holding that “the contracting 13 officer’s election to terminate for the government’s convenience is conclusive” absent “bad faith or [a] clear abuse of discretion”
How later courts described this case
- holding that “the contracting 13 officer’s election to terminate for the government’s convenience is conclusive” absent “bad faith or [a] clear abuse of discretion”
- describing the intersection between Heyer-like claims and this court’s § 1491(b) bid protest jurisdiction
- noting that the relief sought, although not dispositive, informs whether FASA applies
Written by the judges who cited it.
The opinion
In the United States Court of Federal Claims
No. 22-1870
(Filed: July 18, 2025)
(Re-issued: July 25, 2025) *
********************
SIEMENS GOVERNMENT
TECHNOLOGIES, INC.,
Plaintiff,
v.
THE UNITED STATES,
Defendant.
*********************
Robert Nichols, Washington, D.C., with whom were Michael
Bhargava and Logan Kemp, for plaintiff, Siemens Government
Technologies, Inc.
Thomas J. Adair, Trial Attorney, United States Department of Justice,
Commercial Litigation Branch, Washington, D.C., with whom were Yaakov
M. Roth, Acting Assistant Attorney General, Patricia M. McCarthy,
Director, and Deborah A. Bynum, Assistant Director, for the defendant.
OPINION
BRUGGINK, Senior Judge.
This breach of contract case arises from the U.S. Army Corps of
Engineering’s (“COE”) energy savings project at Spangdahlem Air Force
Base in Germany. Plaintiff—Siemens Government Technologies, Inc.
(“Siemens”)—advances various theories in support of one overarching
proposition: defendant owes Siemens roughly $3,000,000, which is the
*
This opinion was originally issued under seal to afford the parties an
opportunity to propose redactions of protected information. The parties agree
that no redactions are necessary.
amount Siemens spent bidding on the Spangdahlem project. Bringing claims
under the Contract Dispute Act (“CDA”) and this court’s bid protest
jurisdiction, Siemens sues in this court to recover those costs. Defendant
moves to dismiss under Rule 12(b)(1) and 12(b)(6) of the Rules of the United
States Court of Federal Claims. The matter is fully briefed, and the court
held oral argument on June 10, 2025. For the reasons set out herein, we deny
defendant’s motion.
BACKGROUND 1
I. National Energy Conservation Policy Act
This case originates in 1978. That year, Congress enacted the
National Energy Conservation Policy Act (“NECPA”). Pub. L. No. 95-619,
92 Stat. 3206 (1978) (codified at 42 U.S.C. § 8201 et seq). NECPA tasks the
Department of Energy (“DOE”) with overseeing the Act’s energy savings
program. See 42 U.S.C. § 8287. The program empowers DOE to award
umbrella indefinite delivery, indefinite quantity (“IDIQ”) energy savings
performance contracts (“energy contracts”) to energy contractors. About
Federal Energy Savings Performance Contracts, Energy.gov (last accessed
June 30, 2025), https://www.energy.gov/femp/about-federal-energy-
savings-performance-contracts.
Under NECPA, an energy contract provides for the “design,
acquisition, installation, testing,” “operation, maintenance, and repair” of
energy or water conservation measures. § 8287c(3); see also FAR 2.101.
Congress designed energy contracts to “achiev[e] energy savings,” along
with other “ancillary” “benefits.” §§ 8287, 8287c(3). An energy or water
conservation measure is anything that improves energy or water use, is “life
cycle cost effective,” and involves, among other things, the conservation and
improvement of energy and water operations and efficiencies. §§ 8259(4),
8287c(4)(A)–(B). And “energy savings” are “reduction[s] in the cost of
energy, water, or wastewater treatment,” an “increase[]” in the “efficient use
of existing energy” and “water” “source[s],” the “sale or transfer” of excess
energy or water, or “any revenue generated from a reduction in energy or
water use.” § 8287c(2)(A)–(F).
Furthering Congress’ goal of securing energy savings, NECPA ties
energy contractors’ earnings to the amount of cost savings they can generate
1
The facts are taken from the complaint and assumed to be true for purposes
of ruling on defendant’s motion.
2
for the government. So while energy contractors bear the cost of
implementing energy savings measures, they get a cut “of any energy savings
directly resulting from implementation of [energy savings] measures during”
the contract’s lifespan. § 8287(a)(1). Said differently, energy contractors’
pay is performance-based, rather than a flat fee.
NECPA implements this incentive structure through a two-tiered
procurement process. First, DOE awards an umbrella contract to an energy
contractor, which makes the contractor eligible to bid on other federal
agencies’ energy projects. See § 8287(c).
Next, federal agencies can solicit bids from umbrella contract holders
and award task orders for energy conservation measures. See id. The agency
begins by notifying all umbrella contract holders that “the agency proposes
to discuss energy savings performance services” and requesting
“submissions” “of interest” and “contractor qualifications.”
§ 8287(c)(1)(A). The agency then reviews energy contractors’ submissions
and selects one or more energy contractors “to conduct site surveys,
investigations, feasibility designs and studies, or similar assessment[s] . . . .”
§ 8287(c)(1)(B), (D)(i)–(ii). Typically, those investigations take the form of
preliminary assessments prepared by the energy contractors.
See Am. Compl. ¶ 18. Then, the agency can issuance a notice of intent to
award a task order, and the selected contractor prepares an audit prior to the
issuance of a task order. Id. If satisfied with the audit, the agency can issue
a task order—an entirely new contract—for energy savings services to the
contractor. § 8287(c)(1)(F)–(G). The new task order contract will be
between the agency and the contractor, while the contractor still retains the
separate umbrella contract with DOE.
As relevant here, the umbrella contract contains a key additional
provision. Section H.6.2 warns that “[t]he agency will not be responsible for
any costs incurred, such as proposal preparation costs or the costs incurred
in conducting the [investment grade audit] unless a [task order] is awarded
or authorized by the [contracting] agency [contracting officer].” Am. Compl.
¶ 21.
II. Siemens and Spangdahlem Air Force Base
On October 11, 2007, DOE awarded Siemens an umbrella energy
contract. Id. ¶ 16. Eight years later, COE issued an opportunity notice for
an energy savings project at Spangdahlem Air Force Base in Germany. Id.
3
¶ 22. COE’s goal was to reduce energy consumption and maximize reliance
on renewable energy sources. Id. ¶ 23.
Siemens responded to the opportunity notice, and COE sent Siemens
two selection letters. Id. ¶¶ 24–25. The letters informed Siemens that it had
been selected for the Spangdahlem project, explained that development costs
were only recoverable for energy cost savings measures that were acceptable
to the government and incorporated in the task order, and authorized Siemens
to prepare a preliminary assessment. Id. ¶¶ 26–27.
In March 2016, Siemens submitted its 110-page assessment. Id. ¶ 28.
The assessment outlined thirty-seven energy conservation measures, which
would cost $35,093,097 over 13.5 years. Id. The assessment predicted
energy savings of $60,287,706 over the same period. Id.
After reviewing the assessment, COE sent Siemens a notice of intent
to award a task order and a request for proposal. Id. ¶ 30. Per the request for
proposal, COE instructed Siemens to prepare an investment grade audit that
would “includ[e] detailed cost and pricing data” for the energy conservation
measures. Id.
Four months later, COE and the Air Force met with Siemens to
discuss the project. Id. ¶ 31. Air Force officers said that German labor
regulations would apply to the project, but they assured Siemens that the
government would meet with Germany’s regional construction office and
figure out which labor regulations would apply. 2 Id. ¶ 32.
In the meantime, COE gave Siemens conflicting instructions on how
to prepare the audit. Originally, Siemens designed the audit as a single-phase
study, 3 which meant that Siemens would provide recommendations for all
thirty-seven energy conservation measures in one audit. See id. ¶¶ 30, 33.
But by September 2016, COE had changed its mind and amended the request
for proposal to require a two-phase study. Id. That meant Siemens would
do two audits, the first for four conservation measures and the second for the
2
Siemens does not tell us who was present or the specifics of what was said.
3
Siemens cites no specific verbal or written instructions from COE regarding
how COE wanted the audit prepared. See Am. Compl. ¶¶ 30–32. Nor does
the umbrella energy contract shed light on what a single-phase study would
look like. See Mot. to Dismiss Attach. 1 at 40–41.
4
remaining measures. See id. COE gave Siemens a little over a month to
complete the phase I audit. Id. ¶¶ 33, 35.
Siemens requested a time extension for the phase I audit, which COE
denied. Id. ¶¶ 34–35. Siemens insisted it needed Spangdahlem’s energy
utility data and rate structure information before it could finish the audit.
Id. ¶ 34. COE believed otherwise and refused Siemen’s request. Id. ¶ 35.
Siemens nevertheless completed its phase I audit in October 2016.
Id. ¶ 36. It later submitted a revised phase I audit in December 2016. Id.
Three days later, the Spangdahlem Commander stated that the Air Force
wanted a single-phase, not two-phase, audit. Id. ¶ 37. COE then rejected the
phase I audit and told Siemens to start over. Id. ¶¶ 38–39.
While Siemens attempted to put together a new audit, another issue
plagued its efforts: Auftragsbautengrundsatze 1975 (“ABG-75”). ABG-75
is an agreement between the United States and Germany that governs
American military construction projects in Germany. Id. ¶ 40.
Projects subject to ABG-75 must apply German labor regulations, which
require that some construction tasks use unionized German labor. Id.
Germany’s regional construction offices decide whether ABG-75 applies to
a project. Id. ¶ 41.
Siemens had encountered ABG-75 before. Specifically, Siemens
dealt with ABG-75’s application while working on a military project in
Sembach, Rhineland-Pfalz, Germany. Id. ¶ 42.
Aware that ABG-75 could apply, Siemens asked COE during the July
2016 meeting whether ABG-75 would apply to the Spangdahlem project.
Id. ¶ 43. COE assured Siemens that the government would ask the regional
German construction office. Id. Yet by November 2016, COE had done
nothing. Id. ¶¶ 44–45. Siemens’s requests for clarification on the ABG-75
issue went unanswered until the Spangdahlem Command also pressed COE
for an answer. Id. ¶ 47. Only then did COE reply, saying that it would reach
out to the construction office. Id. ¶ 48. Meanwhile, Siemens designed the
new audit on the premise that ABG-75 would not apply. Id. ¶¶ 48–50.
COE also did not respond to Siemens’s requests for information on
Spangdahlem’s energy usage. Siemens repeatedly asked COE for
Spangdahlem’s energy usage statistics, as well as ABG-75’s applicability.
Id. ¶¶ 51–52. COE did not respond. See id. Siemens warned that completing
its audit would be “very difficult” without Spangdahlem’s energy statistics.
5
Id. ¶ 53. COE still did not answer. Lacking other options, Siemens met with
Spangdahlem Command to discuss energy statistics. Id. ¶ 54. That prompted
COE to finally respond, namely by reprimanding Siemens for meeting with
Spangdahlem Command without notifying COE. Id.
By March 2017, Siemens, along with Spangdahlem Command, again
pressed COE for answers on ABG-75’s applicability. Id. ¶ 56. Seven
months later—and three months after Siemens submitted its new audit—
COE finally met with the regional German construction office. Id. ¶¶ 58–59.
German officials told COE that not only did ABG-75 apply to the
Spangdahlem project, but that the project violated the treaty because “it
involved the construction of a new natural gas facility by a contracting
process” that transgressed German law. Id. ¶ 59. To avoid ABG-75’s
application, the German officials told COE that it would have to limit the
project to repair, replacement, or renovation work. Id.
COE turned to Siemens and ordered Siemens to fix the problem.
Id. ¶ 60. Nevertheless, COE simultaneously warned that the Air Force was
going to cancel the procurement. Id. Siemens reminded COE that ABG-75
was a “government to government issue to resolve.” Id. ¶ 61.
Still, throughout the balance of 2017 and early 2018, Siemens conferred with
COE and German agencies in an effort to resolve the ABG-75 issue. Id. ¶ 62.
Ultimately, Siemens joined forces with COE and Air Force and petitioned
U.S. Air Forces in Europe 4 to request a waiver of ABG-75 for the
Spangdahlem project from the German government. Id. ¶ 63.
U.S. Air Forces in Europe refused to advance the requst. Id. ¶ 64.
Citing the request’s “political sensitivity,” it advised that it “must be
evaluated for its relative importance to other ongoing programs in Germany.”
Id. In the meantime, it considered “the project to be on-hold.” Id.
Even so, COE requested a third audit from Siemens for six non-
construction energy measures. Id. ¶ 67. Siemens prepared the audit and
submitted it in late 2018. Id. ¶¶ 68–69. Six months later, COE cancelled the
Spangdahlem project altogether. Id. ¶ 70. In total, Siemens spent $2,889,715
preparing the assessment and three audits. Id. ¶ 71.
4
U.S. Air Forces in Europe is the overarching Air Force command in Europe.
See About Us, U.S. Air Forces in Europe – Air Forces Africa (last accessed
July 8, 2025), https://www.usafe.af.mil/About-Us/.
6
III. Procedural History
In February 2020, Siemens submitted certified claims to COE and
DOE for preparing its bid for the Spangdahlem project. See id. ¶ 74. Siemens
cited the energy contract’s section H.6.2, which granted COE discretion to
cover bid preparation costs. Id. ¶ 74. COE denied Siemens’s claim. Id. ¶
76. DOE likewise denied Siemens’s duplicative claim. Id. Siemens then
sued here and at the Armed Services Board of Contract Appeals. (We later
consolidated the Contract Appeals action with this case.)
While a bit confusing, we understand Siemens’s claims as follows.
First, Siemens’s Count I claim is for a breach of contract pursuant to the
CDA. For that claim, Siemens alleges that defendant breached the (express)
umbrella energy contract between Siemens and DOE. That breach resulted,
however, not from DOE’s conduct but from COE’s alleged wrongdoing.
Specifically, Siemens alleges that COE’s refusal to cover Siemens’s bid
preparation costs—as allowed by section H.6.2 of the energy contract—
amounts to an abuse of discretion. 5 See id. ¶¶ 80–90. COE’s abuse of
discretion, in turn, breached the energy contract that Siemens had with DOE.
See id. Said succinctly, COE’s misconduct and abuse of discretion breached
the express contract between DOE and Siemens.
Counts II and III are brought pursuant to our bid protest jurisdiction.
Count II claims that COE also breached an implied contract that Siemens’s
alleges arose between it and COE when COE invited Siemens to bid on a
task order award. Siemens alleges that an implied contract to fairly and
honestly consider its bid was breached by COE’s assertedly arbitrary and
unreasonable conduct. Id. ¶ 93 (citing Heyer Products, Co. v. United States,
140 F. Supp. 409, 413 (Ct. Cl. 1956)). Having failed to act reasonably, COE,
and by extension, the government, is liable for Siemens’s bid preparation
costs.
Under Count III, Siemens claims that defendant violated various FAR
provisions which require that bidders receive a fair opportunity to compete
for a task order. See id. ¶¶ 100–11.
Defendant moves to dismiss under Rule 12(b)(1) and (6). It argues
that Counts II and III are barred by the Federal Acquisition Streamlining Act
5
While Siemens lists “at least five ways” COE allegedly breached the energy
contract, they boil down to an abuse of discretion argument. See Am. Compl.
¶¶ 84–89.
7
(“FASA”) while Counts I and II fail to state a claim. For the reasons set out
below, we deny the motion.
DISCUSSION
I. Standard of Review
Subject matter jurisdiction is the “threshold matter” before this court
can consider a case’s merits. Golden v. United States, 137 Fed. Cl. 155, 168
(2018). When a Rule 12(b)(1) motion challenges our jurisdiction, the
plaintiff must establish jurisdiction by a preponderance of the evidence.
Williams v. United States, 165 Fed. Cl. 72, 74 (2023). We view the
complaint’s allegations as true and construe them in a light most favorable
to the plaintiff. Id.
To avoid dismissal for failure to state a claim under Rule 12(b)(6), “a
complaint must allege facts ‘plausibly suggesting (not merely consistent
with)’ a showing of entitlement to relief.” Acceptance Ins. Cos. v. United
States, 583 F.3d 849, 853 (Fed. Cir. 2009) (quoting Bell Atl. Corp. v.
Twombly, 550 U.S. 544, 557 (2007)). We accept all well-pleaded factual
allegations as true and draw all reasonable inferences in plaintiff’s favor.
Harris v. United States, 868 F.3d 1376, 1379 (Fed. Cir. 2017).
II. FASA Does Not Bar Siemens’s Counts II and III Claims
Defendant argues that FASA bars Counts II and III of plaintiff’s
complaint. 6 FASA bars bid protests arising in connection with the issuance
or proposed issuance of a task order. Both the assessment and the audits,
defendant claims, were links in the direct causal chain leading to the possible
issuance of a task order. Defendant thus concludes that Siemens’s suit is in
connection with a task order because the nonpayment of costs connects to
actions that were in the direct casual chain leading to plaintiff’s pursuit of a
task order.
Siemens counters that FASA only applies to the issuance or proposed
issuance of a task order, not just to any action related to a task order. Because
Siemens does not challenge the non-issuance of a task order, but rather
6
FASA does not apply to CDA breach-of-contract claims, see Orbis Sibro,
Inc. v. United States, 117 Fed. Cl. 446, 455 (2014), and defendant (correctly)
does not argue that FASA bars Siemens’s Count I claims.
8
challenges defendant’s refusal to cover Siemens’s bid preparation costs,
FASA does not apply. We agree with plaintiff.
FASA provides that “[a] protest is not authorized in connection with
the issuance or proposed issuance of a task or delivery order” absent limited
circumstances. 10 U.S.C. § 3406(f). “Consistent with the statutory focus on
‘issuance,’” FASA will bar a protest “if it challenges the issuance of the task
order directly or by challenging a government action . . . whose
wrongfulness would cause the task order’s issuance to be improper.”
Percipient.ai, Inc. v. United States, 104 F.4th 839, 847 (Fed. Cir. 2024),
reh’g en banc granted and opinion vacated, 121 F.4th 1311 (Fed. Cir. 2024)
(mem.). 7 Mere connection to a task order, however, is not enough for FASA
to apply. See id. at 849. Rather, the protest must relate to the “issuance or
proposed issuance of a task order” before FASA will bar the suit. Id. (cleaned
up). Therefore, while FASA bars challenges to “government action[s] in the
direct causal chain sustaining the issuance of a task order,” not “all actions
taken under or after issuance of a proper task order” are “directly and casually
connected” to a task order’s issuance. Id. at 850.
FASA does not bar Siemens’s suit. Like the plaintiff in Percipient,
Siemens does not “assert the wrongfulness of, or seek to set aside, any task
order.” Percipient, 104 F.4th at 846–47. Instead, Siemens pursues a purely
monetary remedy: reimbursement of the money it spent preparing the
assessment and audits. Am. Compl. ¶¶ at 28–29 (describing relief sought);
see also Percipient, 104 F.4th at 851 (finding that FASA did not apply to
Percipient’s suit because its “requested relief would not alter” the task order’s
issuance); SRA Int’l, Inc. v. United States, 766 F.3d 1409, 1414 (Fed. Cir.
2014) (noting that the relief sought, although not dispositive, informs
whether FASA applies). Because Siemens does not challenge either “the
issuance of the task order” or “a government action . . . whose wrongfulness
would cause the task order’s issuance to be improper,” Percipient, 104 F.4th
at 847, the bar is not applicable.
7
In Percipient, the Federal Circuit granted the government’s petition for
rehearing en banc and vacated the panel opinion, reinstating the appeal.
Percipient, 121 F.4th at 1312. The Federal Circuit limited the rehearing to
Percipient’s standing component and instructed that “[t]he court will not
revisit and does not require additional briefing on the” FASA bar. Id.
Thus, while the en banc court’s order deprives the panel’s “opinion of
precedential effect,” O’Connor v. Donaldson, 422 U.S. 563, 577 n.12 (1975),
the panel opinion remains “at least persuasive” authority for our court,
Crowson v. Washington County, 983 F.3d 1166, 1187 n.10 (10th Cir. 2020).
9
Our recent decision in another Siemens lawsuit involving application
of NECPA is instructive. See Siemens Gov. Techs., Inc. v. United States, 176
Fed. Cl. 450 (2025). There, Siemens sued to recover money it spent on
energy savings assessments for six Navy bases. Id. at 453. Initially, the
Navy awarded Siemens six contracts but later cancelled two of them after
Siemens learned that the Navy had duplicate contracts for two of the bases.
Id. at 454–55. Siemens sued to recover its bid preparation costs for those
two bases. Id. at 455. Defendant moved to dismiss, arguing that FASA
barred Siemens’s claims. Id.
This court held that FASA did not bar Siemens’s suit. First, the court
noted that the preexisting contracts for energy savings services meant that
the “task order was void from the start.” Id. at 456–59. As relevant here, the
court also ruled that FASA did not apply because “Siemens has never sought
to set aside or generally interfere with any pending or issued task order; it
only wishes to be made whole after being led astray by the U.S. Navy’s false
procurement needs—a claim FASA does not bar.” Id. at 457. To be sure,
this court acknowledged that if Siemens had tried to either “rescind the non-
redundant task order or block award of a task order,” that would be in
connection to a task order and barred by FASA. Id. Instead, because “[n]o
task order” would be revoked, this court ruled that FASA did not apply. Id.
at 459.
So too here. Siemens’s suit proceeds on an identical theory (wrongful
government action means it can recover its bid preparation costs) for the
same requested remedy (monetary damages). Thus, our decision in Siemens
suggests the same result here.
Defendant’s counterarguments are unpersuasive. First, defendant’s
primary approach—counting how often Siemens mentions the words “task
order” or “procurement”—says little about whether Siemens challenges the
issuance or proposed issuance of a task order.
Second, defendant cannot distinguish Percipient. While Percipient
may be distinct in some regards, Siemens’s pursuit of a wholly monetary
remedy “mak[es] this case [more] like Percipient” than some of our other
post-Percipient decisions. Siemens, 176 Fed. Cl. at 459. In Computer World
Services Corporation v. United States, for example, we found that FASA
barred a suit seeking to empanel a new technical evaluation committee
because that would result in the court “effectively rescind[ing]” the task order
award, which “[o]bviously . . . connects . . . to the task order.” 173 Fed. Cl.
10
582, 586 (2024). Similarly, in Radiance Technologies, Inc. v. United States,
we found that plaintiff’s requested relief—changing solicitation language to
“allow[] additional” “not currently qualified” bidders to submit offers—
“would necessarily” affect the task order’s issuance. 174 Fed. Cl. 197, 204
(2024). Other decisions are to similar effect. See, e.g., Prime Physicians,
PLLC v. United States, 174 Fed. Cl. 190, 196 (2024) (FASA barred challenge
that targeted a solicitation’s terms).
Third, defendant is incorrect that Siemens’s claims are directly and
causally connected to the issuance of a task order. It is true that section H.6.2
of the energy contract outlines the steps leading up to the agency’s decision
whether to award a task order. And it is also true that Siemens seeks to
recover the money it spent following those steps. But it is not true that, in
doing so, Siemens’s claims are directly and causally connected to the
issuance of a task order. To be so connected, Siemens would need to
challenge the task order’s language or defendant’s decision not to award a
task order. Cf. Radiance Techs., 174 Fed. Cl. at 204 (applying FASA to a
challenge to a solicitation’s terms). Siemens does neither. All it asks is that
defendant cover its bid preparation costs, a claim which is not connected
directly to the issuance of task order. See Siemens, 176 Fed. Cl. at 459;
Percipient, 104 F.4th at 851. Accordingly, given that Siemens’s claims are
not directly and causally connected to the issuance of a task order, FASA
does not apply.
III. Siemens States a Claim Under Count I for Breach of the Energy
Contract
In this section, we analyze whether Count I of Siemens’s complaint—
which alleges that COE breached section H of the express energy contract
that exists between Siemens and DOE—fails to state a claim.
Defendant argues that Siemens fails to state a claim for breach of
contract. Defendant notes that the energy contract gave the contracting
officer discretion as to whether defendant would pay for Siemens’s bid
preparation costs. As a result, it argues, Siemens cannot hold defendant
liable for the contracting officer refusing to exercise that discretion. Further,
defendant asserts that the Federal Circuit’s decision in another Siemens
lawsuit estops Siemens from arguing that defendant must pay for Siemens’s
bid preparation costs. See Siemens Gov. Techs., Inc. v. Sec’y of the Navy,
2024 WL 2043201, at *4 (Fed. Cir. May 8, 2024) (holding in a case in which
the Navy awarded and then rescinded two task orders that the Navy was not
required to pay for Siemens’s bid preparation costs).
11
Siemens responds that it adequately pleads a breach of contract.
Siemens notes that the energy contract, namely, section H.6.2, allows
defendant to reimburse Siemens’s bid preparation costs even if it does not
mandate it. Under the circumstances, then, defendant abused its discretion
by not authorizing payment of Siemens’s bid preparation costs.
To show a breach of contract, Siemens must plead four things.
San Carlos Irrigation & Drainage Dist. v. United States, 877 F.2d 957, 959
(Fed. Cir. 1989). Those are (1) a valid contract exists between it and
defendant, (2) there is an obligation or duty arising out of the contract, (3)
defendant breached that duty, and (4) that breach damaged Siemens. Id.
The parties do not dispute that an express contract exists (i.e., the
energy contract between Siemens and DOE) or that it gives defendant
discretion to pay for bid preparation costs. Even so, when a contract gives
the government “unilateral authority to make a decision affecting its
contracting partner,” the “government’s ‘judgment should be exercised not
capriciously or fraudulently, but reasonably, and with due regard to the rights
of both contracting parties.’” 27-35 Jackson Ave, LLC v. United States, 127
F.4th 1314, 1319 (Fed. Cir. 2025) (quoting Ripley v. United States, 223 U.S.
895, 701–02 (1912)). Indeed, while the government’s exercise (or non-
exercise) of contractual discretion is often “conclusive,” that discretion “is
not without limits.” Id. (quoting Kihlberg v. United States, 97 U.S. 398, 400
(1878)). Put another way, “[a] party vested with contractual discretion must
exercise his discretion reasonably and may not do so arbitrarily or
capriciously.” Id. (quoting Pac. Far E. Line, Inc. v. United States, 394 F.2d
990, 998 (Ct. Cl. 1968)). This duty satisfies the second element Siemens
must allege.
Siemens also plausibly alleges that defendant, acting through COE,
breached that duty when it abused its discretion in refusing to pay for
Siemens’s bid preparation costs under the energy contract with DOE.
Siemens contends that it wasted millions of dollars preparing audits for a
project which defendant should have known was untenable. Indeed, even
while COE promised to investigate ABG-75’s applicability, it dragged its
feet for over a year before finally meeting with German officials.
See Am. Compl. ¶¶ 32, 41, 43, 58. What is worse, Siemens alleges, is that
COE’s intransigence persisted despite multiple attempts by Siemens to
clarify whether ABG-75 applied. Id. ¶¶ 44–48, 52–53, 55, 57. All the while,
Siemens—relying on COE’s assurances—racked up costs preparing audits
for a doomed project. See id. ¶¶ 58–59.
12
Beyond mishandling ABG-75, Siemens plausibly alleges that COE
did not provide Siemens with critical information. Siemens repeatedly
requested information on energy usage at Spangdahlem—information that
was critical for Siemens’s audits. Id. ¶ 51. For example, Siemens warned
that the lack of energy usage information would make “modeling” “the
project” “very difficult to complete.” Id. ¶ 53. COE did not respond.
And when Siemens met with Spangdahlem Command to get the base’s
energy statistics, COE upbraided Siemens, saying that “Siemens MUST
NOT meet with the Spangdahlem leadership without government
participation AND advance knowledge of the meeting.” Id. ¶ 54.
Meanwhile, COE failed to provide critical information to Siemens. Id. ¶ 55.
Siemens also plausibly alleges that COE’s about-face on how to
prepare the audit further exacerbated Siemens’s costs. Rather than
consulting with Spangdahlem Command, COE wasted Siemens’s time and
resources preparing an audit that Spangdahlem Command did not want. Id.
¶¶ 33, 37. Worse, after COE discovered that ABG-75 applied, it asked for a
third audit—which Siemens completed—even though it knew the Air Force
was likely going to cancel the solicitation. Id. ¶¶ 60, 64, 66–70.
In short, Siemens plausibly alleges a breach of contract in that, but for
COE’s refusal to timely meet with German officials, provide energy
statistics, and ascertain what kind of audit Spangdahlem needed, Siemens
would not have spent approximately $3,000,000 on a project destined to go
nowhere. Taken together, these allegations—which we assume to be true for
the purposes of a motion to dismiss—plausibly establish that COE, and, by
extension, defendant, abused its discretion by refusing to pay for Siemens’s
bid preparation costs. Plaintiff’s claimed costs fill in the fourth element of
the necessary pleading.
Defendant’s objections fall short. While defendant insists that the
exercise of “its unilateral discretion does not create a viable cause of action,”
Def.’s Reply in Support of Mot. to Dismiss at 12, that is misguided.
Even when a contractual provision vests the government with “essentially
unfettered discretion,” contractors “can recover for the government’s failure
to exercise an option if the government’s failure was in bad faith.”
Vanquish Worldwide, LLC v. United States, 147 Fed. Cl. 390, 401 (2020)
(quoting Dekatron Corp. v. United States, 128 Fed. Cl. 115, 118, (2016)).
And the Federal Circuit has recognized as much when the government
terminates contracts for convenience. See T&M Distributors, Inc. v. United
States, 185 F.3d 1279, 1283 (Fed. Cir. 1999) (holding that “the contracting
13
officer’s election to terminate for the government’s convenience is
conclusive” absent “bad faith or [a] clear abuse of discretion”).
In fact, defendant’s own cases confirm what we noted earlier:
defendant can be liable for abusing its discretion when exercising a unilateral
contractual right. See Vanquish Worldwide, LLC v. United States, 164 Fed.
Cl. 671, 686 (2023) (“A contractor can recover for the government’s failure
to exercise an option if the government’s failure was in bad faith.” (cleaned
up)); Kurkijan v. Sec’y of the Army, No. 2020-2201, 2021 WL 3520624, at
*5 n.1 (Fed. Cir. Aug. 11, 2021) (recognizing that failure to exercise an
option “is not actionable unless the failure is motivated by bad faith or is
arbitrary and capricious.” (quoting Kurkijan, ASBCA No. 61154, 20-1 BCA
¶ 37,594)); Hi-Shear Tech. Corp. v. United States, 53 Fed. Cl. 420, 436
(2002) (similar), aff’d, 356 F.3d 1372 (Fed. Cir. 2004).
The energy contract obligated defendant to exercise its discretion
“reasonably and fairly,” not “arbitrar[ily] and capricious[ly].” 27-35 Jackson
Ave, 127 F.4th at 1320 (quoting W.G. Cornell Co. of Washington, D.C., Inc.
v. United States, 376 F.2d 299, 313 (Ct. Cl. 1967)). Because Siemens has
plausibly alleged that defendant’s actions were arbitrary and capricious, it
states a cognizable claim for breach of the energy contract.
Nor is Siemens’s claim barred by issue preclusion. Defendant claims
that Siemens’s loss in its other NECPA case bars its CDA claim here because
both involve the umbrella contract. Issue preclusion bars a subsequent cause
of action if (1) the issue is identical to one decided in the first action, (2) the
issue was actually litigated in the first action, (3) resolution of the issue was
essential to final judgment in the first action, and (4) plaintiff had a full and
fair opportunity to litigate the issue in the first action. Angel v. United States,
172 Fed. Cl. 102, 116 (2024).
The first step is not met here because the issues are not identical. In
the Federal Circuit appeal, Siemens argued the issue of whether an awarded
task order mandated that defendant pay for Siemens’s bid preparation costs.
See Siemens, 2024 WL 2043201, at *4. Here, Siemens argues that the energy
contract permits—but does not require—the defendant to pay for Siemens’s
bid preparation costs and that defendant’s refusal to do so constituted an
abuse of discretion. Am. Compl. ¶ 89. As a result, the issues are not
identical, and Siemens’s argument is not precluded.
14
IV. Siemens States a Claim Under Count II for Breach of the Implied
Contract to Consider Bids Fairly and Honestly
In this section, we analyze whether Count II of Siemens’s
complaint—which alleges that COE breached the implied contract to treat
bids fairly and honestly between itself and Siemens—fails to state a claim.
Defendant argues that the energy contract forecloses Siemens’s
implied contract claim. As noted, the energy contract contains a clause
vesting defendant with discretion on whether it will pay Siemens’s bid
preparation costs. As a result, defendant maintains that there cannot also be
an implied contract for preparation costs because the energy contract already
addresses that matter. Nor can Siemens, according to defendant, use implied
duties to replace the energy contract’s express language.
Siemens responds that it can advance its implied contract claim for
three reasons. First, Siemens argues that its implied contract claim does not
relate to the same subject as the energy contract claim because one involves
DOE and the other is against COE. Second, Siemens argues that its implied
contract claim is an alternative basis for relief if its express contract claim
fails. Finally, Siemens argues that caselaw recognizes the viability of
implied contract claims in the procurement context.
Historically, “federal procurement decisions” were “largely immune
from judicial review” until Heyer Products Company v. United States.
Validata Chem. Servs. v. U.S. Dep’t of Energy, 169 F. Supp. 3d 69, 75
(D.D.C. 2016). In Heyer, the Court of Claims held that bidders on
government contracts possess “the right to have [their] bid[s] honestly
considered.” 140 F. Supp. at 413. If the government breaches that duty, “and
plaintiff is put to needless expense in preparing its bid, it is entitled to recover
such expenses.” Id. at 413–14.
While Heyer framed the government’s duty narrowly, see id. at 414,
later decisions teach that the government’s conduct breaches the duty so long
as it “is found to be ‘arbitrary and capricious toward the bidder-claimant,’”
Southfork Sys., Inc. v. United States, 141 F.3d 1124, 1132 (Fed. Cir. 1998)
(quoting Cent. Ark. Maint., Inc. v. United States, 68 F.3d 1338, 1341 (Fed.
Cir. 1995)); see also Zolon PCS II, LLC v. United States, 176 Fed. Cl. 279,
296 (2025) (same). And the enactment of the Administrative Dispute
Resolution Act did not eliminate Heyer-like claims; rather, it empowered this
court, through its grant of “jurisdiction over procurement bid protest
matters,” Safeguard Base Operations, LLC v. United States, 989 F.3d 1326,
15
1342 (Fed. Cir. 2021), to “award any relief that the court considers proper,”
including monetary relief “limited to bid preparation and proposal costs,”
§ 1491(b)(2); see also Tender Years Learning Corp. v. United States, 134
Fed. Cl. 336, 342 (2017) (describing the intersection between Heyer-like
claims and this court’s § 1491(b) bid protest jurisdiction).
At this stage, Siemens adequately pleads that defendant violated the
duty to consider bids fairly. As we explained above, Siemens plausibly
alleges that COE acted arbitrarily and capriciously in failing to ascertain
ABG-75’s applicability, failing to provide needed energy usage information,
and requiring multiple (and duplicative) audits, all of which increased
Siemens’s costs despite Siemens being ultimately ineligible for award. As a
result, Siemens has alleged enough facts at this early stage to overcome
defendant’s motion to dismiss.
Defendant’s arguments are unavailing. Principally, defendant
contends that the energy contract precludes the existence of any implied
contract. That is mistaken. True, an implied-in-fact contract cannot exist if
an express contract already covers the same subject matter. Solaria Corp. v.
United States, 123 Fed. Cl. 105, 118 (2015), aff’d, 671 F. App’x 797 (Fed.
Cir. 2016), cert. denied, 581 U.S. 940 (2017). But the energy contract only
addressed the contracting officer’s authority to award bid preparation costs;
it did not eliminate the government’s inherent duty to treat bids fairly and
honestly. By failing to observe that duty, the government can be sued for bid
preparation costs. Thus, the energy contract does not preclude the implied
contract to treat bids fairly.
CONCLUSION
We deny defendant’s motion to dismiss. The parties shall file a Joint
Status Report proposing further proceedings on or before August 8, 2025.
s/Eric G. Bruggink
ERIC G. BRUGGINK
Senior Judge
16