“It is not the responsibility or function of this court to rewrite the parties’ contract in order to provide for a more equitable result. A contract ‘does not become ambiguous by reason of the fact that in its operation it will work a hardship upon one of the parties thereto.’”
How later courts described this case
- “It is not the responsibility or function of this court to rewrite the parties’ contract in order to provide for a more equitable result. A contract ‘does not become ambiguous by reason of the fact that in its operation it will work a hardship upon one of the parties thereto.’”
- if one construction would make a doubtful condition meaningless, then the meaningful construction prevails
Written by the judges who cited it.
The opinion
[This opinion has been published in Ohio Official Reports at 78 Ohio St.3d 353.]
FOSTER WHEELER ENVIRESPONSE, INC., APPELLEE AND CROSS-APPELLANT, v.
FRANKLIN COUNTY CONVENTION FACILITIES AUTHORITY, APPELLANT;
LAWHON & ASSOCIATES, INC., CROSS-APPELLEE.
[Cite as Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention
Facilities Auth., 1997-Ohio-202.]
Contracts—Removal and disposal of hazardous waste from construction site—
Action by excavator for breach of contract and negligent
misrepresentation—Motions for summary judgment by defendants proper,
when.
(No. 95-2467—Submitted January 7, 1997—Decided May 14, 1997.)
APPEAL and CROSS-APPEAL from the Court of Appeals for Franklin County, No.
95APE04-401.
__________________
{¶ 1} This action arises out of a contract for the removal and disposal of
hazardous waste from the construction site of the Greater Columbus Convention
Center.
{¶ 2} Defendant-appellant, Franklin County Convention Facilities
Authority (“CFA”), is a public agency governed by a volunteer public board
pursuant to R.C. 351.04. Defendant and cross-appellee, Lawhon & Associates, Inc.
(“Lawhon”), is an environmental consulting firm engaged by CFA on April 1,
1990, to perform hazardous material consulting services at the construction site of
the convention center. Plaintiff-appellee and cross-appellant, Foster Wheeler
Enviresponse, Inc. (“Enviresponse”), is an environmental hazards remediation
contractor engaged by CFA on October 1, 1991, to excavate and dispose of certain
hazardous waste discovered at the convention site.
SUPREME COURT OF OHIO
{¶ 3} During the early phase of construction, a drain line was being installed
in the southeast section of the property. The excavator tore the corner of a large
wooden box buried beneath the surface, and coal tar waste was released from the
box and into the sewer trench. Upon further investigation, the box was found to be
sixty-one feet long, thirty-one feet wide and eleven feet deep, and filled with dirt
and creosote. The area in which the box was located was formerly a railroad depot.
It was believed that the box had been used as a pit in which railroad ties were
creosoted, and that when the site was no longer used for this purpose the remaining
creosote was left in the pit and covered with dirt.
{¶ 4} Laboratory analysis indicated that the constituent benzene was
present in sufficient quantities to characterize the material in the box as hazardous
waste. Upon the advice of Lawhon, and with the concurrence of the Ohio
Environmental Protection Agency, CFA elected a plan of remediation which
involved removing the clean soil above the creosote and contaminated soil,
solidifying and removing the waste remaining in the box, excavating and
transporting “[t]he solidified waste, waste contaminated earth, and all contaminated
areas *** to a hazardous waste landfill for disposal,” and backfilling the excavated
area with clean fill.
{¶ 5} In July 1991, the contract for the disposal of the coal tar waste was
publicly bid. The bid specifications stated:
“[T]he contents of the box consisted of 8 to 8.5 ft. of earth on top of 1.5 to
2 ft. of tar and tar contaminated material. *** The material has not moved into the
soil, and there is little contamination outside of the box except in areas of recent
disturbance. The quantity of tar and tar contaminated soil is estimated to be 140
cubic yards.
“Samples of the soil over the waste were taken *** down to 8 feet depth.
Samples were composited from 0-3, 3-6, and 6-8 feet. *** The results show that
2
January Term, 1997
the soil above the waste has negligible contamination and can be placed back in the
excavation.”
{¶ 6} The cost for disposing of the coal tar waste was estimated at $175,000.
Bidders were instructed to submit proposals for a base price to remove and dispose
of the estimated one hundred forty cubic yards of contaminated waste, and for a
unit price, to be used in the event that “the quantity of coal tar waste and
contaminated soil that must be treated as hazardous waste is more or less than 140
cubic yards, the consultant’s estimate.”
{¶ 7} Enviresponse was found to be the lowest responsive and responsible
bidder with a base bid of $165,000 and a unit price bid of $265 per cubic yard of
waste. Accordingly, on October 1, 1991, CFA and Enviresponse entered into a
contract on these terms for disposal of the coal tar waste.
{¶ 8} The contract between CFA and Enviresponse consists of an eleven-
page writing entitled “CONTRACT,” and several other writings specifically “made
part of this Contract.” The contract documents are identified as “[t]he plans,
Specifications, General Conditions, Special Conditions, Addenda and other
Contract Documents.”
{¶ 9} The contract describes the work to be performed as “ITEM NO. 1—
COAL TAR WASTE DISPOSAL—BASE BID,” and sets forth that the “TOTAL
AMOUNT OF THIS CONTRACT IS $165,000.00 subject to any additions or
deductions during construction.”
{¶ 10} Article 3 of the contract, entitled “CHANGE ORDERS,
ADDITIONS, AND DEDUCTIONS,” provides: “No alterations shall be made in
the work shown or described by the plans and specifications, except upon the
written order of the Owner, and when so made, the value of the work added or
omitted shall be computed for approval by the Owner, and the amount so
ascertained shall be added to or deducted from the base bid amount.”
3
SUPREME COURT OF OHIO
{¶ 11} Under Article 5, Section h of the general conditions, “it is understood
that the scheduled quantities of work to be done and materials to be furnished may
each be increased or decreased as hereinafter provided.” Article 7, Section b of the
general conditions provides:
“In instances involving a unit price Contract, the Owner may, by written
instructions to the Contractor, make alterations in the Plans involving increases or
decreases in the quantity of work as may be necessary. Such alterations shall not
be considered a waiver of any conditions of the Contract, nor invalidate any of the
provisions thereof, unless the alterations materially change the scope of the work.
The cost of increases or decreases in quantities of items shall be computed at the
unit price bid and shall be added to or deducted from the original Contract by the
endorsement of Change Order forms.”
{¶ 12} In a document entitled “CONTRACT ATTACHMENT A,” the
following is provided:
“UNIT PRICES
“*** The unit prices will apply to the net difference in quantities on any
given change[.]
“The unit prices may be used to adjust the Contract sum should there be an
authorized increase or decrease in the scope of work stated.
“DESCRIPTION OF ITEM UNIT UNIT PRICE*
“All activities associated with Cubic Two Hundred Sixty Five
disposal of coal tar waste in Yards and 00/100 Dollars
quantities either in excess of ($265.00)
or less than the base bid of
140 cubic yards.
“* The unit price will be used to adjust the contract sum up or down
depending on whether the quantity of coal tar waste and contaminated soil that must
be treated as hazardous waste is more than or less than 140 cubic yards, the
4
January Term, 1997
consultant’s estimate. Adjustments will not be made for less than one cubic yard
and will be made to the closest cubic yard. Contractor shall make measurements
observed by a representative of the consultant.”
{¶ 13} On October 15, 1991, Enviresponse commenced excavation of the
soil above the waste. However, it began to encounter odors and saturated soil
sooner than anticipated based on the bid specifications. On the same day, David
“Mike” Finton, then manager of Enviresponse’s Ohio office, telephoned Claire A.
Sawaya, then Executive Director of CFA, to inform her that there was more coal
tar waste than originally estimated.
{¶ 14} According to Finton, Sawaya told him that he “should take ***
direction from Lawhon.” Finton “took that to mean that what Lawhon told [him]
to do was how [he] was to proceed with this project.” It was Finton’s understanding
that Enviresponse would automatically be paid the unit price for all contaminated
material removed in excess of one hundred forty cubic yards, so long as Lawhon
took measurements confirming the amount of material that was being excavated.
However, Finton testified that he did not specifically recall any discussion with
Sawaya concerning unit price, and that Sawaya “[a]bsolutely [did] not” indicate
that Enviresponse was free to disregard the contract documents.
{¶ 15} According to Sawaya, her conversation with Finton dealt
specifically with Finton’s contention that the soil already removed from on top of
the coal tar waste was contaminated. It was Sawaya’s impression that Finton
wanted owner approval to dispose of the material that Enviresponse had excavated.
Since no determination had yet been made by Lawhon that such soil was
contaminated, she told Finton “that it was his responsibility to contact Lawhon with
respect to what he believed the site conditions to be and that [CFA] would take
advice from Lawhon concerning the scope of the work.” She presumed, however,
that if additional material needed to be disposed of, “the normal [written] change
order and [written] authorization process would proceed.”
5
SUPREME COURT OF OHIO
{¶ 16} Against this backdrop of divergent presumptions, Enviresponse
continued to remove and transport hazardous waste from the construction site.
However, the migration of contaminants outside the box proved to be quite
extensive. Paul Braun, Lawhon’s on-site monitor, observed that “every time they
[Enviresponse] dug 10 more feet, it [the contamination] would just be as bad as it
was when they started,” and agreed that there “[s]eem[ed] to be no end to the lateral
movement of the contaminated material.”
{¶ 17} On October 27, 1991, Finton faxed a letter to Gilbert E. Raines,
Ph.D., Vice-President of Engineering for Lawhon, informing as to “the current
status of the project and to give *** some indication of where *** the project is
headed.” The letter stated that one thousand four hundred cubic yards of additional
waste beyond the original estimate of one hundred forty cubic yards had been
removed from the pit and transported by the truckload to the Envirosafe facility in
Oregon, Ohio. “At $265 per cubic yard [the unit price], the additional cost for
exhumation, transport and disposal of material from the pit is $371,000.” The letter
also estimated that there remained “an additional eight hundred (800) cubic yards
of material to be removed from the pit *** represent[ing] an additional cost of
$212,000.”
{¶ 18} The next morning, Lawhon faxed a response to Finton advising “that
no additional costs other than those in the base contract are to be incurred unless
prior written approval is received from us.”
{¶ 19} Nevertheless, Enviresponse continued to transport hazardous
material from the construction site to the Envirosafe landfill until October 31, when
Lawhon told it to cease activities.1 According to Finton, the work continued
1. It is not entirely clear from the record whether Enviresponse also continued excavation between
October 28 and October 31, 1991. It appears from Finton’s October 27 letter to Raines that, as of
that time, Enviresponse had “removed” an extra one thousand four hundred cubic yards of
contaminated material from the pit, and estimated that another eight hundred cubic yards “must be
removed from the still contaminated side walls.” However, Enviresponse ultimately notified
6
January Term, 1997
because, despite Lawhon’s October 28 fax, Braun was “still signing [hazardous
waste] manifests [for disposal of the material at the landfill] and still shipping loads
even as this thing [the October 28 fax] was being sent to us [Enviresponse].”2
Patrick H. Bigelow, Enviresponse’s project superintendent, testified at deposition
that “[e]verything we took out of there was directed to us by Paul Braun.”
{¶ 20} Braun admitted that he filled out and signed waste manifests for each
truck that left the construction site destined for Envirosafe, both before and after
October 28, 1991.3 He admitted that on October 18, he asked whether Envirosafe
could expose a sand seam outside the box to confirm that contaminants had
migrated outside the box. Except for this request, he testified that he gave no
direction to Enviresponse on how to proceed, that he was a passive observer to the
work being performed by Enviresponse, and that Enviresponse was operating
completely of its own accord.
{¶ 21} The record also reveals some disparity as to whether Braun
represented that written authorization was unnecessary to trigger payment under
Lawhon on November 8 that “[t]he extra amount is 3546 yd 3 x $256/yd3 = $939,690.00.” This
would appear to indicate that excavation was ongoing after October 28. However, Finton testified
at deposition that after receiving Lawhon’s fax on the morning of October 28, “we continued to ship
loads. We did not continue to excavate.” Yet, at another point in his testimony, Finton explained
that he “really [did not] know for certain” whether Enviresponse continued to excavate after
receiving Lawhon’s October 28 fax. Braun testified that excavation activities continued after
October 28.
2. Finton was not aware of whether CFA was provided copies of the manifests as the work was
ongoing. However, Sawaya testified that she did receive copies of the waste manifests that were
returned by Envirosafe.
3. There were initial problems regarding the signing of the manifests. Each manifest contained a
generator’s certification. There was some trepidation on the part of CFA in signing the manifest
because it was not the generator of the waste. Accordingly, CFA attached a statement to each
manifest explaining its role vis-à-vis the contamination. Also, manifests for the first three trucks
leaving the construction site were executed by Sawaya. This apparently created some inefficiency.
Thus, Braun was given authority to sign all manifests thereafter.
7
SUPREME COURT OF OHIO
the unit-price provision of the CFA-Enviresponse contract. The following colloquy
took place at Finton’s deposition:
“Q. Did you ever have any conversations with Paul Braun where he
specifically told you that he was the agent of [CFA]? And specifically the word
‘agent.’
“A. I don’t recall any.
“Q. Do you recall any conversations with Paul Braun where he specifically
advised you that there was no need for [Enviresponse] to obtain a written change
order or written authorization from [CFA] in order for [Enviresponse] to be paid
for hazardous waste above and beyond 140 cubic yards?
“A. As I indicated before, the only time that change orders were discussed
were well past this time, November 4th, and by Bill Lawhon.”
{¶ 22} However, in an affidavit filed subsequent to the taking of his
deposition, Finton stated:
“On one of my visits to the job site after the additional contamination was
discovered, I asked Paul Braun whether he had approval to direct us [Enviresponse]
to remove the additional contaminated material. Braun assured us that he did have
approval from his superiors and that we (Enviresponse) would be paid for the
additional work.”
{¶ 23} Also contained within the record are the field notes of Hank
Markferding, who was an on-site sales representative of Enviresponse.4 The note
4. It is unclear from the record what role Markferding played at the construction site. He was
apparently hired by Enviresponse in the summer of 1991 primarily as a salesman. According to
Finton’s deposition testimony, Markferding had no prior experience as a hazardous waste
remediation specialist, and was not assigned by Enviresponse to act in any authoritative capacity at
the construction site. Finton explained further that Markferding “had sold this project, this was his
find, and, therefore, he wanted to make sure that the project went well. And he was also interested
in being on site and learning firsthand how these projects were done.”
Yet, in qualifying Markferding’s field notes, Finton stated in his affidavit, “Hank
Markferding [was] assigned by me to work on the Franklin County Convention Center coal tar
remediation project. *** Markferding *** [was] present at the job site during my visits throughout
the excavation, and gave me periodic reports of the activity on-site.”
8
January Term, 1997
dated October 16 reads in part: “Consultant states that the contract allows for the
extra work without a change order.”
{¶ 24} Braun denies having ever made that or any similar statement.
According to Braun, whenever Markferding would question him as to the extra
work or the unit price, he would inform Markferding that that was an issue for
Enviresponse to take up with CFA.
{¶ 25} On November 8, 1991, Enviresponse submitted a request for
clarification, seeking “an increase in fee to cover the work performed for additional
hazardous waste material removed, transported, and disposed of at the Envirosafe
Landfill. *** The extra amount is 3546 yd3 x $265/yd3 = $939,690.00.” That same
day, Lawhon denied the request on the basis that “[a]ll material removed beyond
the amount specified in the contract [i.e., one hundred forty cubic yards] required
written authorization.”
{¶ 26} Thereafter, Enviresponse initiated this action against CFA and
Lawhon, alleging that CFA had breached its contract, and that Lawhon had
negligently misrepresented the amount of hazardous waste that was present at the
construction site and that there was no need to obtain written authorization.
{¶ 27} Initially, Lawhon filed a motion to dismiss pursuant to Civ.R.
12(B)(6), which the trial court granted. However, the court of appeals reversed and
remanded the cause in Foster Wheeler Enviresponse, Inc. v. Franklin Cty.
Convention Facilities Auth. (1993), 88 Ohio App.3d 73, 623 N.E.2d 134.
{¶ 28} After completion of discovery, the trial court granted CFA’s and
Lawhon’s motions for summary judgment.
Markferding was dismissed after the project was terminated and apparently CFA was
unable to schedule his deposition. CFA filed a motion with the trial court to strike Markferding’s
affidavit or, alternatively, to exclude his field notes. This motion was denied. The court of appeals
held moot CFA’s assignment of error on its cross-appeal regarding the striking of Markferding’s
affidavit. As to the field notes, the appellate court found that the granting or denying of a motion in
limine is an interlocutory order and, therefore, not final and appealable. No further appeal to this
court has been taken regarding these issues.
9
SUPREME COURT OF OHIO
{¶ 29} The court of appeals reversed the trial court’s judgment as to CFA,
but affirmed its decision as to Lawhon on the basis that since Enviresponse “is
entitled to compensation under its contract with CFA, *** plaintiff [Enviresponse]
cannot show that it relied upon, or that it suffered pecuniary loss as a result of either
of Lawhon’s alleged negligent misrepresentations.”
{¶ 30} The cause is now before this court pursuant to the allowance of a
discretionary appeal and cross-appeal.
__________________
Vorys, Sater, Seymour & Pease, Michael W. Donaldson and John C. Elam,
for appellee and cross-appellant.
Chester, Willcox & Saxbe, Richard A. Frye, John J. Chester and Karen H.
Penley, for appellant.
Taft, Stettinius & Hollister and Michael A. Byers, for cross-appellee
Lawhon & Associates.
Janet E. Jackson, City Attorney, and Daniel W. Drake, First Assistant City
Attorney, urging reversal for amicus curiae, city of Columbus, Ohio.
John E. Gotherman, urging reversal for amici curiae, Ohio Municipal
League and Ohio Municipal Attorneys Association.
Calfee, Halter & Griswold, Stanley J. Dobrowski and Albert J. Lucas,
urging reversal for amicus curiae, Ohio Building Authority.
__________________
ALICE ROBIE RESNICK, J.
{¶ 31} The broad issue in this case is whether Enviresponse may recover
from CFA, or alternatively from Lawhon, for the contaminated material in excess
of one hundred forty cubic yards that Enviresponse excavated and transported from
the construction site of the Greater Columbus Convention Center. Since the cause
comes to the court upon an appeal from summary judgment, our inquiry is
circumscribed by the standard set forth in Civ.R. 56(C).
10
January Term, 1997
I
CFA’S APPEAL
{¶ 32} It is universally recognized that where a building or construction
contract, public or private, stipulates that additional, altered, or extra work must be
ordered in writing, the stipulation is valid and binding upon the parties, and no
recovery can be had for such work without a written directive therefor in
compliance with the terms of the contract, unless waived by the owner or employer.
Lathrop Co. v. Toledo (1966), 5 Ohio St.2d 165, 34 O.O.2d 278, 214 N.E.2d 408;
Portsmouth v. Nicola Bldg. Co. (1922), 106 Ohio St. 550, 140 N.E. 174; Expanded
Metal Fire-Proofing Co. v. Noel Constr. Co. (1913), 87 Ohio St. 428, 101 N.E. 348;
Carthage v. Diekmeier (1909), 79 Ohio St. 323, 87 N.E. 178; Baltimore & Ohio
RR. Co. v. Jolly Bros. & Co. (1904), 71 Ohio St. 92, 72 N.E. 888; Ashley v. Henahan
(1897), 56 Ohio St. 559, 47 N.E. 573; Cincinnati v. Cameron (1878), 33 Ohio St.
336; 65; American Jurisprudence 2d (1972) 75-87, Public Works and Contracts,
Sections 189-198; Annotation, Effect of Stipulation, In Private Building or
Construction Contract, That Alterations or Extras Must Be Ordered In Writing
(1965), 2 A.L.R.3d 620, 631, Section 3; Annotation, Effect of Stipulation, In Public
Building or Construction Contract, That Alterations or Extras Must Be Ordered In
Writing (1965), 1 A.L.R.3d 1273, 1281-1282, Section 3; 7 P.O.F.2d (1975) 239,
247-248, Authorization for Extra Work Under Building Contract, Section 2; 25
P.O.F.2d (1981) 561, 571, 573-574, Building and Construction Contracts--Waiver
of Provision Requiring Written Change Orders, Sections 2 and 3.
{¶ 33} The pivotal question in this case is whether the contract between
CFA and Enviresponse should be interpreted to contain a requirement for written
authorization where more than the base amount of one hundred forty cubic yards
of contaminated material is found to be present at the site.
{¶ 34} Despite the parties’ attempts to correlate this case with others, our
review of the innumerable cases and commentary on the subject leads us to the
11
SUPREME COURT OF OHIO
inescapable conclusion that the meaning of any particular construction contract is
to be determined on a case-by-case and contract-by-contract basis, pursuant to the
usual rules for interpreting written instruments. See Cameron, supra, 33 Ohio St.
at 374.
{¶ 35} The cardinal purpose for judicial examination of any written
instrument is to ascertain and give effect to the intent of the parties. Aultman Hosp.
Assn. v. Community Mut. Ins. Co. (1989), 46 Ohio St.3d 51, 53, 544 N.E.2d 920,
923. “The intent of the parties to a contract is presumed to reside in the language
they chose to employ in the agreement.” Kelly v. Med. Life Ins. Co. (1987), 31
Ohio St.3d 130, 31 OBR 289, 509 N.E.2d 411, paragraph one of the syllabus.
{¶ 36} “Common words appearing in a written instrument will be given
their ordinary meaning unless manifest absurdity results, or unless some other
meaning is clearly evidenced from the face or overall contents of the instrument.”
Alexander v. Buckeye Pipe Line Co. (1978), 53 Ohio St.2d 241, 7 O.O.3d 403, 374
N.E.2d 146, paragraph two of the syllabus. Technical terms will be given their
technical meaning, unless a different intention is clearly expressed. Cincinnati Ins.
Co. v. Duffield (1856), 6 Ohio St. 200, paragraph one of the syllabus.
{¶ 37} Most important to this case, a writing, or writings executed as part
of the same transaction, will be read as a whole, and the intent of each part will be
gathered from a consideration of the whole. Legler v. United States Fid. & Guar.
Co. (1913), 88 Ohio St. 336, 103 N.E. 897; Kelly v. Carthage Wheel Co. (1900),
62 Ohio St. 598, 610, 57 N.E. 984, 986; Lesher v. Karshner (1890), 47 Ohio St.
302, 305, 24 N.E. 882; Miller v. Ratterman (1890), 47 Ohio St. 141, 156, 24 N.E.
496, 499; Cincinnati, Sandusky & Cleveland RR. Co. v. Indiana, Bloomington &
W. Ry. Co. (1886), 44 Ohio St. 287, 7 N.E. 139; Dodd v. Bartholomew (1886), 44
Ohio St. 171, 175, 5 N.E. 866, 867. See, also, New York Coal Co. v. New Pittsburgh
Coal Co. (1912), 86 Ohio St. 140, 167, 174, 99 N.E. 198, 204, 206 (recognizing the
12
January Term, 1997
maxim noscitur a sociis, that the meaning of words or provisions in a contract may
be indicated or controlled by those with which they are associated).
{¶ 38} Both CFA and Enviresponse agree upon the rule as expressed in
Farmers Natl. Bank v. Delaware Ins. Co. (1911), 83 Ohio St. 309, 94 N.E. 834,
paragraph six of the syllabus:
“In the construction of a contract courts should give effect, if possible, to
every provision therein contained, and if one construction of a doubtful condition
written in a contract would make that condition meaningless, and it is possible to
give it another construction that would give it meaning and purpose, then the latter
construction must obtain.”
{¶ 39} Although these rules contain a measure of flexibility in their
application, they are designed only to ascertain the parties’ intent. It is not the
responsibility or function of this court to rewrite the parties’ contract in order to
provide for a more equitable result. A contract “does not become ambiguous by
reason of the fact that in its operation it will work a hardship upon one of the parties
thereto.” Ohio Crane Co. v. Hicks (1924), 110 Ohio St. 168, 172, 143 N.E. 388,
389. See, also, Aultman Hosp. Assn., supra, 46 Ohio St.3d at 54-55, 544 N.E.2d at
924.
{¶ 40} The parties and the courts below all agree that Enviresponse was
required under its contract with CFA to obtain written authorization for any changes
in the “scope of work.” However, the court of appeals took the view that written
authorization was required only for changes in the “scope of work.” Accordingly,
it saw the determinative issue as being whether the removal and disposal of
contaminated waste in excess of the base bid amount of one hundred forty cubic
yards could properly be characterized as an “increase *** in the scope of work
stated.” The appellate court concluded that no change in the scope of work occurred
when Enviresponse excavated and transported more than the estimated one hundred
13
SUPREME COURT OF OHIO
forty cubic yards and, therefore, no written authorization was required. We
disagree.
{¶ 41} Article 3 of the contract provides that “[n]o alterations shall be made
in the work shown or described by the plans and specifications, except upon the
written order of the Owner.” (Emphasis added.) Only after the alteration is made
pursuant to a written order is the “value of the work added *** [to] be computed
***, and the amount so ascertained [to] be added to *** the base bid amount.”
(Emphasis added.) Article 7, Section b of the general conditions makes clear that
the term “alterations” is intended to encompass “increases *** in the quantity of
work.” Whatever legal significance there may be in other contexts of defining
“scope of work,” and regardless of whether the removal of excess contaminated
waste falls within that definition, such work constitutes an “alteration,” as that term
is used in this contract, for which a written order is required.
{¶ 42} Enviresponse argues that such an interpretation fails to give meaning
and purpose to “the final paragraph of [i.e., the footnote in] the Unit Prices
Attachment A.” According to Enviresponse, we must “establish[] constructions of
the second and final paragraphs of the Unit Prices Attachment A that [give]
‘meaning and purpose’ *** to both paragraphs.” The construction urged is that
“CFA obligated itself to pay Enviresponse for each cubic yard of hazardous waste
beyond the 140 cu. yd. estimate. *** [T]he mechanism for obligating itself was not
by written change order but instead by contractor measurements observed by the
consultant.”
{¶ 43} If the Unit Price Attachment constituted the entire agreement
between CFA and Enviresponse, we might find some merit in Enviresponse’s
interpretation of the footnote thereto. However, the point to reading the contract as
a whole is to avoid this very kind of abstract interpretation. In construing the
agreement, we must attempt to give effect to each and every part of it, not just “the
second and final paragraphs of the Unit Price Attachment A,” and avoid any
14
January Term, 1997
interpretation of one part which will annul another part. Legler, supra, 88 Ohio St.
336, 103 N.E. 897; Farmers Natl. Bank, supra, 83 Ohio St. 309, 94 N.E. 834, at
paragraph six of the syllabus.
{¶ 44} Construing the agreement as a whole, we find that the parties’ intent
in inserting the footnote was to set forth a prenegotiated unit price for adjusting the
contract sum in the event an alteration involving an increase or decrease in the
quantity of work was ordered in writing. The unit price is a preset method of
calculating the value of additional work to be used to adjust the contract sum where
the amount of waste is found to be more than the one hundred forty cubic yards. It
is not a prenegotiated waiver of the requirement for written authorization. “The
compensation to be paid was, therefore, based upon a price fixed as a result of
competitive bidding, and was not left to the subsequent agreement of the parties
when it might be possible for either to take advantage of the situation of the other.”
Nicola, supra, 106 Ohio St. at 557, 140 N.E. at 176.
{¶ 45} This interpretation affords meaning and purpose to all parts of the
agreement, whereas the interpretation urged by Enviresponse would in effect annul
those parts requiring a written order for any alteration. The primary purpose of
requiring written authorization for alterations in a building or construction contract
is to protect the owner against unjust and exorbitant claims for compensation for
extra work. It is generally regarded as one of the most effective methods of
protection because such clauses limit the source and means of introducing
additional work into the project at hand. It allows the owner to investigate the
validity of a claim when evidence is still available and to consider early on
alternative methods of construction that may prove to be more economically viable.
It protects against runaway projects and is, in the final analysis, a necessary adjunct
to fiscal planning. Ashley, supra, 56 Ohio St. at 572-573, 47 N.E. at 57; Cameron,
supra, 33 Ohio St. at 369-370; Johnson Constr., Inc. v. Rugby Mun. Airport Auth.
(N.D.1992), 492 N.W.2d 61, 63-64; 65 American Jurisprudence 2d, supra, at 76,
15
SUPREME COURT OF OHIO
Section 190; 25 P.O.F.2d, supra, at 569, Section 1. It is doubtful that the footnote
was intended to serve in any capacity which would override the written-order
provisions, or permit an increase of the contract sum solely upon the unilateral
performance of additional work by Enviresponse.
{¶ 46} Enviresponse further argues that it is entitled to recovery pursuant to
Nicola, Lathrop, and Cameron, supra. These cases essentially provide that, under
proper circumstances, the refusal of a public entity to give a contractor a written
order for alterations, in accordance with a contract stipulation therefor, may
constitute a breach of the contract or amount to a waiver of written orders.
However, in each case it was undisputed that the alteration was in fact ordered,
either orally or in writing, by someone with the authority to do so.
{¶ 47} There is no evidence in the record that CFA ordered Enviresponse
to remove and transport more than the base amount of one hundred forty cubic
yards of contaminated waste. The most that can be inferred from the record is that
CFA had knowledge that alterations involving increases in the quantity of work
were being made, and asserted no objection. However, mere knowledge, and even
acquiescence, is not enough for recovery. Lathrop, supra, 5 Ohio St.2d at 174, 34
O.O.2d at 283, 214 N.E.2d at 414; Diekmeier, supra, 79 Ohio St. at 344-345, 87
N.E. at 184. “Such stipulation [for a written order] being for the benefit of the
employer, proof of a waiver must either be in writing, or by such clear and
convincing evidence as to leave no reasonable doubt about it.” Ashley, supra, 56
Ohio St. 559, 47 N.E. 573, paragraph five of the syllabus. Thus, “‘[e]quivocal
conduct, or conduct of doubtful import, is not sufficient.’” Id., 56 Ohio St. at 574,
47 N.E. at 577, quoting O’Keefe v. St. Francis’s Church (1890), 59 Conn. 551, 561,
22 A. 325, 327.
{¶ 48} Nor can recovery against CFA be predicated on actions taken or
statements made by Lawhon. It is generally recognized that, in the absence of
express authority, an engineer, architect, superintendent or inspector in charge of
16
January Term, 1997
or assigned to public building or construction work has no power to waive or
modify a stipulation requiring a written order for alterations, even where that person
may authorize alterations in writing. Jolly Bros. & Co., supra, 71 Ohio St. 92, 72
N.E. 888, at paragraph one of the syllabus; Ashley, supra, 56 Ohio St. at 572-573,
47 N.E. at 576; Annotation, supra, 1 A.L.R.3d at 1312-1318, Sections 21-25; 65
American Jurisprudence 2d, supra, at 81-82, Public Works and Contracts, Section
194. There is nothing about the nature and duties of an environmental consultant
that would suggest that he falls outside the purview of this rule. There was nothing
in either the contract between CFA and Enviresponse or the contract between CFA
and Lawhon which gave Lawhon the authority to waive the requirement for written
orders. Under the CFA-Lawhon contract, Lawhon’s authority is limited to ordering
“minor changes in the Work not involving an adjustment in the Contract sum or an
extension of the Contract Time.”
{¶ 49} Accordingly, summary judgment was properly entered in favor of
CFA, and the judgment of the court of appeals is reversed on this issue.
II
ENVIRESPONSE’S CROSS-APPEAL
{¶ 50} The issue presented here is whether Enviresponse may proceed
against Lawhon on its claims for negligent misrepresentation.
{¶ 51} In its first claim, Enviresponse alleges that “[t]he bid specifications
and the contract [prepared by Lawhon] negligently represented that the amount of
contaminated waste was approximately 140 cubic yards, that the soil immediately
above the waste had negligible contamination and could be used as backfill, and
that there was little contamination of soil outside the box.”
{¶ 52} In its second claim, Enviresponse alleges that Lawhon
misrepresented that “no additional authorization was needed to remove the
additional contaminated material discovered on the site.” In support, Enviresponse
relies upon Finton’s affidavit and Markferding’s field notes.
17
SUPREME COURT OF OHIO
{¶ 53} Enviresponse’s argument is primarily devoted to distinguishing the
court’s decision in Floor Craft Floor Covering, Inc. v. Parma Community Gen.
Hosp. Assn. (1990), 54 Ohio St.3d 1, 560 N.E.2d 206. There it was held that “[i]n
the absence of privity of contract no cause of action exists in tort to recover
economic damages against design professionals involved in drafting plans and
specifications.” Id. at the syllabus. Enviresponse contends that Lawhon was given
excessive control over Enviresponse on this project, and that such control
constitutes a sufficient nexus between them to substitute for contractual privity.
See In re Hughes-Bechtol, Inc. (Bankr.S.D.Ohio 1991), 124 B.R. 1007, 1019-1020;
A.R. Moyer, Inc. v. Graham (Fla.1973), 285 So.2d 397; Annotation, Tort Liability
of Project Architect for Economic Damages Suffered by Contractor (1975), 65
A.L.R.3d 249.
{¶ 54} There is no need for the court to revisit, clarify, or define the
parameters of Floor Craft at this time. It is sufficient to note that there is no such
thing as a cause of action for excessive control. Privity, or its substitute, is not a
tort; it serves only to identify an interest or establish a relationship necessary to
allow for the bringing of a tort action for purely economic damages. Regardless of
whether the threshold requirement for privity is met, or even justified, there can be
no recovery where a necessary element to the tort itself is found to be missing.
{¶ 55} Article 5, Section h of the general conditions cautions that “[i]n unit
price Contracts, the quantities listed in the Form of Proposal are to be considered
as approximate and are to be used for the comparison of bids only.” This language
operates as a disclaimer, putting Enviresponse on notice not to rely on the estimates
as to the quantity of waste. See Delman v. Cleveland Hts. (1989), 41 Ohio St.3d 1,
4, 534 N.E.2d 835, 837-838. Thus, “as a matter of law, [Enviresponse] could not
have justifiably relied on the alleged misrepresentation of the quantity of waste.”
R.J. Wildner Contracting Co., Inc. v. Ohio Turnpike Comm. (N.D.Ohio 1996), 913
F.Supp. 1031, 1040.
18
January Term, 1997
{¶ 56} Enviresponse argues that Wildner does not apply because Lawhon
did not have a contract with Enviresponse; thus, the disclaimer cannot protect
Lawhon. However, the gravamen of Enviresponse’s claim is that the alleged
misrepresentations emanated from “[t]he bid specifications and the contract.”
These documents formed the agreement between Enviresponse and CFA. Thus,
the very sources of the alleged misrepresentations embodied a disclaimer as to
reliance thereon.
{¶ 57} In any event, Finton testified that prior to submitting the proposal for
work to CFA, it was his “feeling *** that the way that this project was put out in a
specification, that there was a likelihood that we would encounter additional
volume of materials. *** [W]ithout actually excavating *** it would be very
difficult to be able to determine that a hundred and forty cubic yards was the only
amount of material that was going to have to be removed.” He recalled “wanting
to make sure that the unit price was sufficient so that if we got into additional
materials found, that we were going to be able to do the work and still make
money.” He explained further:
“I have worked on a large number of site clean-ups where materials are to
be removed, and I’m aware of a lot of others that I was not directly involved with;
and I don’t know of any where the specified amount of material was not exceeded
in terms of remediation.
“It is very difficult when you’re working with something like this
circumstance where it is below ground and all you can do is do drillings in a grid
pattern over the affected area to determine specifically what the volumes are that
you’re going to have to deal with.
“The only way to do that is to get in and actually do the excavation and keep
track of what you’re removing.”
{¶ 58} Thus, irrespective of the contractual disclaimer, Enviresponse could
not have justifiably relied on the estimates relative to the quantity of waste.
19
SUPREME COURT OF OHIO
{¶ 59} As to Enviresponse’s second claim, there is no allegation that anyone
other than Braun represented that no additional authorization was required to
remove the excess contaminated waste. Pursuant to the supplementary conditions
set forth as part of the agreement between Enviresponse and CFA, the following
pertinent limitations of authority were placed upon the on-site monitor:
“SC-2.1.6.1 OSM has no authority to permit or require any deviation
from the Contract Documents or substitution of materials or equipment.”
“SC-2.1.6.3 OSM will not advise on, issue directives relative to, or
assume control over any aspect of the means, methods, techniques, sequences, or
procedures unless such advice or directions are specifically required by the Contract
Documents.”
“SC-2.1.6.5 OSM will not accept Contractor’s Work on behalf of either
Consultant or Owner.”
“SC-2.1.6.7 OSM has no authority to act as agent of the Consultant except
as set forth herein.”
{¶ 60} In applying the economic-loss rule to bar tort recovery in
construction contract cases, the majority in Floor Craft, supra, was concerned that
by asserting a tort claim, the contractor may try to “avoid its contract terms.” Id.,
54 Ohio St.3d at 7, 560 N.E.2d at 212. The dissenting opinion in Floor Craft
agreed, but felt there was no need to “disinter the privity doctrine to do this.” Id.,
54 Ohio St.3d at 14, 560 N.E.2d at 217 (H. Brown, J., dissenting). Thus, the one
point on which the majority and dissenting opinions in Floor Craft agree is that the
contractor should not be permitted to circumvent its contract terms by virtue of
labeling the action a tort.
{¶ 61} The limitations placed upon Braun’s authority by the supplementary
conditions clearly preclude Enviresponse from relying upon Braun’s alleged
representations regarding the lack of need for written orders. Although it appears
20
January Term, 1997
from the record that no one from Enviresponse had read the contract, it is
nevertheless bound by its terms.
{¶ 62} Accordingly, the judgment of the court of appeals, for the reasons
stated herein, is affirmed as to this issue.
{¶ 63} In light of the foregoing, the judgment of the court of appeals is
reversed as to CFA and affirmed as to Lawhon, and the summary judgment entered
by the trial court is reinstated.
Judgment affirmed in part
and reversed in part.
MOYER, C.J., DOUGLAS, COOK and LUNDBERG STRATTON, JJ., concur.
F.E. SWEENEY AND PFEIFER, JJ., dissent.
__________________
21