Opinion

Day Island Yacht Club v. City of University Place

Court
District Court, W.D. Washington
Filed
Aug 22, 2025
Cited by
0 cases
Authority
More cited than 38.9%

res judicata does not bar claims for aggravation occurring after date 19 of final order

How later courts described this case

  • res judicata does not bar claims for aggravation occurring after date 19 of final order

Written by the judges who cited it.

The opinion

1

2

3

4

5

UNITED STATES DISTRICT COURT

6 WESTERN DISTRICT OF WASHINGTON

AT TACOMA

7

DAY ISLAND YACHT CLUB, CASE NO. 3:23-cv-5652

8

Plaintiff, ORDER DENYING MOTIONS FOR

9 SUMMARY JUDGMENT

v.

10

CITY OF UNIVERSITY PLACE and

11 CITY OF TACOMA,

12 Defendants.

13

CITY OF TACOMA,

14

Cross-Claimant,

15

v.

16

CITY OF UNIVERSITY PLACE,

17

Cross-Defendant.

18

19 1. INTRODUCTION

20 This Clean Water Act (CWA) citizen suit presents competing summary

21 judgment motions about whether the municipal defendants have violated their

22 obligations in connection with the Day Island Bridge Pond, a waterbody referred to

23 throughout the pleadings as the “Pond.” Plaintiff Day Island Yacht Club (“Yacht

1 Club”) alleges that Defendants City of University Place and City of Tacoma failed to

2 maintain the Pond as a stormwater facility, resulting in sediment discharge into

3 navigable waters. Dkt. No. 27 ¶¶ 50–56, 74–83. Tacoma also brings crossclaims

4 against University Place for trespass and public nuisance. Dkt. No. 58 ¶¶ 5–15.

5 University Place moves for summary judgment on all claims, arguing that

6 the Pond falls outside its federal water discharge permit coverage, that procedural

7 defenses bar the claims, and that res judicata precludes relitigating issues resolved

8 in a 1990 state court action. Dkt. No. 71. Tacoma seeks summary judgment against

9 Yacht Club, contending it has satisfied its permit coordination requirements and

10 that its permit prohibits maintenance activities in natural wetlands. Dkt. No. 68.

11 The motions turn on contested factual questions about the nature and

12 purpose of the Pond, whether it satisfies the technical criteria for wetland

13 designation, and whether Tacoma’s coordination efforts satisfy its permit

14 requirements. While the parties present competing expert opinions and technical

15 evidence on these issues, genuine disputes of material fact preclude resolution on

16 summary judgment. The Court therefore DENIES both motions for summary

17 judgment. Dkt. Nos. 68, 71.

18

2. BACKGROUND

19

This case has a lengthy factual history, and many parts of the record are in

20

dispute. The Court does not provide a comprehensive statement of facts, but instead

21

recounts background facts relevant to Defendants’ motions for summary judgment

22

construed in the light most favorable to Yacht Club.

23

1 2.1 The Pond operates within a cross-boundary drainage system subject

to federal permit requirements.

2

The Pond1 is located at the downstream end of the Day Island Waterway

3

Basin (“DIW Basin”), a 480-acre drainage area consisting primarily of residential

4

and commercial development. Dkt. No. 78-2 at 15–16. The Pond, as it exists today,

5

straddles the municipal boundary between Tacoma and University Place, with most

6

of it located on Tacoma-owned property and a smaller portion on University Place

7

land. Dkt. Nos. 70-6; 70-7.

8

Stormwater and suburban run off from the DIW Basin drains northward

9

through storm sewers, culverts, and detention ponds to a storm sewer that runs

10

along 27th Street West, growing from 24 inches to 36 inches in diameter towards

11

the lower portion of the DIW Basin alongside Day Island Bridge Road and Lemons

12

Beach Road West. Dkt. No. 78-2 at 15–16. Water leaving the Pond discharges

13

through twin 36-inch culverts into the Day Island Lagoon and marina facilities

14

owned by Yacht Club located at 2120 91st Avenue West, University Place

15

(“Marina”). Id. at 9, 15–16.

16

Yacht Club, comprised of around 375 members, provides docking and

17

moorage facilities for its members’ boats, and owns both the real property at the

18

Marina and the abutting saltwater tidelands at Day Island Lagoon. Dkt. No. 27 ¶

19

13.a–13.b. According to Yacht Club, sediment discharged from the Pond has

20

21 1 The parties dispute whether this area is a “pond” or is more accurately

characterized as a natural wetland or estuary. Because the Court must view the

22 facts in the light most favorable to the non-moving party on summary judgment, it

adopts Plaintiff’s nomenclature for purposes of this order without making any legal

23 determination regarding the area’s actual nature or classification.

1 negatively interfered with its moorage operations, boat navigation within its

2 tidelands, and safe use by its members. Id. ¶ 14.

3 Both municipalities operate stormwater systems under federal discharge

4 permits issued by the National Pollutant Discharge Elimination System (NPDES),

5 which is a permitting program under the Clean Water Act. University Place

6 operates under a Phase II Municipal Stormwater NPDES Permit (“UP NPDES

7 Permit”) covering small Municipal Separate Storm Sewer Systems, so called

8 “MS4s,” while Tacoma operates under a Phase I Municipal Stormwater NPDES

9 Permit (“Tacoma NPDES Permit”). Dkt. No. 27 ¶¶ 11.b., 12.b.

10 University Place received Phase II permit coverage in January 2007 that

11 required development of a Stormwater Management Program (“SWMP”) to

12 establish requirements for its MS4. Id. ¶¶ 51, 53. The UP NPDES Permit requires

13 maintenance when accumulated sediment exceeds ten percent of the designed pond

14 depth. Id. ¶ 53. Yacht Club alleges that the Pond constitutes a small MS4 under

15 University Place’s permit that has exceeded the ten percent sediment threshold,

16 causing increased discharge into Day Island Lagoon. Id. ¶¶ 54–56.

17 As to Tacoma, Yacht Club alleges that Tacoma’s Phase I permit requires

18 coordination with University Place to prevent sediment discharge from the cross-

19 boundary Pond area. Id. ¶ 81. The parties dispute whether the Pond constitutes

20 part of University Place’s regulated MS4 system and what coordination obligations,

21 if any, apply to the Pond.

22

23

1 2.2 The parties previously litigated stormwater issues in the 1990s.

This is not the first time the parties have litigated issues related to the Day

2

Island Bridge Pond. In 1990, Yacht Club sued Pierce County and Tacoma in state

3

court, alleging inverse condemnation based on harmful stormwater discharges onto

4

Yacht Club’s property. See Day Island Yacht Club v. Pierce Cnty. City of Tacoma &

5

City of University Place, No. 90-2-00308-1 (Pierce Cnty. Sup. Ct. 1990). After

6

University Place’s incorporation in 1995, Yacht Club added the city as a defendant

7

in the case. Dkt. No. 71 at 4. The suit resolved in January 1997 through an accepted

8

Offer of Judgment that included money damages. Dkt. Nos. 27 ¶ 23 n.1; 71 at 4. As

9

part of the resolution of this lawsuit, the municipalities exchanged correspondence

10

regarding future maintenance responsibilities. University Place’s understanding

11

was that “Tacoma has . . . agreed to grant to the City of University Place whatever

12

easements or rights of way are necessary to [construct] a maintenance road for the

13

27th Street improvements.” Dkt. No. 71-5 at 4. However, the parties dispute the

14

scope and duration of any permission granted.

15

16

2.3 The parties dispute the Pond’s origins and development.

17 The parties dispute the Pond’s history. According to Yacht Club, Pierce

18 County installed a 36-inch storm pipe and a settling pond downstream from the

19 Marina in the same area as the Pond in the mid-1980s. Dkt. Nos. 70-23 at 7, 9; 71-7

20 at 11–13; 80-4 at 2. As a result, Yacht Club witnessed a surge in sediment flow into

21 the Pond area and Day Island Lagoon, which prompted the 1990 litigation. Dkt. No.

22 71-7 at 11–13.

23

1 In 1998, Tacoma and University Place entered an Interlocal Agreement

2 dividing responsibility for maintaining shared rights-of-way with University Place

3 assuming jurisdiction for the entire 27th Street West corridor. Dkt. No. 70-4 at 2.

4 Gary Cooper, University Place’s Public Works Superintendent from 1995 to 2022,

5 testified during his deposition that “when you’re maintaining the entire right-of-

6 way, that’s not only the pavement and the shoulder and the signs but also any

7 storm drain that may be in there,” and extended to maintaining the Pond and

8 Lemons Beach Road. Dkt. No. 80-6 at 38–39.

9 In 1999, University Place contracted with engineers for the “27th Street

10 Detention Pond Repair” and “Stormwater Project—27th Street Detention Pond,”

11 involving retrofitting the Pond. Dkt. No. 80-11 at 2–9. The projects included

12 constructing a berm—a raised area of land—in the northern end of the Pond to

13 prevent tidal backflow and excavating soil and sediment below the 36-inch outlet

14 pipe upstream of the pipes that discharge into the Day Island Lagoon. Dkt. Nos. 78-

15 2 at 11; 80-12.

16 University Place obtained a shoreline substantial development permit

17 (SSDP) for the project in April 2001, Dkt. No. 80-13 at 3–6, and that same month,

18 received approval from the Army Corps of Engineers to go forward without a federal

19 permit after representing that improvements were occurring in an “existing storm

20 pond” to “improve water quality.” Dkt. No. 80-14 at 14–16. According to Cooper’s

21 testimony, University Place built the project to the specifications prepared by its

22 engineers and retrofitted the Pond. Dkt. No. 80-6 at 78–79.

23

1 University Place and Tacoma dispute this characterization of the Pond.

2 Defendants cite a Washington Department of Ecology determination that the area

3 is a “historic wetland estuary for Day Creek” that “serves no stormwater purpose”

4 and is not a constructed stormwater treatment facility. Dkt. No. 71-6 at 54–56.

5 Yacht Club challenges the admissibility of this “determination.”

6

2.4 Tacoma challenged University Place’s maintenance authority in

2019.

7

In Spring 2019, University Place cut some trees in the Lemons Beach Road

8

and 27th Street right-of-way. Dkt. No. 71-6 at 24. Tacoma Environmental Services

9

Department responded by letter to Cooper requesting that University Place “no

10

longer maintain the section of Lemons Beach Road located within the City of

11

Tacoma limits excluding the maintenance and care associated with the

12

. . . [designated] tree replanting and 3-year maintenance period.” Id. Cooper replied

13

that University Place remained willing to maintain the area but recommended an

14

on-site meeting to “make sure [they were] all on the same page for the future.” Dkt.

15

No. 80-17 at 2. Several months later, in December 2019, Tacoma requested

16

information from University Place about the Pond, but when Cooper sought

17

clarification about what records were needed, Tacoma failed to follow up and no

18

clear agreement between the cities was reached. Dkt. No. 80-6 at 130–31.

19

The parties dispute the legal effect these exchanges had on University Place’s

20

maintenance obligations and Tacoma’s permit compliance.

21

22

23

1 2.5 The current litigation involves federal and state-law claims.

Yacht Club alleges that both municipalities violated the Clean Water Act by

2

allowing sediment discharge into navigable waters. Against University Place, Yacht

3

Club claims the Pond is part of University Place’s MS4 that requires maintenance

4

under its Phase II NPDES permit. Dkt. No. 27 ¶¶ 54–56. Against Tacoma, Yacht

5

Club alleges violations of coordination requirements and direct maintenance

6

obligations under Tacoma’s Phase I NPDES permit. Id. ¶¶ 75–81.

7

Yacht Club seeks declaratory judgment, injunctive relief requiring Pond

8

maintenance, civil penalties, and attorney’s fees under 33 U.S.C. § 1365(d). Id. at

9

36. Tacoma brings crossclaims against University Place for trespass and public

10

nuisance, alleging University Place “continued to operate the Day Island Bridge

11

Pond as part of its stormwater infrastructure on Tacoma’s property for at least

12

twenty-five years from 1995-2019.” Dkt. No. 58 ¶ 8.

13

14

3. DISCUSSION

15

3.1 Legal standard.

16 “[S]ummary judgment is appropriate when there is no genuine dispute as to

17 any material fact and the movant is entitled to judgment as a matter of law.”

18 Frlekin v. Apple, Inc., 979 F.3d 639, 643 (9th Cir. 2020) (citation omitted). A dispute

19 is “genuine” if “a reasonable jury could return a verdict for the nonmoving party,”

20 and a fact is material if it “might affect the outcome of the suit under the governing

21 law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). When considering a

22 summary judgment motion, courts must view the evidence “in the light most

23

1 favorable to the non-moving party.” Barnes v. Chase Home Fin., LLC, 934 F.3d 901,

2 906 (9th Cir. 2019) (internal citation omitted).

3

3.2 University Place’s motion for summary judgment against Yacht Club.

4

University Place advances multiple grounds for summary dismissal,2

5

including procedural defenses and a substantive challenge to the scope of its

6

NPDES permit obligations. The Court addresses whether Yacht Club satisfied the

7

Clean Water Act’s pre-suit notice requirements, whether it has standing to bring

8

these claims, whether res judicata bars the suit, and finally whether the Pond falls

9

within University Place’s regulatory responsibilities. The Court concludes that

10

genuine disputes of material fact preclude summary judgment on the permit

11

coverage issue that forms the heart of this dispute.

12

3.2.1 Yacht Club provided sufficient pre-suit notice to University

13 Place.

14 University Place argues that Yacht Club failed to comply with the CWA’s pre-

15 suit notice requirement under 40 C.F.R. § 135.2(a)(2), which requires service “upon,

16 the head of such agency” for state or local government violators. Dkt. No. 71 at 15–

17 17. University Place contends that because it operates under a council-manager

18 form of government, the City Manager—not the Mayor—serves as the “head of such

19

20

21 2 University Place’s motion bears the title “summary judgment” and argues

exclusively under Rule 56. Yet the motion also cites Rules 12(b)(1) and 12(b)(6) in

22 its introduction—rules University Place never mentions again. Dkt. No. 71 at 2. The

Court will not chase shadows but will instead evaluate the motion for what it is: one

23 for summary judgment.

1 agency,” and Yacht Club’s failure to serve the City Manager before suing warrants

2 dismissal. Id.

3 Yacht Club responds that its notice was legally sufficient under the “overall

4 sufficiency” standard and that service on University Place’s Mayor and Public

5 Works Director, who had actual authority over NPDES compliance, satisfied the

6 regulatory purpose. Dkt. No. 82 at 23–26. The Court agrees with Yacht Club.

7 Before private persons and entities may bring citizen suits to enforce the

8 CWA, they “must give a 60-day notice of intent to sue.” Ctr. For Biological Diversity

9 v. Marina Point Dev. Co., 566 F.3d 794, 800 (9th Cir. 2009) (citing 33 U.S.C.

10 § 1365(a)-(b)). The notice serves two important public purposes: first, it “allows

11 Government agencies to take responsibility for enforcing environmental regulations,

12 thus obviating the need for citizen suits”; and second, it gives the alleged violator an

13 opportunity to comply. Id. (quoting Hallstrom v. Tillamook Cnty., 493 U.S. 20, 29

14 (1989)).

15 “[T]he analysis of whether notice was properly given ‘turns on the “overall

16 sufficiency” of the notice.’” Puget Soundkeeper All. v. Louis Dreyfus Commodities

17 LLC, No. C14-803-RAJ, 2016 WL 7718644, at *4 (W.D. Wash. Mar. 11, 2016)

18 (quoting Klamath-Siskiyou Wildlands Ctr. V. MacWhorter, 79 F.3d 645, 651 (9th

19 Cir. 2015)). Courts may look to “both the notice itself and the behavior of its

20 recipients to determine whether they understood or reasonably should have

21 understood the alleged violations.” Cascadia Wildlands v. Scott Timber Co., 105

22 F.4th 1144, 1154–55 (9th Cir. 2024) (quoting Klamath-Siskiyou, 797 F.3d at 651)).

23

1 While University Place correctly notes that the City Manager serves as chief

2 executive officer under Washington’s council-manager statutes, RCW 35A.13.010,

3 this technical reading ignores the functional reality of NPDES compliance. Yacht

4 Club served notice on Jack Ecklund, University Place’s Public Works Director and

5 designated NPDES “responsible official,” along with the NPDES Coordinator,

6 Mayor, and City Attorney. Dkt. No. 27 at 39–46; Dkt. No. 82 at 24.

7 Ecklund possessed actual authority to respond to alleged NPDES violations

8 and immediately did so. Upon receiving the notice, he promptly contacted the

9 Washington Department of Ecology, informed them of University Place’s position,

10 and invited a site visit to evaluate the claimed violation. Dkt. Nos. 71-6 at 9–10; 82

11 at 25. This response shows that the notice reached the person with operational

12 responsibility for the specific regulatory program at issue.

13 Courts routinely reject arguments that pre-suit notice was insufficient

14 because of service on the wrong person when the recipient receives adequate

15 information to identify the alleged violator and violations. Waste Action Project v.

16 Draper Valley Holdings LLC, 49 F. Supp. 3d 799, 814 (W.D. Wash. 2014). For

17 example, in Draper Valley Holdings, a court in this District found a pre-suit notice

18 sufficient even though it identified the alleged polluter by the wrong company name

19 because, “[t]aken in the context of the remainder of the notice, defendant could not

20 possibly have been confused about the identity of the alleged polluter” in light of the

21 relevant permit number, location of the polluting facility, and dates on which the

22 violations allegedly occurred. Id. at 814.

23

1 Like the notice in Draper Valley Holdings, the notice given here specified the

2 relevant permits, facility location, and nature of alleged violations. Dkt. No. 27 at

3 39–46. University Place cannot credibly claim confusion about the identity of the

4 alleged violator, or the substance of the claims given the specificity of the notice and

5 Ecklund’s immediate substantive response.

6 Thus, the Court finds Yacht Club’s pre-suit notice legally sufficient.

7

3.2.2 Yacht Club has standing to sue.

8

University Place argues that Yacht Club lacks standing because it was

9

already compensated for its injuries in the 1990 lawsuit. Specifically, University

10

Place contends that Yacht Club’s inverse condemnation covered permanent damage

11

to property and that receiving damages bars Yacht Club’s claims based on the same

12

sediment discharge. Thus, according to University Place, Yacht Club has no further

13

injury upon which to base its claims. Dkt. No. 71 at 17–19.

14

This argument fails because the current lawsuit involves fundamentally

15

different injuries and remedies. In the 1990 lawsuit, Yacht Club claimed that

16

University Place and Tacoma physically harmed, trespassed, and impermissibly

17

took its property. In contrast, the current lawsuit—brought over two decades

18

later—alleges permit violations based on University Place’s and Tacoma’s failure to

19

maintain the Pond which was retrofitted in 2001 to prevent future sedimentation

20

problems. Indeed, University Place’s Public Works Superintendent testified that the

21

Pond was renovated because “we decided that we would go through there and try

22

and make sure . . . there’s never a lawsuit again” by creating “a couple of cells so

23

1 stormwater has an opportunity to slow down and any particulates settle out.” Dkt.

2 No. 80-6 at 23.

3 Moreover, Clean Water Act remedies serve public rather than private

4 interests. Unlike the 1990 lawsuit seeking monetary compensation for property

5 damage, Clean Water Act citizen suits do not provide damages to prevailing

6 plaintiffs. Sierra Club v. Chevron U.S.A., Inc., 834 F.2d 1517, 1522 (9th Cir. 1987).

7 Any penalties or benefits from the lawsuit “inure[ ] to the public or to the United

8 States.” Id. (quoting Chesapeake Bay Found. v. Bethlehem Steel Corp., 608 F. Supp.

9 440, 449 (D. Md. 1985)). Rather than seeking compensation for past harm, Yacht

10 Club seeks permit compliance and maintenance. Dkt. No. 27 at 36.

11 Finally, Yacht Club’s allegations satisfy Article III standing requirements

12 regardless of the prior litigation. Courts have long held that environmental

13 plaintiffs have pled an injury-in-fact by alleging their use of land have lessened

14 aesthetic and recreational value on account of NPDES permit violations. See

15 Friends of the Earth, Inc. v. Laidlaw Env’t Servs., Inc., 528 U.S. 167, 181 (2000)

16 (“The relevant showing for purposes of Article III standing [in CWA citizen suits],

17 however, is not injury to the environment but injury to the plaintiff.”). Yacht Club

18 alleges that sediment discharge from the unmaintained pond interferes with

19 moorage operations, boat navigation, and member use of its marina and tidelands.

20 Dkt. No. 27 ¶ 14. And University Place acknowledges these allegations satisfy

21 Article III requirements. Dkt. No. 71 at 18.

22 Accordingly, Yacht Club has standing to sue.

23

1 3.2.3 Res judicata does not bar Yacht Club’s current claims.

University Place argues that the 1990 lawsuit involves the same alleged

2

storm system and resulted in final judgment that should preclude Yacht Club’s

3

claims under the res judicata doctrine. Dkt. No. 71 at 19. “For the doctrine to apply,

4

a prior judgment must have a concurrence of identity with a subsequent action in

5

(1) subject matter, (2) cause of action, and (3) persons and parties, and (4) the

6

quality of the persons for or against whom the claim is made.” Loveridge v. Fred

7

Meyer, Inc., 887 P.2d 898, 900 (Wash. 1995). When these requirements are met, all

8

matters that were litigated or could have been litigated in the prior action cannot

9

support a later action. Feminist Women’s Health Ctr. v. Codispoti, 63 F.3d 863, 867

10

(9th Cir. 1995) (quoting Shoemaker v. Bremerton, 745 P.2d 858, 860 (Wash. 1987)).

11

As discussed above, the current lawsuit involves different subject matter and

12

causes of action from the 1990 litigation. While the 1990 lawsuit concerned

13

preexisting conditions and sought property damage compensation, this lawsuit

14

challenges University Place’s failure to maintain infrastructure constructed in 2001

15

to address the problems identified in the prior litigation. It almost goes without

16

saying that res judicata cannot bar claims based on conduct that occurred after the

17

prior judgment was entered. See Collins v. Dep’t of Lab. & Indus., 259 P.2d 643, 644

18

(Wash. 1953) (res judicata does not bar claims for aggravation occurring after date

19

of final order).

20

The distinct legal frameworks and relief sought further distinguish the

21

actions. The 1990 lawsuit sought monetary damages and injunctive relief under

22

state tort law, while this lawsuit seeks regulatory compliance under federal

23

1 environmental law. Environmental defendants can be held liable for repeating

2 conduct they were previously ordered to cease and remediate. Kelly v. U.S. E.P.A.,

3 203 F.3d 519, 522 (7th Cir. 2000).

4 University Place’s argument that both lawsuits concern the “same wrongful

5 act” ignores the temporal and legal distinctions. The current claims are based on

6 permit maintenance failures involving infrastructure that did not exist when the

7 1990 lawsuit was resolved, creating genuinely new claims rather than repackaged

8 theories for previously adjudicated harm.

9

3.2.4 Factual disputes preclude summary judgment on the merits.

10

University Place argues that the Pond falls outside its NPDES Permit

11

coverage because it is not a small MS4 under the permit’s definitional

12

requirements. University Place contends that an MS4 must be a conveyance system

13

“designed or used for collecting or conveying stormwater” and argues that such

14

systems include only “the infrastructure through which stormwater flows” up to “a

15

discharge point to a receiving waterway.” Dkt. No. 71 at 9–10. Under this

16

interpretation, University Place’s MS4 includes only the 36-inch storm sewer pipe,

17

not the Pond itself. University Place further argues that the Washington

18

Department of Ecology has characterized the Pond as a historic wetland estuary

19

that “serves no stormwater purpose.” Id. at 11–12.

20

Contested facts, however, prevent resolution of the MS4 coverage question.

21

The parties present fundamentally different accounts of the Pond’s nature and

22

operational history that are essential to determining permit coverage. University

23

1 Place argues that the area is historically a natural wetland estuary that has never

2 been designed or modified to function as stormwater infrastructure, while Yacht

3 Club contends that University Place deliberately retrofitted the Pond and

4 surrounding area in 2001 to serve as a stormwater Best Management Practice

5 (BMP). Cooper testified that University Place retrofitted the area specifically to

6 “make a couple of cells so stormwater has an opportunity to slow down and any

7 particulates settle out before they can flow through those twin culverts into the

8 . . . bay.” Dkt. No. 80-6 at 23–24. Yacht Club also argues that University Place is

9 estopped from denying the Pond’s stormwater purpose based on its representations

10 to the Army Corps of Engineers that improvements were occurring in an “existing

11 storm pond” to “improve water quality.” Dkt. No. 80-14 at 14.

12 These competing characterizations of intent and function—wetland

13 maintenance versus stormwater infrastructure creation—directly determine

14 whether the regulatory definition of MS4 as a system “designed or used for

15 collecting or conveying stormwater” applies to the Pond. University Place’s position

16 requires the Court to accept its factual premise that the Pond is a historically

17 natural feature that hasn’t been modified for stormwater purposes, while Yacht

18 Club’s evidence of deliberate construction and retrofitting, if credited, could satisfy

19 the MS4 definitional requirements. The Court cannot resolve MS4 coverage without

20 resolving material questions of fact.

21 The Department of Ecology’s technical determination does not resolve these

22 factual disputes. While University Place argues that Ecology’s conclusion should

23 control, Yacht Club challenges both the reliability and admissibility of the unsigned

1 internal memorandum. The Court need not rule on the admissibility of the memo

2 now, but even assuming it is admissible, it would carry little weight on summary

3 judgment given the factual disputes about the Pond’s construction, purpose, and

4 operation. The determination appears to assess current site conditions rather than

5 analyze the historical evidence of University Place’s 2001 retrofitting work or

6 representations to federal agencies about “existing storm pond” improvements.

7 Questions of MS4 coverage require resolving contested facts about facility design

8 and intent that cannot be determined by agency technical opinions focused on

9 present-day conditions. Moreover, Yacht Club has presented evidence that Ecology

10 officials themselves questioned whether the memo constituted an “official

11 determination or final agency action,” further undermining its probative value on

12 summary judgment. Dkt. No. 82 at 22–23.

13 Expert testimony also shows contested factual issues. Yacht Club’s expert

14 Chris Carter opines that the Pond constitutes a “legacy BMP” that remains part of

15 University Place’s regulated stormwater system despite maintenance deficiencies,

16 concluding that University Place’s “failure to maintain the Pond does not meet that

17 NPDES Permit standard.” Dkt. No. 78 at 7. Cooper acknowledged that the Pond

18 “was collecting silt, as intended, but now is due for a cleaning as it has reached its

19 limit.” Dkt. No. 80-6 at 115.

20 The Court cannot determine whether the Pond satisfies the regulatory

21 criteria for MS4 coverage without resolving these underlying factual disputes about

22 the Pond’s construction, purpose, operation, and current condition. These are issues

23 for trial.

1 3.3 University Place’s motion to dismiss Tacoma’s crossclaims.

University Place moves for summary judgment on Tacoma’s trespass and

2

nuisance crossclaims, arguing that Tacoma disregarded state tort claim filing

3

requirements and that the claims are barred by statutes of limitations. University

4

Place also contends that Tacoma granted permission for the complained-of

5

activities. The Court finds that genuine disputes of material fact preclude summary

6

judgment on these crossclaims.

7

8

3.3.1 Tacoma substantially complied with the tort claim filing

requirement.

9

University Place argues that Tacoma failed to comply with RCW 4.96.020(4)’s

10

requirement to serve a tort-claim form 60 days before suing, pointing to several

11

alleged compliance failures and arguing that dismissal is mandatory. This

12

argument lacks merit given University Place’s own conduct and the substantial

13

compliance standard.

14

The substantial compliance standard governs claim filing requirements.

15

RCW 4.96.020(5) provides that claim filing requirements “are liberally construed so

16

that substantial compliance will be deemed satisfactory.” Courts apply substantial

17

compliance when “the statute has been followed sufficiently so as to carry out the

18

intent for which the statute was adopted.” A.T. v. Everett Sch. Dist., 300 F. Supp. 3d

19

1243, 1253 (W.D. Wash. 2018). The statute’s purpose is to provide local

20

governments with “notice of potential tort claims, the identity of the claimant, and

21

general information about the claim.” Renner v. City of Marysville, 230 P.3d 569,

22

571 (Wash. 2010)

23

1 University Place authorized Tacoma’s email filing and cannot now claim

2 noncompliance. During telephone conversations about claim filing procedures,

3 University Place’s Risk Manager “expressly invited” Tacoma’s counsel to submit the

4 tort claim form by email. Dkt. No. 76 at 10. Tacoma transmitted the claim form on

5 June 11, 2024, at 3:45 p.m., with metadata confirming delivery 31 seconds later. Id.

6 University Place’s IT Manager acknowledges he cannot dispute the transmission

7 evidence and finds it “plausible” that such an email was sent. Dkt. No. 71-4 ¶ 7.

8 University Place’s argument that it never received the email rings hollow when its

9 own authorized agent invited email filing and its IT personnel cannot dispute the

10 transmission evidence.

11 The Court finds that Tacoma substantially complied with RCW 4.96.020’s

12 requirements through authorized email filing that provided University Place with

13 adequate notice and opportunity to investigate the claims.

14

3.3.2 University Place’s remaining arguments are doomed by

disputed facts.

15

University Place argues Tacoma’s crossclaims are time-barred and should be

16

dismissed based on permission. First, University Place contends the claims accrued

17

in 2001 when it constructed an access road on Tacoma’s property to reach the pond

18

area, making those claims time-barred years ago. Alternatively, University Place

19

argues that even if the claims accrued in 2019 when Tacoma requested the

20

University Place cease maintenance activities in the area, the claims would still be

21

time-barred. Second, University Place argues it had Tacoma’s permission to perform

22

23

1 the work, which bars both trespass and nuisance claims as a matter of law. Dkt. No.

2 71 at 24–26.

3 Tacoma responds that it did not discover the full scope of University Place’s

4 modifications until this litigation began, and that any permission was limited to

5 maintenance road construction. Dkt. No. 76 at 14–19. Tacoma argues the statute of

6 limitations does not bar its claims because RCW 4.16.080 “provides a three-year

7 statute of limitations for trespass claims ‘after discovery by aggrieved party of the

8 acts or acts from which such liability has arisen or shall arise.’” Dkt. No. 76 at 18–

9 19. But Tacoma misquotes the statute. As University Place points out in its reply,

10 RCW 4.16.080(1) governs the statute of limitation for trespass claims, while

11 Tacoma’s quoted language appears in subsection (6), which addresses entirely

12 different causes of action. Dkt. No. 88 at 12 n.8.

13 Under Washington law, trespass claims must be brought within three years

14 and nuisance claims within two years. RCW 4.16.080(1); Wallace v. Lewis Cnty., 137

15 P.3d 101, 110 (Wash. 2006). University Place argues the discovery rule is

16 inapplicable to trespass claims, citing Bradley v. Am. Smelting & Ref. Co., 709 P.2d

17 782 (Wash. 1985). Bradley did indeed “reject the discovery rule as being

18 inappropriate for a continuing trespass claim.” Id. at 693. Bradley also recognized

19 the “continuing trespass” doctrine, which affects the statute of limitations analysis.

20 Id.

21 As the Washington Court of Appeals explained, in Fradkin v. Northshore

22 Util. Dist., 977 P.2d 1265, 1267 (Wash. Ct. App. 1999), “[i]f a condition causing

23 damage to land is reasonably abatable, the statute of limitations does not bar an

1 action for continuing trespass. So long as the intrusion continues, the statute of

2 limitation serves only to limit damages to those incurred in the three-year period

3 before the suit was filed.” (emphasis added). Whether a claim qualifies as a

4 “continuing trespass” turns on the “reasonable abatability of an intrusive

5 condition.” Id. at 1270. A trespass is “reasonably abatable” when “[t]he condition

6 . . . can be removed ‘without unreasonable hardship and expense.’” Id. at 1270 n.25

7 (quoting Mangini v. Aerojet–Gen. Corp., 912 P.2d 1220, 1225 (Cal. 1996)). “Periodic

8 flooding due to defective construction of a drainage system is a recognized fact

9 pattern in the category of continuing trespass.” Id. at 1270.

10 With regard to Tacoma’s public nuisance claim, a similar continuing nuisance

11 theory applies. “‘A nuisance cause of action accrues when the plaintiff initially

12 suffers from some actual and appreciable harm or when the plaintiff should have

13 discovered the basis for a nuisance action.’” Raymond Slate v. Pierce Cnty., No. 3:14-

14 CV-05161, 2016 WL 410182, at *5 (W.D. Wash. Feb. 3, 2016) (quoting Wallace v.

15 Lewis Cnty., 137 P.3d 101, 110 (Wash. Ct. App. 2006), as corrected (Aug. 15, 2006)).

16 But “if the nuisance remains, the plaintiff may continue to collect damages for

17 uncompensated harm until the nuisance is abated.” Id.

18 The abatability analysis requires factual development that is absent from the

19 record. In Skokomish Indian Tribe v. United States, 410 F.3d 506, 518 (9th Cir.

20 2005), the Ninth Circuit determined as a matter of law that alleged damages were

21 not reasonably abatable because the tribe’s expert provided specific evidence:

22 property valued at $2.17 million would require $3.77 million in remediation costs.

23 The court found this “large discrepancy between the cost of repair and the actual

1 value of the land” clearly established that “the damages could be abated only with

2 unreasonable hardship and expense.” Id. Even there, the concurring judge noted

3 that the evidence indicated a factual dispute, distinguishing between costs of

4 repairing consequential property damage versus “the perhaps much lower cost to

5 abate the aggradation itself, by way of dredging or flushing flows.” Id. at 521–22

6 (Graber, J., concurring).

7 Here, the record contains no comparable cost evidence. Cooper testified that

8 the pond was collecting silt as intended but is now due for cleaning, and that

9 University Place had maintenance plans including monitoring and cleaning. Dkt.

10 No. 80-6 at 115–116. But the record contains no expert reports, cost estimates, or

11 other evidence of unreasonable hardship and expense regarding remedial measures.

12 Without such evidence, the Court cannot determine whether remediation would

13 involve “unreasonable hardship and expense.”

14 Genuine factual disputes also exist about the scope of Tacoma’s permission.

15 The 1997 letter authorized “a maintenance road” but University Place performed

16 broader pond retrofitting work including berms and excavation. Dkt. Nos. 71-5 at 4;

17 80-12. The 2019 correspondence further suggests limited or withdrawn permission.

18 Dkt. No. 80-17.

19 Because genuine disputes exist about both the abatability of any alleged

20 trespass and nuisance conditions and the scope of Tacoma’s permission, the Court

21 cannot dismiss the crossclaims as a matter of law.

22

23

1 3.4 Tacoma’s motion for summary judgment against Yacht Club.

Tacoma argues it is entitled to summary judgment for two reasons. First,

2

Tacoma argues that it has fulfilled its obligation to coordinate with University Place

3

under its NPDES permit by participating in regional stormwater coordination

4

groups. Dkt. No. 68 at 6. Second, Tacoma contends that its permit prohibits

5

construction and maintenance of stormwater treatment facilities within natural

6

wetlands, including the Pond. Id. Yacht Club disputes both the adequacy of

7

Tacoma’s coordination efforts and the characterization of the Pond as a natural

8

wetland subject to such restrictions.

9

Contested facts prevent resolution of whether Tacoma’s coordination efforts

10

discharged its permit obligations. Tacoma’s permit requires coordination

11

mechanisms “among entities covered under a municipal stormwater NPDES permit

12

to encourage coordinated stormwater-related policies, programs, and projects within

13

a watershed.” Dkt. No. 70-1 at 15. The permit specifically mandates coordination for

14

“shared waterbodies” and between “physically interconnected MS4s.” Id. at 15–16.

15

While Tacoma points to its participation in regional working groups and general

16

communications with University Place, Yacht Club argues that meaningful

17

coordination about the Pond specifically was required given the ongoing

18

jurisdictional disputes and shared responsibility for the Pond and surrounding area.

19

The record reveals genuine disputes about the nature, timing, and adequacy

20

of coordination efforts. Tacoma claims in its crossclaims against University Place

21

that it “was not aware of University Place’s 2001 retrofitting or lack of subsequent

22

maintenance,” which contradicts any assertion of effective coordination about the

23

1 Pond. Dkt. No. 58 ¶¶ 7–8. The extent of coordination—what was discussed, when,

2 with whom, and whether it addressed the Pond specifically—presents factual

3 questions that cannot be resolved on summary judgment. Whether Tacoma’s

4 general regional participation constituted adequate coordination for this particular

5 shared “facility” requires examining the specific circumstances at issue.

6 Similarly, and as noted in the Court’s analysis of University Place’s motion,

7 whether the Pond qualifies as a wetland exempt from permit requirements depends

8 on contested factual determinations. Tacoma argues that multiple independent

9 experts have concluded the Pond contains wetlands, making maintenance

10 obligations inapplicable under permit restrictions. Dkt. No. 68 at 6. However, Yacht

11 Club’s expert Chris Carter challenges this characterization, arguing that “the

12 absence of historical wetlands assessments or delineations, combined with the fact

13 that the Pond and the area around it has been significantly altered by manmade

14 improvements over the past several decades, make it impossible to determine if the

15 Pond lies within or near a natural wetland.” Dkt. No. 78 ¶ 23.

16 The competing expert opinions reflect deeper factual disputes about the

17 Pond’s history and current status. Carter argues that because of the “long-standing

18 history of artificial stormwater drainage to this area and surrounding

19 improvements,” Tacoma’s permit does not prohibit categorizing the Pond as a BMP

20 that requires maintenance. Id. ¶ 28. This directly contradicts Tacoma’s position that

21 the area constitutes a natural wetland subject to permit restrictions. The parties

22 present strikingly different accounts of whether decades of artificial modifications

23 have transformed what may have been natural wetlands into constructed

1 stormwater infrastructure. If Yacht Club’s allegations are proven at trial—that

2 Tacoma allowed stormwater infrastructure on its property for decades, then

3 prevented maintenance efforts, only to claim environmental immunity when

4 problems arose—such conduct would raise serious concerns about parties invoking

5 environmental protections to avoid responsibility for harm they helped create. But

6 these are contested factual allegations that must be resolved through trial rather

7 than summary adjudication.

8 Because genuine disputes exist about the adequacy of Tacoma’s coordination

9 efforts and the nature of the Pond’s wetland characteristics, the Court cannot grant

10 summary judgment in Tacoma’s favor.

11

4. CONCLUSION

12

The Court DENIES Tacoma’s motion for summary judgment, Dkt. No. 68.

13

The Court also DENIES University Place’s motion for summary judgment against

14

Yacht Club and Tacoma. Dkt. No. 71.

15

Dated this 22nd day of August, 2025.

16

17 A

18 Jamal N. Whitehead

United States District Judge

19

20

21

22

23