Opinion

Eastern Maine Conservation Initiative v. Board of Environmental Protection

  • 2025 ME 35
Court
Supreme Judicial Court of Maine
Filed
Apr 10, 2025
Status
Published
Author
DOUGLAS, J.
On the bench
STANFILL, C.J., and MEAD, HORTON, CONNORS, LAWRENCE, and DOUGLAS, JJ.
Cited by
3 cases
Authority
More cited than 54.4%

The opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions

Decision: 2025 ME 35

Docket: Ken-23-348

Argued: April 10, 2024

Decided: April 10, 2025

Panel: STANFILL, C.J., and MEAD, HORTON, CONNORS, LAWRENCE, and DOUGLAS, JJ.

EASTERN MAINE CONSERVATION INITIATIVE et al.

v.

BOARD OF ENVIRONMENTAL PROTECTION

DOUGLAS, J.

[¶1] Eastern Maine Conservation Initiative and Roque Island Gardner

Homestead Corporation (collectively, “Petitioners”) appeal from a judgment of

the Superior Court (Kennebec County, Murphy, J.) affirming the Board of

Environmental Protection’s decision upholding a permit issued by the

Department of Environmental Protection to Kingfish Maine, Inc. for an

aquaculture operation in Jonesport. The permit, which the Department issued

after conditionally granting Kingfish a wastewater discharge permit for the

same project, authorized Kingfish to construct a facility in accordance with the

Site Location of Development Law (Site Law), 38 M.R.S. §§ 481 to 489-E (2024),

and to install intake and outfall pipes pursuant to the requirements of the

Natural Resources Protection Act (NRPA), 38 M.R.S. §§ 480-A to 480-JJ (2024).

2

Petitioners argue that the Board erred in determining the scope of its review

under NRPA and by approving the NRPA component of the permit without

independently evaluating the environmental impacts associated with the

discharge of treated wastewater. We disagree and affirm the judgment.

I. BACKGROUND

[¶2] The following facts and procedure are derived from the Board’s

supported findings and the procedural record. See Sultan Corp. v. Dep’t of Env’t

Prot., 2022 ME 21, ¶ 2, 272 A.3d 296; Martin v. MacMahan, 2021 ME 62, ¶ 2, 264

A.3d 1224.

[¶3] In 2020, Kingfish began the process of securing permits from the

Department to construct and operate a land-based recirculating aquaculture

system designed to raise saltwater fish. The project involves the construction

of a facility consisting of two primary buildings, access roads, and ancillary

buildings. It also involves the installation of two approximately 1,400-foot-long

intake pipes to draw water from Chandler Bay and two approximately

2,800-foot-long outfall pipes to discharge treated wastewater into the bay.

Kingfish proposed to begin construction of the facility and the pipes upon

obtaining all required federal, state, and local permits.

3

A. Agency Proceedings

1. The Discharge Permit

[¶4] In August 2020, Kingfish applied to the Department for a combined

Maine Pollutant Discharge Elimination System Permit and Water Discharge

License (the discharge permit) to allow for a daily maximum discharge of 28.7

million gallons of treated wastewater from the proposed aquaculture facility.

See 38 M.R.S. § 413 (2024).

[¶5] In June 2021, the Department approved Kingfish’s application and

issued the discharge permit. The Department found that the effluent discharge

from the facility into Chandler Bay would not lower the quality of any classified

body of water below its stated classification or the quality of any unclassified

body of water below its anticipated classification.1 See 38 M.R.S.

§ 414-A(1)(A), (B) (2024); 38 M.R.S. § 465-B(2) (2020)2. In addition, the

Chandler Bay is a Class SB body of water, the “2nd highest classi ication.” 38 M.R.S. § 465-B(2)

1

(2020). Petitioners do not dispute this fact.

2 Section 465-B(2) has recently been amended. See P.L. 2021, ch. 551, § 15 (effective Aug. 8, 2022)

(codi ied at 38 M.R.S. § 465-B(2)(B) (2024)); see also infra n.14. Because this amendment took effect

after King ish’s discharge permit application became complete on August 17, 2020, we cite to the

2020 Maine Revised Statutes, which contain the version of section 465-B(2) that was effective on that

date. See 06-096 C.M.R. ch. 2, § 11(F) (effective June 9, 2018) (“Unless otherwise provided by law, all

license applications . . . are subject to the substantive laws and rules in effect on the date the

application is accepted as complete for processing.”).

Several other statutes referenced in this opinion have also been amended recently. See, e.g., P.L.

2023, ch. 481, § 11 (effective Oct. 25, 2023) (codi ied at 38 M.R.S. § 480-D(1) (2024)); P.L. 2021, ch.

551, § 7 (effective Aug. 8, 2022) (codi ied at 38 M.R.S. § 464(4)(F)(2) (2024)). In each of these other

4

Department found that the effluent discharge associated with Kingfish’s project

would satisfy various applicable licensing standards, including dilution criteria,

06-096 C.M.R. ch. 530, §§ 2-4 (effective Mar. 21, 2012), dissolved oxygen

criteria, 38 M.R.S. § 465-B(2)(B), and temperature criteria, 06-096 C.M.R.

ch. 582 (effective May 4, 1996). But the Department found that the effluent

discharge would exceed the default threshold for levels of nitrogen

concentration and would therefore lower water quality3 specifically in relation

to eelgrass habitat.4 The Department explained, however, that its finding of an

anticipated lowering of water quality “is not a determination that there is

toxicity related to the discharge nor . . . a determination that the discharge is in

violation of any water quality criterion or standard. Rather, this determination

triggers the [State’s] antidegradation process in 38 M.R.S. § 464(4)(F)(5).”5 The

instances, we cite the 2024 Maine Revised Statutes because the amendments do not concern the

issues on appeal.

3 A lowering of “the existing quality of any body of water,” 38 M.R.S. § 414-A(1)(C) (2024), is

statutorily distinct from a lowering of “the quality of any classi ied body of water below such

classi ication,” 38 M.R.S. § 414-A(1)(A).

4 Without a uniform state or federal threshold for nitrogen concentration, the Department

employed a concentration threshold that was consistent with its historical practice and that took into

account the proximity of eelgrass to the discharge location.

5 The State’s antidegradation process enables the Department to approve a discharge permit even

if the proposed discharge is found to lower water quality. 38 M.R.S. § 464(4)(F); 38 M.R.S.

§ 414-A(1)(C). For a proposed discharge to qualify for a permit under this policy, the Department

must ind, following an opportunity for public participation, that the discharge is, among other

criteria, “necessary to achieve important economic or social bene its to the State” and that the water

body’s classi ication standard is either satis ied or, if it is not satis ied, that this de iciency is not

5

Department further found that the existing in-stream use of Chandler Bay by

the surrounding species and habitat would be maintained and protected.

See 38 M.R.S. § 464(4)(F)(1-A) (2024).

[¶6] The discharge permit imposes a number of standard and special

conditions, including numeric and narrative effluent limitations as well as

monitoring requirements. The narrative effluent limitations provide, in part,

that Kingfish “must not discharge effluent that contains materials in

concentrations or combinations which are hazardous or toxic to aquatic life”

and “must not discharge effluent that lowers the quality of any classified body

of water below such classification.” In addition, Kingfish is subject to ongoing

monitoring requirements whereby it must regularly measure and report on

water quality, including specifically the nitrogen concentration. The discharge

permit expressly provides that the Department may “modify this permit” to

require different effluent limits “where there is a reasonable potential that the

attributable to the proposed discharge. 38 M.R.S. § 464(4)(F)(3), (5). In applying the policy, the

Department can refer on a case-by-case basis to considerations in its non-binding Antidegradation

Waste Discharge Program Guidance. See Waste Discharge Program Guidance Memorandum from

Brian Kavanah, Director, Div. of Water Res. Regul., to Water Licensing & Compliance Staff (June 13,

2001), https://www.maine.gov/dep/bep/2021/12-16-21/TR%20AppB1_MDEP_WW-DEPLW0267

%20-%20antidegradation.pdf [https://perma.cc/T3H2-YSLF]. Such considerations include the

project’s potential to generate commercial activity, the applicant’s ability to comply with ef luent

limitations, the treatment facility’s maintenance, and the feasibility of alternative measures to

mitigate the diminution in water quality. Id.

6

effluent may cause water quality criteria to be exceeded” or to “change

monitoring requirements or limitations based on new information.”

[¶7] Petitioners did not appeal the Department’s decision to

conditionally approve Kingfish’s application for the discharge permit. Another

interested party, Sierra Club, did appeal the decision, but the Board dismissed

the appeal for lack of standing and for failing to comply with the Board’s

content-related requirements for appeals.

2. The NRPA and Site Law Permits

[¶8] In March 2021, Kingfish applied to the Department for a Site Law

permit to construct the facility, and also applied for a NRPA permit to install the

intake and outfall pipes. A NRPA permit was required because of the potential

impacts to freshwater and coastal wetlands from the construction and dredging

activities necessary for the pipes to be installed. See 38 M.R.S.

§ 480-C(2)(A), (D).

[¶9] On November 12, 2021, the Department approved Kingfish’s

application and issued a combined NRPA and Site Law permit with conditions.

With respect to the NRPA permit, Kingfish’s application satisfied the eleven

standards set out in the NRPA statute at 38 M.R.S. § 480-D, including the

standard relevant in this appeal, with the Department finding that

7

[t]he proposed activity will not unreasonably harm any significant

wildlife habitat, freshwater wetland plant habitat, threatened or

endangered plant habitat, aquatic habitat, travel corridor,

freshwater, estuarine, or marine fisheries or other aquatic life

provided that the applicant meets the requirements of Findings 6

and 16.6

See 38 M.R.S. § 480-D(3).

[¶10] Petitioners timely appealed to the Board.7

3. Petitioners’ Appeal to the Board

[¶11] In their written appeal to the Board, Petitioners, in making several

arguments, expressed broad concerns about the negative effects of the project

on the environment and fishing industries and specific concerns about the

effects of effluent on water quality, eelgrass, and other species. They also

asserted that the Department did not receive sufficient data to support its

issuance of the NRPA and Site Law permits and requested a public hearing

before the Board.

6 In the section of its decision referred to as “Finding 6,” the Department found that the pipeline

installation would not unreasonably harm neighboring wildlife and isheries. Speci ically, based on

the separately conducted reviews of the Maine Department of Inland Fisheries and Wildlife and the

Maine Department of Marine Resources, the Department found that the pipeline construction would

not signi icantly impact nearby wildlife, such as butter ly, lobster, and scallop populations. Similarly,

in the section referred to as “Finding 16,” the Department found that King ish’s proposal would

minimize anticipated alterations to freshwater and coastal wetlands and ensure adequate measures

to monitor wetland impacts and compensate for negative impacts where necessary.

7 Although Sierra Club also appealed the issuance of the combined NRPA and Site Law permit to

the Board, it is not a party to the present appeal.

8

[¶12] On August 4, 2022, the Board held a two-hour meeting at which it

heard presentations from Petitioners, Sierra Club, Kingfish, and the

Department. Petitioners renewed their request for a public hearing.

[¶13] Following the presentations, the Board voted on two items. First,

it voted to deny Petitioners’ request for a public hearing for two reasons—

because the record created before the Department was sufficient for the Board

to make a decision and because Petitioners did not provide a satisfactory offer

of proof as to what additional evidence they would present.8 See 06-096 C.M.R.

ch. 2, § 24(A), (B)(4) (effective June 9, 2018). Next, the Board voted to affirm

the Department’s order. The Board subsequently released written findings of

fact and conclusions of law supporting its decision to affirm the Department’s

issuance of the NRPA and Site Law permits.9

[¶14] In its written findings, the Board addressed several issues,

including the impacts of Kingfish’s project on water quality and neighboring

wildlife. With regard to the impacts on water quality, the Board concluded that

Petitioners, by not raising it here or before the Superior Court, have waived any challenge to the

8

Board’s exercise of discretion in declining to conduct another hearing to receive additional public

input and evidence. See Holland v. Sebunya, 2000 ME 160, ¶ 9 n.6, 759 A.2d 205.

9 In the written decision, the Board found that Petitioners had standing to appeal based on

Petitioners’ assertion that the project could cause them to suffer “a potential particularized injury to

lands [or other property interests] held in ownership” by them. No party has challenged Petitioners’

standing.

9

the Department did not err in relying on the previously granted discharge

permit to determine that Kingfish’s project complied with the relevant

standards under NRPA, see 38 M.R.S. § 480-D(5). The Board reasoned as

follows:

When the Department reviews water quality impacts under the

NRPA in a case in which a [discharge permit] application is being or

has separately been evaluated, the focus of the NRPA review is

impacts from regulated activities such as dredging, filling, disturbing

soil, and placement of structures in, on, over, or adjacent to wetlands

and waterbodies. In this context, the direct discharge of

wastewater would be analyzed in the context of the [discharge

permit] application review, and compliance with the NRPA licensing

criteria is based on how the project complies with Chapter 310,

protecting wetlands and waterbodies, and Chapter 335, protecting

significant wildlife and fisheries habitat.

....

Appellants challenge the findings underlying [the discharge

permit] in this appeal of the Site Law and NRPA permit decision,

but the Board finds no error in the Department’s reliance on

another valid Department order, and will not consider a challenge

to the findings made in that license in the context of this appeal. . . .

The Board finds that [Kingfish] complied with the Department’s

regulations by submitting evidence of a valid [discharge permit]

and on that basis finds that the effluent discharge from the

proposed project will not have an unreasonable adverse effect on

water quality.

(Emphasis added and footnote omitted.)

[¶15] With respect to the effects of the project on wildlife and fisheries,

the Board stated:

10

While [Sierra Club and Petitioners] both primarily raise wildlife

and fisheries concerns associated with the waste discharge, and

issues addressed in that licensing process, some issues they raise

are appropriately subject to review under the NRPA or Site Law

licensing criteria.

The Board observed that “the Department solicit[ed] comments from sister

agencies with subject matter expertise, such as the Department of Marine

Resources (DMR) and the Department of Inland Fisheries and Wildlife

(MDIFW).” The Board determined that the input from Marine Resources and

Inland Fisheries and Wildlife constituted evidence that “supports the

Department’s findings on the effects of the discharge on fisheries.”10

Specifically with regard to the construction of the intake and outfall pipes, the

Board found that modifications agreed to by Kingfish in conjunction with the

special conditions ordered by the Department “minimize[] impacts[,] and those

impacts that will occur will be temporary and unlikely to cause a significant

disturbance to relevant species.” The Board concluded:

On the basis of this evidence, and the DMR comments, the Board

finds that the proposed project will not unreasonably harm any

10The Board stated that “each agency availed themselves of the opportunity to comment on the

project and, while MDIFW expressed concerns regarding peatland habitat, and DMR expressed

concerns regarding potential for gear entanglement, neither agency expressed any concerns

regarding any threatened or endangered species.” The Board further credited the Department of

Maine Resources comments that the pipeline construction and ef luent discharge should have little

or no long-term impact on lobster biology or the lobster industry, that the ef luent discharge does not

appear to threaten the scallop population, and that the proposed project should not result in

signi icant adverse impacts to marine resources.

11

significant wildlife habitat, freshwater wetland plant habitat,

threatened or endangered plant habitat, aquatic or adjacent upland

habitat, travel corridor, freshwater, estuarine or marine fisheries

or other aquatic life, and will not cause an undue adverse effect on

the natural environment.

[¶16] Petitioners timely appealed to the Superior Court. See M.R. Civ. P.

80C; 5 M.R.S. § 11002(3) (2024).

B. Rule 80C Review

[¶17] In their appeal to the Superior Court, Petitioners challenged the

agency’s interpretation of its obligations under NRPA and its failure to conduct

an independent assessment under NRPA of the unreasonableness of the harm

that the project would cause to wildlife habitats.11 Petitioners contended that

the NRPA standards for assessing impacts on wildlife are distinct from those

applicable to the discharge licensing process.

[¶18] The court determined that the Board had undertaken an

independent assessment of the impacts on wildlife associated with the

installation of the pipes but not of specific wildlife impacts associated with

wastewater discharge. It nonetheless affirmed the Board’s decision, stating

11In their Rule 80C petition, Petitioners also contended that the agency’s issuance of a NRPA

permit was erroneous because the agency failed to assess whether King ish adequately complied with

its obligation to analyze practicable, less environmentally damaging alternatives to the proposed

project. See 06-096 C.M.R. ch. 310, §§ 5(A), 9(A) (effective Nov. 11, 2018). The Superior Court did

not address this issue, and we do not consider it either because it was presented neither to the Board

nor to us. See Holland, 2000 ME 160, ¶ 9 n.6, 759 A.2d 205.

12

that the Board “did not contravene the letter or purpose of NRPA by forgoing

an independent analysis of the harms associated with the proposed wastewater

discharge and by relying on the findings of the previously issued discharge

permit.” The court determined that although the Board was not prohibited

from considering the impacts on wildlife resulting from the pipes’ use, it was

not obligated to do so because wastewater discharge is not an activity regulated

by NRPA. The court further concluded that the Board’s decision to forgo an

independent inquiry was reasonable because the impacts of the proposed

discharge had been analyzed during the discharge permit approval process,

and the standards for assessing impacts on wildlife at each of the two

permitting stages were not so divergent as to constitute an error of law.

[¶19] Petitioners timely appealed to us. See M.R. App. P. 2B(c)(1);

14 M.R.S. § 1851 (2024).

II. DISCUSSION

[¶20] As they did in the Superior Court, Petitioners advance two

principal arguments here. First, they contend that the Board was required

under NRPA to assess the impact on wildlife habitat by the use of the intake and

outfall pipes in discharging effluent into Chandler Bay. Second, they argue that

the Board abused its discretion by relying on the Department’s issuance of the

13

discharge permit instead of conducting its own independent analysis to

determine whether or not the intended use of the pipes to discharge treated

wastewater would unreasonably harm wildlife habitat.

A. Standard of Review

[¶21] When the Superior Court acts in its intermediate appellate capacity

under M.R. Civ. P. 80C, we review the agency’s decision directly. Uliano v. Bd. of

Env’t Prot., 2009 ME 89, ¶ 12, 977 A.2d 400. Because the Board acted as the

factfinder and reviewed the legal issues de novo, 06-096 C.M.R. ch. 2, § 24(G)

(effective June 9, 2018), it is the Board’s decision that we review on appeal,

see Passadumkeag Mountain Friends v. Bd. of Env’t Prot., 2014 ME 116, ¶¶ 9-10,

102 A.3d 1181; Concerned Citizens to Save Roxbury v. Bd. of Env’t Prot., 2011 ME

39, ¶ 17, 15 A.3d 1263. We review the Board’s decision for errors of law, factual

findings unsupported by substantial record evidence, or an abuse of discretion.

Forest Ecology Network v. Land Use Regul. Comm’n, 2012 ME 36, ¶ 28, 39 A.3d

74.

[¶22] When interpreting a statutory scheme that is “both administered

by [an] agency and within the agency’s expertise,” we apply “a two-part

inquiry.” NextEra Energy Res., LLC v. Me. Pub. Utils. Comm’n, 2020 ME 34, ¶ 22,

227 A.3d 1117 (quotation marks omitted). We first determine whether the

14

statute’s language is ambiguous. Id. Then if the statute’s language is

unambiguous, we construe the statute in accordance with its plain meaning. Id.

If the statute’s language is ambiguous, “we defer to the interpretation of a

statutory scheme by the agency charged with its implementation as long as the

agency’s construction is reasonable.” Conservation L. Found., Inc. v. Dep’t of

Env’t Prot., 2003 ME 62, ¶ 23, 823 A.2d 551; see also S.D. Warren Co. v. Bd. of

Env’t Prot., 2005 ME 27, ¶ 4, 868 A.2d 210.

B. The Scope of Review under NRPA

[¶23] To curtail or eliminate environmental threats posed by alterations

to “resources of state significance,” 38 M.R.S. § 480-A, NRPA requires a person

to obtain a permit before undertaking a specified “activity” when “the activity

is located in, on or over any protected natural resource or is located adjacent to

. . . [a] coastal wetland,” 38 M.R.S. § 480-C(1)(A). Section 480-C(2) specifies the

“activities” requiring a permit under NRPA:

2. Activities requiring a permit. The following activities require a

permit:

A. Dredging, bulldozing, removing or displacing soil, sand,

vegetation or other materials;

B. Draining or otherwise dewatering;

C. Filling, including adding sand or other material to a sand

dune; or

15

D. Any construction, repair or alteration of any permanent

structure.

Id. § 480-C(2) (emphasis added).

[¶24] If an “activity” requires a permit, NRPA provides that the

Department “shall grant a permit when it finds that the applicant has

demonstrated that the proposed activity meets the standards set forth in

subsections 1 to 11.” 38 M.R.S. § 480-D (emphasis added). Here, the NRPA

standard that Petitioners contend the Board failed to properly consider

requires that “[t]he activity will not unreasonably harm any significant wildlife

habitat, . . . aquatic or adjacent upland habitat, . . . freshwater, estuarine or

marine fisheries or other aquatic life.” 38 M.R.S. § 480-D(3).

[¶25] Kingfish’s proposed installation of intake and outfall pipes

requires a NRPA permit because it will involve regulated “activities” listed in

section 480-C, including “construction” and “dredging” in a coastal wetland.

See 38 M.R.S. § 480-C(2)(A), (D). Petitioners do not challenge the Board’s

evaluation of the impact of these activities. Rather, they assert that NRPA also

requires the Board and the Department to analyze the specific effects of the

effluent discharge into Chandler Bay.

16

[¶26] The statute’s plain language provides otherwise. The list in section

480-C(2) of “activities” triggering Department review in connection with an

application for a permit under NRPA is specific and unambiguous. The statute

reflects a clear intention on the part of the Legislature to subject only certain,

defined “activities” to review under the NRPA standards in section

480-D(1)-(11). See Uliano, 2009 ME 89, ¶ 17, 977 A.2d 400 (holding that the

NRPA standards in section 480-D “only appl[y] to the specific activities listed in

Section 480-C(2)(A)-(D)”); Murphy v. Bd. of Env’t Prot., 615 A.2d 255, 258

(Me. 1992) (noting that NRPA applies to only the particular activities listed in

section 480-C(2)). The discharge of treated wastewater through use of the

operation’s outfall pipes is not a specified activity under section 480-C(2).

[¶27] Petitioners argue that even if the plain language of section 480-C

does not expressly provide that the intended use of the facility (and the intake

and outfall pipes, specifically) is an activity subject to NRPA review, the use

should “factor into the Department’s decision about whether to grant a NRPA

permit to construct an aquaculture facility” because we have “declined to adopt

such a restrictive view of . . . Section 480-C(2).” Petitioners rely on Hannum v.

17

Bd. of Env’t Prot., 2006 ME 51, ¶ 10, 898 A.2d 392, in support of this assertion.12

Their argument is unpersuasive.

[¶28] In Hannum, a trustee of property challenged the Board’s denial of

a permit under NRPA to install a pier and floating dock on the shore of the

property, which was in a coastal wetland. Id. ¶¶ 2-3, 7-8. The trustee argued

that the Board’s decision was in error because it was based not only on whether

the construction of the dock itself would harm wildlife but also on the Board’s

determination that the use of the dock would “increase boat traffic in the cove

which [would] disturb the existing tern and seal colonies.” Id. ¶¶ 12-15

(quotation marks omitted). We affirmed the Board’s decision, concluding that

“the Board has the power to deny a permit application for a dock based on the

dock’s use.” Id. ¶ 14.

[¶29] To be clear, in Hannum we did not say that the agency is obligated

under NRPA to consider the expected effects on wildlife of the intended use of

a structure or facility. Rather, Hannum held that it was within the agency’s

12 Petitioners also argue that an interpretation of section 480-C(2) that con ines the scope of NRPA

review to the speci ic activities listed is inconsistent with past Department practice of “routinely

consider[ing] long-term use when determining whether to issue permits under NRPA.” Because this

argument was not raised before either the Board or the Superior Court, we decline to consider it.

Cf. Off. of the Pub. Advoc. v. Pub. Utils. Comm’n, 2023 ME 77, ¶¶ 27-28, 306 A.3d 633 (concluding that

an argument alleging the Public Utilities Commission’s failure to create an evidentiary record was

waived since it was not raised to the Commission); Indus. Energy Consumer Grp. v. Pub. Utils. Comm’n,

2024 ME 60, ¶¶ 28-31, 320 A.3d 437 (declining to review a federal preemption challenge in the

absence of a “fully developed administrative record”).

18

discretion to take those impacts into consideration in evaluating compliance

with the standard in 38 M.R.S. § 480-D(3). See id. ¶¶ 11, 14 (“[W]e will accord

deference to the Board’s reasonable conclusion that it may examine the impact

of the use of a structure for which a permit is required along with the impact of

the structure itself.” (emphasis added)).

[¶30] The Board, therefore, did not err in focusing its NRPA evaluation

in this case on the “activities” listed in section 480-C(2) relating to the

installation of the intake and outfall pipes. It was not required in this instance

to assess the impact of the use, as opposed to the installation, of the facility’s

intake and outfall pipes because, as the Board stated, the impacts of the direct

discharge of wastewater “[had] separately been evaluated” by the Department

in the context of Kingfish’s application for the discharge permit. Whether the

Board’s reliance on that prior approval was reasonable and a proper exercise

of its discretion is the subject of Petitioners’ second principal argument, which

we address next.

C. The Board’s Reliance on the Discharge Permit

[¶31] Petitioners contend that the Board’s decision to rely on the

Department’s previously issued discharge permit to satisfy NRPA requirements

rather than to conduct its own independent analysis was an abuse of discretion.

19

They argue that the standards for assessing environmental harm in connection

with the discharge permit are significantly different from the applicable NRPA

standard, and further that the allowance of “economic or social benefits,”

38 M.R.S. § 414-A(1)(C), to counterbalance potential water quality degradation

in evaluating a discharge permit application renders reliance on those

standards unreasonable in the context of reviewing an application for a NRPA

permit.

[¶32] We conclude that the Board did not abuse its discretion in relying

on the previously issued discharge permit and that the reliance was reasonable

when the Board was determining whether Kingfish’s proposed project would

not “unreasonably harm any significant wildlife habitat” or “other aquatic life.”

38 M.R.S. § 480-D(3). The discharge licensing process considers impacts on

wildlife in two ways. First, the requirements to obtain a permit focus upon

whether a proposed discharge would interfere with a water body’s

classification,13 which is a metric that accounts for impacts on marine habitat

13 The relevant portions of section 414-A require that “[t]he discharge . . . will not lower the

quality” of a “classi ied” or “unclassi ied” body of water below the relevant classi ication. 38 M.R.S.

§ 414-A(1)(A), (B); see also 38 M.R.S. § 413(10)(B) (2024) (imposing this requirement in connection

with marine aquaculture projects). Section 414-A also requires ef luent limitations, see 38 M.R.S.

§ 414-A(1)(D), and prohibits discharges that lower water quality by any amount at all—even if the

water classi ication remains the same—unless “following opportunity for public participation, the

department inds that the discharge is necessary to achieve important economic or social bene its,”

id. § 414-A(1)(C).

20

and wildlife. For instance, Chandler Bay’s status as a Class SB water body

requires that it be “suitable . . . as habitat for fish and other estuarine and marine

life”; that it not receive “[d]ischarges” that “cause adverse impact to estuarine

and marine life”; and that it comply with numeric limitations, including

standards for dissolved oxygen concentration.14 See 38 M.R.S.

§ 465-B(2)(A)-(C). Second, the Department must, in deciding whether to issue

a discharge permit, find that “the proposed activity would not have a significant

impact on” an “existing in-stream use . . . of the water body by a population of

plant life, wildlife, or aquatic, estuarine or marine life” or on their respective

habitats. See 38 M.R.S. § 464(4)(F)(1-A)(a).

[¶33] In granting the discharge permit to Kingfish, the Department

examined the effects of the intended discharge from the outfall pipes on wildlife

habitat and aquatic life and made findings consistent with these statutory

14 We note that 38 M.R.S. § 465-B(2)(B) was amended to add an introductory sentence that reads,

“Class SB waters must be of suf icient quality to support all estuarine and marine species indigenous

to those waters without detrimental changes in the resident biological community.” P.L. 2021, ch. 551,

§ 15 (effective Aug. 8, 2022) (codi ied at 38 M.R.S. § 465-B(2)(B) (2024)). As considered in this case,

the amendment is of little consequence because (i) it took effect after King ish’s completed discharge

permit application was iled, see supra n.2, and (ii) even if it applied to the circumstances here, the

prefatory standard added to subsection (B) (“waters must be of suf icient quality to support all

estuarine and marine species indigenous to those waters without detrimental changes in the resident

biological community”) would essentially overlap with the standard in subsection (C) (“[d]ischarges

to Class SB waters may not cause adverse impact to estuarine and marine life in that the receiving

waters must be of suf icient quality to support all estuarine and marine species indigenous to the

receiving water without detrimental changes in the resident biological community”), 38 M.R.S.

§ 465-B(2)(C) (emphasis added).

21

requirements. It found that the proposed discharge would not lower the

classification status of any water body and that “[e]xisting in-stream water use

will be maintained and protected.” And, as noted above, the discharge permit

includes ongoing sampling and monitoring requirements intended to protect

aquatic life and habitat as well as authority for the Department to modify or

require different effluent limits “where there is a reasonable potential that the

effluent may cause water quality criteria to be exceeded.” See supra ¶ 6.

[¶34] Finally, contrary to Petitioners’ argument, the Board’s reliance on

the discharge permit in the context of the NRPA review in this instance was not

unreasonable because the Department considered the project’s economic and

social benefits under the State’s antidegradation policy. Even when considering

economic and social benefits, the Department still cannot issue the permit if it

determines that the discharge will “cause or contribute to the failure of the

water body to meet the standards of classification.” 38 M.R.S. § 464(4)(F)(3).

Nor may the Department issue a permit where the discharge “would cause

unreasonable degradation of marine waters.” 38 M.R.S. § 464(4)(A)(11). And

particularly for Chandler Bay, a Class SB water body, any discharge “may not

cause adverse impact to estuarine and marine life.” 38 M.R.S. § 465-B(2)(C).

22

[¶35] Accordingly, the Board did not err in interpreting the scope of

review under NRPA or abuse its discretion in relying upon the Department’s

separate evaluation of impacts of the intended effluent discharge.

The entry is:

Judgment affirmed.

Elizabeth A. Boepple, Esq. (orally), Sean R. Turley, Esq., and Ellen P. Masalsky,

Esq., Murray, Plumb & Murray, Portland, for appellant Eastern Maine

Conservation Initiative and Roque Island Gardner Homestead Corporation

Aaron M. Frey, Attorney General, Robert L. Martin, Asst. Atty. Gen. (orally), and

Jack Dafoe, Asst. Atty. Gen., Of ice of the Attorney General, Augusta, for appellee

Board of Environmental Protection

Patrick I. Marass, Esq. (orally), Katherine A. Joyce, Esq., and Rachael McEntee,

Esq., Bernstein Shur, Portland, for appellee King ish Maine, Inc.

Kennebec County Superior Court docket number AP-2022-33

FOR CLERK REFERENCE ONLY

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.