Filed 10/23/25; certified for publication 11/18/25 (order attached)

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

ANTON’S SERVICES INC., D084833

Appellant,

v. (Super. Ct. No. 37-2023-

00021117-CU-WM-CTL)

KATRINA S. HAGEN, as Director, etc.

et al.,

Respondents;

DIVISION OF LABOR STANDARDS

ENFORCEMENT,

Real Party in Interest and

Respondent.

APPEAL from a judgment of the Superior Court of San Diego County,

Wendy M. Behan, Judge. Affirmed.

Silver Law Firm and Zvi Silver for Appellant.

No appearance for Respondents.

Lance A. Grucela for Real Party in Interest and Respondent.

Plaintiff and appellant Anton’s Services Inc. allegedly violated state

labor statutes and regulations applicable to public works by misclassifying

and underpaying workers and failing to comply with apprenticeship

requirements. Real party in interest and respondent Division of Labor

Standards Enforcement (DLSE) cited Anton’s for those violations and

assessed penalties. Anton’s administrative appeal was unsuccessful, and it

thereafter filed a petition for writ of administrative mandamus under Code of

Civil Procedure section 1094.5, which the superior court denied.

On appeal, Anton’s contends the superior court erroneously upheld

administrative findings that: (1) Anton’s misclassified workers on two public

works projects; (2) Anton’s is liable for penalties for failing to pay these

workers the prevailing wage; (3) Anton’s is liable for liquidated damages;

(4) Anton’s failed to comply with apprenticeship requirements; and

(5) Anton’s is liable for penalties for failing to comply with apprenticeship

requirements. Finding no error, we affirm.

BACKGROUND

A. Prevailing Wage Law

Under the Prevailing Wage Law, Labor Code1 sections 1720 through

1861, workers employed under a public works contract must generally be

paid “prevailing wages.” (§ 1771.) The prevailing wage is set by the Director

of Industrial Relations (Director) and depends on worker classification and

location. (See §§ 1770, 1773, 1773.9.) The Director also creates worker

classifications, determining the scope of work for each. (See § 1773.5, subd.

(a); Cal. Code Regs., tit. 8, § 16303, subd. (a).) Contractors on public works

projects must pay workers the prevailing wage under the proper job

classification. (See § 1774.)

1 Undesignated statutory references are to the Labor Code.

2

In addition, before commencing work on a contract for public works,

every contractor must submit contract award information to an applicable

apprenticeship program that can supply apprentices to the project. (§ 1777.5,

subd. (e).) Unless an exemption applies, contractors must employ apprentices

to perform one hour of work for every five hours of work performed by

journeypersons in the applicable craft or trade. (§ 1777.5, subd. (i); Cal. Code

Regs., tit. 8, § 230.1, subd. (a).) If a contractor is “not already employing

sufficient registered apprentices” to meet this requirement, it “must request

the dispatch of required apprentices from” appropriate apprenticeship

committees “by giving the committee written notice of at least 72 hours

(excluding Saturdays, Sundays and holidays) before the date on which one or

more apprentices are required.” (Cal. Code Regs., tit. 8, § 230.1, subd. (a).)

There is thus both an initial notice requirement and a subsequent

requirement that contractors request dispatch of apprentices if unable to

meet the required ratio.

The DLSE is charged with enforcing these prevailing wage and

apprenticeship requirements. (Lab. Code, § 1741.) The DLSE issues civil

wage and penalty assessments for violations of the Prevailing Wage Law.

(Ibid.) A party may challenge a civil wage and penalty assessment in a

hearing before the Director. (Lab. Code, § 1742.) A party can, in turn, seek

judicial review of the Director’s decision under Code of Civil Procedure

section 1094.5.

B. Factual Background

1. The Torrey Pines Road Project

In 2017, the City of San Diego (City) awarded Hazard Construction

Company (Hazard) a contract for road improvement and slope restoration

along Torrey Pines Road (the Torrey Pines Road Project). The contract

3

specified that California prevailing wage rates applied to the project. The

scope of work under the contract included: excavation of the slope to achieve

the required space for a sidewalk; removal of sloughing soil and debris from

the slope face; installation of permanent soil-nails wall; installation of new

sidewalk, retaining curb, and walls; installation of a pedestrian crossing with

street lighting and crosswalk systems; asphalt concrete overlay with striping

of buffered bike lanes; and installation of a flush stamped and painted

asphalt median.

Hazard contracted with Anton’s as a “Clearing/Demolition Constructor”

on the Torrey Pines Road Project. According to inspection reports, Anton’s

work included “clearing and grubbing” the slope. Generally, “[c]learing and

grubbing consists of methodically ‘scarifying’ or tilling the soil on a

construction site to remove vegetation, roots, and other undesirable

material.” (Moorefield Construction, Inc. v. Intervest-Mortgage Investment

Co. (2014) 230 Cal.App.4th 146, 150.) Anton’s brief indicates that its work

was consistent with this definition. Anton’s claims the clearing included

removal of a small palm tree, which it contends “was in a public utility

easement.”2

As the work continued, concerns arose that a Torrey pine tree might

fall if the slope became unstable. After consulting with the City, Anton’s

stabilized the tree with cables and belts and trimmed it back before

proceeding with additional clearing and grubbing.

Following an investigation, the DLSE issued a civil wage and penalty

assessment, concluding that Anton’s had failed to properly classify workers,

failed to pay prevailing wages, and had committed apprenticeship violations.

2 As discussed below, Anton’s improperly relies on documents not

submitted in the administrative proceedings.

4

From the start of its work at the Torrey Pines Road Project, Anton’s paid

workers the rates for “Tree Maintenance.” The scope of work for the “Tree

Maintenance (Laborer)” classification includes:

“2. tree maintenance, including trimming, pruning,

topping, tree/stump removal, grinding of stumps, root

pruning and root barrier installation; handling, piling,

hauling and chipping of brush and limbs; removal and

replacement of trees; The operation of all vehicles, tools and

equipment including but not limited to hand tools of any

type, chainsaws, pole saws, pruners, stump grinders for

trees, boom trucks, loaders and trucks for personnel,

material and equipment, debris removal and towing.

“3. This [classification] does not cover (a) any work of

any employee performing construction or landscape

construction work (including work incidental to

construction or post-construction maintenance during the

plant installation and establishment period) and (b) tree

trimmer utility line clearance work within the scope of

work in any pre-existing prevailing wage determinations

for Tree Trimmer (High Voltage Line Clearance) and Tree

Trimmer (Line Clearance), issued by the Director of

Industrial Relations.”

The DLSE determined Anton’s should have paid its workers the prevailing

wage under the “Laborer (Engineering Construction)” classification, a broad

category that includes:

“(2) Street and highway work, grading and paving,

excavation of earth and rock, including non-destructive

utility line location (hydrovac operations), grade

separations, elevated highways, viaducts, bridges,

abutments, retaining walls, subways, airport grading,

surfacing and drainage, electric transmission line and

conduit projects, underground communication and conduit

installation, fiberoptic installation, blowing, splicing,

testing and related work for telephone, T.V. or other

communication transmission through underground conduit,

water supply, water, development, reclamation, irrigation,

5

draining and flood control projects, water mains, pipe lines,

sanitation and sewer projects, dams, aqueducts, canals,

reservoirs, intakes, channels, levees, dikes, revetments,

quarrying of breakwater or riprap stone, foundations, pile

driving, piers, locks, river and harbor projects,

breakwaters, jetties, dredging, tunnels. [¶] . . . [¶]

“(11) All work in connection with excavation for incidental

building and other construction including digging of

trenches, piers, foundations and holes; digging, lagging,

sheeting, cribbing and bracing of foundations, holes,

caissons, cofferdams, manning, setting and moving all

manually movable pumps. [¶] . . . [¶]

“(14) All work in the excavation, grading, preparation,

concreting, asphalt and mastic paving, paving, ramming,

curbing, flagging, traffic control by any method, and laying

of other stone materials, . . . and bridges. [¶] . . . [¶]

“(16) All work in connection with the cutting of streets and

ways for all purposes, including aligning by any method,

digging of trenches, manholes, etc., handling and conveying

of all materials for same; concrete of same; and the

backfilling, grading and resurfacing of same.”

Based on the misclassification of workers, the DLSE determined that Anton’s

owed additional wages and apprenticeship training fees.

The DLSE also found that Anton’s failed to submit contract award

information to applicable apprenticeship committees before starting work,

failed to request dispatch of apprentices from the applicable apprenticeship

committees, and did not employ apprentices in the required ratio. The Civil

Wage and Penalty Assessment for the Torrey Pines Road Project, which

totaled $36,626.30, included $22,526.30 in unpaid prevailing wages, $12,720

in penalties under section 1775 for failing to pay prevailing wages, and

$1,380.00 in penalties under section 1777.7 for apprenticeship violations. As

required by section 1727, subdivision (b), after the Civil Wage and Penalty

6

Assessment was issued, Hazard withheld $36,626.30 from Anton’s and

transmitted those funds to the City.

2. The Voltaire Street Project

Also in 2017, the City awarded Hazard a public works contract to

renovate an overpass on Voltaire Street in San Diego County (the Voltaire

Street Project). The scope of work included: removing and replacing existing

barrier rails and sidewalks; removing the existing raised median; repairing

the concrete bridge deck; reducing the number of through-lanes; removing

and replacing street lights; installing accessible curb ramps; and modifying

storm drain inlets on and immediately adjacent to the overpass. Hazard

contracted with Anton’s for “[r]emoval of bridge sidewalk, railing, and edge

concrete.” Anton’s performed work on the Voltaire Street Project between

February 1, 2018, and September 28, 2018. Anton’s claims that its work on

the Voltaire Street Project also included tree removal.

Following an investigation, the DLSE issued a Civil Wage and Penalty

Assessment for the Voltaire Street Project. As on the Torrey Pines Road

Project, DLSE found Anton’s had classified workers under “Tree

Maintenance” instead of “Laborer,” thus underpaying workers and failing to

pay appropriate apprenticeship fees. This Civil Wage and Penalty

Assessment totaled $10,653.88, including $1,653.88 in unpaid prevailing

wages and $9,000 in penalties under section 1775 for failing to pay prevailing

wages.

C. Administrative Proceedings

Anton’s challenged both Civil Wage and Penalty Assessments under

section 1742. The parties agreed to submit the matters to the Director for

decision on stipulated facts and documentary evidence. After considering the

7

parties’ submissions, the Director issued a decision affirming the

Assessments.

The Director first found that Anton’s had misclassified workers on both

projects. The Director found “the nature of work” for each project was

“construction work,” and noted that “the applicable scope of work for the Tree

Maintenance classification . . . specifically excluded coverage of construction

or landscape construction work, including work incidental to construction.”

The Director rejected Anton’s argument that the tree work on the

Torrey Pines Road Project was not incidental to construction “because it was

the subject of a [change order] that expanded the contract to include

additional work on the tree.” Rather, the Director found “the additional work

on the Torrey [p]ine tree was part of the construction project, because the

tree had to be trimmed before clearing work could continue on the soil nail

wall.”

Although Anton’s argued “that it ‘received no compensation for [its]

work [on the Voltaire Street Project] because the City determined this was

outside the original contract scope of work,’ ” the Director noted Anton’s had

not cited any “evidence to support this claim.” Similarly, although Anton’s

argued it could have properly classified its workers as “Tree Trimmer (High

Voltage Line Clearance)” at a lower rate of pay due to the presence of

utilities, the Director found “[n]either scope of work for either [p]roject

contains any reference to line clearance for communications lines or electric

power lines, nor is there evidence that Anton’s workers performed such line

clearance work.”

Next, the Director addressed the $120 per-day penalties imposed

under section 1775, subdivision (a). After noting it was Anton’s burden to

establish the penalty constituted an abuse of discretion (Cal. Code Regs.,

8

tit. 8, § 17250, subd. (c)), the Director concluded Anton had not provided any

“compelling or probative evidence establishing that the workers had not been

misclassified or underpaid,” and had not produced “evidence that [it] made

a good faith mistake, or that it promptly and voluntarily corrected its

misclassification error and the consequent failure to pay the correct

prevailing wage when these issues were brought to its attention.” In fact,

the Director found “Anton’s lacks any reasonable defense to worker

misclassification, which supports a finding that the violations were willful.”

The Director also found Anton’s liable for liquidated damages under

section 1742.1, subdivision (a), which provides that “[a]fter 60 days following

the service of a civil wage and penalty assessment,” a party “shall be liable

for liquidated damages in an amount equal to the wages, or portion thereof,

that still remain unpaid.” Section 1742.1, subdivision (b) provides, “there

shall be no liability for liquidated damages if the full amount of the

assessment or notice, including penalties, has been deposited with the

Department of Industrial Relations, within 60 days following service of the

assessment or notice, for the department to hold in escrow pending

administrative and judicial review.” The Director found Anton’s had neither

paid back wages nor deposited the full amount of either assessment with the

Department of Industrial Relations (Department), and thus was liable for

liquidated damages.

The Director upheld the DLSE’s finding that Anton’s failed to comply

with the apprenticeship requirements of section 1777.5 on the Torrey Pines

Road Project. The Director found, under section 1777.5, subdivision (e),

Anton’s was “required to submit contract award information to the [San

Diego Chapter of the Associated General Contractors of America Joint

Apprenticeship Committee (Apprenticeship Committee)] prior to the

9

commencement of work on the Torrey Pines Road Project.” Anton’s conceded

it did not submit contract award information to the Apprenticeship

Committee before starting work. The Director also found Anton’s had

violated section 1777.5 and related regulations by failing to request or employ

an adequate number of apprentices. (See § 1777.5, subd. (i); Cal. Code Regs.,

tit. 8, § 230.1, subd. (a).)

Finally, the Director upheld the DLSE’s imposition of penalties

under section 1777.7, subdivision (a)(1), which requires penalties if a

contractor “knowingly violate[s] Section 1777.5.” The Director found Anton’s

“ ‘knowingly violated’ the requirement of a 1:5 ratio of apprentice hours to

journeyperson hours because it employed insufficient Laborer apprentices,”

applying an “irrebuttable presumption that Anton’s knew or should have

known of the apprenticeship requirements of section 1777.5 applies because

Anton’s was issued prior assessments for apprenticeship violations and

because the contract for the Torrey Pines Road Project notified Anton’s of its

obligation to comply with prevailing wage requirements.” (See Cal. Code

Regs., tit. 8, § 231, subd. (h).)

D. Mandate Proceedings

Anton’s filed a petition for writ of mandate under Code of Civil

Procedure section 1094.5, seeking judicial review of the Director’s decision.

The trial court rejected Anton’s efforts to rely on extra-record evidence in

support of its petition. Applying the substantial evidence standard, the court

found that the administrative record and applicable law supported the

Director’s decision.

10

DISCUSSION

A. Standard and Scope of Review

Code of Civil Procedure section 1094.5 governs review of a decision by

the Director concerning a Civil Wage and Penalty Assessment. (See, e.g.,

Reliable Tree Experts v. Baker (2011) 200 Cal.App.4th 785, 790.) Where, as

here, the trial court has reviewed the Director’s decision under the

substantial evidence standard, this court also reviews the administrative

record as a whole for substantial evidence. (See Code Civ. Proc., § 1094.5,

subd. (c); Lab. Code, § 1742, subd. (c).) Under this standard, we do not

reweigh the evidence, and we resolve any conflicts in the evidence and

reasonable doubts about the decision in the Director’s favor. (See City of

Hesperia v. Lake Arrowhead Community Services Dist. (2019) 37 Cal.App.5th

734, 761.) The appellant has the burden of establishing that the Director’s

findings are not supported by substantial evidence in the administrative

record. (See Schutte & Koerting, Inc. v. Regional Water Quality Control Bd.

(2007) 158 Cal.App.4th 1373, 1384.)

Several of Anton’s arguments rely on documents outside the

administrative record. Evidence outside the administrative record is

generally not admissible in proceedings filed under Code of Civil Procedure

section 1094.5. (See, e.g., Western States Petroleum Assn. v. Superior Court

(1995) 9 Cal.4th 559, 578; Nightlife Partners v. City of Beverly Hills (2003)

108 Cal.App.4th 81, 89).) DLSE objected to Anton’s notice of lodgment of

extra-record material in the trial court. It appears Anton’s did not seek to

justify its reliance on this material and did not respond to the DLSE’s

objection. In its order, the trial court rejected Anton’s attempts to rely on

extra-record material.

11

Anton’s does not challenge the trial court’s exclusion of this evidence

and does not explain why this court should consider evidence not contained in

the administrative record. Anton’s has forfeited such arguments. (See, e.g.,

Asaro v. Maniscalco (2024) 103 Cal.App.5th 717, 728, fn. 4 (Asaro) [a party

forfeits arguments not briefed on appeal].) We thus limit our review to the

administrative record and will not consider arguments that rely on extra-

record evidence.

B. Misclassification

1. Torrey Pines Road Project Classification

Anton’s principally argues it properly classified workers on the Torrey

Pines Road Project because they performed work on a Torrey pine tree.

However, Anton’s does not dispute that the Torrey Pines Road Project was a

construction project. Anton’s was designated as a “Clearing/Demolition

Constructor.” (Italics added.) Anton’s actual work performed principally

consisted of “clearing and grubbing,” which is the removal of vegetation. As

Anton’s concedes, this work was necessary preparatory work for the slope

stabilization, and thus incidental to construction work. Anton’s work

stabilizing and trimming the Torrey pine tree was also incidental to the

broader construction project, as the tree only needed to be stabilized so the

slope work could proceed. The Tree Maintenance classification expressly

“does not cover . . . any work of any employee performing construction or

landscape construction work (including work incidental to construction or

post-construction maintenance during the plant installation and

establishment period).”

Anton’s argues, in several different ways, that its work on the Torrey

pine tree should be considered separate from, and not incidental to the

12

broader Torrey Pines Road Project. Anton’s cites no authority in support of

its various arguments. Nor do we find them persuasive.

Anton’s argues: (1) it holds an arborist license, was acting as an

arborist when working on the tree, and invoiced the services as “Arborist

Services”; (2) other work stopped while waiting for the tree to be stabilized;

and (3) the trunk of the tree was outside of the project area.3 None of

these factors undermine the conclusion that the work was “incidental” to

construction. (See, e.g., Cleveland National Forest Foundation v. County of

San Diego (2019) 37 Cal.App.5th 1021, 1051 [meaning of “incidental” may

“include the concept of an association or dependency on the primary use”];

Black’s Law Dictionary (12th ed. 2024) p. 908, col. 1 [“incidental” defined as

“Subordinate to something of greater importance; having a minor role”].)

Anton’s also claims the tree work was not part of the original scope of

work for the project. But the additional tree work only became necessary to

further the broader construction project, so remains incidental to that work.

Relatedly, Anton’s argues that because the work was performed pursuant to

a change order, it could have simply passed along costs to the City and made

additional profit, as it was entitled to five percent profit on the amount of

the change order. Whether or not this is true does not affect our analysis.

Regardless of motives, substantial evidence supports the finding that Anton’s

failed to properly classify its workers and thus underpaid them.

Separate from the Torrey pine work, Anton’s argues that its clearing

and grubbing involved removal of a “small palm tree” that should qualify as

Tree Maintenance work. This assertion and much of Anton’s related

3 Anton’s single record citation does not support its assertion that the

trunk of the tree was outside of the project area.

13

arguments rely on evidence outside of the record, which we will not

consider.4

2. Voltaire Street Project Classification

Anton’s also fails to demonstrate that the Director erred by finding

Anton’s misclassified workers on the Voltaire Street Project. The Voltaire

Street Project involved renovating an overpass, and Anton’s was contracted

to “[r]emov[e] [a] bridge sidewalk, railing, and edge concrete.” Anton’s fails to

cite any evidence in the administrative record supporting its claim that its

work on this project involved any tree maintenance or removal at all. Anton’s

provides no basis to assess the nature of the alleged tree-related work and

thus no grounds to conclude that the Director erred.

Relatedly, Anton’s has failed to support and thus forfeited other

arguments concerning the Voltaire Street Project, including that the work

“was outside the geographical area of the” Voltaire Street Project area and

thus, it was not subject to public works laws.5 Many of the statements

4 Anton’s also argues, in the “Summary of the Significant Facts”

section of its opening brief, that it erroneously claimed to have worked on the

Torrey Pines Road Project on April 16, 2018, in its certified payroll reports.

“ ‘Failure to provide proper headings forfeits issues that may be discussed in

the brief but are not clearly identified by a heading.’ ” (Bitner v. Department

of Corrections & Rehabilitation (2023) 87 Cal.App.5th 1048, 1065.) In any

case, Anton’s stipulated in the administrative proceedings that its “certified

payroll reports [citation] accurately reflect the hours worked by, and amounts

Anton’s paid to, its employees on both projects.”

5 We note that Anton’s did not make this argument in proceedings before

the Director, and in fact stipulated that the “work subject to the Assessments

was performed on public works and required the employment of apprentices

and the payment of prevailing wages under the California Prevailing Wage

Law . . . .”

14

Anton’s makes regarding the Voltaire Street Project in the “Summary of the

Significant Facts” section of its opening brief are not supported by any record

citations in violation of California Rules of Court, rule 8.204, subdivision

(a)(1)(C). (Ibid. [an appellate brief must “[s]upport any reference to a matter

in the record by a citation to the volume and page number of the record where

the matter appears”].) “We are not required to search the record to ascertain

whether it contains support for [Anton’s] contentions.” (Mansell v. Board of

Administration (1994) 30 Cal.App.4th 539, 545.) With one immaterial

exception,6 the limited evidence Anton’s cites in this portion of the brief is

outside of the administrative record, and (as discussed above) not cognizable

in these proceedings. In light of these deficiencies, we decline to further

address the merits of Anton’s arguments regarding the Voltaire Street

Project misclassification.

C. Penalties under Section 1775

Under section 1775, subdivision (a)(1), a subcontractor “shall . . . forfeit

not more than two hundred dollars ($200) for each calendar day . . . for each

worker paid less than the prevailing wage.”

“(A) The amount of the penalty shall be determined by the

Labor Commissioner based on consideration of both of the

following:

“(i) Whether the failure of the contractor or subcontractor

to pay the correct rate of per diem wages was a good faith

mistake and, if so, the error was promptly and voluntarily

corrected when brought to the attention of the contractor or

subcontractor.

6 Anton’s cites to the administrative record for the proposition that it

“started demolition work on the Voltaire Project on February 21, 2018.”

15

“(ii) Whether the contractor or subcontractor has a prior

record of failing to meet its prevailing wage obligations.”

(§ 1775, subd. (a)(2)(A).)

“[I]n reviewing the penalty imposed by an administrative body, . . . an

appellate court is [not] free to substitute its own discretion as to the matter.”

(Nightingale v. State Personnel Board (1972) 7 Cal.3d 507, 515.)

Anton’s suggests it should not be liable for penalties because it acted in

a good-faith belief that it was properly classifying its workers, citing its legal

arguments in this appeal as support. As we have discussed, Anton’s

arguments in this appeal are unsupported by either appropriate factual

citations, relevant legal authority, or both. We cannot agree that the

arguments presented demonstrate that the misclassification was a good-faith

mistake.

Anton’s also argues its good faith is evidenced by the fact that its

classification of workers was against its own interests, suggesting that it

would not have intentionally underpaid workers because it could have passed

along higher costs to the City and increased its own profit margin. Anton’s

adds that it properly classified and paid workers on portions of each project.

Anton’s ignores the countervailing evidence that bears directly on the

statutorily mandated considerations: Anton’s failure to “promptly and

voluntarily correct[]” its underpayment in connection with these projects and

a prior record of prevailing wage violations and penalties under section 1775.

In sum, Anton’s fails to show that the Director’s decision is not supported by

substantial evidence.

16

D. Liquidated Damages on the Torrey Pines Road Project

Anton’s argues the Director improperly imposed liquidated damages

under section 1742.1, which provides:

“(a) After 60 days following the service of a civil wage

and penalty assessment under Section 1741 or a notice of

withholding under subdivision (a) of Section 1771.6, the

affected contractor, subcontractor, and surety on a bond or

bonds issued to secure the payment of wages covered by

the assessment or notice shall be liable for liquidated

damages in an amount equal to the wages, or portion

thereof, that still remain unpaid. If the assessment or

notice subsequently is overturned or modified after

administrative or judicial review, liquidated damages

shall be payable only on the wages found to be due and

unpaid. Any liquidated damages shall be distributed to

the employee along with the unpaid wages. . . .

“(b) Notwithstanding subdivision (a), there shall be no

liability for liquidated damages if the full amount of the

assessment or notice, including penalties, has been

deposited with the Department of Industrial Relations,

within 60 days following service of the assessment or

notice, for the department to hold in escrow pending

administrative and judicial review. . . .”

It claims that, because Hazard withheld $36,626.30 from Anton’s and

transmitted those funds to the City under section 1727, subdivision (b), no

“wages . . . remain[ed] unpaid” for purposes of section 1742.1, subdivision (a).

Anton’s claims that “if the amount of the assessment is paid by anyone to any

proper governmental body,” a party cannot be liable for liquidated damages.

We do not agree.

Statutory interpretation is “a question of law that we review de novo.”

(Bruns v. E–Commerce Exchange, Inc. (2011) 51 Cal.4th 717, 724.) “Our

fundamental task in interpreting a statute is to determine the Legislature’s

intent so as to effectuate the law’s purpose. We first examine the statutory

17

language, giving it a plain and commonsense meaning. We do not examine

that language in isolation, but in the context of the statutory framework as a

whole in order to determine its scope and purpose and to harmonize the

various parts of the enactment.” (Coalition of Concerned Communities, Inc. v.

City of Los Angeles (2004) 34 Cal.4th 733, 737.) “If the language is clear, [we]

must generally follow its plain meaning unless a literal interpretation would

result in absurd consequences the Legislature did not intend.” (Ibid.)7

Under a plain and commonsense meaning, withholding money due

under a contract is not the payment of “wages.” While Anton’s correctly notes

that section 1742.1, subdivision (a), does not explicitly direct the payment of

“wages” to any particular party, a “wage” is “[p]ayment for labor or services.”

(E.g., Black’s Law Dict. (12th ed. 2024) p. 1898, col. 1.) The phrase “wages

that still remain unpaid” makes clear that the money must be paid to the

workers who should have already received it.

This provision is not satisfied by the contractor withholding funds

from the responsible subcontractor under section 1727, subdivision (b),

which provides: “If the awarding body has not retained sufficient money

under the contract to satisfy a civil wage and penalty assessment based on a

subcontractor’s violations, the contractor shall, upon the request of the Labor

Commissioner, withhold sufficient money due the subcontractor under the

contract to satisfy the assessment and transfer the money to the awarding

body. These amounts shall not be disbursed by the awarding body until

receipt of a final order that is no longer subject to judicial review.” The funds

withheld from the subcontractor are not “paid” to anyone until after final

7 The DLSE seeks judicial notice of certain aspects of the legislative

history of section 1742.1. Finding the language clear, we need not rely on

these materials. The request is therefore denied.

18

review. Thus, they remain “unpaid.” Nothing in the language of section

1742.1 suggests that a subcontractor’s liability for liquidated damages can be

avoided by the contractor’s withholding of funds under section 1727,

subdivision (b). Section 1742.1 contains no reference to section 1727 and by

its terms specifies only one way to avoid liability for liquidated damages

other than paying the workers: depositing the full amount of the assessment

or notice, including penalties, with the Department.

Anton’s nonetheless claims its position is supported by the clause

specifying: “If the assessment or notice subsequently is overturned or

modified after administrative or judicial review, liquidated damages shall be

payable only on the wages found to be due and unpaid.” (§ 1742.1, subd. (a).)

Anton’s argues, “The unpaid wages that was [sic] overturned by the Court

were certainly not ‘paid to the workers,’ yet, there is no imposition of

liquidate[d] damages for the overturned amount. This demonstrates that

there is no requirement that the money be actually paid to the workers.”

The language quoted by Anton’s merely clarifies that liquidated damages

may only be assessed on the wages found to be unpaid upon review. That is

in no way inconsistent with the understanding that “wages” remain “unpaid”

until they are actually paid to the workers who earned them.

We appreciate that automatically withholding money from a

subcontractor under section 1727 would seem to make it harder for that

party to satisfy section 1742.1, subdivision (a), by paying workers.8 It

may similarly make it more difficult for that party to insulate itself from

liquidated damages by making a deposit in accordance with section 1742.1,

8 There is no evidence that these are the circumstances in this case, as

Anton’s asserts that it gave money to Hazard to satisfy the withholding

under section 1727.

19

subdivision (b). But these are policy concerns for the Legislature to weigh,

not this court when faced with the application of clear statutory language.

(See, e.g., Standon Co. v. Superior Court (1990) 225 Cal.App.3d 898, 904

[“Unless the plain language of a statute leads to absurdity, a court may not

so construe it as to substitute its wisdom for that of the legislature.”].) We

are not at liberty to rewrite the plain language of section 1742.1 by creating a

new exception to its liquidated damages provision for cases in which the

contractor has withheld funds under section 1727. “Where, as here, the

Legislature has not created an exception, a court may not insert one into the

statute.” (Mamer v. Weingarten (2025) 108 Cal.App.5th 169, 174.)

Anton’s also suggests that, because sections 1727 and 1742.1,

subdivision (b), serve similar purposes, a subcontractor should not be held

liable for liquidated damages if the contractor has withheld funds and

transmitted them to the awarding body. As Anton’s observes, section 1742,

subdivision (f), provides that money withheld under section 1727 is released

to the Department in the event the assessment is affirmed. Thus, under both

statutes, money is eventually sent to the Department.

However, the Legislature chose only to insulate a party from liability

for liquidated damages if it deposits money directly with the Department,

and it is not unreasonable to respect the distinction between these statutes.

Requiring withholding by the contractor or awarding body secures funds for

the payment of the assessment and penalties regardless of the offending

subcontractor’s actions or status, including possible bankruptcy or inability to

pay. The Legislature also could have considered redundancy appropriate to

cover interest on the unpaid wages. (See § 1741, subd. (b).) As noted by the

DLSE, multiple “statutes guaranteeing timely payment of progress and

retention amounts . . . permit[] the owner or direct contractor to withhold up

20

to 150 percent of the amount in dispute from the contractor or subcontractor,

respectively.” (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.

(2018) 4 Cal.5th 1082, 1088 [collecting statutes].) We do not think it absurd

that sections 1727 and 1742.1 may result in the parties setting aside up to

200 percent of the assessment prior to review.9 Nor do we need to decide how

the parties would recoup any overage after the proceedings have concluded.

Anton’s argues the DLSE should be “equitably estopped” from pursuing

liquidated damages because it directed Hazard to transfer the withheld

money to the City. Under section 1727, subdivision (b), “upon the request of

the Labor Commissioner, [the contractor shall] withhold sufficient money due

the subcontractor under the contract to satisfy the assessment and transfer

the money to the awarding body.” Anton’s fails to explain how following the

language of the statute supports estoppel.

Anton’s also briefly raises a constitutional argument, but fails to

explain its theory or provide supportive authority. “We are not bound to

develop appellants’ arguments for them. [Citation.] The absence of cogent

legal argument or citation to authority allows this court to treat the

contentions as [forfeited].” (In re Marriage of Falcone & Fyke (2008) 164

Cal.App.4th 814, 830 (Falcone).)

Anton’s remaining arguments iterate on these contentions and fail to

change our view of the relevant statutes. Again, while there appears to be

some redundancy built into the statutory scheme, we do not see any absurd

9 Anton’s argument that the statutes may result in interested parties

withholding, depositing, or paying 900 percent of the assessment lacks

foundation. Any party who may be liable for liquidated damages can either

pay workers their unpaid wages within 60 days or deposit the entire amount

of the assessment with the Department of Industrial Relations. (§ 1742.1.)

21

results that would warrant a departure from the plain language of section

1742.1.

E. Apprenticeship Violations on the Torrey Pines Road Project

Anton’s was held liable for three apprenticeship-related violations:

(1) failure to give timely notice of the Torrey Pines Road Project; (2) failure

to employ a sufficient number of apprentices; and (3) failure to request

apprentices from local committees. With regard to the first violation, Anton’s

does not dispute that it failed to submit contract award information to any

apprenticeship program before starting work on the Torrey Pines Road

Project. Instead, Anton’s argues it was not required to do so “because Anton’s

hires and trains its own apprentices.” Anton’s cites no authority for this

proposition, and there is no such carve-out in section 1777.5, subdivision (e),

which provides: “Before commencing work on a contract for public works,

every contractor shall submit contract award information to an applicable

apprenticeship program that can supply apprentices to the site of the public

work.” (Italics added.)

Second, Anton’s fails to show it employed an adequate number of

apprentices on the Torrey Pines Road Project. (See § 1777.5, subd. (i); Cal.

Code Regs., tit. 8, § 230.1, subd. (a).) Anton’s claims, “only straight time

hours count toward the minimum ratio. Several days worked on the Torrey

Pines [Road] Project were Saturday or overtime shifts due to the emergent

nature of the project. Thus, Anton’s ratio [of journeymen to apprentices] was

correct.” As with other arguments, Anton’s fails to provide any legal support

or appropriate citation to the record. Accordingly, this argument is forfeited.

(See Falcone, supra, 164 Cal.App.4th at p. 830.)

Third, Anton’s does not dispute that it failed to request the dispatch of

apprentices from appropriate committees. (Cal. Code Regs., tit. 8, § 230.1,

22

subd. (a).) It asserts it did not need to do so because it “has ongoing approval

to train apprentices.” A contractor need only request apprentices if it is “not

already employing sufficient registered apprentices” to meet the required

ratio. (Ibid.) As Anton’s has not shown it already employed sufficient

apprentices, the fact it could have done so is not relevant.

Next, Anton’s challenges the DLSE’s imposition of penalties under

section 1777.7, subdivision (a)(1), which provides for penalties up to $100

per day for a contractor who “knowingly violate[s] Section 1777.5.” “[A]

contractor knowingly violates Labor Code Section 1777.5 if the contractor

knew or should have known of the requirements of that Section and fails to

comply, unless the failure to comply was due to circumstances beyond the

contractor’s control.” (Cal. Code Regs., tit. 8, § 231, subd. (h).)

Anton’s fails to argue that its violations of section 1777.5 were not

“knowing[],” instead reiterating its argument that it did not violate section

1777.5. For the reasons explained above, we conclude otherwise.

Moreover, Anton’s does not address the Director’s finding that there

was an “irrebuttable presumption that Anton’s knew or should have known

of the apprenticeship requirements of section 1777.5 . . . because Anton’s

was issued prior assessments for apprenticeship violations and because the

contract for the Torrey Pines Road Project notified Anton’s of its obligation to

comply with prevailing wage requirements.” Under California Code of

Regulations, title 8, section 231, subdivision (h), “There is an irrebuttable

presumption that a contractor knew or should have known of the

requirement of Section 1777.5 if the contractor had previously been found to

have violated that Section, or the contract and/or bid documents notified the

contractor of the obligation to comply . . . .” By failing to challenge this

23

finding, Anton’s has forfeited its arguments. (See, e.g., Asaro, supra, 103

Cal.App.5th at p. 728, fn. 4.)

Finally, Anton’s claims it should not be liable for underpaying workers

due to excessive payment to apprenticeship funds. Anton’s fails to provide

any record citations for its factual assertions or any authority for its

arguments, which are thus forfeited. (See Falcone, supra, 164 Cal.App.4th at

p. 830.)

DISPOSITION

The judgment is affirmed. Respondents are entitled to costs on appeal.

BUCHANAN, J.

WE CONCUR:

McCONNELL, P. J.

O’ROURKE, J.

24

Filed 11/18/25

CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

ANTON’S SERVICES INC., D084833

Appellant,

v. (Super. Ct. No. 37-2023-

00021117-CU-WM-CTL)

KATRINA S. HAGEN, as Director, etc.,

et al.,

Respondents; ORDER CERTIFYING

OPINION FOR PUBLICATION

DIVISION OF LABOR STANDARDS

ENFORCEMENT,

Real Party in Interest and

Respondent.

THE COURT:

The opinion in this case filed October 23, 2025 was not certified for

publication. It appearing the opinion meets the standards for publication

specified in California Rules of Court, rule 8.1105(c), the request pursuant to

rule 8.1120(a) for publication is GRANTED.

IT IS HEREBY CERTIFIED that the opinion meets the standards for

publication specified in California Rules of Court, rule 8.1105(c); and

ORDERED that the words “Not to Be Published in the Official Reports”

appearing on page one of said opinion be deleted and the opinion herein be

published in the Official Reports.

McCONNELL, P.J.

Copies to: All parties

2

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.