Opinion

Trailer Bridge v. LA Intl Marine

Court
Court of Appeals for the Fifth Circuit
Filed
Jun 17, 2026
Status
Published
Nature of suit
Private Civil Federal
Cited by
0 cases
Authority
More cited than 41.0%

explaining that the statutory presumption in favor of the creation of maritime liens did not eliminate “the idea of credit to the vessel being a prerequisite to a lien” (quoting Equilease, 793 F.2d at 605)

How later courts described this case

  • explaining that the statutory presumption in favor of the creation of maritime liens did not eliminate “the idea of credit to the vessel being a prerequisite to a lien” (quoting Equilease, 793 F.2d at 605)
  • “The [1971] amendment certainly affected the power of the materialman to acquire a maritime lien . . . but it had no effect on other contractors. . . . [I]t has never purported to govern the shipper’s or subcharterer’s lien.” (emphasis in original)
  • finding that a party lacked adequate notice of a no-lien provision when the provision had not been disclosed “at the time [the party] entered into the contract to provide stevedoring services”
  • explaining that “necessaries” include “the things that a prudent owner would provide to enable a ship to perform well the functions for which she has been engaged”

Written by the judges who cited it.

The opinion

United States Court of Appeals

for the Fifth Circuit United States Court of Appeals

____________ Fifth Circuit

FILED

No. 25-30331 June 11, 2026

____________ Lyle W. Cayce

Clerk

Trailer Bridge, Incorporated,

Plaintiff—Appellant/Cross-Appellee,

versus

Louisiana International Marine, L.L.C.,

Defendant—Appellee/Cross-Appellant,

versus

Atlanta Bridge, in rem, together with their engines,

tackle, furniture, apparel, appurtenances, etc.;

Memphis Bridge, in rem, together with their engines,

tackle, furniture, apparel, appurtenances, etc.,

Third Party Defendants—Appellants/Cross-Appellees.

______________________________

Appeal from the United States District Court

for the Eastern District of Louisiana

USDC No. 2:22-CV-5358

______________________________

Before Jones, Stewart, and Willett, Circuit Judges.

By Edith Hollan Jones, Circuit Judge:

Louisiana International Marine (“LIM”), the owner of two tugboats,

seeks to recover unpaid invoices for towing a pair of barges along the Gulf of

No. 25-30331

America coast. The former barge owner objects that the towage services

were received only after the barges were chartered to a third party in an

agreement that expressly forbade the third party from incurring liens on the

barges. Because LIM lacked actual knowledge of the “no-lien” provision at

the time it contracted to provide towage services, a maritime lien attached to

the barges. The district court’s judgment is AFFIRMED.

Background

In August 2020, Plaintiff Appellant Trailer Bridge, Inc., a freight

service company, chartered two oceangoing, flat deck barges, the

ATLANTA BRIDGE and the MEMPHIS BRIDGE (“the Barges”), to

Work Cat Trans Gulf1 (“Work Cat”). Trailer Bridge chartered the Barges

pursuant to a Standard Barge Charter Party Agreement (“the Barge

Charter”). The Barge Charter contained a “no-lien” clause that required

Work Cat to “indemnify and hold [Trailer Bridge] harmless against any lien

of whatsoever nature arising upon the Barge” during the contract period.

Work Cat needed the Barges to transport containers between Tampa,

Florida, and Brownsville, Texas. To that end, Work Cat also chartered two

tugboats (“the Tugs”), the LA COMMANDER and the LA INVADER,

from LIM to propel the Barges. Work Cat and LIM finalized a six-month

charter agreement for the Tugs (“the Tug Charter”) in November 2020,

commencing in mid-December 2020. The Tug Charter required Work Cat

to pay a daily rate for the Tugs, in addition to covering the cost of fuel and

lubricant the Tugs required.

On December 11, 2020, Work Cat began using the Tugs to tow the

Barges. Work Cat continued using the Tugs until June 18, 2021. Although

_____________________

1

Work Cat Trans Gulf was renamed to Work Cat Florida in August 2021.

2

No. 25-30331

Work Cat paid LIM for the Tugs for about two weeks until December 31,

2020, Work Cat paid less than a quarter of LIM’s remaining invoices.

In May 2021, Work Cat filed for bankruptcy. LIM filed a proof of

claim in the bankruptcy, seeking to recover its unpaid invoices for towage

services and supplies. Trailer Bridge also filed a proof of claim.

Outside of the bankruptcy proceeding, LIM filed two notices of lien

claims with the National Vessel Documentation Center, asserting two liens

valued at $1,364,214.16 against the Barges. LIM later demanded payment

from Trailer Bridge to cover its unpaid towage, fuel, and lubricant invoices.

Trailer Bridge refused to pay.

By November 2022, Trailer Bridge had sold the Barges to nonparties.

LIM sent a Notice of Lien and Demand for Payment to one of the purchasers

of the Barges. Pursuant to its purchase agreement with the new barge

owners, Trailer Bridge stepped in to defend the lawsuit and indemnify the

purchasers against LIM’s claims.2 Trailer Bridge filed a lawsuit seeking a

declaration that the Barges were not subject to LIM’s maritime lien.

Relevant here, Trailer Bridge argued that no lien had attached to the Barges

because the Barge Charter contained a no-lien provision and that LIM had

relied exclusively on the credit of Work Cat, not the Barges. Trailer Bridge

also sought to recover attorney’s fees under 46 U.S.C. § 31343(c)(2), a part

of the Commercial Instruments and Maritime Liens Act (CIMLA). LIM

counterclaimed for attorney’s fees against Trailer Bridge in personam. In

addition, LIM filed a Third-Party Claim against the Barges, in rem, seeking

_____________________

2

LIM and Trailer Bridge entered a lien escrow agreement that transferred LIM’s

liens to cash held in escrow so that Trailer Bridge could finalize the sale of the Barges free

and clear of any liens. That lien escrow agreement permits LIM to look to the lien escrow

funds and Trailer Bridge to satisfy its claims.

3

No. 25-30331

$1,556,414.16 for unpaid towage services and $361,381.56 for fuel and

lubricant costs.

After a two-day bench trial, the district court concluded that LIM had

a lien against the MEMPHIS BRIDGE for $863,162.50 and against the

ATLANTA BRIDGE for $630,420.10. In its initial judgment, the district

court awarded LIM attorney’s fees, but it did not include Trailer Bridge as a

party to the judgment. LIM moved to obtain $186,717.50 in attorney’s fees

and to add Trailer Bridge as a party to the judgment so that it could recover

attorney’s fees in personam. After reviewing both motions, the district court

changed its mind and refused to award attorney’s fees to either party.

Trailer Bridge appealed on behalf of the Barges. LIM cross appealed.

Discussion

On appeal, Trailer Bridge contends that LIM has no maritime liens on

the Barges, but it alternatively disputes the value and scope of those liens.

LIM cross-appeals for attorney’s fees.

A. LIM’s Maritime Lien

The parties first dispute whether LIM has any maritime lien on the

Barges at all. “Whether a maritime lien exists is a question of law, reviewed

de novo.” Martin Energy Servs., L.L.C. v. Bourbon Petrel M/V, 962 F.3d 827,

830 (5th Cir. 2020) (quoting Comar Marine, Corp. v. Raider Marine Logistics,

LLC, 792 F.3d 564, 575 (5th Cir. 2015)). Underlying findings of fact are

reviewed for clear error. See Comar, 792 F.3d at 575. A factual finding is

“clearly erroneous when although there is evidence to support it, the

reviewing court on the entire evidence is left with the definite and firm

conviction that a mistake has been committed.” Guzman v. Hacienda Recs.

& Recording Studio, Inc., 808 F.3d 1031, 1036 (5th Cir. 2015) (quoting

4

No. 25-30331

Anderson v. City of Bessemer City, 470 U.S. 564, 573, 105 S. Ct. 1504, 1511

(1985)).

Under CIMLA, a party may obtain a maritime lien if it (a) provides

necessaries (b) to a vessel (c) on the order of the owner, or a person

authorized by the owner. ING Bank N.V. v. Bomin Bunker Oil Corp., 953 F.3d

390, 393–94 (5th Cir. 2020); see also 46 U.S.C. § 31342(a). “Necessaries”

include “repairs, supplies, towage, and the use of a dry dock or marine

railway.” 46 U.S.C. § 31301(4); see also Equilease Corp. v. M/V Sampson, 793

F.2d 598, 603 (5th Cir. 1986) (explaining that “necessaries” include “the

things that a prudent owner would provide to enable a ship to perform well

the functions for which she has been engaged”). Officers or agents appointed

by a charterer “are presumed to have authority to procure necessaries for a

vessel.” 46 U.S.C. § 31341(a), (a)(4).

LIM fulfilled CIMLA’s three requirements to attach a maritime lien

on the Barges. By using the Tugs to provide towage services to the Barges,

LIM provided a type of necessary explicitly enumerated in CIMLA. See 46

U.S.C. § 31301(4). It provided those necessaries to a vessel. See 1 U.S.C. § 3

(“The word ‘vessel’ includes every description of watercraft or other

artificial contrivance used, or capable of being used, as a means of

transportation on water.”); see also Norton v. Warner Co., 321 U.S. 565, 571,

64 S. Ct. 747, 751 (1944) (extending the definition of “vessel” in 1 U.S.C. § 3

to barges because they are “means of transportation on water”). And,

because Work Cat chartered the Barges, its agents were presumed to have

authority to procure necessaries for the Barges under 46 U.S.C.

§ 31341(a)(4)(B). Work Cat’s agents did just that when they entered into the

Tug Charter with LIM. Accordingly, the towage services were obtained by

“a person authorized by the owner” of the Barges to obtain necessaries. 46

U.S.C. § 31342(a).

5

No. 25-30331

Trailer Bridge raises numerous countervailing arguments. To begin,

Trailer Bridge asserts that LIM relied exclusively on the credit of Work Cat

when it provided towage services, rather than on the credit of the Barges.

Where a party does not rely on the credit of the vessel on which a lien is

claimed, no lien is formed. See Equilease, 793 F.2d at 605–06; see also Racal

Surv. U.S.A., Inc. v. M/V Count Fleet, 231 F.3d 183, 189 (5th Cir. 2000)

(explaining that the statutory presumption in favor of the creation of

maritime liens did not eliminate “the idea of credit to the vessel being a

prerequisite to a lien” (quoting Equilease, 793 F.2d at 605)). “Because of the

strong presumption in favor of a maritime lien,” however, Trailer Bridge

must demonstrate that LIM “deliberately intended to look solely to the

owner’s personal credit and to forego the valuable privilege afforded it by

law.” Equilease, 793 F.2d at 606.

To establish that LIM looked solely to Work Cat’s personal credit,

Trailer Bridge points to two pieces of evidence. It asserts that LIM invoiced

Work Cat for the cost of towage, not the Barges or Trailer Bridge. But

“invoicing the charterer . . . [is] inadequate to show that a creditor relied

solely on such charterer.” Maritrend, Inc. v. Serac & Co. (Shipping), 348 F.3d

469, 474–75 (5th Cir. 2003). “[I]nvoicing only the charterer . . . only shows

that a party attempted to receive the payment from the charterer first, not

that it never intended to rely on the credit of the vessel.” Id. at 475.

Maritrend directly rebuts Trailer Bridge’s argument.

More significantly, Trailer Bridge relies on the deposition of LIM’s

corporate representative, Anthony Roberts, who stated that he did not work

for the Barges or extend them credit. In focusing on Roberts’s deposition,

Trailer Bridge ignores his subsequent trial testimony, in which he clarified

that LIM did not view Work Cat “as the sole source” of payment for the

invoices because LIM “had the opportunity, if [it] didn’t get paid, to lien the

cargo, the equipment, [and] the barge.” Roberts’s isolated deposition

6

No. 25-30331

statement, later clarified at trial, is insufficient to rebut the presumption that

a maritime lien formed here.

Next, Trailer Bridge contends that even if LIM satisfied CIMLA’s

maritime lien prerequisites, the Barge Charter’s “no-lien” provision

prevented LIM from obtaining a lien. In relevant part, the provision states:

The Charterers will not suffer, nor permit to be continued, any lien or

encumbrance incurred by them or their agents, which might have

priority over the title and interest of the Owners in the Barge. (a) The

Charterers shall indemnify and hold the Owners harmless against any

lien of whatsoever nature arising upon the Barge during the Charter

Party period while she is under the control of the Charterers and on

any claims against the Owners arising out of or in relation to the

operation of the Barge by the Charterers.

If applicable, the no-lien provision would bar the formation of LIM’s

maritime lien.

“A no-lien clause does not prevent a maritime lien from arising unless

the entity providing necessaries had actual knowledge of the clause.” John

Bludworth Shipyard, L.L.C. v. Bechtolt, 138 F.4th 372, 376 n.1 (5th Cir. 2025)

(quoting Lake Charles Stevedores, Inc. v. Professor Vladimir Popov MV, 199

F.3d 220, 225 (5th Cir. 1999)). Proving actual knowledge typically entails

showing “an affirmative communication by the Vessel or her Owner to one

of the supplier’s employees who has the ability to effect the negotiations and

the contract prior to the time the contract is entered into.” ING Bank, N.V.

v. M/V Charana Naree, 446 F. Supp. 3d 163, 172 (W.D. La. 2020) (emphasis

in original) (quoting O.W. Bunker Malta Ltd. v. M/V TROGIR, 2013 WL

326993, at *3 (C.D. Cal. Jan. 29, 2013)); see also TTT Stevedores of Texas, Inc.

v. M/V Jagat Vijeta, 696 F.2d 1135, 1138 (5th Cir. 1983) (finding that a party

lacked adequate notice of a no-lien provision when the provision had not been

disclosed “at the time [the party] entered into the contract to provide

stevedoring services”).

7

No. 25-30331

According to Trailer Bridge, LIM gained actual knowledge of the no-

lien provision from an email Roberts received on December 20, 2020. The

email contained a copy of the Barge Charter in which the no-lien provision

appears. LIM responds that Roberts received the Barge Charter in answer to

an unrelated inquiry. Roberts only reviewed the charter to resolve that

inquiry, and he claims he never consulted the part of the charter that

contained the no-lien provision.

LIM undeniably had actual knowledge of the no-lien provision as of

December 20, 2020. The “law simply cannot allow a supplier to deny

knowledge of a no lien clause when it was delivered in a manner that was both

customary and reliable in the shipping business.” Stevens Shipping &

Terminal Co. v. Japan Rainbow, II MV, 334 F.3d 439, 444 (5th Cir. 2003).

LIM does not appear to dispute that email is both a customary and reliable

manner of delivering documents. Because LIM received the Barge Charter

in a reliable and customary manner, it cannot claim ignorance merely by

denying that its agent read the relevant portion of the agreement.

Unfortunately for Trailer Bridge, however, the Tug Charter had

already been finalized by December 20, 2020. Work Cat and LIM executed

the Tug Charter on November 12, 2020. Performance began a month later,

on December 11. Under TTT Stevedores of Texas, actual knowledge of a no-

lien provision must precede the completion of an agreement. 696 F.2d at

1138. Here, LIM had already entered a six-month charter with Work Cat by

the time it received the Barge Charter and learned of that document’s no-lien

provision. That was too late for the provision to have any bearing on its

negotiations or decision-making. Accordingly, LIM lacked actual knowledge

of the no-lien provision at the relevant time, before it agreed on the Tug

Charter.

8

No. 25-30331

Trailer Bridge makes two further arguments to shore up the no-lien

provision’s effectiveness. Trailer Bridge begins by suggesting that LIM had

an independent duty to investigate whether any no-lien provision applied to

the Barges. If this case had arisen under the statute that preceded CIMLA,

Trailer Bridge would certainly have been correct. That statute, the Federal

Maritime Lien Act (FMLA), imposed a duty of reasonable diligence on

suppliers of necessaries. See Act of June 5, 1920, ch. 250, § 30(R), 41 Stat.

1005 (1920) (“[N]othing in this section shall be construed to confer a lien

when the furnisher knew, or by exercise of reasonable diligence could have

ascertained, that because of the terms of a charter party . . . the person

ordering the . . . necessaries was without authority to bind the vessel

therefor.”); see also Gulf Oil Trading Co., a Div. of Gulf Oil Co. v. M/V

CARIBE MAR, 757 F.2d 743, 747 (5th Cir. 1985). In 1971, Congress amended

the law, removing the reference to an “exercise of reasonable diligence.” See

Racal, 231 F.3d at 188. Because courts generally “refuse to interpret [a

statute] in a way that negates its recent revision,” Congress’s removal of the

reasonable diligence requirement is strong evidence that the requirement no

longer exists. Rumsfeld v. F. for Acad. & Institutional Rts., Inc., 547 U.S. 47,

57–58, 126 S. Ct. 1297, 1306 (2006).

Undeterred, Trailer Bridge points to a decision in which this court

suggested that the 1971 amendments eliminated the reasonable diligence

requirement only for materialmen. See Cardinal Shipping Corp. v. M/S Seisho

Maru, 744 F.2d 461, 470 (5th Cir. 1984) (“The [1971] amendment certainly

affected the power of the materialman to acquire a maritime lien . . . but it had

no effect on other contractors. . . . [I]t has never purported to govern the

shipper’s or subcharterer’s lien.” (emphasis in original)). Proffering a

narrow definition of materialman that includes only “shoreside business[es]

that suppl[y] goods and repairs to vessels usually holding a maritime lien for

services and goods,” Trailer Bridge argues that LIM is not a materialman and

9

No. 25-30331

thus retains a duty of reasonable investigation. NICHOLAS J. HEALY, ET. AL,

CASES AND MATERIAL ON ADMIRALTY 919 (Thomson Reuters, 5th ed.

2012).

A closer examination of the Cardinal court’s reasoning reveals that it

encompasses more maritime suppliers than Trailer Bridge’s narrow

definition. The court in Cardinal reasoned from the premise that “[t]he

Maritime Lien Act delineated the rights only of materialmen.” Cardinal, 744

F.2d at 470. The original and amended versions of the act applied to “[a]ny

person furnishing repairs, supplies, towage, use of dry dock or marine railway,

or other necessaries, to any vessel . . . .” 46 U.S.C. § 971 (1976) (emphasis

added), amended by, 46 U.S.C. § 31342. Based on this provision, if the

Cardinal court understood materialmen in the sense advocated by Trailer

Bridge, it would have contradicted the statute’s unambiguous reference to

towage services. But Cardinal did not misinterpret CIMLA; the court used

“materialmen” in a generic sense to mean all suppliers covered by CIMLA.

Treatises on admiralty law confirm that parties providing the services

enumerated in the act no longer have a duty of reasonable inquiry. THOMAS

J. SCHOENBAUM, 1 ADMIRALTY & MAR. LAW § 9:3 (7th ed. 2026) (“The 1971

amendment negates the duty of reasonable inquiry only with respect to

materialmen and suppliers covered by the Federal Maritime Lien Act.”

(emphasis added)). LIM, as a provider of towage services, is covered by

CIMLA and therefore benefits from the statute’s elimination of the

reasonable diligence requirement.3

Trying a different angle, Trailer Bridge contends that the no-lien

provision contained in the Barge Charter makes it impossible for LIM to

_____________________

3

Our holding does not displace Cardinal’s conclusion that the duty of reasonable

diligence persists for suppliers, shippers, and charterers who provide services or enter

contracts that are not covered by CIMLA.

10

No. 25-30331

satisfy the third prong of 46 U.S.C. § 31342(a), that the necessaries be

obtained by a person authorized to do so. The no-lien provision, the

argument goes, rendered Work Cat’s agents incapable of incurring liens on

the Barges. Thus, Work Cat’s agents were not “authorized by the owner”

to procure towage services. Trailer Bridge’s position cannot be reconciled

with the statute or this court’s cases. The statute requires only that the

person who obtained necessaries be authorized to obtain the necessaries, not

that the person be authorized to incur a lien. The statutory presumption in

46 U.S.C. § 31341(a)(4) renders Work Cat’s agents capable of obtaining

necessaries. Moreover, Trailer Bridge’s reading would render the “actual

knowledge” requirement established in this court’s case law irrelevant. If a

no-lien provision barred the formation of liens under § 31342(a) regardless of

knowledge, then there would be no reason to inquire whether a party had

actual knowledge of the provision. Trailer Bridge’s stance would vitiate

decades of this court’s precedents applying the actual knowledge

requirement.

With the existence of LIM’s maritime lien confirmed, we must still

determine its value. Trailer Bridge suggests that LIM’s invoices are too

nonspecific to appropriately quantify the value of its lien. LIM, on the other

hand, suggests the district court erred by excluding fuel and lubricant costs

from its award of damages. Both parties are incorrect. The district court

appropriately calculated the value of towage services LIM provided to the

Barges, and that amount properly excluded the cost of fuel and lubricants.

A maritime lien is based on the cost of the necessaries provided. Here,

the Tugs were attached to the Barges around the clock. Some of that time

was spent towing the Barges. But some of that time was also spent idling,

including the “standby time” when the Barges were being loaded or

unloaded in port. Trailer Bridge contends that LIM’s lien can only include

the time spent under towage, not standby time. Because LIM’s invoices do

11

No. 25-30331

not distinguish between towing and standby time, Trailer Bridge challenges

the district court’s conclusion that the invoices reflect the correct amount of

LIM’s lien.

This court’s holding in Trico Marine Operators, Inc. v. Falcon Drilling

Co., 116 F.3d 159 (5th Cir. 1997), refutes Trailer Bridge’s argument. There,

this court approved the district court’s decision that “transit and standby

time . . . [are] also lienable.” Trico Marine Operations, Inc. v. Falcon Drilling

Co., No. CIV. A. 95-0381, 1996 WL 96883, at *6 (E.D. La. Mar. 1, 1996).

Trailer Bridge attempts to distinguish Trico by arguing that the contract in

Trico expressly contemplated standby time. By structuring the Tug Charters

to depend on day rates, however, Work Cat and LIM necessarily included

standby time in the scope of their contract. LIM’s invoices prove the amount

of the lien.

Dissatisfied with merely recovering the cost of its towage services,

LIM also seeks to recover the costs of fuel and lubricant used while the Tugs

were servicing the Barges. The district court denied this request, reasoning

that these supplies were necessaries provided to the Tugs, not to the Barges.

LIM challenges this reasoning, as it characterizes the fuel and lubricants as

“an element of the reasonable value of towage services provided to the

Barges.” LIM also points out that the costs of fuel and lubricant were

included in the Tug Charter.

The district court properly excluded fuel and lubricant costs in its

calculation of LIM’s maritime lien. CIMLA’s provisions are applied stricti

juris and are not “lightly extended by construction, analogy, or inference.”

Valero Mktg. & Supply Co. v. M/V Almi Sun, IMO No. 9579535, 893 F.3d 290,

292 (5th Cir. 2018) (quoting Atl. & Gulf Stevedores, Inc. v. M/V Grand Loyalty,

608 F.2d 197, 200–01 (5th Cir. 1979)). Far from narrowly construing

necessaries, LIM’s position lacks any limiting principle. If consumable costs

12

No. 25-30331

for the Tugs constitute necessaries provided to the Barges, then labor or

repair costs for tugboats might also qualify. By opening the door to these

possibilities, LIM’s position runs afoul of this court’s practice of strictly

limiting necessaries. Moreover, that the contract provided for fuel and

lubricant costs separately from the day rate for towage services emphasizes

that these costs were different. Because the cost of consumables provided to

the Tugs is distinct from the value of the services provided to the Barges, the

district court’s calculation of LIM’s maritime lien was correct.

B. Attorney’s Fees

The district court initially awarded attorney’s fees in rem to LIM as

the prevailing party in Trailer Bridge’s suit. When LIM moved to have the

fees awarded in personam against Trailer Bridge instead, the district court

ordered each party to bear its own legal costs. The court explained that LIM

“provide[d] no authority, nor can the Court locate any, wherein attorney’s

fees and costs were awarded in personam when the underlying prevailing

claim was in rem.” LIM disagrees and asserts that the joinder of in rem claims

to an in personam action does not undermine an award of attorney’s fees.

Courts of appeals review a district court’s award of attorney’s fees

under 46 U.S.C. § 31343(c)(2) for an abuse of discretion. See, e.g., Whalen v.

M/V Miluska, 385 Fed. Appx. 717, 719 (9th Cir. 2010).

In “a civil action in Admiralty to declare that a vessel is not subject to

a lien,” a district “court may award costs and attorneys fees to the prevailing

party, unless the court finds that the position of the other party was

substantially justified or other circumstances make an award of costs and

attorneys fees unjust.” 46 U.S.C. § 31343(c)(2). It is undisputed that when

a court awards such attorney’s fees, they must be awarded in personam. This

is because attorney’s fees are not necessaries, and they thus cannot be part of

the value of a maritime lien. See Gulf Marine & Indus. Supplies v. Golden Prince

13

No. 25-30331

M/V, 230 F.3d 178, 180 (5th Cir. 2000) (“Since Congress enacted the

FMLA, courts have consistently held that legal services are not

necessaries.”); Bradford Marine, Inc. v. M/V Sea Falcon, 64 F.3d 585, 588–89

(11th Cir. 1995) (“A suit in rem to enforce a maritime lien is limited to the

value of the lien itself.”).

LIM prevailed in Trailer Bridge’s suit to declare that the Barges were

not subject to a lien. This is a precondition for a fee award under 46 U.S.C.

§ 31343(c)(2). In addition, contrary to Trailer Bridge’s contention, the

district court dismissed Trailer Bridge as a party for only the non-attorney’s

fees claims. As a result, an in personam recovery of fees from Trailer Bridge

seems possible if Trailer Bridge had become a party to the judgment.

Nevertheless, the district court did not abuse its discretion in rejecting

LIM’s request. The statute gives courts discretion to award attorney’s fees.

See 46 U.S.C. § 31343(c)(2) (“The court may award costs and attorneys

fees.” (emphasis added)). Although the statute lists two circumstances in

which a court may not award fees, it specifies no circumstances in which a

court is required to award fees. Given that unconstrained discretion, the

district court was justified in finding that the unique posture of this litigation

made it equitable for each party to bear its own costs. Ordinarily, plaintiffs

who bring an in rem action against a vessel may also pursue an “in personam

action against any party that is directly liable in contract, tort, or some other

substantive law.” Dowell Div. of the Dow Chem. Co. v. Franconia Sea Transp.,

Ltd., 504 F. Supp. 579, 581 (S.D.N.Y. 1980), aff'd sub nom. Dowell Div. of Dow

Chem. v. Franconia Sea Transp. Ltd., 659 F.2d 1058 (2d Cir. 1981). But if

there is no “separate basis of substantive liability,” the in personam defendant

is generally not “liable to the plaintiff merely because a maritime lien has

come into existence.” Id. Because there is no separate basis for Trailer

Bridge’s liability to LIM, the district court concluded that it was equitable for

each party to bear its own costs. The district court’s adherence to the

14

No. 25-30331

traditional understanding of in personam recoveries is not an abuse of

discretion. Accordingly, LIM’s claim for attorney’s fees fails.

C. Alternative Grounds for Reversal

Trailer Bridge urges reversal on two other grounds, but neither is

persuasive. First, Trailer Bridge argues that LIM’s claims were discharged

in the Work Cat bankruptcy proceedings. The bankruptcy court approved a

settlement and compromise between LIM and the bankruptcy trustee for

some of LIM’s unpaid invoices. But the “discharge of a debt of the debtor

does not affect the liability of any other entity on . . . such debt.” 11 U.S.C.

§ 524(e). The discharge of Work Cat’s debts did not discharge the debts of

Trailer Bridge or the Barges.4 Instead, the amount LIM recovered in the

bankruptcy, $86,280, merely reduced the amount it can recover here, and

LIM reduced its demand in this case accordingly.

Second, Trailer Bridge suggests the district court abused its discretion

by awarding LIM prejudgment interest from the date of the last unpaid

invoice. “As a general rule, prejudgment interest should be awarded in

admiralty cases.” Kenai Ironclad Corp. v. CP Marine Servs., LLC, 84 F.4th

600, 614 (5th Cir.2023) (quoting Comar, 792 F.3d at 580). District courts may

decline to award prejudgment interest only where doing so would create an

inequitable result. Id. Trailer Bridge does not adequately explain why

awarding prejudgment interest was inequitable here. It was hardly

unreasonable, much less an abuse of discretion, to begin counting interest

from the date of the last invoice, when LIM last provided its services to the

Barges.

_____________________

4

Because the compromise in the bankruptcy proceedings involved different

parties, res judicata also does not foreclose LIM from recovering in this suit.

15

No. 25-30331

The judgment of the district court is AFFIRMED.

16

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.