Opinion

Friends of Maine's Mountains v. Board of Environmental Protection

  • 61 A.3d 689
  • 43 Envtl. L. Rep. (Envtl. Law Inst.) 20056
  • 2013 ME 25
  • 2013 Me. LEXIS 26
  • 2013 WL 791598
Court
Supreme Judicial Court of Maine
Filed
Mar 5, 2013
Status
Published
Author
Silver
On the bench
Saufley, Levy, Silver, Mead, Gorman, Jabar
Cited by
20 cases
Authority
More cited than 84.1%

observing that there exist "extraordinary circumstances ... in which extreme bias completely renders a state adjudicator incompetent and inflicts irreparable harm upon the petitioner"

How later courts described this case

  • observing that there exist "extraordinary circumstances ... in which extreme bias completely renders a state adjudicator incompetent and inflicts irreparable harm upon the petitioner"

Written by the judges who cited it.

The opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions

Decision: 2013 ME 25

Docket: BEP-12-137

Argued: November 8, 2012

Decided: March 5, 2013

Panel: SAUFLEY, C.J., and LEVY, SILVER, MEAD, GORMAN, and JABAR, JJ.*

FRIENDS OF MAINE’S MOUNTAINS et al.

v.

BOARD OF ENVIRONMENTAL PROTECTION et al.

SILVER, J.

[¶1] Friends of Maine’s Mountains, Friends of Saddleback Mountain, and

several individuals1 (collectively, Friends) appeal from a final order of the Board

of Environmental Protection. The Board affirmed the Department of

Environmental Protection’s order approving the application of Saddleback Ridge

Wind, LLC (Saddleback), for a permit to construct the Saddleback Ridge Wind

Project.

[¶2] Friends argues that the Board abused its discretion when determining

which nighttime sound level limit to apply to the applications. Friends also makes

three constitutional arguments: (1) that the Maine Wind Energy Act, 35-A M.R.S.

*

Alexander, J., sat at oral argument but did not participate in the development of the opinion.

1

The record is unclear about which specific individuals are appealing to this Court. The parties that

appealed the Department’s decision to the Board, however, included several individuals who own

properties that are located near the project site and were used in the Noise Impact Study.

2

§§ 3401-3458 (2012)2, denies Friends equal protection by denying protection for

lakes not rated for scenic resources in the Maine’s Finest Lakes Study

(MFL Study); (2) that the Wind Energy Act violates the Separation of Powers

Clause of the Maine Constitution by having overly vague criteria for assessing

visual impact pursuant to 35-A M.R.S. § 3452(3); and (3) that the Department and

Board demonstrated bias, thus violating Friends’s due process rights. We vacate

the Board’s order related to nighttime sound requirements and remand for further

proceedings.

I. BACKGROUND AND PROCEDURE

[¶3] On October 26, 2010, Saddleback filed with the Department

applications pursuant to the Site Location of Development Law and the Natural

Resource Protection Act, seeking a permit to build a wind energy development in

the Towns of Carthage, Canton, and Dixfield. The applications described the

development as a “12-turbine, 33 [megawatt] wind energy project and associated

transmission line and substation.” The applications included a noise impact study

and a visual impact assessment, which the Department hired consultants to review

as part of its application review. The visual impact assessment evaluated the effect

of the project on “scenic resource[s] of state or national significance,” 35-A M.R.S.

2

The Maine Wind Energy Act, 35-A M.R.S. §§ 3401-3458 (2012), was amended in 2011, but the

amendments do not impact this opinion. P.L. 2011, ch. 655 (Apr. 24, 2012); P.L. 2011, ch. 682

(Aug. 30, 2012).

3

§ 3451(9), that are located near the project. It did not assess the visual impact on

Webb Lake, which is located near the project, because the lake is not classified as a

“scenic resource of state or national significance.” The noise impact study

assessed the effect of the noise from the project on the thirty-four residences

located near the project.

[¶4] Friends objected to the permit application, attaching exhibits including

extensive scientific literature on the health effects of the noise emitted by wind

turbines, and requested that the Department hold a public hearing. The

Department reviewed the material, and the acting commissioner for the

Department issued a letter denying the hearing request.

[¶5] In response to the public interest in the project, the Department held a

public meeting, pursuant to 38 M.R.S. § 345-A(5) (2012), in the Town of Dixfield.

During the meeting, many individuals shared their concerns about the project.

Apart from the meeting, the Department also received comments, articles, and

petitions from individuals and organizations both for and against the project. As

part of its opposition to the project, Friends commissioned a report that found that

Webb Lake fulfilled “the definitions for the label ‘significant’ or ‘outstanding’ as

they relate to scenic quality and shoreline character” as assessed in the MFL Study.

[¶6] In its final order, issued by the acting commissioner on

October 6, 2011, the Department approved the application subject to certain

4

conditions. Although only the Department has jurisdiction to grant wind energy

applications, 38 M.R.S. § 341-D(2) (2012) (removing jurisdiction from the Board

for expedited wind energy developments); 35-A M.R.S. § 3451(8)(A) (defining the

Department as the primary siting authority for expedited wind energy

developments), the Board3 conducts appellate review of the Department’s

expedited wind energy development decisions, 38 M.R.S. § 341-D(4)(D) (2012).

On appeal, the Board has the authority to “affirm, amend, reverse or remand to the

commissioner for further proceedings . . . permit decisions regarding an expedited

wind energy development.” Id. The Board is also tasked with responsibility for

“major substantive rulemaking, decisions on selected permit applications . . . and

recommending changes in the law to the Legislature.” 38 M.R.S. § 341-B (2012)

(stating the purpose of the Board).

[¶7] Friends appealed the Department’s order to the Board. On appeal,

Friends requested “a public hearing before an impartial hearing officer” to assist

the Board in understanding the conflicting technical evidence. See 38 M.R.S.

§ 345-A(1-A) (2012) (permitting public hearings at the discretion of the Board).

Friends also challenged the Department’s order regarding its findings on noise,

visual impact, and tangible benefit payments. The Board issued its final order on

3

The Board consists of seven members appointed by the Governor, 38 M.R.S. § 341-C(1) (2012), and

is a subset of the Department, 38 M.R.S. § 341-A(2) (2012) (stating that the Department consists of the

Board and the commissioner).

5

February 18, 2012, denying the request for a public hearing and affirming the

Department’s approval of the permit application.

[¶8] Specifically, the Board affirmed the Department’s decision to apply the

nighttime sound level limit in effect at the time of the order, which was 45 dBA.

The Board also found that the visual impact criteria of the Wind Energy Act

provided adequate guidance for its consideration of the project, and that neither the

Department nor the Board had the authority to treat Webb Lake as a “scenic

resource of state or national significance.” Friends appealed the Board’s order

directly to this Court, pursuant to 38 M.R.S. § 346(4) (2012) (providing the Law

Court with exclusive jurisdiction to review the Board’s final action on expedited

wind energy developments).

[¶9] While Saddleback’s applications were pending before the Department,

the Board, in its role as the body responsible for making rules and providing

guidance to the Legislature, was studying the noise emitted by wind energy

developments. A petition to amend the noise regulation at 2 C.M.R. 06 096 375-6

to -15 § 10 (2001) was filed with the Board on December 17, 2010, sixty days after

Saddleback submitted its permit applications. The Board received comments and

evidence regarding the amendment and held a hearing on July 7, 2011. On

September 15, 2011—twenty-one days before the Department approved

Saddleback’s permit limiting the nighttime noise emission to 45 dBA—the Board

6

provisionally adopted the amendment that, among other changes, lowered the

nighttime sound limit for wind energy projects from 45 dBA to 42 dBA.

Compare 2 C.M.R. 06 096 375-7 § 10(C)(1)(a)(v) (2001) with 2 C.M.R. 06 096

375-15 § 10(I)(2)(b) (2012). The Board submitted the rule to the Legislature for

final adoption, pursuant to 5 M.R.S. § 8072 (2012). After legislative approval, the

amendment went into effect on June 10, 2012.

[¶10] As noted above, the Board’s affirmance of the Department’s decision

to apply the 45 dBA limit to this project occurred on February 15, 2012, five

months after the Board adopted the 42 dBA nighttime sound level limits, subject

only to final legislative approval.

II. DISCUSSION

[¶11] Friends asserts that the Board applied the incorrect nighttime sound

level limit to Saddleback’s permit applications. Additionally, it makes three

constitutional arguments, two of which challenge the constitutionality of the Wind

Energy Act, with the third argument asserting that the Board and Department

violated Friends’s due process rights. We review for an abuse of discretion the

Board’s decision regarding which sound level limit to apply. 5 M.R.S.

§ 11007(C)(6) (2012). “An abuse of discretion may be found where an appellant

demonstrates that the decisionmaker exceeded the bounds of the reasonable

choices available to it, considering the facts and circumstances of the particular

7

case and the governing law.” Sager v. Town of Bowdoinham, 2004 ME 40, ¶ 11,

845 A.2d 567. Whether the Wind Energy Act is constitutional and whether

Friends’s due process rights were violated are questions of law we review de novo.

Town of Frye Island v. State, 2008 ME 27, ¶ 13, 940 A.2d 1065 (regarding

constitutionality of statutes); State v. Bilynsky, 2008 ME 33, ¶ 5, 942 A.2d 1234

(regarding due process).

A. Nighttime Sound Level Limits

[¶12] The Board regulates the sound levels of wind projects to protect “the

health and welfare of nearby neighbors.” 2 C.M.R. 06 096 375-6 § 10(A) (2012).

In order to fulfill this goal, the Board’s rules provide it with the flexibility

necessary to impose limits on proposed wind projects so that sound levels are

adequately controlled. 2 C.M.R. 06 096 375-10 § 10(E) (2012).4 See also Martha

A. Powers Trust v. Bd. of Envtl. Prot., 2011 ME 40, ¶ 12, 15 A.3d 1273 (noting

that the Board may alter sound level limits). The Department and then the Board

are solely responsible for ensuring that wind energy developments do not present

4

The Board has discretion pursuant to 2 C.M.R. 06 096 375-10 § 10(E) (2012):

The Board may, as a term or condition of approval, establish any reasonable requirement

to ensure that the developer has made adequate provision for the control of noise from the

development and to reduce the impact of noise on protected locations. Such conditions

may include, but are not limited to, enclosing equipment or operations, imposing limits

on hours of operation, or requiring the employment of specific design technologies, site

design, modes of operation, or traffic patterns.

8

undue hazards to the health of Maine’s people.5 While acting in its legislative

capacity, the Board recognized that the 45 dBA limit did not adequately protect the

health and welfare of a project’s neighbors. Here, by applying the 45 dBA limit,

the Board failed to meet its statutory obligation to protect the health and welfare of

the project’s neighbors. In so doing, it abused its discretion.

[¶13] Saddleback’s permit application shows that the project does meet the

45 dBA nighttime sound level limit, as required by the pre-amendment rules. See

2 C.M.R. 06 096 375-7 § 10(C)(1)(a)(v) (2001). The application does not show,

however, that the project meets the amended nighttime sound level limit of

42 dBA. See 2 C.M.R. 06 096 375-15 § 10(I)(2)(b) (2012). On appeal, the Board

“is not bound by the [acting] commissioner’s findings of fact or conclusions of law

but may adopt, modify or reverse findings of fact or conclusions of law established

by the commissioner.” 38 M.R.S. § 341-D(4)(A) (2012). However, the Board

generally must limit its factual consideration to the Department’s record.

38 M.R.S. § 341-D(4)(D). Here, Friends provided the Department with essentially

the same evidence it provided the Board regarding the rule amendment. As a

result, the evidence the Board reviewed for the appeal of Saddleback’s permit

included the evidence that it reviewed for the rule amendment, i.e., the evidence

5

In addition to issues concerning noise, the Department and Board are also responsible for ensuring

that wind power projects do not cause groundwater contamination. 2 C.M.R. 06 096 375-5 § 7 (2012).

9

that convinced the Board that wind project nighttime noise of 45 dBA or louder

has a negative effect on the health of residents who live near wind project sites.

Saddleback provided substantial evidence showing that the modeled sound level

limit would meet the then-existing level of 45 dBA. It did not attempt to show that

the project would meet the 42 dBA limit.

[¶14] The Board does not commit an abuse of discretion simply by making

discretionary judgments that we, as a reviewing court, disagree with. Sager,

2004 ME 40, ¶ 11, 845 A.2d 567. Here, however, the Board, in its legislative role,

explicitly determined that 45 dBA does not protect nearby residents as a nighttime

sound level limit for wind projects, but it does nonetheless continue to apply that

sound level limit in its adjudicatory role.6

[¶15] As discussed above, in its legislative capacity, the Board adopted the

reduced sound level limit in order to minimize the impact from wind projects on

the health of nearby residents, noting “[t]he available data demonstrates that

persons living near existing wind energy development with actual sound level

measurements near the 45 dBA limit . . . are experiencing adverse effects.” The

Board made this finding and took this action before Friends appealed the

Department’s decision to it.

6

Pursuant to 38 M.R.S. § 341-H(1) (2012) the Board is tasked with amending substantive rules, such

as the rule at issue here. The Department’s staff reviews and comments on the change, but the Board

makes the final decision regarding the amendment. See 38 M.R.S. § 341-H(3) (2012) (describing the

Department’s role in rulemaking).

10

[¶16] Saddleback’s noise impact study shows that the modeled nighttime

sound level at the most significantly affected residence7 is 44 dBA, and it asserts

that due to the use of conservative models, the monitored level is likely to be even

lower. The Board appeared to rely on this model calibration in its decision to

uphold the Department’s approval of the permit application, stating:

If the Board was convinced under specific facts that requiring lower

sound levels in the modeling results was necessary in order to achieve

adequate control of noise from a development the Board could do so

under Chapter 375(10)(E). However, the Board finds that the

Chapter 375 standards currently in effect should adequately control

noise due to the reliability of the model and the facts and assumptions

used by the applicant in its modeling.

In essence, the Board found that the residents would not be exposed to the effects

of 45 dBA nighttime sound levels, but instead the noise would be somewhere

below that limit. There is no indication, however, that the nighttime sound levels

would be as low as 42 dBA.8

7

This residence is 1133 meters, or 3716 feet, from the closest turbine. The buffer area around this

residence has a modeled nighttime sound level of 45 dBA.

8

It is unclear from the record how the Department and Board intend to enforce sound level limits for

wind projects. In its response to public comment, the Board noted, “[T]he 42 dBA sound limit is an

enforceable standard which must be met regardless of pre-development modeling predictions.” The

Board’s rules provide guidance on obtaining measurements for enforcement, but not on the enforcement

procedure. 2 C.M.R. 06 096 375-14 § 10(H)(4.1)(a) (2012). If the Board enforces the 42 dBA limit after

approving the permits pursuant to the 45 dBA limit, then Saddleback is subjected to an unfair double

standard. If the Board enforces the project pursuant to the 45 dBA standard, then any potential benefit is

not guaranteed after construction, leaving the residents without protection. By requiring Saddleback’s

model to comply with the amended limits, the project is treated with consistency and the residents’ health

is protected.

11

[¶17] Because the Board is responsible for regulating sound levels in order

to minimize health impacts—and because when doing so it determined that the

appropriate nighttime sound level limit to minimize health impacts is 42 dBA—the

Board abused its discretion by approving Saddleback’s permit applications.9

Although the project’s models predict nighttime sound levels slightly below

45 dBA, the Board failed to give the nearby residents the acknowledged protection

of the amended rules. We vacate the Board’s order and remand for further review

using the 42 dBA nighttime sound level limit as introduced in 2 C.M.R. 06 096

375-15 § 10(I)(2)(b) (2012).

B. Equal Protection Clause and the Wind Energy Act

[¶18] Friends argues that the Wind Energy Act violates the Equal Protection

Clause by refusing to treat Webb Lake as a “scenic resource of state or national

significance.” Because the users of Webb Lake are not members of a suspect

class, Friends must show “(1) that similarly situated persons are not treated equally

under the law, and (2) that the statute is not rationally related to a legitimate state

interest.” MacImage of Me., LLC v. Androscoggin Cnty., 2012 ME 44, ¶ 33,

40 A.3d 975 (quotation marks omitted).

9

To be clear, we do not determine that the provisional rules became applicable to the previously

pending application as a matter of law. Rather, in this case, where the Board is directly responsible for

protecting the public health, we conclude that the Board cannot ignore its own findings related to public

health in deciding whether the project is harmful to the public.

12

[¶19] When reviewing a permit application pursuant to the Wind Energy

Act, the Board determines whether the project “significantly compromises views

from a scenic resource of state or national significance.” 35-A M.R.S. § 3452(1).

The phrase “scenic resource of state or national significance” is defined in relation

to “great ponds” in organized areas as: “One of the 66 great ponds located in the

State’s organized area identified as having outstanding or significant scenic quality

in the ‘Maine’s Finest Lakes’ study . . . .” 35-A M.R.S. § 3451(9)(D)(1). In 1989,

the Department of Conservation’s Land Use Regulation Commission conducted an

assessment that inventoried a variety of natural values associated with Maine lakes

that are ten acres or larger in size. The findings from this assessment were

published in the MFL Study, which noted that “these lake ratings should be

regarded as minimal findings.” Although Friends presented evidence that Webb

Lake meets all of the necessary criteria to have an “outstanding” or “significant”

rating in the MFL Study, the lake did not receive such a rating.

[¶20] The Legislature enacted the Wind Energy Act as a means to promote

wind as a renewable energy source and streamline the permitting process for wind

energy. See 35-A M.R.S. § 3402(1)-(2).10 We have previously held that the “state

10

The general purpose of the Wind Energy Act is stated in 35-A M.R.S. § 3402:

The Legislature finds that it is in the public interest to explore opportunities for and

encourage the development, where appropriate, of wind energy production in the State in

a manner that is consistent with all state and federal environmental standards and that

13

interest in facilitating the rapid development of alternative, renewable energy

resources” is a legitimate interest that rationally relates to provisions in the Wind

Energy Act. Friends of Lincoln Lakes v. Bd. of Envtl. Prot., 2010 ME 18, ¶¶ 1, 30,

989 A.2d 1128 (rejecting an equal protection argument regarding the Board’s

jurisdiction for wind permit applications and the direct appeals to this Court

allowed by the Wind Energy Act). Here, the State streamlined the permitting

process by concisely defining a “scenic resource of state or national significance.”

Because this statutory definition rationally relates to the State’s legitimate interest

in promoting wind energy and using an efficient permitting process, it does not

violate the Equal Protection Clause.

C. Separation of Powers Clause and the Wind Energy Act

[¶21] Friends argues that the Wind Energy Act’s criteria for assessing visual

impact, 35-A M.R.S. § 3452(3), is overly vague and, therefore, it results in an

unlawful delegation that violates the Separation of Powers Clause. A statute is not

achieves reliable, cost-effective, sustainable energy production on those sites in the State

that will attract investment and permit the development of viable wind energy

projects. . . . The Legislature finds it is in the public interest to encourage the

construction and operation of community wind power generation facilities in the State.

The Wind Energy Act also states findings related to the regulatory process in 35-A M.R.S. § 3402(2):

The Legislature finds that it is in the public interest to reduce the potential for

controversy regarding siting of grid-scale wind energy development by expediting

development in places where it is most compatible with existing patterns of development

and resource values when considered broadly at the landscape level. Accordingly, the

Legislature finds that certain aspects of the State’s regulatory process for determining the

environmental acceptability of wind energy developments should be modified to

encourage the siting of wind energy developments in these areas.

14

an unlawful delegation of power if it offers “an intelligible principle to which the

person or body authorized to act is directed to conform.” Uliano v. Bd. of Envtl.

Prot., 2009 ME 89, ¶ 30, 977 A.2d 400 (quotation marks omitted). In evaluating

the statute, we will, if possible, “construe the statute to preserve its

constitutionality.” Town of Baldwin v. Carter, 2002 ME 52, ¶ 9, 794 A.2d 62.

Although it is preferable for statutes to have clarity, “[o]bjective quantification,

mathematical certainty, and absolute precision are not required by either the United

States Constitution or Maine Constitution.” Id. ¶ 7 n.2.

[¶22] The criteria in dispute consist of six factors the Board considers when

making its determination regarding a wind energy project’s impact on scenic

resources. 35-A M.R.S. § 3452(3)(A)-(F).11 These criteria are not easily

quantified. See Uliano, 2009 ME 89, ¶ 30, 977 A.2d 400 (noting that “scenic and

aesthetic uses are not readily susceptible to quantitative analysis”). Even the

11

The statute, 35-A M.R.S. § 3452(3)(A)-(F), lists the factors as follows:

A. The significance of the potentially affected scenic resource of state or national

significance;

B. The existing character of the surrounding area;

C. The expectations of the typical viewer;

D. The expedited wind energy development’s purpose and the context of the proposed

activity;

E. The extent, nature and duration of potentially affected public uses of the scenic

resource of state or national significance and the potential effect of the generating

facilities’ presence on the public’s continued use and enjoyment of the scenic resource of

state or national significance; and

F. The scope and scale of the potential effect of views of the generating facilities on the

scenic resource of state or national significance, including but not limited to issues related

to the number and extent of turbines visible from the scenic resource of state or national

significance, the distance from the scenic resource of state or national significance and

the effect of prominent features of the development on the landscape.

15

Department’s expert from Scenic Quality Consultants, who reviewed the visual

impact assessment, initially found the criteria difficult to interpret and apply.

Regardless, we do not find statutes unconstitutional merely due to difficult

application. See Town of Baldwin, 2002 ME 52, ¶ 7 n.2, 794 A.2d 62 (discussing

the difficulty in defining an “annoying” dog bark). In Uliano, we upheld the

“existing scenic and aesthetic use standard” of the National Resource Protection

Act, 38 M.R.S. § 480-D(1) (2012), despite its non-quantifiable and difficult to

apply characteristics. 2009 ME 89, ¶¶ 25-28, 977 A.2d 400. We upheld that

statute because it provided sufficient guidance to the agency regarding its

application, and any risk that the agency would commit an abuse of discretion was

tempered by the Maine Administrative Procedure Act and agency regulations. Id.

See also In re Spring Valley Dev., 300 A.2d 736, 749-52 (Me. 1973) (declining to

find the Site Location Law unconstitutionally vague). Here, the statute has similar

guidance and protections and, therefore, it is not so vague as to constitute a

violation of the Separation of Powers Clause.

D. Due Process Rights and the Bias

[¶23] Finally, Friends argues that its due process rights were violated

because the Department and Board were not impartial fact-finders. Due process

requires a fair and unbiased hearing. Lane Constr. Corp. v. Town of Washington,

2008 ME 45, ¶ 29, 942 A.2d 1202. In order to show bias, however, Friends must

16

present evidence sufficient to overcome a presumption that the fact-finders, as state

administrators, acted in good faith. Mallinckrodt LLC v. Littell, 616 F. Supp. 2d

128, 142 (D. Me. 2009); see Mutton Hill Estates, Inc. v. Town of Oakland,

468 A.2d 989, 991 (Me. 1983) (finding bias due to ex parte meetings). Although

the Department and Board ruled against Friends, the rulings do not demonstrate

bias. As a result, Friends’s due process rights were not violated.

The entry is:

Judgment vacated and remanded for further

proceedings consistent with this opinion.

On the briefs:

Rufus E. Brown, Esq., Brown & Burke, Portland, for appellants Friends of

Maine’s Mountains, Friends of Saddleback Mountain, and several

individuals

William J. Schneider, Attorney General, and Gerald D. Reid, Asst. Atty.

Gen., Augusta, for appellee Board of Environmental Protection

Gordon R. Smith, Esq., and Juliet T. Browne, Esq., Verrill Dana, LLP,

Portland, for appellee Saddleback Ridge Wind, LLC

At oral argument:

Rufus E. Brown, Esq., for appellants Friends of Maine’s Mountains, Friends

of Saddleback Mountain, and several individuals

Gerald D. Reid, Asst. Atty. Gen., for appellee Board of Environmental

Protection

17

Gordon R. Smith, Esq., for appellee Saddleback Ridge Wind, LLC

Board of Environmental Protection case number L-25137

FOR CLERK REFERENCE ONLY

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.