disregarding a PLA’s “boilerplate language” claiming time was of the essence where it was not
How later courts described this case
- disregarding a PLA’s “boilerplate language” claiming time was of the essence where it was not
Written by the judges who cited it.
The opinion
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Associated Builders and :
Contractors, Inc., Eastern :
Pennsylvania Chapter, :
Appellant :
:
v. :
:
Bucks County Community : No. 1172 C.D. 2025
College : Argued: November 5, 2025
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
OPINION BY
JUDGE COVEY FILED: December 5, 2025
Associated Builders and Contractors, Inc., Eastern Pennsylvania
Chapter (ABC Eastern) appeals from the Bucks County Common Pleas Court’s (trial
court) order dated September 3, 2025 (docketed September 4, 2025): (1) vacating
the trial court’s order dated August 27, 2025 (docketed August 28, 2025) that
directed Bucks County Community College (College) to not open bids for the
construction of the Center for Advanced Technologies (CAT) Building heating,
ventilation, and air conditioning (HVAC) Lab & Building Enhancement Project
(Project) pending further trial court order; (2) denying ABC Eastern’s request for
preliminary injunction; and (3) releasing ABC Eastern’s security. The issue before
this Court is whether the trial court erred by denying ABC Eastern’s request for a
preliminary injunction. After extensive review, this Court reverses.
Facts
On January 6, 2023, the College issued a Public Labor Agreement
(PLA) that required the exclusive use of union workers hired through the union
hiring hall, but permitted use of workers from any source if union workers were not
available. The PLA also defined its scope to include all construction projects
completed on College property that met or exceeded estimated construction costs of
$500,000.00 during the next five years, or until December 31, 2028. The PLA
enumerated goals such as the need to avoid costly delays of potential strikes, ensure
reliable sources of skilled and experienced labor, and expedite the construction
process.
On September 23, 2024, the United States Department of Energy
(DOE) awarded a grant to the College (Grant), which the College was using to fund
a portion of the development of the HVAC curriculum, and to hire instructors to run
the program, but that the College would not use to pay for the costs of construction.
According to the Grant’s terms and conditions, the College was required to start the
Project on July 1, 2025, and have it at least 50% completed by September 30, 2025.
On July 24, 2025, the College issued an Invitation for Bids (IFB) for the Project.
The IFB incorporated the PLA.
On August 23, 2025, five days before the bids were scheduled to open
on August 28, 2025 (as per the IFB), ABC Eastern filed a complaint in the trial court
seeking to preliminarily and permanently enjoin the College from proceeding with
bid solicitation for the Project, and a declaratory judgment that the PLA was
unlawful because it discriminated against nonunion workers and was implemented
without extraordinary circumstances, in contravention of Pennsylvania case law. On
August 25, 2025, ABC Eastern filed an emergency motion for preliminary injunction
in the trial court.
2
On August 27, 2025, the trial court held a temporary restraining order
(TRO) proceeding and, from the bench, issued a TRO of the Project’s solicitation
process until a fuller review of the matter could be conducted. That day, the trial
court scheduled an evidentiary hearing on ABC Eastern’s emergency motion for
preliminary injunction for September 2, 2025. At the hearing, ABC Eastern
presented testimony from its President and Chief Executive Officer Marissa Bankert,
and Stephen Worth, the Principal of one of its members, Worth & Company. In
response, the College presented its Chief Operating Officer Michael Harris and Vice
President of Work Force and Strategic Partnerships Tracy Timby (Timby).
On September 3, 2025, the trial court vacated the TRO and denied ABC
Eastern’s emergency motion for preliminary injunction. On September 5, 2025,
ABC Eastern sought an emergency stay in the trial court, in compliance with
Pennsylvania Rule of Appellate Procedure 1732(a), which the trial court denied by
September 9, 2025 order. On September 10, 2025, ABC Eastern filed an appeal
from the trial court’s September 3, 2025 order to this Court.1
On September 11, 2025, ABC Eastern filed an Emergency Application
for Stay in the Nature of a Preliminary Injunction Pending Appeal (Emergency
Application) in this Court, which the College opposed by September 15, 2025
Answer. Following oral argument, on September 22, 2025, this Court granted the
1
[O]n an appeal from the grant or denial of a preliminary injunction,
[this Court] do[es] not inquire into the merits of the controversy, but
only examine[s] the record to determine if there were any apparently
reasonable grounds for the action of the court below. Only if it is
plain that no grounds exist to support the decree or that the rule of
law relied upon was palpably erroneous or misapplied will [this
Court] interfere with the decision of the [trial court].
Summit Towne Ctr., Inc. v. Shoe Show of Rocky Mount, Inc., 828 A.2d 995, 1000 (Pa. 2003)
(quoting Roberts v. Bd. of Dirs. of the Sch. Dist. of the City of Scranton, 341 A.2d 475, 478 (Pa.
1975)).
3
Emergency Application, issuing a preliminary injunction of the Project’s bid
solicitation until resolution of the appeal from the trial court’s order denying the
preliminary injunction.2
Discussion
Initially, in SEIU Healthcare Pennsylvania v. Commonwealth, 104
A.3d 495 (Pa. 2014), the Pennsylvania Supreme Court declared:
The six essential prerequisites that a moving party must
demonstrate to obtain a preliminary injunction are as
follows: (1) the injunction is necessary to prevent
immediate and irreparable harm that cannot be
compensated adequately by damages; (2) greater injury
would result from refusing the injunction than from
granting it, and, concomitantly, the issuance of an
injunction will not substantially harm other interested
parties in the proceedings; (3) the preliminary injunction
will properly restore the parties to their status as it existed
immediately prior to the alleged wrongful conduct; (4) the
party seeking injunctive relief has a clear right to relief and
is likely to prevail on the merits; (5) the injunction is
reasonably suited to abate the offending activity; and[] (6)
the preliminary injunction will not adversely affect the
public interest. [See] Warehime v. Warehime, . . . 860
A.2d 41, 46-47 ([Pa.] 2004) (citing Summit Towne [Ctr.],
Inc.[ v. Shoe Show of Rocky Mount, Inc.], 828 A.2d [995,]
1001 [(Pa. 2003))].
SEIU Healthcare, 104 A.3d at 502.
[This Court] . . . examine[s] the record to determine if there
were any apparently reasonable grounds supporting the
2
On November 3, 2025, the College filed a Motion for Leave to File an Amended Brief
(Application), therein alleging that the attorney who wrote the initial brief notified the College’s
current counsel that the initial brief contained Artificial Intelligence-generated case citations and
factual representations. By November 24, 2025 Order, this Court denied the Application and
struck the initial brief. Accordingly, this Court did not consider the College’s brief herein.
4
[trial court’s] denial of the preliminary injunction. Summit
Towne [Ctr.], Inc., 828 A.2d at 1000. [This Court]
reiterate[s] that “apparently reasonable grounds” exist
to support a [trial] court’s denial of injunctive relief where
the [trial] court has properly found that any one of the
six prerequisites for a preliminary injunction is not
satisfied. Id. at 1002. Because [ABC Eastern’s] focus in
this appeal is on whether [ABC Eastern] has a clear right
to relief and is likely to prevail on the merits of the
underlying action, [this Court] address[es] that prong first.
SEIU Healthcare, 104 A.3d at 506 (bold and italic emphasis added).
Clear Right to Relief/Likely to Prevail on the Merits
“In the context of a motion for a preliminary injunction, only a
substantial legal issue need be apparent for the moving party to prevail on the clear-
right-to-relief prong.” Marcellus Shale Coal v. Dep’t of Env’t Prot., 185 A.3d 985,
995 (Pa. 2018). “This implicates a less deferential standard relative to the agency’s
interpretation of the governing statute than would be applicable to a trial court’s final
merits determination.” Id.
ABC Eastern argues that a plain reading of the PLA makes clear it is
not limited to the Project, but rather, the PLA blankets any and all on-site
construction for the College and extends through December 31, 2028. ABC Eastern
further contends that the PLA’s terms do not provide for exceptions or exclusions,
nor do they include any provisions calling for a case-by-case assessment of whether
the PLA is appropriate for a particular project. Instead, ABC Eastern asserts, the
PLA applies to all College construction projects, without discretion or consideration
of whether there are extraordinary circumstances. ABC Eastern maintains that the
PLA closes the door on nonunion contractors’ ability to employ their own labor
forces in favor of local unions with whom nonunion contractors do not have
5
relationships and whose skills they cannot accurately assess before bidding on public
works projects.
ABC Eastern emphasizes that the PLA at issue here is a blanket PLA
which the College entered into in 2023 - two years before the Project was
commenced - and which applies to virtually all construction projects at the College
through 2028; thus, the College did not, because it could not, take into consideration
any aspect of this Project or other future projects when it signed the PLA. ABC
Eastern argues, therefore, the College did not show extraordinary circumstances
permitting the use of the PLA for the Project. ABC Eastern claims that the record is
devoid of any credible evidence to demonstrate urgency, complexity or labor
shortage giving rise to extraordinary circumstances warranting the imposition of a
PLA. ABC Eastern contends that, with regard to the High Priority Occupation
(HPO) List, a theoretical shortage of HVAC labor seven years from now does not
constitute extraordinary circumstances warranting the imposition of a discriminatory
PLA. ABC Eastern further proclaims that the College offered no credible evidence,
apart from unsupported, speculative testimony, to support the trial court’s holding
that the College’s funding from the Grant was actually at risk of being pulled. In
addition, ABC Eastern asserts that the College did not present any evidence that
future, theoretical grants from the federal government would be impacted by a
preliminary injunction and removal of the PLA from the bid requirements.
The Pennsylvania Supreme Court has explained:
Bidding requirements “are for the purpose of inviting
competition, to guard against favoritism, improvidence,
extravagance, fraud and corruption in the awarding of
municipal contracts and to secure the best work or supplies
at the lowest price practicable, and are enacted for the
benefit of property holders and taxpayers, and not for the
benefit or enrichment of bidders, and should be so
construed and administered as to accomplish such purpose
fairly and reasonably with sole reference to the public
6
interest.” (Footnotes omitted.) 10 McQuillan, Municipal
Corporations § 29.29, at 266-67 (3[]d ed. 1950).
EZY Parks v. Larson, 454 A.2d 928, 932 (Pa. 1982) (quoting Yohe v. Lower Burrell,
208 A.2d 847, 850 (Pa. 1965)). “When competitive bidding is used and the
procedures followed emasculate the benefits of such bidding, judicial intervention is
proper.” Id. This Court has held: “The use of a PLA is permitted where the
contracting agency can establish extraordinary circumstances[.]” Allan Myers, L.P.
v. Dep’t of Transp., 202 A.3d 205, 215 (Pa. Cmwlth. 2019) (en banc). Extraordinary
circumstances have been held to include: (1) the need for prompt completion of the
project where used to reduce potential delays and inefficiencies, see id.; (2) where
there is a labor shortage in the area, see id.; and (3) where the complexity of the
project warrants its use. See also Associated Builders & Contractors, Inc., Keystone
Chapter v. Dep’t of Gen. Servs. (ABC Keystone II) (Pa. Cmwlth. No. 189 M.D. 2025,
filed July 1, 2025) (single-Judge Opinion) (Covey, J.), slip op. at 39 (“that the Project
is so urgent, complex, or that there are valid concerns regarding the availability of a
qualified workforce, that a PLA is necessary”).3
Here, contrary to the trial court’s conclusion, the PLA clearly favors
union contractors. The trial court focused on Article 4, Section 3 of the PLA entitled
“Non-Discrimination in Referrals,” which provides:
The local Unions represent that their hiring halls and
referral systems will be operated in a non-
discriminatory manner and in full compliance with all
applicable federal, state[,] and local laws and regulations,
which require equal employment opportunities. Referrals
shall not be affected in any way by the rules, regulations,
bylaws, constitutional provisions[,] or any other aspects or
obligations of union membership, policies[,] or
requirements and shall be subject to such other conditions
3
This unreported single-judge opinion is cited as persuasive authority pursuant to Section
414(a), (b) of this Court’s Internal Operating Procedures, 210 Pa. Code § 69.414(a), (b).
7
as are established in this Article. No employment
applicant shall be discriminated against by any referral
system or hiring hall because of the applicant’s union
membership, or lack thereof.
Reproduced Record (R.R.) at 136a (emphasis added). However, Article 4, Section
2 of the PLA entitled “Union Referral,” mandates:
Hiring Procedures. The Contractor shall have the right to
determine the required skills and competence of all
employees, the right to determine the number of
employees required and the sole responsibility for
selecting the employees to be laid-off consistent with this
[PLA] and regardless of membership or nonmembership
in the Union(s). Subject to these rights, the Contractor
shall hire employees through the referral system(s), if
any, provided in the Collective Bargaining Agreements
[(CBA)] of the appropriate Union(s) set forth in
Schedule A hereto. Any such referral system, whether by
contract or practice, must be operated in full compliance
with [f]ederal, state[,] and local laws and regulations that
require equal employment opportunities and non-
discrimination.
In the event that a local Union is unable to fill any
requests for qualified employees within a 48-hour
period after such requisition is made by the Contractor
(Saturdays, Sundays[,] and holidays excepted), the
Contractor may employ qualified applicants from any
other available source. In the event that the local Union
does not have a job referral system, the Contractor shall
give the local Union first preference to refer applicants
subject to the other provisions of this Article. The
Contractor shall notify the local Union of craft employees
hired within its jurisdiction from any source other than
referral by the Union.
Id. (emphasis added). Significantly, no CBAs were attached to the PLA.
Moreover, the IFB mandated:
PLA Requirements
All Prime Contractors and Subcontractors shall comply
with the mandatory and binding requirements of the
8
Project’s [PLA][.] Bidders are expected to familiarize
themselves with these requirements (the full text of the
PLA is attached to this document for reference). Bidders
that cannot fulfill these requirements should not submit a
bid. Each contractor selected to perform work on the
Project will be required to sign the PLA.
R.R. at 101a (bold emphasis in original; italic emphasis added). Thus,
notwithstanding that the referral system is operated in a non-discriminatory manner,
and that contractors can hire their own employees if the Union does not refer
employees within 48 hours, the fact that the contractors are forced to use the Union
referral system in the first place clearly puts the non-union contractors at a
disadvantage.
Further, and most significantly, the PLA states in no uncertain terms
that it will apply to all projects on the College’s premises where the estimated
costs are equal to or exceed $500,000.00 “commenced prior to December 31,
2028.” R.R. at 135a (PLA Art. 3 §1) (emphasis added); see also R.R. at 133a (Art.
2 §1). Moreover, it is undisputed that the study regarding the use of the PLA for the
Project was completed after the PLA was issued and before the IFB was
disseminated. Given that the PLA discriminates against nonunion contractors and
PLAs are only permitted where “extraordinary circumstances” exist to justify their
usage, Allan Myers, L.P., 202 A.3d at 215, and here the PLA was issued before the
study regarding use of the PLA for the Project was completed, ABC Eastern has
presented a “substantial legal issue,” Marcellus Shale Coal, 185 A.3d at 995, as to
whether the PLA’s use in this instance was permissible. Accordingly, ABC Eastern
satisfied the fourth prerequisite to obtain a preliminary injunction.
The Dissent maintains that the Majority and this Court’s precedents
hold that using a PLA is an exception to an otherwise strict rule effectively
precluding them. The Dissent disagrees with this holding. However, neither the
Majority nor this Court’s precedents so hold. As stated above, the Allan Myers Court
9
ruled: “The use of a PLA is permitted where the contracting agency can
establish extraordinary circumstances[.]” Allan Myers, 202 A.3d at 215
(emphasis added). Here, the College issued the PLA before the DOE awarded the
College the Grant, which was the impetus for the Project. The PLA defined its
scope to include all construction projects completed on College property that met or
exceeded estimated construction costs of $500,000.00 during the next five years, or
until December 31, 2028, see R.R. at 133a, and enumerated goals such as the need
to avoid costly delays of potential strikes, ensure reliable sources of skilled and
experienced labor, and expedite the construction process. See R.R. at 132a. Thus,
because the PLA was in place before the College conceived the Project, there is a
substantial question as to whether extraordinary circumstances truly existed to
warrant the PLA.
The lack of extraordinary circumstances in this case is especially
suspect because the urgency the College claims as the reason for supporting the need
for the PLA appears to be of its own doing. To accept that reasoning in this case
would encourage such action in the future. For example, if an entity wishes to use
exigency as a reason for using a PLA, it could delay a project until it was indeed
urgent and claim extraordinary circumstances. Because the PLA included
expediting the construction process as a reason for the PLA before the Project was
born, ABC Eastern has clearly presented a substantial legal issue as to whether
extraordinary circumstances existed to permit the College’s use of the PLA in this
instance.4
4
The Dissent counters that the College commissioned a study concerning the need for a
PLA, determined that a PLA was appropriate given the urgency of the Project, and utilized a PLA
which it found satisfactory to address the need for it. However, the trial court sustained ABC
Eastern’s objection to the study, i.e., the Keystone Report, as it was inadmissible hearsay. See
Notes of Testimony, Sept. 2, 2025, at 112-113. Further, Timby testified that the College made the
decision to include the PLA for the Project before the Keystone Report’s preparation. See id. at
10
Immediate and Irreparable Harm
The Pennsylvania Supreme Court has declared: “When the [l]egislature
declares certain conduct to be unlawful it is tantamount in law to calling it injurious
to the public. For one to continue such unlawful conduct constitutes irreparable
injury.” Pa. Pub. Util. Comm’n v. Israel, 52 A.2d 317, 321 (Pa. 1947); see also
Philips Bros. Elec. Contractors, Inc. v. Valley Forge Sewer Auth., 999 A.2d 652 (Pa.
Cmwlth. 2010).
ABC Eastern argues that the PLA in question violates the
Commonwealth’s competitive bidding laws. ABC Eastern contends that, as the trial
court noted, “a violation of competitive bidding laws would be a substantial injury.”
Trial Ct. Op. at 14. ABC Eastern emphasizes that the Pennsylvania Supreme Court
has held that “to continue . . . unlawful conduct constitutes irreparable injury[,]” and
“[s]preading unlawful conduct is irreparable injury of the most serious nature[.]”
Israel, 52 A.2d at 321.
Indeed, our Supreme Court has declared that “case law hold[s] that
where the offending conduct sought to be restrained through a preliminary injunction
violates a statutory mandate, irreparable injury will have been established.” SEIU
Healthcare, 104 A.3d at 508. Because ABC Eastern raised a substantial issue as to
whether the College’s use of the PLA violates competitive bidding laws, irreparable
115. Thus, the Dissent’s reliance on said study to substantiate extraordinary circumstances is
unsupported by the record evidence.
In addition, the Dissent states that if ABC Eastern’s burden on this prong is simply to
demonstrate that substantial legal questions exist, ABC Eastern may only have done so because
this Court began deviating from its own precedent in Allan Myers. However, as stated above, this
Court continues to follow Allan Myers, as the Majority has in the instant case. Further, the
Pennsylvania Supreme Court has instructed: “In the context of a motion for a preliminary
injunction, only a substantial legal issue need be apparent for the moving party to prevail on
the clear-right-to-relief prong.” Marcellus Shale, 185 A.3d at 995 (emphasis added). Thus, there
is no question that ABC Eastern met its burden in accordance with Marcellus Shale and Allan
Myers.
11
harm per se was established. See SEIU Healthcare; Wolk v. Sch. Dist. of Lower
Merion, 228 A.3d 595 (Pa. Cmwlth. 2020). Further, since absent a preliminary
injunction, the College intended to continue the bidding process (i.e., the College
opened bids for the Project on September 5, 2025; posted bids to PennLive on
September 11, 2025; and issued letters of intent to three contractors on September
15, 2025), ABC Eastern’s harm was immediate. Accordingly, ABC Eastern satisfied
the first prerequisite to obtain a preliminary injunction.
Greater Injury/Substantial Harm
The second preliminary injunction prerequisite requires this Court to
“examine whether [ABC Eastern] has demonstrated that ‘greater injury would result
from refusing an injunction than from granting it, and, concomitantly, that issuance
of an injunction will not substantially harm other interested parties in the
proceedings.’” SEIU Healthcare, 104 A.3d at 509 (quoting Summit Towne Ctr., Inc.,
828 A.2d at 1001).
ABC Eastern asserts that the trial court erred by holding that ABC
Eastern failed to demonstrate that greater injury would result from refusing the
injunction than by granting it, because an injunction would likely result in the Project
not meeting its Grant deadlines,5 and the HVAC Training Program would be
5
The trial court explained:
[U]nder the Grant, the Project must be complete and ready for
students by March 30, 2026, so that the first cohort of students can
start in the HVAC Training Program in April 2026. . . . [T]his
$2,000,000[.00.] Grant is the largest federal grant the College has
received . . . , and that failure to meet the Grant timetable will not
only deprive the College of these Grant funds but will also likely
impact the College’s ability to receive future federal grants.
Trial Ct. Op. at 5 (internal record citations omitted).
12
delayed.6 See Trial Ct. Op. at 12-13. ABC Eastern contends that the College
provided only speculative testimony that the Grant would be in jeopardy if an
injunction were granted. ABC Eastern further maintains that the College’s own
witnesses admitted at the preliminary injunction hearing that the IFB could be
reissued within a week, and it afforded the College a 60-day window to award the
bid. ABC Eastern claims that, pursuant to the plain language of the Grant’s terms
and conditions, the College was required to achieve 50% completion of the Project
by September 30, 2025; however, the College had not yet even begun construction.
Therefore, ABC Eastern proclaims that the College has willingly missed deadlines
set forth within the Grant, without the consequences its witnesses speculated could
occur. Thus, ABC Eastern maintains that greater injury would result in rejecting the
preliminary injunction than in granting it; and denying the preliminary injunction
would permit the College to award the contracts, thus, harming ABC Eastern’s
nonunion contractor members and Pennsylvania taxpayers.
Here, the trial court concluded:
[A]n injunction which puts the Project on hold during the
course of this litigation would likely result in the Project
not meeting its deadlines under the . . . Grant. As a result,
the College would lose a two million dollar
($2,000,000[.00]) federal grant and would risk the loss of
future federal grants. Further, the HVAC Training
Program would be delayed, with resultant harm to the
6
The trial court expounded:
The HVAC Training Program itself is also time-sensitive, beyond
the time-sensitivity of the Grant funding. . . . [T]he [HPO L]ist for
Bucks County has identified a compelling need for the new HVAC
workers that the [HVAC Training] Program will train. Indeed, the
Bucks County HPO [List] identified a significant shortage of labor
in HVAC and anticipated a need for 1,300 HVAC workers in [Bucks
C]ounty for 2032.
Trial Ct. Op. at 5 (internal record citations omitted).
13
trainees, their potential employers, and the community’s
significant need for additional trained HVAC technicians.
Trial Ct. Op. at 15. However, while the potential harm to the College may be
concerning, “[t]he argument that a violation of law can be a benefit to the public is
without merit.” Israel, 52 A.2d at 321.
Moreover, here, the harm to the College is self-inflicted. The Grant
was awarded on September 23, 2024, and according to its terms and conditions, the
College was required to start the Project on July 1, 2025, and have it at least 50%
completed by September 30, 2025. However, the College did not even solicit bids
until after the date it was to begin construction on the Project. Given this Court’s
conclusion that there is a substantial issue as to whether the PLA was permitted and,
thus, bidding laws were potentially violated, ABC Eastern has demonstrated that
greater injury would result from refusing an injunction than from granting it and that
issuance of an injunction will not substantially harm other interested parties in the
proceedings. Accordingly, ABC Eastern satisfied the second prerequisite to obtain
a preliminary injunction.7
Status Quo
To satisfy the status quo requirement, “the party must show that a
preliminary injunction will properly restore the parties to their status as it existed
immediately prior to the alleged wrongful conduct.” Summit Towne Ctr., 828 A.2d
at 1001. “Courts have defined the term ‘status quo []’ as ‘the last peaceable and
7
The Dissent would rule that the Project’s time sensitivity and the attendant risks for failing
to comply with the terms of the Grant outweigh any alleged harm to ABC Eastern. However, as
stated above, it is well-settled law that “a violation of law can[not] be a benefit to the public[.]”
Israel, 52 A.2d at 321. Because there is a substantial question as to whether the College’s use of
the PLA was permitted, this Court cannot find that any harm to the College outweighs any risk to
the public.
14
lawful uncontested status preceding the underlying controversy.’” Hatfield Twp. v.
Lexon Ins. Co., 15 A.3d 547, 555 (Pa. Cmwlth. 2011) (quoting In Re Milton Hershey
Sch. Tr., 807 A.2d 324, 333 (Pa. Cmwlth. 2002)).
ABC Eastern argues that the injunctive relief sought would maintain
the status quo. ABC Eastern contends that halting the procurement process now - at
a point when no contracts have been executed, no work has begun, and it is still
possible for the College to cancel this procurement and re-issue an RFP - if this Court
ultimately finds in ABC Eastern’s favor - would maintain the status quo while the
trial court reviews the ultimate merits of ABC Eastern’s case and prevents
irreparable injury or gross injustice.
Although the College maintains that, in defiance of the trial court’s
order, it has submitted letters of intent to several contractors regarding the Project
and will be placed further behind schedule on their construction plans if the
preliminary injunction is granted, halting the procurement process now - at a point
when no contracts have been executed, no work has begun, and it is still possible for
the College to cancel this procurement and re-issue an IFP if this Court ultimately
finds in ABC’s favor - would, at least, maintain the current status quo pending this
Court’s review of the merits of ABC Eastern’s case. Accordingly, ABC Eastern has
satisfied the third prerequisite.
Abate Offending Activity
To satisfy the abatement prerequisite, “the party must show that the
injunction it seeks is reasonably suited to abate the offending activity.” Summit
Towne Ctr., 828 A.2d at 1001.
ABC Eastern argues that the offending activity is the College’s
inclusion of a discriminatory PLA in its IFB without necessary extraordinary
circumstances warranting the same. ABC Eastern contends that granting a
15
preliminary injunction pending the trial court’s determination on the merits is
reasonably suited to ensure that contracts are not awarded under the current IFB,
which includes the discriminatory PLA.
When there is a bid protest, “if the court determines that the solicitation
or award of a contract is contrary to law, then the remedy the court shall order is
limited to canceling the solicitation or award and declaring void any resulting
contract.” Section 1711.1(j) of the Commonwealth Procurement Code, 62 Pa.C.S.
§ 1711.1(j). Given the offending activity here is the use of a PLA which violates the
Commonwealth’s competitive bidding laws, then granting a preliminary injunction
pending the trial court’s determination on the merits is reasonably suited to ensure
contracts are not awarded under the current IFB, which includes the discriminatory
PLA. Accordingly, ABC Eastern has satisfied the fifth prerequisite.
Public Interest
To satisfy the public interest prerequisite, “the party seeking an
injunction must show that a preliminary injunction will not adversely affect the
public interest.” Summit Towne Ctr., 828 A.2d at 1001.
ABC Eastern argues that the public interest would be protected if a
preliminary injunction is entered because it will restrain the College from awarding
contracts during the pendency of litigation and, in turn, protect the integrity of the
public bidding process.
The Pennsylvania Supreme Court has long held that competitive
bidding requirements “guard against favoritism, improvidence, extravagance,
fraud[,] and corruption in the awarding of . . . contracts . . . and are enacted for the
benefit of property holders and taxpayers, and not for the benefit or enrichment
of bidders[.]” Yohe, 208 A.2d at 850 (quotation marks omitted) (emphasis added).
Clearly a preliminary injunction enjoining the use of a discriminatory PLA would
16
not adversely affect the public interest. Accordingly, ABC Eastern has satisfied the
sixth and final prerequisite.
Reasonable Grounds
[This Court] conclude[s] that [ABC Eastern] satisfied the
stringent criteria for the grant of a preliminary injunction,
and can identify no reasonable ground for the denial of
interim relief. Thus, the [trial court’s] denial of the request
for injunctive relief is reversed and [this Court] issue[s] a
preliminary injunction, instructing the [College to not
open bids for the construction of the Project, until the
merits of ABC Eastern’s action have been ruled upon].
SEIU Healthcare, 104 A.3d at 509-10.
Conclusion
For all of the above reasons, the trial court’s order is reversed, and a
preliminary injunction is entered prohibiting the College from opening bids or taking
other action for the construction of the Project, until the trial court decides the merits
of ABC Eastern’s action.
________________________________
ANNE E. COVEY, Judge
17
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Associated Builders and :
Contractors, Inc., Eastern :
Pennsylvania Chapter, :
Appellant :
:
v. :
:
Bucks County Community : No. 1172 C.D. 2025
College :
ORDER
AND NOW, this 5th day of December, 2025, the Bucks County
Common Pleas Court’s (trial court) order dated September 3, 2025 (docketed
September 4, 2025) is REVERSED.
FURTHER, a PRELIMINARY INJUNCTION IS ENTERED
prohibiting Bucks County Community College from opening bids or taking further
action for the construction of the Center for Advanced Technologies Building
heating, ventilation, and air conditioning Lab & Building Enhancement Project until
the trial court rules upon the merits of Associated Builders and Contractors, Inc.,
Eastern Pennsylvania Chapter’s (ABC Eastern) action.
ABC Eastern shall deposit with the trial court’s Prothonotary $1,000.00
as security, in accordance with Rule 1531(b) of the Pennsylvania Rules of Civil
Procedure.
Jurisdiction is relinquished.
_______________________________
ANNE E. COVEY, Judge
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Associated Builders and :
Contractors, Inc., Eastern :
Pennsylvania Chapter, :
:
Appellant :
:
v. : No. 1172 C.D. 2025
: Argued: November 5, 2025
Bucks County Community :
College :
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
DISSENTING OPINION
BY JUDGE WOJCIK FILED: December 5, 2025
I do not share this Court’s ever-growing conviction that the use of a
PLA1 violates the Commonwealth’s competitive bidding requirements or that their
use is an exception to an otherwise strict rule effectively precluding them. In fact, I
believe that a faithful reading of our precedent indicates the opposite. This, in
tandem with my concern that the College will suffer greater harm from the grant of
the preliminary injunction than from its refusal, leads me to respectfully dissent from
the Majority’s well-written Opinion.
1
For ease of discussion, I will incorporate the Majority’s definitions as my own. For
example, here, a project labor agreement will be referred to as a PLA. “A PLA is an agreement
between a government authority and a collection of unions represented by a council (often a
construction trades council) which applies to parts of a construction project. The terms of PLAs
vary according to the terms negotiated in each agreement.” A. Pickett Construction, Inc. v. Luzerne
County, 738 A.2d 20, 21-22 (Pa. Cmwlth. 1999).
At the outset, I remain mindful that appellate courts may only review a
trial court order refusing a preliminary injunction for an abuse of discretion. Summit
Towne Centre, Inc. v. Shoe Show of Rocky Mount, Inc., 828 A.2d 995, 1000 (Pa.
2003). Here, we may “not inquire into the merits of the controversy, but [may] only
examine[] the record to determine ‘if there were any apparently reasonable grounds
for the action of the court below.’” SEIU Healthcare Pennsylvania v.
Commonwealth, 104 A.3d 495, 501 (Pa. 2014) (quoting Roberts v. Board of
Directors of School District of City of Scranton, 341 A.2d 475, 478 (Pa. 1975)).
“‘Apparently reasonable grounds’ exists to support a lower court’s denial of
preliminary injunctive relief where the lower court has properly found that any one
of the ‘six essential prerequisites’ for a preliminary injunction is not satisfied.” Id.
Preliminary injunctive relief is warranted when the moving party
establishes six prerequisites:
(1) the injunction is necessary to prevent immediate and
irreparable harm that cannot be compensated adequately
by damages; (2) greater injury would result from refusing
the injunction than from granting it; and, concomitantly,
the issuance of an injunction will not substantially harm
other interested parties in the proceedings; (3) the
preliminary injunction will properly restore the parties to
their status as it existed immediately prior to the alleged
wrongful conduct; (4) the party seeking injunctive relief
has a clear right to relief and is likely to prevail on the
merits; (5) the injunction is reasonably suited to abate the
offending activity; and (6) the preliminary injunction will
not adversely affect the public interest.
SEIU Healthcare, 104 A.3d at 502 (Pa. 2014).
MHW-2
Presently, I find our review of the trial court’s denial of ABC Eastern’s
request for a preliminary injunction a bit more awkward or challenging than usual.2
“A preliminary injunction is designed to preserve the subject of the controversy in
the condition in which it is when the order is made[;] it is not to subvert, but to
maintain the existing status quo until the legality of the challenged conduct can be
determined on the merits.” Greater Nanticoke Area Education Association v.
Greater Nanticoke Area School District, 938 A.2d 1177, 1183 (Pa. Cmwlth. 2007).
As Justice Wecht recounted in his dissenting opinion in Weeks v. Department of
Human Services, the law concerning preliminary injunctions has oscillated between
a more demanding showing of a movant’s clear right to relief and “a standard more
harmonious with the idea that preliminary injunction proceedings should not become
an arena to decide the underlying challenge.” 222 A.3d 722, 738 (Pa. 2019) (Wecht,
J., dissenting). Herein lies the tension with our review now: while we are
admonished to maintain the status quo and to refrain from turning this preliminary
injunction proceeding into a final merits determination, the exigency of the Project
means that this decision may very well be the dispositive ruling on the underlying
challenge.
2
As our Supreme Court has explained:
It is somewhat embarrassing to an appellate court to discuss the
reasons for or against a preliminary decree, because generally in
such an issue we are not in full possession of the case either as to
the law or testimony; hence our almost invariable rule is to affirm
the decree, or if we reverse it to give only a brief outline of our
reasons, reserving further discussion until appeal, should there be
one, from final judgment or decree in law and equity.
Hicks v. American Natural Gas Co., 57 A. 55, 55-56 (Pa. 1904).
MHW-3
With that in mind, as it concerns the clear right to relief prong, I am less
convinced of ABC Eastern’s arguments than the Majority. In A. Pickett
Construction, Inc. v. Luzerne County Convention Center Authority, 738 A.2d 20, 21-
22 (Pa. Cmwlth. 1999), a county authority adopted a PLA for the construction of a
new arena-convention center and required bidders to sign the PLA as a requirement
of the bid solicitation. The PLA also required that the awardee agree to employ a
certain number of union workers notwithstanding the awardee’s own union status.
Id. Critically, the project carried an “inflexible deadline” because of state funding
requirements and because the anchor tenant (a hockey team) required use of the
arena. Id. at 22.
A non-union contractor challenged the inclusion of the PLA, in part, on
the basis that the PLA favored union contractors and prevented non-union
contractors from bidding because the required inclusion of union workers
necessitated “drastic revisions in their working relationships . . . .” Pickett, 738 A.2d
at 25. On appeal, this Court agreed that our “competitive bidding statute precludes
public bodies from discriminating between union and non[-]union contractors in the
award of public contracts . . . .” Id. But this Court concluded that the PLA therein
did not in fact favor union contractors: “Quite simply, that it may be difficult or
distasteful for [non-union contractors] to accept the provisions of the PLA does not
mean it is anti-competitive.” Id. Importantly, we also noted that the “undisputed
critical need for timely completion of the [p]roject” conferred the discretion upon
the County authority to enter the PLA. Id. at 24.
Nine years later, in Sossong v. Shaler Area School District, 945 A.2d
788, 790 (Pa. Cmwlth. 2008), a school district sought bids for work on two separate
construction projects which required all bidders, regardless of union-affiliation, to
MHW-4
enter a PLA. An individual contractor sought a preliminary injunction, challenging
the PLA requirement on the basis that it favored union contractors and frustrated the
“lowest responsible bidder” requirement under our competitive bidding laws. Id. at
791-93. The trial court denied and this Court affirmed. In pertinent part, relying on
Pickett, we observed it was once again undisputed that the construction project
required prompt completion for student use – the PLA identified that the project had
to be completed without delay – such that the school district “did not abuse its
discretion by requiring that the lowest responsible bidder enter into the PLA.” Id. at
794.
In Glenn O. Hawbaker, Inc. v. Department of General Services (Pa.
Cmwlth., No. 405 M.D. 2009, filed December 1, 2009) (Pellegrini, J.) (single-judge
op.),3 the Department of General Services required the winning bidder for the design
and construction of a 4,100-bed prison at the State Correctional Institution at
Graterford to execute a PLA. The PLA mandated the integration of local CBAs;
required craft employees to join and be hired through union hiring halls; did not
permit contractors to hire non-union personnel; but permitted bidding from all non-
union and union contractors. The PLA also identified that the project was costly
(roughly $15 million) and complex, and that the PLA was necessary “to maintain an
expedited and uninterrupted construction schedule to ensure completion and
occupancy on or before the construction deadline.” Slip op. at 5. A true exigent
circumstance also existed: the overpopulation of the prison was becoming an
emergency situation. Id. at 29. A number of contractors sought a preliminary
injunction in this Court’s original jurisdiction under the theory that the PLA
3
“Except as provided in subsection (d) (relating to single-Judge opinions in election law
matters), a single-Judge opinion of this Court, even if reported, shall be cited only for its persuasive
value and not as binding precedent.” 210 Pa. Code §69.414(b).
MHW-5
“unlawfully discriminate[d] against non-union contractors and employees, because,
among other things, the contractors, [were] not guaranteed that they [would] be able
to use only their employees, lessening their ability to compete.” Id. at 7.
Judge Pellegrini recognized that there was very little Pennsylvania case
law on the question of whether a public body could mandate the use of only union
or non-union labor, finding a single Superior Court decision indicating that such
discrimination was illegal. Hawbaker, slip op. at 14-15 (citing Daniel B.
VanCampen Corporation v. Building and Construction Trades Council of
Philadelphia and Vicinity, 195 A.2d 134 (Pa. Super. 1963)). Still, Judge Pellegrini
expressed “great doubts that the provisions of the SCI-Graterford PLA had taken the
case ‘over the line’ and resulted in illegal discrimination.’” Id. at 15. Rather, after
surveying the PLAs at issue in Pickett and Sossong, Judge Pellegrini found many
common elements between the respective PLAs and concluded “[b]ased on the
approval of the past PLAs, especially in Sossong, I cannot say that all PLAs or this
one are illegal.” Id. at 15-17
More recently, in Allan Myers, L.P. v. Department of Transportation,
202 A.3d 205, 207-08 (Pa. Cmwlth. 2019),4 albeit on a different procedural posture,
this Court considered whether the Secretary of Transportation properly dismissed a
non-union contractor’s bid protest. The protest complained that a Department of
Transportation’s bid solicitation was anti-competitive because it required the
awardee to sign a PLA. The PLA therein stated that time was of the essence, but,
more importantly, required all union and non-union contractors to hire through the
unions that were party to the PLA, with one exception: if the contractor was a United
Steelworker (USW) contractor then it could use its USW workforce. Id. at 209.
4
See also J.D. Eckman v. Department of Transportation, 202 A.3d 832 (Pa. Cmwlth. 2019)
(Allan Myer companion case).
MHW-6
Upon review, and relying on Pickett, Sossong, and Hawbaker, we
reversed, reasoning that the pertinent PLA was discriminatory. In our view, the PLA
clearly favored USW contractors. But it also favored union contractors more
broadly. We explained that “[u]nlike contractors affiliated with the [l]ocal [u]nions
or [USW], a non[-]union contractor that bid[] on . . . [the project could not] use its
own experienced workforce.” Allan Myers, 202 A.3d at 214. By requiring bidders
to abide by the PLA, this Court determined that the Department had “effectively
precluded” non-union contractors from bidding as the non-union contractor could
not seriously put forth a bid with an “unknown workforce.” Id. at 215. Further, this
Court observed that no extraordinary circumstance warranted the PLA. Unlike
Pickett, which required prompt completion to obtain state funding and to keep its
anchor tenant, and unlike Sossong, in which the project required prompt completion
for the upcoming school year, the project at issue (a long-term road improvement
project) was not actually urgent. Id.
In my view, we must not read Allan Myers overbroadly or countenance
a change to our precedent which relegates Pickett, Sossong, and Hawbaker as
exceptions to a general rule against PLAs. See Associated Builders and Contractors,
Inc., Keystone Chapter v. Department of General Services (Pa. Cmwlth., No. 30
M.D. 2023, filed February 27, 2023) (Wojcik, J.) (single-judge op.) (ABC Keystone
I) (“The Court does not read Allan Myers so broadly as to declare that all PLAs are
impermissible, and the Court disagrees with Petitioners’ stance that Pickett, Sossong
and Hawbaker are exceptions to a general rule.”); but cf. Associated Builders and
Contractors, Inc., Keystone Chapter v. Department of General Services (Pa.
Cmwlth., No. 189 M.D. 2025, filed July 1, 2025) (Covey, J.) (single-judge op.) (ABC
Keystone II). In fact, I believe that Allan Myers suffers from a great irony: it relies
MHW-7
on Pickett, Sossong, and Hawbaker in reaching its conclusion but none of those
respective PLAs could have survived Allan Myers’ scrutiny concerning
discrimination.
For example, if we accept Allan Myers’ proposition that a non-union
contractor’s inability to use its own workforce for the completion of a public body’s
project is discriminatory under the Commonwealth’s competitive bidding
requirements, how could we have approved Pickett’s mandate of employing a certain
number of union employees? How could we have approved Sossong and
Hawbaker’s PLAs which, as here, also required the winning bidder to sign a PLA
integrating union CBAs and required the use of union hiring halls? How could we
approve any PLA given that such a stipulation is a rather common characteristic?
See Hawbaker, slip op. at 4 (quoting Associated Builders and Contractors, Inc. v.
Southern Nevada Water Authority, 979 P.2d 224, 226 (Nev. 1999) (“Under PLAs,
‘[t]he union is designated the collective bargaining representative for all employees
on the project and agrees that no labor strikes or disputes will disrupt the project.
The contractor must abide by certain union conditions, such as hiring through union
halls and complying with union wage rules.”)).5
I do not believe that engaging in an after-the-fact analysis of the
required extraordinary circumstances provides the answer or otherwise harmonizes
our case law on this point. In other words, while the trial court read Allan Myers as
tolerating a discriminatory PLA where an extraordinary circumstance justified the
discrimination, see Trial Court’s Op. at 11-12, I do not read Allan Myers as
establishing an analytical framework by which we first assess whether the PLA is
discriminatory and then assess whether extraordinary circumstances permit the PLA
5
See also 51A Corpus Juris Secundum (C.J.S.) Labor Relations §316 (May 2025) (same).
MHW-8
anyway.6 Read strictly, the Court’s discussion distinguishing Pickett and Sossong
was primarily for the purpose of rejecting PennDOT’s arguments. Allan Myers, 202
A.3d at 214. If anything, the Allan Myers Court found any discrimination or
differing bidding standards to be intolerable. See id. at 215-16 (“[W]e need not
consider whether PennDOT acted in good faith in revising the PLA . . . This is
because courts will not authorize a bid with ‘a clear potential to become a means of
favoritism, regardless of the fact that the . . . officials may have acted in good faith
in the particular case.’ PennDOT’s good faith, or lack thereof, is irrelevant because
the PLA places [USW] contractors in a favored position.”) (internal citation
omitted).
I would consequently summarize this Court’s precedent as follows.
Public bodies retain a great deal of discretion in developing specifications for bid
solicitations, requests for proposals, or the award of contracts generally.
Extraordinary circumstances, like the need for prompt completion of the project,
inter alia, routinely warrant the use of a PLA. Pickett, 738 A.2d at 24; Sossong, 945
A.2d at 791; Hawbaker, slip op. at 29. However, the proffered extraordinary
circumstance must be genuine; this Court will set aside PLAs that nominally, but
disingenuously, claim an extraordinary circumstance by way of “lip service” or
“boilerplate language.” Allan Myers, 202 A.3d at 215. Finally, while the public
body may not discriminate on the basis of union affiliation, “the mere inclusion of a
6
Even if Allan Myers may read that way at first blush, to date, the issue of whether a
discriminatory PLA is justified by extraordinary circumstances has never manifested. In other
words, where we have found that extraordinary circumstances warranted a PLA, we have found
that the PLA was not discriminatory. See Pickett, 738 A.2d at 25-26; Sossong, 945 A.2d at 788-
89 (did not violate lowest bidder requirement); Hawbaker, slip op. at 15-17. Conversely, where
the PLA was discriminatory there were also no extraordinary circumstances to warrant the
imposition of a PLA. Allan Myers, 202 A.3d at 14-15; J.D. Eckman, 202 A.3d at 832; ABC
Keystone II, slip op. at 34-36.
MHW-9
PLA does not constitute illegal discrimination.” Pickett, 738 A. 2d at 25; see also
Hawbaker, slip op. at 14-15; Allan Myers, 202 A.3d at 214. Where the PLA confers
a tangible benefit upon specific contractors, like the ability for some union
contractors to use their own workforce but no other union or non-union contractors,
Allan Myers, 202 A.3d at 214-15, the PLA will constitute discrimination. Where the
terms of the PLA are simply distasteful or difficult to accept for certain contractors,
Pickett, 738 A.2d at 25, like the required use of union hiring halls, Hawbaker, slip
op. at 15-17, the PLA will not be deemed anti-competitive or discriminatory.
As such, here, I disagree with the Majority’s conclusion “that the PLA
clearly favors union contractors.” Associated Builders and Contractors, Inc.,
Eastern Pennsylvania Chapter v. Bucks County Community College, __ A.3d __,
(Pa. Cmwlth., No. 1172 C.D. 2025, filed December 5, 2025), slip op. at 7 (ABC
Eastern). Indeed, as explained above, the use of union hiring halls is a routine
characteristic of PLAs and a characteristic we have approved in the past. Moreover,
while the PLA guarantees that hiring will occur through union hiring halls, the PLA
also requires non-discrimination in referrals, e.g., “[n]o employment applicant shall
be discriminated against by any referral system or hiring hall because of the
applicant’s union membership, or lack thereof.” Reproduced Record at 136a. Stated
differently, yes, the unions will play a significant role in the hiring process. But the
unions are bound not to discriminate on the basis of union membership, such that all
union contractors, like non-union contractors, must bid with an unknown workforce.
Thus, bidders for the Project are “‘on an equal footing’ and enjoy the same
opportunity for open and fair competition.” Allan Myers, 202 A.3d at 211 (quoting
Philadelphia Warehousing and Cold Storage v. Hallowell, 490 A.2d 955, 957 (Pa.
Cmwlth. 1985)).
MHW-10
Further, the Majority finds it significant that the PLA predates the IFB.
ABC Eastern, __ A.3d at __, slip op. at 9. I do not. Our precedent concerning PLAs
and the extraordinary circumstances that warrant them places substance over form.
Allan Myers, 202 A.3d at 215 (disregarding a PLA’s “boilerplate language” claiming
time was of the essence where it was not). In my view, if we are going to scrutinize
purported extraordinary circumstances in this manner it must cut both ways and I
would not fault a PLA on this basis where, as here, a genuine extraordinary
circumstance exists. I am therefore satisfied that the incredibly urgent need to
complete the Project within the Grant’s deadline provides the necessary
extraordinary circumstance to warrant the PLA. In any case, I observe that it is not
clear that the PLA has been used for any other construction project aside from the
instant Project, see Trial Court’s Op., 9/18/25, at 2, and that the College nevertheless
commissioned a study regarding the PLA’s use before issuing the IFB. See Trial
Court’s Exhibit 2 at 452. Thus, setting aside the pedantic debate concerning the use
of a preceding PLA, the College commissioned a study concerning the need for a
PLA,7 determined that a PLA was appropriate given the urgency of the Project, and
utilized a PLA which it found satisfactory to address the need for it.
7
The scholarly Majority rightly notes, ABC Eastern, __ A.3d at __, slip op. at 10 n.4, that
the trial court excluded the content of the report as inadmissible hearsay as in Keystone II. To the
extent I reference the same, it is only for the fact of it, i.e., I do not reference it for the substance
of the report. ABC Eastern’s own counsel, notwithstanding their objection, did the same at the
hearing. See, e.g., Trial Court’s Hearing, 9/2/25, Notes of Testimony (N.T) at 113 (ABC Eastern’s
counsel stated: “For that very narrow purpose I think the question [relating to the fact of the report
and timeline of events] would be okay. I wouldn’t object to it. Thank you, [j]udge.”); see also id.,
N.T. at 114-15. As such, I believe that the sheer fact of the report suggests the College’s inclusion
of the PLA was far more thoughtful than the Majority gives it credit for. So too, I find the
Majority’s reliance on Tracy Timby’s testimony to be misplaced and uncharitable. Although
Timby testified that the decision to use the PLA preceded the issuance of the report, Timby also
testified that this was her belief because she did not have firsthand knowledge of that portion of
(Footnote continued on next page…)
MHW-11
For all these reasons, if ABC Eastern’s burden on this prong is simply
to demonstrate that substantial legal questions exist, SEIU Healthcare, 104 A.3d at
506, ABC Eastern may only have done so because this Court began deviating from
its own precedent in Allan Myers. To put a finer point on it, this Court’s decision to
continue Allan Myers’ misreading of our precedent means that any non-union
contractor can rather easily raise a “substantial legal question” and obtain a
preliminary injunction forestalling the use of a PLA. Non-union contractors may
even do so where, as here, there is not discrimination between union and non-union
contractors and the project’s completion is sufficiently urgent to warrant one’s use.
This same misreading risks creating a chilling effect: public bodies might refrain
from entering PLAs even where the situation is truly urgent. After all, there may be
greater risk of delay in litigation, like here, than there would be in simply foregoing
the PLA. Consequently, I am greatly concerned that this decision will perpetuate
the errors that I have discussed above by disposing of the underlying challenge
concerning the use of a PLA and effectively serving as the final merits decision.
Without belaboring this final point, I also believe apparently reasonable
grounds exist to affirm the trial court’s order because the balance of harms weighs
in the College’s favor. Here, the Grant requires that the Project must be substantially
completed by February 2026 and it also requires that the first cohort of students
begin the HVAC-training program in April 2026. If further halting the bid process
means the College is unable to comply with the terms of the Grant, it may lose the
$2 million in funding and it may become ineligible for future federal funds. As I
explained in Associated Builders and Contractors, Inc., Eastern Pennsylvania
the bidding process. Id., N.T. at 115. However, as discussed infra, it is not dispositive to my
analysis: I find the urgency of the College’s situation to be plain on its face. The Majority therefore
slightly misapprehends my analysis on this point.
MHW-12
Chapter v. Bucks County Community College (Pa. Cmwlth., No. 1172 C.D. 2025,
filed October 20, 2025) (Wojcik, J.) (single-judge op.), “[t]hese concerns are made
only more dire by the now heavily litigated, politically delicate question of federal
funding in academia, a tightrope the College, like other higher education institutions,
must now walk.” Slip op. at 13. To the extent my analysis now differs from my
analysis therein, it is because our standard of review requires us to affirm when there
are “apparently reasonable grounds” for the denial of a preliminary injunction. With
the benefit of further review, I am convinced that the trial court had reasonable
grounds to find in the College’s favor because the Project’s time sensitivity and the
attendant risks for failing to comply with the terms of the Grant outweigh any alleged
harm to ABC Eastern.
Accordingly, because I would affirm the trial court’s order, I
respectfully dissent.
MICHAEL H. WOJCIK, Judge
MHW-13