilities as part of the procurement

planning process. Viewed within this framework, the Commission’s order approving a

procurement plan requiring ComEd to enter a sourcing agreement with FutureGen 2.0 on

behalf of ARES customers, while not explicitly condoned by statute, is within its “inherent

authority and wide latitude to adopt regulations or policies reasonably necessary to perform

the agency’s statutory dut[y].” (Internal quotation marks omitted.) Resource Technology

Corp. v. Commonwealth Edison Co., 343 Ill. App. 3d 36, 44 (2003).

¶ 28 ComEd argues, however, that even if the Commission has authority to approve the

alternate approach, it failed to support its finding with substantial evidence that the approach

was necessary to avoid administrative burdens on the parties. Upon review, courts consider

the Commission’s factual findings prima facie true and its orders prima facie reasonable.

United Cities Gas Co., 163 Ill. 2d at 11. Furthermore, the Commission need not provide

findings on each evidentiary claim; it is sufficient if the findings are specific enough for

courts to review the order. Commonwealth Edison Co. v. Illinois Commerce Comm’n, 2013 IL

App (2d) 120334, ¶ 38. Substantial evidence is evidence that a reasoning mind finds

sufficient to support a finding. Central Illinois Public Service Co. v. Illinois Commerce

Comm’n, 268 Ill. App. 3d 471, 479 (1994). Substantial evidence is more than a mere

scintilla, but need not rise to the level of a preponderance of the evidence. Commonwealth

Edison Co., 2013 IL App (2d) 120334, ¶ 38. A party who argues that the Commission’s

findings were not supported by substantial evidence must show more than the mere fact that

the evidence supports a different conclusion. Instead, the party must show that the opposite

conclusion was clearly evident. Abbott Laboratories, Inc. v. Illinois Commerce Comm’n, 289

Ill. App. 3d 705, 714 (1997).

¶ 29 The parties agreed to proceed before the Commission without hearings and addressed any

issues by filing verified responses to comments and objections, and by filing replies. The

Commission’s staff contended that requiring the Illinois Power Agency to negotiate separate

-9-

sourcing agreements with an estimated 70 separate ARES, as well as with ComEd and

Ameren, would be burdensome. Specifically, the staff determined that the utilities would

bear the costs of providing FutureGen with billing records for each customer served by

ARES, ARES and FutureGen would bear costs associated with entering into and managing

70 additional contracts, and the staff would need to devote extra time to review all of the

annual reports of compliance with the clean coal portfolio standard by each party and to

ensure compliance with the standard by each ARES. In support of its position, the staff

presented affidavits of the following staff members: Diana Hathhorn (accountant in the

Commission’s financial analysis division), Jennifer L. Hinman (economic analyst in the

Commission’s policy division), Rochelle Phipps (senior financial analyst in the financial

analysis division), and Jim Zolnierek (director of the policy division). The affidavits stated

that the witnesses had personal knowledge of the facts and matters discussed in the response

and objections, and to the best of their knowledge, information, and belief, the facts and

nonlegal opinions expressed are accurate and true.

¶ 30 ComEd, however, complains that the Commission did not support its findings with

substantial evidence because it “did not attempt to quantify or analyze in any systematic way

the burdens” on the parties, nor did it adequately consider the burdens placed on ComEd.

ComEd provides no authority for its position that the Commission must provide quantifiable

findings on each evidentiary claim. It is self-evident that the administration of several

sourcing agreements is overall less burdensome than the administration and monitoring of

more than 70 agreements. Affidavits from Commission staff support that conclusion. We find

the evidence sufficient to support the Commission’s decision. Furthermore, ComEd does not

show that the opposite conclusion is clearly evident. It argues only that the Commission

made no finding that the administrative burdens avoided by the alternate approach outweigh

the administrative burdens the approach imposes on ComEd.

¶ 31 Pursuant to the Public Utilities Act, the Commission “should act to promote the

development of an effectively competitive electricity market that operates efficiently and is

equitable to all consumers.” 220 ILCS 5/16-101A(d) (West 2012). By adopting the alternate

approach, which presented a more streamlined administration of the clean coal portfolio

standard required of the utilities and ARES, the Commission properly exercised its authority

to formulate reasonable means of achieving legislative objectives. We find the Commission’s

order approving the alternate approach lawful and supported by substantial evidence.

¶ 32 ICEA/IIEC make an additional argument that the Commission has no authority to impose

a competitively neutral charge, that is not a delivery service charge, upon ARES customers.

ComEd disagrees, arguing that if the Commission has authority to compel utilities to procure

electricity from retrofitted clean coal facilities for ARES customers, ComEd should recover

the costs associated with that procurement. As discussed above, the Commission’s authority

to compel ComEd to enter into a sourcing agreement with FutureGen 2.0 derives from the

Illinois Power Agency’s authority to develop a procurement plan for utilities that comply

with the clean coal portfolio standard of the Illinois Power Agency Act. See 20 ILCS

3855/1-75(d) (West 2012). Subsection (d)(6) states that “[c]osts incurred under this

subsection (d) or pursuant to a contract entered into under this subsection (d) shall be deemed

prudently incurred and reasonable in amount and the electric utility shall be entitled to full

cost recovery pursuant to the tariffs filed with the Commission.” 20 ILCS 3855/1-75(d)(6)

(West 2012). Allowing ComEd to recover these costs from ARES customers further

- 10 -

promotes the legislature’s intent to allocate the costs of supplying utility services “to those

who cause the costs to be incurred.” 220 ILCS 5/1-102(d)(iii) (West 2012). Therefore,

according to the plain terms of the statute, ComEd is entitled to recover from ARES

customers its costs of entering into the sourcing agreement with FutureGen 2.0 on ARES’

behalf.

¶ 33 ComEd and ICEA/IIEC also argue that the Commission’s order violates the dormant

commerce clause and is therefore unconstitutional. This negative component of the

commerce clause prohibits states from enacting regulatory measures designed to benefit

in-state interests at the expense of out-of-state competitors. New Energy Co. of Indiana v.

Limbach, 486 U.S. 269, 273-74 (1988). In other words, “state statutes that clearly

discriminate against interstate commerce are routinely struck down [citations], unless the

discrimination is demonstrably justified by a valid factor unrelated to economic

protectionism.” Id. at 274.

¶ 34 Appellants argue that the Commission’s order is unconstitutional because it requires

ComEd to enter into a sourcing agreement for clean-coal energy with FutureGen 2.0, an

Illinois facility, effectively excluding from consideration out-of-state clean electric sources.

They allege that the order also has a discriminatory effect because 70% of the rate cap

imposed on ComEd for clean coal electricity is devoted to FutureGen 2.0’s output, “leaving

little room for any [other competitors] to place their clean coal electricity on the Illinois

market.” The order thus prevents customers from obtaining less costly clean coal electricity

procured from out-of-state sources, in violation of the dormant commerce clause.

¶ 35 Before addressing these constitutional arguments on the merits, however, we first

determine whether ICEA/IIEC and ComEd have standing to challenge the constitutionality of

the statute. The doctrine of standing “ensure[s] that courts are deciding actual, specific

controversies, and not abstract questions or moot issues.” In re Marriage of Rodriguez, 131

Ill. 2d 273, 279-80 (1989). Generally, courts will not consider a constitutional challenge to a

statutory provision unless the party challenging it is directly affected by the provision. In re

M.I., 2013 IL 113776, ¶ 32. In other words, the party challenging the provision “must be

directly or materially affected by the attacked provision and must be in immediate danger of

sustaining a direct injury” from the statute’s enforcement. Id. Without evidence of facts

showing such injury, a party does not have standing to challenge the statutory provision on

the ground that it would be unconstitutional if applied to third parties in a hypothetical case.

Id.

¶ 36 The Commission argues that ICEA/IIEC and ComEd have not shown “any evidence of

discrimination on any similarly situated clean coal facility.” On the issue of standing to

challenge this provision, however, the relevant question is whether ICEA/IIEC and/or

ComEd is “directly or materially affected by the attacked provision” and “in immediate

danger of sustaining a direct injury” from enforcement of the provision. See In re M.I., 2013

IL 113776, ¶ 32. In their briefs, both parties acknowledge that the injured parties directly

affected by the provision are out-of-state facilities that would compete against FutureGen 2.0

in the production of clean coal electricity. See also Alliance for Clean Coal v. Miller, 44 F.3d

591, 594 (7th Cir. 1995) (for the purpose of standing to challenge a statute that subsidized the

use of Illinois coal over the use of western coal, the relevant injury is the inability “to

compete on an equal footing in interstate commerce”). Neither ICEA/IIEC or ComEd claim

an interest in producing clean coal electricity. Furthermore, neither party has shown a direct,

- 11 -

material injury that would result from enforcement of the provision. In fact, the Commission

has not had the opportunity to enforce the provision since the FutureGen 2.0 facility is not

yet operable. Therefore, we find that ICEA/IIEC and ComEd do not have standing to

challenge the constitutionality of the provision at this time and, accordingly, we decline to

address the issue here.

¶ 37 For the foregoing reasons, we affirm the order of the Commission.

¶ 38 Affirmed.

¶ 39 JUSTICE PUCINSKI, dissenting.

¶ 40 With great respect, I dissent from the opinion of the majority.

¶ 41 This is a one-word/one-phrase case. Some one-word cases require the court to determine

what the legislature meant by a word that is undefined. Local Union Nos. 15, 51, & 702 v.

Illinois Commerce Comm’n, 331 Ill. App. 3d 607 (5th Dist. 2002), is a good example. There

the court, looking at the Public Utilities Act, had to decide whether the word “if” meant: “ ‘in

the event that’ ” or on the condition that. Id. at 614-15. Either use led to dramatically

different results. More recently, and more famously, the court has been required to decide

what the words “ ‘reside in’ ” mean in the Illinois Municipal Code and the Election Code.

Maksym v. Board of Election Commissioners, 242 Ill. 2d 303, 324 (2011). Some other

one-word cases call on us to decide what a missing word means. That is, whether we should

insert it, as though it was an oversight by the legislature to have left it out, or leave the

language of the statute as written, and consider that the legislature had a purpose in leaving

the word out when they passed it.

¶ 42 Here the statute in question is the Illinois Power Agency Act (20 ILCS 3855/1-75(d)(5)

(West 2012)):

“(5) [Sentence 1] Re-powering and retrofitting coal-fired power plants previously

owned by Illinois utilities to qualify as clean coal facilities. [Sentence 2] During the

2009 procurement planning process and thereafter, the Agency and the Commission

shall consider sourcing agreements covering electricity generated by power plants

that were previously owned by Illinois utilities and that have been or will be

converted into clean coal facilities, as defined by Section 1-10 of this Act. [Sentence

3] Pursuant to such procurement planning process, the owners of such facilities may

propose to the Agency sourcing agreements with utilities and alternative retail

electric suppliers required to comply with subsection (d) of this Section and item (5)

of subsection (d) of Section 16-115 of the Public Utilities Act, covering electricity

generated by such facilities. [Sentence 4] In the case of sourcing agreements that are

power purchase agreements, the contract price for electricity sales shall be established

on a cost of service basis. [Sentence 5] In the case of sourcing agreements that are

contracts for differences, the contract price from which the reference price is

subtracted shall be established on a cost of service basis. [Sentence 6] The Agency

and the Commission may approve any such utility sourcing agreements that do not

exceed cost-based benchmarks developed by the procurement administrator, in

consultation with the Commission staff, Agency staff and the procurement monitor,

subject to Commission review and approval.” (Emphases added.)

- 12 -

¶ 43 Under the plain language of sentence 2 above it is clear that FutureGen 2.0 qualifies

under this section since it is a retrofitted coal fired power plant previously owned by an

Illinois utility, in this case Ameren. And, with all the federal money (about $1.5 billion)

coming into the state to develop FutureGen 2.0’s new technology, along with the dedicated

property, equipment and plant in Meredosia, Illinois, and the pipeline and

storage/sequestration facility for the carbon dioxide at the Mt. Sinai formation in Morgan

County, it is clear that the state’s policy makers have decided that FutureGen 2.0 qualifies–at

least in theory–as a clean coal facility as defined by section 1-10 of the Illinois Power

Agency Act. Of course it is not up and running yet and will not be until 2017, and then the

energy it produces will be more expensive than other clean coal facility energy, because our

legislature has also decided that “all coal used by a clean coal facility shall have high volatile

bituminous rank and greater than 1.7 pounds of sulfur per million btu content,” a restriction

which favors Illinois coal. 20 ILCS 3855/1-10 (West 2012). Further, the record and

statements at oral argument make it clear that FutureGen 2.0 cannot even continue its

development without the sourcing agreements at issue in place because without a guaranteed

revenue stream–these sourcing agreements–it cannot attract future investment in the project.

¶ 44 Sentence 3 mandates the Illinois Power Agency and the Commission “shall” consider

sourcing agreements from such plants, and since FutureGen 2.0 is the only one like it, it is

pretty clear that the Illinois Power Agency and the Commission shall at least give sourcing

agreements with FutureGen 2.0 some consideration, but note the statute does not require that

the sourcing agreement be accepted, just that it shall be considered, the kind of waffling that

leaves all the discretion to the Illinois Power Agency and the Commission, and neatly takes

the legislature off the hook in case someone complains that just maybe this is a restraint of

trade issue.

¶ 45 Sentence 4 gives the owners of the facilities, in this case FutureGen 2.0, the opportunity

to propose sourcing agreements to the Illinois Power Agency for both utilities and ARES, but

only the opportunity to propose the agreements, not any guarantee that the sourcing

agreements must be accepted.

¶ 46 The rub comes at sentence 6, which says the “Agency and the Commission may approve

any such utility sourcing agreements” but totally ignores whether the Illinois Power Agency

and the Commission may also approve such sourcing agreements for ARES. (Emphasis

added.) 20 ILCS 3855/1-75(d)(5) (West 2012).

¶ 47 The FutureGen 2.0 and Commission briefs want us to insert the phrase: “and alternative

retail electric suppliers” to sentence 6, so that it would read: the “Agency and the

Commission may approve such utility and alternative retail electric suppliers sourcing

agreements.” (Emphasis added.)

¶ 48 Clearly the Illinois Power Agency staff thinks so too, or they would not have proposed

the FutureGen 2.0 sourcing agreements for ARES, but adding those words has a complicated

result in that it frustrates the reason the legislature passed another statute, the Rate Relief

Law, which at section 16-101A(d) calls on the Commission to “act to promote the

development of an effectively competitive electricity market that operates efficiently and is

equitable to all consumers” thereby committing this state to a system that is both equitable

and competitive. 220 ILCS 5/16-101A(d) (West 2012).

¶ 49 While it is true that the plan approved by the Commission is equitable to all customers in

the sense that every customer of every electricity supplier in Illinois will share in the higher

- 13 -

cost of the FutureGen 2.0 electricity, so the burden is spread around, that is because only

clean coal facilities that burn the kind of coal we have in abundance in Illinois qualify as

clean coal suppliers to either utilities or ARES. Coincidentally, FutureGen 2.0 is the only one

in existence anywhere identified in the record that burns that kind of coal.

¶ 50 However, it is also true that the FutureGen 2.0 energy will be more expensive than other

clean coal facility electricity that is generated without the particular problems associated with

Illinois coal thus frustrating the competitive purpose of the Customer Choice Act.

¶ 51 All of this is further complicated by the approval by the Commission of the Illinois

Power Agency’s staff recommendation to require ComEd and Ameren (not a party to this

appeal) to actually do the sourcing agreements on behalf of all ARES. ComEd reasonably

wonders under what authority the Commission requires it, a regulated utility, to enter into

contracts on behalf of private sector ARES, even though the Commission has neatly provided

a way for ComEd to recoup its costs of doing so.

¶ 52 The Commission says it can do this because it has the authority to do those things

necessary to implement its mandates. However, the Commission has not provided any statute

to this court demonstrating that there is a mandate, that it has the authority, or that the state

has a public policy to guarantee 100% of FutureGen 2.0’s output for the next 20 years in

noncompetitive contracts, let alone by ComEd for the benefit of ARES customers.

¶ 53 I would reverse the order of the Commission and let the legislature work to make sure

that all the interrelated, overlapping and conflicting laws and public policies are reconciled.

¶ 54 As an alternative, and as suggested by the Illinois Power Agency, the Commission should

at the very least engage in its rulemaking process to fully develop the set of rules that would

permit this level of regulatory agency sleight-of-hand.

- 14 -