“[A] statute [means] what it says.”
How later courts described this case
- “[A] statute [means] what it says.”
- explaining that, under 28 U.S.C. § 1491(b)(1), the federal contracting acquisition process is constructed around determining government “need”
- Courts are “not free to overlook plain statutory commands.”
- “While a litigant must have [its] day in court, [it] is not entitled to repeat that same day in a different court.”
Written by the judges who cited it.
The opinion
In the United States Court of Federal Claims
No. 22-698
(Issued Under Seal: March 28, 2025) 1
Reissued: April 15, 2025
)
SIEMENS GOVERNMENT )
TECHNOLOGIES, INC., )
)
Plaintiff, )
)
v. )
)
THE UNITED STATES, )
)
Defendant. )
)
Michael Bhargava, Nichols Liu LLP, Washington, D.C., for plaintiff. Also represented
by Robert Nichols.
Reta E. Bezak, U.S. Department of Justice, Civil Division, Washington, D.C., for
defendant.
MEMORANDUM OPINION AND ORDER
SMITH, Senior Judge
Today’s dismissal motion—raised by defendant, the United States of America,
against plaintiff, Siemens Government Technologies, Inc. (“Siemens”)—is essentially a
dispute over the definitional context in the Federal Acquisition Streamlining Act
(“FASA”) jurisdictional task order bar, 10 U.S.C. § 3406(f). 2 See generally
Defendant’s Motion to Dismiss, ECF No. 25 [hereinafter Def.’s Mot.]. In context, are
Siemens’ claims “to recover its bid preparation costs that it incurred” in pursuing the
1
This opinion was issued under seal on March 28, 2025. The parties were given an opportunity to propose
redactions before public release, but no proposals were made.
2
This section applies to contracts made with the armed forces; however, a civilian task order bar, under 41
U.S.C. § 4106(f), also exists, whose language is identical to 10 U.S.C. § 3406(f). Percipient.ai, Inc. v. United
States, CACI, Inc.-Fed., 104 F.4th 839, 846 n. 2 (Fed. Cir.) (“There is a FASA task order bar that applies to public
contracts generally, 41 U.S.C. § 4106(f)(1), and one that applies to the Department of Defense in particular, 10
U.S.C. § 3406(f)(1). The text of the two provisions is similar, except for the different monetary thresholds over
which task order protests may be heard by the Comptroller General.” (emphasis added and citations in original)),
reh’g en banc granted, opinion vacated sub nom. on other grounds, Percipient.ai, Inc. v. United States, 121 F.4th
1311 (Fed. Cir. 2024). Accordingly, given the identical operative language and purpose of each task order bar, the
Court treats each’s caselaw as concomitantly informative on the meaning and statutory purpose of § 3406(f).
United States Department of the Navy’s Solicitation No. N39430-14-F-EURAFSWA
(the “Solicitation”), see First Amended Complaint at 1, ECF No. 20 [hereinafter
Compl.], made “in connection with the issuance or proposed issuance of a task or
delivery order,” 10 U.S.C. § 3406(f)? If the task order bar applies, dismissal is
“required.” Computer World Servs. Corp. v. United States, 173 Fed. Cl. 582, 586
(2024). Otherwise, the case proceeds, sans some additional reason requiring dismissal.
The Court holds that FASA’s bar is inapplicable because FASA’s two
requirements are not satisfied. First, the U.S. Navy did not (nor could it) issue or
propose to issue the Solicitation. Second, this protest is not connected to the
Solicitation because Siemens neither seeks to set aside nor generally interfere with the
Solicitation. With neither FASA element satisfied, Siemens’ lawsuit is therefore
jurisdictionally proper under this case’s rare facts and must be allowed to proceed.
I
On June 21, 2022, Siemens filed its original complaint against defendant,
seeking recovery of its bid preparation costs incurred in pursing the Solicitation. See
generally Complaint, ECF No 1. But Siemens quickly moved unopposed on July 5,
2022, to stay the proceedings until a parallel appeal of an Armed Services Board of
Contract Appeals (the “Board”) decision was resolved by the United States Court of
Appeals for the Federal Circuit. See generally Plaintiff’s Unopposed Motion to Stay
Proceedings, ECF No 8. On July 8, 2022, the Court stayed the proceedings. See
generally Order Staying Case, ECF No. 11.
On May 29, 2024, Siemens informed the Court that the Federal Circuit had
denied Siemens’ parallel appeal. See generally Joint Status Report, ECF No. 17 (citing
Siemens Gov’t Techs., Inc., v. Sec’y of the Navy, No. 2022-2240, 2024 WL 2043201
(Fed. Cir. May 8, 2024)). Accordingly, “Siemens now intends to pursue a claim or
claims before this Court.” Id. at 1. On June 6, 2024, the Court lifted the stay. See
generally Status Conference Order, ECF No. 18. After a status conference on June 14,
2024, the Court adopted an amended complaint and motion to dismiss briefing schedule
until September 2024. See generally Order Lifting Stay and Scheduling Order, ECF
No. 19. On June 24, 2024, Siemens filed their Amended Complaint, alleging that the
U.S. “Navy’s mishandling of the [Solicitation], culminating in its refusal to reimburse
Siemens for its wasted proposal costs, was arbitrary and capricious, constituted an
abuse of discretion and otherwise was not in accordance with” the U.S. Navy’s statutory
obligations. Compl. at 2. And like in its original complaint, Siemens seeks “to recover
its bid preparation costs that it incurred” in pursuing the Solicitation. Id. at 1. Broken
down, Siemens’ claim arises from four key events.
Event One: Siemens Becomes the Provisional Solicitation Awardee. On
September 19, 2014, pursuant to an October 2007 United States Department of Energy
Indefinite Delivery, Indefinite Quantity (“IDIQ”) Energy Saving Performance Contract,
the U.S. Navy solicited a preliminary assessment of the “merits, technical feasibility,
-2-
level of projected energy savings, economics, and price” to “install energy conservation
measures at six overseas [U.S. Navy] bases.” Id. at 1, 6. Those bases are:
• Naval Air Station Sigonella, Italy (“Sigonella”);
• Naval Station Rota, Spain (“Rota”);
• Naval Support Activity Naples, Italy (“Naples”);
• Naval Support Activity Bahrain (“Bahrain”);
• Naval Support Activity Souda Bay (“Souda Bay”); and
• Camp Lemonnier, Djibouti (“Camp Lemonnier”).
Id. at 6. Between 2014 and 2015, the U.S. Navy and Siemens held multiple discussions
with the U.S. Navy to repeatedly revise proposals on the U.S. Navy’s needs at the
bases. Id. at 6–7. Eventually, on December 1, 2015, the U.S. Navy tentatively awarded
the contract to Siemens, including all six components. Id. at 8. The U.S. Navy directed
Siemens to conduct energy conservation audits at Souda Bay and at Camp Lemonnier
on December 2, 2015, and on March 8, 2016, respectively. Id. at 8–9.
Event Two: Siemens Is Informed of Duplicative Projects at Souda Bay. On
February 5, 2016, Siemens arrived at Souda Bay to begin its audit process—and made a
shocking discovery. Id. at 9. “During its first few weeks at the facility, Siemens
discovered that the [U.S.] Navy had already commissioned energy conservation
measures at Souda Bay that duplicated and directly undermined the scope of work for
the projects that the [U.S.] Navy had directed Siemens to undertake.” Id. Siemens was
not aware of the U.S. Navy’s parallel procurement of Souda Bay energy conservation
efforts. Id. Nevertheless, the U.S. Navy, by requiring years of planning and by
receiving Congressional appropriations for such efforts, was allegedly aware of “these
duplicative procurement[s] at Souda Bay before it asked Siemens to conduct a
preliminary assessment.” Id. Siemens later discovered duplicative energy conservation
projects at Sigonella, Naples, and Rota as well. Id. at 10. On February 19, 2016,
Siemens informed the U.S. Navy of its discoveries and requested an investigation into
the matter. Id. at 9–10.
Event Three: Siemens Is Informed of Duplicative Projects at Camp
Lemonnier. On May 13, 2016, Siemens arrived at Camp Lemonnier to being its audit
process—and once again discovered the existence of a duplicate project. Id. at 11.
“During the first few days of [Siemens’] site visit, [it] observed that significant
construction had occurred at Camp Lemonnier since the [U.S.] Navy issued its”
Solicitation. Id. Like at Souda Bay, a parallel procurement had been issued to a
different contractor prior to Siemens’ award. Siemens alleges that U.S. Navy officials
discussed the existence of the duplicate contract in email communications in the months
prior to Siemens arriving at Camp Lemonnier. Id. at 10–11. Between March 18, 2016,
-3-
and March 25, 2016, U.S. Navy officials “acknowledge[d] that Siemens was unaware of
[the Camp Lemonnier’s] duplicative effort and that Siemens would be harmed if the
[U.S.] Navy continued to withhold this information.” Id. at 10. Particularly, U.S. Navy
Commander, Darren Hale, “expressed ‘concern about our partnership with Siemens on
the other $150M+ in contracts in Europe’ if ‘there is a negative financial impact on
Siemens’ on the Camp Lemonnier project”; and because of this risk, Commander Hale
informed U.S. Navy Contracting Officer, Bryson Jo, that U.S. Navy Commander
Micheal Oesterreicher was “ready to call the Expeditionary Warfare Center (the [U.S.]
Navy entity that issued the Solicitation).” Id. Officer Jo, nonetheless, dissuaded
Commanders Hale and Oesterreicher from contacting the Expeditionary Warfare Center
because “the U.S. Navy would not be liable to reimburse them for their efforts” at
Camp Lemonnier. Id. at 11. The U.S. Navy heeded Officer Jo’s advice; Siemens was
not informed. Id. On May 3, 2016, Siemens informed the U.S. Navy about its
discovery at Camp Lemonnier. Id. at 12.
Event Four: The U.S. Navy Cancels Siemens’ Souda Bay and Camp
Lemonnier Provisional Solicitation Awards. On April 13, 2016, Siemens sent a letter
to the U.S. Navy, concerned that the U.S. Navy “had withheld . . . information and, to
that date, still ha[s] not formally acknowledge[d] or resolved the [duplicative
procurements] issue, [despite the fact that] Siemens had alerted the [U.S.] Navy of the
problem at Souda Bay as early as February 19, 2016.” Id. For two months, from May
2016 until June 2016, Siemens continually raised similar concerns with the U.S. Navy,
arguing that both the Camp Lemonnier and the Souda Bay energy conservation projects
were likely no longer economically viable. Id. 12–13.
Acknowledging these “frustrat[ing]” issues, the U.S. Navy decided to undergo a
viability analysis of Siemens’ Souda Bay contract. Id. at 14–15. On September 14,
2016, the U.S. Navy completed this analysis and determined that the project should “not
‘continue to final proposal.’” Id. at 15. On April 7, 2017, the U.S. Navy canceled
Siemens’ Souda Bay energy conservation planning. Id. On March 8, 2019, after
determining that Siemens’ Camp Lemonnier energy conservation efforts were also not
viable, the U.S. Navy canceled Siemens’ Camp Lemonnier planning as well. Id. at 16.
Nonetheless, on September 26, 2018, the U.S. Navy still awarded Siemens the
Sigonella, Rota, and Naples energy conservation contracts. Id. at 17.
Due to the U.S. Navy cancelling the Souda Bay and Camp Lemonnier
procurements, Siemens lost a total of $5,182,641.97 in bid preparation costs. Id. at 17–
18. Siemens then sued the U.S. Navy in this Court to recoup these costs. See generally
id.; Complaint, ECF No 1.
On September 26, 2024, defendant filed its motion to dismiss arguing, first, that
FASA’s task order bar applied and, second, that regardless of FASA’s application, most
of Siemens’ claims are barred by collateral estoppel. See generally Def.’s Mot. On
October 24, 2024, Siemens responded in oppostion to defendant’s motion to dismiss.
See generally Siemens’ Response in Opposition to the Motion to Dismiss, ECF No. 29
[hereinafter Pl.’s Resp.]. On November 7, 2024, defendant replied in support of its
-4-
motion to dismiss. See generally Defendant’s Reply in Support of its Motion to
Dismiss, ECF No. 30 [hereinafter Def.’s Reply]. On November 20, 2024, the Court
held oral argument on the motion to dismiss. On March 22, 2025, the Court denied
defendant’s motion to dismiss and promised a memorandum opinion to follow. See
generally Order denying Defendant’s Motion to Dismiss, ECF No. 34.
II
Being its jurisdictional backbone, the Tucker Act (along with its sister statutes)
allows the Court to “render judgment upon any claim against the United States founded
either upon the Constitution, or any Act of Congress or any regulation of an expressed
or implied contract with the United States, or for liquidated or unliquidated damages in
cases not sounding in tort,” 28 U.S.C. § 1491(a)(1), including government solicitation
protests, 28 U.S.C. § 1491(b)(1); e.g., Computer World Servs. Corp., 173 Fed. Cl. at
585.
FASA limits the Tucker Act’s jurisdictional grant by preventing causes-of-action
made “in connection with the issuance or proposed issuance of a task or delivery
order.” 10 U.S.C. § 3406(f). If a cause-of-action “contravenes FASA, then it must be
dismissed for lack of subject-matter jurisdiction” under Rule 12(h)(3) of the Rules of
the Court of Federal Claims. Computer World Servs. Corp., 173 Fed. Cl. at 585 (citing
Percipient.ai, Inc. v. United States, 104 F.4th 839, 847 (Fed. Cir.), reh’g en banc
granted, opinion vacated on other grounds, 121 F.4th 1311 (Fed. Cir. 2024) (denying
rehearing on FASA’s jurisdictional bar)).
When considering defendant’s motion to dismiss for lack of subject-matter
jurisdiction, the Court must take the facts alleged in Siemens’ complaint as true.
Erickson v. Pardus, 551 U.S. 89, 93–94 (2007) (per curiam). But if a motion to dismiss
challenges the jurisdictional facts, the Court can look beyond the complaint itself, see
Moyer v. United States, 190 F.3d 1314, 1318 (Fed. Cir. 1999), for “allegations alone are
insufficient to meet the [plaintiff's] burden” of properly invoking the Court's subject-
matter jurisdiction, see Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1584 (Fed.
Cir. 1993).
III
Defendant moves to dismiss on two grounds. First, FASA’s jurisdictional bar
blocks Siemens’ claims because the Solicitation was a task order. Def.’s Mot. at 14–15.
Second, irrespective of FASA’s applicability, Siemens’ claims are collaterally estopped
because, as sought here, Siemens’ request to be reimbursed for its proposal preparation
costs was already denied in the parallel appeal of the Board’s decision. Id. at 14–15.
Both arguments fail.
-5-
A
The Court starts with the statutory text. Barnhart v. Sigmon Coal Co., 534 U.S.
438, 461 (2002) (“Our role is to interpret the language of the statute enacted by
Congress.”). 10 U.S.C. § 3406(f) disallows any “protest . . . in connection with the
issuance or proposed issuance of a task or delivery order.” This statutory language is
“clear,” SRA Int’l, Inc. v. United States, 766 F.3d 1409, 1413 (Fed. Cir. 2014), and
therefore interpreted unambiguously, Connecticut Nat. Bank v. Germain, 503 U.S. 249,
253–54 (1992) (“[A] statute [means] what it says.”), meaning “any claim” associated
with an issued or proposed task order “is beyond our subject-matter jurisdiction,”
Computer World Servs. Corp., 173 Fed. Cl. at 585 (emphasis in original). Ironically,
this clarity can invite confusion.
Defendant believes that FASA’s analysis is simplistic: The Solicitation is labeled
‘task order’ and so FASA’s jurisdiction bar mandates dismissal, seemingly saying ‘key-
in ‘ctrl+f’ to find similar wording in a document and, if it is there, case closed.’ See
Def.’s Mot. at 9–14; see also Percipient.ai, Inc., 104 F.4th at 849 (“[T]he Government
reads the statute as if it broadly bars all protests made in connection with a task order . .
. rather than just those protests made in connection with the issuance or proposed
issuance of a task order.” (internal quotation marks omitted and emphasis in original)).
Often, the analysis can be straightforward. E.g., Computer World Servs. Corp., 173
Fed. Cl. at 585; Prime Physicians, PLLC v. United States, 174 Fed. Cl. 190, 196 (2024)
(barring a protest because it “turn[ed] on the lawfulness of the language of a task
order.”).
Often is not always. E.g., Mlinqs, LLC v. United States, No. 22-1351, 2023 WL
2366654, at *14–16 (Fed. Cl. Mar. 6, 2023) (holding that temporally disconnected
protests on a procurement originating as a routine solicitation and was converted into a
task order is not jurisdictionally barred). Sometimes, like here, applying FASA’s
jurisdictional bar is factually complex under its two-element test which only prevents
lawsuits “in connection with” a proposed or issued task order—which means that two
elements must be established. 10 U.S.C. § 3406(f); see also Bostock v. Clayton Cnty.,
Georgia, 590 U.S. 644, 683 (2020) (Courts are “not free to overlook plain statutory
commands.”).
First, a proposed or issued task order must exist to be protested. But does the
FASA bar apply when an agency solicits redundant proposals from potential bidders?
As alleged, the U.S. Navy knew or should have been aware—from the beginning—that
it had previously awarded a contract to another corporation for the same services sought
at six overseas bases. Compl. at 5. If the U.S. Navy’s need is fictional, the agency
would have violated its requirements “to act in good faith and use reasonable care in
computing its estimated needs.” Medart, Inc. v. Austin, 967 F.2d 579, 581 (Fed. Cir.
1992); see Rumsfeld v. Applied Companies, Inc., 325 F.3d 1328, 1334–35 (Fed. Cir.
2003) (reaffirming Medart, Inc.). Without a “‘realistic’” need, Fed. Grp., Inc. v. United
States, 67 Fed. Cl. 87, 97 (2005) (citing 48 C.F.R. § 16.503), the Agency’s solicitation
was illegitimate—meaning it cannot propose (read as “something offered for . . .
-6-
acceptance”) a need that is already fulfilled—and, thus, the U.S. Navy could neither
have awarded a contract to Siemens nor could Siemens have accepted that award.
Proposal, B LACK ’ S L AW D ICTIONARY (11th ed. 2019); e.g., Compl. at 13–17 (alleging
that the U.S. Navy was internally aware that the Camp Lemonier and Souda Bay
contract components were already awarded to a party other than Siemens). In this
unique context, FASA’s bar is inapplicable because the task order was void from the
start.
Second, the protest must be predicated upon the proposed or issued task order.
Caselaw instructs that FASA’s jurisdictional bar is linked to the form of relief being
requested. Cf., e.g., Computer World Servs. Corp., 173 Fed. Cl. at 586. While not
“dispositive,” relief sought can inform the purpose of Siemens’ claims. SRA Int'l, Inc.,
766 F.3d at 1414. Had Siemens, like Computer World, sought relief to either rescind
the non-redundant task order or block award of a task order, its lawsuit would
“[o]bviously” be in connection with a task order. 173 Fed. Cl. at 586. But Siemens did
not request this relief. Instead, Siemens only seeks to be reimbursed after the
government, in violation of statutory obligations, allegedly mislead Siemens about its
needs, see Compl. 18–24, making this case closer to Percipient.ai, where the Federal
Circuit found that the claim and the relief sought—that being, whether an agency’s
statutory misinterpretation of task order obligations harmed Percipient.ai—“did ‘not
assert the wrongfulness of, or seek to set aside, any task order’ or an agency’s
corrective action of a task order that was issued or pending,” Computer World Servs.
Corp., 173 Fed. Cl. at 586 (quoting Percipient.ai, Inc., 104 F.4th at 846–47). Siemens
has never sought to set aside or generally interfere with any pending or issued task
order; it only wishes to be made whole after being led astray by the U.S. Navy’s false
procurement needs—a claim FASA does not bar.
Neither element, as applied to this case’s rare factual allegations, is satisfied.
Siemens’ lawsuit is therefore jurisdictionally proper under the parameters discussed
more thoroughly below.
1
An agency must have “issued or proposed [the] issuance of a task . . . order” for
the jurisdictional bar to apply. 10 U.S.C. § 3406(f). This requirement is so obvious
that it has been rarely remarked upon. E.g., Mori Assocs., Inc. v. United States, 113
Fed. Cl. 33, 37 (2013) (illustrating the importance of element one); see also, e.g.,
Percipient.ai, Inc., 104 F.4th at 849 (noting that the FASA bar only applies if there is
an “issuance or proposed issuance of a task order.” (emphasis in original)). Still, the
requirement is nonetheless crucial—for if no task order has either been awarded or
proffered by an agency, then the FASA bar is inapplicable. 22nd Century Techs., Inc.
v. United States, 57 F.4th 993, 999 (Fed. Cir. 2023) (rooting “FASA’s unambiguous
language” as barring claims only made against task or delivery orders).
Siemens is only seeking recovery of bid preparation costs relating to two
“canceled Sonda Bay and Camp Lemonnier components of this procurement,” Compl. at
-7-
17, as opposed to seeking costs arising from the awarded, i.e., ‘issued,’ Sigonella, Rota,
and Naples camp components, 3 id. at 18–24. The only dispute, then, is whether the
Solicitation’s Sonda Bay and Camp Lemonnier components were properly “proposed”
by the U.S. Navy. 10 U.S.C. § 3406(f); compare Def.’s Reply at 5, with Pl.’s Resp. at
8–10.
FASA neither defines ‘proposed issuance,’ see 10 U.S.C. § 3401, nor seemingly
has the Federal Circuit defined the phrase. The Court therefore relies upon statutory
interpretation principles instead.
Statutory application is “more than [its] separate words, as a melody is more than
[its] notes.” Helvering v. Gregory, 69 F.2d 809, 810–11 (2d Cir. 1934) (Hand, J.). A
word or phrase’s placement in a sentence determines the statutory command, for
linguistic structure guides how text is to be enforced. Gundy v. United States, 588 U.S.
128, 140–41 (2019) (plurality opinion) (reasoning that “statutory interpretation [is] a
‘holistic endeavor’ which determines meaning by looking not to isolated words, but to
text in context, along with purpose and history.”). So, the phrase, “proposed issuance,”
must be read in context with the meaning of both ‘proposed’ and ‘issuance,’ 10 U.S.C.
§ 3406(f). Definitionally, to issue a task order is to award an agency contract, see
Computer World Servs. Corp., 173 Fed. Cl. at 585–86, and to propose is to “offer[] for .
. . acceptance,” Proposal, B LACK ’ S L AW D ICTIONARY (11th ed. 2019). Putting the
definitions together, a task order’s proposed issuance exists when an agency can offer
to award a contract that can be accepted by a successful party—and, here, no valid
award could be offered or accepted.
This definition introduces a crucial question: What prerequisite is required for
an agency to offer, i.e., ‘propose,’ the issuance of a task order? An agency solicitation
can only “solicit goods or services” to satisfy actual needs or obligations. Mori
Assocs., Inc., 113 Fed. Cl. at 37; cf. Distributed Sols., Inc. v. United States, 539 F.3d
1340, 1346 (Fed. Cir. 2008) (explaining that, under 28 U.S.C. § 1491(b)(1), the federal
contracting acquisition process is constructed around determining government “need”).
Hence, an agency cannot “carelessly guess at its needs” when proposing a contract
because its requests must result in real satisfaction. Medart, Inc., 967 F.2d at 581; see
Applied Companies, 325 F.3d at 1334–35 (reaffirming Medart, Inc.); Fed. Grp., Inc., 67
Fed. Cl. at 97 (agency needs must be “‘realistic’” (citing 48 C.F.R. § 16.503)).
Consequently, only when an obligation—the goods or services required to fulfill agency
needs—exists can the agency offer, or put differently, propose to award a contract, for
only then can a successful party, like Siemens, accept the contract to satisfy the need
itself.
Agencies are, of course, welcome to reevaluate their needs. Organizational
demands do shift. But revaluating needs assumes that a need existed initially. If no
contractual obligation could be satisfied, or was already satisfied, by a preceding
3
FASA unequivocally blocks a claim based on the awarded components—Sigonella, Rota, and Naples—
anyway. 10 U.S.C. § 3406(f); e.g., SRA Int’l, Inc., 766 F.3d at 1413; 22nd Century Techs., Inc., 57 F.4th at 999;
Computer World Servs. Corp., 173 Fed. Cl. at 585.
-8-
contract, a subsequent offer to fulfill that same need is unacceptable because no
“obligation to support the contract” exists. Torncello v. United States, 681 F.2d 756,
769 (Ct. Cl. 1982). An offer that cannot be accepted is a nullity; it is an illusion. Id.
Often, when a contract is terminated “without consequence” to the parties’ right(s), the
discontinuance can prove that the contract was unacceptable and thus illusory. Woll v.
United States, 45 Fed. Cl. 475, 478 (1999), aff’d, 251 F.3d 171 (Fed. Cir. 2000). That
scenario allegedly occurred here—but Siemens was nonetheless harmed.
The U.S. Navy, as exemplified in internal communications and later in
communications with Siemens, awarded energy conservation contracts at Camp
Lemonier and Souda Bay before proposing the Solicitation at issue. E.g., Compl. at 9–
12, 14–15. This necessarily implies that the U.S. Navy had no actual need—a fact it
should have been aware of—prior to proclaiming that it would eventually award the
Solicitation to Siemens. Id. Neither could the U.S. Navy award the Solicitation nor
could Siemens have accepted the Solicitation award because the U.S. Navy had already
fulfilled its need for energy conservation at Camp Lemonier and Souda Bay. Indeed,
when the U.S. Navy terminated the Camp Lemonier and Souda Bay contract
components, it did so aware that the award was of no consequence; its energy
conservation needs were allegedly already fulfilled by a prior contract. Id. at 13–17. In
short, no agency need equals no offer that can be accepted; or put differently, no
proposed task order existed. FASA’s jurisdictional bar is therefore inapplicable for that
reason.
2
The protest must be “in connection with” the proposed or issued task order for
the jurisdictional bar to apply. 10 U.S.C. § 3406(f). While, usually, “any claim . . .
made ‘in connection with the issuance or proposed issuance of a task or delivery order’
is beyond our subject-matter jurisdiction,” Computer World Servs. Corp., 173 Fed. Cl.
at 585 (emphasis in original) (relying, in part, upon SRA Int’l, Inc., 766 F.3d at 1413),
the Federal Circuit recently recognized an exception in Percipient.ai, Inc. that applies
here.
Percipient.ai, Inc.—like its sister Federal Circuit cases, SRA Int’l, Inc. and 22nd
Century Techs.—links the ‘in connection with’ element to the form of relief requested
by a plaintiff. See SRA Int’l, Inc., 766 F.3d at 1414 (reasoning that, while not
“dispositive,” relief sought can inform the purpose of a plaintiff’s claims); cf., e.g.,
Computer World Servs. Corp., 173 Fed. Cl. at 586. For instance, Percipient.ai, Inc. did
“not challenge the issuance of” any task order specifically. Percipient.ai, Inc., 104
F.4th at 849–51. Rather, it sought a revaluation of the statutory language used by the
agency to issue task orders generally. Id.
Hypothetically, if the Camp Lemonier and Souda Bay contract components were
proposed, Percipient.ai, Inc. directly applies because Siemens “did ‘not assert the
wrongfulness of, or seek to set aside, any task order’ or an agency's corrective action of
a task order that was issued or pending.” Computer World Servs. Corp., 173 Fed. Cl. at
586 (quoting Percipient.ai, Inc., 104 F.4th at 846–47). No task order related to Camp
-9-
Lemonier and Souda Bay will be tossed aside, like in a plethora of other blocked cases,
Computer World Servs. Corp., 173 Fed. Cl. at 585; Prime Physicians, PLLC, 174 Fed.
Cl. at 196, given that Siemens does not seek that result, see Compl. 18–24; Pl.’s Resp.
at 13. Nor could Siemens even demand this result, for the U.S. Navy has already
rescinded those contract components. See Compl. at 13–17; cf. Computer World Servs.
Corp., 173 Fed. Cl. at 586 (“Obviously, to rescind the Task Order connects the relief to
the Task Order itself.”). Moreover, Siemens’ claim is not predicated upon the
“wrongfulness” of a task order’s contractual requirements. Computer World Servs.
Corp., 173 Fed. Cl. at 586. Instead, Siemens only seeks to be reimbursed after the U.S.
Navy, in violation of its statutory obligations, allegedly mislead Siemens about its
needs, making this case like Percipient.ai. See Compl. 18–24; Pl.’s Resp. at 13.
Siemens’ lawsuit is therefore not in connection with a task order, making FASA’s
jurisdictional bar inapplicable.
Fittingly, by battling this comparison, defendant only further highlights its
applicability. For instance, at oral argument, the Court asked: “Well, it seems that
[Siemens is] asking the [U.S.] Navy to give them money because they were
misinformed by the [U.S.] Navy for whatever reason?” Oral Argument 24:4–24:7. In
answering, defendant’s counsel affirmed that, in any other situation, the remedy of
restitution is available; only the supposed existence of a task order eliminates the
Court’s authority—an inapplicable point. Id. at 23:16–24:7.
B
Defendant’s reliance on collateral estoppel is also unsuccessful. Def.’s Mot. at
14–15. Siemens’ parallel appeal of the Armed Services Board of Contract Appeals’
decision concerned whether the U.S. “Navy was contractually obligated to reimburse it”
under the IDIQ; but here, Siemens seeks reimbursement under statutory obligations, not
contractual ones. Compare Siemens Gov’t Techs., Inc., 2024 WL 2043201, at *2, with
Compl. at 21, 23. Both cases obviously concern different “legal principles”—
evaluating contractual versus statutory duties—and, therefore, Siemens is not seeking to
relitigate already adjudicated issues, making collateral estoppel inapplicable. Montana
v. United States, 440 U.S. 147, 157 (1979); see Mobility Sys. & Equip. Co. v. United
States, 51 Fed. Cl. 233, 235 (2001) (“While a litigant must have [its] day in court, [it] is
not entitled to repeat that same day in a different court.”).
“Collateral estoppel is only appropriate if the issue in the current litigation is
identical to [the] issue decided in the [previous] action,” Biafora v. United States, 773
F.3d 1326, 1333 (Fed. Cir. 2014), and, if so, would preclude the Court from
adjudicating the case, In re Freeman, 30 F.3d 1459, 1465 (Fed. Cir. 1994). With this
outcome, the doctrine is unsurprisingly strenuous, and only applies when all four
requirements are established:
(1) the issue being presented is identical with the issue previously
adjudicated; (2) the issue was actually litigated in the prior action; (3) the
resolution of the issue was essential to a final judgment in the prior action;
- 10 -
and (4) the party against whom collateral estoppel is being asserted had a
full and fair opportunity to litigate the issue in the prior action.
Google LLC v. Hammond Development International, Inc., 54 F.4th 1377, 1381 (Fed.
Cir. 2022) (quoting In re Freeman, 30 F.3d at 1465). By analyzing the very first
requirement—that the current issues presented are “identical” to the issues in the prior
adjudication—defendant’s position crumbles. Id.
Again, the Federal Circuit in the parallel appeal rejected Siemens’ argument that
the U.S. Navy was contractually obligated under the IDIQ to reimburse Siemens for its
bid preparation costs, see Siemens Gov’t Techs., Inc., 2024 WL 2043201, at *3–4,
whereas, here, Siemens is seeking reimbursement of its bid preparation costs due to
statutory violations, see Compl. at 21, 23. Because there are different “legal
principles” at work in the previous and current litigation—i.e., whether statutory text,
as opposed to an IDIQ contract, requires reimbursement—the issues are not identical
for collateral estoppel purposes. Montana, 440 U.S. at 157. For this reason alone, as
all its requirements must be met, collateral estoppel does not apply to the present
dispute. 4
* * *
Defendant’s Motion to Dismiss, ECF No. 25, is DENIED. The Court
SHALL hold a status conference on April 15, 2025, at 3:00 PM EDT to discuss the
case’s next stage.
IT IS SO ORDERED.
s/ Loren A. Smith
Loren A. Smith,
Senior Judge
4
Defendant, in footnote four of its Motion, argues that Siemens’ claim is a “Contract Disputes Act” issue
because Siemens believes the U.S. Navy “failed to honor a contractual relationship.” Def.’s Mot. at 15 n.4. In
response, Siemens affirms that it is not making a Contract Disputes Act claim. Pl.’s Resp. at 14. The Court sees no
reason to distrust this affirmation, nor does the Court believe Siemens is making such a claim anyway. This case
involves statutory obligations, not contractual ones.
- 11 -