Opinion

Citizens Against Airport Pollution v. City of San Jose

  • 227 Cal. App. 4th 788
Court
California Court of Appeal
Filed
Jul 2, 2014
Status
Published
Author
Bamattre-Manoukian
On the bench
Bamattre-Manoukian
Cited by
12 cases
Authority
More cited than 60.5%

The opinion

Filed 6/6/14 Certified for publication 7/2/14 (order attached)

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

CITIZENS AGAINST AIRPORT H038781

POLLUTION, (Santa Clara County

Super. Ct. No. 110CV177290)

Plaintiff and Appellant,

v.

CITY OF SAN JOSE et al.,

Defendants and Respondents.

I. INTRODUCTION

This CEQA1 case arises from the eighth addendum to the 1997 environmental

impact report for respondent City of San Jose’s International Airport Master Plan. The

eighth addendum concerns the environmental impacts of recent amendments made by the

City of San Jose (City) to the Airport Master Plan, which include changes to the size and

location of future air cargo facilities, the replacement of air cargo facilities with 44 acres

of general aviation facilities, and the modification of two taxiways to provide better

access for corporate jets.

1

California Environmental Quality Act, Public Resources Code section 21000,

et seq. All further statutory references are to the Public Resources Code unless otherwise

indicated.

Appellant Citizens Against Airport Pollution (CAAP) contends that the trial court

erred in denying their petition for writ of mandamus challenging City’s approval of the

eighth addendum. CAAP argues that the amendments to the Airport Master Plan that are

addressed in the eighth addendum constitute a new project as a matter of law, and

therefore an environmental impact report (EIR) addendum is barred under CEQA.

Alternatively, CAAP contends that an EIR addendum cannot be used to analyze the

environmental impacts of the project changes included in the amendments, since those

changes are substantial and require major revisions to the EIR with respect to noise,

greenhouse gas emissions, toxic air contaminants, and the burrowing owl habitat.

For reasons that we will explain, we will affirm the judgment without reaching

City’s claim that CAAP failed to exhaust its administrative remedies.

II. FACTUAL AND PROCEDURAL BACKGROUND

A. The San Jose International Airport Master Plan Update and EIR

In 1988, City began preparation of an update to the 1980 Airport Master Plan for

the San Jose International Airport in order to accommodate projected growth in passenger

and air cargo traffic through a planning horizon year of 2010. In 1995, City issued a

notice of preparation of an EIR for the proposed Airport Master Plan update.

The final EIR (FEIR) for the updated Airport Master Plan was approved in 1997.

A supplemental EIR (SEIR) was certified in 2003. From 1997 through 2010, eight EIR

addenda that addressed the environmental impacts of amendments to the Airport Master

Plan were approved. At issue in the present appeal is the eighth addendum.

B. The Eighth Addendum

The eighth addendum to the Airport Master Plan EIR concerns amendments that

change the Airport Master Plan by shifting the planning horizon year to 2027 and

modifying certain master plan projects for air cargo and general aviation facilities. One

reason for the amendments is that the level of air passenger activity that was projected to

be reached by the year 2017 is now projected to be reached in 2027, due to a recent

2

decrease in the annual number of passengers. Another reason for the amendments is that

the current projections show that the volume of air cargo and the demand for general

aviation will be less than originally projected.

Due to these changes in demand forecasts, City proposed amending the Airport

Master Plan with the following modifications: (1) changes in the size and location of

future air cargo facilities; (2) replacement of previously planned future air cargo facilities

with 44 acres of general aviation facilities, in order to accommodate the forecast that

large corporate jets will comprise the majority of general aviation; and (3) modification

of Taxiway H and Taxiway K by adding new segments to provide better access for

corporate jets.

The eighth addendum states that the proposed modifications “will not have any

significant environmental impacts not previously disclosed in the Airport Master Plan

EIR, nor will there be a substantial increase in the severity of previously-identified

significant environmental impacts. Therefore, no subsequent or supplement EIR is

warranted or required.” The City Council approved the eighth addendum in June 2010.

C. The Petition for Writ of Mandamus

In July 2010 CAAP filed a petition for writ of mandamus challenging City’s

approval of the eighth addendum. CAAP is an unincorporated association whose

members include residents and property owners in San Jose.

In its petition, CAAP argued that City violated CEQA by approving a major

amendment to the Airport Master Plan without preparing a supplemental or subsequent

EIR. According to CAAP, the eighth addendum failed to adequately assess or analyze

the impacts of the taxiway modifications and the construction of general aviation

facilities on noise, air pollution, and the burrowing owl habitat. Additionally, CAAP

argued that the eighth addendum failed to comply with newly adopted rules mandating

review of project impacts on greenhouse gases and climate change.

3

In its opening brief in support of the petition, CAAP further argued that it was not

required to exhaust administrative remedies since there had been no public comment

period or noticed public hearing on the eighth addendum. Alternatively, CAAP

contended that it had exhausted its administrative remedies by objecting to the eighth

addendum in a letter to the City Council and during an informal meeting with airport

staff.

CAAP also argued that the eighth addendum violated CEQA because the proposed

major amendments to the Airport Master Plan constituted a new project that required

preparation of a new environmental document with a public comment period and a

noticed public hearing. Alternatively, CAAP asserted that the reconfiguration and

expansion of general aviation facilities that were proposed in the amendments constituted

substantial project changes and/or changed circumstances, which required a supplemental

EIR to assess significant unstudied environmental impacts on noise, greenhouse gas

emissions, toxic air contaminants, and the burrowing owl habitat.

D. The Trial Court’s Order

The trial court’s order denying CAAP’s petition for writ of mandamus was filed

on August 2, 2012. At the outset, the court rejected City’s contention that CAAP had

failed to exhaust its administrative remedies. Although the court recognized that

exhaustion of administrative remedies is a jurisdictional prerequisite to a CEQA action,

the court found that CAAP was excused because there had been no public notice that “a

CEQA determination or a CEQA document would be forthcoming or was contemplated.”

However, the trial court found no merit in CAAP’s CEQA challenge to City’s

approval of the eighth addendum. Relying primarily on this court’s decision in Santa

Teresa Citizen Action Group v. City of San Jose (2003) 114 Cal.App.4th 689 (Santa

Teresa), the trial court found that there was substantial evidence to support City’s

decision that an EIR addendum, rather than a SEIR, was appropriate under CEQA

because (1) the noise analysis attached to the eighth addendum showed that noise impacts

4

from the proposed airport modifications would be less than the impacts that were

disclosed in the 1997 FEIR and the 2003 SEIR; (2) the effects of greenhouse gases do not

constitute new information that could not have been known at the time the 1997 FEIR

was certified as complete; (3) the proposed airport modifications would not increase air

pollution, since the projections showed that air cargo and general aviation traffic would

be less than was originally projected, with a corresponding decrease in associated ground

vehicle traffic; and (4) the biological survey attached to the eighth addendum stated that

any burrowing owl habitat loss caused by the construction of the taxiway improvements

could be mitigated, and therefore the severity of the previously identified impact on the

burrowing owls would not be increased.

CAAP filed a timely notice of appeal from the trial court’s order. We treat an

order denying a petition for writ of mandamus under CEQA as an appealable final

judgment. (Concerned Citizens of South Central L.A. v. Los Angeles Unified School Dist.

(1994) 24 Cal.App.4th 826, 831-832.)

III. DISCUSSION

The issues raised by CAAP on appeal include the following: (1) the trial court

erred in denying its writ petition because the amendments to the Airport Master Plan

addressed in the eighth addendum constitute a new project as a matter of law, and

therefore CEQA bars the use of an addendum; and (2) alternatively, the trial court erred

in denying its writ petition because the amendments to the Airport Master Plan addressed

in the eighth addendum constitute substantial project changes that under CEQA require

major EIR revisions with respect to noise, greenhouse gas emissions, toxic air

contaminants, and the burrowing owl habitat. City contends that we need not reach the

issues raised by CAAP on appeal since the CEQA challenge is precluded due to CAAP’s

failure to exhaust its administrative remedies.

We will begin our analysis with a brief overview of CEQA, the rules that apply to

an EIR addendum, and the applicable standard of review.

5

A. CEQA Overview

“ ‘CEQA [section 21000 et seq.] embodies our state’s policy that “the long-term

protection of the environment . . . shall be the guiding criterion in public decisions.” ’

[Citations.] As this court has observed, ‘the overriding purpose of CEQA is to ensure

that agencies regulating activities that may affect the quality of the environment give

primary consideration to preventing environmental damage. [Citation.]’ [Citation.]

Consistent with this strong environmental policy, the CEQA statutes and the Guidelines[2]

issued by the California Resources Agency to implement CEQA ‘have established a

three-tiered process to ensure that public agencies inform their decisions with

environmental considerations.’ [Citation.]” Save Our Carmel River v. Monterey

Peninsula Water Management Dist. (2006) 141 Cal.App.4th 677, 687 (Save Our Carmel

River).)

1. EIR

The first tier of the CEQA process requires an agency to conduct a preliminary

review to determine whether CEQA applies to a proposed project. (Guidelines,

§§ 15060, 15061; Save Our Carmel River, supra, 141 Cal.App.4th at p. 687.) “If the

initial study shows that there is ‘no substantial evidence that the project or any of its

aspects may cause a significant effect on the environment,’ the agency prepares a

negative declaration so stating. [Citations.] If the project does not qualify for a negative

declaration, the agency must proceed to the third step in the process, full environmental

review in an EIR.” (Save Our Carmel River, supra, at p. 688.)

2

The regulations that guide the application of CEQA are set forth in title 14 of the

California Code of Regulations, and are often referred to as the CEQA Guidelines.

(Communities for a Better Environment v. South Coast Air Quality Management Dist.

(2010) 48 Cal.4th 310, 319, fn. 4 (Communities for a Better Environment).) The CEQA

Guidelines are accorded “ ‘great weight except where they are clearly unauthorized or

erroneous.’ [Citation.]” (Ibid.) References to “Guidelines” hereafter are to the state

CEQA Guidelines. (Cal. Code Regs., tit. 14, § 15000 et seq.)

6

Thus, under CEQA, a public agency must prepare an EIR only with regard to

“projects that may have significant environmental effects. (§§ 21100, subd. (a), 21151,

subd. (a)).” (Communities for a Better Environment, supra, 48 Cal.4th at p. 315.) “The

EIR’s function is to ensure that government officials who decide to build or approve a

project do so with a full understanding of the environmental consequences and, equally

important, that the public is assured those consequences have been taken into account.

[Citation.]” (Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho

Cordova (2007) 40 Cal.4th 412, 449 (Vineyard).)

2. Subsequent or Supplemental EIR

“CEQA does not require an EIR to be prepared for every step taken in the course

of a project. Once a proper EIR has been prepared, no subsequent or supplemental EIR

[SEIR] is required unless (1) ‘[s]ubstantial changes’ are proposed in the project, requiring

‘major revisions’ in the EIR; (2) substantial changes arise in the circumstances of the

project’s undertaking, requiring major revisions in the EIR; or (3) new information

appears that was not known or available at the time the EIR was certified. (§ 21166; see

also Guidelines, § 15162; [citation].) ‘[S]ection 21166 comes into play precisely because

in-depth review has already occurred, the time for challenging the sufficiency of the

original EIR has long since expired (§ 21167, subd. (c)), and the question is whether

circumstances have changed enough to justify repeating a substantial portion of the

process.’ [Citation.]” (Committee for Green Foothills v. Santa Clara County Bd. of

Supervisors (2010) 48 Cal.4th 32, 54-55.)

3. Addendum

In addition to a SEIR, the Guidelines provide for an addendum to an EIR. “The

lead agency or a responsible agency shall prepare an addendum to a previously certified

EIR if some changes or additions are necessary but none of the conditions described in

7

Section 15162[3] calling for preparation of a subsequent EIR have occurred.”

(Guidelines, § 15164, subd. (a).) “An addendum need not be circulated for public review

but can be included in or attached to the final EIR or adopted negative declaration.” (Id.,

subd. (c).) “The decision-making body shall consider the addendum with the final EIR or

adopted negative declaration prior to making a decision on the project. [¶] . . . A brief

explanation of the decision not to prepare a subsequent EIR pursuant to Section 15162

should be included in an addendum to an EIR, the lead agency’s required findings on the

project, or elsewhere in the record. The explanation must be supported by substantial

evidence.” (Id., subds. (d), (e); see Mani Brothers Real Estate Group v. City of Los

Angeles (2007) 153 Cal.App.4th 1385, 1398 (Mani Brothers).)

3

California Code of Regulations, title 14, section 15162, subdivision (a) states:

“When an EIR has been certified or a negative declaration adopted for a project, no

subsequent EIR shall be prepared for that project unless the lead agency determines, on

the basis of substantial evidence in the light of the whole record, one or more of the

following: [¶] (1) Substantial changes are proposed in the project which will require

major revisions of the previous EIR or negative declaration due to the involvement of

new significant environmental effects or a substantial increase in the severity of

previously identified significant effects; [¶] (2) Substantial changes occur with respect to

the circumstances under which the project is undertaken which will require major

revisions of the previous EIR or negative declaration due to the involvement of new

significant, environmental effects or a substantial increase in the severity of previously

identified significant effects; or [¶] (3) New information of substantial importance,

which was not known and could not have been known with the exercise of reasonable

diligence at the time the previous EIR was certified as complete or the negative

declaration was adopted, shows any of the following: [¶] (A) The project will have one

or more significant effects not discussed in the previous EIR or negative declaration; [¶]

(B) Significant effects previously examined will be substantially more severe than shown

in the previous EIR; [¶] (C) Mitigation measures or alternatives previously found not to

be feasible would in fact be feasible and would substantially reduce one or more

significant effects of the project, but the project proponents decline to adopt the

mitigation measure or alternative; or [¶] (D) Mitigation measures or alternatives which

are considerably different from those analyzed in the previous EIR would substantially

reduce one or more significant effects on the environment, but the project proponents

decline to adopt the mitigation measure or alternative.”

8

B. Standard of Review

“In reviewing an agency’s compliance with CEQA in the course of its legislative

or quasi-legislative actions, the courts’ inquiry ‘shall extend only to whether there was a

prejudicial abuse of discretion.’ (. . . § 21168.5.) Such an abuse is established ‘if the

agency has not proceeded in a manner required by law or if the determination or decision

is not supported by substantial evidence.’ [Citations.]” (Vineyard, supra, 40 Cal.4th at

pp. 426-427, fns. omitted.)

Thus, as this court has stated, “[t]he reviewing court upholds an agency’s decision

not to require an SEIR if the administrative record as a whole contains substantial

evidence to support the determination that the changes in the project or its circumstances

were not so substantial as to require major modifications of the EIR. [Citation.] This

deferential standard is a reflection of the fact that in-depth review has already occurred.

[Citation.]” (Santa Teresa, supra, 114 Cal.App.4th at p. 703.) “The burden is on the

appellant to show there is no substantial evidence to support the findings of the agency.

[Citation.]” (American Canyon Community United for Responsible Growth v. City of

American Canyon (2006) 145 Cal.App.4th 1062, 1070 (American Canyon).)

“Our role here is precisely the same as the trial court’s. ‘ “[I]n an administrative

mandamus action where no limited trial de novo is authorized by law, the trial and

appellate courts occupy in essence identical positions with regard to the administrative

record, exercising the appellate function of determining whether the record is free from

legal error. [Citations.” [Citation.] Thus, the conclusions of the superior court, and its

disposition of the issues in this case, are not conclusive on appeal. [Citation.]’

[Citations.]” (Bowman v. City of Petaluma (1986) 185 Cal.App.3d 1065, 1076.)

C. Analysis

1. Exhaustion of Administrative Remedies

As a threshold matter, City contends that CAAP’s CEQA challenge is barred

because CAAP failed to exhaust its administrative remedies by objecting to City’s

9

approval of the eighth addendum during the public meetings that were held before the

addendum was approved.

This court stated the exhaustion requirement in Santa Teresa: “In order to attack a

decision that is subject to CEQA, the alleged grounds for noncompliance must have been

presented to the public agency, and the person attacking the decision must have raised

some objection during the administrative proceedings. (§ 21177, subds. (a), (b).)[4]

These restrictions do not apply to ‘any alleged grounds for noncompliance with [CEQA]

for which there was no public hearing or other opportunity for members of the public to

raise those objections orally or in writing prior to the approval of the project, . . . .’

(§ 21177, subd. (e).) This subdivision codifies the rule that unless there is a clearly

defined administrative procedure for resolving complaints, the exhaustion doctrine is

inapplicable. [Citation.]” (Santa Teresa, supra, 114 Cal.App.4th at pp. 701-702.)

Another appellate court has explained that “[t]he rationale for exhaustion is that

the agency ‘ “is entitled to learn the contentions of interested parties before litigation is

instituted. If [plaintiffs] have previously sought administrative relief . . . the [agency]

will have had its opportunity to act and to render litigation unnecessary, if it had chosen

to do so.” ’ [Citation.] The ‘exact issue’ must have been presented to the administrative

agency to satisfy the exhaustion requirement. [Citation.]” (Mani Brothers, supra, 153

Cal.App.4th at p. 1394.)

4

Section 21177, subdivisions (a) and (b) state: “An action or proceeding shall not

be brought pursuant to Section 21167 unless the alleged grounds for noncompliance with

this division were presented to the public agency orally or in writing by any person

during the public comment period provided by this division or prior to the close of the

public hearing on the project before the issuance of the notice of determination. [¶] . . .

A person shall not maintain an action or proceeding unless that person objected to the

approval of the project orally or in writing during the public comment period provided by

this division or prior to the close of the public hearing on the project before the filing of

the notice of determination pursuant to Sections 21108 and 21152.”

10

In Santa Teresa, this court determined that since the City had not either given

notice that an initial study for a new water pipeline was being prepared or circulated the

addendum adopting the initial study, “there was no clearly defined administrative

procedure for petitioners to resolve their concerns about the project as it was finally

configured, which means that the exhaustion requirement of section 21177 does not

apply. [Citation.]” (Santa Teresa, supra, 114 Cal.App.4th at p. 702.) In contrast, in

Mani Brothers the appellate court ruled that although no public hearing or public

comment period had been provided for an addendum, the exhaustion requirement applied

and was satisfied because the petitioners had repeatedly objected to the addendum at

several public meetings. (Mani Brothers, supra, 153 Cal.App.4th at p. 1395.)

City relies upon the California Supreme Court’s decision in Tomlinson v. County

of Alameda (2012) 54 Cal.4th 281, 290, in which the court ruled that “[i]f a notice of

determination is filed, the public hearing provision [§ 21177, subd. (a)] requires a party

wishing to challenge the project in court to raise the party’s objections to the project at a

public hearing held before the notice of determination is filed.” City asserts that it filed a

notice of determination for the project addressed in the eighth addendum and held several

public meetings regarding the project before the addendum was approved. Additionally,

City contends that CAAP merely made general comments on several environmental

issues in its letter to the City Council, which did not satisfy the exhaustion requirement,

or, alternatively, were insufficient to constitute exhaustion as to certain issues raised by

CAAP in its writ petition.

CAAP acknowledges that in its letter to the City Council it “did not comment on

the Eighth Addendum’s inadequacy as to greenhouse gas emissions and toxic air

contaminants.” However, CAAP contends that it was not required to exhaust

administrative remedies under Santa Teresa, supra, 114 Cal.App.4th 689 since there was

no clearly defined administrative procedure to resolve concerns about the project

addressed in the eighth addendum. CAAP also asserts that the public notice of the City

11

Council hearing that was held before project approval did not give any notice of CEQA

action.

We need not determine as a threshold matter whether CAAP was required to or

did exhaust its administrative remedies with regard to the eighth addendum. For the

reasons discussed below, we may affirm the trial court’s order denying CAAP’s petition

for writ of mandamus on the merits without reaching the exhaustion issue.

2. New Project

CAAP’s primary argument on appeal is that the changes proposed in the

amendments to the Airport Master Plan addressed in the eighth addendum constitute a

new project for which a new EIR, not an addendum, must be prepared. CAAP relies on

the decision in Center for Sierra Nevada Conservation v. County of El Dorado (2012)

202 Cal.App.4th 1156 (Center for Sierra Nevada) in arguing that as a matter of law the

amendments addressed in the eighth addendum constitute a new project because the

proposed changes are “not within the scope of the 1997 Airport Master Plan or its

program EIR.”

City rejects CAAP’s characterization of the amendments addressed in the eight

addendum as a new project. According to City, “there is no ‘new project’ but merely an

adjustment to the existing plan that has already received environmental review.” City

also disputes CAAP’s characterization of the 1997 EIR for the Airport Master Plan as a

program EIR. According to City, the EIR “is a project-level document and has been used

as such. Had the 1997 EIR been a program-level document, the many projects that have

been constructed since that time would have undergone additional CEQA review.”

The decision relied upon by CAAP, Center for Sierra Nevada, supra, 202

Cal.App.4th 1156 for the proposition that the reviewing court determines as a matter of

law whether proposed changes constitute a new project for which an EIR is required, is

distinguishable. The decision involved a program EIR adopted by El Dorado County in

2004 that acknowledged the impact of development on oak woodlands and wildlife, and

12

provided that the effects would be mitigated by formulating an “integrated natural

resources management plan” within five years. (Id. at pp. 1162-1163.) In 2008, the

county Board of Supervisors adopted an oak woodland management plan that allowed

developers to pay a fee for removing oak canopies, which was based on a negative

declaration. (Id. at p. 1166.) The appellate court determined that the administrative

record supported a fair argument that the oak woodland management plan and fee

program would have “a potentially significant effect on the environment” and that the

2004 program EIR did not adequately cover the fee mitigation program. (Id. at p. 1184.)

For those reasons, the court ruled that the oak woodland management plan was a specific

project and the county was required to prepare a tiered EIR “to examine its specific

mitigation measures and fee rate.” (Id. at p. 1184.)

CAAP also relies on another distinguishable decision, Sierra Club v. County of

Sonoma (1992) 6 Cal.App.4th 1307 (Sierra Club). In that case, Sonoma County certified

and adopted a program EIR for mining operations that included terrace mining adjacent

to a river. (Id. at p. 1313.) A company applied for a use permit to mine 50 acres of a

145-acre parcel along the river that had been designated for agriculture. (Id. at p. 1314.)

The Board of Supervisors adopted a negative declaration and approved the application

since all of the environmental impacts that might result from the proposed changes had

already been considered in the program EIR. (Ibid.) The appellate court determined that

the trial court had properly ordered Sonoma County to set aside its approval of the project

pending preparation of an EIR on the ground that the evidence did not support a

determination that the company’s “proposed site-specific project was either the same as

or within the scope of the project, program, or plan described in the program EIR.

[Citation.]” (Id. at pp. 1320-1321.)

The decisions in Sierra Club and Center for Sierra Nevada are distinguishable

from the present case because both cases involved a county’s adoption of a negative

declaration for a project where the issue was whether the project came within the scope

13

of a prior program EIR. The California Supreme Court has explained the difference

between a program EIR and a project EIR: “A program EIR . . . is ‘an EIR which may be

prepared on a series of actions that can be characterized as one large project’ and are

related in specified ways. (Cal. Code Regs., tit. 14, § 15168, subd. (a).)[5] An advantage

of using a program EIR is that it can ‘[a]llow the lead agency to consider broad policy

alternatives and program wide mitigation measures at an early time when the agency has

greater flexibility to deal with basic problems or cumulative impacts.’ (Id., § 15168,

subd. (b)(4).) Accordingly, a program EIR is distinct from a project EIR, which is

prepared for a specific project and must examine in detail site-specific considerations.

(Id., § 15161.)[6]” (In re Bay-Delta etc. (2008) 43 Cal.4th 1143, 1169.) “[W]here an

agency prepares a ‘program EIR’ for a broad policy document such as a local general

plan, Guidelines section 15168, subdivision (c)(2) allows agencies to limit future

environmental review for later activities that are found to be ‘within the scope’ of the

program EIR.” (Latinos Unidos de Napa v. City of Napa (2013) 221 Cal.App.4th 192,

196.)

This court addressed a program EIR for a transit plan in May v. City of Milpitas

(2013) 217 Cal.App.4th 1307, 1316-1317 (May) and stated the section 21166 standard

5

California Code of Regulations, title 14, section 15168, subdivision (a) states:

“A program EIR is an EIR which may be prepared on a series of actions that can be

characterized as one large project and are related either: [¶] (1) Geographically, [¶]

(2) As logical parts in the chain of contemplated actions, [¶] (3) In connection with

issuance of rules, regulations, plans, or other general criteria to govern the conduct of a

continuing program, or [¶] (4) As individual activities carried out under the same

authorizing statutory or regulatory authority and having generally similar environmental

effects which can be mitigated in similar ways.”

6

California Code of Regulations, title 14, section 15161 states: “The most

common type of EIR examines the environmental impacts of a specific development

project. This type of EIR should focus primarily on the changes in the environment that

would result from the development project. The EIR shall examine all phases of the

project including planning, construction, and operation.”

14

for further environmental review where a program EIR has already been prepared. In

May, this court determined that “[s]ection 21166, part of CEQA, provides: ‘When an

environmental impact report has been prepared for a project pursuant to this division, no

subsequent or supplemental environmental impact report shall be required by the lead

agency or by any responsible agency, unless one or more of the following events occurs:

[¶] (a) Substantial changes are proposed in the project which will require major revisions

of the environmental impact report. [¶] (b) Substantial changes occur with respect to the

circumstances under which the project is being undertaken which will require major

revisions in the environmental impact report. [¶] (c) New information, which was not

known and could not have been known at the time the environmental impact report was

certified as complete, becomes available.’ Where environmental review has been

conducted through a program EIR, CEQA requires further review only in these limited

circumstances. [Citations.]” (May, supra, at pp. 1325-1326, italics added.)

As we will explain, we find there is substantial evidence in the administrative

record showing that the amendments to the Airport Master Plan that are addressed in the

eighth addendum will not result in any new significant impacts on noise, air quality, and

the burrowing owl habitat that are substantially different from those described in the 1997

EIR and the 2003 SEIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 704;

Guidelines, § 15162, subds. (a)(1) & (2).) Therefore, even assuming, without deciding,

that the 1997 EIR for the Airport Master Plan constitutes a program EIR, as CAAP

argues, we are not persuaded that the proposed changes to the Airport Master Plan that

are addressed in the eighth addendum constitute a new project that requires a new EIR.

3. Noise Impacts

The eighth addendum analyzed whether the changes proposed in the amendments

to the Airport Master Plan would result in new or greater noise impacts than had been

quantified in the 1997 EIR and the 2003 SEIR. The addendum concluded: “The

proposed changes to the Airport Master Plan would not result in any new significant

15

noise impacts and/or noise impacts that are substantially different from those described in

the 1997 SJC Master Plan Update EIR and 2003 Master Plan Update Supplemental EIR.”

(Italics omitted.)

In support of this conclusion, the eighth addendum stated that the data showed

that the number of average daily aircraft operations would be 20 percent less in 2027

than had been projected to occur in 2010 and 2017. Additionally, the data showed that in

2027 there would “be far fewer operations by older and noisier aircraft (e.g., Boeing 727,

MD-80 series, etc.) than there will be in 2010/2017. This is a result of older aircraft

gradually being phased out over time and being replaced with newer and quieter aircraft.”

Using “the same methodology and thresholds as those contained in the 1997

Master Plan EIR, as updated by the 2003 Master Plan Supplemental EIR,” the eighth

addendum further stated that the noise levels at all of the reference point locations in the

vicinity of the airport would be lower in 2027 than was projected for 2017. Also, using

the community noise equivalent level (CNEL) contour, which depicts the “noise

footprint” of the airport, the addendum stated that the area that would be exposed to

aircraft noise of 65 decibels or greater in 2027 would be reduced by 28 percent from the

area projected for 2017.

Relying on the decision in Berkeley Keep Jets Over the Bay Com. v. Board of Port

Cmrs. (2001) 91 Cal.App.4th 1344 (Berkeley Jets), CAAP argues that the eighth

addendum failed to include any analysis of the noise impacts of single-event noise from

the nighttime operation of large corporate jets, and also failed to analyze the noise impact

of the support facilities for those jets. Additionally, relying on this court’s decision in

Lighthouse Field Beach Rescue v. City of Santa Cruz (2005) 131 Cal.App.4th 1170

(Lighthouse), CAAP argues that the eighth addendum improperly used an “ ‘overall’ ” or

“ ‘net’ ” approach to analyzing the noise impacts of the proposed amendments to the

Airport Master Plan. CAAP therefore contends that there is not substantial evidence to

16

support the eighth addendum’s conclusion that the noise impacts of the proposed

amendments to the Airport Master Plan would not be significant.

City responds that the 1997 EIR contains an extensive noise impact analysis,

including the impact of aircraft maintenance and support facilities and both cumulative

and single-event noise analysis; the 2003 SEIR included a noise impact analysis stating

that single event noise levels had not been recomputed since the aircraft fleet had become

quieter since completion of the 1997 EIR; and the eighth addendum used the same

methodology as the 1997 EIR and the 2003 SEIR in finding that noise impacts will

decrease due to fewer aircraft operations and a higher percentage of new, quieter

airplanes.

We emphasize that the standard of review that applies to a CEQA attack on an

agency’s use of an addendum to an EIR is deferential. (See Santa Teresa, supra, 114

Cal.App.4th at p. 704.) “When an agency has already prepared an EIR, its decision not to

prepare an SEIR for a later project is reviewed under the deferential substantial evidence

standard. [Citation.]” (Id. at p. 702.) “We independently review the administrative

record. [Citation.] We resolve reasonable doubts in favor of the administrative decision.

[Citation.] ‘We do not judge the wisdom of the agency’s action in approving the Project

or pass upon the correctness of the EIR’s environmental conclusions. [Citations.] Our

function is simply to determine whether the agency followed proper procedures and

whether there is substantial evidence supporting the agency’s determination that the

changes in the Project (or its circumstances) were not substantial enough to require an

SEIR.’ [Citation.]” (Id. at p.704.)

In Santa Teresa, this court rejected a CEQA challenge to the City’s use of an

addendum to the FEIR for a proposed water pipeline realignment, instead of a SEIR,

because “the record contain[ed] substantial evidence supporting the conclusion that the

environmental impact of the Silver Creek alignment upon the groundwater in North

Coyote Valley was not substantially different from or greater than the impacts considered

17

in the previous [environmental] studies.” (Santa Teresa, supra, 114 Cal.App.4th at

p. 705.) We reach a similar result in the present case.

“The CEQA Guidelines define ‘substantial evidence’ as ‘enough relevant

information and reasonable inferences from this information that a fair argument can be

made to support a conclusion, even though other conclusions might also be reached. . . .

Argument, speculation, unsubstantiated opinion or narrative, evidence which is clearly

erroneous or inaccurate, or evidence of social or economic impacts which do not

contribute to or are not caused by physical impacts on the environment does not

constitute substantial evidence.’ (Guidelines, § 15384, subd. (a).) Additionally,

‘[s]ubstantial evidence shall include facts, reasonable assumptions predicated upon facts,

and expert opinion supported by facts.’ (Guidelines, § 15384, subd. (b).)” (Pfeiffer v.

City of Sunnyvale City Council (2011) 200 Cal.App.4th 1552, 1569.)

We find there is substantial evidence to support the eighth addendum’s conclusion

that the proposed changes to the Airport Master Plan would not result in any new

significant noise impacts and/or noise impacts that are substantially different from those

described in the 1997 EIR and the 2003 SEIR. Appendix A to the eighth addendum

includes the January 11, 2010 “analysis of changes in predicted future aircraft noise

exposure that would occur upon adoption of the proposed Updated Master Plan Forecast

for the year 2027 (2027 forecast) at [San Jose International Airport],” which was

prepared by Brown-Buntin Associates, Inc. (Brown-Buntin). Brown-Buntin states in its

report that its practice includes “Aviation Noise Studies.”

The Brown-Buntin noise analysis includes tables that (1) compare the forecasts for

daily aircraft operations and show a decrease in daily operations from 904.10 in 2010 to

722.70 in 2027; (2) state the 2027 forecast for annual average runway use by various

types of aircraft, including corporate jets; and (3) show a decrease in the CNEL from

2010 to 2027 at the reference grid locations used in the 1997 EIR and 2003 SEIR. Thus,

Brown-Buntin’s analysis of the forecast changes and the data constitutes expert opinion

18

based on facts that the noise impact from aircraft operations is decreasing, and therefore

it may be reasonably assumed that the changes proposed in the amendments to the

Airport Master Plan will not result in any new significant noise impacts and/or noise

impacts that are substantially different from those described in the 1997 EIR and the 2003

SEIR. As we have noted, the Guidelines provide that substantial evidence includes

“reasonable assumptions predicated upon facts, and expert opinion supported by facts.”

(Guidelines, § 15384, subd. (b).)

Moreover, the decisions in Berkeley Jets and Lighthouse, on which CAAP relies

for a contrary conclusion, do not aid CAAP. Those decisions are distinguishable since

neither one involved an addendum to an EIR. In Berkeley Jets, supra, 91 Cal.App.4th

1344 citizen groups challenged the adequacy of the EIR prepared for an expansion

proposal for the Metropolitan Oakland International Airport. (Id. at p. 1350.) In

Lighthouse, an advocacy association challenged the City of Santa Cruz’s decision to

adopt a negative declaration, instead of preparing an EIR, for revisions to the general plan

for a state beach. (Lighthouse, supra, 131 Cal.App.4th at p. 1177.)

As we have discussed, a different standard applies where, as here, the agency has

already prepared an EIR. “In the first instance, an agency must prepare an EIR

‘whenever it can be fairly argued on the basis of substantial evidence that the project may

have significant environmental impact.’ [Citation.] This test establishes a low threshold

for initial preparation of an EIR, which reflects a preference for resolving doubts in favor

of environmental review. [Citation.] [¶] When the public agency has already prepared

an EIR . . . [t]he reviewing court upholds an agency’s decision not to require an SEIR if

the administrative record as a whole contains substantial evidence to support the

determination that the changes in the project or its circumstances were not so substantial

as to require major modifications of the EIR. [Citation.]” (Santa Teresa, 114

Cal.App.4th at p. 703.) In short, “ ‘[a]fter a project has been subjected to environmental

review, the statutory presumption flips in favor of the developer and against further

19

review.’ [Citation.]” (Citizens for Responsible Equitable Environmental Development v.

City of San Diego (2011) 196 Cal.App.4th 515, 532 (CREED).)

In this case, we have determined that substantial evidence supports the eighth

addendum’s conclusion that the proposed changes to the Airport Master Plan would not

result in any new significant noise impacts and/or noise impacts that are substantially

different from those described in the 1997 EIR and the 2003 SEIR.

4. Greenhouse Gas Emissions

According to CAAP, the eighth addendum violates CEQA because it failed to

comply with section 15064.4, subdivision (a)7 of the Guidelines by making “ ‘a good-

7

California Code of Regulations, title 14, subdivision 15064.4 states: “(a) The

determination of the significance of greenhouse gas emissions calls for a careful

judgment by the lead agency consistent with the provisions in section 15064. A lead

agency should make a good-faith effort, based to the extent possible on scientific and

factual data, to describe, calculate or estimate the amount of greenhouse gas emissions

resulting from a project. A lead agency shall have discretion to determine, in the context

of a particular project, whether to: [¶] (1) Use a model or methodology to quantify

greenhouse gas emissions resulting from a project, and which model or methodology to

use. The lead agency has discretion to select the model or methodology it considers most

appropriate provided it supports its decision with substantial evidence. The lead agency

should explain the limitations of the particular model or methodology selected for use;

and/or [¶] (2) Rely on a qualitative analysis or performance based standards. [¶] (b) A

lead agency should consider the following factors, among others, when assessing the

significance of impacts from greenhouse gas emissions on the environment: [¶] (1) The

extent to which the project may increase or reduce greenhouse gas emissions as

compared to the existing environmental setting; [¶] (2) Whether the project emissions

exceed a threshold of significance that the lead agency determines applies to the project.

[¶] (3) The extent to which the project complies with regulations or requirements

adopted to implement a statewide, regional, or local plan for the reduction or mitigation

of greenhouse gas emissions. Such requirements must be adopted by the relevant public

agency through a public review process and must reduce or mitigate the project’s

incremental contribution of greenhouse gas emissions. If there is substantial evidence

that the possible effects of a particular project are still cumulatively considerable

notwithstanding compliance with the adopted regulations or requirements, an EIR must

be prepared for the project.”

20

faith effort, based to the extent possible on scientific and factual data, to describe,

calculate, or estimate the amount of greenhouse gas emissions resulting from a

project.’ ”8

City maintains, relying on the decision in CREED, supra, 196 Cal.App.4th 515,

that “[a]nalysis of greenhouse gas impacts was not required when the 1997 EIR or the

2003 Supplemental EIR were prepared, nor is a supplemental EIR required for that

purpose now.” We agree.

A requirement that the potential environmental impact of greenhouse gas

emissions be analyzed was recently added to the Guidelines: “Effective March 18, 2010,

the Guidelines were amended to address greenhouse gas emissions. (Guidelines,

§ 15064.4.) The amendment confirms that lead agencies retain the discretion to

determine the significance of greenhouse gas emissions and should ‘make a good-faith

effort, based to the extent possible on scientific and factual data, to describe, calculate or

estimate the amount of greenhouse gas emissions resulting from a project.’ (Guidelines,

§ 15064.4(a).)” (Citizens for Responsible Equitable Environmental Development v. City

of Chula Vista (2011) 197 Cal.App.4th 327, 336; see also Rialto Citizens for Responsible

Growth v. City of Rialto (2012) 208 Cal.App.4th 899, 940.) Thus, the Guidelines did not

require analysis of greenhouse gas emissions at the time the 1997 EIR and the 2003 SEIR

for the Airport Master Plan were certified.

However, the potential environmental impact of greenhouse gas emissions has

been known since the 1970’s. “ ‘In the late 1970’s, the Federal Government began

devoting serious attention to the possibility that carbon dioxide emissions associated with

8

The Guidelines state that the definition of “ ‘[g]reenhouse gas’ or ‘greenhouse

gases’ includes but is not limited to: carbon dioxide, methane, nitrous oxide,

hydrofluorocarbons, perfluorocarbons and sulfur hexafluoride.” (Cal. Code Regs., tit. 14,

§ 15364.5.)

21

human activity could provoke climate change. In 1978, Congress enacted the National

Climate Program Act, 92 Stat. 601, which required the President to establish a program to

“assist the Nation and the world to understand and respond to natural and man-induced

climate processes and their implications,” [citation]. . . .’ [Citation.]” (CREED, supra,

196 Cal.App.4th at p. 531, quoting Massachusetts v. EPA (2007) 549 U.S. 497, 507-508.)

Moreover, as one appellate court has noted, “ ‘In 2002, information about the

potential impacts of GHGs [greenhouse gases] was widely known. The United Nations

Framework Convention on Climate Change was established in 1992. The regulation of

greenhouse gas emissions to reduce climate change impacts was extensively debated and

analyzed throughout the early 1990s. The studies and analyses of this issue resulted in

the adoption of the Kyoto Protocol in 1997. In the early and mid 2000s, GHG’s and

climate change were extensively discussed and analyzed in California. In 2000, SB 1771

established the California Climate Action Registry for the recordation of greenhouse gas

emissions to provide information about potential environmental impacts.’ ” (Concerned

Dublin Citizens v. City of Dublin (2013) 214 Cal.App.4th 1301, 1319 (Concerned

Citizens).)

Thus, information about the potential environmental impact of greenhouse gas

emissions was known or could have been known at the time the 1997 EIR and the 2003

SEIR for the Airport Master Plan were certified. We reiterate, as stated in CREED, that

under section 21166, subdivision (c), “an agency may not require an SEIR unless ‘[n]ew

information, which was not known and could not have been known at the time the [EIR]

was certified as complete, becomes available.’ ” (CREED, supra, 196 Cal.App.4th at

p. 532.) Since the potential environmental impact of greenhouse gas emissions does not

constitute new information within the meaning of section 21166, subdivision (c), City did

not violate section 15064.4 of the Guidelines by failing to analyze greenhouse gas

emissions in the eighth addendum. (See CREED, supra, at p. 532 [use of addendum

upheld; SEIR was not required because information on the effect of greenhouse gas

22

emissions was known before approval of the 1994 FEIR]; see also Concerned Citizens,

supra, 214 Cal.App.4th at p. 1320 [new Guidelines on greenhouse gas emissions did not

require a SEIR where potential effects of greenhouse gases could have been addressed

when EIR certified in 2002].)

5. Air Quality

Regarding air quality, the eighth addendum concludes that “[t]he proposed

changes to the Airport Master Plan would not result in any new significant air quality

impacts and/or air quality impacts that are substantially different from those described in

the 1997 SJC Master Plan Update EIR.” (Italics omitted.)

In support of this conclusion, the eighth addendum states: “[N]one of the

proposed modifications to the approved Airport Master Plan will result in 1) an increase

in activity levels at the Airport beyond that identified in the Plan, or 2) an increase in the

capacity of the Airport beyond that identified in the Plan. Therefore, emissions of air

pollutants, as pertains to the Airport, and as identified in the 1997 Airport Master Plan

EIR, are not expected to change.”

CAAP briefly argues, in reliance on the decision in Berkeley Jets, that the eighth

addendum “simply states that there will be no change in air pollutants” and that the

change in general aviation operations triggers the need for an updated analysis of toxic air

contaminants.

City responds that the eighth addendum correctly concluded that the proposed

changes to the Airport Master Plan will not result in any significant or substantially

different air quality impacts, since “the 1997 EIR disclosed air pollution for higher levels

of activity at the Airport than that anticipated for the horizon year 2027.”

We determine that CAAP has not met its burden to show that the eighth

addendum’s conclusion regarding air quality is not supported by substantial evidence.

(See American Canyon, supra, 145 Cal.App.4th at p. 1070.) CAAP does not dispute the

evidence showing that daily aircraft operations are projected to decrease from 904.10 in

23

2010 to 722.70 in 2027. Thus, the record contains substantial evidence supporting the

eight addendum’s conclusion that impact of the Airport Master Plan project changes upon

air quality was not substantially different from or greater than the impacts considered in

the previous EIR and SEIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 705.)

The decision in Berkeley Jets does not alter our conclusion. As we have noted,

Berkeley Jets is not applicable here because it did not involve review of an addendum to

an EIR. (Berkeley Jets, supra, 91 Cal.App.4th at p. 1350 [challenge to adequacy of the

EIR prepared for an expansion proposal for the Metropolitan Oakland International

Airport; EIR inadequate due to outdated information about the emission of toxic air

contaminants].)

6. Biological Resource Impacts (Burrowing Owls)

The eighth addendum concludes that “[t]he proposed changes to the Airport

Master Plan would not result in any new significant biologic impacts and/or biologic

impacts that are substantially different from those described in the 1997 SJC Master Plan

Update EIR.” (Italics omitted.)

In support of this conclusion, the eighth addendum states that the 2008 biological

survey showed that the four acres of airfield that will be used for the proposed taxiway

extensions are limited to grassland and herbaceous plants, and that trees and wetlands are

absent. The eighth addendum also states that there is no suitable habitat on the airfield

for any endangered species. However, the eighth addendum acknowledges that

construction of the taxiway extensions will cause the permanent loss of approximately

four acres of burrowing owl habitat. The burrowing owl is a “California species of

concern, . . . known to nest and forage on portions of the Airport, most notably the

unpaved areas of the airfield.” To offset the loss of four acres of burrowing owl habitat,

the eight addendum includes a number of mitigation measures.

CAAP contends that there is no substantial evidence that the changes proposed in

the amendments to the Airport Master Plan “will not be significant” and asserts that the

24

impacts on the burrowing owl habitat “must be studied and subjected to public and

agency review.” Further, CAAP argues that a much more detailed burrowing owl plan

was found inadequate in San Joaquin Raptor Rescue Center v. County of Merced (2007)

149 Cal.App.4th 645 (San Joaquin Raptor). In response, City argues that the eighth

addendum explains that the impact on the burrowing owl habitat will be mitigated as

stated in the Burrowing Owl Management Plan set forth in the 1997 EIR.

Our analysis is again governed by the deferential standard of review that we apply

to an agency’s decision to use an EIR addendum instead of a SEIR. “When an agency

has already prepared an EIR, its decision not to prepare an SEIR for a later project is

reviewed under the deferential substantial evidence standard. [Citation.]” (Santa Teresa,

supra, 114 Cal.App.4th at p. 702.) “ ‘Our function is simply to determine whether the

agency followed proper procedures and whether there is substantial evidence supporting

the agency’s determination that the changes in the Project (or its circumstances) were not

substantial enough to require an SEIR.’ [Citation.]” (Id. at p.704.) Moreover, it has

been held that “[m]itigation measures adopted when a project is approved may be

changed or deleted if the agency states a legitimate reason for making the changes and

the reason is supported by substantial evidence. [Citation.]” (Mani Brothers, supra, 153

Cal.App.4th at p. 1403 [no SEIR required where substantial evidence supported reasons

for changes in EIR’s mitigation measures].)

We determine that, with regard to the burrowing owls, the record contains

substantial evidence to support City’s conclusion that the project changes proposed in the

amendments to the Airport Master Plan were not substantial enough to require an SEIR,

because the impact on the burrowing owl population is not substantially different from or

greater than the impact considered in the 1997 EIR. (See Santa Teresa, supra, 114

Cal.App.4th at p. 705.)

The 1997 EIR for the Airport Master Plan concluded that implementation of the

projects proposed in the Airport Master Plan update would impact the burrowing owl

25

population by replacing 38 acres of their grassland habitat with paving or structures or by

destroying nesting habitat during construction activities. The EIR further stated: “The

elimination of burrowing owl habitat and the potential mortality of burrowing owls due to

construction or operational causes are both direct effects to a California species of special

concern.”

The 1997 EIR included measures to mitigate the impact on the burrowing owl

population, which were set forth in the Burrowing Owl Management Plan. Among other

detailed measures, the Burrowing Owl Management Plan provided that “[a]pproximately

84 acres of infield will be designated specifically for burrowing owl management at the

ends of the runways and between taxiways Y and Z. Burrowing owls that have

established nests in Runway Safety Areas or construction area will be relocated to

designated management areas. Burrowing owl management areas will be mowed

according to the regular mowing regime throughout the Airport infields to maintain the

low, open vegetation that is an important characteristic of burrowing owl habitat.” The

mitigation measures also include the regular monitoring of the burrowing owl population.

The 1997 EIR further states: “The above feasible mitigation measures, which are

incorporated into the Project as a condition of approval, will avoid or substantially lessen

the significant environmental impact described above to a less-than-significant level.”

The mitigation measures included in the eighth addendum additionally provide

that the Airport will offset the four acres of burrowing owls habitat that will be lost when

the taxiway extensions are constructed, by designating four different acres of grassland as

a permanent owl management area. Biologists have recommended that particular

location due to “its proximity to the population of owls on the airfield, its suitable habitat,

and its absence of human activity (except for occasional maintenance). To maintain

comparable habitat conditions for burrowing owls, the vegetation on the . . . site will be

mowed regularly according to the same schedule of mowing for the airfield infields.”

26

The eighth addendum’s mitigation measures also provide that a biologist will

survey the area of the taxiway extensions before construction begins to identify the

burrowing owls’ burrows so that one-way doors can be installed for at least 48 hours, in

order to avoid trapping owls inside a closed burrow. Additionally, the artificial burrows

that will be impacted by the taxiway extensions will be installed elsewhere in the airport.

The eighth addendum states: “This mitigation is part of the Burrowing Owl Management

Plan and is a standard mitigation for all airfield projects.”

Thus, there is substantial evidence in the record to support City’s reasons for

changing the mitigation measures for the impact on the burrowing owl population. (See

Mani Brothers, supra, 153 Cal.App.4th at p. 1403.) Due to the construction of the

taxiway extensions, City will change the location of four acres of the 84 acres originally

designated as the burrowing owl management area in the 1997 EIR, prevent the owls

from being trapped in the burrows, and relocate the impacted artificial burrows. The

newly designated four acres will be managed under the existing Burrowing Owl

Management Plan as set forth in the 1997 EIR. We may therefore reasonably assume that

the mitigation measures incorporated in the eight addendum will maintain the

environmental impacts on the Airport’s burrowing owl population to less a than

significant level. Accordingly, the relocation of four acres of burrowing owl

management area does not constitute “a substantial increase in the severity of previously

identified significant effects” that would warrant a subsequent EIR. (Guidelines,

§ 15162, subds. (a)(1) & (2).)

The decision in San Joaquin Raptor does not aid CAAP’s contrary argument

because that decision did not involve review of an EIR addendum and is otherwise

distinguishable. In San Joaquin Raptor, the CEQA challenge concerned the adequacy of

the EIR’s analysis regarding the impacts on biological resources and wildlife habitat,

including burrowing owl habitat. (San Joaquin Raptor, supra, 149 Cal.App.4th at

p. 668.) The appellate court determined that “[a]lthough many valid mitigation measures

27

are described, no reason is given for deferral of the land management plan concerning the

burrowing owl preserve, nor are any criteria or standards of performance set forth.” (Id.

at p. 671.) In contrast, in the present case there is no indication that the mitigation

measures intended for the burrowing owl population under the Burrowing Owl

Management Plan will be deferred.

D. Conclusion

For these reasons, we find there is substantial evidence in the administrative

record showing that the amendments to the Airport Master Plan that are addressed in the

eighth addendum will not result in any new significant impacts on noise, air quality, and

the burrowing owl habitat that are substantially different from those described in the 1997

EIR and the 2003 SEIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 704;

Guidelines, § 15162, subds. (a)(1) & (2).) Consequently, we also determine that the

amendments (which include changes to the size and location of future air cargo facilities,

the replacement of air cargo facilities with 44 acres of general aviation facilities, and the

modification of two taxiways) do not constitute a new project and do not require a SEIR

under section 21166. We also determine that City did not violate section 15064.4 of the

Guidelines by failing to analyze greenhouse gas emissions in the eighth addendum. We

therefore conclude that the trial court did not err in denying CAAP’s petition for writ of

mandamus.

IV. DISPOSITION

The judgment is affirmed. Costs on appeal are awarded to respondents.

___________________________________________

BAMATTRE-MANOUKIAN, ACTING P.J.

WE CONCUR:

__________________________

MÁRQUEZ, J.

__________________________

GROVER, J.

28

Filed 7/2/14

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

CITIZENS AGAINST AIRPORT H038781

POLLUTION, (Santa Clara County

Super. Ct. No. 110CV177290)

Plaintiff and Appellant,

ORDER CERTIFYING OPINION

v. FOR PUBLICATION

CITY OF SAN JOSE et al.,

Defendants and Respondents.

THE COURT:

The law partnership of Remy, Moose, Manley, LLP; the law firm of Nossaman

Guthner Knox et al; the Silicon Valley Leadership Group; and respondents have

requested that our opinion, filed on June 6, 2014, be certified for publication. Appellant

filed opposition.

It appears that our opinion meets the standards set forth in California Rules of

Court, rules 8.1105(c). The requests are GRANTED. The opinion is ordered published

in the Official Reports.

_________________________________________

BAMATTRE-MANOUKIAN, ACTING P.J.

__________________________________________

MÁRQUEZ, J.

___________________________________________

GROVER, J.

Trial Court: Santa Clara County Superior Court

Superior Court No.: 110CV177290

Trial Judge: Hon. Joseph Huber

Attorney for Appellant: Brandt-Hawley Law Group

Citizens Against Airport Pollution Susan Brandt-Hawley

Attorneys for Respondents: Office of the City Attorney

City of San Jose et al. Margo Laskowska

Office of the City Attorney

Nora Frimann

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.