“The [Supreme] Court often applies this interpretive rule, usually referred to as the ‘series-qualifier canon.’”
How later courts described this case
- “The [Supreme] Court often applies this interpretive rule, usually referred to as the ‘series-qualifier canon.’”
- “Avatar’s ulterior motive for De Pani’s termination has no relevance[,] as Article 67 of the Master Contract provided Avatar with the right to terminate De Pani at any time. Florida law required nothing more of Avatar.” (internal citation omitted)
- explaining that “sole discretion” is a “high degree of discretion”
- finding that, although the management agreement required written notice of termination, plaintiff waived this requirement by his conduct and by failing to raise the issue of written notice until suit was filed
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF LOUISIANA
UNITED STATES OF AMERICA,
for the use and benefit of
TIMBERLINE CONSTRUCTION
GROUP, LLC
CIVIL ACTION
VERSUS
NO. 24-669-JWD-EWD
APTIM FEDERAL SERVICES, LLC,
ET AL.
RULING AND ORDER
This matter comes before the Court on APTIM’s Motion for Partial Summary Judgment
(“Partial MSJ”) (Doc. 118) filed by APTIM Federal Services, LLC (“APTIM”). Timberline
Construction Group, LLC (“Timberline”) opposes the motion. (Doc. 134.) APTIM filed a reply.
(Doc. 139.) Oral argument is not necessary. The Court has carefully considered the law, the facts
in the record, and the arguments and submissions of the parties and is prepared to rule. For the
following reasons, APTIM’s Partial MSJ is granted.
I. RELEVANT BACKGROUND
A. Factual Background
Following Hurricane Ian, the United States Army Corps of Engineers (“USACE”)
undertook to build temporary housing (“the Project”) in Lee County, Florida. (Statement of
Material Facts (“SMF”), Doc. 118-1 at 1, ¶ 1.)1 The USACE hired Brice Aptim JV, LLC
(“BAJV”) as general contractor. (Id.) BAJV subcontracted work to its member APTIM. (Id. at 1,
¶ 2.) In turn, APTIM subcontracted work to Timberline. (Id. at 1–2, ¶ 3.) Under the subcontract
1 Unless otherwise indicated (e.g., with a qualifying record citation), when the Court cites the Statement of Material
Facts, Timberline has admitted the cited material. See M.D. La. Civ. R. 56(f).
between APTIM and Timberline (“the Timberline Subcontract”), Timberline was to construct the
Project’s water, sewer, and drainage systems, among other improvements. (See Doc. 118-4 at 40.)
The USACE’s specifications for the Project incorporated the Lee County Utilities Operational
Manual (“the Manual”). (See, e.g., Doc. 118-5 at 131 n.1.) Section 3 of the Manual—titled
“Sanitary Sewer Systems”—therefore controlled Timberline’s work on the sewer system. (Id. at
146.) Section 3.4 opens: “It is imperative that all sanitary sewers and associated service lines be
constructed watertight to prevent infiltration and/or exfiltration.” (Id. at 157.)
1. Timberline Subcontract
The Timberline Subcontract provided that Timberline “shall supervise and direct the
Subcontract Work, and shall cooperate with [APTIM] in scheduling and performing the
Subcontract Work to avoid conflict, delay in, or interference with the Project, the [USACE], or
[APTIM].” (Doc. 118-4 at 45.) Timberline had “the sole authority to control and direct the
performance of the details of the Subcontract Work being rendered by its and its lower tier sub-
subcontractors’ employees.” (Id. at 54.) “[T]he detail, manner and method of performing
Subcontract Work [was] the responsibility of, and under the supervision and control of
[Timberline] and its Subcontractors.” (Id.) In addition, Timberline warranted that its work would
be (i) of good quality and new, and free from defects and deficiencies (including
with respect to, but not limited to, materials, construction, design, title and
workmanship); (ii) fit for the purposes specified in the Subcontract or, where no
such purpose [wa]s specified, fit for its ordinary purpose; (iii) performed in
accordance with all law; (iv) performed in accordance with the specifications,
requirements and conditions of the Subcontract; (v) performed in accordance with
the Project schedule or otherwise timely; (vi) performed with a high degree of care
and professional skill and diligence and (vii) sufficient to achieve the performance
criteria (if any) set out in the Subcontract.
(Id. at 50.) Any work which did not conform to the above was “defective.” (Id.) “[W]ithin 24 hours
of discovering defective work or after receiving notice from [APTIM],” Timberline was required
to “proceed to take down and remove” all defective work and to “replace same with proper and
satisfactory Subcontract Work.” (Id.) Lastly, APTIM was authorized to terminate the Timberline
Subcontract “by issuance of a written termination notice to [Timberline]” if
in [APTIM’s] sole discretion, any or all Subcontract Work to be performed under
[the Timberline] Subcontract [wa]s abandoned by [Timberline]; or [Timberline]
fail[ed] to meet its payroll or other current obligations, or allow[ed] any liens to
attach to the site of the Subcontract Work or bonds; or the schedule of the
Subcontract Work [wa]s not being maintained; or [Timberline] [wa]s in breach of
or [wa]s otherwise violating any of the conditions, provisions, obligations, or
representations contained in the[] [Terms & Conditions] or [the Timberline]
Subcontract, in whole or in part; or [Timberline] [wa]s refusing or failing to
perform properly any Subcontract Work; or [Timberline] [wa]s failing to provide
the labor, supervision, tools, equipment or materials necessary for the prompt
performance of the Subcontract Work or [wa]s failing to use due diligence in the
performance thereof . . . .
(Id. at 58 (emphasis added).)
Absent any state laws governing the contract between the USACE and BAJV (“the Prime
Contract”), the Timberline Subcontract was to be “governed by and interpreted pursuant to the
rules and laws of the state” where the Prime Contract work was performed. (Id. at 61.) The Prime
Contract provided only that “United States law will apply to resolve any claim of breach.” (Doc.
118-3 at 169.) The parties therefore agree that Florida law governs the Timberline Subcontract.
(See Doc. 118-2 at 7 (“Florida contract law will supply the key princip[le]s applicable here.”);
Doc. 134 at 13, 23 (applying Florida’s implied covenant of good faith and fair dealing).)
2. Timberline’s Performance
The USACE issued a “Notice to Proceed” with the Project on April 21, 2023. (Doc. 136-4
at 1–2.) The period of performance was 60 days—from April 21 until June 20, 2023. (Id.) On May
6, 2023, Timberline notified APTIM of “potential delays in the schedule due to unforeseen
conditions,” including a layer of limestone rock, changes to the design of the Project, and “design
issues” like “incorrect elevations” and “unidentified existing systems/structures.” (Doc. 136-8 at
1–2; see also Doc. 134-1 at 20, ¶ 7.) Timberline reserved its right to seek an extension of time for
performance and advised that it would (1) keep APTIM apprised of delays and (2) “diligently seek
to minimize . . . the effects of the[] [existing] delays on [Timberline’s] work.” (Doc. 136-8 at 2.)
On May 25, 2023, APTIM sent a cure notice to Timberline via e-mail. (Doc. 118-7 at 1–
2.) That notice expressed concern that, “based on the level of resources . . . on site,” Timberline
would not meet its deadline. (Id. at 2.) It also informed Timberline that APTIM would “mobilize”
its own resources in order to assist Timberline. (Id.) APTIM was entitled to do so under the
Timberline Subcontract. (See Doc. 118-4 at 60.) As directed by the cure notice, Timberline
provided APTIM with a corrective action plan on May 26, 2023. (Doc. 118-1 at 2, ¶ 6.) That plan
indicated that Timberline was already working on the sewer system and estimated completion
thereof by June 6, 2023. (Doc. 118-7 at 5.) It also explained that, by May 30, 2023, Timberline
expected to have approximately 16 employees working on site. (Id. at 6.) Between May 25 and
May 29, 2023, Timberline had 17–18 employees on site. (Doc. 118-1 at 3, ¶ 11.) APTIM “did not
have a single operator or laborer on site” on May 27, 2023. (Id. at 3, ¶ 12.) It had one operator on
site on May 28, 2023. (Id.) And it had one operator and one laborer on site on May 30, 2023.2 (Id.)
On May 29, 2023, the USACE sent BAJV a letter expressing concern over “significant
deficiencies” with “the [P]roject’s underground utilities.” (Doc. 118-7 at 9.) The USACE attributed
at least some of the defective work to “lack of proper equipment” and “lack of qualified personnel,”
as well as failures of quality control. (Id.) APTIM forwarded this letter to Timberline on May 30,
2023. (Doc. 118-9 at 1–3.) Subsequently, on June 1, 2023, a Lee County inspector noted that “no
2 The parties do not mention May 29, 2023. (See, e.g., Doc. 118-1 at 3, ¶¶ 11–12 (citing Doc. 118-3 at 517–31).)
Having examined the record, the Court observes that the “Daily Log of Construction” cited by APTIM jumps from
Sunday, May 28 to Monday, May 30. (Doc. 118-3 at 524–25.) May 30 fell on a Tuesday in 2023. Presumably, then,
when the parties discuss the number of APTIM operators and laborers on-site on May 30, they are actually discussing
the number of APTIM operators and laborers on-site on May 29. But because the “Daily Log of Construction” does
not clearly indicate whether the day of the week or the date itself is incorrect—and because the parties do not dispute
the facts which rely on this record citation—the Court will use May 30, same as the parties.
less than ten sewer service laterals were incorrectly installed and required rework.” (Doc. 118-1 at
3, ¶ 13.) In addition, this inspector “personally observed laterals being installed in violation of Lee
County specifications.” (Id.) Timberline was performing this defective work. (Id. at 4, ¶ 16.) At
the USACE’s direction, incorrectly installed lines were “ripped out and replaced.” (Id. at 4, ¶ 15.)
On June 8, 2023, APTIM issued a second cure notice to Timberline. (Doc. 118-7 at 19–
20.) The subject line read: “CURE NOTICE – Failure to Construct, Failure to provide appropriate
and trained personnel, Failure to meet technical project requirements without re-work.” (Id. at 19
(emphasis omitted).) The notice identified defective work performed on multiple occasions,
including on June 8 and “[d]uring the first visit by Lee County, on June 1.” (Id. at 19–20.) APTIM
warned that “[a] single additional instance of re-work caused by Timberline’s inability to
construct accurately and in accordance with specifications and schedule w[ould] result in
immediate termination for default.” (Id. at 20 (emphasis in original).) APTIM requested that
Timberline submit another corrective action plan. (Id.)
In its second corrective action plan, Timberline assured APTIM that it “ha[d] the resources,
skilled trades, and management” to perform “in accordance with the plans and specifications and
within the contract period of performance.” (Id. at 21.) It pointed, however, to “delays beyond [its]
control,” including “unquantifiable delays . . . caused by BAJV personnel added to ‘assist’
Timberline.” (Id.) Timberline suggested that the defective work on June 8 “could have been
avoided if APTIM and Br[i]ce’s personnel were not involved in the construction activities.” (Id.)
As for the defective work on June 1, Timberline acknowledged that it had “misinterpreted the
plans,” although it blamed this mistake on “drawing inconsistencies.” (Id. at 22.) Timberline added
that neither the USACE nor BAJV had “raise[d] concerns about improperly installed sewer lines
during the installation.” (Id.) Lastly, Timberline reiterated that it “c[ould] complete th[e] work as
required by the plans and specifications and within the required timeline.” (Id.)
Subsequently, the Lee County inspector performed “a couple” of pressure tests in order to
ensure that the sewer system was watertight. (Doc. 118-10 at 12–13; see also Doc. 118-5 at 146,
157 (“It is imperative that all sanitary sewers and associated service lines be constructed watertight
to prevent infiltration and/or exfiltration.”).) The sewer system failed these pressure tests and
therefore was “not acceptable to Lee County.” (Doc. 118-10 at 13.) Timberline was present for the
failed tests. (Id.) Additionally, Timberline noted in its Daily Reports from June 21 through June
24, 2023, that it was finding and repairing sewer leaks. (Doc. 118-7 at 54, 70, 105, 109, 157, 186.)
APTIM and Brice assigned employees to “supplement Timberline’s . . . work” on the sewer
system. (Doc. 136-32 at 7–8.) The parties dispute whether and to what extent APTIM and Brice
employees worked in their own crews, as opposed to being under Timberline’s supervision.
(Compare Doc. 118-15 at 4–5, with Doc. 136-34 at 8–9, 13; Doc. 136-35 at 6; Doc. 136-36 at 7.)
Regardless, these APTIM and Brice employees seemingly worked extensively on the sewer mains.
(See, e.g., Doc. 136-33 at 3; Doc. 136-34 at 10; Doc. 136-35 at 3–5; Doc. 136-36 at 5; Doc. 136-
39 at 3–4; Doc. 136-41 at 5–6.) However, the Lee County inspector testified that, when he visited
the site, “[i]t was Timberline doing most of the sewer line work”—both to the sewer mains and to
the sewer laterals. (Doc. 118-10 at 5.) According to the inspector, Timberline’s employees were
readily identifiable because “[t]hey had their Timberline shirts on.” (Id. at 5–6.) At the time, the
inspector did not see APTIM or Brice employees working on the sewer line. (Id. at 6.)
While on site, Timberline “attended meetings with [the] USACE where [the USACE] was
critical of the [Project’s] infrastructure construction.” (Doc. 118-1 at 8, ¶ 41.) Further, the USACE
“regularly requested” that BAJV’s responsible manager “accompany [the] USACE into the field
to look at deficiencies in Timberline’s work.” (Id. at 8, ¶ 42; see also Doc. 118-14 at 6–7
(explaining that the USACE was “severe[ly] frustrat[ed]” with Timberline and was “on board and
agreed with terminating Timberline”).)
On June 23, 2023, APTIM sent Timberline a “Notification of Breach of Contract,”
explaining that the period for “substantial completion” of the Project had already elapsed and that
“[Timberline’s] performance ha[d] resulted in a delay which forecast[] [late] completion of the
[P]rime [C]ontract . . . and therefore [wa]s in breach.” (Doc. 118-7 at 190–91.) Then, on June 25,
2023, APTIM informed Timberline via e-mail that it was terminating the Timberline Subcontract.
(Doc. 118-4 at 66.) A more formal “Notice of Termination for Default” followed on June 27, 2023.
(Doc. 118-7 at 192–93.) In that notice, APTIM explained that it was terminating Timberline for
“the continued performance and schedule issues addressed with Timberline” via on-site meetings
and correspondence. (Id. at 192.) “At the time Timberline was terminated, Lee County had not
accepted any of the work performed by Timberline on the sewer lines.” (Doc. 118-1 at 8, ¶ 40.)
B. Procedural Background
Timberline filed suit against APTIM in the Middle District of Florida on August 11, 2023.
(Doc. 1.) On August 15, 2024, the Middle District of Florida transferred the case to this Court due
to a forum-selection clause in the Timberline Subcontract. (Doc. 66.) Shortly before transfer—on
July 31, 2024—Timberline filed its Third Amended Complaint (Doc. 63), bringing claims against
APTIM for, inter alia, breach of contract and breach of the implied covenant of good faith and fair
dealing. (Doc. 63 at 13, 15–16.) Both of these claims allege that APTIM improperly terminated
Timberline for default. (Id.) The parties have sought a bench trial in the present case. On August
29, 2025, APTIM filed the instant motion, seeking partial summary judgment “on the issue of
whether APTIM properly terminated, for cause, its contract with [Timberline].” (Doc. 118-2 at 1.)
II. SUMMARY JUDGMENT STANDARD
“The court shall grant summary judgment if the movant shows that there is no genuine
dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R.
Civ. P. 56(a). “The movant bears the initial burden and must identify ‘those portions of the
pleadings, depositions, answers to interrogatories, and admissions on file, together with the
affidavits, if any, which it believes demonstrate the absence of a genuine issue of material fact.’”
Pioneer Expl., L.L.C. v. Steadfast Ins. Co., 767 F.3d 503, 511 (5th Cir. 2014) (quoting Celotex
Corp. v. Catrett, 477 U.S. 317, 323 (1986) (internal quotation marks omitted)).
“A movant for summary judgment need not set forth evidence when the nonmovant bears
the burden of persuasion at trial.” Wease v. Ocwen Loan Servicing, L.L.C., 915 F.3d 987, 997 (5th
Cir. 2019) (citing Celotex, 477 U.S. at 323 (“[W]e find no express or implied requirement in Rule
56 that the moving party support its motion with affidavits or other similar materials negating the
opponent’s claim.” (emphasis in original))). “The moving party may meet its burden to
demonstrate the absence of a genuine issue of material fact by pointing out that the record contains
no support for the non-moving party’s claim.” Id. (quoting Stahl v. Novartis Pharm. Corp., 283
F.3d 254, 263 (5th Cir. 2002)).
If the movant bears its burden of showing that there is no genuine issue of material fact,
“its opponent must do more than simply show that there is some metaphysical doubt as to the
material facts. . . . [T]he nonmoving party must come forward with ‘specific facts showing that
there is a genuine issue for trial.’” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S.
574, 586–87 (1986) (internal citations omitted) (quoting Fed. R. Civ. P. 56(e)). The nonmovant’s
burden is not satisfied by “conclusory allegations, by unsubstantiated assertions, or by only a
scintilla of evidence.” Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994) (en banc) (per
curiam) (cleaned up).
Additionally, “[w]hen evidence exists in the summary judgment record but the nonmovant
fails even to refer to it in the response to the motion for summary judgment, that evidence is not
properly before the district court.” Malacara v. Garber, 353 F.3d 393, 405 (5th Cir. 2003) (citing
Ragas v. Tenn. Gas Pipeline Co., 136 F.3d 455, 458 (5th Cir. 1998); Skotak v. Tenneco Resins,
Inc., 953 F.2d 909, 916 (5th Cir. 1992)). “Rule 56 does not impose upon the district court a duty
to sift through the record in search of evidence to support a party’s opposition to summary
judgment.” Id. (quoting, inter alia, Ragas, 136 F.3d at 458); see also Nissho-Iwai Am. Corp. v.
Kline, 845 F.2d 1300, 1307 (5th Cir. 1988) (rejecting the position “that the entire record in the
case must be searched and found bereft of a genuine issue of material fact before summary
judgment may be properly entered”); cf. United States v. Dunkel, 927 F.2d 955, 956 (7th Cir. 1991)
(per curiam) (“Judges are not like pigs, hunting for truffles buried in briefs.”).
“[W]here the record taken as a whole could not lead a rational trier of fact to find for the
non-moving party, there is no genuine issue for trial.” Matsushita Elec. Indus. Co., 475 U.S. at 587
(cleaned up). Further:
In resolving the motion, the court may not undertake to evaluate the credibility of
the witnesses, weigh the evidence, or resolve factual disputes; so long as the
evidence in the record is such that a reasonable jury drawing all inferences in favor
of the nonmoving party could arrive at a verdict in that party’s favor, the court must
deny the motion.
Int’l Shortstop, Inc. v. Rally’s, Inc., 939 F.2d 1257, 1263 (5th Cir. 1991) (citations omitted).
Finally, the Fifth Circuit has explained:
“[A] district court has somewhat greater discretion to consider what weight it will
accord the evidence [presented on a motion for summary judgment] in a bench trial
than in a jury trial.” If a “[bench] trial on the merits will not enhance the court’s
ability to draw inferences and conclusions, then a district court properly should
‘draw his inferences without resort to the expense of trial.’” However, the Fifth
Circuit has cautioned that “a district court must be aware that assessments of
credibility come into sharper focus” at the time of trial, therefore, “even at the
summary judgment stage a judge in a bench trial has the limited discretion to decide
that the same evidence, presented to him or her as trier of fact in a plenary trial,
could not possibly lead to a different result.”
Turner v. Pleasant, No. 10-1823, 2013 WL 823426, at *7 (E.D. La. Mar. 6, 2013) (quoting In re
Placid Oil Co., 932 F.2d 394, 397–98 (5th Cir. 1991)); accord In re Ecoserv, No. 19-132, 2021
WL 26953, at *2 (M.D. La. Jan. 4, 2021) (Dick, C.J.); see also In re Placid Oil Co., 932 F.2d at
398 (“We follow the Nunez court in recognizing that it makes little sense to forbid the judge from
drawing inferences from the evidence submitted on summary judgment when that same judge will
act as the trier of fact, unless those inferences involve issues of witness credibility or disputed
material facts.” (citing Nunez v. Superior Oil Co., 572 F.2d 1119, 1124 (5th Cir. 1978))).
III. PARTIES’ ARGUMENTS
A. APTIM’s Partial MSJ (Doc. 118)
APTIM stresses that the only question currently before the Court is whether, in terminating
the Timberline Subcontract, APTIM “exercised its sole discretion in good faith.” (Doc. 118-2 at
1.) According to APTIM, it did. (Id.) Specifically, APTIM terminated the subcontract because
Timberline engaged in “unsafe work practices,” performed “defective[]” work, and “refus[ed] to
procure a payment and performance bond.” (Id. at 2.) Consequently, APTIM says, partial summary
judgment is warranted, and the Court should “find[] that [APTIM] properly terminated Timberline
for cause under the subcontract terms[,] with damages to be determined at trial.” (Id.) APTIM
notes also that Timberline “has failed to allege that APTIM acted in bad faith in exercising its sole
discretion” to terminate Timberline. (Id. at 1 n.2.) Such a claim would require showing “that
APTIM acted capriciously and that ‘no reasonable party would have made the same discretionary
decision.’” (Id. at 2 (quoting Ernie Haire Ford, Inc. v. Ford Motor Co., 260 F.3d 1285, 1291 (11th
Cir. 2001) (cleaned up)).)
APTIM recites the following legal principles: First, the meaning of each contract provision
is a question of law. (Id. at 7 (citing Otis Elevator v. WG Yates & Sons Constr. Co., 589 F. App’x
953, 958 (11th Cir. 2014) (per curiam)).) Second, a court must read contract provisions
“harmoniously,” giving effect to each. (Id. (quoting Devs. Sur. & Indem. Co. v. Archer W.
Contractors, LLC, No. 16-1875, 2018 WL 2100032, at *5 (M.D. Fla. May 7, 2018)).) And third,
under Florida law, contracts “contain an implied covenant of good faith and fair dealing.” (Id.
(citing Archer, 2018 WL 2100032, at *8, *11).) This covenant limits “somewhat” provisions
allowing parties to act in their “sole discretion.” (Id. (emphasis omitted) (quoting Ernie Haire
Ford, 260 F.3d at 1291).) A discretionary decision is made in bad-faith if “no reasonable party
would have made [it].” (Id. (emphasis omitted) (quoting Ernie Haire Ford, 260 F.3d at 1291).)
But otherwise, this “sole discretion” language affords “substantial leeway.” (Id. (emphasis
omitted) (quoting Archer, 2018 WL 2100032, at *11).)
APTIM argues that the Timberline Subcontract’s “Termination for Default” provision
allowed APTIM to terminate Timberline if, in APTIM’s sole discretion, Timberline (1) breached
the Timberline Subcontract in whole or in part; (2) “fail[ed] to perform properly any Subcontract
Work”; (3) performed work “not in accordance with the terms of the Subcontract”; or (4) “fail[ed]
to provide the labor, supervision, tools, equipment or materials necessary for the prompt
performance of the Subcontract Work.” (Id. at 8 (quoting Doc. 118-4 at 58).) In APTIM’s view, it
“had at least three legitimate reasons for terminating Timberline.” (Id. at 9.)
1. Defective Work
First, Timberline’s work (e.g., installing sewer lines, installing the reinforced concrete pipe
used in the stormwater system) was defective. (Id. (referencing Doc. 118-4 at 50–51).) And despite
receiving a cure notice on May 25, 2023, “Timberline failed to remedy” the defects. (Id. at 10; see
also id. at 10–11 (citing Doc. 118-5 at 26–28; Doc. 118-7 at 1–8).)3 On May 29, 2023, the USACE
issued a “letter of concern” to APTIM, noting “significant deficiencies” with the sewer system,
which “appeared to be the result of a lack of proper equipment . . . [and] qualified personnel.” (Id.
at 11 (quoting Doc. 118-7 at 9).) APTIM forwarded this letter to Timberline on May 30, 2023. (Id.
(citing Doc. 118-9).) Then, on June 1, 2023, a Lee County inspector “personally observed”
Timberline employees performing defective work. (Id. (citing Doc. 118-10 at 11–12).) Timberline
admits that it was performing defective work on that day. (Id. at 11–12 (citing Doc. 118-5 at 32).)
On June 8, 2023, APTIM sent Timberline a second cure notice. (Id. at 12 (citing Doc. 118-
7 at 19–20).) At that time, APTIM informed Timberline that “[a] single additional instance of re-
work caused by Timberline’s inability to construct accurately and in accordance with
specifications and schedule w[ould] result in immediate termination for default.” (Id. at 12
(emphasis omitted) (quoting Doc. 118-7 at 20).) Thereafter, the sewer lines installed by Timberline
failed to pass the pressure tests required by the Timberline Subcontract. (Id. at 12–13 (citing, inter
alia, Doc. 118-10 at 13; Doc. 118-7 at 47–193; Doc. 118-5 at 131 n.1).) “At the time Timberline
was terminated, Lee County had not accepted any of the work performed by Timberline on the
3 Throughout its brief, APTIM has cited “deposition exhibits” contained within larger submissions. (See, e.g., Doc.
118-2 at 12 n.62.) In particular, APTIM makes frequent reference to deposition exhibits within Exhibit C. (Id.) Exhibit
C is more than 1,200 pages long. Deposition exhibit numbers appear only on the first page of each deposition exhibit.
APTIM has provided no other way to identify deposition exhibits, forcing the Court to search (repeatedly) for the
needle in the haystack. The parties are reminded that it is not the job of this Court to sift through thousands of pages
to find the parties’ support for their respective positions. See, e.g., M.D. La. Civ. R. 7(d), (f); id. 56(f); see also Dunkel,
927 F.2d at 956 (“Judges are not like pigs, hunting for truffles buried in briefs.”).
sewer lines.” (Id. at 14 (cleaned up) (citing Doc. 118-10 at 18).) “Without Lee County’s acceptance
of the Subcontract Work, the sewer system could never be placed into service . . . .” (Id.)
APTIM draws parallels to Developers Surety & Indemnity Co. v. Archer Western
Contractors, LLC, where the court granted summary judgment in favor of a contractor which had
exercised its sole discretion in terminating a subcontractor, consistent with the subcontract terms.
(Id. at 14–15 (citing Archer, 2018 WL 2100032, at *11).) In that case, the court determined that
there was no genuine issue whether the contractor acted in good faith, in part because of the
“numerous documented complaints” as well as a Registered Landscape Architect Report
concerning the subcontractor’s deficient work. (Id. (quoting Archer, 2018 WL 2100032, at *12).)
APTIM observes that, here, Timberline’s performance was likewise defective. (Id. at 15–16.)
Thus, APTIM contends, it “properly exercised its sole discretion in terminating the Subcontract.”
(Id. at 16.) It emphasizes that it gave Timberline multiple opportunities to cure. (See id. at 16–17;
see also id. at 17–18 (citing, inter alia, Doc. 118-12 at 2–3; Doc. 118-7 at 11–15) (adding that
there were multiple “on-site discussions about Timberline’s failures” and that Timberline was “on
site when its noted deficiencies occurred”).)
2. Unsupervised, Unskilled, Unsafe Work
Second, APTIM argues that, despite Timberline’s representations that it was “fully skilled
and experienced ‘in all work necessary to successfully complete the Subcontract Work,’ including
supervision,” “no one at Timberline had operational control of the Subcontract Work.” (Id. at 21–
22 (emphasis omitted) (citing Doc. 118-4 at 50).) Further, “most of Timberline’s subcontractors
for this project were not skilled laborers.” (Id. at 23 (citing Doc. 118-5 at 20–21).) APTIM repeats
that the USACE suggested that “lack of qualified personnel” was a reason for the “significant
deficiencies” with the sewer system. (Id. at 22 (quoting Doc. 118-7 at 9).) It adds that Timberline
was required to supply personnel under the Timberline Subcontract. (Id. (citing Doc. 118-4 at 39).)
Further, APTIM says, Timberline performed unsafe work, despite the Timberline
Subcontract’s requirement that Timberline “take reasonable safety precautions with respect to the
performance of the Subcontract Work.” (Id. at 23 (citing Doc. 118-4 at 50).) Specifically, one
Timberline employee “failed to adhere to the warnings inside the cab of an excavator and broke
the glass with the attached bucket.” (Id. (citing Doc. 118-8 at 9–11).) Another “was operating an
excavator and hit two sewer laterals, requiring rework.” (Id. (citing, inter alia, Doc. 118-5 at 38).)
And a third “was removed [from the Project] for hot fueling a water pump.” (Id. (citing Doc. 118-
8 at 11, 13, 55).) APTIM contends that “each instance of unsafe work . . . was . . . a good[-]faith
reason for termination.” (Id.) It reiterates that the USACE frequently complained about
Timberline’s performance. (Id. at 24 (citing, inter alia, Doc. 118-14 at 3–4).)
3. Failure to Procure Bond
Third, APTIM argues that Timberline failed to procure a payment and performance bond,
despite being required to do so and despite “includ[ing] pricing for a bond in its proposal” to
APTIM, as well as in an invoice dated May 15, 2023. (Id. at 24–25 (citing Doc. 118-5 at 10, 702–
05).) According to APTIM, “the final specifications for the project required a performance bond.”
(Id. at 25 (citing Doc. 118-5 at 16–17, 338).) On June 23, 2023, APTIM demanded that Timberline
“furnish the Payment and Performance bond or a letter of credit for the full contract value by June
24, 2023, or be held in default.” (Id. (citing Doc. 118-7 at 190–91).) “Timberline presented no such
bond and no credit for same.” (Id.) APTIM claims that Timberline’s failure here was “another
contractually sound reason for termination.” (Id. (citing Logan & Clark, Inc. v. Adaptable Dev.,
Inc., 450 So. 2d 1189, 1190 (Fla. 4th DCA 1984) (per curiam)).)
B. Timberline’s Opposition (Doc. 134)
Timberline counters that, because the termination of a contract is a “drastic action,” courts
“require strict compliance with the terms of the relevant contract and that the terminating party
first provide” adequate notice and an opportunity to cure. (Doc. 134 at 1.) Timberline denies that
APTIM can show material breach, adequate notice, and an opportunity to cure. (Id. at 1.)
“Termination would be improper because Timberline promptly began to repair each instance of
non-conf[o]rming work once made aware.” (Id.) Timberline also contends that APTIM is
responsible for some of the defective work, both by doing such work itself and by refusing to give
Timberline additional time for performance. (Id. at 1–2.) According to Timberline, termination for
unsafe work was improper “because APTIM never stated [that] it [was] terminat[ing] Timberline
for safety.” (Id. at 2.) Likewise, termination for failure to procure a bond was improper “because
the subcontract did not require Timberline to provide a bond until requested.” (Id.)
Timberline reiterates that termination for cause is a “‘drastic sanction’ which should be
imposed (or sustained) only for good grounds and on ‘solid evidence.’” (Id. at 8 (quoting CJP
Contractors, Inc. v. United States, 45 Fed. Cl. 343, 371 (1999)); see also id. at 8–9 (citing 7 Bruner
& O’Connor on Construction Law § 18:39 (2024) (citations omitted)).) Thus, “even when a
contract does not explicitly require notice and an opportunity to cure, courts imply the requirement
as a matter of law for construction contracts.” (Id. at 9 (citing Centerplan Constr. Co., LLC v. City
of Hartford, 343 Conn. 368, 412 (2022); 5 Bruner & O’Connor on Construction Law § 18:15
(2014)); see also id. (citing MV Lady B, LLC v. Rolly Marine Serv. Co., No. 23-61769, 2024 WL
4881034, at *3–4 (S.D. Fla. Oct. 9, 2024)).) APTIM must therefore prove: (1) material breach,
(2) “APTIM’s lack of prior breach,” (3) APTIM’s good faith, (4) adequate notice, and (5) a
reasonable opportunity to cure. (Id. at 9–10.)
1. “Sole Discretion”
First, Timberline disagrees that the Timberline Subcontract gave APTIM “sole discretion”
to terminate Timberline for the reasons given and argues that “there is at least a question of fact as
to Timberline’s alleged default.” (Id. at 7–8; see also id. at 10.) In Timberline’s view, the relevant
subcontract provision is “clear as mud.” (Id. at 10.) But simultaneously, Timberline insists that the
“sole discretion” language modifies “only the first item in the list.” (Id.) Accordingly, APTIM
could, in its sole discretion, determine that Timberline abandoned “any or all Subcontract Work”
but not, e.g., that Timberline “perform[ed] Subcontract Work not in accordance with the terms of
the Subcontract.” (Id. at 11.) Timberline contends that this interpretation of the provision “is
supported by the basic rules of contractual interpretation,” explaining that, under the “proximity
rule,” “modifiers generally attach to the nearest reasonable word or phrase.” (Id. (citing Bryan A.
Garner, Garner’s Modern English Usage 597 (4th ed. 2016)).) Timberline claims that “[t]here is
no grammatical signal (e.g., a colon) extending the modifier to the entire series.” (Id. at 11–12.)
Rather, the modifier “in [APTIM’s] sole discretion” is “embedded within the first ‘if’ condition.”
(Id. at 11.)
Timberline gives additional reasons for its reading of the relevant provision. “Under
parallelism rules, modifiers do not automatically ‘float’ across coordinate clauses unless repeated
or clearly scoped.” (Id. at 12 (quoting Garner, Garner’s Modern English Usage, supra, at 670–71)
(citing Bryan A. Garner, The Redbook: A Manual on Legal Style § 10.50(b) (3d ed. 2013)).) And
commas set off the “sole discretion” language, “mak[ing] it a parenthetical, [thereby] limiting its
reach to its immediate clause.” (Id. (citing Garner, The Redbook, supra, § 1.3).) At a minimum,
Timberline says, the provision is ambiguous, in which case it must be construed against the drafter
(i.e., APTIM). (Id. (citing First Fin. N.W., Inc. v. Laver, 410 So. 3d 1, 3 (Fla. 4th DCA 2025)).) It
therefore reiterates that “APTIM only had ‘sole discretion’ to determine whether Timberline
abandoned, not whether it was in default for any other reason.” (Id.)
2. Notice & Opportunity to Cure
Next, Timberline explains that the implied covenant of good faith and fair dealing “is a
‘gap-filling default rule’ which is ‘usually raised when a question is not resolved by the terms of
the contract or when one party has the power to make a discretionary decision without defined
standards.’” (Id. at 13 (quoting Publix Super Mkts., Inc. v. Wilder Corp. of Del., 876 So. 2d 652,
654 (Fla. 2d DCA 2004)).) It “cannot be used to vary the unambiguous terms of a written contract.”
(Id. (quoting Avatar Dev. Corp. v. De Pani Constr., Inc., 834 So. 2d 873, 876 (Fla. 4th DCA
2002)).) Thus, Timberline argues, “all objective requirements still apply,” meaning that APTIM
must still “show notice, opportunity to cure, and lack of prior breach.” (Id. (citing 7 Bruner &
O’Connor on Construction Law § 18:39 (2024)).)
A cure notice must, according to Timberline, “fairly appraise the breaching party of the
specific breaches considered to warrant termination.” (Id. (quoting 7 Bruner & O’Connor on
Construction Law § 18:41 (2024)).) “[I]nforming the other party of an issue, without indication
that the non-breaching party is considering termination, is insufficient.” (Id. at 14 (citing Hannon
Elec. Co. v. United States, 31 Fed. Cl. 135, 148 (1994), aff’d, 52 F.3d 343 (Fed. Cir. 1995);
Eddystone Borough v. Peter V. Pirozzi Gen. Contracting, LLC, No. 13-1470, 2015 WL 1542284,
at *8 (E.D. Pa. Apr. 7, 2015)).)
3. Performance & Bond Procurement
Timberline contends that APTIM could not have properly or in good faith terminated
Timberline for defective work “because Timberline promptly began to repair each and every
instance of improper work of which it had knowledge.” (Id.) According to Timberline, APTIM
must show not only that Timberline’s work was defective but also that, in contravention of Section
11 of the Timberline Subcontract, Timberline failed to take remedial action within the appropriate
timeframe. (Id. at 15.) Timberline avers that, in all cases, it timely took such action. (Id. (citing,
inter alia, Doc. 136-32 at 9–18).) It also asserts that it was “actively working on repairs” to the
sewer system but was terminated—without notice or an opportunity to cure—before those repairs
could be completed. (Id. at 15–16 (citing Doc. 136-32 at 31; Doc. 136-39 at 6).)
In addition, Timberline argues that APTIM has not established that Timberline was
responsible for all defective work, noting that APTIM and Brice both sent employees to
supplement Timberline’s work, including on the sewer system. (Id. at 16 (citing, inter alia, Doc.
136-32 at 7–8); see also id. at 16–17.) Specifically, Timberline says, APTIM and Brice employees
“installed the entirety of the sewer mains except one portion.” (Id. at 16 (citing, inter alia, Doc.
136-33 at 3–4).) Terminating the Timberline Subcontract “for defective work performed by
APTIM’s own employees cannot be a proper termination []or an exercise in good faith.” (Id.)
Finally, Timberline blames APTIM for “failing to provide Timberline additional time” to perform,
which “contributed to quality issues” by forcing Timberline to “stack[]” tasks rather than to
complete them “in a linear sequence.” (Id. at 17 & n.1 (citing Doc. 136-33 at 12–13, 16–17, 18–
20; Doc. 136-28 at 1–2).) Timberline contends that APTIM’s failure was a breach of contract. (Id.)
Timberline further argues that APTIM has “take[n] [the] USACE’s complaint regarding
the ‘lack of proper equipment’ and ‘lack of qualified personnel’ out of context.” (Id. at 17 (citing
Doc. 118-2 at 22).) According to Timberline, the USACE’s May 29 letter pertained to failures of
quality control, for which APTIM was responsible. (Id. (citing Doc. 118-2 at 22; Doc. 136-32 at
3).) Timberline avers that it had proper equipment on-site, (id. (citing, inter alia, Doc. 136-33 at
4–7)), and that any issues with equipment and personnel were a consequence of the “compression
of the schedule,” (id. (citing Doc. 136-33 at 16–20)). Lastly, Timberline claims that it had
“[m]ultiple competent supervisors” on-site. (Id. at 17–18 (citing, inter alia, Doc. 136-34 at 3–7).)
Timberline denies that “meeting minutes, health and safety reports, and daily reports”
constituted notice, because none of them indicated that “APTIM was considering terminating
Timberline for the issues being raised.” (Id. at 18 (citing 7 Bruner & O’Connor on Construction
Law § 18:41 (2024)); see also id. at 18–19 (rehashing arguments).) And in any event, Timberline
says, it “cured every instance of defective work of which it was aware.” (Id.) Thus, there are
“questions of fact as to whether APTIM properly and in good faith terminated Timberline for
defective work.” (Id. at 19.) Relatedly, Timberline argues that, prior to this litigation, APTIM did
not “use Timberline’s safety record as a reason for termination.” (Id. (citing, inter alia, Docs. 136-
12, 136-19, 136-23).) Consequently, “termination for that reason would be improper.” (Id.) But
regardless, the instances of unsafe work identified by APTIM were “[i]solated” and therefore “can
hardly be considered a ‘persistent’ pattern . . . sufficient to constitute a material breach.” (Id. at 20
(citing 7 Bruner & O’Connor on Construction Law § 18:28 (2024)).)
As for its failure to procure a bond, Timberline argues that (1) APTIM “did not terminate
Timberline because it failed to provide a bond,” and (2) “the Subcontract only required Timberline
to provide a bond upon request.” (Id. at 20–21 (citing Doc. 136-32 at 27–28, 30).) During its
corporate deposition, APTIM did not identify failure to procure a bond as one of the reasons for
terminating Timberline. (Id. at 21 (citing Doc. 136-32 at 27–28, 30).) And during performance of
the Timberline Subcontract, when APTIM at last requested a bond from Timberline, Timberline
promptly reached out to its surety. (Id. (citing Doc. 136-22 at 1).) The surety was willing to furnish
a bond once APTIM provided a letter or e-mail stating that “a bond was required and was
overlooked by the parties” and that “the job [wa]s on schedule and there [we]re no disputes.” (Id.
at 22 (quoting Doc. 136-22 at 1).) Thus, when APTIM demanded that Timberline procure a bond
in its June 23 “Notification of Breach of Contract,” APTIM “knew that Timberline needed
documentation from APTIM to do so.” (Id.) Timberline therefore disputes that this demand for a
bond was made in good faith. (Id.)
4. APTIM’s Lack of Good Faith
Finally, Timberline argues that APTIM did not terminate the Timberline Subcontract in
good faith. (Id. at 23.) Timberline acknowledges that, prior to the “Notice of Termination for
Default,” APTIM provided Timberline with multiple “Letters of Concern / Cure Notices.” (Id.
(citing Doc. 136-25).) Timberline also admits that such correspondence addressed delays, as well
as defective work. (Id. at 23–24.) But Timberline emphasizes that “it was not until [APTIM] sent
the ‘Notification of Breach of Contract’ that [it] formally held Timberline in default.” (Id. at 24.)
“[A]nd even then,” Timberline says, “the default was limited to schedule and delays, which is [sic]
now absent from APTIM’s arguments.” (Id. (citing Doc. 136-32 at 19–24).)
Timberline posits that the reason why APTIM has not cited delay as a basis for termination
is that “BAJV requested and obtained 83 . . . additional days from [the] USACE for the exact same
issues [about which] Timberline complained.” (Id. (citing, inter alia, Doc. 136-29; Doc. 136-30;
Doc. 136-38 at 5–13).) But simultaneously, Timberline speculates that “delay was not even the
true motive for APTIM’s wrongful termination [of Timberline].” (Id. (emphasis omitted).) Instead,
Timberline suggests that APTIM “use[d] Timberline as a scapegoat . . . after [APTIM’s] own poor
management of the project resulted in six written complaints.” (Id. at 24–25; see also id. at 25
(citing Doc. 136-27).) It directs the Court to an e-mail from BAJV’s responsible manager:
At this point, we [BAJV] had our free pass to remove Timberline and make good,
but that card is now 3/4 out the window. The next to come is going to be a full
deficiency in the [quality control] on the project as there are no more
[subcontractors] to pass blame on, plus in my opinion we didn’t respond strong
enough, especially with all the continued repairs that are showing up. Complete
[quality control] failure and incompetence is my guess on the big bomb that the
hatches are open to launch any day. . . . [F]rom my perspective I do not see that the
[quality control] was in place to prevent any of these massive failures.
(Id. (quoting Doc. 136-27 at 1); see also id. (quoting Doc. 136-26 at 1) (“[W]e are about to have
used up our one and only chance at redemption on this project . . . .” (emphasis omitted)).)
C. APTIM’s Reply (Doc. 139)
APTIM reiterates that the only question before the Court is “whether APTIM exercised its
sole discretion in good faith.” (Doc. 139 at 1.) It notes that Timberline “relies heavily on secondary
sources while ignoring case law from Florida directly on point.” (Id. at 1 & n.2 (citing Archer,
2018 WL 2100032).) Specifically, APTIM explains that, in Archer, the court granted summary
judgment over an opposition which relied on a “hypertechnical view of ‘notice’” and which alleged
that the general contractor (i.e., the movant) had “breached the Subcontract on numerous
occasions.” (Id. at 2 (citing Archer, 2018 WL 2100032, at *7, *12).) “[F]inding ‘numerous
documented complaints’ against the subcontractor,” the Archer court “was ‘satisfied’ that the
general contractor did not violate its duty of good faith.” (Id. (citing Archer, 2018 WL 2100032,
at *12).) APTIM urges that Archer “clearly supports granting” the Partial MSJ here. (Id.)
In addition, APTIM says, Timberline’s arguments merely distract from the issue at hand.
(Id.) “Timberline has failed to show that APTIM acted in bad faith, capriciously[,] or in
contravention of the parties’ reasonable expectations.” (Id. at 2–3 (citing Mount Sinai Med. Ctr. of
Greater Miami, Inc. v. Heidrick & Struggles, Inc., 329 F. Supp. 2d 1309, 1313 (S.D. Fla. 2004),
aff’d, 188 F. App’x 966 (11th Cir. 2006)).) Put another way, Timberline has not shown that “no
reasonable party would have made the same discretionary decision” as APTIM. (Id. (emphasis
omitted) (quoting Ernie Haire Ford, 260 F.3d at 1291).)
APTIM observes that the “sole discretion” language in Section 25 of the Timberline
Subcontract precedes items in a series (i.e., a list) and therefore contends that the language logically
concerns the entire series. (Id. at 3 (citing Garner, The Redbook, supra, at § 1.18).) According to
APTIM, case law supports this reading. (Id. at 4 (citing United States v. Marshall, 808 F. App’x
11, 14 (2d Cir. 2020) (summary order); United States v. Loyd, 886 F.3d 686, 688 (8th Cir. 2018);
Philadelphia Indem. Ins. Co. v. Bellin Mem’l Hosp., 126 F.4th 532, 539 (7th Cir. 2025)).) “The
series-qualifier canon ‘requires a modifier to apply to all items in a series when such an application
would represent a natural construction.’” (Id. (quoting Loyd, 886 F.3d at 688).) APTIM argues that
applying the “sole discretion” language to just the first item in the series “results in a nonsensical,
unharmonious interpretation depriving the contract of its natural meaning.” (Id. (citing, inter alia,
Kipp v. Kipp, 844 So. 2d 691, 693 (Fla. 4th DCA 2003)).)
Next, APTIM denies that the implied covenant of good faith and fair dealing required it
“to provide Timberline endless chances to cure its defective work.” (Id. at 5.) The Timberline
Subcontract was clear that “Subcontract Work not conforming to the[] requirements [of the
subcontract] w[ould] be considered defective.” (Id. (quoting Doc. 118-4 at 50).) And “[i]t is
undisputed that there were continuous sewer leaks [which] Timberline failed to cure, and that the
sewer lines failed multiple pressure tests.” (Id. (citing Doc. 118-10 at 13).) Consequently, the Lee
County inspector refused to accept Timberline’s work. (Id. at 6 (citing Doc. 118-2 at 13).) APTIM
also notes that the “Notification of Breach of Contract” specifically mentioned “schedule,
performance, and . . . deficiencies in [Timberline’s] subcontract work.” (Id. (quoting Doc. 136-32
at 21).) APTIM adds that, because the sewer leaks were “continued defects,” Timberline’s
arguments about lack of notice and an opportunity to cure are meritless. (Id. at 5 n.20.)
According to APTIM, it is irrelevant whether APTIM performed defective work on-site.
(Id. at 6.) Under the Timberline Subcontract, Timberline was responsible for the work on the sewer
system. (Id. at 6–7 (referencing Doc. 118-4 at 45).) APTIM could supplement Timberline’s
workforce, “while Timberline retain[ed] full authority over the execution of its contractual
responsibilities.” (Id. at 7.) Indeed, Timberline’s superintendent was “in charge when defective
work was performed.” (Id. (citing Doc. 118-13 at 21–22).) Further, it was Timberline which
“performed the deficient work that Lee County would not accept.” (Id. at 6–7 (citing Doc. 118-5
at 32).) And it was Timberline which failed “to fix the leaks in the sewer system” from June 21–
24. (Id. at 7 (citing Doc. 118-7 at 47–193).)
Penultimately, APTIM observes that the Timberline Subcontract provided for remediation
of defects “within 24 hours of discovering defective work or after receiving notice.” (Id. at 7–8
(emphasis added) (presumably, intending to quote Doc. 118-4 at 50).) Thus, APTIM says,
“‘discovery’ start[ed] the period of time in which an opportunity to cure [wa]s provided.” (Id. at
8.) This interpretation is easy to square with the rest of the Timberline Subcontract, which did not
require that notice be in writing. (Id.) But in any event “APTIM issued two formal cure notices,
each allowing two weeks for Timberline to address the identified defects.” (Id. (citing Doc. 118-7
at 1–2, 19).) And Timberline “readily admits” that it received formal notices from APTIM. (Id. at
7 (citing Doc. 134 at 5).)
APTIM argues that the Timberline Subcontract “did not provide any requirements for a
‘proper’ notice and opportunity to cure.” (Id. at 8.) But the June 8 cure notice was in writing,
identified itself as a cure notice, specified what Timberline needed to address, and warned that
“termination for default was now on the table.” (Id. at 8–9 (citing Doc. 118-7 at 19–20).) APTIM
contests Timberline’s invocation and use of an implied duty of notice and an opportunity to cure:
“To suggest that APTIM could only rely on defective work that Timberline did not repair [as a
basis for termination] misses the point. It was the repeated discovery of defects that caused APTIM
to put termination on the table in its June 8 notice and provided APTIM a basis to terminate the
Subcontract on June 25.” (Id. at 9.)
APTIM makes a number of observations related to the above. First, “it is not unusual for a
construction contract to provide no pre-termination notice and no opportunity to cure.” (Id. at 8
(emphasis omitted) (citing Gibson v. Barron Dev. Corp., 2018 Fla. Cir. LEXIS 12094, at *4 (Fla.
11th Cir. Ct. Mar. 12, 2018)).) Second, where the Subcontract is silent, “federal courts have found
that meeting minutes, phone calls, and verbal communication may constitute sufficient notice.”
(Id. at 9 (citing, inter alia, Parkcrest Builders, LLC v. Hous. Auth. of New Orleans, No. 15-1533,
2017 WL 3394033 (E.D. La. Aug. 8, 2017)).) Third, “Timberline was on site daily and had
numerous conversations with APTIM, [the] USACE, and Lee County regarding the [sewer system]
issues.” (Id.) And fourth, “Timberline was actively discovering leaks through continued failed
pressure tests.” (Id. (citing Doc. 118-8 at 59, 62, 65).)
Finally, APTIM emphasizes that “Timberline was ultimately terminated for its defective
work.” (Id. at 10.) Whether Timberline should have been allowed additional time—and the fact
that APTIM “never gave Timberline any additional time”—are not issues before the Court. (Id.)
IV. DISCUSSION
A. Extent of APTIM’s “Sole Discretion”
1. Interpretation of Contracts, Generally
“The interpretation of a contract is a legal conclusion.” Otis, 589 F. App’x at 958 (citing
Allapattah Servs., Inc. v. Exxon Corp., 333 F.3d 1248, 1261 (11th Cir. 2003)). “[C]ontractual
language is ambiguous only if it is susceptible to more than one reasonable interpretation.”
Seritage SRC Finance, LLC v. Town Ctr. at Boca Raton Tr., 397 So. 3d 44, 46 (Fla. 4th DCA
2024) (emphasis in original) (quoting BKD Twenty-One Mgmt. Co. v. Delsordo, 127 So. 3d 527,
530 (Fla. 4th DCA 2012)). Ambiguities must be “‘construed against the drafter’ of the [contract].”
First Fin. N.W., 410 So. 3d at 3 (quoting City of Homestead v. Johnson, 760 So. 2d 80, 84 (Fla.
2000)). But where one interpretation is sound and another “would be absurd,” the sound
interpretation applies. Seritage, 397 So. 3d at 46–47 (quoting BKD Twenty-One, 127 So. 3d at
530); accord Kipp, 844 So. 2d at 693 (citing Katz v. Katz, 666 So. 2d 1025, 1028 (Fla. 4th DCA
1996)) (“[A] court must construe a contract in a manner that accords with reason and probability
. . . and [must] avoid an absurd construction.”).
Similarly, courts must select an interpretation that gives force to all contractual provisions
“over an alternative interpretation that relies on negation of some of the . . . provisions.” Pierce
Law Grp., LLP v. Factor, 408 So. 3d 148, 151 (Fla. 3d DCA 2025) (quoting Siegle v. Progressive
Consumers Ins. Co., 819 So. 2d 732, 739 (Fla. 2002)). In doing so, courts must ordinarily “give
words and phrases . . . the[ir] natural meaning[s] or th[ose] meaning[s] most commonly
understood” given the context. Rupp Hotel Operating Co. v. Donn, 29 So. 2d 441, 445 (Fla. 1947);
accord Kipp, 844 So. 2d at 693 (citing McIlmoil v. McIlmoil, 784 So. 2d 557, 561 (Fla. 1st DCA
2001)). Ultimately, the court’s role is to enforce the contract, not to “rewrite [it] to make it more
reasonable for one of the parties.” KRG Oldsmar Project Co., LLC v. CWI, Inc., 358 So. 3d 464,
468 (Fla. 2d DCA 2023) (quoting Snyder v. Fla. Prepaid Coll. Bd., 269 So. 3d 586, 592 (Fla. 1st
DCA 2019)); accord Ernie Haire Ford, 260 F.3d at 1290 (“[I]t is well settled that ‘when the terms
of a voluntary contract are clear and unambiguous, . . . the contracting parties are bound by those
terms, and a court is powerless to rewrite the contract to make it more reasonable or advantageous
for one of the contracting parties.’” (quoting Emergency Assocs. of Tampa, P.A. v. Sassano, 664
So. 2d 1000, 1003 (Fla. 2d DCA 1995))).
2. Series-Qualifier Canon
“Typically, ‘a modifier at the beginning . . . of a series of terms modifies all terms.’”
Marshall, 808 F. App’x at 14 (quoting United States v. Lockhart, 749 F.3d 148, 152 (2d Cir. 2014),
aff’d, 577 U.S. 347 (2016)); accord Loyd, 886 F.3d at 687–88 (citing Lockhart, 577 U.S. at 355)
(explaining that the series-qualifier canon “requires a modifier to apply to all items when such an
application would represent a natural construction”); see also Facebook, Inc. v. Duguid, 592 U.S.
395, 403 (2021) (“The [Supreme] Court often applies this interpretive rule, usually referred to as
the ‘series-qualifier canon.’”); cf. id. at 403–04 (“A qualifying phrase separated from antecedents
by a comma is evidence that the qualifier is supposed to apply to all the antecedents instead of
only to the immediately preceding one.” (cleaned up) (quoting W. Eskridge, Interpreting Law: A
Primer on How To Read Statutes and the Constitution 67–68 (2018))).
In Philadelphia Indemnity Insurance Co. v. Bellin Memorial Hospital, for example, the
relevant insurance policy defined a “wrongful act” as “a negligent act, error, or omission.” 126
F.4th at 539. The Seventh Circuit explained that the definition “follows a familiar structure of a
modifier preceding a list of nouns.” Id. at 540. “Grammar rules dictate that when ‘a
straightforward, parallel construction that involves all nouns or verbs in a series’ is preceded by a
modifier, that modifier ‘normally applies to the entire series.’” Id. (quoting Antonin Scalia &
Bryan A. Garner, Reading Law: The Interpretation of Legal Texts 147 (2012)); accord Anhui
Powerguard Tech. Co., Ltd. v. DRE Health Corp., 95 F.4th 1146, 1149–50 (8th Cir. 2024) (citing
State v. Champagne, 561 S.W.3d 869, 873 (Mo. Ct. App. 2018)). “This interpretive rule, known
as the series-qualifier canon, generally provides the most natural reading of a sentence.”
Philadelphia Indem., 126 F.4th at 540; accord Facebook, 592 U.S. at 403.
Likewise, the Eleventh Circuit and Florida courts have implicitly and explicitly applied the
series-qualifier canon when interpreting contracts. See, e.g., ECB USA, Inc. v. Chubb Ins. Co. of
N.J., 113 F.4th 1312, 1322 (11th Cir. 2024) (“[The canon] reflects the unremarkable convention
that ‘[w]hen several words are followed by a clause [that] [] is applicable as much to the first and
other words as to the last, the natural construction of the language demands that the clause be read
as applicable to all.’” (quoting Paroline v. United States, 572 U.S. 434, 447 (2014))); see also
Archer, 2018 WL 2100032, at *2, *11 (considering a conditional sentence similar to the one at
issue here); cf. Davis v. Verandah at Lake Grady Homeowners Ass’n, Inc., 354 So. 3d 1140, 1144–
45 (Fla. 2d DCA 2023) (“Since ‘of record’ appears in the middle of the list, the series[-]qualifier
canon does not apply here.”). Ernie Haire Ford, Inc. v. Ford Motor Co., for example, concerned
a “dealership agreement” which provided: “[Appellee] reserves the right to determine, from time
to time, in its best judgment, the numbers, locations and sizes of authorized dealers necessary for
proper and satisfactory sales and service representation . . . .” 260 F.3d at 1289 (emphasis in
original). The Eleventh Circuit agreed with the district court that “[u]nder the [contract], it [wa]s
[Appellee’s] own judgment that control[led] . . . in determining the relocation of its dealerships.”
Id. at 1291 (second emphasis added). In other words, both courts applied the modifier “in its best
judgment” to the second noun in the series (i.e., “locations”). See id. at 1289, 1291.
3. Analysis
Preliminarily, the Court considers the extent of the application of the “sole discretion”
language appearing in Section 25 of the Timberline Subcontract. (See Doc. 118-4 at 58.) Again,
the relevant portion of that section reads:
If, in [APTIM’s] sole discretion, any or all Subcontract Work to be performed under
[the Timberline] Subcontract [wa]s abandoned by [Timberline]; or [Timberline]
fail[ed] to meet its payroll or other current obligations, or allow[ed] any liens to
attach to the site of the Subcontract Work or bonds; or the schedule of the
Subcontract Work [wa]s not being maintained; or [Timberline] [wa]s in breach of
or [wa]s otherwise violating any of the conditions, provisions, obligations, or
representations contained in the[] [Terms & Conditions] or [the Timberline]
Subcontract, in whole or in part; or [Timberline] [wa]s refusing or failing to
perform properly any Subcontract Work; or [Timberline] [wa]s failing to provide
the labor, supervision, tools, equipment or materials necessary for the prompt
performance of the Subcontract Work or [wa]s failing to use due diligence in the
performance thereof, [APTIM could], without notice to [Timberline’s] sureties and
without prejudice to or limiting other remedies as may be available to [APTIM],
terminate [the Timberline] Subcontract . . . by issuance of a written termination
notice to [Timberline].
(Id.) This lengthy sentence is a conditional. The “if” clause contains items in a series.4 Because
these items are complex—that is, because they feature internal punctuation and/or conjunctions—
they are separated by semicolons rather than commas, consistent with the rules of English
grammar. See, e.g., Bryan A. Garner, The Redbook: A Manual on Legal Style §§ 1.3(b), 1.18(b)
(4th ed. 2018).
The modifier “in [APTIM’s] sole discretion” precedes all items in the series. (Doc. 118-4
at 58.) It can apply as naturally to the last item as to the first. See ECB USA, 113 F.4th at 1322.
Indeed, it would be unnatural if APTIM had “sole discretion” to determine whether Timberline
abandoned the Subcontract Work but not, e.g., whether the schedule was being maintained or
whether Timberline “[wa]s refusing or failing to perform properly any Subcontract Work.” (See
Doc. 118-4 at 58); see also Seritage, 397 So. 3d at 46–47; Kipp, 844 So. 2d at 693. Consequently,
this conditional sentence is unambiguous (i.e., not “susceptible to more than one reasonable
4 It seems to the Court indisputable that the items form a series. (See also Doc. 134 at 12 (describing the items as a
“series of seven ‘if’ conditions joined by or”).) But at least one reason for this reading is that the items are parallel
constructions which “pertain to a common subject matter,” viz., the bases for terminating Timberline. See Anhui, 95
F.4th at 1150; see also Philadelphia Indem., 126 F.4th at 540 (“The Supreme Court has said that the most natural way
to view a modifying term is as applied to the entire clause when that ‘clause hangs together as a unified whole.’”
(quoting Cyan, Inc. v. Beaver Cnty. Emps. Ret. Fund, 583 U.S. 416, 440 (2018))).
interpretation”). See Seritage, 397 So. 3d at 46; see also ECB USA, 113 F.4th at 1322 (“[T]he
natural construction of the language demands that the clause be read as applicable to all.”
(emphasis added) (quoting Paroline, 572 U.S. at 447)). The series-qualifier canon applies, so the
“sole discretion” language modifies all items in the series. See, e.g., Ernie Haire Ford, 260 F.3d
at 1289 (applying the modifier “in its best judgment” to the second noun in a series); Archer, 2018
WL 2100032, at *2, *11 (applying the “sole discretion” language to the last item in a series).
Lastly, the series uses the disjunctive “or.” (Doc. 118-4 at 58.) Thus, if APTIM determined,
in its “sole discretion,” that Timberline had violated any condition in the series, then it could
terminate the Timberline Subcontract “by issuance of a written termination notice to
[Timberline].” (Id.) While this conditional sentence vested APTIM with considerable power, it is
not the Court’s prerogative to rewrite the contract “to make it more reasonable” for Timberline.
See KRG Oldsmar, 358 So. 3d at 468; Ernie Haire Ford, 260 F.3d at 1290.
B. APTIM’s Good Faith
1. Implied Covenant of Good Faith and Fair Dealing
“Under Florida law, the implied covenant of good faith and fair dealing is part of every
contract.” Archer, 2018 WL 2100032, at *8 (quoting Burger King v. Weaver, 169 F.3d 1310, 1315
(11th Cir. 1999)). This rule is “gap-filling,” “usually raised when a question is not resolved by the
terms of the contract or when one party has the power to make a discretionary decision without
defined standards.” Publix Super Mkts., 876 So. 2d at 654–55 (citing Sepe, 761 So. 2d at 1185). It
prohibits the parties to a contract from “capriciously exercis[ing] discretion accorded . . . under
[the] contract so as to thwart the contracting parties’ reasonable expectations.” Ernie Haire Ford,
260 F.3d at 1291 (citing, inter alia, Sepe, 761 So. 2d at 1185).
The implied covenant of good faith and fair dealing necessarily concerns “the performance
of a specific contractual obligation.” Ernie Haire Ford, 260 F.3d at 1291 (quoting Johnson Enters.
of Jacksonville, Inc. v. FPL, Grp., Inc., 162 F.3d 1290, 1314 (11th Cir. 1998)). Importantly,
though, it “cannot override an express contractual term.” Id. (citing Ins. Concepts & Design, Inc.
v. Heathplan Servs., Inc., 785 So. 2d 1232, 1234 (Fla. 4th DCA 2001)); accord Archer, 2018 WL
2100032, at *8. Nor can it “be used to create a breach of contract . . . where there was no breach
of any express term of the contract.” Avatar Dev. Corp., 834 So. 2d at 876. In other words, the
implied covenant “is not an abstract and independent term of a contract which may be asserted as
a source of breach when all other terms have been performed pursuant to the contract
requirements.” Id. (quoting Hosp. Corp. of Am. v. Fla. Med. Ctr., Inc., 710 So. 2d 573, 574 (Fla.
4th DCA 1998) (per curiam)).
Where a contract vests one party with the power to make a determination in its “sole
discretion,” the parties’ expectations as to that determination “should ‘reasonably’ be more
limited.” Sepe, 761 So. 2d at 1185; accord Sembler Fam. Partnership No. 41, Ltd. v. Brinker Fla.,
Inc., 660 F. Supp. 2d 1307, 1312 (M.D. Fla. 2009) (explaining that “sole discretion” is a “high
degree of discretion”). “Nevertheless, sole discretion does not permit a party to make a
discretionary decision that violates the covenant of good faith.” Id. (citing Mesler v. Holly, 318
So. 2d 530 (Fla. 2d DCA 1975)); see also id. at 1185 n.2 (collecting cases). In order to establish
that a party’s exercise of sole discretion violates the implied covenant of good faith and fair
dealing, the other party must:
demonstrate a failure or refusal to discharge contractual responsibilities, prompted
not by an honest mistake, bad judgment, or negligence[,] but rather by a conscious
and deliberate act, which unfairly frustrates the agreed upon common purpose and
disappoints the reasonable expectations of the other party thereby depriving that
party of the benefits of the agreement.
Mount Sinai Med. Ctr, 329 F. Supp. 2d at 1313 (quoting Shibata v. Lim, 133 F. Supp. 2d 1311,
1319 (M.D. Fla. 2000)). “Unless no reasonable party . . . would have made the same discretionary
decision . . . , it seems unlikely that [a party’s] decision would violate the covenant of good faith
. . . .” Ernie Haire Ford, 260 F.3d at 1291 (quoting Sepe, 761 So. 2d at 1185).
2. Analysis
Timberline bears a heavy burden. Namely, it must show that a reasonable trier of fact could
find that APTIM “capriciously exercise[d] discretion accorded it under the contract so as to thwart
the contracting parties’ reasonable expectations.” See Ernie Haire Ford, 260 F.3d at 1291. Or, put
another way, Timberline must show that a reasonable trier of fact could find that “no reasonable
party” would have terminated the Timberline Subcontract. See id. Largely, Timberline contests
APTIM’s Partial MSJ by raising related issues, including whether Timberline was actually in
default, whether APTIM gave Timberline adequate notice and a reasonable opportunity to cure,
and whether APTIM materially breached the Timberline Subcontract first. (See Doc. 134 at 7–8.
But see id. at 23–25 (straightforwardly discussing the implied covenant of good faith).) Having
carefully considered Timberline’s arguments, the Court finds that they do not move the needle.
a. Timberline’s Defective Work
Timberline raises the possibility that APTIM was responsible for some of the defective
work for which Timberline was ultimately terminated. (See Doc. 134 at 16 (citing, inter alia, Doc.
136-32 at 7–8).) But even assuming that Timberline is correct, there remains no genuine issue as
to the following: First, Timberline was hired to construct the Project’s sewer system. (See, e.g.,
Doc. 118-4 at 40.) The Project commenced on April 21, 2023. (Doc. 136-4 at 2.) It was not until
May 25, 2023, that APTIM announced that it was “mobiliz[ing]” its own resources to assist
Timberline. (Doc. 118-7 at 1–2.) And even then, APTIM had no more than one operator and one
laborer on-site from May 25 through May 30, 2023. (Doc. 118-1 at 3, ¶ 12.) Before APTIM’s
employees began working on-site—and from May 25–30—Timberline was already installing the
sewer system. (See, e.g., Doc. 118-6 at 78, 121–23, 202, 314; Doc. 118-7 at 5–6.)
In its May 29 letter to BAJV, the USACE expressed concern over “significant deficiencies”
with “the [P]roject’s underground utilities,” including the sewer system. (Doc. 118-7 at 9.) The
letter identified specific instances of defective work and attributed at least some of them to “lack
of proper equipment” and “lack of qualified personnel.” (Id.) Necessarily, it would have been
Timberline’s employees who were performing defective work on the sewer system at this time.
Second, while on site on June 1, 2023, a Lee County inspector determined that “no less
than ten sewer service laterals were incorrectly installed and required rework.” (Doc. 118-1 at 3,
¶ 13.) As well, this inspector “personally observed laterals being installed in violation of Lee
County specifications.” (Id.) Timberline has admitted that it performed this defective work. (Id. at
4, ¶ 16.) In its second corrective action plan, Timberline acknowledged that it had “misinterpreted
the plans” for these laterals, although it blamed “drawing inconsistencies.” (Doc. 118-7 at 22.)
These incorrectly installed sewer lines had to be “ripped out and replaced.” (Doc. 118-1 at 4, ¶ 15.)
Third, APTIM issued its second cure notice to Timberline on June 8, 2023. (Doc. 118-7 at
19–20.) This notice warned that “[a] single additional instance of re-work caused by Timberline’s
inability to construct accurately and in accordance with specifications and schedule w[ould] result
in immediate termination for default.” (Id. at 20 (emphasis omitted).) Subsequently, the same Lee
County inspector performed multiple pressure tests of the sewer system. (Doc. 118-10 at 12–13.)
Timberline was present for these tests. (Id. at 13.) The sewer system failed, meaning that it was
“not acceptable to Lee County.” (Id.) In its Daily Reports from June 21 through June 24, 2023,
Timberline noted that it was finding and repairing sewer leaks. (Doc. 118-7 at 54, 70, 105, 109,
157, 186.) Timberline admits that, when it was terminated, “Lee County had not accepted any of
the work performed by Timberline on the sewer lines.” (Doc. 118-1 at 8, ¶ 40 (emphasis added).)
Under the Timberline Subcontract, “the detail, manner and method of performing
Subcontract Work [was] the responsibility of, and under the supervision and control of
[Timberline] and its Subcontractors.” (Doc. 118-4 at 54.) Also under the subcontract, Timberline
warranted that the Subcontract Work would be (1) “of good quality and new, and free from defects
and deficiencies (including with respect to, but not limited to, materials, construction, design, title
and workmanship)” and (2) “performed in accordance with the specifications, requirements and
conditions of the Subcontract.” (Id. at 50 (emphasis added).) Any work which did not conform to
the above was “defective.” (Id.)
It bears repeating: Here, the question is not whether Timberline was objectively in default,
but whether APTIM breached the implied covenant of good faith and fair dealing in determining,
in its sole discretion, that Timberline had performed defective work. (See Doc. 118-4 at 58.) In
order to survive summary judgment, Timberline must do more than simply sow doubt about
whether some (or even most) of the defective work on the sewer system is attributable to APTIM.
It must show that a reasonable trier of fact could find that APTIM acted “capriciously,” or that “no
reasonable party” would have terminated the Timberline Subcontract under the circumstances. See
Ernie Haire Ford, 260 F.3d at 1291. Considering the above, Timberline has not carried its burden.
That is, regardless of the issues which Timberline raises here, no reasonable trier of fact could find
that APTIM was acting in bad faith when it terminated the subcontract.
Archer is a useful illustration of the plaintiff’s burden when opposing a motion such as this.
There, the general contractor, Archer, subcontracted Prince Land Services (“Prince”) to perform
landscaping and irrigation work on commuter rail stations in Florida. Archer, 2018 WL 2100032,
at *1. Eventually, Archer put Prince in default for “numerous alleged failures of performance.” Id.
at *2. It then made a claim on the bond which Prince’s surety, DSIC, had issued. Id. at *1–2. DSIC
sued. Id. at *4. Archer counterclaimed. Id. The parties ultimately filed cross-motions for summary
judgment. Id. The district court granted Archer’s motion for summary judgment, finding that
Archer did not breach its implied duty of good faith and fair dealing. Id. at *8, *13.
One of DSIC’s arguments in opposition to Archer’s motion was that “genuine issues of
material fact exist[ed] as to whether Prince [had] defaulted on the Subcontract.” Id. at *11. The
court rejected this argument, noting that Archer was authorized to take remedial action if it
determined, “‘at [i]ts sole discretion,’ that Prince materially breached the Subcontract.” Id. The
court pointed to documentation of Prince’s defective work, including punch lists, complaints, and
a Registered Landscape Architect Report identifying “significant flaws in Prince’s performance.”
Id. Although DSIC “filed an affidavit from Prince’s principal stating that Prince complied with its
obligations under the Subcontract,” that “there was no basis for Archer to terminate Prince,” and
even that “Archer breached the Subcontract on numerous occasions,” the court nevertheless
concluded:
In light of the numerous documented complaints regarding Prince’s work, the
punch lists documenting same, and [the] Report describing deficiencies in Prince’s
performance, the Court is satisfied that Archer’s default of Prince did not violate
its duty of good faith. That is, Archer’s conduct was not “capricious[],” nor did it
“contravene the reasonable contractual expectations of the other part[ies]. See
[Dep’t of Revenue v. Gen. Motors LLC, 104 So. 3d 1191, 1198 (Fla. 1st DCA 2012)
(quoting Cox v. CSX Intermodal, Inc., 732 So. 2d 1092, 1097–98 (Fla. 1st DCA
1999)).] That Archer acted within its “discretion” when it terminated [Prince] for
material breach of the Subcontract is not a genuine issue of material fact foreclosing
summary judgment.
Id. (emphasis added). The instant motion follows this logic: Timberline cannot rely upon tangential
issues, such as whether it was objectively in default or whether APTIM also performed defective
work. Rather, Timberline must raise a genuine issue whether APTIM acted “capriciously” in
terminating the Timberline Subcontract. See Ernie Haire Ford, 260 F.3d at 1291; accord Archer,
2018 WL 2100032, at *12.
b. Whether APTIM Breached First
Somewhat related to the above, Timberline argues that unforeseen delays “contributed to
quality issues” by forcing it to “stack[]” tasks rather than to complete them “in a linear sequence.”
(Doc. 134 at 17 & n.1 (citing Doc. 136-33 at 12–13, 16–17, 18–20; Doc. 136-28 at 1–2).) It posits
that APTIM materially breached the Timberline Subcontract first—by “failing to provide
Timberline additional time” for performance. (Id.; see also id. at 8–9 (citing 7 Bruner & O’Connor
on Construction Law § 18:39 (2024)) (explaining that “termination of a construction contract may
be upheld only if the terminating party meets its burden of proof that . . . the material breach was
not induced, preceded, or otherwise excused by the terminating party’s own supervening material
breaches . . . .”).)
It is “a fundamental principle of Florida contract law that a material breach by one party
excuses . . . performance by the other.” Hamilton v. Suntrust Mortg. Inc., 6 F. Supp. 3d 1300, 1309
(S.D. Fla. 2014) (citing Indem. Ins. Corp. of DC. v. Caylao, 130 So. 3d 783, 786 (Fla. 1st DCA
2014)). At the same time, however:
There are few principles of contract law better established, or more uniformly
acknowledged, than the rule that when a contract not fully performed on either side
is continued in spite of a known excuse, the right to rely upon the known excuse is
waived . . . .
Id. (quoting MDS (Canada) Inc. v. Rad Source Techs., Inc., 720 F.3d 833, 859 (11th Cir. 2013)
(Pryor, J., concurring in part and dissenting in part)); accord 13 Williston on Contracts § 39:31
(4th ed. 2025) (“A party to a contract may waive . . . a breach of the contract’s provisions . . . by
conduct manifesting a continued recognition of the contract’s existence after learning of the breach
or failure of the condition, such as by continuing to perform . . . .”); Dunkin’ Donuts of Am., Inc.
v. Minerva, Inc., 956 F.2d 1566, 1571–72 (11th Cir. 1992) (citing Cities Serv. Helex, Inc. v. United
States, 543 F.2d 1306, 1313 (Ct. Cl. 1976)) (considering “the effect of continued performance after
a material breach”).
The facts do not support Timberline’s argument that APTIM breached the Timberline
Subcontract by failing to give Timberline additional time to perform. On May 6, 2023, Timberline
notified APTIM of “potential delays in the schedule due to unforeseen conditions.” (Doc. 136-8 at
1.) But at that time, Timberline merely reserved its right to seek an extension for performance. (Id.
at 1–2.) It also informed APTIM that it would “diligently seek to minimize . . . the effects of these
delays on [its] work.” (Id. at 2.) Then, in its second corrective action plan—sent to APTIM on June
9, 2023—Timberline assured APTIM that it “ha[d] the resources, skilled trades, and management”
to perform “in accordance with the plans and specifications and within the contract period of
performance.” (Doc. 136-20 at 3 (emphasis added).) While Timberline pointed to “delays beyond
[its] control,” it concluded the document by again insisting that it “c[ould] complete th[e] work as
required by the plans and specifications and within the required timeline.” (Id. at 4 (emphasis
added).) Consequently, Timberline has not shown whether or how APTIM breached first.
Relatedly, Timberline has not shown that it regarded APTIM as having materially breached—or
that Timberline did not waive this excuse by continuing to perform.
c. Notice & Opportunity to Cure
Timberline posits that Section 11 of the Timberline Subcontract circumscribes APTIM’s
“sole discretion,” viz., by entitling Timberline to an opportunity to cure. (See Doc. 134 at 14–15.)
Preliminarily, the Court notes that it doubts Timberline’s interpretation.5 Section 11 provides:
5 Even if Timberline is correct that Section 11 of the Timberline Subcontract circumscribed Section 25 by entitling
Timberline to an opportunity to cure, the plain language of Section 11 also establishes that the cure period started
when Timberline “discover[ed] defective work.” (See Doc. 118-4 at 50; see also Doc. 139 at 7–8.) Crucially, Section
[Timberline] shall, within 24 hours of discovering defective work or after receiving
notice from [APTIM], proceed to take down and remove all portions of the
Subcontract Work which shall have been determined to have been defective and
shall replace same with proper and satisfactory Subcontract Work, and shall make
good all work damaged or destroyed thereby.
(Doc. 118-4 at 50.) Plainly, this section required that Timberline begin remediating defective work
within 24 hours of discovery or notice thereof. (See id.) But it does not follow that this section
qualified APTIM’s ability to terminate the Timberline Subcontract under Section 25. (See id. at 58
(“If, in [APTIM’s] sole discretion, . . . [Timberline] [wa]s refusing or failing to perform properly
any Subcontract Work . . . , [APTIM could] . . . terminate [the Timberline] Subcontract . . . by
issuance of a written termination notice to [Timberline].”); see also id. at 50 (warranting that
Timberline’s work would be “free from defects and deficiencies”).) Indeed, such an interpretation
would seem to negate the broad latitude afforded APTIM under that section. See also Pierce Law
Grp., 408 So. 3d at 151 (“Where the contract is susceptible to an interpretation that gives effect to
all of its provisions, the court should select that interpretation over an alternative interpretation
that relies on negation of some of the contractual provisions.” (quoting Siegle, 819 So. 2d at 739)).
Perhaps for this reason, Timberline primarily argues that, regardless of the terms of the
Timberline Subcontract, it had an implied right to adequate notice and a reasonable opportunity to
cure. (See Doc. 134 at 8–9 (citing 7 Bruner & O’Connor on Construction Law § 18:39 (2024)).)
Worth noting, Timberline cites virtually no caselaw in support of this position. (See, e.g., id. at 8–
10, 13–14.) But see Centerplan Constr. Co., 343 Conn. at 412–13 (citing, inter alia, Fraunhofer-
Gesellschaft zur Förderung der Angewandten Forschung E.V. v. Sirius XM Radio, Inc., 940 F.3d
11 did not specify a cure period. (See Doc. 118-4 at 50.) It merely provided that Timberline would begin remediating
defective work within 24 hours of discovery or notice thereof. (Id.) Thus, what constituted a “reasonable” opportunity
to cure would seem to have been left up to APTIM. (See id. at 58.) Timberline’s Daily Reports reflect that, at a
minimum, Timberline had four days—from June 21 through June 24, 2023—in which to cure sewer system defects.
(Doc. 118-7 at 54, 70, 105, 109, 157, 186.) Especially given the abbreviated schedule for the Project, (Doc. 136-4 at
2), Timberline has not raised a genuine issue whether APTIM breached the implied covenant of good faith and fair
dealing by failing to give Timberline a reasonable opportunity to cure.
1372, 1379 (Fed. Cir. 2019)) (“[S]ilence in a contract regarding notice and cure rights . . . supports
a presumption in favor of common-law notice and cure rights . . . .”); McClain v. Kimbrough
Constr. Co., 806 S.W.2d 194, 198 (Tenn. App. 1990) (citing United States ex rel. Cortolano &
Barone, Inc. v. Morano Constr. Corp., 724 F. Supp. 88, 98 (S.D.N.Y. 1989); Cyclo Floor Mach.
Corp. v. Nat’l Housewares, Inc., 296 F. Supp. 665, 682 (D. Utah 1968)) (“[E]ven when the parties
have not included a ‘take over’ clause in their contract, courts have imposed upon contractors the
duty to give subcontractors notice and an opportunity to cure before terminating the contract for
faulty performance.”). And conspicuously, the cases which Timberline does cite do not concern
Florida law,6 even though the parties agree that Florida law governs the Timberline Subcontract.
(See Doc. 134 at 8–10, 13–14; see also Doc. 118-2 at 7.)
But even assuming, arguendo, that Timberline was entitled to adequate notice, as well as
a reasonable opportunity to cure, there is no genuine issue that it received both. On June 8, 2023,
APTIM issued its second cure notice to Timberline. (Doc. 118-7 at 19–20.) This notice was in
writing, identified itself as a cure notice, and specified instances of Timberline’s defective work
on the sewer system, including during Lee County’s visit on June 1, 2023. (Id.) The notice also
warned that “[a] single additional instance of re-work caused by Timberline’s inability to
construct accurately and in accordance with specifications and schedule w[ould] result in
6 Timberline points to MV Lady B, LLC v. Rolly Marine Service Co. (See Doc. 134 at 9 (citing MV Lady B, 2024 WL
4881034, at *3–4).) In MV Lady B, the district court observed that “[c]ourts overwhelmingly disfavor reading implied
terms into . . . contract[s].” MV Lady B, 2024 WL 4881034, at *3 (citing Hughes v. S.W. Airlines Co., 961 F.3d 986,
989–90 (7th Cir. 2020)). It added that courts have “specifically declined to infer a right to cure default or breach.” Id.
(citing Al Owaidah v. Mazzei, No. 18-246, 2020 WL 1041091, at *12 (C.D. Cal. Jan. 27, 2020); Aurora Loan Servs.
LLC v. NGBI, Inc., No. 7-6501, 2009 WL 10670622, at *11 (C.D. Cal. Apr. 27, 2009)). Because the defendant in MV
Lady B relied on the same cases which Timberline now cites, the court concluded that, “[a]t most, the . . . cases support
the proposition that there is an implied right to cure in construction contracts.” Id. (emphasis added) (citing Gray
Constr., Inc. v. Medline Indus., Inc., No. 19-3405, 2023 WL 2333218, at *13 (D. Md. Mar. 1, 2023)). But this statement
is hardly even dictum. The court was not considering whether there is, in fact, an implied right to cure in construction
contracts. See id. at *4. Rather, it was explaining that it did not need to consider whether the cases which the defendant
had cited accurately reflected Florida law, because the cases themselves were inapposite. See id. For its part, this Court
is unaware of any Florida case implying a right to adequate notice and an opportunity to cure, particularly where the
underlying question is whether a party breached the implied covenant of good faith and fair dealing.
immediate termination for default.” (Id. at 20 (emphasis in original).) Subsequently, the sewer
system failed the multiple pressure tests performed by Lee County. (Doc. 118-10 at 12–13.)
Timberline was present for these failed pressure tests. (Id. at 13.) Additionally, Timberline noted
in its Daily Reports that it was finding and repairing sewer leaks from June 21 through June 24,
2023. (Doc. 118-7 at 54, 70, 105, 109, 157, 186.) “At the time Timberline was terminated, Lee
County had not accepted any of the work performed by Timberline on the sewer lines.” (Doc. 118-
1 at 8, ¶ 40 (emphasis added).) On June 23, 2023, APTIM informed Timberline via the
“Notification of Breach of Contract” that Timberline’s performance “ha[d] resulted in a delay
which forecast[] [late] completion of the [P]rime [C]ontract . . . and therefore [wa]s in breach.”7
(Doc. 118-7 at 190.) The June 27 “Notice of Termination for Default” likewise stated that APTIM
was terminating Timberline “for the continued performance and schedule issues addressed with
Timberline” via on-site meetings and correspondence (e.g., the June 8 cure notice). (Id. at 192.)
Given the June 8 cure notice, the Court need not consider whether other notices to
Timberline were adequate. (See Doc. 139 at 7–9 (citing Doc. 118-7 at 19–20).) The Court notes,
however, that Timberline has not provided any support for its argument that, even where notice is
merely implied, it must take a specific form. (See Doc. 134 at 13–14, 18–19 (citing Eddystone,
2015 WL 1542284, at *8 (dealing with a contract provision requiring specific written notice)).)
And other cases have held that even a contractual requirement that one party deliver notice in
writing “may be waived when ‘the consistent actions of the two parties’ lead to . . . [the]
conclusion” that the party entitled to notice “was aware of the delays and their cause” and “had
the opportunity to ascertain the facts surrounding the delays.” Parkcrest Builders, 2017 WL
7 Contrary to Timberline’s assertion, the “Notification of Breach of Contract” was not limited to “schedule and delays.”
(See Doc. 134 at 23–24.) Rather, the document explained that Timberline’s defective work had caused delays. (See
Doc. 118-7 at 190.) Other documents (e.g., the June 8 cure notice, the “Notice of Termination for Default”) also make
clear that defective work could be and was a basis for termination. (See, e.g., id. at 19–20.)
3394033, at *5 (quoting Nat Harrison Assocs., Inc. v. Gulf States Utils. Co., 491 F.2d 578, 583
(5th Cir. 1974)); see also Fort Walton Beach Lincoln-Mercury, Inc. v. Pearson, 731 So. 2d 859,
860 (Fla. 1st DCA 1999) (finding that, although the management agreement required written notice
of termination, plaintiff waived this requirement by his conduct and by failing to raise the issue of
written notice until suit was filed); id. at 860 n.2 (collecting cases).
In Parkcrest Builders, LLC v. Housing Authority of New Orleans, for example, the court
found that the defendant waived notice because it “was aware of the problems with the electrical
grid . . . and was reminded of these problems on a weekly basis during . . . progress meetings.”
2017 WL 3394033, at *5. Likewise, in the instant case, Timberline was aware of the defective
work—through complaints by the USACE, through the cure notices sent by APTIM, through
regular on-site meetings and other verbal communications, through its presence during the multiple
failed pressure tests performed by Lee County, and through its own work on the sewer system,
documented in its Daily Reports. (See, e.g., Doc. 118-2. at 16–17; see also id. at 17–18 (citing,
inter alia, Doc. 118-12 at 2–3; 118-7 at 11–15); Doc. 118-1 at 8, ¶ 41.) And after receiving the
June 8 cure notice, Timberline was aware that APTIM was considering termination for additional
re-work necessitated by defective work. (See Doc. 118-7 at 19–20.)
Timberline argues that it cured all instances of defective work identified by APTIM in the
June 8 cure notice, citing APTIM’s corporate deposition as support. (Doc. 134 at 15 (citing Doc.
136-32 at 9–18).) But APTIM’s corporate representative testified that, while Timberline’s re-work
passed visual inspection and was accepted by APTIM “[i]n that particular phase of work,” the
sewer system “ultimately require[d] testing” for defects which “[we]re not verifiable by visual
means.” (Doc. 136-32 at 15–16 (emphasis added).) For example, while Timberline’s re-work
between manholes 7 and 8 “met a visual standard,” it “was not mechanically tested[,] so it was not
accepted.” (Id. at 16–17.) The same was true of the ten sewer laterals which Timberline installed
incorrectly and which had to be re-installed. (Id. at 17–18.) APTIM’s corporate representative was
adamant that passing mechanical testing “was required prior to any of the [sewer] system being
accepted.” (Id. at 17; see also id. (“[I]t’s a function of final acceptance.”).) Thus, the fact that
Timberline’s re-work passed visual inspection does not mean that Timberline cured the defects
identified, nor does it mean that APTIM deemed all defects to have been cured.8
Even if the Court accepts Timberline’s argument that it was entitled to notice and an
opportunity to cure, it rejects Timberline’s position that the sewer leaks in late-June were new
defects for which APTIM needed to provide additional, specific notice and an opportunity to cure.
The sewer leaks were part of a continuum of defective work performed on the sewer system. (See
also Doc. 139 at 8 (regarding the June 8 cure notice as providing “two weeks for Timberline to
address the identified defects” with the sewer system); see also id. at 5 n.20 (denying that the
defects “‘discovered’ on June 24, 2023” were “isolated issues,” instead describing them as
“continued defects that Timberline consistently failed to fix”); Doc. 136-32 at 15–18 (explaining
that, while Timberline’s re-work passed visual inspection, mechanical testing “was required prior
to any of the [sewer] system being accepted”).) And Timberline was aware of these continued
defects, as evidenced by the Lee County inspector’s testimony, (Doc. 118-10 at 13), and by
Timberline’s own Daily Reports, (Doc. 118-7 at 54, 70, 105, 109, 157, 186). Given all of the above,
8 The Court has carefully reviewed the other deposition testimony cited by Timberline in support of its related
contention that it “cured or attempted to cure all quality workmanship issues promptly.” (See Doc. 134 at 15 (citing
Doc. 136-41 at 3–4; Doc. 136-39 at 5–6; Doc. 136-37 at 3–4).) Two of these deposition excerpts are unequivocal that
Timberline performed defective work and that at least some of this defective work could not be cured quickly, if at
all. (See Doc. 136-41 at 3–4; Doc. 136-39 at 5–6.) The other deposition acknowledges that Timberline made
“mistakes” while working on the sewer, although it explains that these mistakes “were caught fairly early, and so . . .
adjustments were made early on.” (Doc. 136-37 at 3–4.) None of these depositions establishes that Timberline cured
all defective work on the sewer or—more to the point—that it was deprived of a reasonable opportunity to do so.
Timberline has not raised a genuine issue whether APTIM provided adequate notice and a
reasonable opportunity to cure.
d. Whether APTIM Terminated Timberline in Bad Faith
Finally, Timberline straightforwardly argues that APTIM terminated Timberline in bad
faith—specifically, that APTIM used Timberline “as a scapegoat” in order to “place itself back in
[the] USACE’s good graces after its own poor management of the Project.” (Doc. 134 at 24–25.)
Notably, an ulterior motive for termination does not, ipso facto, establish breach of the implied
covenant of good faith and fair dealing. See, e.g., Avatar Dev. Corp., 834 So. 2d at 876 (“Avatar’s
ulterior motive for De Pani’s termination has no relevance[,] as Article 67 of the Master Contract
provided Avatar with the right to terminate De Pani at any time. Florida law required nothing more
of Avatar.” (internal citation omitted)). Again, Timberline must show that a reasonable trier of fact
could find that “no reasonable party” would have terminated the Timberline Subcontract under the
circumstances. See Ernie Haire Ford, 260 F.3d at 1291. As discussed above, it has failed to do so.
But even assuming that Timberline’s “scapegoat” argument independently raises concerns
over APTIM’s good faith, the facts are not on Timberline’s side. Timberline quotes a June 29 e-
mail from BAJV’s responsible manager to suggest that APTIM terminated Timberline in order to
redeem BAJV in the eyes of the USACE. (See Doc. 134 at 25 (quoting Doc. 136-26 at 1).) The
quote—“[W]e are about to have used up our one and only chance at redemption on this project
. . . .”—has been selectively edited. (See Doc. 136-26 at 1 (emphasis omitted).) The full sentence
reads: “I will tell everyone right now that we are about to have used up our one and only chance
at redemption on this project by not having any accountability on all these ancillary items that
apparently we ignored while our field team was engrossed in the failures of Timberline on site.”
(Id. (cleaned up).) Preceding sentences are similarly unequivocal: Timberline dropped the ball, at
least from APTIM’s perspective. (See id. (“What is the purpose of a team having a full [quality
control] group if nobody is holding our sub[contractor] accountable . . . ? Did no one ever follow
up and ask Timberline to provide proof that they were actually doing anything? . . . Or did we just
take them for [sic] their word after they did nothing to prove [that] they provided a truthful
statement on status? . . .”).)
Timberline also quotes a July 5 e-mail from BAJV’s responsible manager, this time in full.
(Doc. 134 at 25 (quoting Doc. 136-27 at 1).) But that e-mail likewise suggests that APTIM believed
that Timberline had performed defective work. (See Doc. 136-27 at 1.) Specifically, BAJV’s
responsible manager wrote:
At this point, we had our free pass to remove Timberline and make good, but that
card is now 3/4 out the window. The next to come is going to be a full deficiency
in the [quality control] on the project[,] as there are no more [subcontractors] to
pass blame on, plus in my opinion we didn’t respond strong enough, especially with
all the continued repairs that are showing up.
(Id. (emphasis added).) At most, these e-mails indicate that Timberline performed defective work
and that BAJV was itself performing poorly (i.e., under the Prime Contract). Both things can be
true, however. These e-mails do not alter the finding of APTIM’s good faith.
As discussed above, the Timberline Subcontract empowered APTIM to determine, in its
sole discretion, whether Timberline’s work was defective and, if so, to terminate the Timberline
Subcontract by written notice to Timberline. Timberline does not dispute that it performed
defective work on the sewer system, that it received a formal cure notice on June 8, 2023, and that
issues with the sewer system continued to manifest afterward. It admits that it was on site when
the Lee County inspector performed multiple pressure tests, that those pressure tests failed, and
that from June 21 through June 24, 2023, it noted in its Daily Reports that it was finding and
repairing sewer leaks. At the time Timberline was terminated, Lee County had not accepted any
of the work performed on the sewer system by Timberline.
APTIM terminated Timberline via e-mail on June 25, 2023, followed by formal notice on
June 27, 2023. That formal notice identified Timberline’s performance as a reason for termination.
Thus, Timberline has not raised a genuine issue whether it received adequate notice and a
reasonable opportunity to cure or whether APTIM properly terminated the Timberline
Subcontract. Likewise, it has not shown that a reasonable trier of fact could find that APTIM
breached the implied covenant of good faith and fair dealing—that is, that APTIM acted
capriciously—when it determined, in its sole discretion, that Timberline had performed defective
work. Because, for the above reasons, no reasonable trier of fact could find that APTIM terminated
the Timberline Subcontract in bad faith, the Court need not reach the other bases for termination
identified by APTIM (e.g., unsafe, unskilled work and the failure to procure a bond).
V. CONCLUSION
Accordingly,
IT IS ORDERED that APTIM’s Motion for Partial Summary Judgment (Doc. 118) is
GRANTED. The Court finds that (a) APTIM did not breach the implied covenant of good faith
and fair dealing and (b) APTIM properly terminated the Timberline Subcontract.
Signed in Baton Rouge, Louisiana, on February 4, 2026.
S
JUDGE JOHN W. deGRAVELLES
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF LOUISIANA