Opinion

Titan Constr. Servs., LLC v. Board of Mgrs. of PS 90 Condominium

  • 2025 NY Slip Op 32286(U)
Court
New York Supreme Court, New York County
Filed
Jun 23, 2025
Status
Unpublished
Author
Melissa A. Crane
Cited by
0 cases
Authority
More cited than 37.2%

The opinion

Titan Constr. Servs., LLC v Board of Mgrs. of PS 90

Condominium

2025 NY Slip Op 32286(U)

June 23, 2025

Supreme Court, New York County

Docket Number: Index No. 652243/2021

Judge: Melissa A. Crane

Cases posted with a "30000" identifier, i.e., 2013 NY Slip

Op 30001(U), are republished from various New York

State and local government sources, including the New

York State Unified Court System's eCourts Service.

This opinion is uncorrected and not selected for official

publication.

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

SUPREME COURT OF THE STATE OF NEW YORK

NEW YORK COUNTY

PRESENT: HON. MELISSA A. CRANE PART ----~----'-----

60M

Justice

---------------------------------------------------X

TITAN CONSTRUCTION SERVICES, LLC INDEX NO. 652243/2021

Plaintiff,

Decision After Bench Trial

- V -

BOARD OF MANAGERS OF PS 90 CONDOMINIUM D/B/A

PS90 CONDOMINIUM ASSOCIATION,

Defendant.

________ ,___x

Melissa A. Crane, JSC

This case concerns a construction project. On September 29, 2023, this court denied

summary judgment to plaintiff, Titan, finding issues of fact about whether there was a mutual

mistake and, if so, whether plaintiff should receive $2.06 a square inch for its terracotta work, as

defendant contends, or whether it should receive what plaintiff would consider a reasonable

price. Thus, the main issue for trial was: (1) whether the parties agreed to a particular price, and,

(2) if not, what a reasonable price would be. There are also issues concerning other work Titan

performed on the site. Defendant contends that the parties agreed to $2.06 per square inch and

that price is reasonable. Plaintiff contends that the parties did not agree to that price which

plaintiff postures is umeasonably low. The following is the court's decision after a bench trial.

I. The Price for the TRC 02 Work

On July 11, 2016, plaintiff Titan and defendant PS90, the property owner, entered into a

contract for Titan to perform work on PS90's condominium building (Ex. C) Part of the work

was for "TRC 02" repair, a type ofrepair to terracotta (id at§ 3.2.3). At§ 6.1.5, the contract

OTHER ORDER - NON-MOTION

1 of 8 Paae 1 of 9

[* 1]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

lists as an "Addenda" a certain "Revised Bid Form" signed APRIL 13, 2016. Plaintiff attached

that bid form to the contract. It reads $285.00 per square inch as the unit price for the TRC 02

Terra Cotta Spall Repair (id at bates stamp 000053; see also Ex Eat 000063).

It is clear there was a mistake on that April bid form and that plaintiff meant to bid

$285/sq foot in that April bid. Although plaintiff claims in its post-trial brief that "There is no

evidence of a mutual mistake in the within action," this contradicts plaintiffs position elsewhere,

including, strangely, in the same post trial brief (see EDOC 115 pg. 2 "TITAN does not dispute

that the intended result was not what the parties' contract specifically contemplated"). The

position Plaintiffs counsel took on the record at trial also confirmed the presence of a mutual

mistake. At trial plaintiffs counsel conceded that "There was a bid submission of $2.06 that was

changed later that day to $285 a square inch. In our view it should have been $285 a square foot,

not a square inch." (Trial Transcript (TT) 106-107). Moreover, this on-the-record admission was

in keeping with plaintiffs position throughout the case. In its pretrial statement, plaintiff again

admitted that:

"TITAN does not dispute that the intended result was not what the parties'

contract specifically contemplated. That is because the quantity should have been

square feet by location, not the number of square inches multiplied by $285.00

per square inch, which is what the contract actually states."

(EDOC 108 pg. 2) Having conceded the existence of a mutual mistake in the contract

previously, plaintiff cannot now take a contrary position. Thus, it would appear no party

disputes that it was a mistake to append the April bid form containing the bid of $285 per square

inch to the contract.

Plaintiff does not argue that a court will reform the instrument to do what is reasonable in

the face of evidence of actual intent. Rather, PLAINTIFF ADMITS that "Where a written

instrument fails to conform to the intended agreement between the parties whether caused by the

2 of 8 Paae 2 of 9

[* 2]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

mutual mistake of the parties, however induced, or of the mistake of one party and fraud of the

other, or for some other reason a court will reform the instrument so as to make it conform to

the actual agreement between the parties" (Pl Post Trial Br. [EDOC 115] at pg 17). This

position comports with the law. "Where there is no mistake about the agreement and the only mistake

alleged is in the reduction of that agreement to writing, such mistake of the scrivener, or of either party,

no matter how it occurred, may be corrected." (Nash v. Kornblum, 12 N.Y.2d 42, 47 [1962] (quoting

I

Born v. Schrenkeisen, 110 N.Y. 55, 59 [1888]).

Unfortunately for plaintiff, the evidence shows that the parties had meant to agree to

$2.06 a square inch. First, there is the May 16, 2016 bid submission (Ex Fat 000072). This Bid

Submission, which post dates the April bid submission, and is Titan's final bid, lists a square

inch price of $2.06 for the TRC 02 work (id. at 000072). Moreover, an email from Eric Mercado

at Titan to Mathew Cronin, dated May 17, 2016 (Ex 00), reflects that the May bid submission

was sent and included a change for TRC 02 work to "Square inch." It was after the final May

bid submission that defendant awarded the contract to Titan.

It was Titan who assembled the contract (see Testimony of Mr. Garcia (Titan) at pg 40:

"And in terms of putting together the paper documents with the signatures and the final version,

someone at Titan did that, right, and sent the whole thing back to SuperStructures? A: Yes."

Therefore, it is highly likely that someone at Titan incorrectly attached the April bid document to

the contract containing $285 per square inch, when they were supposed to have attached the May

bid document containing $2.06 per square inch.

There is more. The field reports, upon which Titan was always cc' d, all list the TRC 02

work in square inches at $2.06 per Unit Price (see Ex 000 spreadsheet at bates no 001660,

001691, and 001710). Titan's own exhibit ZZZ (Field Report 13) also lists $2.06 for TRC 02

3 of 8 Paqe 3 of 9

[* 3]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

work. There is nothing in the record to suggest that Titan challenged this designation. In fact,

Titan submitted payment applications and accepted payment at $2.06 per square inch for the

terra cotta work. Joint Exhibit JJJ is an application and certificate for payment. At the point JJJ

was created, 100% of the original work was complete and Titan accepted $1, 710 for

approximately 832 square inches of work. Mathematically, this works out, rounded up by half a

cent, to $2.06 a square inch, just like the May bid called for. During the trial, in relation to Ex

JJJ, Mr. Garcia from Titan admitted that Titan billed $1,710 for approximately 832 inches of

TRC 02 work (See Ex JJJ at 001526 and TT 67-68). Thus, for the original scope of work Titan

charged and was paid at the rate of $2.06 for TRC 02 work.

At some subsequent point, the project expanded to an additional 50,026 square inches of

TRC 02 work. Mr. Garcia admitted that the bid unit pricing meant that the contractor would

perform additional work at the same unit price (TT 71). Nevertheless, Titan interposed a change

order that asked for $14 million dollars for the 50,026 square inches of additional work (see Ex

FFFF). Mr. Garcia admitted this request for $14M was based on $285 a square inch, a number

plaintiff has conceded was NOT what the parties had agreed to.

Plaintiff had apparently balked at the large amount of additional work, finding it

financially infeasible at $2.06/sq inch (see Ex GGG entitled "Response to AG&A letter dated

February 20th, 2019"):

"Furthermore, based on the project drawings and specifications, in

addition to the insignificant base bid quantity of TRC 02, the detailed work to

performed TRC 02 at $2.06 per square inch is absurd based on Industry cost. To

execute and complete a typical square inch TRC 02 repair it would take a

minimum 4 days excluding materials limitation to weather as per project

documents guidelines. The difference to replace 1SF vs. 1SI is a material cost

only, as labor tools remain unchanged."

4 of 8 Paqe 4 of 9

[* 4]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

However, Titan does not explain why this circumstance enabled Titan to raise its unit

price when, as Mr. Garcia admitted, the original bid price was supposed to carry through to

additional work (TT 71). In addition. the increase in square inches should not matter. Titan was

being paid for the amount of work, not a flat fee. More square inches meant more money. If

Titan underbid the project, that circumstance is irrelevant to its contractual obligations.

Neither side briefed the standard of proof to demonstrate what a proponent of reformation

needs to adhere to after both sides agree that the contract contains a mutual mistake of fact, but

disagree about what the parties' actual agreement was. Hence, in an abundance of caution, the

court will apply a clear and convincing standard of proof (see Empery Asset Master Ltd, v Ait

Therapeutics, Inc., 215 AD3d 10, 14-15 [1 st Dep't 2023] [affirming decision after bench trial that

investors had established a mutual mistake in omitting anti-dilution provisions]).

The pattern jury instructions (PJI 1:64) describe clear and convincing evidence:

it is not enough to find that the preponderance of the evidence is in the

plaintiffs favor. A party who must prove (his, her) case by a preponderance of the

evidence only need satisfy you that the evidence supporting (his, her) case more

nearly represents what actually happened than the evidence which is opposed to

it. But a party who must establish (his, her) case by clear and convincing evidence

must satisfy you that the evidence makes it highly probable that what (he, she)

claims is what actually happened.

Applying that standard here, it is highly probable that the parties meant to agree to a unit

price of $2.06. As discussed, plaintiff has conceded that the unit price of $285/sq inch in the bid

document attached to the parties' contract was a mistake. The remaining evidence supports that

Titan bid, and defendant accepted, a unit price of $2.06. This evidence includes, as discussed

supra: Titan's final May bid containing a $2.06 unit price for TRC 02 work, the testimony at

trial, the field reports, Titan's invoices and its acceptance of payment at the rate of $2.06/inch.

5 of 8 Paoe 5 of 9

[* 5]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

There is also Mr. Garcia's testimony that the accepted bid unit price was supposed to apply to

additional work.

Meanwhile, plaintiffs' assertions about the correct unit price are a moving target. First,

Mr. Garcia testified that Titan intended to bid $285 per square inch (TT46) This contradicts

Plaintiffs own counsel who said: "In our view it should have been $285 per square foot, not a

square inch" (TT 106). However, $285 per square foot also makes no sense for plaintiff as $285

per square foot divides down to $1.98 per square inch, an amount that is even less than the $2.06

plaintiff rejects. Going the other way, 50,026 square inches is 347 square feet. At $285 a square

foot, plaintiff would only be owed $98,895.00.

Even if Mr. Garcia's testimony, that Titan intended to bid $285 per square inch, did not

contradict plaintiffs position throughout this litigation, his testimony is not credible. In

defendant's exhibit 2, an April 17, 2019 email from Mr. Garcia, he claims yet a different amount.

He asserts there was now a "clerical error" on the May bid form "changing it from $206.00 to

$2.06" per square inch. What happened to the $285 per square inch? Which is it?

Then, there is plaintiffs expert's calculations. Plaintiffs expert developed a formula,

apparently for this litigation, to calculate linear flat and decorative patch work. His report

calculated a range from $700,000 to $900,000. This in itself is a moving target. The constantly

changing and contrived nature of plaintiff's supposed unit price does not reflect well on its

credibility.

Thus, defendant has carried its burden by clear and convincing evidence to show that the

parties actually intended to agree to $2.06 per square inch for the TRC 02 work. Because the

evidence shows what the parties actually agreed to, the court does not need to reach plaintiffs

expert and what he, or anyone else, considered to be reasonable.

6 of 8 Paae 6 of 9

[* 6]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

II. Titan's Allegedly Incomplete and Defective Work

Defendant contends that Titan failed to: (1) fix damages metal panels, (2) properly

reconstruct the parapet walls that led to water intrusion, (3) repair and replace metal pavers and

(4) repair damage to a door.

A. The parapet wall

Defendant failed to carry its burden to show that Titan was responsible for the defects in the

construction of the parapet wall. Titan objected to the design, but built it to the specifications

that SSX gave it. Titan did what it was instructed to do. If the design was poor, that is not

Titan's fault. Further, all relevant entities, including the Department of Buildings, signed off on

the wall and Titan was paid for that work. Defendant terminated Titan on July 23, 2019. The

only reasons given in the termination letter (see Joint Ex. P), were (1) "failure to supply enough

properly skilled workers and proper materials" and (2) it's having issued change orders with

"Wholly unsubstantiated and commercially unreasonable" unit prices. There is no mention of

the wall. Finally, Mr. Galetta is not a neutral witness. SSX is his company and probably

responsible for the faulty design.

B. The remaining defects:

Titan appears to concede some of defendant's remaining grievances constitute defective

work. This is because on page 21 of its post-trial brief, it issues "Credits for defective work for

which evidence was presented." These total $34,415.00 and involve: (1) the panels to be

replaced, (2) coating on the meal doorframes, (3) drywall repair, (4) painting and (5) pavers.

Aside from the work underlying these credits, there is no evidence that plaintiff owes

defendant anything for other work. In Joint exhibit LL, Defendant lists additional work, some of

which it failed to discuss in the post trial brief, to claim that Titan owes it $425,028.00.

7 of 8 Paae 7 of 9

[* 7]

[FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021

NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025

However, there is no support in the record for most of the remaining entries and some are highly

suspicious. For instance, the largest bulk amount of the $425,028.00 is "SSX Services (to date)

$180,478" (see Ex LL). No where in Mr. Galetta' s direct trial affidavit ( see EDOC 110) does he explain

why SSX needed to charge $180,478 due to Titan's allegedly defective work. The lack of explanation is

compounded by the self-serving nature of the testimony as SSX is Galetta's own company. There is

utterly no explanation as to what New Bedford Management Services did to earn $59,884 and why Titan

should pay for it. Rather, the $425,028.00 seems to be a last minute contrivance to lessen the blow should

defendant have lost on the TRC 02 issue.

By defendant's own calculations, it still owes Titan $93,800.04 (see Ex LLL) for the TRC 02

work. With the credit of$34,415.00 for Titan's defective work, defendant still owes $59,385.04. As

Titan has not proved its case with respect to the unit price, and defendant has largely failed to prove its

counterclaims, neither party can be considered the prevailing party for purposes of the attorney fee

provision of the contract. Therefore, all requests for attorney's fees are denied.

The court has considered the remaining contentions of both parties and finds them unavailing.

Accordingly, it is

ORDERED THAT the clerk enter judgment in the amount of $59,385.04 with pre judgment

interest from July 15, 2019, the date Titan was terminated, in favor of Titan Construction Services and

against Board of Managers of PS 90 Condominium; and it is further

ADJUDGED, DECREED AND DECLARED that there was a mutual mistake in the parties'

contract concerning the unit pricing for TRC 02 work; and it is further

ADJUDGED, DECREED AND DECLARED that the Parties agreed that Titan would perform

the additional TRC 02 Work at a unit cost of $2.06 per square inch; and it is further

ORDERED THAT there shall be no motion practice whatsoever without prior conference with

the court, briefs that fail to contain a table of contents and table of authorities will be rejected.

6/23/2025

DATE

~

MELISSA A. CRANE, J.S.C.

CHECK ONE: Q CASE DISPOSED □ NON-FINAL DISPOSITION

□ GRANTED □ DENIED □ GRANTED IN PART □ OTHER

8 of 8 Paae 8 of 9

[* 8]