“An arbitration agreement is just a type of contract, and the FAA does not itself provide a substantive law governing the formation or general interpretation of contracts, so ordinary state contract law always fills in crucial gaps in any arbitration agreement.”
How later courts described this case
- “An arbitration agreement is just a type of contract, and the FAA does not itself provide a substantive law governing the formation or general interpretation of contracts, so ordinary state contract law always fills in crucial gaps in any arbitration agreement.”
- looking to federal judicial precedent when defining “arbitration” under the FAA
- “There shall be no strike or lockout until the procedures set forth in the previous paragraph has reached an impasse.”
- describing “common incidents of arbitration” as “an independent adjudicator, substantive standards . . . , and an opportunity for each side to present its case”
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
CENTRAL DISTRICT OF ILLINOIS
ROCK ISLAND DIVISION
INTERNATIONAL UNION OF )
OPERATING ENGINEERS LOCAL 649, )
)
Plaintiff, )
)
v. ) Case No. 4:25-cv-04158-SLD-RLH
)
TYRO CONSTRUCTION, INC., )
)
Defendant. )
ORDER
Before the Court is Plaintiff International Union of Operating Engineers Local 649’s
(“the Union”) motion for default judgment, ECF No. 10. For the following reasons, the motion
is GRANTED.
BACKGROUND1
Plaintiff, a labor organization, entered into a collective bargaining agreement (“CBA”)
with the Associated General Contractors of Illinois, effective from April 1, 2020, through March
31, 2025. Defendant Tyro Construction, Inc. (“Tyro”), is a signatory to the CBA and is bound
by its provisions. Article 21 of the CBA provides that disputes that cannot be resolved by an
employer and the business manager of the Union are referred to a Negotiating Committee that
“will meet and attempt to adjust the dispute.” CBA 21, Compl. Ex. A, ECF No. 1-1.
In May 2024, Tyro failed to timely pay four operating engineers—Johnathan Starcevich,
Lester Atwood, Emily Emerick, and Jared Biggs. The same month, Tyro allowed eight hours of
1 Unless otherwise noted, the facts related herein are taken from the Complaint, ECF No. 1. Exhibits attached to the
complaint are properly considered part of the complaint. See Fed. R. Civ. P. 10(c) (“A copy of a written instrument
that is an exhibit to a pleading is a part of the pleading for all purposes.”). The Court accepts the allegations relating
to liability as true by virtue of Defendant’s default. See Wehrs v. Wells, 688 F.3d 886, 892 (7th Cir. 2012).
bargaining unit work to be performed by a non-bargaining unit employee, denying Jared Biggs
the opportunity to perform the work.
On July 3, 2024, the Union filed a grievance on behalf of employees who performed
work for Tyro, stating that Tyro had violated several articles of the CBA relating to pay, benefits
contributions, and referral of workers from the Union. On September 17, 2024, the Negotiating
Committee convened and issued a finding that Tyro violated the CBA. The Negotiating
Committee ordered Tyro to pay a total of $3,263.32, broken down as follows:
i. $746.72 payable to Johnathan Starcevich;
ii. $746.72 payable to Lester Atwood;
iii. $746.72 payable to Emily Emerick;
iv. $697.96 payable to Jared Biggs;
v. $325.20 in fringe benefits payable to several fringe benefits funds.
All payments were to be made within 30 days of the hearing. Defendant has not complied with
the Negotiating Committee’s decision.
In September 2025, the Union brought a two-count complaint (I) asking the Court to
confirm the Negotiating Committee’s award pursuant to the Federal Arbitration Act (“FAA”), 9
U.S.C. §§ 1–402, and, alternatively, (II) seeking identical relief under the Labor Management
Relations Act (“LMRA”), 29 U.S.C. §§ 141–197, for breach of the CBA. Mem. Supp. Mot.
Default J. 7, ECF No. 11. Tyro did not answer the complaint and, on February 26, 2026, the
Court entered Tyro’s Default. See Feb. 24, 2026 Text Order.
DISCUSSION
I. Legal Standard
The Federal Rules of Civil Procedure allow courts to enter judgment by default against a
party that fails to plead or otherwise defend against suit. Default judgment is a two-step process.
First, after a party fails to plead or otherwise defend, the Court must enter that party’s default.
See Fed. R. Civ. P. 55(a). Once default has been entered, the opposing party may move for
default judgment pursuant to Rule 55(b). To be entitled to default judgment, a plaintiff “must
establish his entitlement to the relief he seeks.” In re Catt, 368 F.3d 789, 793 (7th Cir. 2004). In
determining whether a plaintiff is entitled to relief, the Court accepts as true all well-pleaded
allegations of the complaint relating to liability, but not those relating to damages. Dundee
Cement Co. v. Howard Pipe & Concrete Prods., Inc., 722 F.2d 1319, 1323 (7th Cir. 1983). The
amount of any damages must be definitely established. Id. This can be done at a damages
hearing or through documentary evidence or affidavits. Id.
II. Analysis
The Union brought counts under both the FAA and the LMRA. “[A]s a technical matter,
in seeking to confirm an arbitration award created by virtue of a collective bargaining agreement,
recourse is to the LMRA, not the FAA.” Part-Time Fac. Ass’n at Columbia Coll. Chi. v.
Columbia Coll. Chi., 892 F.3d 860, 864 n.3 (7th Cir. 2018) (quotation marks and alteration
omitted). However, “arbitration under the LMRA and the FAA are generally subject to the same
governing principles.” Id. (quotation marks omitted). Under the LMRA, courts have jurisdiction
over “[s]uits for violation of contracts between an employer and a labor organization
representing employees in an industry affecting commerce.” 29 U.S.C. § 185(a).
This jurisdiction “include[s] a request to enforce (or vacate) an award entered as a result
of the procedure specified in a collective bargaining agreement for the arbitration of grievances.”
Unite Here Loc. 1 v. Hyatt Corp., 862 F.3d 588, 595 (7th Cir. 2017). As emphasized by all
levels of courts, the LMRA reflects a policy favoring the enforcement of arbitration awards
because “[w]hen Congress conferred jurisdiction on the federal judiciary over disputes arising
under collective bargaining agreements, it meant for [courts] to support and reinforce, rather than
displace, the arbitration process.” Id. Accordingly, a court’s role is “very limited.” Ameren Ill.
Co. v. Int’l Bhd. of Elec. Workers, 906 F.3d 612, 616 (7th Cir. 2018) (quoting United
Steelworkers of Am. v. Am. Mfg. Co., 363 U.S. 564, 567 (1960)). It will confirm an award so
long as it “draws its essence from the collective bargaining agreement.” United Steelworkers of
Am. v. Enter. Wheel & Car Corp., 363 U.S. 593, 597 (1960). An award generally does so if it is
rooted in an interpretation of the CBA, even if in doing so the arbitrator erred in making factual
or legal conclusions. See Ameren Ill. Co., 906 F.3d at 616. Courts will overturn arbitration
awards only in a very limited set of circumstances, such as if the arbitrator “exceeded the scope
of his submission.” Id. at 617 (quotation marks omitted).
The first, threshold question is whether the dispute resolution process outlined in the
CBA qualifies as “arbitration.” Article 21 nowhere describes the process as such. It states
instead:
If disputes cannot be resolved by the EMPLOYER and the Business Manager of
the UNION, then within forty-eight (48) hours of notification (excluding Saturdays,
Sundays and Holidays) a committee consisting of at least one member each from
the EMPLOYER side and the UNION side of the negotiating committee of this
Agreement will meet and attempt to adjust the dispute.
There shall be no strike or lockout until the procedures set forth in the previous
paragraph has reached an impasse.
CBA 21.
In the Seventh Circuit, when determining whether a contractual provision constitutes an
agreement to arbitrate, courts look to state contract law. Druco Rests., Inc. v. Steak N Shake
Enters., Inc., 765 F.3d 776, 781–82 (7th Cir. 2014); Rodgers-Rouzier v. Am. Queen Steamboat
Operating Co., 104 F.4th 978, 991 (7th Cir. 2024) (“An arbitration agreement is just a type of
contract, and the FAA does not itself provide a substantive law governing the formation or
general interpretation of contracts, so ordinary state contract law always fills in crucial gaps in
any arbitration agreement.”). In this case, Illinois law applies since, in the absence of a dispute,
the Court applies the law of the forum state. Kass v. PayPal Inc., 75 F.4th 693, 701 (7th Cir.
2023). In deciding whether an agreement to arbitrate exists, there is no presumption favoring
arbitration. Druco Rests., 765 F.3d at 781.
Although there are some exceptions, in Illinois, arbitration is generally understood to be a
binding alternative to judicial resolution of a dispute. See Am. Fam. Mut. Ins. Co. v. Baaske, 572
N.E.2d 308, 310 (Ill. App. Ct. 1991). In determining whether such an agreement constitutes
arbitration, the Illinois Supreme Court has suggested that the FAA uses “arbitration” as a term of
art that is defined according to federal law. See Borowiec v. Gateway 2000, Inc., 808 N.E.2d
957, 968–70 (Ill. 2004) (citing Harrison v. Nissan Motor Corp., 111 F.3d 343, 350–51 (3d Cir.
1997)), for the following definition of arbitration under the FAA: “the essence of arbitration, we
think, is that, when the parties agree to submit their disputes to it, they have agreed to arbitrate
these disputes through to completion.”). This would comport with precedent in several other
circuits that found the definition of “arbitration” under the FAA to be a question of federal law.
See Fit Tech, Inc. v. Bally Total Fitness Holding Corp., 374 F.3d 1, 6 (1st Cir. 2004) (“That a
uniform federal definition [of arbitration under the FAA] is required is obvious to us.”);
Advanced Bodycare Sols., LLC v. Thione Int’l, Inc., 524 F.3d 1235, 1239 (11th Cir. 2008)
(looking to federal judicial precedent when defining “arbitration” under the FAA). District
courts in this circuit have applied a federal definition of “arbitration” under the FAA to
determine whether a dispute resolution process qualified as arbitration under the LMRA. See,
e.g., Brock Indus. Servs., LLC v. Laborers Int’l Union of N. Am., No. 16-CV-780-NJR-DGW,
2017 WL 1132621, at *4 (S.D. Ill. Mar. 27, 2017). Following this example is not contrary to the
Seventh Circuit’s instruction in Druco since the substance of the CBA—“who promised to do
what”—remains governed by state law, it is only “whether what has been agreed to amounts to
‘arbitration’” that “depends on what Congress meant by the term in the [FAA].” Fit Tech, Inc.,
374 F.3d at 6.
Since it is apparent that the parties agreed to be bound by the terms of Article 21 of the
CBA, the only remaining question is whether the dispute resolution process described in Article
21 amounts to “arbitration.” Given the similarities between the FAA and LMRA, see Part-Time
Fac. Ass’n, 892 F.3d at 864 n.3, this question is rightly determined with reference to FAA’s
definition of “arbitration” under federal law. The Seventh Circuit has not directly addressed
what procedures qualify as “arbitration,” but federal law is clear that the presence of the word
“arbitration” in an agreement is not dispositive. See Fit Tech, Inc., 374 F.3d at 7 (“Whether the
accounting remedy is ‘arbitration’ . . . . does not depend on the nomenclature used in the
agreement.”). The Eleventh Circuit has articulated four factors that are common indicia of
arbitration: “(i) an independent adjudicator, (ii) who applies substantive legal standards (i.e. the
parties’ agreement and background contract law), (iii) considers evidence and argument
(however formally or informally) from each party, and (iv) renders a decision that purports to
resolve the rights and duties of the parties, typically by awarding damages or equitable relief.”
Advanced Bodycare Sols., 524 F.3d at 1239; see also Fit Tech, Inc., 374 F.3d at 7 (describing
“common incidents of arbitration” as “an independent adjudicator, substantive standards . . . ,
and an opportunity for each side to present its case”). “The presence or absence of any one of
these circumstances will not always be determinative, and parties have great flexibility under the
FAA to select pre-packaged dispute resolution procedures, or to craft their own.” Advanced
Bodycare Sols., 524 F.3d at 1239.
Article 21 does not describe the dispute resolution procedure with specificity, but the
process is rightly deemed arbitration, especially considering how it was applied in this case.
Article 21 clearly anticipates the submission of disputes to an independent adjudicator: “a
committee consisting of at least one member each from the EMPLOYER side and the UNION
side of the negotiating committee of this Agreement.” CBA 21. Since a decision by the
Negotiating Committee purports to bar strikes or lockouts, see id. (“There shall be no strike or
lockout until the procedures set forth in the previous paragraph has reached an impasse.”), it is
also evident that Article 21 intended to decisively settle the rights of the parties. Further, agents
of both parties to the CBA submitted affidavits stating that “[i]t was the intention of the parties to
the Articles of Agreement that the Negotiating Committee’s Decision be final and binding on the
parties and enforceable in federal court.” Kazenske Decl. 2, Compl. Ex. C, ECF No. 1-3;
Shreves Decl. 2, Compl. Ex. D, ECF No. 1-4.
As effectuated in this case, during adversarial proceedings, representatives of Tyro and
the Union presented their arguments, including testimony, to the Negotiating Committee, which
returned a decision that purported to resolve the rights of the parties by awarding damages. See
generally Negotiating Committee Decision, Compl. Ex. E, ECF No. 1-5; Kazenske Decl. 2;
Shreves Decl. 1 (stating that both parties participated fully in the process before the Negotiating
Committee). The eventual award was rooted in specific findings that Tyro violated the same
four sections of the CBA cited in the grievance petition. See generally Negotiating Committee
Decision. In this case, then, the dispute resolution process met each of the indicia of arbitration
identified in Advanced Bodycare Solutions and Fit Tech, Inc. Though this procedure was not
laid out in the CBA itself, the complaint establishes that both parties fully participated in this
process that was, in effect, “arbitration in everything but name,” Fit Tech, Inc., 374 F.3d at 7.
Given Tyro’s participation in the process, the brevity of the arbitration clause in the CBA cannot
vitiate a process that functionally adhered to all of the requirements of arbitration. See Fortune,
Alsweet & Eldridge, Inc. v. Daniel, 724 F.2d 1355, 1357 (9th Cir. 1983) (“It would be
unreasonable and unjust to allow [the defendant] to challenge the legitimacy of the arbitration
process, in which he had voluntarily participated over a period of several months . . . .”).
Having established that the decision by the Negotiating Committee is properly considered
arbitration, it follows readily that the decision drew its essence from the CBA. A grievance
regarding Tyro’s violation of four articles of the CBA was submitted to the Negotiating
Committee pursuant to the “Disputes” article of the CBA. See generally Grievance
Documentation, Compl. Ex. B, ECF No. 1-2. The eventual award was rooted in specific findings
that Tyro violated the same four sections of the CBA cited in the grievance petition. See
generally Negotiating Committee Decision. These provisions, including articles regarding
referral of workers by the Union (Article 4), pay (Article 18), and fringe benefits contributions
(Article 25), are related to the factual circumstances underlying the submission of the grievance.
See generally id. The Court therefore finds that the allegations of the complaint establish Tyro’s
liability under the LMRA.
The Union has also submitted documentary evidence sufficient to definitely establish the
amount of damages due. The proper remedy for a suit brought under the LMRA to enforce an
arbitration award is simply to confirm the award and thereby “place[] the weight of a court’s
contempt power behind the award.” Unite Here Local 1, 862 F.3d at 596. The Court therefore
need not independently evaluate the appropriate compensation for a violation of the CBA to
confirm the Negotiating Committee’s decision. The Complaint establishes that the Negotiating
Committee awarded $3,263.32, payable as follows: $746.72 to Johnathan Starcevich; $746.72 to
Lester Atwood; $746.72 to Emily Emerick; $697.96 to Jared Biggs; and $325.20 in fringe
benefits, distributed as described in the arbitration award. See Negotiating Committee Decision
4.
The Union also requests $405.00 in filing fees and $188.60 in service costs. Mot. Default
J. 5. Federal Rule of Civil Procedure 54(d)(1) provides that “[u]nless a federal statute, these
rules, or a court order provides otherwise, costs—other than attorney’s fees—should be allowed
to the prevailing party.” The docket indicates that the $405.00 filing fee was paid, so such costs
are awarded to the Union pursuant to Rule 54. However, the Union has not submitted any
documentation substantiating the claimed $188.60 in service costs. If it seeks to recover these
costs, it may file a post-judgment bill of costs with documentation supporting its request. See
Civil LR 54.1.
CONCLUSION
Accordingly, Plaintiff International Union of Operating Engineers Local 649’s motion for
default judgment, ECF No. 10, is GRANTED. Defendant Tyro Construction, Inc. is ORDERED
to pay the sum of $3,263.32 as stated in the Negotiating Committee’s decision, together with
$405.00 in costs. The Clerk is directed to enter judgment and close the case.
Entered this 25th day of June, 2026.
s/ Sara Darrow
SARA DARROW
UNITED STATES DISTRICT JUDGE