affirming the application of the clean hands doctrine where the plaintiff “chose to proceed in equity rather than seek damages in an action at law”
How later courts described this case
- affirming the application of the clean hands doctrine where the plaintiff “chose to proceed in equity rather than seek damages in an action at law”
Written by the judges who cited it.
The opinion
IN THE UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF ARKANSAS
FAYETTEVILLE DIVISION
PROGRESSIVE TECHNOLOGIES, INC. PLAINTIFF
V. CASE NO. 5:24-CV-5101
ADEPT PATRIOT SERVICES, LLC DEFENDANT
MEMORANDUM OPINION AND ORDER
Before the Court is Plaintiff Progressive Technologies, Inc.’s (“Progressive”)
Motion for Summary Judgment (Doc. 48), which Defendant Adept Patriot Services, LLC
(“Adept”) opposes.’ For the reasons stated below, the Motion is DENIED.
1. BACKGROUND
This case arises out of a construction dispute between Progressive, a
subcontractor, and Adept, a general contractor. Adept was hired to install a fire alarm
system (“the Project”) in eighteen buildings of the Veterans’ Affairs (“VA”) Health Care
System Campus located in Fayetteville, Arkansas. Adept then subcontracted certain jobs
to Progressive, including demolition work on the existing fire alarm system and
installation, testing, and commissioning the upgraded system. The total amount Adept
agreed to pay Progressive under the subcontract was $171,555.00. Adept subcontracted
other jobs to nonparty Axis Electric, which was tasked with placing conduits for cable and
1 In addition to the Motion, the Court considered Progressive’s Brief in Support of
Summary Judgment (Doc. 48) and Statement of Facts (Doc. 50); Adept’s Brief in
Opposition to Summary Judgment (Doc. 58), Response to Progressive’s Statement of
Facts (Doc. 56), and separate Statement of Facts (Doc. 57); and Progressive’s Reply in
Support of Summary Judgment (Doc. 65) and Response to Adept’s Statement of Facts
(Doc. 66).
supplying power to the Project. Adept’s role was to oversee all subcontractor work and
install fiber optic cable for the new fire alarm system.
At some point, VA eliminated a few of the buildings from the scope of work, and
Adept presented VA with a proposal to reduce the prime contract amount to account for
the reduced scope. Progressive proposed that its payment under the subcontract be
reduced by $1,415.00 to account for the elimination of the three buildings, but Adept never
agreed to Progressive’s proposal, and the parties still disagree about the value of the
reduced scope of work.
The entire Project was supposed to have been completed by December 17, 2021;
however, some tasks ran behind schedule. According to Progressive, both Axis Electric
and Adept improperly installed a number of items or delayed installation, which caused
Progressive to fall behind on its own installation deadlines. Adept counters that
Progressive’s delays were its own fault, as Progressive procrastinated its jobs and failed
to send enough personnel to the worksite.
Progressive maintains that by January 2022, VA had approved all work on the
Project. The only remaining task was the installation of two workstations in Building 1.
After the parts for these two units arrived, Progressive attempted to complete the job but
contends it was once again delayed—this time by both Adept and VA. Progressive claims
it finally finished its work under the subcontract in May 2022.
Adept tells a different story. Its position is that Progressive still had more work to
do as of June 2022 but refused to complete it. As a result, Adept was forced to take over
the Project and complete Progressive’s work at Adept’s expense. Progressive denies all
this and insists that the tasks Adept asked it to perform in June were outside the agreed
scope of work. For example, Adept supposedly requested that Progressive reprogram a
new fire alarm control panel to be compatible with outdated software—as a cost-saving
measure. Progressive refused because it believed reprogramming the panel this way
would have voided the manufacturer’s warranty on the new panel.
In the end, Adept passed all of Progressive’s bills on to VA for payment, and VA
paid every bill in full. However, Adept refused to tender all payments to Progressive
because it believed Progressive breached the subcontract. Of the $171,555.00 that
Progressive billed to the Project, Adept paid Progressive only $45,414.62 and kept the
rest. Sometime in June 2022, Adept presented Progressive with a damages estimate of
$53,084.18 but allegedly failed to explain why it was retaining the remaining balance—
over $73,000.00. It was only after Progressive filed suit that Adept created a new
damages estimate of $137,647.97—well in excess of the amount Adept retained from
VA’s payments. Progressive asserts that Adept’s new damages estimate bears no
relationship to actual costs Adept expended on the Project and is not substantiated by
receipts, invoices, or employee time sheets.
In addition to moving for summary judgment on its own breach of contract claim,
Progressive argues that Adept’s counterclaim for breach of contract should be dismissed
as a matter of law. Progressive asserts two affirmative defenses to breach: unclean hands
and estoppel. Both defenses rest on the theory that Adept should be equitably barred
from retaining Progressive’s money because Adept certified to VA in writing—using
Federal Acquisition Regulation Form 52.232-5(c)(3) (“FAR Form”)—that the bills did “not
include any amounts which [Adept] intend[ed] to withhold or retain from a subcontractor
or supplier in accordance with the terms and conditions of the subcontract.” Progressive
points out that Adept did withhold some payments from Progressive, which means Adept
violated the certifications and has unclean hands or should otherwise be estopped from
retaining the funds. Adept responds that these affirmative defenses are meritless. In
Adept's view, each time it submitted a FAR Form and invoice, Adept fully intended to pay
Progressive; but as the Project came to an end and it became clear that Progressive
would not complete the work on time, Adept enforced its contractual right to retain certain
payments. Section 1.2 of the subcontract states:
In the event of any breach by the Subcontractor of any provision or
obligation of this Subcontract, . . . the Contractor shall have the right to retain
out of any payments due or to become due to the Subcontractor an amount
sufficient to completely protect the Contractor from any and all loss, damage
or expense there from, until the situation has been satisfactorily remedied
or adjusted by the Subcontractor.
(Doc. 50-6).
ll. LEGAL STANDARD
A party moving for summary judgment must establish the absence of a genuine
dispute of material fact and its entitlement to judgment as a matter of law. See Fed. R.
Civ. P. 56; Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87
(1986); Nat’ Bank of Commerce of El Dorado v. Dow Chem. Co., 165 F.3d 602 (8th Cir.
1999). The same standard applies where, as here, the parties have filed cross-motions
for summary judgment. When there exists no genuine issue as to any material fact,
2 It is undisputed that Adept submitted multiple FAR Forms to VA for Progressive’s bills
over the course of months. See Doc. 49, pp. 14-15.
“summary judgment is a useful tool whereby needless trials may be avoided, and it should
not be withheld in an appropriate case.” United States v. Porter, 581 F.2d 698, 703 (8th
Cir. 1978). “[T]he plain language of Rule 56(c) mandates the entry of summary judgment,
after adequate time for discovery and upon motion, against a party who fails to make a
showing sufficient to establish the existence of an element essential to that party's case,
and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477
U.S. 317, 322 (1986).
ill. DISCUSSION
Progressive’s request for summary judgment on its claim for breach of contract is
easily denied. As the above factual recitation shows, there remain genuine, material
disputes of fact that preclude summary judgment. In particular, the parties disagree about
whether Project delays occurred, and if so, who was to blame. They further disagree
about whether Adept completed any of Progressive’s work and whether Adept is entitled
to retain any of Progressive’s fees in payment for that work. At trial, the parties will present
their dueling theories and demands for damages.
As for Progressive’s request for judgment on Adept’s counterclaim for breach of
contract, the Court finds that Progressive’s affirmative defenses of unclean hands and
estoppel are no bar to Adept’s claim. The “clean hands maxim” stands for the proposition
that “[one] who comes into equity must come with clean hands’ and, thus, “bars relief to
those guilty of improper conduct in the matter as to which they seek relief.” Marshall v.
Marshall, 227 Ark. 582, 586 (1957) (citation omitted). Adept appears to acknowledge that
equitable defenses generally cannot bar legal claims—like breach of contract. Cf Poff v.
Brown, 374 Ark. 453, 456-57 (2008) (affirming the application of the clean hands doctrine
where the plaintiff “chose to proceed in equity rather than seek damages in an action at
law”). But even if the unclean hands defense were somehow applicable here, Progressive
fails to cite any law to suggest a prime contractor's signature on a FAR Form would trump
its right under the subcontract to retain and recoup any fees, costs, and expenses for
nonperformance. Furthermore, even if a so-called false certification on a FAR Form could
support an argument for unclean hands, there is at least a genuine, material dispute of
fact about whether Adept’s certifications were, indeed, false. Adept insists that at the time
it submitted each FAR Form, it intended to pay Progressive in full. It was only later, once
the Project was done, that Adept decided it must retain some of the funds due to
nonperformance. Relatedly, Adept is not equitably estopped from attempting to enforce
Section 1.2 of the subcontract, which, by its plain language, permits Adept to “retain out
of any payments due or to become due to the Subcontractor an amount sufficient to
completely protect the Contractor from any and all loss.” (Doc. 50-6).
IV. CONCLUSION
IT IS THEREFORE ORDERED that Progressive’s Motion for Summary Judgment
(Doc. 48) is DENIED. He
IT IS SO ORDERED on this pp day of October, 2025.
{IEF UNITED STATES DISTRICT JUDGE