Opinion

The Haskell Company

Court
Armed Services Board of Contract Appeals
Filed
May 5, 2026
Status
Published
On the bench
Arnett
Cited by
0 cases
Authority
More cited than 40.8%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - )

)

The Haskell Company ) ASBCA Nos. 64380, 64381

)

Under Contract No. N40085-17-C-8327 )

APPEARANCES FOR THE APPELLANT: Brendan R. Geraghty, Esq.

Jay W. Matthews, Esq.

Demetrius Pyburn, Esq.

Haynsworth Sinkler Boyd, P.A.

Greenville, SC

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq.

Navy Chief Trial Attorney

David M. Ruddy, Esq.

Devin A. Wolak, Esq.

Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE ARNETT ON

THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION

This matter comes before the Board on two appeals arising from a contracting

officer’s final decision denying a “pass-through sponsored claim” filed by the

subcontractor, ENFRA MCC LLC (ENFRA), in the name of the prime contractor,

The Haskell Company (Haskell). The Department of the Navy (the Navy or

government) has moved to dismiss the appeals for lack of jurisdiction. The Navy

asserts that the “pass-through sponsored claim” is invalid because ENFRA has

no privity of contract with the Navy and the claim lacks certification by the prime

contractor, as required by the Contract Disputes Act (CDA). ENFRA contends that

the claim was properly certified and sponsored by the prime contractor.

For the reasons stated below, we deny the Navy’s motion to dismiss for lack of

jurisdiction.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

Background:

1. On June 29, 2017, the Navy awarded Contract No. N40085-17-C8327 (the

Contract) to Haskell (R4, tab 26 at 3323-24).

2. On or about September 8, 2017, Haskell awarded a subcontract to ENFRA

f/k/a Bernhard MCC, LLC 1 for the design and construction of mechanical systems for

the Contract (R4, tab 77 at 3541).

Claim Correspondence and the Contracting Officer’s Final Decision:

3. As early as February 2024, email correspondence between counsel for

ENFRA and counsel for Haskell indicate that they were discussing ENFRA’s intent to

submit a pass-through claim and whether Haskell would “support a pass-through

claim” (app. resp. ex. 1 at 40-41). For approximately one year, their communication

continued monthly, until ENFRA confirmed to Haskell that it had sent a claim letter to

the government on February 3, 2025 (id. at 18).

4. In a document dated February 3, 2025, ENFRA submitted a “pass-through

sponsored claim” to the Navy relating to the Contract between Haskell and the Navy

(R4, tab 77 at 3532).

5. The claim included Enclosure 1, labelled “Certification – Haskell”, which

was signed by Mr. Roger McDonell, Haskell’s VP of Construction. It stated:

This Claim is being filed by our subcontractor and

inasmuch as they do not have contract privity with you, we

are acting as a conduit on their behalf in this matter. We

do not have access to their books and records, and

therefore, cannot make any statement with respect to the

amount of their Claim. However, we have no reason to

believe that their cost figures and delay estimates are

incorrect.

(Id. at 3538) We find that Haskell’s certification deviates from the language

prescribed by the CDA, 41 U.S.C. § 7103(b)(1).

6. The claim also included Enclosure 2 which was labelled as a “Certification”

and signed by Mr. Richard D. Barnes, ENFRA’s VP for Operations. It stated:

I certify that the claim is made in good faith; that the

supporting data are accurate and complete to the best of

my knowledge and belief; that the amount requested

accurately reflects the contract adjustment for which the

1

It is undisputed that ENFRA was previously known as Bernhard MCC, LCC (R4,

tab 84 at 4193; gov’t mot. at 3 n.2). For simplicity, it is referred to throughout

this document as ENFRA.

2

contractor believes the Government is liable; and that I am

duly authorized to certify the claim on behalf of the

contractor.

(Id. at 3539) We find that ENFRA’s certification mirrors the language prescribed by

the CDA, 41 U.S.C. § 7103(b)(1) but is signed by a subcontractor.

7. On March 6, 2025, the Contracting Officer (CO) issued a letter to Haskell

indicating that the Navy had received ENFRA’s February 3, 2025 correspondence

purporting to be a claim under the Contract Disputes Act (R4, tab 78 at 3855_1-2).

The CO concluded that ENFRA had improperly attempted to assert a claim directly to

the government (id.). She stated that the government would only act on a claim

asserted by Haskell and declined to issue a final decision (id.).

8. On April 4, 2025, ENFRA’s counsel responded, contending that a

subcontractor may submit a claim if the claim indicates that it is sponsored by the

prime contractor, as Haskell demonstrated through its certification (R4, tab 80

at 3858).

9. On May 1, 2025, the Navy CO reiterated her position to Haskell that, if the

prime contractor wished to sponsor the proposed pass-through claim, it needed to

submit the claim directly to the government (R4, tab 81).

10. On May 27, 2025, Mr. Jeff Miller, VP, General Counsel of Haskell, sent a

“draft letter seeking review of [ENFRA’s] claim submission” to ENFRA’s counsel for

his input (app. resp. ex. 1 at 17-18).

11. On June 4, 2025, Mr. Miller, VP, General Counsel of Haskell, responded

to the CO’s May 1, 2025 letter and specifically requested that the Navy “review and

consider” the claim submitted by ENFRA “as a properly submitted pass through claim

sponsored by Haskell” (R4, tab 82). Further, Haskell stated that it “agrees with

[ENFRA’s] interpretation of the CDA and relevant case law provided for your review

that their claim submission is proper, adequately sponsored by Haskell and deserving

of review and consideration” (id.). In closing, the letter stated, “If you do not wish to

review and consider [ENFRA’s] claim, please deny in total and provide a Final

Decision” (id.). We find that, through its June 4, 2025 letter, Haskell sponsored

ENFRA’s claim.

12. On July 31, 2025, the Navy CO issued a Final Decision (COFD) addressed

to Haskell, which stated:

I have reviewed reference (1), The Haskell Company’s

(Haskell) pass-through claim where it alleges that

3

subcontractor . . . [ENFRA] incurred costs in the total

amount of $899,656.29 due to project delays alleged to be

attributable to the Government (“the Claim”). In

reviewing the Claim and the relevant contract documents,

your Claim is denied in its entirety.

(R4, tab 83 at 4190-92) The COFD asserted that Haskell had an obligation to account

for subcontractor costs when negotiating modifications with the government, cited

bilateral modifications executed by the parties to the contract, and denied the claim, in

its entirety, on the basis that it “did not demonstrate entitlement for additional costs”

(id. at 4191).

13. We find that the CO reviewed and rendered a decision addressed to the

prime contractor on the substance of the pass-through claim. The denial was not based

upon a lack of privity of contract or a defective certification.

The Appeals:

14. On October 15, 2025, counsel for ENFRA emailed Mr. Jeff Miller, Haskell

General Counsel, stating ENFRA’s intent to appeal the denial of its claim and

inquiring whether Haskell would “update the letter . . . confirming sponsorship of the

claim” (app. resp. ex. 1 at 16).

15. On October 27, 2025, counsel for ENFRA submitted a notice of appeal to

the Board stating ENFRA’s intent to appeal the July 31, 2025 COFD. The notice

stated, “ENFRA’s claims were submitted to the Government as a pass-through

sponsored claim under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-09.

Haskell provided consent and certification of the claims.” (Notice at 1) We find that

Mr. Jeff Miller and Mr. Roger McDonnell, who are both identified as Haskell VPs,

were copied on the email filing to the Board (app. resp. at 6, ex. 2).

16. On October 30, 2025, the Board docketed two appeals under the name of

the prime contractor, The Haskell Company. ASBCA No. 64380 pertains to a claim

for “Changed Work”, and ASBCA No. 64381 pertains to a claim related to

COVID-19.

17. On December 11, 2025, the Navy filed a Motion to Dismiss both appeals,

citing a lack of jurisdiction (gov’t mot. at 16).

18. On December 12, 2025, ENFRA filed a complaint which stated that it was

submitted “through the Haskell Company” and that Haskell “provided consent and

certification of the claims” (compl. ¶ 1). The complaint also alleged that Haskell

4

“separately submitted a letter to the Government further confirming sponsorship of the

claims” (id.).

19. On January 9, 2026, ENFRA filed its Response to Respondent’s Motion to

Dismiss. On the same date, Mr. Jeffrey Miller, VP, General Counsel of Haskell, filed

a letter with the Board confirming that Haskell “is aware that ENFRA . . . has filed the

subject Appeals in the name of Haskell . . . and agrees to sponsor such Appeals and the

underlying claims.” (App. resp. ex. 3 at 45)

20. On February 9, 2026, the Navy filed its Reply in Support of its Motion to

Dismiss (gov’t reply at 14).

DECISION

The Parties’ Contentions

The Navy requests dismissal of these appeals for lack of jurisdiction on two

grounds: 1) ENFRA has failed to establish privity of contract with the Navy (gov’t

mot. at 5-10) and 2) the claim is invalid because it lacks the required CDA certification

(id. at 10-15). As to the privity of contract argument, the Navy asserts that ENFRA

has not satisfied the sponsorship exception to the requirement for privity of contract

(id. at 8-10). Specifically, the Navy contends that ENFRA has not established that

Haskell is proceeding on ENFRA’s behalf or has authorized ENFRA to proceed in

Haskell’s name in this forum (id.). As to the certification issue, the Navy posits that

Haskell’s certification lacks the required elements of a CDA certification and is

tantamount to a lack of certification which is not a curable defect (id. at 10-15).

In response, ENFRA asserts that privity is not required for a properly sponsored

pass-through claim and that Haskell sponsored ENFRA’s claim (app. resp. at 3-9).

ENFRA submitted email correspondence with Haskell leading up to submission of the

claim to demonstrate Haskell’s “continued cooperation” (id. at 3-5). ENFRA contends

that Haskell was aware that ENFRA intended to appeal the claim denial, noting that

Haskell was copied on the email when the notice of appeal was filed (id. at 6, ex. 2).

ENFRA argues that Haskell’s sponsorship need not be reaffirmed and that the identity

of the party who filed the notice of appeal does not “negate jurisdiction where the

appeal arises from a properly sponsored claim” (id. at 7-8). As to the certification

issue, ENFRA contends that Haskell’s certification substantially complied with the

CDA and was intentionally drafted to mirror certification language upheld in prior

precedent (id. at 9-11). Finally, ENFRA argues that, at the very least, the claim

certification was defective and amenable to correction (id. at 11-12).

In its Reply, the Navy argues that prime contractor sponsorship must be evident

both at the presentation of the claim to the government and at the notice of appeal

5

(gov’t reply at 4-6). The Navy asserts that there is no evidence of Haskell’s

sponsorship at the time the Notice of Appeal was filed which it alleges is the critical

juncture when the Board’s jurisdiction must be determined (id. at 6-7). The Navy

contends that a lack of sponsorship at the Notice of Appeal violates 41 U.S.C. §

7104(a) because ENFRA is not a “contractor” authorized to appeal under the statute

(id. at 7). Although ENFRA has produced contemporaneous claim-related email

correspondence with Haskell, the Navy contends that it is “irrelevant to the

sponsorship analysis” because the government was not copied on the communication

(id. at 4). Finally, the Navy argues that Haskell’s January 9, 2026 letter is belated

sponsorship since it was submitted after the 90-day appeal period had elapsed and that

ENFRA cannot retroactively establish jurisdiction (id. at 7-8).

Standard of Review

Once jurisdiction has been challenged, appellant bears the burden of proving

the Board’s jurisdiction by a preponderance of the evidence. Reynolds v. Army and

Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988). We accept uncontroverted

factual allegations as true for purposes of deciding motions to dismiss for lack of

jurisdiction, and “other facts underlying the jurisdiction allegations are subject to

fact-finding” based upon our review of the record. L-3 Commc’ns Integrated Sys.,

L.P., ASBCA Nos. 60713, 60716, 17-1 BCA ¶ 36,865 at 179,625. We may “look

beyond the pleadings and ‘inquire into jurisdictional facts’ that are disputed in order

to determine whether or not we have jurisdiction.” Env’t Safety Consultants, Inc.,

ASBCA No. 54615, 07-1 BCA ¶ 33,483 at 165,979 (quoting Recovich v. United States,

933 F.2d 991, 993 (Fed. Cir. 1991)).

The Privity of Contract Issue

This Board’s jurisdiction over an appeal of a CDA claim arises from 41 U.S.C.

§ 7105(e)(1)(A), which confers “jurisdiction to decide any appeal from a decision of a

contracting officer . . . relative to a contract made by that department or agency.” A

CO’s decision which serves as the basis for an appeal must be issued in response to a

claim filed by a “contractor” relating to a contract with the federal government. 41

U.S.C. § 7103(a)(1)-(2). Within 90 days of the receipt of a CO’s decision, a

“contractor” may appeal the decision to an agency board. 41 U.S.C. § 7104(a). The

term “contractor” is defined as “a party to a Federal Government contract other than

the Federal Government.” 41 U.S.C. § 7101(7). Thus, a “contractor” may file a claim

under the CDA and may appeal a CO’s decision to the Board.

ENFRA is not a “contractor” for purposes of the CDA.

In this case, Haskell is a “contractor”; ENFRA is not. ENFRA has no privity of

contract with the government. ENFRA acknowledges that it is a subcontractor and

6

does not dispute that it lacks privity of contract with the Navy (app. resp. at 2).

Rather, ENFRA 2 argues that sponsorship by the prime contractor is a recognized

exception to the privity requirement (id.).

We have recognized two limited exceptions to the privity requirement for

subcontractors: (1) cases where a prime contractor acts as an agent for the

government, and (2) cases where a prime contractor sponsors the subcontractor’s

appeal. Frontline Support Solutions, LLC, ASBCA No. 64022, 25-1 BCA ¶ 38,803

at 188,731; United States v. Johnson Controls, 713 F.2d 1541, 1551 (Fed. Cir. 1983);

Holmes & Narver Servs., Inc., ASBCA No. 51155, 00-2 BCA ¶ 30,972 at 152,850-51.

ENFRA has not alleged that Haskell acted as an agent for the government. Instead,

ENFRA asserts that Haskell sponsored its claim (app. resp. at 2). Thus, we focus our

analysis on the second exception.

What is required for prime sponsorship of a subcontractor claim?

In a series of cases, we have delineated what is required for a prime contractor’s

sponsorship of a subcontractor’s claim and appeal. We have consistently considered

the circumstances of the claim to determine if the appeal was made with the

authorization and sponsorship of the prime contractor. J.E. McAmis, Inc., ASBCA

No. 54455, 04-2 BCA ¶ 32,746 at 161,953; Batteast Constr. Co., ASBCA Nos. 33357,

30452, 89-3 BCA ¶ 21,933 at 110,340-41; Foster Co. of Greenville, Inc., ASBCA

Nos. 29132, 28955, 84-2 BCA ¶ 17,481 at 87,090.

In Algernon Blair Indus. Contractors, ASBCA No. 25277, 83-2 BCA ¶ 16,737

at 78,618, we concluded that a subcontractor was authorized to appeal in the name of

the prime contractor based upon the prime contractor’s “consistent cooperation”

throughout the process of pursuing the claim. We also considered a timely notice of

appeal filed by the subcontractor in the name of the prime contractor where the prime

contractor subsequently filed an untimely notice upon learning that the government

did not regard the subcontractor’s notice as “proper.” We found no reason to question

that the subcontractor “acted with the requisite authority when he signed the appeal . . .

in the name of the appellant” and determined that the prime contractor’s late notice

was further evidence of the “pattern of cooperation.”

In Foster Co. of Greenville, Inc., 84-2 BCA ¶ 17,481 at 87,090, we addressed a

subcontractor’s claim which was submitted by the prime contractor, denied by the

2

Notwithstanding their actual interests, ENFRA is not the named party in this case.

Haskell is. As a consequence of sponsorship and consistent with our precedent,

ENFRA must litigate in the name of the prime contractor. Thus, in future

filings, the appellant shall refer to itself as Haskell and will be addressed by the

Board as such.

7

government, and timely appealed by the subcontractor in its own name. Subsequently,

the prime contractor filed an untimely amended notice of appeal to ratify the notice

filed by its subcontractor. We addressed the question of “whether the Notice of

Appeal filed by the subcontractor should be deemed to have been filed by the Prime

Contractor.” Having found that “the requisite sponsorship and authorization existed”

when the subcontractor filed its notice of appeal, we held that the subcontractor’s

notice of appeal, as ratified by the prime contractor, was timely and effective and

substituted the name of the prime contractor as appellant.

In Batteast, ASBCA Nos. 33357, 30452, 89-3 BCA ¶ 21,933 at 110,339, the

notice of appeal stated that the subcontractor, by and through the prime contractor, was

appealing the COFD. It was submitted by the subcontractor to the CO, the prime

contractor, and the Board. Id. We found “abundant evidence” that the prime

contractor sponsored the claim” and “no evidence” that it “did not intend to continue

its sponsorship of the claim” following issuance of the COFD. Id. at 110,341. We

specifically considered correspondence between counsel for the prime and the

subcontractor as evidence of the prime’s continued sponsorship. We concluded that

the subcontractor could appeal in the name and under the sponsorship of the prime

contractor. Id.

“Sponsorship and authority can be inferred when the prime contractor

subsequently ratifies the filing of that appeal and ‘consistently cooperates’ in the

presentation of the claim even if the prime contractor did not specifically authorize the

subcontractor to file the appeal prior to the expiration of the appeal period.” Holmes &

Narver, 00-2 BCA ¶ 30,972 at 152,851; J.E. McAmis, Inc., 04-2 BCA ¶ 32,746 at

161,953. However, where there is no evidence of prime sponsorship until months after

the subcontractor filed a notice of appeal, a belated sponsorship agreement without

actual ratification by the prime contractor is ineffectual to establish jurisdiction. Door

Pro Sys., Inc., ASBCA No. 34114, 87-3 BCA ¶ 19,997 at 101,287.

Haskell sponsored ENFRA’s claim.

Here, the Navy challenges Haskell’s sponsorship of both ENFRA’s claim and

the subsequent appeal. As to the claim, the Navy cites “only two occasions” where

Haskell “provided input to the claim process”: 1) Haskell’s certification and 2) its

June 4, 2025 letter to the CO (gov’t mot. at 9). The Navy argues there is “no evidence

of consistent cooperation” (id. at 10). We disagree.

We have found Haskell’s June 4, 2025 letter to the CO requesting that she

“review and consider” ENFRA’s claim as a “properly submitted pass through claim

sponsored by Haskell” expressly demonstrated Haskell’s sponsorship of the claim

(SOF ¶¶ 10-11). Further, the email correspondence between ENFRA and Haskell’s

counsel demonstrates “consistent cooperation” for more than a year, culminating with

8

submission of the claim (SOF ¶¶ 3-4). We also note that the CO directed claim

correspondence and the COFD to Haskell which reflects a contemporaneous

understanding that the claim was sponsored by Haskell (SOF ¶¶ 7, 9, 12). There is

ample evidence of Haskell’s sponsorship of the claim.

There is no evidence that Haskell’s sponsorship was discontinued at the Notice

of Appeal.

The Navy contends that “nothing in the notice of appeal indicated or suggested

that Haskell co-signed, sponsored, or was otherwise involved in this appeal in any

way” (gov’t reply at 6-7). We disagree.

The Notice of Appeal stated that the claim had been submitted as a

“pass-through sponsored claim” and affirmatively represented that Haskell “provided

consent and certification” (SOF ¶ 15). We previously found that two Haskell VPs,

Mr. Miller and Mr. McDonnell, were copied on the filing of the notice of appeal (id.).

Correspondence between counsel for ENFRA and Haskell also demonstrates Haskell’s

continued sponsorship (SOF ¶¶ 3, 10).

The facts in this case are very similar to those presented in Batteast, 89-3 BCA

21,933. In both instances, the subcontractor directly filed a notice of appeal and

provided a copy to the prime contractor at the time of filing (SOF ¶ 15). Like Batteast,

we conclude here that there is abundant evidence that the prime sponsored ENFRA’s

claim and no evidence that it did not intend to continue its sponsorship following

issuance of the COFD.

Haskell’s January 9, 2026 letter is not belated sponsorship.

The Navy also argues that Haskell’s January 9, 2026 letter is belated

sponsorship comparable to the facts addressed by the Board in Door Pro Sys., Inc.,

87-1 BCA ¶ 19,997 at 101,287. However, we conclude that this case differs

significantly from the limited facts presented in Door Pro.

In Door Pro, we held that a letter filed almost five months later was insufficient

to establish sponsorship of the claim at the time notice of appeal was filed. There was

no evidence of prime sponsorship prior to submission of the letter. Id.

Here, Haskell was aware of ENFRA’s claim a year prior to its filing, provided a

certification to accompany the February 3, 2025 claim, specifically requested that the

Navy consider ENFRA’s claim as a “properly submitted pass through claim sponsored

by Haskell”, and was copied on the notice of appeal (SOF ¶¶ 3-4, 11, 15). There is

abundant evidence of Haskell’s sponsorship of the claim and appeal, unlike the facts in

Door Pro.

9

The Certification Issue

The CDA requires certification of claims which exceed $100,000. 41 U.S.C.

§§ 7101-09, 7103(b). The certification must be “executed by an individual authorized

to bind the contractor with respect to the claim” and must certify that (a) the claim is

made in good faith; (b) the supporting data are accurate and complete to the best of the

contractor’s knowledge and belief; (c) the amount requested accurately reflects the

contract adjustment for which the contractor believes the Federal Government is

liable; and (d) the certifier is authorized to certify the claim on behalf of the contractor.

Id. at 7103(b)(1). A defect in the certification does not deprive a court or an agency

board of jurisdiction over the claim if it is corrected prior to the Board’s final decision.

Id. at 7103(b)(3). A defective certification is “a certificate which alters or otherwise

deviates from the [statutory certification] language in [FAR] 33.207(c) or which is not

executed by a person authorized to bind the contractor with respect to the claim.

Failure to certify shall not be deemed to be a defective certification.” Federal

Acquisition Regulation (FAR) 33.201. “[T]here needs to be something purporting

to be a certification in order to reach the threshold of being a defective certification.”

Kamaludin Slyman CSC, ASBCA No. 62006, 21-1 BCA ¶ 37,849 at 183,794 (holding

that the contractor’s “implicit certification” derived from “cobbled-together portions of

the claim” did not constitute a defective, remediable certification).

The Claim included certifications from both the prime and subcontractor.

The Navy alleges that Haskell’s certification is so lacking that it is tantamount

to no certification (gov’t mot. at 13). The complete omission of a certification is not a

curable defect. Abdul Ahad Khadim Constr. Co., ASBCA No. 59206, 14-1 BCA

¶ 35,694 at 174,765; CDM Int’l, Inc., ASBCA No. 52123, 99-2 BCA ¶ 30,467

at 150,514. The Navy argues that we should follow our holding from Kamaludin

Slyman CSC, ASBCA No. 62006, 21-1 BCA ¶ 37,849 at 183,793, and conclude that

the claim was “not merely defectively certified, but wasn’t certified at all.” We find

the Navy’s arguments unavailing because the cases cited by the Navy involve claims

which completely lack certification.

Here, ENFRA’s claim included two certifications which were distinctly labeled

and signed: one from Haskell and one from ENFRA (SOF ¶¶ 5, 6). Thus, our prior

decisions in Abdul Ahad Khadim, CDM Int’l, and Kamaludin Slyman do not guide our

decision here.

The Court of Appeals for the Federal Circuit has set a standard for a prime

contractor’s certification of a sponsored subcontractor claim.

Appellant contends that Haskell’s certification was “intentionally drafted to

mirror the certification approved by the Federal Circuit in Transamerica Insurance

10

Corp. v. United States and that it reflects precisely the good-faith belief standard

articulated in United States v. Turner Construction Co.” (App. resp. at 2) We have

found that Haskell’s certification deviated from the language prescribed by the CDA

(SOF ¶ 5). We must determine whether the deviation renders the certification

defective, but subject to correction. The Court of Appeals for the Federal Circuit has

addressed a prime contractor’s certification of a subcontractor’s pass-through claim in

several cases and provides binding precedent for resolution of this issue.

In United States v. Turner Construction Co., 827 F.2d 1554, 1559 (Fed. Cir.

1987), the government challenged a prime contractor’s certification of a pass-through

sponsored claim, arguing that it was invalid because it was qualified by, and in conflict

with, an adverse recommendation previously submitted to the government. Id. The

Court rejected the government’s argument that the certification “must reflect the prime

contractor’s own belief” that the claim reflects the amount owed by the government

and “that to allow the prime to substitute the subcontractor’s belief for its own in

making a certification would make a sham of the certification requirement . . . and

would render meaningless the prohibition against direct appeals by subcontractors.”

Id. at 1561. The Court held that “the certification requirement requires not that the

prime contractor believe the subcontractor’s claim to be certain, but that the prime

contractor believe that there is good ground for the claim.” Id. Having found that the

prime contractor’s certification included the required statutory elements, the Court

held that it was sufficient to confer jurisdiction. Id. at 1561-62.

In Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1579-81 (Fed. Cir.

1992) , the Court considered a certification signed by a prime contractor which was

3

accompanied by a subcontractor certification. The Claims Court had found the

certification defective because it was “unduly qualified” by language in the prime’s

cover letter which stated:

This claim is being filed by our subcontractor and

inasmuch as they do not have contract privity with you, we

are acting as a conduit on their behalf in this matter. We

do not have access to their books and records and,

therefore, cannot make any statement with respect to the

amount of their claim. However, we have no reason to

believe that their cost figures and delay estimates are

incorrect.

3

The Federal Circuit’s decision in Transamerica Ins. Corp was overruled on other

grounds by its decision in Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1583

(Fed. Cir. 1995).

11

Id. at 1580. On appeal, the Federal Circuit held that the prime’s certification was

“valid and not so qualified as to make it ineffective” and concluded that the

certification “clearly complied with the chief policy underlying the CDA certification

requirement, that being the purpose of submitting the contractor to liability for fraud.”

Id. at 1581.

In Dai Global, LLC v. Administrator of USAID, 945 F.3d 1196, 1199 (Fed. Cir.

2019), the Federal Circuit addressed an appeal arising from the dismissal of multiple

subcontractor pass-through claims sponsored by the prime contractor where the prime

contractor provided a cover letter “certification” as well as certifications signed by its

subcontractor. The prime’s cover letter expressed its belief that there was a “sound

basis” for the claims and stated the following:

Given that [EI] is the real party in interest and is the only

one who can logically and realistically certify these claims,

DAI hereby submits this certification in satisfaction of the

requirements of the Contract Disputes Act. As DAI is not

the real party in interest, DAI must accept and rely on the

[EI] certification at face value. In addition, DAI has no

knowledge, which suggests that [EI] has knowingly or

intentionally failed to comply with the requirements of the

Contract[ ] Disputes Act or has acted in bad faith.

Id. The Court found that the prime contractor’s cover letter conveyed “a clear intent to

certify the underlying claims” and that the subcontractor’s certifications were “further

evidence” of that intent. The Court held, “[t]aken together, [the cover letter and

subcontractor’s certification] are sufficient to constitute a defective certification within

the meaning of 7103(b)(3).” Id.

Taken together, the certifications produced by Haskell and ENFRA constitute a

defective, but remediable, certification.

While appellant may have intended to follow the guidance from Turner and

Transamerica, there is a critical factual distinction that we cannot overlook—both of

those cases involved CDA-compliant certifications executed by the prime contractor

which were challenged as “qualified” because of contemporaneous communications.

In Turner, the qualifying language was found in a separate report in which the prime

recommended rejection of the claim. 827 F.2d at 1557. In Transamerica, the

qualifying language was in a cover letter accompanying the claim. 973 F.2d at 1580.

Here, we do not have a CDA-compliant prime certification that is qualified. We have

a prime contractor’s certification which deviates from the required statutory language

(SOF ¶ 5). Thus, the decisions in Turner and Transamerica do not squarely address

the facts before us.

12

However, the Court’s decision in Dai Global is on point and serves as binding

precedent for our decision here. Like the prime contractor’s cover letter certification

in Dai Global, Haskell’s certification conveys a clear intent to certify ENFRA’s

claims, stating that it has “no reason to believe that” the claimed costs and delay were

incorrect (SOF ¶ 5). Like the subcontractor certification in Dai Global, ENFRA

provided a certification that mirrors the requirements of the CDA, thereby

demonstrating its intent to certify its claim (SOF ¶ 6). We conclude that, taken

together, these documents are sufficient to constitute a defective certification pursuant

to 41 U.S.C. § 7103(b)(3). 4

Accordingly, this defect in the certification does not deprive the Board of

jurisdiction so long as it is corrected prior to the Board’s final decision. Id.

CONCLUSION

The Navy’s motion to dismiss is denied.

Dated: May 5, 2026

LAURA J. ARNETT

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

J. REID PROUTY DAVID D’ALESSANDRIS

Administrative Judge Administrative Judge

Acting Chairman Acting Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

4

We do not decide whether Haskell’s certification alone constitutes a “defective

certification.”

13

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 64380, 64381, Appeals of

The Haskell Company, rendered in conformance with the Board’s Charter.

Dated: May 5, 2026

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

14

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.