The opinion

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF COLUMBIA

______________________________

)

UNITED STATES OF AMERICA, )

)

Plaintiff, )

)

v. ) Civil Action No. 04-1608 (RWR)

)

DRC, INC., )

)

Defendant. )

______________________________)

MEMORANDUM OPINION AND ORDER

The government brings suit against defendant DRC, Inc. (also

known as Disaster Relief Construction, Inc.) under the False

Claims Act (“FCA”), 31 U.S.C. §§ 3729 et seq., alleging that DRC

submitted false pre-qualification documents and false invoices in

connection with a contract awarded to DRC to provide relief

assistance in Honduras that was financed by the United States

Agency for International Development (“USAID”). DRC filed a

motion for partial summary judgment on the false invoices claim.

The claim alleges that DRC’s unauthorized subcontracting of work

violated the terms of DRC’s contract with Honduras. The parties

dispute whether the contract required DRC to seek USAID’s

approval for subcontracting and, if so, whether DRC’s invoices

were false because they impliedly certified that DRC had complied

with that obligation when it had not. There are genuine

issues of material fact with respect to elements of the false

- 2 -

invoices claim with regard to claims for payment submitted from

December 2000 to April 2001 and after October 2001. However, the

government cannot show that DRC possessed the scienter required

to give rise to FCA liability with respect to claims for payment

submitted between April 2001 and October 2001. DRC’s motion for

partial summary judgment therefore will be granted in part and

denied in part.

BACKGROUND

The contract at the heart of this dispute was financed by

USAID in order to help Honduras and other countries rebuild after

Hurricane Mitch struck in 1998. USAID collaborated with the

Honduran Social Investment Fund (“FHIS”), an agency of the

government of Honduras, on a project to construct and reconstruct

water, sewer, and sanitation infrastructure in the wake of the

hurricane. (Am. Compl. ¶ 10.) DRC participated in a competitive

bidding process for a contract to perform the construction work

and in connection with its bid submitted numerous pre-

qualification documents representing its equipment, inventory,

personnel, and financial obligations. (Id. ¶¶ 11-12.) The pre-

qualification documents also requested information about the

contractor’s plans to subcontract. (Pl.’s Opp’n to Def.’s First

Mot. Partial Summ. J. (“Pl.’s Opp’n”), Exs. 4 and 5.) DRC did

not identify any subcontractors with which it planned to work and

- 3 -

represented that the company had no intention of subcontracting.

(Id.)

On the basis of its pre-qualification score and low bid, DRC

obtained a contract for construction projects in Honduras. (Am.

Compl. ¶ 13.) The contract took the form of a “host country

contract,” an agreement between a foreign country and a

third-party contractor, where USAID provides funding but is not

itself a party. (Def.’s Reply in Support of Def.’s First Mot.

Summ. J. (“Def.’s Reply”), Def.’s Stmt. of Undisputed Facts for

Def.’s First Mot. Summ. J. (“Def.’s Stmt. Undisputed Facts”)

¶¶ 10-11.) DRC ultimately submitted twenty eight vouchers for

payment under the contract (Compl., Ex. C), each of which the

government alleges constitutes a false claim (Am. Compl. ¶¶ 30-

36).

I. SUBCONTRACTING OBLIGATIONS IN THE CONTRACT

The construction contract between DRC and FHIS was executed

on June 21, 2000. (Def.’s Stmt. Undisputed Facts ¶ 26.) The

contract contained twelve constituent sections, many of which

were written only in Spanish.1 (Id. ¶¶ 4-5.) USAID required the

inclusion of two of those sections, Attachment A and Attachment B

(“the Mandatory Clauses”), which were rendered both in Spanish

and in English. (Id. ¶¶ 6-7.)

1

Renditions in this opinion of provisions written in Spanish

rely on the parties’ translations, the accuracy of which has not

been contested.

- 4 -

Multiple provisions in the contract addressed

subcontracting. First, Section 28 of the contract provided that

“[t]he contractor may not . . . subcontract with third parties

without obtaining the advance, written consent of FHIS and

USAID.” (Id. ¶ 20; Def.’s First Mot. Summ. J., Ex. 2.) Section

28 further provided that subcontracted work could not exceed 40

percent of the total work budget. (Def.’s Stmt. Undisputed Facts

¶ 21.) The contract listed five instances in which payment could

be withheld, including “[f]ailure of the Contractor to make

payments due to subcontractors for materials or labor.” (Id.

¶ 157.)

Second, both Attachment A, in Section 3(G)(2)(e), and

Attachment B, in Section 3(F)(2)(e), state that “[u]nder a fixed-

price construction contract of any value, the prime contractor

may procure locally produced goods and services under

subcontracts.” (Id. ¶¶ 16-17; Def.’s First Mot. Summ. J., Ex.

3.)

Third, both Attachments, in Section 2, provide that “the

Contract has reserved to USAID certain rights such as . . . the

right to approve the terms of this Contract, the Contractor, and

any or all . . . subcontracts . . . related to this Contract and

the Program/Activity of which it is part.” (Def.’s First Mot.

Summ. J., Ex. 3.) Section 2 in Attachment A further states that

“[a]ny approval (or failure to disapprove) by USAID shall not bar

- 5 -

the Contracting Agency or USAID from asserting any right, or

relieve the Contractor of any liability which the Contractor

might otherwise have to the Contracting Agency or USAID.” (Id.)2

Finally, Attachment A contains Section 14, entitled

“Assignment, Subcontract Clauses and Procurements.” Subsection A

provides that “USAID’s prior written consent to any assignment of

obligations under the Contract, in addition to the consent of the

Contracting Agency, is required”; subsection B obligates the

contractor to include specified provisions of the Attachment in

all subcontracts. (Id.)3

II. DRC’S NEGOTIATIONS CONCERNING SUBCONTRACTING

FHIS issued a notice to proceed on June 23, 2000, two days

after the contract was executed, giving DRC fifteen days in which

to begin work. (Def.’s Stmt. Undisputed Facts ¶ 27.) According

to DRC’s Executive Vice President, Sid Vogel, he told FHIS on

July 3, 2000 that DRC planned to subcontract and submitted a list

of subcontractors for FHIS approval at a meeting with Moises

Starkman, the Minister of FHIS, Ramon Cardona, the FHIS director

of major infrastructure projects (the “DIM”) who was responsible

for administering the contract, and others. (Def.’s First Mot.

2

Section 2 in Attachment B contains the same language, but

refers to the “Supplier” rather than the “Contractor.” (Def.’s

First Mot. Summ. J., Ex. 3.)

3

The analogous section 14 in Attachment B is entitled

simply “Assignment” and contains only the requirement of prior

written consent for assignment of obligations. (Id.)

- 6 -

Partial Summ. J., Ex. 8 (Vogel Dep. 71:20-72:10, 152:18-153:20).)

Vogel testified that he asked Starkman the next day “what

[Starkman] want[ed] [Vogel] to do” and Starkman “told [Vogel] to

go to work,” which Vogel understood to constitute “approval [for

DRC] to . . . go out there and go to work with these

subcontractors.” (Id. 72:11-15.)

Several months later, on November 7, 2000, Cardona sent a

letter to DRC stating that FHIS had “been informed” that DRC was

engaged in subcontracting and reminding DRC that the project “can

only be contracted up to 40 percent of the project, previous

authorization from FHIS.” (Def.’s First Mot. Partial Summ. J.,

Ex. 9.) The letter concluded, “[w]e would appreciate that you do

not effect any subcontractions [sic] without previous

authorization.” (Id.) Cardona sent a copy of the letter to Todd

Sloan, the head of the USAID section that administered the

construction contract. (Def.’s Stmt. Undisputed Facts ¶¶ 32-33.)

On November 8, 2000, DRC submitted “participation contracts” to

FHIS in order to receive FHIS’s legal evaluation of whether those

contracts required formal approval under the construction

contract. (Id. ¶ 37.) In the preceding months, DRC “had

replaced its original subcontracts with ‘participation contracts’

and argued, based on advice of Honduran legal counsel, that the

Contract did not require DRC to obtain further approval from FHIS

concerning these ‘participation contracts’ and [that] the 40

- 7 -

percent [subcontracting] limit did not apply.’” (Def.’s First

Mot. Partial Summ. J., Def.’s Stmt. of Material Facts (“Def.’s

Stmt. of Material Facts”) ¶ 34 (citing Ex. 11, Pelaez Dep. at

115:16-118:11; 27:22-28:7).) FHIS issued a legal opinion on

November 11, 2000 that the participation contracts did require

approval and were subject to the limit. (Def.’s Stmt. Undisputed

Facts ¶ 38.)

After receiving FHIS’s legal opinion, DRC Project Manager

Francisco Pelaez submitted a memorandum on November 15, 2000

addressed to Starkman acknowledging the parties’ difference of

opinion about the status of participation agreements and, given

FHIS’s legal position, submitting a list of subcontractors for

the approval of both FHIS and USAID. (Def.’s Stmt. Undisputed

Facts ¶¶ 39-40; Def.’s First Mot. Partial Summ. J., Ex. 18.) The

memorandum represented that, regardless of the form of agreement

with local companies, the budgeted amount was below the 40

percent threshold. (Id.) A series of meetings and letter

exchanges among DRC, FHIS, and USAID followed, lasting several

months. (Def.’s Stmt. Undisputed Facts ¶ 42.) DRC requested

USAID and FHIS approval for subcontracting again later in

November, along with revised subcontract forms. (Id. ¶¶ 61-63.)

A report by a USAID auditor, Christine Byrne, who visited DRC

work sites in November noted that at several work sites it

appeared that DRC had subcontracted the vast majority of the

- 8 -

work. (Def.’s First Mot. Partial Summ. J., Ex. 12.) From

December through early March, DRC submitted several requests to

FHIS requesting approval for subcontractors, copying USAID on the

letters. (Def.’s Stmt. Undisputed Facts ¶¶ 65, 66, 68, 69, 71-

73, 75, 76, 78, 79.) In January 2001, Sloan wrote to Cardona and

expressed USAID’s concern about one subcontractor currently

working for DRC and requested additional information about the

subcontractor. (Id. ¶ 75.) Cardona forwarded USAID’s request to

DRC. (Id. ¶ 76.)4

At various points during these negotiations, USAID officials

suggested that the portion of overall work that DRC subcontracted

was not important. USAID contracting head John McAvoy drafted a

December 6, 2000 letter, signed by USAID Mission Director Timothy

Mahoney, in which USAID asked FHIS to increase the permissible

subcontracting quota from 40 percent to 75 percent. (Def.’s

First Mot. Partial Summ. J., Ex. 39; id., Ex. 1 (McAvoy Dep.

39:9-41:7).) USAID Deputy Mission Director Joseph Lombardo

testified that the 40 percent limit was a matter of local law and

that, from USAID’s perspective, “they could be contracting out 99

4

The adequacy of DRC’s response is a disputed point between

the parties. DRC maintains that it had previously provided the

requested information and informed FHIS of that fact, while the

government contends that DRC never provided the information.

(Def.’s Stmt. of Material Facts ¶ 77; Pl.’s Opp’n to Def.’s Stmt.

of Material Facts in Supp. of First Mot. Partial Summ. J. ¶ 77.)

- 9 -

percent of it and we wouldn’t care.” (Def.’s First Mot. Partial

Summ. J., Ex. 68 (Lombardo Dep. 120:16-121:9).5

FHIS eventually, on March 19, 2001, issued a formal

resolution approving DRC’s subcontracting, subject to USAID

review. (Id. ¶¶ 43-44.) At a meeting with DRC and FHIS on

April 6, 2001, Carlos Flores, a USAID technical officer who

worked under Sloan, represented orally that Flores would be the

“sole representative of USAID in charge of dealing with matters

related to the project” and that approval by USAID “is not

necessary to authorize DRC subcontracting endeavors.” (Def.’s

First Mot. Partial Summ. J., Ex. 24 (Memorandum of Francisco

Pelaez relating minutes of meeting); see also id., Ex. 11 (Pelaez

Dep. 81:9-82:2); Def.’s Stmt. of Material Facts ¶¶ 46-48.)6

5

According to DRC, the inclusion of the 40 percent limit on

subcontracting rested on a mistaken interpretation of Honduran

law. The provisions imposing the limit came verbatim from

Article 88 of the Honduras State Contracting Law, which restricts

the amount a domestic contractor may subcontract on public

projects to a maximum of 40 percent. (Def.’s Stmt. Undisputed

Facts ¶¶ 112-113.) However, Article 123 of the same law requires

that foreign companies subcontract a minimum of 40 percent of

work to local companies. (Id. ¶ 115.) The origin of this

provision is not relevant to the resolution of the instant

motion. The government’s theory of implied false certification

is that USAID approval of DRC’s subcontractors was material to

payment, irrespective of the allowable amount of subcontracting

under the contract.

6

The government does not dispute that Flores made these

statements to DRC. (Cf. Pl.’s Opp’n to Def.’s Stmt. of Material

Facts in Supp. of First Mot. Partial Summ. J. at 3, 7.)

- 10 -

In June 2001, DRC changed the subcontractors assigned to

certain project sites and advised FHIS and USAID of the changes.

(Def.’s Stmt. Undisputed Facts ¶ 90.) In August 2001, DRC’s new

project manager, Mario Maciel, sought a formal response from

Sloan about subcontracting by sending a copy of the March 2001

FHIS resolution and stating that DRC “assume[d] that [Sloan] had

no objections to th[e] approval.” (Def.’s First Mot. Partial

Summ. J., Ex. 66.) Sloan’s response is a disputed point between

the parties. DRC proffers an undated, unsigned “draft response”

from Sloan to Maciel, in which Sloan stated that USAID is

“concerned that DRC, Inc. previously subcontracted work . . .

without the prior approval of USAID and FHIS,” but that “[i]n

light of the need to complete the work . . ., [USAID] will raise

no objection to the approval by FHIS set forth in the FHIS

Resolution; however, USAID reserves all of its rights with

respect to the subcontracting of work by DRC, Inc. . . . without

the prior approval of USAID and FHIS.” (Def.’s First Mot.

Partial Summ. J., Ex. 67.) The government meanwhile proffers a

letter to Maciel, signed by Sloan and dated October 16, 2001, in

which Sloan states “subcontracting requires prior written

approval of FHIS and USAID” and that “USAID (i) cannot

retroactively approve the subcontracting of work already

completed under the Group I Contract, (ii) reserves all its

rights regarding compliance with Section 28 of the Group I

- 11 -

Contract.” (Pl.’s Opp’n, Ex. 15.) The letter then enumerated

the information and documents that DRC should submit to secure

USAID approval in the future. (Id.)

During the ongoing discussions about DRC’s subcontracting,

USAID issued a Letter of Commitment, on December 5, 2000, in

which it “guarantee[d] payment” to DRC “in accordance with the

terms and conditions specified in the contract.” (Def.’s First

Mot. Partial Summ. J., Ex. 70.) DRC submitted on December 11,

2000 its first invoice for work performed (Def.’s Stmt.

Undisputed Facts ¶ 53), and it certified that “the services

. . . for which payment is requested have been satisfactorily

performed (delivered) and the payment requested is in accordance

with the terms of the contract.” (Compl., Ex. C2.)7 Each

subsequent invoice contained an identical certification. (Id.,

Exs. C3-C28.)

III. THE SUIT

The government filed suit under the False Claims Act in

September 2004. The government alleges that DRC made false

statements in its pre-qualification documents regarding its

inventory, equipment, and personnel (Am. Compl. ¶¶ 16-23), and

that it falsely certified performance of work that had actually

been completed by unauthorized subcontractors (Am. Compl. ¶¶ 24-

7

It is undisputed that DRC’s first invoice, submitted

July 3, 2000, was for mobilization only, and not for work

performed. (Def.’s Stmt. Undisputed Facts ¶ 52; Compl., Ex. C1.)

- 12 -

34). DRC’s motion to dismiss for failure to state a claim, lack

of personal jurisdiction, and improper venue, or, alternatively,

to transfer, was denied.

In its pending motion for partial summary judgment, DRC

argues that its invoices were not false because the underlying

contract permitted subcontracting, because the FHIS approved the

subcontracting and USAID told FHIS and DRC that USAID approval

was unnecessary, and because DRC’s invoices did not impliedly

certify that no unapproved subcontracting had taken place. DRC

also argues that it is entitled to judgment on the false invoices

claim because DRC lacked the requisite scienter and because the

government did not suffer any actual damages from DRC’s

subcontracting. DRC’s motion for partial summary judgment does

not address the government’s allegations regarding the pre-

qualification process.8

8

In addition to asserting liability on the basis of a false

implied certification theory, the government’s opposition also

appears to contend that DRC may be liable under a fraudulent

inducement theory because DRC would not have been awarded the

contract had USAID known of its intent to subcontract

extensively. (Pl.’s Opp’n at 9-11.) This argument overlaps with

the government’s distinct pre-qualification documents claim -- on

which DRC has not moved for summary judgment -- that DRC would

not have obtained the contract had it not misrepresented its

inventory, personnel, and equipment. DRC does not directly

address the fraudulent inducement theory in its motion or in its

reply.

- 13 -

DISCUSSION

A party may move for summary judgment on an individual claim

or part of a claim. Fed. R. Civ. P. 56(a). Summary judgment may

be granted when the pleadings, the discovery and disclosure

materials on file, and any affidavits show “that there is no

genuine dispute as to any material fact and the movant is

entitled to judgment as a matter of law.” Id.; see also Moore v.

Hartman, 571 F.3d 62, 66 (D.C. Cir. 2009). A court considering a

motion for summary judgment must draw all “justifiable

inferences” from the evidence in favor of the nonmovant.

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986). The

nonmovant must either “come forward with specific facts showing

that there is a genuine issue for trial[,]” or show that the

materials by the movant do not establish the absence of a genuine

dispute. Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio

Corp., 475 U.S. 574, 587 (1986) (internal quotation marks and

emphasis omitted).

The FCA created a cause of action against anyone who

“knowingly presents, or causes to be presented, to an officer or

employee of the United States Government . . . a false or

fraudulent claim for payment or approval[.]” 31 U.S.C.

§ 3729(a)(1) (2000).9 “[T]he elements of section 3729(a)(1) are

9

Congress amended the FCA in the Fraud Enforcement and

Recovery Act of 2009 (“FERA”), altering slightly the language in

the presentment provision. The amendment of the presentment

- 14 -

(1) the defendant submitted a claim to the government, (2) the

claim was false, and (3) the defendant knew the claim was false.”

United States ex rel. Harris v. Bernad, 275 F. Supp. 2d 1, 6

(D.D.C. 2003). “Any request for payment is properly considered a

claim for purposes of the FCA.” United States ex rel. Siewick v.

Jamieson Sci. & Eng’g, Inc., 214 F.3d 1372, 1375-76 (D.C. Cir.

2000); see also 31 U.S.C. § 3729(c) (defining claim broadly to

include “any request or demand, whether under a contract or

otherwise, for money or property which is made to a contractor,

grantee, or other recipient if the United States Government

provides any portion of the money or property which is requested

or demanded.”)

A claim may be “legally false” if it represents falsely that

the party submitting the claim has complied with an applicable

federal statute or regulation, or with a contractual term.

United States v. Sci. Applications Int’l Corp., 626 F.3d 1257,

1266 (D.C. Cir. 2010) (“SAIC”). Such a “false certification” can

be inferred from silence if “certification was a prerequisite to

the government action sought.” Siewick, 214 F.3d at 1376. “To

establish FCA liability under an implied certification theory,

provision took “effect on the date of enactment of this Act and

shall apply to conduct on or after the date of enactment[.]”

Pub. L. No. 111-21, § 4, 123 Stat. 1617, 1625 (2009). Since the

alleged conduct here occurred before 2009, the provision as

amended in 2009 does not apply here, and references in this

opinion to § 3729(a)(1) are to the pre-amendment version.

- 15 -

the plaintiff must prove by a preponderance of the evidence that

compliance with the legal requirement in question is material to

the government’s decision to pay.” SAIC, 626 F.3d at 1271. The

materiality of a contractual requirement may be evident from

“[t]he existence of express contractual language specifically

linking compliance to eligibility for payment.” Id. at 1269.

But a contractual requirement can also be considered material in

the absence of express language if “both parties to the contract

understood that payment was conditional on compliance with the

requirement at issue.” Id.; see also United States v. TDC Mgmt.

Corp., Inc., 288 F.3d 421, 426 (D.C. Cir. 2002) (noting that

withholding “‘information critical to the decision to pay’” is a

false claim (quoting Ab-Tech Constr., Inc. v. United States, 31

Fed. Cl. 429, 434 (Fed. Cl. 1994))). Interpreting the plain

language of a contract is a question of law, not a question of

fact. See LTV Corp. v. Gulf States Steel, Inc. of Ala., 969 F.3d

1050, 1055 (D.C. Cir. 1992).

The FCA also imposes a scienter requirement, requiring that

a defendant present a false claim knowingly, which entails having

“actual knowledge of the information[,]” acting “in deliberate

ignorance of the truth or falsity of the information[,]” or

acting “in reckless disregard of the truth or falsity of the

information.” 31 U.S.C. § 3729(b). “Strict enforcement of the

FCA’s scienter requirement will . . . help to ensure that

- 16 -

ordinary breaches of contract are not converted into FCA

liability.” SAIC, 626 F.3d at 1271. If parties to a contract

merely disagreed about how to interpret ambiguous contract

language, the government cannot satisfy the requirement to show

that the defendant presented claims knowingly. United States ex

rel. K&R Ltd. P’ship v. Mass. Housing Finance Agency, 530 F.3d

980, 984 (D.C. Cir. 2008). Liability under an implied

certification theory therefore is limited to cases where “the

contractor knew, or recklessly disregarded a risk, that its

certification of compliance was false.” Shaw v. AAA Eng’g &

Drafting, Inc., 213 F.3d 519, 533 (10th Cir. 2000).

“Establishing knowledge under this provision [section 3729(a)(1)]

on the basis of implied certification requires the plaintiff to

prove that the defendant knows (1) that it violated a contractual

obligation, and (2) that its compliance with that obligation was

material to the government’s decision to pay.” SAIC, 626 F.3d at

1271.

Claims for payment submitted under a contract procured by

fraud also may be actionable. See United States ex rel. Bettis

v. Odebrecht Contractors of Cal., Inc., 393 F.3d 1321, 1326 (D.C.

Cir. 2005). Congress intended that “‘each and every claim

submitted under a contract . . . or other agreement which was

originally obtained by means of false statements or other corrupt

or fraudulent conduct . . . constitutes a false claim” under

- 17 -

§ 3729(a). Id. (quoting S. Rep. No. 99-345, at 9 (1986),

reprinted in 1986 U.S.C.C.A.N. 5266, 5274). In United States ex

rel. Schwedt v. Planning Research Corp., 59 F.3d 196, 197 (D.C.

Cir. 1995), the D.C. Circuit considered an FCA action against a

defendant who contracted to design software for the government.

The court noted that a § 3729(a)(1) claim could rest on

allegations that the defendant “made an initial misrepresentation

about its capability to perform the contract in order to induce

the government to enter into the contract[,] and . . . this

original misrepresentation tainted every subsequent claim made in

relation to the contract[.]” Id. at 199.10

A defendant who submits a false claim “is liable for civil

penalties regardless of whether the government shows that the

submission of that claim caused the government damages.” SAIC,

626 F.3d at 1277. The defendant may also be liable for “3 times

the amount of damages which the Government sustains because of

the act of [the defendant].” Id. at 1277-78 (quoting 31 U.S.C.

§ 3729(a)). Damages may arise even where the defendant completes

satisfactorily the work required under the contract, if the

defendant’s violation of the contract provisions deprived the

10

Thus, the government may seek to hold DRC liable for each

claim for payment on the government’s fraudulent inducement

theory -- the theory about which DRC did not seek summary

judgment -- wholly independent of the government’s allegations

that all of DRC’s claims for payment falsely implied that DRC

complied with the requirement to obtain prior written approval

for subcontracting.

- 18 -

government of receiving the work under the conditions it

required. In SAIC, the defendant contended that its alleged

violation of conflict-of-interest provisions did not give rise to

damages because the defendant completed the required work. The

D.C. Circuit rejected the argument since it was reasonable to

conclude that “no matter how technically proficient SAIC’s

performance, the value of that performance [to the

government]. . . was compromised by the appearance of bias

created by the company’s failure to live up to its contractual

conflict of interest obligations.” Id. at 1278.11

I. PRESENTMENT

DRC argues in its reply in support of its motion for partial

summary judgment that the government cannot prove its FCA claim

because the government was not a party to the contract between

11

In view of this case law, DRC’s argument that the

government suffered no damages, because the construction work for

Honduras was satisfactorily performed under the contract, is

without merit. The D.C. Circuit has held that in cases “where

the defendant fraudulently sought payments for participating in

programs designed to benefit third-parties rather than the

government itself, the government can easily establish that it

received nothing of value from the defendant and that all

payments made are therefore recoverable as damages.” SAIC, 626

F.3d at 1279. The government argues that USAID’s funding of the

contract was a humanitarian project, implemented in part to

promote foreign policy objectives, and that it was willing to pay

more for adherence to contractual requirements. (Pl.’s Opp’n at

33.) The construction contract produced tangible benefit for

Honduras, not for the government. The degree to which alleged

misrepresentations in the pre-qualification documents vitiated

the value to the government of the contract awarded to DRC would

be relevant to calculating damages.

- 19 -

DRC and FHIS. (Def.’s Reply at 7-8.) However, DRC cites no

authority for the proposition that liability under the FCA

depends on the existence of a contract between the claimant and

the government; what matters is whether DRC submitted to the

government a claim for payment. Because FHIS may readily be

characterized as a grantee of the United States, satisfying the

FCA’s presentment requirement entails showing either that “the

Government provides the funds to the grantee upon presentment of

a claim [by the defendant] to the Government” or that “after the

grantee presents the claim, the Government provides the funds

directly to the claimant[.]” United States ex rel. Totten v.

Bombardier Corp., 380 F.3d 488, 493 (D.C. Cir. 2004) (emphasis

omitted). USAID disbursed funds directly to DRC upon receipt of

invoices that included certifications from both DRC and FHIS.

(See Compl., Ex. C.; see also Def.’s First Mot. Partial Summ. J.,

Ex. 3 (Attachment A, Section 13, Alternative II (A)(1))

(“Payments under this Contract shall be made in U.S. Dollars

financed with funds made available by USAID. Such payments will

be made to the Contractor directly by USAID[.]”).) This

financing arrangement satisfies the requirement that DRC

submitted claims for payment to the government.

II. IMPLIED FALSE CERTIFICATION

DRC does not contest that it subcontracted work without

obtaining written prior approval from USAID. The claims for

- 20 -

payment DRC made under the contract may be considered “false”

therefore if the contract (1) required DRC to secure USAID’s

prior approval for subcontracting, (2) that requirement was

material, and (3) DRC withheld information about its non-

compliance with that requirement. The government must also prove

that DRC knew that it violated the requirement and knew that its

compliance with the requirement was material to the government’s

decision to pay. SAIC, 626 F.3d at 1271.

A. Contractual obligations

If FCA liability is to be premised on an implied false

certification of compliance with contractual term, the term must

be clear and unambiguous because FCA liability is not triggered

where parties “simply disagree about how to interpret ambiguous

contract language.” Mass. Housing Finance Agency, 530 F.3d at

984; see also United States v. Kellogg Brown & Root Srvcs., Inc.,

800 F. Supp. 2d 143, 156 (D.D.C. 2011) (emphasizing that a

contractor “should not face the severe penalties of the FCA for

merely tangential violations”). DRC argues that the contract

gave it “unconditional authorization to subcontract to local

subcontractors” because the Mandatory Clauses provided that

“[u]nder a fixed-price construction contract of any value, the

prime contractor may procure locally produced goods and services

under subcontracts.” (Def.’s Mem. of P. & A. in Support of First

- 21 -

Mot. Partial Summ. J. (“Def.’s Mem.”) at 4-5.)12 DRC maintains

this contention despite the fact that the contract clearly

provided that “[t]he contractor may not . . . subcontract with

third parties without obtaining the advance, written consent of

FHIS and USAID” (Def.’s First Mot. Partial Summ. J., Ex. 2,

Section 28). The Mandatory Clauses provide, in Section 15, that,

in the event the terms of the contract conflict with provisions

of the Mandatory Clauses, the Mandatory Clauses control. (See

Def.’s First Mot. Partial Summ. J., Ex. 3 (“[F]or matters which

are addressed in both the text of such Contract and this

Attachment, the provisions of this Attachment will constitute

additional requirements for the Contract and, in the event of

ambiguity or conflict between any provision in the text of the

Contract and any provision(s) set forth in this Attachment, the

provisions in this Attachment will control.”) Relying on this

provision, DRC argues that the Mandatory Clauses’ general dictate

that “the prime contractor may procure locally produced goods and

services under subcontracts” (id.), without mention of any

necessary approval, trumps the approval requirement found in the

text of the contract. (Def.’s Mem. at 6.)

DRC’s interpretation of the contract is not tenable. The

term of the Mandatory Clauses allowing DRC to subcontract for

12

The government concedes that the contract was a fixed-

price contract. (Pl.’s Opp’n to Def.’s Stmt. of Material Facts

¶ 18.)

- 22 -

local services does not conflict with Section 28. The two

provisions are complementary, and the Mandatory Clauses may be

harmonized with other, more specific provisions. Although

nothing in the Mandatory Clauses’ express reservation to USAID of

“the right to approve . . . subcontracts” (Def.’s First Mot.

Partial Summ. J., Ex. 3, Section 2) makes clear that DRC would be

required to make a formal submission to USAID for approval before

subcontracting, the specific contract language in Section 28

explicitly does require prior written approval from USAID. The

Mandatory Clauses’ general grant of permission to use

subcontracts simply does not provoke “ambiguity or conflict”

regarding whether approval is necessary, because it is easily

read alongside the more specific provisions describing the

circumstances under which subcontracting may occur. In sum, the

contract did not provide unconditional authority for DRC to

subcontract, but rather permitted subcontracting subject to the

approval of FHIS and USAID.13

13

The government argues that Section 14 of the Mandatory

Clauses clearly required that DRC secure prior approval from

USAID for subcontracting. Section 14 provides that “USAID’s

prior written consent to any assignment of obligations under the

Contract, in addition to the consent of the Contracting Agency,

is required.” (Def.’s First Mot. Summ. J., Ex. 3 (emphasis

added).) An “assignment” of contract obligations, however, as

DRC points out, is a practice that is distinct from

subcontracting work under the contract. (Def.’s Reply at 6.) An

assignment transfers completely a right or obligation under the

contract to a third party, whereas when a party subcontracts with

a third party for the performance of some work, the party retains

all obligations under the contract. This point is confirmed by a

- 23 -

B. Materiality and scienter

DRC’s invoices can be considered false under an implied

false certification theory only if they represent falsely that

DRC complied with a contractual term that is material to payment.

SAIC, 626 F.3d at 1269. USAID pre-approval of subcontractors

could not be considered material per se, because no contractual

provision expressly linked pre-approval to DRC’s eligibility for

payment. Id. The contract enumerated five instances in which

comparison of the versions of Section 14 found in both

Attachments. In Attachment A, the section is entitled

“Assignment, Subcontract Clauses and Procurements,” and it

includes three subsections corresponding with each practice.

Subsection A, addressing assignment, contains the prior written

approval requirement. Subsection B, addressing subcontracts,

simply obligates the contractor to include specified provisions

of the Attachment in all subcontracts. (Def.’s First Mot. Summ.

J., Ex. 3.) In Attachment B, the analogous Section 14 is

entitled only “Assignment” and contains the requirement of prior

written consent for assignment of obligations. Although the

structure of these provisions confirms that the prior written

consent requirement specified in the Mandatory Clauses relates to

a contractor’s assignment of obligations, not to subcontracting,

Section 28 imposes a prior written consent requirement with

regard to subcontracting.

In addition, the government’s briefing contends that Section

3(C)(3)(b) of the Mandatory Clauses, requiring that “[a]t least

half of the supervisors and other Key personnel specified in the

Contract schedule working at the Program/Activity site(s) must be

citizens or permanent legal residents of the United States”

(Def.’s First Mot. Summ. J., Ex. 3), is relevant to assessing

DRC’s liability for false invoices. (Pl.’s Opp’n at 6.) The

government’s complaint alleges liability because DRC “incorrectly

certified that DRC performed the work required by the contract”

(Am. Compl. ¶ 24) and “neither requested, nor received, prior

written approval from USAID or FHIS to authorize any of these

subcontracts” (id. ¶ 29). Section 3(C)(3)(b) bears only

tangentially on subcontracting and imposes no requirement of any

prior authorization.

- 24 -

payment could be withheld, and did not include failure to obtain

prior approval for subcontracting among them. (Def.’s Stmt.

Undisputed Facts ¶ 157.) In the absence of an express link to

payment eligibility, the materiality of USAID approval must rest

on record evidence that “both parties to the contract understood

that payment was conditional on compliance with the requirement

at issue.” SAIC, 626 F.3d at 1269. The materiality inquiry into

the parties’ understanding of the importance of specified terms

overlaps with the FCA’s scienter requirement that a defendant

have submitted false claims knowingly. Articulating the scienter

standard, the D.C. Circuit stated that the government must “prove

that the defendant knows that it (1) “violated a contractual

obligation, and (2) that its compliance with that obligation was

material to the government’s decision to pay,” SAIC, 626 F.3d at

1271.14 Where materiality is established by reference to the

14

In its opening brief, DRC relied on a scienter standard

provided by Allison Engine Co., Inc. v. United States ex rel.

Sanders, 553 U.S. 662 (2008) (requiring a FCA plaintiff to prove

that the defendant intended that the false record or statement be

material to the Government’s decision to pay or approve the false

claim). (Def.’s Mem. at 34.) Allison Engine addressed scienter

in the context of 31 U.S.C.A. § 3729(a)(2) (imposing civil

liability on any person who “knowingly makes, uses, or causes to

be made or used, a false record or statement to get a false or

fraudulent claim paid or approved by the Government”), but as DRC

noted, the government’s implied certification claim arises under

§ 3729(a)(1). (Def.’s Reply at 3-5). The D.C. Circuit’s holding

in SAIC articulates the appropriate scienter standard in this

context. SAIC was decided after the government submitted its

opposition, but before DRC replied. Although DRC cited SAIC for

other purposes in its reply, it did not address SAIC’s holding

regarding scienter.

- 25 -

parties’ own understanding, evidence that a defendant

“underst[ands] that payment [is] conditional on compliance with

the requirement at issue,” id. at 1269, may also reflect the

defendant’s knowledge that its violation of the requirement is

“material to the government’s decision to pay,” id. at 1271.

Because the FCA does not proscribe fraudulent activity in general

but rather prohibits the knowing submission of false claims, the

requisite knowledge must be proven to exist not at just any time

in the course of the parties’ interactions but at the point at

which a defendant submits its claims for payment. See, e.g.,

United States ex rel. Hockett v. Columbia/HCA Healthcare Corp.,

498 F. Supp. 2d 25, 57 (D.D.C. 2007) (emphasizing that the FCA

“goes after claims that are false, not claims that are submitted

while fraud is afoot”); Harrison v. Westinghouse Savannah River

Co., 176 F.3d 776, 785 (4th Cir. 1999) (“The statute attaches

liability, not to the underlying fraudulent activity or to the

government’s wrongful payment, but to the claim for payment.”)

(internal quotations marks omitted). Accordingly, even if the

government establishes that USAID’s prior approval for

subcontracting was material, it must also prove that DRC knew

that it was in violation of that requirement when it submitted

its claims for payment.

Although only DRC and FHIS were “parties to the contract” at

issue here, as is discussed above, the financing arrangement

- 26 -

suffices to expose DRC to liability if the “government’s decision

to pay,” SAIC, 626 F.3d at 1271, depended on DRC’s false implied

certification of compliance with its obligation to seek prior

authorization for subcontractors. To survive summary judgment,

the government must provide evidence that USAID, rather than

FHIS, considered DRC’s securing of USAID approval sufficiently

important and that DRC knew it had violated the pre-approval

requirement and that the requirement was material to payment.

The extensive record demonstrates that there are triable issues

regarding these facts.

The government contends that DRC’s understanding that

USAID’s approval was important can be inferred from DRC’s actions

during the pre-qualification stage. DRC’s Executive Vice

President signed numerous documents during the pre-qualification

stage of the public competition for the host country contract,

including “every page of what became attachment A [of the

Mandatory Clauses],” representing that DRC did not intend to

subcontract. (Pl.’s Opp’n at 10-11.) The government argues that

prompt execution of subcontracts following award of the host

country contract demonstrates DRC’s pre-existing intent to

subcontract on a large scale and in violation of the terms of the

host country contract. (Id.) DRC maintains that, because FHIS

required DRC to begin work only weeks after the execution of the

contract, DRC was “forced . . . to abandon its original approach

- 27 -

and to subcontract a portion of each project.” (Def.’s Mem. at

7.) The government proffers evidence suggesting that DRC

intended to subcontract even before the bid. (See Pl.’s Opp’n

11-12 n.1 (quoting deposition testimony of Robert Isakson, DRC’s

Founder and Managing Director that DRC was “talking to a couple

of subcontractors before the bid”).) Fraudulent intent may be

inferred in circumstances where a defendant rapidly repudiates

promises after a contract is awarded, Bettis, 393 F.3d at 1330,

and such inconsistency might demonstrate the parties’

understanding that the promise was important to the decision to

award the contract. The pre-qualification documents did not

require DRC to promise or certify that it would not subcontract,

and the government does not point to any notification to DRC

during the pre-qualification stage that USAID approval would be

required in the event it did subcontract. Nonetheless, the

parties agreed to a contract bearing an explicit prior approval

requirement. USAID insisted on adding language appearing in

Section 2 of both Attachments reserving its right to approve all

subcontracts, and to assert that right against DRC despite any

failure by USAID to disapprove a subcontract. Drawing

justifiable inferences from the evidence in favor of the non-

movant, a reasonable jury might find that the pre-qualification

documents inquired about subcontracting, DRC hid its intent to

subcontract, the contract contained multiple provisions

- 28 -

addressing and requiring subcontracting pre-approval, and the

parties considered subcontracting procedures important to

contract award and payment.15

The government also argues that DRC’s replacement of its

original subcontracts with “participation agreements” DRC hoped

would avoid the prior approval requirement also tends to show

DRC’s perception that prior approval for subcontracting was an

important contractual obligation.16 DRC maintains that it

attempted to use participation agreements on the advice of its

Honduran counsel, and that it promptly submitted the agreements

15

Evidence that USAID regulations require that program

funding not be paid to subcontractors who have not been

pre-authorized by USAID (Pl.’s Opp’n, Ex. 2 (Agency Directive

E305.5.7a (requiring inclusion of clause reserving USAID’s right

to approve subcontractors))) is relevant to assessing the

government’s perception of the importance of including those

terms in the contract. DRC contests the importance of this

evidence, arguing that the regulations are not binding and that

the government cannot rely on them to maintain an implied false

certification action “for failure to comply with federal

regulations.” (Def.’s Reply at 16.) DRC, however, conflates the

source of the obligation on which an implied certification theory

depends with the relevant evidence to which a court may look to

determine whether the government considered the obligation

material. The agency directives are not proffered as a binding

requirement with which DRC allegedly falsely certified its

compliance. Rather, the government’s theory is that DRC failed

to comply with a contractual term, and the agency directives are

relevant to determining the importance of the term to one of the

parties.

16

In its reply, DRC moved to strike under Rule 56(c)(2) the

government’s Exhibit 10, which contained interview notes by a

USAID agent representing statements from former DRC employees and

USAID employees concerning DRC’s alleged efforts to conceal

subcontracting. The government did not respond to the motion and

this opinion does not rely on Exhibit 10.

- 29 -

to FHIS in order to determine their status under the contract and

did so before submitting any work invoices under the contract.

(Def.’s Mem. at 8.) Assessing the credibility and implications

of DRC’s representations is not an appropriate task on summary

judgment. The evidence is sufficient to raise a jury question

whether DRC’s pursuit of participation agreements in lieu of

subcontracts tends to prove that DRC understood the procedures

surrounding subcontracting, including the prior approval

requirement, to be material to payment.

In addition to establishing a triable issue whether the pre-

approval requirement was material to payment, the record reflects

a triable issue whether DRC possessed the requisite knowledge of

materiality when it submitted its claims for payment. The

government’s awareness of a defendant’s activities is relevant to

determining a defendant’s knowledge that its claims for payment

are impliedly false. “The fact that the government knew of [a

contractor’s] mistakes and limitations, and that [the contractor]

was open with the government about them, suggests that while [the

contractor] might have been groping for solutions, it was not

cheating the government in the effort.” Wang ex rel. United

States v. FMC Corp., 975 F.2d 1412, 1421 (9th Cir. 1992).

Although there is some evidence favoring DRC’s position that it

was forthcoming with its subcontracting plans, there is also

evidence that supports the opposite conclusion. On the one hand,

- 30 -

DRC initiated communication with FHIS regarding subcontracting as

early as July 3, 2000, less than two weeks after the execution of

the host country contract on June 21, 2000. Early openness about

subcontracting would tend to support DRC’s argument that it was

forthcoming with its plans and engaged in good faith negotiations

to meet its contractual obligations. And, according to Vogel,

Starkman told Vogel the day after the July 3, 2000 meeting that

DRC should “go to work,” which Vogel testified he understood to

constitute “approval [for DRC] to . . . go out there and go to

work with these subcontractors.” (Vogel Dep. 72:11-15.) On the

other hand, Section 28 of the contract required prior written

consent of both FHIS and USAID. Whatever a jury might find

concerning what Vogel believed Starkman’s consent to mean, DRC

offers no evidence that DRC sought USAID approval of

subcontractors in July 2000, or at any point over the following

three months.

The course of the discussions concerning DRC’s

subcontracting, which began in November 2000, also could lead a

jury to draw different conclusions. In December 2000, in the

midst of those negotiations, USAID issued a letter of commitment

guaranteeing payment to DRC under the contract and DRC submitted

its first work invoice. (Def.’s Stmt. Undisputed Facts ¶¶ 53,

108.) USAID paid this invoice and twenty one others submitted

between December 11, 2000 and March 4, 2002. (Id. ¶ 98.) That

- 31 -

the government committed to paying and indeed paid DRC even after

it knew that DRC had subcontracted without approval could be

found to support DRC’s argument that it did not know the pre-

approval requirement was important to payment. DRC argues that

USAID did not respond to its multiple requests to approve its

subcontractors, and instead simply facilitated negotiations

between DRC and FHIS, including encouraging FHIS to raise the 40%

limit on subcontracting, precluding a finding that DRC knew prior

USAID approval was important to payment. The undisputed fact

that on April 6, 2001, USAID technical officer Flores told DRC

orally that USAID pre-approval was not necessary lends further

support for this position. (Id. ¶¶ 46-47.)

However, a reasonable jury might conclude from other

evidence regarding the negotiations that DRC did possess the

requisite scienter. In January 2001, a USAID official responded

to a subcontracting request, via FHIS, by requesting additional

information from DRC. (Id. ¶¶ 75-76.) FHIS’s letter to DRC

informing DRC of USAID’s request urged DRC to “send[] the

requested information as soon as possible in order to obtain the

approval from USAID for the subcontracts.” (Def.’s First Mot.

Partial Summ. J., Ex. 48.) This tends to show that DRC was on

notice of the importance of USAID pre-approval. USAID’s general

non-responsiveness to DRC’s requests could weigh against finding

that DRC knew that, by not securing prior written authorization

- 32 -

from USAID, it was in violation of a contractual obligation that

was sufficiently important to the government. But courts must

“eschew making credibility determinations or weighing the

evidence” in deciding summary judgment motions. Czekalski v.

Peters, 475 F.3d 360, 363 (D.C. Cir. 2007). In determining how

USAID’s responses or lack of responses might affect DRC’s

scienter, a reasonable jury might also consider the impact of the

delay of several months between DRC’s beginning work under the

contract and USAID’s learning of the subcontracting issues. The

government argued that this delay forced USAID into the position

of not being able to insist on compliance with contractual

requirements. According to the government, USAID failed to

assert its right to require prior written approval because it did

not want to interrupt assistance to Honduras. The government,

for example, has presented evidence that USAID officials

considered suspending the contract, but decided against it “given

the amount of work that was already in progress.” (Pl.’s Opp’n,

Ex. 12 (Lombardo Dep. 77-78).) See United States ex rel.

Harrison v. Westinghouse Savannah River Co., 352 F.3d 908, 917

(4th Cir. 2003) (noting that a contractual obligation may qualify

as material even though the government continues to fund the

contract after learning of wrongdoing by a contractor because “to

avoid further costs the government might want . . . to continue

the project rather than terminate the contract and start over”).

- 33 -

Although the government presented no evidence that DRC was privy

to these internal discussions, a reasonable jury might conclude

that DRC was aware of the urgency of disaster relief and that it

knew that the prior approval provision was important to payment,

even though under the circumstances USAID did not strictly

enforce it.

In light of the above evidence regarding scienter, the

record establishes a triable issue for all but one period -- the

distinct period of time from April 2001 to October 2001. In

April 2001, Flores told DRC that USAID would not require DRC to

seek prior approval from USAID for subcontracting. The

government does not dispute the fact of Flores’ representation

and does not proffer any evidence tending to qualify or

contradict Flores’ remarks. The government’s general argument

that USAID was forced into a position of not being able to insist

on compliance with contractual requirements does not suffice to

explain how DRC could have known pre-approval was important at

all, much less critical to payment, after a USAID official

explicitly told DRC that USAID’s approval was not necessary.

Presented with the undisputed fact of Flores’ remarks, no

reasonable jury could find DRC possessed the requisite scienter

that claims submitted after Flores’ remarks -- at least until

October 2001 -- were false.

- 34 -

The government has, however, proffered evidence sufficient

to revive its case with respect to claims for payment following

October 2001. In response to DRC’s August 2001 request for a

“formal response” from USAID regarding subcontracting approval,

the government says Sloan informed DRC in October 2001 that prior

authorization was required and that USAID could not retroactively

approve the subcontractors. Sloan’s letter set out the eight

kinds of information that USAID would need in order to approve

subcontractors in the future. (Pl.’s Opp’n, Ex. 15.) The

inconsistency between Sloan’s representation and Flores’ oral

representation a few months earlier is relevant to assessing

whether the pre-approval requirement was understood by DRC to be

of sufficient importance to the government even after Sloan

affirmed the requirement. Nevertheless, viewing the evidence in

the light most favorable to the nonmoving party, a reasonable

jury could find, based on Sloan’s affirmation that USAID

considered its prior written approval important, that DRC knew it

was violating that obligation by failing to secure approval going

forward.

CONCLUSION AND ORDER

The contract underlying this dispute required USAID approval

for DRC subcontracting. The record is insufficient to support

DRC’s entitlement to judgment as a matter of law with respect to

claims submitted from December 2000 to April 2001 and from

- 35 -

October 2001 through March 2002. With respect to claims

submitted following Flores’ representation on April 2, 2001 and

before Sloan’s alleged communication to DRC on or about

October 16, 2001, however, the government has failed to create a

triable issue that DRC knew that compliance with the contract’s

pre-approval requirement was material to payment. Therefore, it

is hereby

ORDERED that DRC’s first motion [43] for partial summary

judgment be, and hereby is, GRANTED IN PART AND DENIED IN PART.

Judgment is granted to DRC on the government’s claim of implied

false certifications on DRC’s invoices submitted between April 2,

2001 and October 16, 2001. The motion is otherwise denied. It

is further

ORDERED that the parties meet and confer and file a joint

status report by May 23, 2012 reflecting their progress in

concluding discovery and proposing three mutually agreeable dates

for a continued post-discovery status conference.

SIGNED this 21st day of April, 2012.

/s/

RICHARD W. ROBERTS

United States District Judge