"the General Assembly undoubtedly did not intend to build into its recently revised [1976] ratemaking formula a means by which the PUCO may effortlessly abrogate that very formula"
How later courts described this case
- "the General Assembly undoubtedly did not intend to build into its recently revised [1976] ratemaking formula a means by which the PUCO may effortlessly abrogate that very formula"
Written by the judges who cited it.
The opinion
OPINIONS OF THE SUPREME COURT OF OHIO
The full texts of the opinions of the Supreme Court of
Ohio are being transmitted electronically beginning May 27,
1992, pursuant to a pilot project implemented by Chief Justice
Thomas J. Moyer.
Please call any errors to the attention of the Reporter's
Office of the Supreme Court of Ohio. Attention: Walter S.
Kobalka, Reporter, or Deborah J. Barrett, Administrative
Assistant. Tel.: (614) 466-4961; in Ohio 1-800-826-9010.
Your comments on this pilot project are also welcome.
NOTE: Corrections may be made by the Supreme Court to the
full texts of the opinions after they have been released
electronically to the public. The reader is therefore advised
to check the bound volumes of Ohio St.3d published by West
Publishing Company for the final versions of these opinions.
The advance sheets to Ohio St.3d will also contain the volume
and page numbers where the opinions will be found in the bound
volumes of the Ohio Official Reports.
Columbus Southern Power Company, Appellant, v. Public Utilities
Commission of Ohio et al., Appellees.
[Cite as Columbus Southern Power Co. v. Pub. Util. Comm.
(1993), Ohio St.3d .]
Public Utilities Commission -- Conversion of nuclear power
plant to coal-fired facility -- Application for rate
increase -- Review of commission order by Supreme Court
governed by R.C. 4903.13.
(No. 92-1773 -- Submitted June 2, 1993 -- Decided
November 4, 1993.)
Appeal from the Public Utilities Commission of Ohio, No.
91-418-EL-AIR.
In 1969, appellant, Columbus Southern Power Company
("CSP") (formerly Columbus & Southern Ohio Electric Company),
Cincinnati Gas & Electric Company, and Dayton Power & Light
Company entered into a joint venture to construct the William
H. Zimmer Nuclear Power Station ("Zimmer"). Zimmer was to
begin operating in 1975. In November 1982, after numerous
construction delays, the Nuclear Regulatory Commission
suspended all safety-related construction at the site. By
agreement dated January 20, 1984, the joint venturers canceled
the Zimmer project as a nuclear plant and agreed to use their
best efforts to convert Zimmer to a coal-fired facility.
On October 23, 1984, appellee, Public Utilities Commission
of Ohio ("PUCO"), initiated In the Matter of the Restatement of
the Accounts and Records of The Cincinnati Gas & Electric
Company, The Dayton Power & Light Company, and Columbus &
Southern Ohio Electric Company, PUCO No. 84-1187-EL-UNC, to
determine the portion of the capital invested in the Zimmer
project "which may not be used and useful in a converted
coal-fired" plant. On October 1, 1985, the parties to that
proceeding, with the exception of the city of Cincinnati and
the Board of Commissioners of Hamilton County, entered into a
stipulation resolving that issue. The stipulation prohibited
the owner utilities from including a total of $861 million in
existing Zimmer investment in future rate applications. The
city of Cincinnati filed objections to the agreement. After
conducting hearings on the city's objections, the PUCO approved
the stipulation by order of November 26, 1985. No appeal was
taken from that order.
Zimmer was converted to a coal-fired generating unit and
was placed in service beginning March 30, 1991. On April 2,
1991, the owner utilities each filed an application to increase
electric rates in their respective service territories. The
utilities' primary purpose was to receive a return on their
Zimmer investment, which totaled $3.069 billion, exclusive of
the $861 million disallowed by the stipulation. CSP's
jurisdictional share was $845,653,000.
In its application, CSP sought a gross annual revenue
increase of $202,137,000. After making adjustments related to
the Zimmer rate-base valuation, the rate of return, and
rate-case expenses, the PUCO, on May 12, 1992, approved a
revenue increase of $123,022,000, with the portion attributable
to the Zimmer investment phased in over a period of three
years.
On July 2, 1992, the PUCO denied CSP's application for
rehearing on the issues raised in this appeal. The cause is
now before this court upon an appeal as of right.
Marvin I. Resnik, Kevin F. Duffy, James R. Bacha, James L.
Reeves and F. Mitchell Dutton, for appellant.
Lee I. Fisher, Attorney General, James B. Gainer, Duane W.
Luckey, Thomas W. McNamee, William L. Wright, Jeffrey D. Van
Niel and Paul A. Colbert, Assistant Attorneys General, for
appellee.
Vicki Miller, Acting Consumers' Counsel, Michael McCord,
Thomas W. Atzberger, Evelyn R. Robinson-McGriff, Richard W.
Pace, Sr., and Barry Cohen, Associate Consumers' Counsel for
intervening appellee Office of Consumers' Counsel.
Emens, Kegler, Brown, Hill & Ritter, Samuel C. Randazzo
and Richard P. Rosenberry, for intervening appellee Industrial
Energy Consumers.
Chester, Hoffman, Willcox & Saxbe and John W. Bentine, for
intervening appellee Ohio Council of Retail Merchants.
Per Curiam. R.C. 4903.13 governs our review of PUCO
orders. It provides in pertinent part:
"A final order made by the public utilities commission
shall be reversed, vacated, or modified by the supreme court on
appeal, if, upon consideration of the record, such court is of
the opinion that such order was unlawful or unreasonable. ***"
In MCI Telecommunications Corp. v. Pub. Util. Comm.
(1988), 38 Ohio St.3d 266, 268-269, 527 N.E.2d 777, 780, we
interpreted this standard of review:
"Under the 'unlawful or unreasonable' standard specified
in R.C. 4903.13, this court will not reverse or modify a PUCO
decision as to questions of fact where the record contains
sufficient probative evidence to show that the PUCO's
determination is not manifestly against the weight of the
evidence and is not so clearly unsupported by the record as to
show misapprehension, mistake, or willful disregard of duty.
Dayton Power & Light Co. v. Pub. Util. Comm. (1983), 4 Ohio
St.3d 91, 4 OBR 341, 447 N.E.2d 733; Columbus v. Pub. Util.
Comm. (1979), 58 Ohio St.2d 103, 12 O.O.3d 112, 388 N.E.2d
1237. This court does, however, have complete and independent
power of review as to questions of law. Legal issues are,
therefore, subjected to a more intensive examination than are
factual questions. Consumers' Counsel v. Pub. Util. Comm.
(1983), 4 Ohio St.3d 111, 4 OBR 358, 447 N.E.2d 749."
We consider and resolve the six errors alleged by CSP with
these standards in mind.
I. THE PHASE-IN PLAN
It is axiomatic that the PUCO, as a creature of statute,
may exercise only that jurisdiction conferred upon it by the
General Assembly. Dayton Communications Corp. v. Pub. Util.
Comm. (1980), 64 Ohio St.2d 302, 18 O.O.3d 478, 414 N.E.2d
1051; Pike Natural Gas Co.v. Pub. Util. Comm. (1981), 68 Ohio
St.2d 181, 22 O.O.3d 410, 429 N.E.2d 444; Consumers' Counsel v.
Pub. Util. Comm. (1981), 67 Ohio St.2d 153, 21 O.O.3d 96, 423
N.E.2d 820; Werlin Corp. v. Pub. Util. Comm. (1978), 53 Ohio
St.2d 76, 7 O.O.3d 152, 372 N.E.2d 592; Ohio Pub. Interest
Action Group, Inc. v. Pub. Util. Comm. (1975), 43 Ohio St.2d
175, 72 O.O.2d 98, 331 N.E.2d 730.
While the General Assembly has delegated authority to the
PUCO to set just and reasonable rates for public utilities
under its jurisdiction, it has done so by providing a detailed,
comprehensive and, as construed by this court, mandatory
ratemaking formula under R.C. 4909.15. See Gen. Motors Corp.
v. Pub. Util. Comm. (1976), 47 Ohio St.2d 58, 1 O.O.3d 35, 351
N.E.2d 183.
R.C. 4909.15(A) requires the PUCO to make a series of
determinations -- the valuation of the utility's property in
service as of date certain (R.C. 4909.15[A][1]), a fair and
reasonable rate of return on that investment (R.C.
4909.15[A][2]), and the expenses incurred in providing service
during the test year (R.C. 4909.15[A][4]). Once those
determinations are made, the PUCO is required to "compute the
gross annual revenues to which the utility is entitled"
(emphasis added) under division (B) by adding the dollar return
on the company's investment (R.C. 4909.15[A][3]) to the
utility's test year expenses. If the charges under the
utility's existing tariff are insufficient to generate those
revenues, the PUCO is required to fix new rates that will raise
the necessary revenue. R.C. 4909.15(D) provides in part:
"When the public utilities commission is of the opinion,
after hearing and after making the determinations under
divisions (A) and (B) of this section, that any rate *** is, or
will be, unjust, unreasonable *** or that the maximum rates ***
chargeable by any such public utility are insufficient to yield
reasonable compensation for the service rendered, and are
unjust and unreasonable, the commission shall:
"***
"(2) With due regard to all such other matters as are
proper, according to the facts of each case,
"***
"(b) *** fix and determine the just and reasonable rate
*** that will provide the public utility the allowable gross
annual revenues under division (B) of this section, and order
such just and reasonable rate *** to be substituted for the
existing one." (Emphasis added.)
In this case, the PUCO made the determinations required by
division (A) and computed the gross annual revenues in
accordance with division (B). It then found that such revenues
exceeded the revenues generated under CSP's present rate
schedule (by $123,022,000) and, noting the magnitude of the
increase, ordered a three year phase-in of the gross annual
revenue increase associated with the converted Zimmer facility
($117,517,000). Further, the PUCO authorized recovery of the
deferrals created in years one and two of the phase-in over a
ten-year period, with carrying charges.
CSP initially argues that the PUCO ordered phase-in of its
revenue increase violates the statutory formula by denying it
the gross annual revenues to which it has otherwise been found
entitled under R.C. 4909.15(B). The PUCO argues that the "all
such other matters as are proper" language of R.C.
4909.15(D)(2) provides the PUCO with broad discretion to
consider a variety of matters in setting rates, including, as
here, the reasonableness of the magnitude of a one-time
increase.
In the leading case of Consumers' Counsel v. Pub. Util.
Comm. (1981), 67 Ohio St.2d 153, 166, 21 O.O.3d 96, 104, 423
N.E.2d 820, 828, we construed "all such other matters as are
proper" more narrowly: "It is our view that R.C.
4909.15(D)(2)(b) is designed to allow the commission [PUCO] to
make minor adjustments to rates ascertained by the statutory
formula when the criteria upon which the rates are based are
skewed for one reason or another. Thus, under R.C.
4909.15(D)(2)(b), the commission may smooth out anomalies in
the ratemaking equation that tend to make the test year data
unrepresentative for ratemaking purposes."
We have applied this exception to the mandatory ratemaking
formula sparingly, stating in Dayton Power & Light Co. v. Pub.
Util. Comm. (1983), 4 Ohio St.3d 91, 95, 4 OBR 341, 344, 447
N.E.2d 733, 736, that such "ad hoc tinkering with the statutory
formula is [to remain the exception and] not to become the
rule." See, also, Consumers' Counsel v. Pub. Util. Comm.
(1981), 67 Ohio St.2d 372, 21 O.O.3d 234, 424 N.E.2d 300; Ohio
Water Service Co. v. Pub. Util. Comm. (1983), 3 Ohio St.3d 1, 3
OBR 300, 444 N.E.2d 1025 (refusal to find an anomaly); Columbus
v. Pub. Util. Comm. (1984), 10 Ohio St.3d 23, 10 OBR 175, 460
N.E.2d 1117 (the matter precipitating the adjustment had no
basis in the underlying ratemaking statutes). Moreover, we
have applied the exception only to permit recovery of
out-of-test-year expenses in appropriate circumstances, see
Montgomery Cty. Bd. of Commrs. v. Pub. Util. Comm. (1982), 1
Ohio St.3d 125, 1 OBR 163, 438 N.E.2d 111, and Consumers'
Counsel v. Pub. Util. Comm. (1983), 6 Ohio St.3d 412, 6 OBR
459, 453 N.E.2d 590), and have not applied it to adjust the
date certain valuation of rate base items, see Consumers'
Counsel v. Pub. Util. Comm. (1979), 58 Ohio St.2d 449, 12
O.O.3d 378, 391 N.E.2d 311, Consumers' Counsel v. Pub. Util.
Comm. (1981), 67 Ohio St.2d 372, 21 O.O.3d 234, 424 N.E.2d 300,
and Ohio Edison Co. v. Pub. Util. Comm. (1992), 63 Ohio St.3d
555, 589 N.E.2d 1292.
It cannot be seriously argued that the phase-in of CSP's
rates, precipitated by the inclusion of the Zimmer facility in
rate base, falls within the revenue adjustments contemplated by
our 1981 Consumers' Counsel decision at 67 Ohio St.2d 153, 21
O.O.3d 96, 423 N.E.2d 820. Clearly, the PUCO did not order the
"adjustment" (or phase-in) because the Zimmer valuation under
R.C. 4909.15(A)(1) was unrepresentative. Rather, it believed
the result of the computation required under R.C. 4909.15(B) to
be unreasonable on its face. Thus, the lawfulness of the
PUCO's phase-in plan hinges on whether the PUCO has the
authority to reduce, or phase-in, the gross annual revenues
computed under R.C. 4909.15(B) in the absence of anomalies in
the underlying ratemaking criteria.
The PUCO and intervening appellees, Industrial Energy
Consumers et al., argue that such authority is provided by our
decision in Industrial Energy Consumers v. Pub. Util. Comm.
(1991), 62 Ohio St.3d 440, 584 N.E.2d 653. We disagree. In
that case, Columbia Gas of Ohio, Inc. filed an application to
increase the rates of its general service class. Pursuant to a
separate investigation initiated under R.C. 4905.26, the PUCO
determined that the rates of another customer class, special
contract customers (R.C. 4905.31), were generating an earned
rate of return for the company of 44.85 percent. The PUCO
combined its investigation of special contract rates with
Columbia's rate cases (bringing all of the company's revenues
before it) and, in setting rates under R.C. 4909.15(D),
credited the "excess special contract revenues" to the general
service revenue requirement, yielding a rate of return found
appropriate for the company as a whole. The PUCO's use of the
excess special contract revenues to satisfy a portion of the
general service revenue requirement did not reduce, or cause to
be phased in, the annual revenues to which the company was
found entitled under R.C. 4909.15(B) and was required to be
provided under R.C. 4909.15(D)(2)(b). Rather, its order
affected only the source from which those revenues would be
derived and our decision to affirm was consistent with the wide
discretion we have afforded the PUCO on other rate design
issues. See Gen. Motors Corp. v. Pub. Util. Comm., supra (47
Ohio St.2d 58, 1 O.O.3d 35, 351 N.E.2d 183).
The PUCO also argues that it has the authority to order
the phase-in of the company's annual revenue increase under
R.C. 4901.02(A), which provides that "[t]he commission shall
possess the powers and duties specified in, as well as all
powers necessary and proper to carry out the purposes of
Chapters *** 4905., [and] *** 4909. *** of the Revised Code."
The PUCO contends that the purpose of R.C. Chapters 4905 and
4909 is to set just and reasonable rates and that, having
determined the size of the rate increase under the statutory
ratemaking formula to be unreasonable, R.C. 4901.02(A) permits
it to implement rates which will be reasonable.
The comprehensive ratemaking formula provided by the
General Assembly is meant to protect and balance the interests
of the public utilities and their ratepayers alike. Dayton
Power & Light Co. v. Pub. Util. Comm., supra (4 Ohio St.3d 91,
4 OBR 341, 447 N.E.2d 733). We cannot conclude that it was the
General Assembly's intent under the above enabling statute,
R.C. 4901.02(A), to permit the PUCO to disregard that very
formula in instances in which it simply did not agree with the
result. Cf. Consumers' Counsel, supra, 67 Ohio St.3d at 165,
21 O.O.3d at 104, 423 N.E.2d at 828 ("the General Assembly
undoubtedly did not intend to build into its recently revised
[1976] ratemaking formula a means by which the PUCO may
effortlessly abrogate that very formula"). Moreover,
considering the detail with which the General Assembly has
legislated in this area, we find that if it had intended to
grant the PUCO authority to phase-in a utility's annual revenue
increase, it would have specifically provided such a
mechanism. If the PUCO now seeks such authority, its recourse
is through the legislature, and not this court. See Pike
Natural Gas Co., supra (68 Ohio St.2d 181, 22 O.O.3d 410, 429
N.E.2d 244).
We find that pursuant to R.C. 4909.15(B), the PUCO is
required to "compute the gross annual revenues to which the
utility is entitled" under the statutory formula, with limited
exceptions not applicable here, and fix rates under R.C.
4909.15(D)(2)(b) that will "provide" the utility with those
annual revenues. The phase-in plan ordered by the PUCO
deprives CSP of the annual revenues to which it is entitled
during the first two years it is in effect,1 and exceeds the
PUCO's statutory authority. Accordingly, we reverse the PUCO's
determination on this issue.2
We must also consider CSP's request that this court
instruct the PUCO on remand to provide a mechanism to recover
the gross annual revenues already deferred. Intervening
appellees Industrial Energy Consumers et al. argue that such
recovery is prohibited under Keco Industries, Inc. v.
Cincinnati & Suburban Bell Tel. Co. (1957), 166 Ohio St. 254, 2
O.O.2d 85, 141 N.E.2d 465.
In Keco, a consumer brought an action for restitution
after this court's reversal of a PUCO order resulted in lower
rates being set on remand. We held that such action would not
lie because a "utility must collect the rates set by the
commission." Id., 166 Ohio St. at 257, 2 O.O.2d at 86-87, 141
N.E.2d at 468. See R.C. 4905.32. Here, Industrial Electric
Consumers et al. seek to extend that holding to situations
where reversal results in higher rates being set, in order to
prevent utilities from recovering revenues not collected during
the pendency of an appeal. This argument ignores that the
PUCO's initial order in this proceeding specifically authorized
recovery of the deferred revenues in question and, thus, those
revenues constitute a portion of the rates to which CSP is
entitled. Keco is clearly not controlling. Further, CSP's
recovery of the deferred revenues, having been authorized by
the PUCO's initial order, would not violate the proscription
against retroactive ratemaking. See Ohio Edison Co. v. Pub.
Util. Comm. (1978), 56 Ohio St.2d 419, 424-425, 10 O.O.3d 523,
526-527, 384 N.E.2d 283, 286.
Accordingly, we instruct the PUCO to fix rates that
provide CSP the gross annual revenues determined in accordance
with R.C. 4909.15(B) and (D)(2)(b), consistent with this
decision. The PUCO also must provide a mechanism by which CSP
is able to recover those revenues deferred to the time the
order on remand is issued.
II. THE SETTLEMENT
CSP next argues that the rate-base disallowances by the
PUCO related to nuclear fuel, nuclear wind-down costs, and
allowance for funds used during construction violated the terms
of the 1985 stipulation which it had approved. The stipulation
provided in pertinent part:
"15. The [commission's] Staff and the parties to this
proceeding did engage in extensive settlement discussions with
the Owners and, as a consequence, the following agreements have
been reached by the Owners and the other parties hereto
[except, as relevant to this case, the city of Cincinnati],
which they recommend that the PUCO adopt as the final
resolution of the above captioned proceeding.
"A. The sum of $861,000,000.00 and any Allowance for
Funds Used During Construction accrued on such sum since
January 31, 1984, (the 'Disallowed Amount') shall be disallowed
[i.e., not included in future rate requests].
"***
"F. In the event that the Owners determine to go forward
with the construction of the converted 1300 MW coal-fired
Zimmer facility and the same is completed and brought into
service, there is agreement that the sunk costs remaining as of
January 31, 1984 after the total Disallowed Amount (including
AFUDC properly accrued thereon subsequent to January 31, 1984)
will not be challenged by any of the parties hereto as being:
(1) the result of mismanagement and/or (2) not being used and
useful in the converted Zimmer facility.
"G. In addition, it is understood and agreed that all of
the non-Owner parties hereto, while expressing no position with
respect to the prudence of the Owners' decisions to use their
best efforts to convert Zimmer to a 1300 MW coal-fired plant,
reserve the right to challenge the reasonableness of any
decision made subsequent to the decision to cancel Zimmer as a
nuclear facility in any future proceedings before the
commission."
A. Allowance For Funds Used During Construction ("AFUDC")3
In its application to increase electric rates, CSP sought
recovery of AFUDC on the remaining Zimmer sunk costs(costs
remaining after the disallowance) from February 1, 1984, to the
plant's completion in March 1991. Several intervenors, who
were signatories to the 1985 stipulation, argued that under
paragraph 15(F) of the stipulation, AFUDC was not "properly
accrued" from February 1984 through February 1987 because
construction of the converted Zimmer facility was "interrupted"
during that period, pending receipt of a construction permit
from the U.S. Army Corps of Engineers (issued March 17, 1987).
The PUCO agreed in part with the intervenors and deducted from
CSP's proposed rate base valuation the AFUDC accrued from
February 1984 until March 1986, the point at which the PUCO
decided sufficient construction activity had commenced. In
reaching this decision the PUCO relied on FERC (Federal Energy
Regulatory Commission) Accounting Release AR-5 (Revised),
effective January 1, 1968, which provides in part:
"Interest during construction may be capitalized starting
from the date that construction costs are continuously incurred
on a planned progressive basis. *** No interest should be
accrued during period [sic] of interrupted construction unless
the company can justify the interruption as being reasonable
under the circumstances." (Emphasis added.)
CSP argues that the AFUDC accrued from February 1984 to
the plant's completion is not subject to challenge in this
proceeding. It reasons that the intent of the parties in
entering the 1985 stipulation was to resolve all issues related
to the nuclear Zimmer facility; that paragraph 15(F)
specifically permits AFUDC on the sunk costs remaining as of
January 31, 1984; and that the PUCO recognized as much in its
order of November 26, 1985 approving the stipulation when it
stated that the "settlement represents an opportunity to put
nuclear Zimmer behind us" and "closes the chapter on nuclear
Zimmer." (Case No. 84-1187-EL-UNC.) As such, CSP argues that
the "properly accrued" language in the 1985 stipulation should
be construed as permitting challenges only to the mathematical
accuracy of the accrual calculations.
We find no basis to construe the stipulation so narrowly.
While it is true that the stipulation and order approving it
intended to put to rest nuclear valuation issues, they did so
as of a specific point in time, January 31, 1984. While the
stipulation clearly permits recovery of AFUDC on the sunk costs
remaining as of that date, it just as clearly conditions such
recovery upon their subsequent proper accrual. We construe
that language to mean that the PUCO must review the accruals
pursuant to applicable accounting conventions, and not simply
for mathematical accuracy. To hold otherwise would be contrary
to the general intent of the stipulation that costs incurred
after January 31, 1984 are subject to challenge in succeeding
PUCO proceedings.
We now turn to the question of whether the AFUDC accruals
between February 1984 and March 1986 were proper under FERC
AR-5. There is little doubt that construction of the Zimmer
facility was interrupted when the Nuclear Regulatory Commission
("NRC") halted safety-related construction in November 1982.
As much is confirmed by an internal American Electric Power
Service Corporation memorandum, dated December 19, 1983, which
states that "[a]t Zimmer, the NRC ordered virtually all
construction stopped pending a determination as to the work
necessary to complete the plant properly."
Finding first that CSP did not carry its burden of showing
the 1982 interruption to be reasonable,4 the PUCO then
determined that construction did not commence on the converted
Zimmer facility on a "planned progressive basis" until major
construction contracts were awarded in February 1986. CSP
argues that construction was occurring on a planned progressive
basis at the facility during the period from February 1984
through February 1987, and points to its witness's testimony
that construction activities during that timeframe consisted of
project planning and scheduling, engineering, design and
procurement, site investigation, licensing and permitting, site
construction activities, and existing facility modifications
and maintenance.
In its order, the PUCO discounted these activities,
finding that many were not construction specific or had
occurred after February 1986. Further, the PUCO noted that the
owner utilities announced on January 20, 1984 their decision to
abandon Zimmer as a nuclear facility, and that they made only a
qualified decision to convert the facility to a coal-fired
plant on August 1, 1984, contingent upon satisfying financial,
regulatory, and environmental concerns. Moreover, the record
reflects that at the time the 1985 stipulation was approved,
the owners had not yet decided to go forward with the
construction of the converted Zimmer facility.
The point at which construction of the converted facility
began on a planned and progressive basis is a question of
fact. The PUCO's determination that construction had not
commenced sufficiently to warrant the accrual of AFUDC until
March 1986, was not "manifestly against the weight of the
evidence and is not so clearly unsupported by the record as to
show misapprehension, mistake, or willful disregard of duty."
MCI Telecommunications, supra (38 Ohio St.3d 266, 527 N.E.2d
777). Accordingly, we affirm the PUCO on this issue.
B. Nuclear Fuel Expense and Nuclear Wind-down Costs
The PUCO also reduced CSP's proposed rate-base valuation
by amounts related to nuclear fuel expense and "nuclear
wind-down costs" (costs incurred after January 31, 1984 for
obligations related to the construction of Zimmer as a nuclear
facility). As above, CSP argues that the intent of the 1985
stipulation was to resolve all nuclear-related issues and
contends that these disallowances were written off as a part of
the $861 million disallowance provided for in paragraph 15(A)
of the stipulation. We disagree.
We have already found that the stipulation was
crafted with regard to the specific date of January 31,
1984. The record shows that neither the nuclear fuel
nor the nuclear wind-down costs were included in the Zimmer
investment considered as of that date by the parties.
Accordingly, we agree with the PUCO and ascribe no intent
to the parties that these amounts were to be disallowed
under paragraph 15(A) or included in the sunk cost not
subject to challenge in paragraph 15(F). Because these
items cannot be regarded as used and useful in a converted
Zimmer facility, the PUCO properly excluded them from rate
base in this case.
III. CONFISCATION
CSP also argues that the PUCO's order resulted in a
confiscation of its property in violation of the Fifth and
Fourteenth Amendments to the United States Constitution. It
bases its claim upon the revenues it will be deprived of as a
result of the phase-in plan and its inability to earn a return
on the rate-base items (AFUDC, nuclear fuel, and nuclear
wind-down costs) disallowed by the PUCO. Our reversal of the
PUCO's phase-in plan renders CSP's claim of confiscation on
that basis moot. Further, because the rate-base items were
properly excluded under the statutory ratemaking formula and,
therefore, CSP is not entitled to any return on these items,
the PUCO's ruling was not confiscatory. See Dayton Power &
Light Co. v. Pub. Util. Comm. (1983), 4 Ohio St.3d 91, 4 OBR
341, 447 N.E.2d 733.
IV. ELECTRIC POWER RESEARCH INSTITUTE DUES
In its application, CSP sought recovery of $2,727,583 in
estimated membership dues associated with its proposal to join
the Electric Power Research Institute ("EPRI") in the future.
To support its request, CSP presented a witness who generally
extolled the benefits of membership, acknowledging that it
would enhance CSP's research and development efforts to the
benefit of the utility and its consumers alike. The witness
further testified that CSP had been considering joining EPRI
for a number of years, but could not explain why it had not
done so in 1990, just prior to the test year, recognizing that
PUCO precedent permitted recovery of the membership dues.
The PUCO denied CSP's request as an improper
out-of-test-year expense. See Columbus v. Pub. Util. Comm.
(1984), 10 Ohio St.3d 23, 25, 10 OBR 175, 177, 460 N.E.2d 1117,
1120 (There is a "strong presumption that only expenses
incurred during the test year may be included in awarding a
rate increase."). The PUCO further found, considering CSP's
evidence regarding the benefits of membership, that the failure
to join EPRI constituted an unreasonable practice and, as a
result, made an unquantified downward adjustment to CSP's
return on equity. The PUCO stated that it "strongly
encourages" and "expects" CSP to join EPRI. It also ordered
CSP "to demonstrate in its next long-term forecast filing that
it has joined EPRI. If the company does not do so, then the
Commission will use its authority pursuant to Section 4909.154,
Revised Code, to remedy the company's unreasonable practice."
CSP does not contest the PUCO's disallowance of this
proposed post-test-year expense. Instead, it characterizes the
PUCO's above statements as an "order" that it join EPRI and
argues that such an order unlawfully interferes with CSP's
managerial discretion. See Elyria Tel. Co. v. Pub. Util. Comm.
(1953), 158 Ohio St. 441, 448, 49 O.O. 391, 394, 110 N.E.2d 59,
63 ("The Public Utilities Commission is a creature of statute.
*** Its powers do not include the right to manage utilities or
dictate their policies."). See, also, R.C. 4909.154
(commission may only recommend management policies on
management practices to the public utility).
We agree that the PUCO is without power to order CSP to
join EPRI. Id. However, we refuse to characterize the
language used by the PUCO in this instance as an "order".
Rather, it is more properly construed as a warning that if CSP
does not join EPRI, it will be subject to possible
disallowances in future rate proceedings. The decision whether
to join EPRI or suffer the possible consequences rests squarely
with CSP. Having so found, we need not address CSP's
alternative argument that, if the "order" is deemed lawful, the
PUCO must allow CSP's recovery of the estimated membership dues.
CSP also argues that R.C. 4909.154 provides the only means
by which the PUCO may make adjustments for imprudent management
decisions and that the downward adjustment to its return on
equity constitutes an unlawful circumvention of the ratemaking
statutes. We disagree.
It is fundamental that a utility's management practices be
considered when setting its authorized rate of return. See,
e.g, Bluefield Water Works & Improvement Co. v. Pub. Serv.
Comm. of W.Va. (1923), 262 U.S. 679, 693, 43 S.Ct. 675, 679, 67
L.Ed. 1176, 1183 ("The return should be reasonably sufficient
to assure confidence in the financial soundness of the utility
and should be adequate, under efficient and economical
management, to maintain and support its credit and enable it to
raise the money necessary for the proper discharge of its
public duties."). As such, the PUCO's broad authority to fix a
fair and reasonable rate of return under R.C. 4909.15(A)(2)
provides an independent source of authority for the PUCO to
consider a utility's management practices. Cf. Babbit v. Pub.
Util. Comm. (1979), 59 Ohio St.2d 81, 13 O.O.3d 67, 391 N.E.2d
1376.
Customarily, as here, the PUCO employs the discounted cash
flow methodology in calculating a utility's cost of common
equity. Recognizing the inherent imprecision in fixing a
return on equity, a range is developed (here, 11.63 to 12.74
percent) and any point therein is considered reasonable -- a
principle which CSP does not contest. It is when considering
what point within the range should be adopted that the PUCO
considers the company's management practices, as well as other
matters. See Cincinnati Bell Tel. Co. v. Pub. Util. Comm.
(1984), 12 Ohio St.3d 280, 12 OBR 356, 466 N.E.2d 848. In this
case, the PUCO considered several of CSP's management practices
that supported selection of a return above the midpoint of the
range, and several factors (specifically, CSP's failure to join
EPRI and lack of commitment to demand side management) that
supported the adoption of a return below the midpoint.
Considering all of these factors, and without quantifying the
effects of any, the PUCO selected a return on equity at the
third quartile of the range (12.46 percent). Because we do not
find unlawful the PUCO's determination that CSP's failure to
join EPRI constituted an unreasonable management practice, we
likewise cannot find the PUCO's cost of equity adjustment to be
unreasonable.
V. RATE CASE EXPENSE
Finally, CSP contends that the PUCO erred by disallowing
the legal fees CSP incurred in defending its right to place its
proposed rates in effect under R.C. 4909.42. We agree.
R.C. 4909.42 provides that if the PUCO does not issue an
order in a utility's rate case within two hundred seventy-five
days of its filing of the application to increase rates, the
utility may, as an interim measure, place in effect the rates
proposed in its application without the PUCO's approval. In
this proceeding, the two-hundred seventy-five day limit expired
before the PUCO had begun hearings on CSP's rate application
and CSP notified the PUCO on December 9, 1991 of its intent to
place its proposed rates in effect. In an accounting order,
the PUCO, sua sponte, attempted to avert CSP's action by
authorizing it to defer certain current expenses for recovery
in its next rate case, finding that such deferrals were all
that was "necessary" to compensate shareholders until the PUCO
issued its order in this proceeding. Nevertheless, CSP elected
to pursue its rights under R.C. 4909.42. Various intervenors
subsequently filed suit in the Franklin County Court of Common
Pleas seeking a declaratory judgment that R.C. 4909.42 is
unconstitutional and a permanent injunction preventing CSP from
charging the interim rates. See State ex rel. Columbus So.
Power Co. v. Sheward (1992), 63 Ohio St.3d 78, 585 N.E.2d 380;
O'Brien v. Columbus So. Power Co. (1992), 73 Ohio App.3d 355,
597 N.E.2d 188.
The PUCO authorized, as "ordinary and necessary" operating
expenses, CSP's recovery of legal fees associated with the
prosecution of this case before the PUCO and recovery of the
legal fees associated with an unsuccessful alternative dispute
resolution process conducted by an independent private entity
prior to hearing. However, the PUCO denied recovery of the
legal fees CSP incurred in defending its right to place its
proposed rates in effect under R.C. 4909.42, reasoning that it
had already found such action "unnecessary" in its previous
accounting order.
We find the PUCO's focus on whether it was necessary for
CSP to place its proposed rates in effect to be misplaced. The
General Assembly has granted utilities the unequivocal right to
do so under R.C. 4909.42 without the PUCO's consent or
interference. See Sheward, supra, at 80, 585 N.E.2d at 382,
fn. 3. The appropriate inquiry is whether legal fees are
ordinary and necessary expenses in obtaining rate relief as
provided by law. On this basis, we have upheld the PUCO's
inclusion of this expense on many occasions and have generally
deferred to its discretion in quantifying the level of the
expense when unclear on the record. See, e.g.,Cincinnati v.
Pub. Util. Comm. (1950), 153 Ohio St. 56, 41 O.O. 129, 90
N.E.2d 681; Cleveland v. Pub. Util. Comm. (1980), 63 Ohio St.2d
62, 17 O.O. 3d 37, 406 N.E.2d 1370; Canton v. Pub. Util. Comm.
(1980), 63 Ohio St.2d 76, 17 O.O.3d 46, 407 N.E.2d 9. Here,
however, there is no dispute as to whether the amount of the
legal fees was reasonable. Having allowed recovery of legal
expenses incurred to obtain rate relief in proceedings before
the PUCO and to obtain rate relief through the alternative
dispute resolution process (even though unsuccessful), we find
it unreasonable to deny recovery of the expenses incurred to
obtain timely rate relief through R.C. 4909.42. Accordingly,
the PUCO's determination on this issue is reversed.
Order affirmed in part,
reversed in part, and cause
remanded to the PUCO for
further action in accordance
with this opinion.
Moyer, C.J., A.W. Sweeney and Wright, JJ., concur.
Douglas, J., concurs separately.
Resnick, F.E. Sweeney and Pfeifer, JJ., dissent.
FOOTNOTES
1 So finding, we reject the PUCO's argument that CSP has
not been prejudiced by the phase-in plan because of its ability
to defer on its books and ultimately collect the revenues
foregone in the first two years of the plan, with carrying
charges. Cf. Alabama Power Co. v. Alabama Pub. Serv. Comm.
(Ala. 1980), 390 So. 2d 1017, 1027 ("There is no authority
found in the statutes that permits the Commission to phase in a
rate increase. *** If the Commission determines a utility has a
rate deficiency, it has a duty to remedy that deficiency. The
fact that the Commission's order will eventually remedy an
existing deficiency does not validate the order." [Emphasis
sic.])
2 Having found that the PUCO is without authority to
order the phase-in of a utility's annual revenues, we need not
address CSP's alternative proposition of law that this
particular phase-in plan is unlawful in that it authorizes a
post-date-certain reduction to the established Zimmer
valuation.
3 AFUDC is an accounting mechanism by which utilities
recognize the capital costs associated with financing
construction. These costs include interest on borrowed funds
as well as the cost of equity capital, and are booked as part
of the value of the asset during construction, and are
subsequently recognized in rates when the asset is included in
rate base. See Consumers' Counsel v. Pub. Util. Comm. (1983),
6 Ohio St.3d 377, 6 OBR 428, 453 N.E.2d 673.
4 On appeal, CSP does not contest the PUCO's finding that
it has failed in its burden. However, Cincinnati Gas &
Electric Co., in its companion appeal decided this date,
Cincinnati Gas & Electric Co. v. Pub. Util. Comm. (1993),
Ohio St.3d , N.E.2d , argues that the interruption
was reasonable because it was ordered by the NRC. The PUCO did
not accept this justification in either CSP's or CG&E's cases
below. Certainly, the NRC order precipitated the interruption
and it was reasonable for the companies to obey that order; but
that does not, in and of itself, justify an interruption of
meaningful construction for a period of over three years.
Indeed, there is nothing in the record before us to refute that
the continued interruption resulted from nothing more than the
companies' indecision on whether to convert the facility.
Accordingly, we affirm the PUCO's finding.
Douglas, J., concurring. I concur. I write separately
to express my concerns over the continued unchallenged validity
and the majority's reference to the so-called proscription
against retroactive ratemaking. The majority says that "* * *
CSP's recovery of the deferred revenues, having been authorized
by the PUCO's initial order, would not violate the proscription
against retroactive ratemaking." This is, of course, flexuous
reasoning -- at best.
Retroactive ratemaking is a long-recognized rule of public
utility regulation. This rule, court recognized, in general
restricts the right or ability of the Public Utilities
Commission to permit a public utility to recover past losses
through future rates and, also prevents refunds to consumers of
profits of a utility which are subsequently found to have been
excessive. Thus, when the commission hears and determines a
rate case, the commission may only look to the future in
determining appropriate utility rates. This is because of the
so-called rule against retroactive ratemaking.
Through the procedures used, the ratemaking process is
prospective in nature. Utilities file with the commission
proposed new rates and the commission enters an order fixing
the rates to be charged in future years. Then, more often than
not, an appeal (by some principal or intervening party) is
taken and if this court reverses the rate order, the case is
remanded to the commission to again set the rates and this,
again, is prospective in nature. Oftentimes, this process goes
on for years (the case at bar commenced in 1984), and,
regardless of the eventual outcome, the cost to all parties is
enormous.
A number of courts across the country (including this
court in today's decision), while paying lipservice to the
rule, have found ways to create necessary exceptions to the
rule to compensate for utility costs created by (1) utility
commissions' changes in accounting methodology; (2) rate orders
containing mistakes; (3) losses occasioned by emergency weather
conditions (ice storms and other storms like the recent one in
Cleveland); (4) revenue loss during periods of rate
proceedings, appeals and remands for new orders after court
review; and (5) nuclear plant cancellation. Apparent slavish
adherence to the rule, making it an absolute of ratemaking, has
been something less than that in practice as courts continue to
create exceptions to the rule. These exceptions are
necessitated by the demands of modern-day utility regulation
operating under very old (and maybe archaic) laws, rules and
regulations. A product of all this is regulatory lag and
seemingly continuous and endless rate proceedings.
Since there seem to be no specific sections of the Revised
Code which prohibit the commission from retroactive ratemaking,
the genesis of the rule is obviously judicial rather than
legislative. I write now only to suggest that perhaps the time
has come for the General Assembly, the commission and/or this
court to meet modern-day utility regulation with new and
innovative thinking. This is not to say that the ratemaking
process should be ever in a state of flux. Reliability is not
only desirable -- it is essential in our ratemaking system.
However, the rule that utility rates must be permanent and can
only be changed prospectively may not provide the flexibility
we need to meet the modern needs of both consumers and
utilities.
I only suggest herein that maybe the time has come for us
not to apply the retroactive ratemaking rule so absolutely. It
is fair that both the commission and this court apply the rule
with a presumption that it is valid in a given case, but we
should review the facts of each case to determine whether the
presumption should apply or has, for good reason, been
effectively rebutted. Applying the rule only as a presumption
would afford the commission and this court the flexibility of
allowing retroactive relief for any number of reasons,
including the period of time while a case is on appeal and
during the remand period after reversal, as here, of a rate
order.
"That court best serves the law which recognizes that the
rules of law which grew up in a remote generation may in the
fullness of experience be found to serve another generation
badly, and which discards the old rule when it finds that
another rule of law represents what should be according to the
established and settled judgment of society, and no
considerable property rights have become vested in reliance
upon the old rule. It is thus great writers upon the common
law have discovered the source and method of its growth, and in
its growth found its health and life. It is not and it should
not be stationary. * * *" Dwy v. Connecticut Co. (1915), 89
Conn. 74, 99, 92 A. 883, 891 (Wheeler, J, concurring).
The results of today's decision will be devastating to
many. Unfortunately, that is sometimes the case when the
result, as here, is driven and dictated by the law. Must it
always be so in public utility rate cases? There must be a
better way! However, I submit, we do not seek possible new and
better ways when we remain totally satisfied with what has gone
on before and by rote say we are not ignoring the rule against
retroactive ratemaking -- while doing just that.
While I concur in the judgment of the majority, I do so
with the hope that this suggestion, with regard to the rule
against retroactive ratemaking, will promote legislative and
commission inquiry, scholarly academic writing and discussion,
and generally enlightened dialogue. Meanwhile, for us to say
we are not violating the rule against retroactive ratemaking,
when in fact we really are, does a disservice, I believe, to
consumers, utilities, the Public Utilities Commission, the
bench and the bar.
Pfeifer, J., dissenting. I would read the "all such
other matters as are proper" clause in R.C. 4909.15(D)(2) as
being broad enough in its scope to authorize the action
undertaken by the Public Utilities Commission of Ohio ("PUCO")
to implement a three-year staggered rate increase. The record
indicates ample evidence supporting the compelling public
policy reasons for the approach taken by the PUCO. Rate shock
can be disastrous not only for the family budget, but also for
Ohio's business climate.
The PUCO, however, has no statutory authority to revoke its
own prior stipulations when they are retrospectively
regretted. The PUCO's own words in its November 26, 1985 order
are unquivocal: "[The] settlement represents an opportunity to
put nuclear Zimmer behind us***[and] closes the chapter on
nuclear Zimmer." (PUCO case No. 84-1187-EL-UNC, 11-12.) These
words memorialize a promise by the PUCO not to further contest
the inclusion in the ratebase of accrued AFUDC, nuclear fuel
expenses, and for nuclear wind-down costs.
A deal's a deal. It is regrettable that a state agency,
which entered into this agreement on behalf of the public in an
effort to encourage utility companies to build new, safer, more
efficient generating facilities, now exhibits bad faith by
renouncing its covenant not to contest once the project was
completed.