finding that an issue of fact existed as to whether asset purchase for inadequate consideration or fraudulent conveyance amounted to an unfair trade practice
How later courts described this case
- finding that an issue of fact existed as to whether asset purchase for inadequate consideration or fraudulent conveyance amounted to an unfair trade practice
Written by the judges who cited it.
The opinion
KRG New Hill Place, LLC v. Springs Investors, LLC, 2015 NCBC 69.
STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE
SUPERIOR COURT DIVISION
COUNTY OF WAKE 13 CVS 14770
KRG NEW HILL PLACE, LLC and KITE )
REALTY NEW HILL PLACE, LLC, )
Plaintiffs )
)
v. ) OPINION AND ORDER
)
SPRINGS INVESTORS, LLC; B. KYLE )
WARD; MICHAEL L. HUNTER and )
STEPHEN C. WARD, )
Defendants )
THIS CAUSE, designated a mandatory complex business case by Order of the Chief
Justice of the North Carolina Supreme Court, pursuant to N.C. Gen. Stat. § 7A-45.4(b)
(hereinafter, references to the North Carolina General Statutes will be to “G.S.”), and
assigned to the undersigned Special Superior Court Judge for Complex Business Cases,
comes before the Court upon Plaintiffs’ Motion for Partial Summary Judgment (“Plaintiffs’
Motion”) and Defendants’ Motion for Partial Summary Judgment (“Defendants’ Motion”)
(collectively, “Motions”). On May 28, 2015, the Court held a hearing on the Motions.
THE COURT, after reviewing the Motions, briefs in support of and in opposition to
the Motions, the record evidence filed by the parties, the arguments of counsel, and other
appropriate matters of record, FINDS and CONCLUDES as stated herein.
Smith Moore Leatherwood LLP by Bradley M. Risinger, Esq. and Barnes & Thornburg
LLP by Robert D. MacGill, Esq., Karoline E. Jackson, Esq., and Alexander P.
Orlowski, Esq. for Plaintiffs.
Shanahan Law Group, PLLC by Kiernan J. Shanahan, Esq., John E. Branch III, Esq.,
Brandon S. Neuman, Esq., Christopher Battles, Esq., and Jeffrey M. Kelly, Esq. for
Defendants.
McGuire, Judge.
PROCEDURAL HISTORY1
1. On November 5, 2013, Plaintiffs initiated this case by filing their Complaint.
On March 6, 2015, Plaintiffs filed their Amended Complaint with leave of Court.
2. The Amended Complaint states claims for breach of contract, breach of implied
covenant of good faith and fair dealing, declaratory judgment, fraudulent transfer, unfair and
deceptive trade practices, and liability of the individual Defendants under G.S. §§ 57C-3-30
and 57C-3-32.
3. On April 30, 2015, Defendants filed their Answer to Amended Complaint and
Counterclaims. Defendants allege counterclaims for breach of contract, breach of the
covenant of good faith and fair dealing, and declaratory judgment.
4. On February 20, 2015, Defendants filed their Motion for Partial Summary
Judgment. Defendants’ Motion seeks summary judgment in their favor as to: (1) Defendants’
counterclaim for breach of contract; (2) Plaintiffs’ request for specific performance on their
claim for breach of contract; and (3) Plaintiffs’ claims for fraudulent transfer and unfair and
deceptive trade practices.
5. On February 20, 2015, Plaintiffs filed their Motion for Partial Summary
Judgment. Plaintiffs’ Motion seeks summary judgment in their favor as to: (1) Defendants’
counterclaim for tortious interference with prospective economic advantage;2 and (2)
Defendants’ counterclaims for breach of contract, breach of good faith, and declaratory
judgment stemming from (a) Defendants’ allegations that Plaintiffs were obligated to
1 The full procedural history of this matter has been included in prior orders of this Court, and for
brevity will not be restated here.
2 In their amended counterclaims, Defendants also re-alleged a claim for tortious interference with
prospective economic advantage that the Court had already dismissed with prejudice in its February
27, 2015 Opinion and Order. Defendants’ counsel conceded at the May 28, 2015 hearing that they
have no viable claim for tortious interference, and the Court will not address that claim again in this
Order.
complete construction under the contract by December 31, 2010, and (b) Defendants’
allegation that Springs Investors, LLC is entitled to credits against any amounts it may owe
for “Confirmed Cost Savings.”
6. On May 28, 2015, the Court held a hearing on the Motions. The Motions have
been fully briefed and argued and are ripe for determination.
FACTUAL BACKGROUND
7. On July 15, 2008, Plaintiffs KRG New Hill Place, LLC and Kite Realty New
Hill Place, LLC (Plaintiffs are hereinafter referred to in the singular as “KRG”) and
Defendant Springs Investors, LLC (“Springs”),3 entered into a written Post-Closing
Development Agreement to coordinate the development of their adjacent properties located
in Holly Springs, North Carolina. In the Development Agreement, KRG and Springs agreed
to share the cost of making certain improvements to existing roadways and the construction
of an internal thoroughfare to enable the public to access both properties (“Infrastructure
Work”).4 The parties intended to develop a shopping center and residential apartments on
the properties.
8. Section 2 of the Development Agreement provided as follows:
KRG shall cause the Infrastructure Work to be constructed and installed in
accordance with the Approved Plans by a general contractor selected in
accordance with Section 2. Following approval of the Approved Plans, KRG
shall bid each of the major trades involved in the Infrastructure Work to not
less than three qualified contractors. KRG and Springs Investors shall jointly
review all such bids and KRG shall promptly notify Springs Investors of KRG’s
decision to award contracts to the respective bidders. KRG shall endeavor to
cause each contract entered into for the performance of the Infrastructure
Work to require substantial completion of the work thereunder to be completed
such that the entire Infrastructure Work shall be completed by December 31,
2010. All construction performed by or on behalf of any party under this
Agreement shall be performed in accordance with all applicable laws,
3 Defendants B. Kyle Ward, Michael L. Hunter, and Stephen C. Ward are the principals in Springs
Investors, LLC, and are collectively referred to in this Opinion and Order as the “Individual
Defendants.”
4 Am. Compl. Ex. 1 (“Development Agreement”).
ordinances, and regulations of the Town or other applicable governmental
entity, and shall be performed in as expeditious manner as reasonably
possible.5
9. Shortly after the Development Agreement was executed, KRG put the
Infrastructure Work on hold due to the downturn in the economy. The Infrastructure Work
has never been completed. Nevertheless, the parties continued to communicate with one
another and work together towards potential completion of the Infrastructure Work until
this lawsuit was filed in November 2013.
10. The parties disagree whether the Section 2 of the Development Agreement
required KRG to complete the Infrastructure Work by December 31, 2010. KRG contends
that the words “shall endeavor” in Section 2 of the Agreement meant that the December 31,
2010 date was a goal, rather than a deadline. Springs contends that the provision required
the completion of all Infrastructure Work by December 31, 2010.6 In addition, KRG contends,
and Springs disputes, that even if December 31, 2010, was the deadline for completion of the
work, Springs waived the deadline by its conduct following December 31, 2010, including
continuing to collaborate with KRG.7 Springs contends that the provision in the Development
Agreement stating that it could only be modified or amended by written agreement, and the
5Id. at § 2.
6Compare Pls.’ Mem. Supp. Mot. Summ. J. 11 (“The plain language of the Agreement states that
[KRG] had no obligation to complete the Infrastructure Work by December 31, 2010.”) with Defs.’
Mem. Supp. Mot. Summ. J. 2-3 (“The parties, at the time they executed the [Development
Agreement], intended December 31, 2010 to serve as a deadline for the completion of the
Infrastructure Work . . . .”; “There is no material dispute of fact that [KRG] failed to complete the
Infrastructure Work by December 31, 2010, which constitutes a material breach” of the Development
Agreement.); Am. Compl. Ex. 3 at 2 (March 11, 2013 letter from KRG to Springs regarding the
December 31, 2010 date, stating that “[w]hile that time frame may have been contemplated by both
parties in July of 2008 when the Agreement was executed, the parties did not and could not have
foreseen the devastating economic downturn that befell the U.S. shortly after the Agreement was
executed”).
7 See, e.g., Pls.’ Mem. Supp. Mot. Summ. J. Ex. 28 (notes from Jan. 4, 2011 meeting).
fact no such written amendment ever occurred, means that the purported deadline was never
changed.8
11. The Development Agreement required KRG to “prepare and submit to
[Springs] a set of plans and specifications for the Infrastructure Work.”9 Springs had ten
business days after receipt of the plans in which to notify KRG of any problems with the
plans. A dispute of fact exists as to whether KRG complied with this requirement and
provided project plans to Springs.10
12. The Development Agreement also provided that the cost of the Infrastructure
Work would be shared between KRG and Springs. KRG was to contribute a fixed sum of
$6,156,394.00 to the Infrastructure Work (the “Contribution Amount”). The parties dispute
whether KRG has expended the Contribution Amount towards work properly attributed the
Infrastructure Work. Springs was to be “solely responsible for the Cost of the Infrastructure
Work in excess of the Contribution Amount,” and was required to deposit $2,915,409.00 into
an escrow account to be applied to any funds needed in excess of the Contribution Amount.11
Springs established the escrow account, but the parties dispute whether Springs is required
to contribute additional amounts to the costs of the Infrastructure Work.12
13. The Development Agreement also provides that Springs would receive credits
against any funds it was required to contribute to the Infrastructure Work for “Confirmed
8 Development Agreement at § 6.
9 Id. § 1.
10 Compare Defs.’ Mot. Summ. J. Ex. D (stating that Defendants “never received any such Plans
prior to going to Bid and, therefore, did not have an opportunity to review any of the Plans pursuant
to the Agreement”) with Am. Compl. ¶ 28 (“Pursuant to Section 1 of the Agreement, on or around
April 25, 2012, Kite provided Springs Investors with the Infrastructure Work Plans.”); Pls.’ Br. Opp.
Defs.’ Mot. Summ. J. Exs. 25-26 (emails discussing attached project plans).
11 Development Agreement at §§ 2-3.
12 Compare Defs.’ Br. Supp. Mot. Summ. J. at 10 (“There is no evidence in the record showing that
[Plaintiffs have] spent approximately $6.1 million on the Infrastructure Work called for in the
PCDA”) with Pls.’ Opp. Defs.’ Mot. Summ. J. 6 (“The latest budget projects that [Defendants] will be
responsible for over $3,000,000 in expenses above [their] escrowed amount.”).
Cost Savings” that Springs was able to achieve on the project.13 There is a dispute of fact as
to whether Springs achieved such Confirmed Costs Savings.
14. KRG contends that it has spent its full Contribution Amount of $6,156,394.00
and that the Development Agreement requires Springs to contribute additional amounts
towards the cost of the Infrastructure Work. Springs alleges that KRG “has not exceeded its
contribution amount because [KRG] continues to include costs outside the scope of the
[Development Agreement] and exclude credits to which Springs is entitled.”14 In December
2012, KRG sent Springs additional bids from contractors for completion of the Infrastructure
Work. KRG alleges that the bids would have put Springs on notice that it would need to
contribute an additional $2 million towards the Infrastructure Work.15 In February 2013,
KRG sent notice to Springs that Springs was obligated to contribute additional amounts to
escrow. In May 2013, Springs notified KRG that it would not make any further contributions
towards the cost of the Infrastructure Work. 16
15. On or around February 28, 2013, shortly after KRG sent notice to Springs that
additional escrow payments were required, Springs transferred certain real property to the
Individual Defendants for little or no consideration.17 Springs also transferred other assets
to sister entities owned by the Individual Defendants. KRG contends that these transfers
left Springs with insufficient equity to cover its existing liabilities, and were made for the
purpose of putting those assets outside the reach of KRG.18 Springs disputes this claim, and
contends that the transfers of property and assets were made for legitimate reasons
13 Development Agreement at § 3.
14 Defs.’ Reply Supp. Partial Summ. J. 2, n.3.
15 Pls.’ Opp. Defs.’ Mot. Partial Summ. J. 3.
16 Id. at 3-5.
17 Id. at 19.
18 Id. Exs. 9 & 11.
unrelated to the notice from KRG. Springs also alleges that the transfers did not leave
Springs unable to fulfill its obligations under the Development Agreement.
ANALYSIS
16. “Summary judgment is appropriate 'if the pleadings, depositions, answers to
interrogatories, and admissions on file, together with the affidavits, if any, show that there
is no genuine issue as to any material fact and that any party is entitled to a judgment as a
matter of law.'” Variety Wholesalers, Inc. v. Salem Logistics Traffic Servs., LLC, 365 N.C.
520, 523 (2012) (quoting Rule 56(c)). Any inference of fact should be drawn against the
movant. Forbis v. Neal, 361 N.C. 519, 523-524 (2007) (citing Caldwell v. Deese, 288 N.C. 375,
378 (1975)). A genuine issue of material fact will require the court to preserve the issue for a
finder of fact. Bumpers v. Cmty. Bank of N. Va, 367 N.C. 81 (2013). Although the court must
view the record “in the light most favorable to the party opposing the motion,” Rule 56(e)
provides that summary judgment may not be defeated by “mere allegations or denials,” but
rather that the opposition must be supported by “specific facts showing that there is a
genuine issue for trial.” Patterson v. Reid, 10 N.C. App. 22, 28 (1970).
Breach of Contract
17. KRG and Springs each claim that the other breached the Development
Agreement. A successful claim for breach of contract shows (1) a valid contract, and (2)
breach of the terms of that contract. Poor v. Hill, 138 N.C. App. 19, 26 (2000).
The December 31, 2010 Completion Deadline
18. The primary dispute underlying the claims in this case centers on whether the
Development Agreement obligated KRG to complete the Infrastructure Work by December
31, 2010. Both parties argue that Section 2 of the Development Agreement is unambiguous
and requires judgment in their favor as matter of law. Springs alleges that KRG breached
the Development Agreement by not entering into contracts requiring “substantial
completion” of the work by December 31, 2010, and by not completing construction before
December 31, 2010. KRG argues that the language of Section 2 unambiguously provides that
KRG only had to “endeavor” to complete the Infrastructure Work by December 31, 2010, and
that it complied with this requirement by continuing the Infrastructure Work
notwithstanding Springs’ refusal to provide its share of the funds.
19. It is well-settled that “[w]here the language of a contract is plain and
unambiguous, the construction of the agreement is a matter of law; and the court . . . must
construe the contract as written, in light of the undisputed evidence as to the custom, usage,
and meaning of its terms.” Happ v. Creep Pointe Homeowner’s Assoc., 215 N.C. App. 96, 103
(2011) (alterations in original) (quoting Hodgin v. Brighton, 196 N.C. App. 126, 128-29
(2009)). Moreover:
Contracts are interpreted according to the intent of the parties. The intent of
the parties is determined by examining the plain language of the contract.
Extrinsic evidence may be consulted when the plain language of the contract
is ambiguous.
Brown v. Ginn, 181 N.C. App. 563, 567 (2007) (citations omitted). “Ambiguities in contracts
are to be resolved . . . upon consideration of ‘the expressions used, the subject matter, the end
in view, the purpose sought, and the situation of the parties at the time.’” Cleland v.
Children’s Home, Inc., 64 N.C. App. 153, 157 (1983) (quoting Silver v. Bd. of Trans., 47 N.C.
App. 261, 268 (1980)).
20. The Court concludes that the language of Section 2 of the Development
Agreement is ambiguous, and that its meaning must be determined by a jury. The terms
“shall endeavor” and “shall be completed” as used in Section 2 appear to be inconsistent with
one another, the former suggesting that the deadline is aspirational and the latter that the
deadline is a firm requirement. The language of the last sentence of Section 2 suggests that
while the parties wished to meet a December 31, 2010 deadline, the construction work under
the agreement needed only to “be performed in as expeditious a manner as reasonably
possible.” In addition, the evidence regarding the intent of parties with regard to Section 2
is disputed, with both parties presenting evidence supporting their respective
interpretations.19 See Root v. Allstate Ins. Co., 272 N.C. 580, 590 (1968) (“[I]f the writing
itself leaves it doubtful or uncertain as to what the agreement was, parol evidence is
competent . . . to show and make certain what was the real agreement between the parties;
and in such case what was meant, is for the jury, under proper instructions from the court.”).
21. The Court also concludes that issues of material fact exist regarding KRG’s
argument that Springs waived the December 31, 2010 completion deadline. Accordingly,
summary judgment on these grounds is not appropriate.
22. The Court further concludes that Springs’ Motion as to its counterclaim that
KRG breached the Development Agreement by failing to provide Springs with plans for the
Infrastructure Work must fail because the because there exist issues of material fact.20
Summary judgment is therefore DENIED as to these issues.
Springs’ Obligation to Provide Additional Funds
23. Springs also moves for summary judgment as to KRG’s first claim for breach
of contract and for an order requiring Springs’ specific performance. KRG alleges that
Springs breached the Development Agreement by failing to provide additional funds towards
19 Because the Court is unable to conclude as a matter of law that failure to complete the
Infrastructure Work by December 31, 2010 was a breach of the Development Agreement, the Court
finds that it cannot properly consider at this time Plaintiffs’ argument that Defendants’ breach of
contract claims are barred by the statute of limitations.
20 Compare Defs.’ Mot. Summ. J. Ex. D (stating that Defendants “never received any such Plans
prior to going to Bid and, therefore, did not have an opportunity to review any of the Plans pursuant
to the Agreement”) with Am. Compl. ¶ 28 (“Pursuant to Section 1 of the Agreement, on or around
April 25, 2012, Kite provided Springs Investors with the Infrastructure Work Plans.”); Pls.’ Br. Opp.
Defs.’ Mot. Summ. J. Exs. 25-26 (emails discussing attached project plans).
the Infrastructure Work. Springs argues that the evidence establishes that KRG had not
reached its contribution amount so as to trigger any further obligation for Springs to
contribute to the Infrastructure Work. Springs further argues that because KRG has
breached the Development Agreement, it cannot seek the equitable remedy of specific
performance.
24. The Court concludes that there exist disputed facts regarding Springs’
obligation to contribute additional funds towards the Infrastructure Work. Similarly, with
regard to Springs’ counterclaim that it is entitled to a credit for “Confirmed Cost Savings”
against any amounts it may owe, the parties dispute the meaning of “Confirmed Cost
Savings”21 as used in the Development Agreement, and the Court concludes that the
provision is ambiguous. Accordingly, summary judgment on this issue is also not
appropriate. Summary judgment as to the issue of Spring’s obligations to contribute
additional funds should be DENIED.
Breach of Good Faith/Declaratory Judgment
25. KRG seeks summary judgment on Defendants’ counterclaim for breach of good
faith and Defendants’ counterclaim for a declaratory judgment “stemming from [Springs’]
contention that the [Development Agreement] . . . obligated [KRG] to complete construction
of the Infrastructure Work by December 31, 2010.”22
26. As discussed above, the record evidence leaves questions of fact as to whether
KRG was bound by a December 31, 2010 deadline. Accordingly, summary judgment should
be DENIED as to these counterclaims.
21 Development Agreement at § 3.
22 Pls.’ Mot. Partial Summ. J. 1-2.
Fraudulent Transfer
27. Defendants seek summary judgment on KRG’s fourth claim alleging that
Springs fraudulently transferred real property and other assets to the Individual Defendants
and sister entities controlled by the Individual Defendants in violation of the North Carolina
Fraudulent Transfers Act, G.S. § 39-23.1 et seq. (“UFTA”). KRG alleges that Springs
transferred the property and assets for less than reasonable value and for the purpose of
making Springs insolvent at the time that Springs would have been obligated to provide
additional funds for the Infrastructure Work. KRG alleges that Springs did so with the intent
of hindering or delaying creditors such as Plaintiffs from collecting amounts due.23
28. A debtor is liable under the UFTA if, inter alia, the debtor transferred assets
with the intent to hinder, delay or defraud any creditor, or if the transfer was made without
receiving “reasonably equivalent value” and the debtor was engaged in or about to engage in
business or incur debts for which the debtor’s remaining assets would be “unreasonably
small” or otherwise insufficient. G.S. § 39-23.4(a).
29. Defendants argue that they are entitled to summary judgment on this claim
because KRG has conceded that Springs has fully satisfied all existing liabilities, and KRG
is therefore not a “creditor” of Springs within the meaning of the statute.24 KRG disputes this
argument, and contends that the facts clearly establish that it meets the definition of a
“creditor” of Springs under the UFTA.25
23 KRG also contends that Springs was dominated and controlled by the Individual Defendants and
that the Court should pierce the corporate veil to reach the transferred assets in the hands of the
Individual Defendants. Am. Compl. ¶¶ 74-79.
24 Defs.’ Mem. Supp. Mot. Partial Summ. J. 11-14.
25 Pls.’ Opp. Defs.’ Mot. Partial Summ. J. 16-21.
30. The Court concludes that significant disputes of material fact exist that
preclude summary judgment as to this claim. Accordingly, summary judgment is DENIED
as to the claim for relief under the UFTA.
Unfair and Deceptive Trade Practices
31. Finally, Defendants have moved for summary judgment on KRG’s claim for
unfair and deceptive trade practices in violation of G.S. §75-1.1 (“UDTPA”). KRG alleges that
Springs induced KRG to continue performing under the Development Agreement after
December 31, 2010 and then fraudulently transferred assets to the Individual Defendants to
avoid Springs’ financial obligations under the Agreement.26 KRG summarizes the basis for
its UDTPA claim as follows:
The Individual Defendants intentionally drained Springs’ assets, engaging in
a series of voluntary and uncompensated transactions that left the entity
insolvent. Second, the Defendants unfairly unfurled a scheme by which it
secured [KRG]’s cooperation in construction of the Infrastructure Work, took
responsibility for securing a key permit and set target dates for projection
completion in 2013, only to later refuse to pay its share of the expenses. Springs
lured [KRG’s] cooperation, gave no contemporaneous notice that it believed
Kite had breached the Agreement, and then systematically drained its assets
so that it would be unable to meet its contractual obligations to [KRG].27
32. To recover for a violation of G.S. § 75-1.1, KRG “must show: (1) defendant
committed an unfair or deceptive act or practice, (2) the action in question was in or affecting
commerce, and (3) the act proximately caused injury to the plaintiff.” Dalton v. Camp, 353
N.C. 647, 656 (2001) (citation omitted). “Whether a particular commercial act or practice
constitutes an unfair or deceptive trade practice is a question of law.” Akzo Nobel Coatings,
Inc. v. Rogers, 2011 NCBC 41 ¶ 108 (N.C. Super. Ct. Nov. 3, 2011) (citing Norman Owen
Trucking, Inc. v. Morkoski, 131 N.C. App. 168, 177 (1998)).
26 Pls.’ Opp. Defs.’ Mot. Partial Summ. J. 21-24.
27 Id. at 22.
33. Defendants argue that KRG has not presented evidence that Defendants
engaged in conduct that was unfair or deceptive or presented evidence that KRG suffered
damages other than damages arising from the alleged breach of the Development
Agreement.28 The Court already has concluded that issues of fact exist regarding, and
Defendants are not entitled to summary judgment on, KRG’s claim for fraudulent transfer.
The fraudulent transfer claim could support a claim for violation of the UDTPA. See L.J.
Best Furniture Distribs., Inc. v. Capital Delivery Serv., Inc., 111 N.C. App. 405, 410 (1993)
(finding that an issue of fact existed as to whether asset purchase for inadequate
consideration or fraudulent conveyance amounted to an unfair trade practice). In addition,
the Court concludes that there are disputed issues of material fact regarding KRG’s claim
that Springs induced KRG to continue performing under the Development Agreement. See
Gress v. Rowboat Co., Inc., 190 N.C. App. 773, 777 (2008) (finding that allegations that a
potential purchaser of businesses induced the businesses to enter into a salary and profit
sharing agreement prior to the purchase of the businesses, when the potential purchaser had
no intention of consummating its purchase of the businesses, supported a claim under G.S. §
75-1.1). Accordingly, the Court concludes there summary judgment is inappropriate on these
grounds.
34. Defendants’ argument that KRG has failed to present evidence that
Defendants’ unfair and deceptive conduct proximately caused KRG injury separate from the
injury resulting from Springs’ alleged breach of the Development Agreement presents a closer
call. KRG does not point to any specific injury or damages caused by Defendants’ unfair
conduct other than amounts owed due to Springs’ alleged breach of the Development
Agreement, namely amounts expended on Infrastructure Work by KRG above its
28 Defs.’ Mem. Supp. Mot. Partial Summ. J. 14-17.
Contribution Amount. KRG summarizes the injury caused by Defendants’ unfair conduct as
follows:
[KRG] has been injured by the Defendants’ maneuvering, which was intended
to make Springs incapable of meeting its contractual obligations. At least one
measure of that injury is the “shortfall” intentionally created by the
Defendants: the difference between the funds above [KRG’s] Contribution
Amount ultimately needed to complete the Infrastructure Work and Springs’
remaining assets.29
35. Although KRG’s alleged injury appears to be coterminous with the damages it
seeks from Springs’ under its breach of contract claim, the Court concludes that the
underlying facts regarding KRG’s Chapter 75 claim are in dispute, and the Court cannot
conclude as a matter of law that KRG has not presented facts that could support a claim for
injury based on the alleged unfair and deceptive acts. First, as noted above, North Carolina
has recognized that conduct amounting to a fraudulent transfer designed to avoid the claims
of creditors can constitute an unfair and deceptive act. Second, evidence of a breach of
contract accompanied by aggravating factors also can support a claim for violation of Chapter
75. Johnson v. Colonial Life & Accident Ins. Co., 173 N.C. App. 365, 370 (2005). In such
cases, the underlying monetary injury would be the amount recoverable for the breach of
contract. Accordingly, that KRG’s primary injury under its claim for unfair and deceptive
trade practices are the amounts allegedly owed by Springs under the Development
Agreement does not defeat KRG’s claim as a matter of law.
NOW THEREFORE, based upon the foregoing, it hereby is ORDERED that:
1. Defendants’ Motion for Partial Summary Judgment is DENIED in its entirety.
2. Plaintiffs’ Motion for Partial Summary Judgment is DENIED in its entirety.
29 Pls.’ Opp. Defs.’ Mot. Partial Summ. J. 23.
This the 8th day of July, 2015.
/s/ Gregory P. McGuire
Gregory P. McGuire
Special Superior Court Judge
for Complex Business Cases