extending deference to the PUC’s interpretation of the Electricity Generation Customer Choice and Competition Act, 66 Pa. C.S. §§2801-2812
How later courts described this case
- extending deference to the PUC’s interpretation of the Electricity Generation Customer Choice and Competition Act, 66 Pa. C.S. §§2801-2812
- observing that “other interpretative rules of statutory construction are to be utilized only where the statute at issue is ambiguous”
Written by the judges who cited it.
The opinion
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
David N. Hommrich, :
:
Petitioner :
:
v. : No. 463 M.D. 2022
: Argued: April 9, 2025
Commonwealth of Pennsylvania, :
Pennsylvania Public Utility :
Commission, :
:
Respondent :
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
OPINION BY JUDGE WOJCIK FILED: August 13, 2025
Before this Court is an Application for Partial Summary Relief (ASR)
filed by Petitioner David N. Hommrich (Hommrich) and Intervenors Kriebel
Minerals, Inc. (Kreibel) and ERD Energy, LLC (ERD) (collectively, Petitioners)
seeking declarations that certain regulations promulgated by the Pennsylvania Public
Utility Commission (PUC) on alternative energy (Regulations)1 are inconsistent with
the Alternative Energy Portfolio Standards Act (AEPS Act)2 and, therefore, are
invalid and unenforceable. After careful review, we deny the ASR.
1
The Regulations are codified in Title 52, Chapter 75 of the Pennsylvania Code,
52 Pa. Code §§75.1-75.72.
2
Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§1648.1-1648.8.
I. Background
Hommrich, who is the sole owner of a solar power project located in
Mercer County, Pennsylvania, and frequent petitioner in alternative energy
litigation, initiated this action by filing, pro se, a petition for review (PFR) in the
nature of a complaint for declaratory relief in this Court’s original jurisdiction, which
he later amended (Amended PFR).3 Kreibel, a natural gas company operating in the
Commonwealth of Pennsylvania, and ERD, its equipment supplier (together,
Intervenors), which are owned and operated by the same individuals, were permitted
to intervene. Intervenors have adopted Hommrich’s Amended PFR in its entirety
with an additional prayer for relief. See Intervenors’ Application for Intervention,
Request for Relief ¶78.
The gravamen of the Amended PFR challenges Regulations pertaining
to the interconnection of “alternative energy systems”4 and requires statutory
interpretation of the AEPS Act. Interconnection is the mechanism through which a
source of generation connects and delivers power to an electrical distribution system.
See Amended PFR, ¶7; Answer to Amended PFR, ¶7. Petitioners are approved
“customer-generators” as defined under Section 2 of the AEPS Act5 that own and/or
3
In response to the PFR, the PUC filed preliminary objections (POs), which were mooted
by the amendment. PUC filed new POs to the Amended PFR, which this Court overruled by order
and opinion dated March 1, 2024. We directed the PUC to file an answer to the Amended PFR.
4
An “alternative energy system” is defined as “[a] facility or energy system that uses a
form of alternative energy source to generate electricity and delivers the electricity it generates to
the distribution system of an electric distribution company or to the transmission system operated
by a regional transmission organization.” Section 2 of the AEPS Act, 73 P.S. §1648.2.
5
A “customer-generator” is defined as:
A nonutility owner or operator of a net metered distributed
generation system with a nameplate capacity of not greater than 50
(Footnote continued on next page…)
2
operate net metered6 distributed generation systems, which generate electricity from
alternative energy sources.7 Customer-generators are customers of electric
distribution companies (EDCs) and generate electricity that flows into the EDCs’
kilowatts if installed at a residential service or not larger than 3,000
kilowatts at other customer service locations, except for customers
whose systems are above three megawatts and up to five megawatts
who make their systems available to operate in parallel with the
electric utility during grid emergencies as defined by the regional
transmission organization or where a microgrid is in place for the
primary or secondary purpose of maintaining critical infrastructure,
such as homeland security assignments, emergency services
facilities, hospitals, traffic signals, wastewater treatment plants or
telecommunications facilities, provided that technical rules for
operating generators interconnected with facilities of an electric
distribution company, electric cooperative or municipal electric
system have been promulgated by the Institute of Electrical and
Electronic Engineers and the [PUC].
73 P.S. §1648.2.
6
“Net metering” refers to:
The means of measuring the difference between the electricity
supplied by an electric utility and the electricity generated by a
customer-generator when any portion of the electricity generated by
the alternative energy generating system is used to offset part or all
of the customer-generator’s requirements for electricity. Virtual
meter aggregation on properties owned or leased and operated by a
customer-generator and located within two miles of the boundaries
of the customer-generator’s property and within a single electric
distribution company’s service territory shall be eligible for net
metering.
Section 2 of the AEPS Act, 73 P.S. §1648.2.
7
The term “alternative energy sources” includes energy sourced from solar; wind;
hydropower; geothermal; biomass; biologically derived methane gas; fuel cells; waste coal; coal
mine methane; energy efficiency; and distributed generation systems. Section 2 of the AEPS Act,
73 P.S. §1648.2.
3
distribution systems. The AEPS Act provides for the retail compensation for any
excess electricity generated by any AEPS-qualified generating system owned or
operated by a customer-generator. To deliver the energy into the EDCs’ distribution
systems, customer-generators must first interconnect with the EDCs’ distribution
systems. Absent an interconnection, customer-generators’ alternative energy
systems cannot deliver and sell excess energy to an EDC.
According to Petitioners, the Regulations have allowed EDCs to cause
customer-generators, like Petitioners, to bear all costs involved in the planning,
design, development, and implementation of distribution system improvements,
including interconnection, that enable EDCs to purchase excess energy generated
from alternative energy sources. Petitioners assert that the AEPS Act does not
obligate customer-generators to pay for these costs, but rather it requires them to be
paid by ratepayers as a cost of generation supply. Petitioners claim that their
business interests are adversely impacted by the Regulations. Petitioners maintain
that the challenged Regulations are invalid because they are contrary to the AEPS
Act and precedent limiting the PUC’s authority in these matters. Petitioners seek
declarations interpreting the AEPS Act and invalidating and/or limiting the
Regulations. See Amended PFR, Requests for Relief A-I; Intervenors’ Application
for Intervention, Request for Relief ¶78(a).
PUC filed an answer to the Amended PFR denying material allegations.
On July 19, 2024, Petitioners filed the ASR and accompanying Memorandum of
Law. The PUC filed an answer and brief in response.
4
Petitioners seek partial summary relief narrowed to the following six
requests:8
• Declare that excess energy purchased from customer-generators by
EDCs pursuant to Section 5 of the AEPS Act, 73 P.S. §1648.5,
constitutes the purchase of a “resource” as that term is described in
Section 3(a)(3)(ii) of the AEPS Act, 73 P.S. § 1648.3(a)(3)(ii). See
Amended PFR, Request for Relief A.
• Declare that the costs to interconnect to EDCs’ distribution systems,
which enables EDCs to purchase electricity generated from alternative
energy sources, are “direct or indirect resource costs” subject to the
mandatory cost recovery mechanism in Section 3(a)(3)(ii) of the AEPS
Act, 73 P.S. §1648.3(a)(3)(ii). As such, those costs must be recovered
from ratepayers on a full and current basis pursuant to an automatic
energy adjustment clause under Section 1307 of the Public Utility
Code, 66 Pa. C.S. §1307, as a cost of generation supply under Section
2807 of the Public Utility Code, 66 Pa. C.S. §2807. See Amended PFR,
Request for Relief B.
• Declare that the AEPS Act does not give the PUC a legislative grant of
authority to promulgate regulations for cost recovery pursuant to
Section 3(a)(3)(ii) of the AEPS Act, 73 P.S. §1648.3(a)(3)(ii), and that
Section 75.67 of the Regulations, 52 Pa. Code §75.67, governing
“alternative energy cost-recovery,” impermissibly alters the clear
language of the AEPS Act and is, therefore, invalid and unenforceable.
See Amended PFR, Request for Relief C.
8
Petitioners have abandoned Requests for Relief E through G in their Amended PFR. See
Petitioners’ ASR, at 2 n.1. They have tabled Request for Relief H, seeking a declaration that
[c]ustomer-generators may utilize third-party contractors, under
confidentiality commitments with an EDC, to provide both impact
studies and design and construction services in order to facilitate a
timely and cost-effective interconnection, so long as the cost or
timeline of the third-party option results in a lower cost or a shorter
timeline for the customer-generator[,]
because additional factual development is necessary and summary relief is not appropriate at this
time. Id.
5
• Extend these holdings by declaring that any other PUC Regulations
allowing EDCs to charge customer-generators for distribution system
improvement costs associated with the interconnection of a renewable
energy systems are invalid and unenforceable as contrary to the AEPS
Act. See Amended PFR, Request for Relief D.
• Declare as invalid the current PUC practice of allowing EDCs to
impose costs on customer-generators in the form of a Contribution in
Aid of Construction (CIAC), a Public Utility Code concept wholly
absent from the AEPS Act, and another example of the PUC improperly
allowing the imposition of costs on customer-generators. See Amended
PFR, Request for Relief I.
• Declare that Sections 75.13(d) and (e) of the Regulations, 52 Pa. Code
§75.13(d) and (e), are unauthorized by and contrary to the AEPS Act,
and therefore invalid and unenforceable. See Intervenors’ Application
for Intervention, Request for Relief ¶78(a).
ASR at 1-2.
II. Discussion
A. Applicable Legal Standards
In ruling on ASRs, this Court has explained:
An [ASR] may be granted if a party’s right to judgment is
clear, and no material issues of fact are in dispute. When
ruling on an [ASR], we must view the evidence of record
in the light most favorable to the non-moving party and
enter judgment only if there is no genuine issue as to any
material facts and the right to judgment is clear as a matter
of law.
Gregory v. Pennsylvania State Police, 185 A.3d 1202, 1205 (Pa. Cmwlth. 2018)
(citations and quotations omitted).
When a regulation is challenged, we consider:
It is axiomatic that all regulations “must be consistent with
the statute under which they were promulgated.” Slippery
Rock Area School District v. Unemployment
Compensation Board of Review, 983 A.2d 1231, 1241
([Pa.] 2009). “A statute is the law and trumps an
6
administrative agency’s regulations.” [Commonwealth v.]
Kerstetter, 62 A.3d [1065,] 1069 [(Pa. Cmwlth. 2013),
aff’d, 94 A.3d 991 (Pa. 2014)]. Similarly, “[w]here there
is a conflict between the statute and a regulation
purporting to implement the provisions of that statute, the
regulation must give way.” Commonwealth v. Colonial
Nissan, Inc., 691 A.2d 1005, 1009 (Pa. Cmwlth. 1997).
“[W]hen an agency adopts a regulation pursuant to its
legislative rule-making power, as opposed to its
interpretive rule-making power, it is valid and binding
upon courts as a statute so long as it is (a) adopted within
the agency’s granted power, (b) issued pursuant to proper
procedure, and (c) reasonable.” Tire Jockey Service, Inc.
v. Department of Environmental Protection, 915 A.2d
1165, 1186 ([Pa.] 2007). When analyzing whether a
regulation is adopted within an agency’s granted power, a
court should consider, inter alia, whether the regulation is
“consistent with the enabling statute” because “clearly, the
[General Assembly] would not authorize agencies to adopt
regulations inconsistent with the enabling statutes.”
Marcellus Shale Coalition v. Department of
Environmental Protection, 216 A.3d 448, 459 . . . (Pa.
Cmwlth. 2019) (internal quotation marks omitted). Thus,
when “a regulation presents ‘an actual conflict with the
statute,’ we cannot reasonably understand the regulation
to be within the agency’s ambit of authority, and the
statute must prevail.” Id. (quoting AMP Inc. v.
Commonwealth, 814 A.2d 782, 786 (Pa. Cmwlth. 2002),
aff’d, 852 A.2d 1161 ([Pa.] 2004)).
Victory Bank v. Commonwealth, 219 A.3d 1236, 1242 (Pa. Cmwlth. 2019), aff’d,
240 A.3d 95 (Pa. 2020) (emphasis added; footnote omitted).
Similar to claims made in Hommrich v. Pennsylvania Public Utility
Commission, 231 A.3d 1027, 1033 (Pa. Cmwlth. 2020) (Hommrich I), Petitioners’
arguments here largely “center[] over whether the PUC has the authority to enact the
challenged [R]egulations and whether those [R]egulations contradict the AEPS
Act.” This calls for a straightforward analysis, as “[s]uch issues may be resolved
7
based on comparison of statutory interpretation and regulatory provisions as a matter
of law.” Id. (citing Marcellus Shale Coalition v. Department of Environmental
Protection, 193 A.3d 447, 460 (Pa. Cmwlth. 2018), appeal quashed, 198 A.3d 330
(Pa. 2018)).
“‘To determine whether a regulation is adopted within an agency’s
granted power, we look for statutory language authorizing the agency to promulgate
the legislative rule and examine that language to determine whether the rule falls
within the grant of authority.’” Hommrich I, 231 A.3d at 1034 (quoting Marcellus
Shale Coalition v. Department of Environmental Protection, 216 A.3d 448, 459 (Pa.
Cmwlth.), appeals quashed, 223 A.3d 655 (Pa. 2019)). “We consider ‘the purpose
of the statute and its reasonable effect’ and whether ‘the regulation is consistent with
the enabling statute.’” Id. (quoting Marcellus Shale, 216 A.3d at 459). The General
Assembly would not authorize an agency “to adopt binding regulations inconsistent
with the applicable enabling statutes.” Id. (citation and quotation omitted). “When
. . . a regulation presents an actual conflict with the statute, we cannot reasonably
understand the regulation to be within the agency’s ambit of authority, and the statute
must prevail.” Id. (citation and quotation omitted). Administrative agencies do not
have the power to make laws, only to prescribe rules and regulations to carry out the
law. Id. at 1035.
In some instances, the General Assembly confers broad regulatory
power upon an agency. Hommrich I, 231 A.3d at 1035. “If the statute makes a clear
grant of authority, then neither a court nor the agency can disregard the clearly
expressed intent of the General Assembly.” Marcellus Shale Coalition v.
Department of Environmental Protection, 292 A.3d 921, 936 (Pa. 2023). Although
the General Assembly has conferred broad powers to agencies in other chapters
8
relating to alternative energy, as this Court has previously recognized, the powers
“conferred to the PUC under the AEPS Act are much narrower.” Hommrich I,
231 A.3d at 1035.
The statutory language of the AEPS Act is the starting point. When
examining statutory language, we follow the rules of statutory construction in the
Statutory Construction Act of 1972 (Statutory Construction Act), 1 Pa. C.S. §1501-
1991. As our Supreme Court has recently explained:
[Section 1921(a) of] [t]he Statutory Construction Act
provides that the object of all statutory interpretation “is to
ascertain and effectuate the intention of the General
Assembly.” 1 Pa. C.S. §1921(a). Generally, the plain
language of the statute provides the best indication of
legislative intent.” Miller v. [County] of Centre, []173
A.3d 1162, 1168 ([Pa.] 2017). If the statutory language is
clear and unambiguous in setting forth the intent of the
General Assembly, then “we cannot disregard the letter of
the statute under the pretext of pursuing its spirit.”
Fletcher v. [Pennsylvania Property & Casualty Insurance
Guarantee Association], []985 A.2d 678, 684 ([Pa.] 2009)
(citing 1 Pa. C.S. §1921(b)). In this vein, “we should not
insert words into [a statute] that are plainly not there.”
Frazier v. Workers’ [Compensation] Appeal [Board]
(Bayada Nurses, Inc.), 616 Pa. 592, 52 A.3d 241, 245
(2012). When the statutory language is ambiguous,
however, we may ascertain the General Assembly’s intent
by considering the factors set forth in Section 1921(c) of
the Statutory Construction Act, 1 Pa. C.S. §1921(c), and
other rules of statutory construction. See [Pennsylvania
School Boards Association], Inc. v. [Public School
Employees Retirement Board], []863 A.2d 432, 436 ([Pa.]
2004) (observing that “other interpretative rules of
statutory construction are to be utilized only where the
statute at issue is ambiguous”). “We also presume that ‘the
General Assembly does not intend a result that is absurd,
impossible of execution or unreasonable,’ and that ‘the
General Assembly intends the entire statute to be effective
and certain.’” Berner v. Montour [Township] Zoning
9
Hearing [Board], []217 A.3d 238, 245 ([Pa.] 2019)
(quoting 1 Pa. C.S. §1922(1)-(2)).
Section 1921(b) of the Statutory Construction Act, which
provides that “when the words of a statute are clear and
free from all ambiguity, the letter of it is not to be
disregarded under the pretext of pursuing its spirit,” is
crucial to our analysis here. If the statute or rule . . . are not
ambiguous, then we cannot apply the presumptions set
forth in Section 1922 of the Statutory Construction Act.
“A statute is ambiguous when there are at least two
reasonable interpretations of the text under review.”
Warrantech Consumer [Products Services], Inc. v.
Reliance [Insurance] Co. in Liquidation, []96 A.3d 346,
354-55 ([Pa.] 2014). “This Court has consistently held that
. . . interpretive rules of statutory construction are to be
utilized only where the statute [or rule] at issue is
ambiguous.” [Pennsylvania School Board Association],
863 A.2d at 436.
Commonwealth v. Green, 291 A.3d 317, 327-28 (Pa. 2023).
Legislative rules that are properly enacted are presumed to be
reasonable, and reviewing courts will accord them a “particularly high measure of
deference.” Marcellus Shale, 292 A.3d at 927 (citation omitted). While this Court
may not substitute its own judgment for that of an agency, we will defer to a
regulation an agency has promulgated pursuant to its interpretative powers where
the regulation is reasonable and “genuinely tracks the meaning of the underlying
statute.” Id. at 929 (citation omitted); accord Tire Jockey, 915 A.2d at 1190. Indeed,
when “faced with interpreting statutory language,” we “afford great deference to the
interpretation rendered by the administrative agency overseeing the implementation
of such legislation.” Winslow–Quattlebaum v. Maryland Ins. Group, 752 A.2d 878,
881 (Pa. 2000). However, “no deference is due where an agency exceeds its legal
authority, or its interpretation is clearly erroneous.” Marcellus Shale, 292 A.3d at
929 (citations omitted). “While an agency’s interpretation of an ambiguous statute
10
it is charged with enforcing is entitled to deference, courts’ deference never comes
into play when the statute is clear.” Seeton v. Pennsylvania Game Commission, 937
A.2d 1028, 1037 (Pa. 2007). With these legal standards in mind, we address each
of Petitioners’ requests for relief.
B. Requests for Relief
Amended PFR, Requests for Relief A, B, and C
Petitioners’ first three requests focus on Section 3(a)(3)(ii) of the AEPS
Act, 73 P.S. §1648.3(a)(3)(ii), which dictates who pays, and how, for the costs
associated with the purchase of electricity generated from alternative energy sources.
Because these requests for relief are interrelated and interdependent, we address
them together.
Petitioners maintain that excess energy purchased from customer-
generators by EDCs pursuant to Section 5 of the AEPS Act, 73 P.S. §1648.5, are
“resource” purchases as described in Section 3(a)(3)(ii) of the AEPS Act,
73 P.S. §1648.3(a)(3)(ii), which include “the purchase of electricity generated from
alternative energy sources.” As resources, Petitioners advance that “any direct or
indirect costs” must be recovered as a cost of generation supply under Section
3(a)(3)(ii) of the AEPS Act. Costs incurred by EDCs – whether direct or indirect –
can only be recovered from ratepayers through the automatic energy adjustment
clause in Section 3(a)(3)(ii). Although the PUC may not agree with the General
Assembly’s decision to compensate customer-generators for excess energy at full
retail value and costs under the AEPS Act, that is how it operates and was intended
to operate. The PUC’s role is to implement the business model chosen by the
General Assembly to encourage growth and investment in renewable sources of
energy. Therefore, Petitioners ask this Court to declare that excess energy purchases
11
under Section 5 of the AEPS Act qualify as resource purchases under Section 3 of
the AEPS Act and, as such, constitute direct and indirect costs that must be recovered
on a full and current basis through an automatic energy adjustment clause under
Section 1307 of the Code, 66 Pa. C.S. §1307, as a cost of generation supply under
Section 2807 of the Code, 66 Pa. C.S. §2807.
If the Court agrees with the foregoing statutory analysis, Petitioners ask
this Court to also declare the Regulation at 52 Pa. Code §75.67, governing
“alternative energy cost-recovery,” invalid and unenforceable for two reasons. First,
this Regulation conflicts with Section 3 of the AEPS Act because it alters the
statutory language to make automatic adjustment clause recovery optional rather
than mandatory through the use of “may” instead of “shall.” This improperly allows
the imposition of interconnection costs on customer-generators rather than
ratepayers. Second, the AEPS Act does not grant the PUC a legislative grant of
authority to promulgate regulations for cost recovery pursuant to Section 3 of the
AEPS Act.
To begin, under Section 5 of the AEPS Act, EDCs are mandated to
purchase all excess energy from net-metered customer-generators. Specifically:
Excess generation from net-metered customer-generators
shall receive full retail value for all energy produced on
an annual basis. The [PUC] shall develop technical and
net metering interconnection rules for customer-
generators intending to operate renewable onsite
generators in parallel with the electric utility grid,
consistent with rules defined in other states within the
service region of the regional transmission organization
that manages the transmission system in any part of this
Commonwealth. The [PUC] shall convene a stakeholder
process to develop Statewide technical and net metering
rules for customer-generators. The [PUC] shall develop
12
these rules within nine months of the effective date of this
act.
73 P.S. §1648.5 (emphasis added). Excess generation, also known as surplus power,
occurs when a customer-generator produces more electricity than needed for all
excess energy produced. Id.; Hommrich I, 231 A.3d at 1034.
Section 3 of the AEPS Act, 73 P.S. §1648.3, governs the cost recovery
for the purchase of electric distribution by EDCs to comply with the AEPS Act.
Specifically, Section 3(a)(3) of the AEPS Act states:
(3) All costs for:
(i) the purchase of electricity generated from
alternative energy sources, including the costs of the
regional transmission organization, in excess of the
regional transmission organization real-time locational
marginal pricing, or its successor, at the delivery point of
the alternative energy source for the electrical production
of the alternative energy sources; and
(ii) payments for alternative energy credits
[(AECs)],
in both cases that are voluntarily acquired by an [EDC]
during the cost recovery period on behalf of its customers
shall be deferred as a regulatory asset by the [EDC] and
fully recovered, with a return on the unamortized balance,
pursuant to an automatic energy adjustment clause under
[Section 1307 of the Public Utility Code,] 66 Pa. C.S.
§1307 (relating to sliding scale of rates; adjustments) as a
cost of generation supply under [Section 2807 of the
Public Utility Code,] 66 Pa. C.S. §2807 (relating to duties
of [EDCs]) in the first year after the expiration of its cost-
recovery period. After the cost-recovery period, any direct
or indirect costs for the purchase by electric distribution
of resources to comply with this section, including, but
not limited to, the purchase of electricity generated from
alternative energy sources, payments for [AECs], cost of
credits banked, payments to any third party administrators
for performance under this act and costs levied by a
13
regional transmission organization to ensure that
alternative energy sources are reliable, shall be recovered
on a full and current basis pursuant to an automatic
energy adjustment clause under 66 Pa. C.S. §1307 as a
cost of generation supply under 66 Pa. C.S. §2807.
73 P.S. §1648.3(a)(3) (emphasis added).
Section 3 of the AEPS Act expressly incorporates by reference Sections
1307 and 2807 of the Public Utility Code, 66 Pa. C.S. §§1307 and 2807. In turn,
Section 2807(e)(3.5) of the Public Utility Code cross references Section 3 of the
AEPS Act:
[T]he provisions of this section shall apply to any type of
energy purchased by a default service provider to provide
electric generation supply service, including energy or
alternative energy portfolio standards credits required to
be purchased under [Section 3 of the AEPS Act] . . . .
66 Pa. C.S. §2807(e)(3.5) (emphasis added). Because Section 3 of the AEPS Act
and 66 Pa. C.S. §§1307 and 2807 “relate to the same persons or things,” i.e., EDC
recovery of the costs of purchasing AECs, these provisions are in pari materia and
must be construed together, if possible, as one statute. Section 1932 of the Statutory
Construction Act, 1 Pa. C.S. §1932.
Complementing the PUC’s power to create an AEC program to
implement Section 3 as required by the AEPS Act, Section 1307 of the Code grants
the PUC authority, “by regulation or order,” to “prescribe for any class of public
utilities . . . a mandatory system for the automatic adjustment of their rates[.]”
66 Pa. C.S. §1307(b) (emphasis added). Meanwhile, Section 2807 of the Code
provides for customer choice in the electric power supply market and requires EDCs,
as “the default service provider,” to “provide electric generation supply service to
[a] customer pursuant to a [PUC]-approved competitive procurement plan.”
66 Pa. C.S. §2807(e)(3.1). Section 2807 of the Code authorizes the PUC to
14
supervise, evaluate, and approve EDC cost recovery of energy supply, including
AECs required by the AEPS Act:
• “The default service provider shall file a plan for
competitive procurement with the [PUC] and obtain
[PUC] approval of the plan . . . .” 66 Pa. C.S.
§2807(e)(3.6).
• “At the time the [PUC] evaluates the plan and prior to
approval, in determining if the default electric service
provider’s plan obtains generation supply at the least cost,
the [PUC] shall consider the default service provider’s
obligation to provide adequate and reliable service to
customers and that the default service provider has
obtained a prudent mix of contracts . . . .” 66 Pa. C.S.
§2807(e)(3.7).
• “[T]he [PUC] may modify contracts or disallow costs
only when the party seeking recovery of the costs” is
found to be at fault for failure to comply with the plan or
fraud, collusion or market manipulation. 66 Pa. C.S.
§2807(e)(3.8).
• “The default service provider shall have the right to
recover on a full and current basis, pursuant to a
reconcilable automatic adjustment clause under section
1307 (relating to sliding scale of rates; adjustments), all
reasonable costs incurred under this section and a [PUC]-
approved competitive procurement plan.” 66 Pa. C.S.
§2807(e)(3.9).
Drawing upon these statutory grants of authority and responsibility, the
PUC conducted rulemaking to implement Section 3 of the AEPS Act and provide
for EDC cost recovery related solely to the ensuring that a certain portion of the
electricity that is sold to customers is generated from alternative energy sources. The
PUC adopted the challenged Regulation, 52 Pa. Code §75.67, after notice and
comment and reasoned deliberation. Section 75.67 of the Regulations governs
alternative energy cost recovery and provides:
15
(a) A default service provider may recover from default
service customers the following reasonable and prudently
incurred costs for compliance with the [AEPS A]ct:
(1) The costs of electricity generated by an
alternative energy system, purchased by a default service
provider, and delivered to default service customers for
purposes of compliance with §75.61 (relating to EDC and
EGS obligations).
(2) The costs of [AECs] purchased and used within
the same reporting period for purposes of compliance with
§75.61.
(3) The costs of [AECs] purchased in one reporting
period and banked for use in later reporting periods,
consistent with §75.69 (relating to banking of [AECs]).
(4) The costs of [AECs] purchased in the true-up
period to satisfy compliance obligations for the most
recently concluded reporting period, consistent with
§75.61(e).
(5) Payments to the [AECs] program administrator
for its costs of administering an [AECs] program,
consistent with §75.64 (relating to alternative energy
credit program administrator).
(6) Payments to a third party for its costs in
operating an [AECs] registry, consistent with §75.70
(relating to the alternative energy credit registry).
(7) The costs levied by a regional transmission
organization to ensure that alternative energy sources are
reliable.
(8) The costs of alternative compliance payments
made under §75.66 (relating to force majeure).
****
16
(d) The costs of compliance with the [AEPS Act] shall be
recovered through an automatic adjustment clause
within the meaning of 66 Pa. C.S. §1307 (relating to
sliding scale of rates; adjustments) and consistent with
§54.187 (relating to default service rate design and the
recovery of reasonable costs) according to the following
standards:
(1) Costs incurred by a default service provider
during the cost-recovery period shall be deferred as a
regulatory asset and fully recovered with a return on the
unamortized balance during the first full 12-month
reporting period after the expiration of the cost-recovery
period in the EDC service territory where it is acting as the
default service provider.
(2) Costs incurred by a default service provider after
the expiration of a cost-recovery period shall be recovered
during the reporting period in which they are incurred,
except as provided for in paragraph (7).
(3) The default service implementation plan shall
include a schedule of rates for the recovery of these costs
as required under 66 Pa. C.S. §1307(a).
(4) A default service provider shall file a report with
the [PUC] within 30 days of the conclusion of each
reporting period that includes the information identified in
66 Pa. C.S. §1307(e)(1).
(5) The [PUC] will hold public hearings on the
substance of these reports, and other matters pertaining to
this subject, as required by 66 Pa. C.S. §1307(e)(2).
(6) The [PUC] will order the default service
provider to provide refunds to or recover additional costs
from default service customers consistent with 66 Pa. C.S.
§1307(e)(3).
(7) The costs of [AECs] purchased by the default
service provider during the true-up period under section
3(e)(5) of the act (73 P.S. §1648.3(e)(5)) shall be
17
recovered during the reporting period in which these costs
are incurred.
52 Pa. Code §75.67(a), (d) (emphasis added).
Upon review, Section 3 of the AEPS Act provides that “any direct or
indirect costs for the purchase by electric distribution of resources to comply with
this section . . . shall be recovered on a full and current basis pursuant to an automatic
energy adjustment clause under 66 Pa. C.S. §1307 as a cost of generation supply
under 66 Pa. C.S. §2807.” 73 P.S. §1648.3(a)(3)(ii) (emphasis added). By its plain
language, Section 3 is limited to costs for the “purchase” by EDCs of resources “to
comply with this section,” meaning Section 3. Id. (emphasis added). Section 3 of
the AEPS Act deals with an EDC’s duty to purchase certain percentages of their total
energy supply from alternative sources and to demonstrate compliance by
accumulating AECs. Section 3 makes clear that qualified alternative energy is a
component of a mix of energy supply contracts EDCs purchase to meet their default
service obligations. Contrary to Petitioners’ assertions, Section 3’s reference to
“resources” refers to alternative energy resources purchased to satisfy Section 3’s
requirements, not an EDC’s obligation to pay for excess generation at the full retail
value under Section 5 of the AEPS Act.
Further, Section 3 incorporates both Sections 1307 and 2807 of the
Public Utility Code, providing the regulatory pathway for EDCs to recover their
Section 3 costs. Section 2807 of the Public Utility Code applies, by its own terms,
“to any type of energy purchased by a default service provider to provide electric
generation supply service, including energy . . . required to be purchased under
. . . the [AEPS] Act.” 66 Pa. C.S. §2807(e)(3.5) (emphasis added). Consequently,
costs associated with interconnection are not “direct or indirect costs” of compliance
with Section 3 of the AEPS Act.
18
Section 75.67(d) of the Regulations closely tracks the statutory
language providing that the “[t]he costs of compliance with the [AEPS A]ct shall be
recovered through an automatic adjustment clause within the meaning of 66 Pa. C.S.
§1307 (relating to sliding scale of rates; adjustments) and consistent with §54.187
(relating to default service rate design and the recovery of reasonable costs).”
52 Pa. Code §75.67(d). The Regulation permits EDCs to recover costs of
compliance with Section 3 of the AEPS Act via the statutory and regulatory
mechanisms established pursuant to Section 1307 and 2807 of the Public Utility
Code.
Petitioners take issue with Section 75.67 of the Regulations,
particularly subsection (a), which provides that a “default service provider may
recover from default service customers the following reasonable and prudently
incurred costs for compliance with the [AEPS A]ct . . . .” 52 Pa. Code §75.67(a)
(emphasis added). Petitioners claim that the PUC impermissibly altered the clear
language of the statute by swapping out the “shall” with “may.” As the PUC
explains, Section 3 of the AEPS Act merely provides that costs “shall be recovered”
pursuant to Sections 1307 and 2807 of the Code. However, it does not provide that
EDCs shall recover every cost they claim. This interpretation is supported by
Sections 1307 and 2807 of the Public Utility Code because those sections require an
EDC to present costs to the PUC for approval as part of a competitive procurement
process. See 66 Pa. C.S. §§1307, 2807. Therefore, not all costs are approved. Any
costs that are approved by the PUC are recovered from ratepayers on a full and
current basis pursuant to an automatic energy adjustment clause under 66 Pa. C.S.
§1307 as a cost of generation supply under 66 Pa. C.S. §2807.
19
Such an interpretation is reasonable and not inconsistent with the plain
language of the AEPS Act. The PUC, as the administrative body charged with
implementing the AEPS Act and the Code, is entitled to substantial deference in the
performance of its duties, and its interpretation of the law should not be overturned
unless it is clear that such construction is erroneous, which Petitioners have not
demonstrated here. See Pennsylvania Power Co. v. Public Utility Commission, 932
A.2d 300, 306 (Pa. Cmwlth. 2007) (extending deference to the PUC’s interpretation
of the Electricity Generation Customer Choice and Competition Act, 66 Pa. C.S.
§§2801-2812).
Moreover, to conclude otherwise and accept the interpretations
advanced by Petitioners would lead to an absurd result. As the PUC explains,
although Petitioners currently limit their argument to interconnection costs as being
an indirect cost of alternative energy, the logical extension of their position is that
all costs associated with project development -- construction, financing, and
operation of a customer-generator system -- would similarly qualify as indirect costs.
This runs counter to two statutory construction principles: (1) “[t]hat the General
Assembly does not intend a result that is absurd, impossible of execution or
unreasonable”; and (2) “[t]hat the General Assembly intends to favor the public
interest as against any private interest.” 1 Pa. C.S. §1922(1), (5). Further, requiring
ratepayers to fully subsidize the development of alternative energy projects would
also run counter to Section 1301 of the Public Utility Code, 66 Pa. C.S. §1301, which
provides “[e]very rate made, demanded, or received by any public utility . . . shall
be just and reasonable, and in conformity with regulations or orders of the [PUC].”
For these reasons, we deny the relief requested as set forth in Requests for Relief A,
B, and C in the Amended PFR.
20
Amended PFR, Requests for Relief D and I
Next, Petitioners claim that any PUC Regulation that allows an EDC to
charge a customer-generator for costs associated with the interconnection of a
customer-generator’s alternative energy system is invalid under the AEPS Act.
Specifically, Petitioners challenge Section 75.39(e)(4) of the Regulations,
52 Pa. Code §75.39(e)(4),9 which requires a customer-generator to pay for studies or
improvements for the interconnection of an alternative energy system, as unlawful
and contrary to the AEPS Act. They also object to the PUC practice of allowing
EDCs to impose costs on customer-generators. Thus, Petitioners ask this Court to
invalidate the PUC Regulations and practices that allow EDCs to charge customer-
generators for distribution system improvement costs related to interconnection.
However, as Petitioners themselves recognize, the declarations sought
under Requests for Relief D and I are wholly dependent upon the success of their
claims under Requests for Relief A through C. Having determined that Petitioners
are not entitled to relief on Requests for Relief A, B, and C, Petitioners are similarly
9
Section 75.39(e)(4) provides:
Upon completion of the interconnection facilities study, and with
the agreement of the interconnection customer to pay for the
interconnection facilities and distribution upgrades identified in the
interconnection facilities study, the EDC shall provide the
interconnection customer with a standard small generator
interconnection agreement within 5 business days.
52 Pa. Code §75.39(e)(4).
21
not entitled to relief on these dependent claims.10 We, therefore, deny the relief
requested as set forth in Requests for Relief D and I in the Amended PFR.
Intervenors’ Application for Intervention, Request for Relief ¶78(a)
Lastly, Petitioners claim they are entitled to the Request for Relief
¶78(a) presented by Intervenors in their Application to Intervene, which concerns
how and when customer-generators are paid by EDCs for excess energy.
Specifically, Petitioners challenge the PUC’s Regulation codified at
52 Pa. Code §75.13(d) and (e), which establishes that EDCs accumulate excess
energy supplied until the end of the reporting year (June 1-May 31), after which the
EDCs pay the customer-generators. According to Petitioners, the AEPS Act does
not grant the PUC rule-making authority over this aspect of the Act. Rather, Section
5 of the AEPS Act granted the PUC the narrow authority to issue “technical and net
metering interconnection rules.” Regulating when and how customer-generators are
paid for the excess energy they produce does not qualify as such a rule. Therefore,
this Court should declare 52 Pa. Code §75.13(d) and (e) invalid and unenforceable.
In 2007, the General Assembly amended Section 5 of the AEPS Act by
adding this provision: “Excess generation from net-metered customer-generators
shall receive full retail value for all energy produced on an annual basis.”
73 P.S. §1648.5. Prior to the amendment, customer-generators were compensated
based on a “monthly standard at the avoided cost of wholesale power.” See In Re
Implementing of Act 35 of 2007: Net Metering and Interconnection, 103 Pa. P.U.C.
91, 2008 WL 6690078 (Pa. P.U.C., filed July 2, 2008). The payment provision
10
We further note that there appears to be disputed issues of fact concerning tariffs and
CIACs, which favors denying summary relief. See Respondents’ Brief at 16; see also Gregory,
185 A.3d at 1205.
22
appears in the same section directing the PUC to develop “technical and net metering
interconnection rules” for customer-generators, which was not altered. Id.
Following the statutory amendment, the PUC made corresponding
changes to its Regulations. Specifically, Section 75.13(d) and (e) of the Regulations
provide:
(d) An EDC and [default service provider] shall credit a
customer-generator at the full retail kilowatt-hour rate,
which shall include generation, transmission and
distribution charges, for each kilowatt-hour produced by a
Tier I or Tier II resource installed on the customer-
generator’s side of the electric revenue meter, up to the
total amount of electricity used by that customer during
the billing period. If a customer-generator supplies more
electricity to the electric distribution system than the EDC
and [default service provider] deliver to the customer-
generator in a given billing period, the excess kilowatt
hours shall be carried forward and credited against the
customer-generator’s kilowatt-hour usage in subsequent
billing periods at the full retail rate. Any excess kilowatt
hours that are not offset by electricity used by the customer
in subsequent billing periods shall continue to accumulate
until the end of the year. For customer-generators involved
in virtual meter aggregation programs, a credit shall be
applied first to the meter through which the generating
facility supplies electricity to the distribution system, then
through the remaining meters for the customer-generator’s
account equally at each meter’s designated rate.
(e) At the end of each year, the [default service provider]
shall compensate the customer-generator for any
remaining excess kilowatt hours generated by the
customer-generator that were not previously credited
against the customer-generator’s usage in prior billing
periods at the [default service provider]’s price to compare
rate.
52 Pa. Code §75.13(d), (e) (emphasis added). The IRRC approved the changes,
noting they implemented the General Assembly’s amendment and were consistent
23
with statutory authority. See PUC Brief, Exhibit 3 (IRRC Approval Order,
Regulation No. 57-264 (#2724), 11/6/08).
Section 5 of the AEPS Act authorizes the PUC to develop “technical
and net metering interconnection rules.” 73 P.S. §1648.5 (emphasis added).
Regulations promulgated pursuant thereto are lawful if they were “(a) adopted
within the agency’s granted power, (b) issued pursuant to proper procedure, and (c)
reasonable.” Marcellus Shale, 292 A.3d at 927. As this Court held in Hommrich I,
231 A.3d at 1037, the General Assembly did not task the PUC with redefining
statutory terms and eligibility standards. However, unlike the regulation at issue in
Hommrich I, the challenged Regulation here does not redefine terms or eligibility
standards. Rather, the Regulation provides necessary guidance on net metering,
specifically, how excess generation is measured, credited, and compensated at the
full retail rate on a yearly basis, consistent with the terms of the AEPS Act. By its
very definition, “net metering” is “[t]he means of measuring the difference between
the electricity supplied by an electric utility and the electricity generated by a
customer-generator when any portion of the electricity generated by the alternative
energy generating system is used to offset part or all of the customer-generator’s
requirements for electricity.” Section 2 of the AEPS Act, 73 P.S. §1648.2.
Customer-generators are entitled to receive compensation for the “excess
generation,” i.e., the difference between the electricity generated by a customer-
generator and electricity supplied by the utility, “at the full retail value . . . on an
annual basis.” 73 P.S. §1648.5 (emphasis added). Although Petitioners advocate
for monthly or even quarterly revenue, Section 5 of the AEPS Act clearly provides
24
for compensation on an annual basis.11 73 P.S. §1648.5. Upon review, the
Regulation falls within the ambit of the PUC’s regulatory authority under the AEPS
Act and tracks the statutory language. For these reasons, we deny the relief
requested in Intervenors’ Application for Intervention, Request for Relief ¶78(a).
III. Conclusion
Based on the foregoing, we deny Petitioners’ ASR.
MICHAEL H. WOJCIK, Judge
Judge Fizzano Cannon did not participate in the decision of this case.
11
We further note that Section 5’s “annual basis” provision corresponds with Section
3(e)(5) of the AEPS Act, which provides that the alternative energy credits program shall be based
on a 12-month “reporting period” from June 1 through May 31. 73 P.S. §1648.3(e)(5); see Section
2 of the AEPS Act, 73 P.S. §1648.2 (defining “reporting period’).
25
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
David N. Hommrich, :
:
Petitioner :
:
v. : No. 463 M.D. 2022
:
Commonwealth of Pennsylvania, :
Pennsylvania Public Utility :
Commission, :
:
Respondent :
ORDER
AND NOW, this 13th day of August, 2025, Petitioner’s Application for
Summary Relief is DENIED.
__________________________________
MICHAEL H. WOJCIK, Judge
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
David N. Hommrich, :
Petitioner :
:
v. : No. 463 M.D. 2022
: Argued: April 9, 2025
Commonwealth of Pennsylvania, :
Pennsylvania Public Utility :
Commission, :
Respondent :
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
CONCURRING AND DISSENTING OPINION
BY JUDGE WALLACE FILED: August 13, 2025
I would hold, based on the plain statutory text, that excess alternative energy
purchased from net metered customer-generators under Section 5 of the Alternative
Energy Portfolio Standards Act (AEPS Act)1 is a “resource” as that term appears in
Section 3(a)(3)(ii) of the AEPS Act,2 and I would grant summary relief with respect
to Request for Relief A. I otherwise join the Majority’s thoughtful opinion, denying
1
Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. § 1648.5.
2
73 P.S. § 1648.3.
summary relief as to the remaining requests. Therefore, I respectfully concur and
dissent.
______________________________
STACY WALLACE, Judge
SW - 2