Opinion

Aggressive Mechanical, Inc. v. Ohio School Facilities Comm.

  • 2012 Ohio 6332
Court
Ohio Court of Claims
Filed
Sep 18, 2012
Status
Published
On the bench
Shaver
Cited by
1 cases
Authority
More cited than 44.7%

The opinion

[Cite as Aggressive Mechanical, Inc. v. Ohio School Facilities Comm., 2012-Ohio-6332.]

Court of Claims of Ohio

The Ohio Judicial Center

65 South Front Street, Third Floor

Columbus, OH 43215

614.387.9800 or 1.800.824.8263

www.cco.state.oh.us

AGGRESSIVE MECHANICAL, INC.

Plaintiff

v.

OHIO SCHOOL FACILITIES COMMISSION

Defendant

Case No. 2010-12745

Judge Joseph T. Clark

Magistrate Holly True Shaver

DECISION OF THE MAGISTRATE

{¶ 1} Plaintiff brought this action alleging breach of contract. The issues of

liability and damages were bifurcated and the case proceeded to trial on the issue of

liability.

{¶ 2} On May 2, 2007, plaintiff entered into a contract with defendant for the

heating, ventilation, and air-conditioning (HVAC) work of a public improvement project

known as Southwood Elementary School. The project called for multiple prime

contractors and consisted of both the renovation of an existing building and the

construction of a new, 20,000 square foot addition. The total HVAC contract price was

$1,767,000. The work was to be completed within 532 days after plaintiff’s receipt of

the notice to proceed, unless an extension of time were granted. The construction

manager, Smoot Elford Resources (SER) was responsible for monitoring the project

schedule for defendant.

{¶ 3} On June 18, 2007, the notice to proceed was issued, which resulted in a

contract end date of November 14, 2008. The work was to begin on the third floor of

the existing building and then flow in a logical sequence down through the lower floors

Case No. 2010-12745 -2- DECISION

and out into the new building as work was completed by predecessor trades. However,

from the outset, the project experienced delays due to problems with the design. An

updated schedule was issued on May 14, 2008, and a recovery schedule was issued on

September 11, 2008.

{¶ 4} On October 2, 2008, SER issued Construction Bulletin 63 (CB 63), which

extended the contract 110 working days (159 calendar days) to April 22, 2009.

(Defendant’s Exhibit DD.) Prior to the issuance of CB 63, SER had advised the

contractors that a bulletin would be issued to extend the contract and invited the

contractors to submit pricing for additional costs related to the extension. In response,

plaintiff submitted a pricing proposal to SER in the amount of $107,976.15.

(Defendant’s Exhibit F.) On December 18, 2008, Peggy Murphy, Project Manager for

SER, issued a letter to plaintiff’s owner, Kevin Hall, wherein she rejected plaintiff’s

pricing proposal. SER explained that plaintiff’s method of calculation was not an

acceptable means of determining costs for the extension of contract time per the

change order pricing guidelines set forth in Article 7.6 of the contract’s General

Conditions (GC). SER directed plaintiff to revise and resubmit its costs associated with

CB 63. (Defendant’s Exhibit H.) On January 22, 2009, plaintiff submitted a revised

proposal in the amount of $81,703.12. (Defendant’s Exhibit F2.)

{¶ 5} On February 13, 2009, SER rejected plaintiff’s revised pricing. SER

referred plaintiff to GC Sections 7.6.6 and 7.6.7 for allowable costs. In an email from

Murphy, she stated: “SER and the Owner agree that there are probable costs due for

the extension of time on this project, but they must be within the structure of the contract

and properly documented.” (Defendant’s Exhibit I.)

{¶ 6} On another matter, on April 21, 2009, Keith Davis, SER’s on-site

superintendent, sent Hall an email requesting something in writing that stated that

plaintiff’s work would not be completed by the April 22, 2009 finish date. Davis advised

Hall to list “all items for which your work is being held up by other trades. This is

Case No. 2010-12745 -3- DECISION

important to identify all items that will not be completed by the scheduled finish date and

a reason for the item’s status.” (Defendant’s Exhibit K.) In response, Hall sent the

following email: “This is to notify that Aggressive [M]echanical’s work on the southwood

elem project will not be complete by the April 22 2009 finish date due to change order

work[.] We will be working on bulletin 82#, bulletin 79#, bulletin 75#, this work should

be completed by 5-5-09 we will also have a little control and balance work to finish.” Id.

{¶ 7} On July 17, 2009, SER sent plaintiff a letter wherein SER adjusted plaintiff’s

figures and issued a proposed change order for CB 63 in the amount of $13,879.20.

(Defendant’s Exhibit L.) Plaintiff refused to sign the proposed change order. On July

30, 2009, Joe Studer, Project Engineer for SER, sent plaintiff an email confirming

plaintiff’s rejection of SER’s proposed change order, wherein he stated: “The change

order previously sent will not be executed and I will delete it from our system. I will

arrange to have a field level Article 8 meeting at SER’s office, just let me know when

works best for you.” (Defendant’s Exhibit Z2.)

{¶ 8} After Studer’s email, no correspondence regarding CB 63 occurred between

the parties until November 24, 2009, when plaintiff sent SER a letter requesting an

Article 8 hearing on its CB 63 claim in the amount of $81,703.12. In the letter, plaintiff

notified SER of an additional claim for an extension of time from April 22 to August 3,

2009 and related costs for that time period in the amount of $75,605.53. (Defendant’s

Exhibit M.) The itemized costs for the CB 63 claim were based on a time period of 110

days and included a daily cost for punch list items and close out, a 10 percent general

overhead charge for those two items, a profit of five percent of that total amount, a

monthly cost for attending progress meetings, a monthly charge for “gangbox and

tools,” a daily cost for extended supervision, a $42,000 charge for demobilization and

remobilization, and a charge for bond and insurance. The itemized costs for the second

claim included the same categories as the CB 63 claim but were based on a time period

of 103 calendar days. Id.

Case No. 2010-12745 -4- DECISION

{¶ 9} On December 16, 2009, SER sent plaintiff a letter addressing plaintiff’s two

claims separately. First, with regard to the request for an equitable adjustment as a

result of CB 63, SER advised plaintiff to follow the specific requirements set forth in GC

Article 8. Murphy stated: “Please understand, that while the time constraints outlined [in

Article 8 of the contract] have been grossly surpassed, the Construction Manager, the

Architect and the Co-Ownership Team will consider your claim if properly documented

and supported.” (Defendant’s Exhibit N.) Second, with regard to the claim for an

extension of time and related costs, SER also advised plaintiff to review the

requirements as set forth in Article 8. Murphy stated: “Without a clear and substantiated

claim of the damages being sought, your request cannot realistically be evaluated.

Please be aware that to date, other than a very brief email sent exclusively to our on-

site superintendent on April 22, 2009, the Project has received no other written

communication regarding this claim and presently, Aggressive Mechanical still has

outstanding Contract Work which the completion of is in no way being impeded by the

Project.” Id.

{¶ 10} On March 1, 2010, plaintiff filed two Article 8 claims with SER: one

regarding its rejected CB 63 pricing and the other regarding the extension of time

referred to in its November 24, 2009 letter. In both claims, plaintiff provided the

following language to correspond with GC Section 8.1.2.2: “The above extension of time

is due to many changes in the contract documents, changes in work and delays in work

caused by design issues and the very extensive time that was taken in resolving job

issues, resulting in the very slow progress of the job. We have provided estimate work

sheets for our claim of time extension. We have estimated our claim from our approved

schedule of values like we have done other Columbus Public School jobs. We used this

same format for Burroughs Elementary School, etc. which was approved by SER and

CPS. It is our hope and intent, that this issue can be resolved at the first step in the

dispute procedure. We are convinced that the extension of time in dispute is not our

Case No. 2010-12745 -5- DECISION

responsibility to burden the cost. Aggressive supplied the man power and equipment to

perform our work by the original completion date. Therefore a request of contract

adjustment is appropriate.” (Defendant’s Exhibits O and O2.)

{¶ 11} On March 15, 2010, SER held a preliminary Article 8 meeting to review

plaintiff’s claims. At the meeting, SER requested that plaintiff provide revised pricing to

include budgeted costs versus actual costs on the project. (Defendant’s Exhibit Q). On

March 17, 2010, SER sent a letter to Hall stating that the first field level Article 8 hearing

was set for March 23, 2010.1 (Defendant’s Exhibit R.) Plaintiff responded to SER’s

request for revised pricing and submitted its actual costs versus its budgeted costs for

the project. (Defendant’s Exhibits T and U.) On March 30, 2010, defendant and SER

held a field level Article 8 meeting with plaintiff to further review plaintiff’s claims based

on the newly submitted pricing. After the March 30, 2010 meeting, SER did not ask

plaintiff for any additional information.

{¶ 12} On May 6, 2010, Thomas Sisterhen, Senior Project Manager with SER,

issued a letter to plaintiff wherein he stated that in response to the field level Article 8

hearing, SER could not recommend a settlement. SER rejected both claims on the

basis of insufficient documentation. Sisterhen also stated that the two Article 8 claims

had not been submitted separately as SER had requested. Sisterhen stated, in relevant

part: “As we discussed, the documentation presented by Aggressive in support of your

response to the extension of time directed by Bulletin 63 is tainted with an additional

claim for costs reported to have been sustained for added manpower and inefficiencies

experienced by the Project. The additional ‘claim’ and the response to Bulletin 63 are

two distinct and separate items that must be supported as such. We also discussed our

concern that the back-up documentation that has been submitted is not sufficient in

either application.

1

At trial, the parties stipulated that the date of the letter was March 17, 2010, not 2009.

Case No. 2010-12745 -6- DECISION

{¶ 13} “This completes the job site dispute resolution procedure of General

Conditions Article 8.2. You are encouraged to review your options as outlined in Article

8.3 and 8.4.”2 (Defendant’s Exhibit W.) Plaintiff did not file an appeal to the

commission and the school district board as set forth in GC Section 8.3, but rather filed

its complaint in this court on December 13, 2010.

{¶ 14} Plaintiff asserts that defendant breached the contract when it failed to

compensate plaintiff for costs incurred as a result of delays on the project that were

caused by the architect and owner. Plaintiff also asserts that defendant owes it

damages for unpaid base contract work performed, along with a claim for unpaid

retainage. Defendant counters that plaintiff breached the contract when it failed to

follow the mandates of GC Articles 6, 7, and 8. Defendant also argues that the court

lacks jurisdiction over plaintiff’s claims in that it failed to exhaust its administrative

remedies before filing suit.

EXHAUSTION OF REMEDIES

{¶ 15} At the close of plaintiff’s case, defendant moved the court to dismiss this

action pursuant to Civ.R. 41(B)(2) on the ground that upon the facts and the law, plaintiff

had shown no right to relief. Defendant argued that the court lacked subject matter

2

GC Section 8.3 states:

“APPEAL TO COMMISSION AND SCHOOL DISTRICT BOARD

“8.3 .1 The Contractor may appeal the recommendation of the Construction Manager about a

Change Order by providing written notice to the Commission and the School District Board within 30 days

of the date of the Construction Manager’s recommendation.

“8.3.2 The Commission and the School District Board shall, within 30 days of receipt of the

Contractor’s notice, schedule a meeting in an effort to resolve the dispute or render a decision on the

dispute, unless an agreement is made between the Contractor, the School District Board, and the

Commission to extend such time limit. The purpose of the meeting shall be to settle the issues in dispute.

Chapter 119, ORC, shall not be applicable to any such meeting.

“8.3.3 The Commission and the School District Board shall, within 60 days of any meeting

scheduled pursuant to paragraph GC 8.3 .1, render a decision on the dispute, unless an agreement is

made between the Contractor, the Commission, and the School District Board to extend such time limit.

“8.3.4 The decision of the Commission and the School District Board shall be final and

conclusive, subject to trial in a court of competent jurisdiction.”

Case No. 2010-12745 -7- DECISION

jurisdiction over plaintiff’s claims in that plaintiff had failed to exhaust its administrative

remedies as required by R.C. 153.12(B)3 before filing suit. At trial, Hall admitted that

after SER denied plaintiff’s Article 8 claims, plaintiff did not appeal SER’s decision to the

Commission and the School District Board as outlined in Section 8.3 of the contract.

Instead, plaintiff filed its complaint in this court.

{¶ 16} As the Tenth District Court of Appeals has stated: “If * * * only an actual

final decision from the state could be deemed a rejection for purposes of when a cause

of action accrues, then the parties would be permitted to delay a decision indefinitely,

preclude the exhaustion of administrative remedies, and either forestall final resolution

of the claim through litigation or, at the least, render dubious the date the cause of

action accrued. Such an interpretation nullifies the ostensible purpose of R.C.

153.16(B): to ensure a remedy against the state for claimants such as plaintiff by

defining when administrative remedies are exhausted, the cause of action accrues, and

a cause of action may be filed in the Court of Claims. Under the statutory provisions at

issue, the state is aware it must resolve disputes within 120 days or face legal action, so

its failure to determine a claim before that 120-day period lapses, in effect, rejects the

claim, withholds money allegedly owed to the plaintiff, and permits the plaintiff to

institute an action against the state.” Painting Co. v. Ohio State Univ., 10th Dist. No.

09AP-78, 2009-Ohio-5710, 2009 Ohio App. LEXIS 4809, ¶13.

{¶ 17} In this case, plaintiff submitted notice of an Article 8 claim to SER on

November 24, 2009, plaintiff filed its written Article 8 claims on March 1, 2010, SER

rejected plaintiff’s claims on May 6, 2010, and plaintiff filed its complaint in this court on

December 13, 2010. The 120-day period starts when a notice of claim is filed. See

R.E. Schweitzer Construction Co. v. Univ. of Cincinnati, 10th Dist. No. 10AP-954, 2011-

3

R.C. 153.12(B) states, in relevant part: “If a dispute arises between the state and a contractor

concerning the terms of a public improvement contract let by the state or concerning a breach of the

contract, and after administrative remedies provided for in such contract and any alternative dispute

resolution procedures provided in accordance with guidelines established by the director of administrative

Case No. 2010-12745 -8- DECISION

Ohio-3703, 2011 Ohio App. LEXIS 3122, ¶ 25. By operation of law, plaintiff’s

administrative remedies were deemed exhausted on March 24, 2010, 120 days after it

submitted its notice of Article 8 claims, despite the fact that plaintiff did not pursue the

appeal process set forth in GC Section 8.3. “R.C. 153.12(B) and 153.16(B)4, construed

together, provide that any claim submitted under a public works contract with the state

necessarily will accrue, at the latest, by the end of the 120-day statutory period when,

by operation of law, all administrative remedies are deemed exhausted under R.C.

153.16(B), the claim is deemed rejected, and money the state allegedly owes is

deemed withheld.” Painting Co., supra, ¶ 14. Accordingly, defendant’s argument that

plaintiff failed to exhaust its administrative remedies by failing to appeal SER’s decision

does not divest the court of jurisdiction over plaintiff’s claims. Defendant’s motion to

dismiss is DENIED.

LAW

{¶ 18} The purpose of contract construction is to give effect to the intention of the

parties, and such intent “is presumed to reside in the language they chose to employ in

the agreement.” Stoll v. United Magazine Co., 10th Dist. No. 03AP-752, 2004-Ohio-

2523, 2004 Ohio App. LEXIS 2129, ¶ 7. In construing a written agreement, common

words appearing in the written instrument are to be given their plain and ordinary

meaning “unless manifest absurdity results, or unless some other meaning is clearly

evidenced from the four corners of the documents.” ld. at ¶ 8, citing Alexander v.

Buckeye Pipe Line Co., 53 Ohio St.2d 241 (1978), paragraph two of the syllabus.

services are exhausted, the contractor may bring an action to the court of claims in accordance with

Chapter 2743. of the Revised Code.”

4

R.C. 153.16(B) states: “Notwithstanding any contract provision to the contrary, any claim

submitted under a public works contract that the state or any institution supported in whole or in part by

the state enters into for any project subject to sections 153.01 to 153.11 of the Revised Code shall be

resolved within one hundred twenty days. After the end of this one hundred twenty-day period, the

contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of

section 153.12 of the Revised Code.”

Case No. 2010-12745 -9- DECISION

Additionally, a court is not required to go beyond the plain language of an agreement to

determine the parties’ rights and obligations if a contract is clear and unambiguous.

Custom Design Technologies, Inc. v. Galt Alloys, Inc., 5th Dist. No. 2001CA00153,

2002-Ohio-100, 2002 Ohio App. LEXIS 43. “If a contract is clear and unambiguous,

then its interpretation is a matter of law and there is no issue of fact to be determined.”

Inland Refuse Transfer Co. v. Browning-Ferris Industries of Ohio, Inc., 15 Ohio St.3d

321, 322 (1984), citing Alexander, supra.

CONSTRUCTION BULLETIN 63

{¶ 19} SER issued CB 63 on October 2, 2008, which extended the contract time.

GC Section 7.1.1 states: “The School District Board, without invalidating the Contract,

may order changes in the Work consisting of additions, deletions or other revisions,

subject to approval by the Commission. To the extent the Contract Time or Contract

Price is affected, the Contract may be equitably adjusted by Change Order in

accordance with this Article.” The court finds that this contract language is

unambiguous. Thus, any costs that were associated with CB 63 were to be addressed

as an equitable adjustment pursuant to the change order provisions of Article 7.

{¶ 20} Hall testified that he had used an approved schedule of values to calculate

proposed change orders on other projects for the Columbus Public Schools in the past,

and that the pricing had been accepted on those jobs. According to Hall, he did not

believe that plaintiff was required to follow Article 7 to price its proposed change orders.

Hall admitted that he priced the claim according to plaintiff’s schedule of values, but that

Murphy requested that he price it according to the change order pricing guidelines

contained in Article 7.

{¶ 21} GC Section 7.6, titled “Change Order Pricing Guidelines,” sets forth the

method for pricing change orders. GC Section 7.6.3 states: “For each change, the

Contractor shall furnish a detailed, written Proposal itemized according to these Pricing

Guidelines. * * * In order to expedite the review and approval process, all Proposals

Case No. 2010-12745 - 10 - DECISION

shall be prepared in the categories and in the order listed below. These pricing

Guidelines are intended to establish the maximum amount which the School District and

the Commission will pay for any Change Order, including without limitation all amounts

for interference, delay, hindrance, or disruption of the Work. * * *” The court finds that

the language in GC Section 7.6 of the contract is unambiguous. Accordingly, plaintiff

was required to use the pricing guidelines in Article 7, not plaintiff’s own schedule of

values, to calculate its proposal in response to CB 63.

{¶ 22} Murphy used the Pricing Guidelines to calculate a proposed change order

in the amount of $13,879.20, which was rejected by plaintiff. GC Section 7.4.8 states:

“If the Contractor does not agree with the School District Board’s determination under

paragraph GC 7.4.7, [adjustment of Contract Price associated with the adjustment of

Contract Time] the Contractor shall request an equitable adjustment of the Contract

under GC Article 8. * * *” The court finds that the language in GC Section 7.4.8 is

unambiguous. Accordingly, when the parties could not reach an agreement on pricing

for a change order as a result of CB 63, GC Section 7.4.8 required plaintiff to request an

equitable adjustment of the contract under GC Article 8. Plaintiff clearly did so in this

case on March 1, 2010, when it submitted a formal claim letter.

{¶ 23} Defendant asserts that plaintiff cannot prevail on its Article 8 claim with

regard to CB 63 because it failed to comply with the 10-day notice requirement in Article

8.1.1.5 In response, plaintiff argues that defendant waived strict compliance with the

notice requirements of Article 8.1.1 by its words and actions. Specifically, plaintiff points

5

GC Section 8.1.1 states: “Any request for equitable adjustment of Contract shall be made in

writing to the Architect, through the Construction Manager, and filed prior to Contract Completion,

provided the Contractor notified the Architect, through the Construction Manager, no more than ten (10)

days after the initial occurrence of the facts which are the basis of the claim. To the fullest extent

permitted by law, failure of the Contractor to timely provide such notice and a contemporaneous

statement of damages shall constitute a waiver by the Contractor of any claim for additional

compensation or for mitigation of Liquidated Damages.” GC Section 8.1.2 states: “In every such written

claim filed in accordance with paragraph GC 8.1.1, the Contractor shall provide the following information

to permit evaluation of the request for equitable adjustment of the Contract.”

Case No. 2010-12745 - 11 - DECISION

to SER’s December 16, 2009 letter wherein Murphy stated: “while the time constraints

outlined [in Article 8 of the contract] have been grossly surpassed, the Construction

Manager, the Architect and the Co-Ownership Team will consider your claim if properly

documented and supported.” (Defendant’s Exhibit N.) “[W]aiver of a contract provision

may be express or implied. * * * ‘[W]aiver by estoppel’ exists when the acts and conduct

of a party are inconsistent with an intent to claim a right, and have been such as to

mislead the other party to his prejudice and thereby estop the party having the right

from insisting upon it. * * * Waiver by estoppel allows a party’s inconsistent conduct,

rather than a party’s intent, to establish a waiver of rights. * * * Whether a party’s

inconsistent conduct constitutes waiver involves a factual determination, * * * and such

a factual determination is properly made by the trier of fact.” Lewis & Michael Moving

and Storage, Inc. v. Stofcheck Ambulance Serv., Inc., 10th Dist. No. 05AP-662, 2006-

Ohio-3810, 2006 Ohio App. LEXIS 3775, ¶ 29-30. (Internal citations omitted; emphasis

in original.) Waiver is an affirmative defense and defendant bears the burden of proving

such defense at trial. See Cleveland Constr., Inc. v. Kent State Univ., 10th Dist. No.

09AP-822, 2010-Ohio-2906, 2010 Ohio App. LEXIS 2407, ¶ 48.

{¶ 24} At trial, Murphy testified that CB 63 was issued because in the summer of

2008 it became clear that the original contract end date could not be met. Murphy

attributed the need for a time extension to the architect’s failure to timely answer

requests for information (RFIs) that various contractors had submitted during the

project. Murphy also testified that the contractors were informed in advance that a

bulletin would be issued to extend the contract end date and that the contractors were

encouraged to submit pricing in response to the bulletin. Murphy did not testify that

plaintiff or any other contractor was responsible for delays on the project which led to

the contract end date being extended.

{¶ 25} The evidence shows that plaintiff submitted a request for an Article 8

hearing to SER on November 24, 2009. In the November 24, 2009 letter, plaintiff

identified two claims: one with regard to CB 63, and another with regard to an additional

Case No. 2010-12745 - 12 - DECISION

extension of time past April 22, 2009, and related damages. At the time it was

submitted, SER was aware that no agreement had been reached with regard to CB 63

at the Article 7 stage and that the claim remained unresolved. Indeed, Studer’s July 30,

2009 email shows that SER expected plaintiff’s claim regarding CB 63 to proceed to the

Article 8 stage, inasmuch as Studer inquired about plaintiff’s availability for a field level

Article 8 meeting. In the December 26, 2009 letter, SER acknowledged that even

though plaintiff’s Article 8 request was untimely, SER would consider plaintiff’s CB 63

claim if it were properly documented. Based upon the evidence presented, the court

finds that defendant waived the 10-day notice requirement set forth in Article 8 with

regard to the CB 63 claim. SER’s conduct as shown in the July 30 and December 16,

2009 correspondence is inconsistent with an intent to claim strict compliance with the

10-day notice requirement in Article 8. Indeed, the parties engaged in the Article 8 field

level process in an effort to compromise the CB 63 claim. Therefore, the court finds that

defendant waived the 10-day notice requirement with regard to plaintiff’s Article 8 claim

for CB 63.

{¶ 26} During the Article 8 process, defendant requested additional information

from plaintiff in an effort to compromise the claim. Hall testified credibly that he

attempted to comply with Article 8 during the meetings about plaintiff’s claims, but he

felt that SER was never satisfied with any of the information that plaintiff submitted to

substantiate its claims. Murphy also testified credibly that she and Hall went back and

forth in an effort to come to a resolution, but that they were not “on the same page”

regarding plaintiff’s claim. It is clear to the court that while plaintiff requested

compensation for items that were not included in Article 7’s change order pricing

guidelines, such as punch lists and closeout, many of the items that plaintiff requested

were recoverable costs, such as overhead and profit. Murphy consistently testified that

SER was trying to decipher plaintiff’s claims, had requested that they be in a certain

format, and that although plaintiff did provide additional information, the form of the

Case No. 2010-12745 - 13 - DECISION

information did not comply with her request. The evidence shows that the parties had

substantially different ways of analyzing the information and significant disputes on what

was a proper measure of damages with regard to CB 63.

{¶ 27} Based upon the evidence presented, the court finds that plaintiff has

proven, by a preponderance of the evidence, that CB 63 was issued as a result of

delays caused by the owner. The court further finds that plaintiff has proven both that

defendant waived the 10-day notice requirement in GC Section 8.1.1, and that plaintiff

complied with Sections 8.1.1 and 8.1.2 by filing its written claim on March 1, 2010.

Moreover, the court finds that defendant’s failure to provide a written recommendation

about a change order for plaintiff’s Article 8 claim with regard to CB 63 was a breach of

GC Section 8.2.3 and that defendant’s failure to recommend any compensation for that

claim violates the prohibition of the waiver of liability for delay as set forth in R.C.

4113.62, inasmuch as defendant denied plaintiff compensation for delay on the project

that was caused by the owner. Accordingly, plaintiff is entitled to compensation for

damages it incurred as a result of CB 63. The court finds that defendant’s refusal to

compensate plaintiff for CB 63 on the basis that plaintiff failed to comply with the

requirements of Article 8 is without merit. Indeed, “an owner cannot cause a delay, and

then avoid the natural consequences for causing the delay by using boilerplate contract

language.” Cleveland Constr., Inc. v. Ohio Pub. Emples. Ret. Sys., 10th Dist. No.

07AP-574, 2008-Ohio-1630, 2008 Ohio App. LEXIS 1403, ¶ 19. The court further finds

that defendant acknowledged that plaintiff was owed at least $13,879.20 with regard to

CB 63 when it was engaged in the Article 7 process. Accordingly, defendant’s failure to

compensate plaintiff for costs it incurred as a result of CB 63 was a breach of contract.

{¶ 28} Inasmuch as the court has found that the contract language in Article 7 is

unambiguous, plaintiff shall be limited by the change order pricing guidelines in GC

Section 7.6 when presenting its claim for damages related to CB 63.

Case No. 2010-12745 - 14 - DECISION

EXTENSION OF TIME AND RELATED DAMAGES

{¶ 29} The second claim for which plaintiff requested an Article 8 hearing in its

November 24, 2009 letter was an extension of time from April 22, 2009 to August 3,

2009, along with a claim for damages in the amount of $75,605.53. (Defendant’s

Exhibit M.) For the following reasons, the court finds that plaintiff failed to prove by a

preponderance of the evidence that defendant waived the contractual requirements

found in Articles 6, 7, or 8, and, therefore, plaintiff cannot prevail on this claim.

{¶ 30} The court notes that on April 22, 2009, plaintiff sent SER the following

email: “This is to notify that Aggressive [M]echanical’s work on the southwood elem

project will not be complete by the April 22 2009 finish date due to change order work[.]

We will be working on bulletin 82#, bulletin 79#, bulletin 75#, this work should be

completed by 5-5-09 we will also have a little control and balance work to finish.”

(Defendant’s Exhibit K.)

{¶ 31} GC Section 7.4.5.2 states: “By signing a Change Order, the Contractor

irrevocably certifies that the scope of the change in the Work, the associated adjustment

Contract Time (if any), and the associated adjustment of the Contract Price (if any) are

completely satisfied, and waives all rights to seek a further adjustment of the Contract

Time, the Contract Price, or both, at a later date with respect to the associated change

in the Work.” At trial, Hall admitted that change orders were issued in connection with

Bulletins 82, 79, and 75, and that plaintiff was paid in accordance with such change

orders even though plaintiff’s work was not complete by April 22, 2009. The court finds

that the language in GC Section 7.4.5.2 is unambiguous. Inasmuch as plaintiff

accepted payment for the change orders issued with regard to bulletins 82, 79, and 75,

plaintiff has waived any additional compensation with regard to those claims.

{¶ 32} Furthermore, to the extent that plaintiff seeks damages related to the

delayed completion of the work, Section 6.4.1 of the contract states: “Any request by the

Case No. 2010-12745 - 15 - DECISION

Contractor for an extension of time shall be made in writing to the Construction Manager

no more than ten (10) days after the initial occurrence of any condition which, in the

Contractor’s opinion, entitles the Contractor to an extension of time. Failure to timely

provide such notice to the Construction Manager shall constitute a waiver by the

Contractor of any claim for extension, damages or mitigation of Liquidated Damages, to

the fullest extent permitted by law.” Although plaintiff notified SER on April 22, 2009

that it was continuing to work on the project past the contract end date, Hall admitted at

trial that the first notice of a claim with regard to a request for an extension of time from

April 22 to August 3, 2009 was made on November 24, 2009.

{¶ 33} Additionally, GC Section 6.4.2 outlines the requirements that must be

contained in the request.6 Hall’s April 22, 2009 email does not contain the required

information as set forth in Section 6.4.2.1-9 of the contract. The court finds that the

language in Article 6 is unambiguous. Therefore, inasmuch as plaintiff failed to comply

with the requirements of Article 6 with respect to a time extension from April 22 to

August 3, 2009, plaintiff’s claim in this regard has been waived.

{¶ 34} With regard to plaintiff’s Article 8 claim for damages related to such

extension in the amount of $75,605.53, plaintiff failed to comply with the 10-day notice

requirements of Article 8. Although plaintiff argues that SER waived strict compliance

with Article 8, the court finds that neither Studer’s July 30, 2009 email nor Murphy’s

December 15, 2009 letter constitutes conduct inconsistent with an intent to enforce the

notice requirements of Article 8. Studer’s email related solely to the unresolved change

order contemplated by CB 63. Murphy’s letter separated plaintiff’s two claims, and with

regard to plaintiff’s claim for an extension of time and related damages, she advised

plaintiff to review the requirements as set forth in Article 8 and stated: “[w]ithout a clear

and substantiated claim of the damages being sought, your request cannot realistically

6

GC Sections 6.4.2.1-6.4.2.9 set forth the specific information that the request for an extension of

time must include, such as nature of the interference, disruption, hindrance or delay; the identification of

Case No. 2010-12745 - 16 - DECISION

be evaluated. Please be aware that to date, other than a very brief email sent

exclusively to our on-site superintendent on April 22, 2009, the Project has received no

other written communication regarding this claim and presently, Aggressive Mechanical

still has outstanding Contract Work which the completion of is in no way being impeded

by the Project.” Id. SER’s conduct with regard to plaintiff’s request for an extension of

time and related damages shows that it did not have timely notice of this claim and that

it did not waive its right to enforce the contractual provisions regarding notice.

{¶ 35} Inasmuch as plaintiff has failed to comply with the contractual

requirements and has failed to prove that defendant waived such compliance, plaintiff’s

claim for an extension of time from April 22 to August 3, 2009, and related damages

must fail.

{¶ 36} Lastly, at trial, plaintiff presented some evidence with regard to unpaid

contract balance and retainage, but it is unclear to the court what amount remains

outstanding. Therefore, the parties shall be permitted to present evidence regarding

those claims at the damages trial.

{¶ 37} For the foregoing reasons, the court finds that plaintiff has proven its

claims regarding CB 63, contract balance, and retainage by a preponderance of the

evidence and, accordingly, judgment is recommended in favor of plaintiff.

{¶ 38} A party may file written objections to the magistrate’s decision within 14

days of the filing of the decision, whether or not the court has adopted the decision

during that 14-day period as permitted by Civ.R. 53(D)(4)(e)(i). If any party timely files

objections, any other party may also file objections not later than ten days after the first

objections are filed. A party shall not assign as error on appeal the court’s adoption of

any factual finding or legal conclusion, whether or not specifically designated as a

finding of fact or conclusion of law under Civ.R. 53(D)(3)(a)(ii), unless the party timely

the reason for the delay; activities on the construction schedule that may be affected; the recommended

action to minimize delay, etc.

Case No. 2010-12745 - 17 - DECISION

and specifically objects to that factual finding or legal conclusion within 14 days of the

filing of the decision, as required by Civ.R. 53(D)(3)(b).

_____________________________________

HOLLY TRUE SHAVER

Magistrate

cc:

David A. Beals Douglas M. Beard

Jon C. Walden Michael F. Copley

Assistant Attorneys General 1015 Cole Road

150 East Gay Street, 18th Floor Galloway, Ohio 43119

Columbus, Ohio 43215-3130

002

Filed September 18, 2012

To S.C. Reporter January 28, 2013