Opinion

Levesque v. City of Bath

Court
Superior Court of Maine
Filed
Apr 22, 2020
Status
Unpublished
On the bench
Daniel I. Billings
Cited by
0 cases
Authority
More cited than 34.2%

"There is no evidence of any construction, street cleaning or repair operations taking place in the parking area at the time [plaintiff fell over a raised curb in the parking area]"

How later courts described this case

  • "There is no evidence of any construction, street cleaning or repair operations taking place in the parking area at the time [plaintiff fell over a raised curb in the parking area]"
  • there is no remedy under the statute if the ditch, drain or culvert is not large enough to care for the amount of stormwater
  • describing this statute as providing for "the liability of cities and towns for damages sustained by travelers by reason of defects in highways"

Written by the judges who cited it.

The opinion

STATE OF MAINE SUPERIOR COURT

SAGADAHOC, ss. CNILACTION

DOCKET NO. CV-19-1

R.J. BRENT LEVESQUE, )

)

Plaintiff, )

)

V. ) ORDER ON DEFENDANT'S MOTION

) FOR SUMMARY JUDGMENT

CITY OF BATH, )

)

Defendant )

INTRODUCTION

The matter before the court is whether Plaintiff R.J. Brent Levesque's ("Levesque")

claims against the City of Bath ("the City") under the Highway Defect Statute survive the

City's Summary Judgment Motion. Levesque raises three main arguments: (1) that this

motion is untimely and should be denied as a sanction under M.R. Civ. P. 16; (2) that the

City is barred from taking this position by the doctrine of judicial estoppel; and (3) that

the statute should be interpreted more broadly to allow suit by any person injured by a

condition on a highway that would potentially be dangerous to travelers. For the reasons

discussed below, the motion is GRANTED.

BACKGROUND

The facts in this case are not materially in dispute. Levesque has lived at his house

on 409 High Street in Bath, Maine for over twenty years. (Supp.'g S.M.F. <JI 5.) His house

sits 8-10 feet from the sidewalk which spans between 3 and 3.5 feet alongside High Street.

(Supp.'g S.M.F. <JI 6.) The alleged harm in this case concerns two things. First, Levesque

contends that the City has been negligent in its maintenance of the road by inadequately

plowing or clearing drains, causing flood damage to his property. ( Supp.'g S.M.F. <JI 10.)

He also alleges that a 2014 re-design project on High Street was conducted in a negligent

manner, which also caused flooding.

1

Levesque filed a complaint dated January 10, 2019, in which he made these

allegations. Levesque alleged claims under the Maine Tort Claims Act ("MTCA", 14

M.R.S. §§ 8101-8118 (2020), the Sewer Maintenance Statute ("SMS"), 23 M.R.S. § 3251

(2020), and the Highway Defect Statute ("HDS"), 23 M.R.S. § 3655 (2020). After discovery

closed, the City moved for partial summary judgment on October 11, 2019, seeking a

declaration that Levesque's claims were not cognizable under the MTCA or the SMS. The

court granted the motion on April 22, 2020. The City now moves for summary judgment

on the remaining claim, arguing that Levesque's claims also fall outside the scope of the

HDS.

STANDARD OF REVIEW

Summary judgment is granted to a moving party where "there is no genuine issue

as to any material fact" and the moving party "is entitled to judgment as a matter of law."

M.R. Civ. P. 56(c). "A material fact is one that can affect the outcome of the case, and

there is a genuine issue when there is sufficient evidence for a fact-finder to choose

between competing versions of the fact." Lougee Conservancy v. City Mortgage, Inc., 2012

ME 103, <JI 11, 48 A.3d 774 (quotation omitted). "Facts contained in a supporting or

opposing statement of material facts, if supported by record citations as required by this

rule, shall be deemed admitted unless properly controverted." M.R. Civ. P. 56(h)(4). In

order to controvert an opposing party's factual statement, a party must "support each

denial or qualification by a record citation." M.R. Civ. P. 56(h)(2). Assertion of material

facts must be supported by record references to evidence that is of a quality that would

be admissible at trial." HSBC Mortg. Servs. v. Murphy, 2011 ME 59 919, 19 A.3d 815.

DISCUSSION

The City argues that Levesque's claims fall outside the HDS, which it argues only

creates a cause of action for travelers on public highways. Levesque responds by first

2

arguing that the City's motion is untimely. On the substance of the motion, he argues

that the City construes the HDS too narrowly and is estopped from raising these issues

by judicial estoppel.

1. Untimeliness

Levesque's untimeliness argument relies on three facts: that the instant motion

was submitted after the motion deadline in the court's Scheduling Order, that all

arguments raised in the motion could have been raised in its first motion for summary

judgment, and that the motion will have the effect of further delaying trial in the case.

Levesque's contention is that the motion should be denied as a sanction for its untimely

submission under M.R. Civ. P. 16(d) in light of these facts.

M.R. Civ. P. 56(b) provides that a defending party in a case may move for

summary judgment "at any time, but within such time as to not delay the trial." As the

City correctly notes, the trial court has discretion whether to allow a late filed summary

judgment motion when doing so would not delay the trial. Levis v. Konitzky, 2016 ME

167, <JI 17, 151 A.3d 20. Where there is a scheduling order that imposes a deadline, better

practice is still to file a motion asking the court for leave to file a late motion if new

grounds develop late in the case. Id. at <JI 16. However, the court still has considerable

discretion in determining whether to grant this late motion. Id.

There are no new grounds raised in the City's motion, only a new legal argument.

Levesque is correct when he points out that these arguments could easily have been

raised in the previous summary judgment motion. It is also worth noting that the City

did not move for leave to file this motion. Best practices aside, the salient question is

whether considering the City's new motion for summary judgment would delay trial.

The motion was filed August 3, 2020, four months before the earliest potential trial date

in November 2019 due to delays in civil trials brought about by COVID-19. To date, there

3

is still a great deal of uncertainty surrounding the scheduling of trial dates. No jury

session has been scheduled on Sagadahoc County matters and only criminal jury trials

are being scheduled anywhere in the state at this time. In light of this, and absent any

indication of bad faith, the court will hear the motion.

2. Judicial Estoppel

Levesque argues that the City is barred from moving for summary judgment on

his HDS claims by the doctrine of judicial estoppel. Specifically, he argues that the City

took the position that his claims were cognizable under the HDS and is therefore

estopped from arguing the reverse here.

The doctrine of judicial estoppel "generally prevents a party from prevailing in

one phase of a case on an argument and then relying on a contradictory argument to

prevail in another phase." Me. Educ. Ass'n v. Me. Cmty. College Sys. Bd. Of Trs., 2007 ME

70, <JI 16, 923 A.2d 914 (quoting New Hampshire v. Maine, 532 U.S. 742, 749 (2001)). "The

contours of the judicial estoppel doctrine are not sharply defined, and there is no

mechanical test for determining its applicability." Id. <JI 17. However, the Law Court has

adopted three factors from New Hampshire v. Maine to guide the analysis:

(1) whether the party's later position is clearly inconsistent with its earlier

position;

(2) whether the party succeeded in persuading a court to accept that party's

earlier position; and

(3) whether an unfair advantage or detriment would be created.

Me. Educ. Ass'n, 20071\,IB 70, <JI 18, 923 A.2d 914. This case does not fit any of the factors .

First, contrary to Levesque's assertion, it does not appear that the City was

taking the affirmative position that plaintiff's claims were cognizable under the HDS.

To support his characterization of the City's prior position, Levesque quotes their reply

4

brief where they state that his claims are "only cognizable pursuant to the HDS."

(Def.'s Reply to Pl.'s Opp. First Mot. Summ. J. at 1, 9.) This ignores the many

conditional statements in the City's filings on that motion which say that Levesque's

claims "may" fall within the HDS or that they "potentially" do. (Def.'s Mot. Partial

Summ. J. at 1, 11.) It is fairly obvious that the City's position in its prior motion was

that it did not want to litigate the HDS issue at that time, not that it was conceding its

applicability to Levesque's claims. At the very least, its prior position is not clearly

inconsistent with its current one.

Second, even if the City were in fact arguing that the HDS applies to Levesque's

claims, the court clearly did not adopt that position. At most, the court's order states

that "the City does not dispute that plaintiff is potentially entitled to relief" under the

statute. The court did not accept the position that the HDS does apply to Levesque's

claims, only that it might. Thus, the second factor weighs against applying judicial

estoppel.

Finally, no unfair advantage or detriment would be created by allowing the City

to argue its current position. These issues were not litigated on the prior summary

judgment motion. Levesque seems to argue that the City prejudiced him by convincing

the court to close down his other avenues for relief because it believed that he would be

able to recover under this statute. This mischaracterizes the court's prior holding. The

court granted partial summary judgment on two other statutes and left the issue of the

HDS for another day. Levesque did not suffer a detriment at all, let alone an unfair one.

In light of the above, the City's arguments are not barred by judicial estoppel.

3. St atutory Interpretation

The substance of the dispute at issue is whether the HDS applies to all people

who sustain injuries as a result of a highway defect, or whether it only applies to

5

"travelers." The City points to cases which endorse the latter interpretation, Levesque

argues that these cases are too antiquated to be relied on and that the statute has been

updated since then to enable actions by any person, so long as they were injured by a

defect that would be dangerous to travelers.

The HDS provides that "highways, town ways and streets legally established

shall be opened and kept in repair so as to be safe and convenient for travelers with

motor vehicles." 23 M.R.S. § 3651 (2020). It further provides that "a person who

receives any bodily injury or suffers damage in the person's property through any

defect or want of repair or sufficient railing in any highway, town way, causeway or

bridge may recover for the same in a civil action." 23 M.R.S. § 3655 (2020).

The Law Court has held that these provisions "were clearly intended to be in

harmony with each other." Cunningham v. Inhabitants of Frankfort, 104 Me. 208,211, 70

A. 441, 442 (1908). The court went on to clarify that these provisions "have always been

construed to mean that a plaintiff is entitled to recover damage only when he suffers it

through any defect or want of repair that will prevent the way from being safe and

convenient for travel." Id.

The City cites other cases, all of which hold that the duty of towns to keep their

roads free of defects is only owed to travelers. In Leslie v. City of Lewiston, for instance,

the court said the following:

The statute requires cities and towns to keep their "ways safe and convenient" for

travellers only; and when this is done they have no further dulies or

responsibilities in relation to them. Hence, when the statute further provid s that

"any person" who suffers damage through any defect in a way, shall have a

remedy, it necessarily refers to that class of p rsons who were, not only in the

lawful use of it, but for whos use and whose safety and convenience it was

established.

62 Me. 468, 470 (1873). Levesque argues that these cases should not apply to the case at

bar, because they are out of date with updates to the statute. However, he is unable to

6

point to a single case that supports his more restrictive reading. In fact, more recent

cases seem to reflect an understanding that this is settled law. See, e.g., Curtis v.

Ellsworth, 292 A.2d 197, 199 (Me. 1972) (describing this statute as providing for "the

liability of cities and towns for damages sustained by travelers by reason of defects in

highways").

While Levesque is correct that the statute at issue has been subject to a

"multitude of amendments/' Thorbjhonson v. Rockland Rockport Lime Co., Inc., 275 A.2d

588, 592-97 (Me. 1971), he fails to point to any amendment that would imply that the

statute has changed in such a way as to negate the precedential value of these cases. He

points to the most recent amendment, passed in 2017, which changed the description of

the party who could sue from "whoever" to "a person." P.L. 2017 Ch. 402 § C-74.

However, a simple glance at that amendment makes it quite clear that the Legislature

was amending the statute to remove the male pronouns that followed and render the

statute gender neutral. More importantly, the two statutory provisions that are

"intended to be in harmony with each other" still refer to travelers when considered as

a cohesive whole.

The case law and legislative history is quite clear on this issue. Maine courts do

not find liability under the HDS for persons who were not using the road as a traveler.

Here, Levesque's harm does not arise from a use of the road at alt as a traveler or

otherwise. His claims arise from his ownership of property abutting the road. This is

not within the scope of the HDS, so summary judgment will be granted for the City.

CONCLUSION

For the foregoing reasons, the City of Bath's Motion for Summary Judgment is

GRANTED. Judgment is entered for the Defendant, plus costs.

7

The clerk is directed to incorporate this Order by reference in the docket in

accordance with M.R. Civ. P. 79(a).

DATED: November 3, 2020

Q;:_ _:_,(/2,-z___---~

Daniel I. Billings /

Justice, Maine Superior Court

8

RJ BRENT LEVESQUE - PLAINTIFF SUPERIOR COURT

409 HIGH STREET SAGADAHOC, ss.

BATH ME 04530 Docket No BATSC-CV-2019-00001

Attorney for: RJ BRENT LEVESQUE

FRED JAY MEYER - RETAINED

TROUBH HEISLER LLC DOCKET RECORD

200 PROFESSIONAL DRIVE, SUITE

SCARBOROUGH ME 04074

vs

CITY OF BATH - DEFENDANT

55 FRONT STREET

BATH ME 04530

Attorney for: CITY OF BATH

JONATHAN BROGAN - RETAINED

NORMAN HANSON & DETROY LLC

PO BOX 4600

TWO CANAL PLAZA

PORTLAND ME 04112-4600

Filing Document: COMPLAINT Minor Case Type: OTHER NON-PERSONAL INJURY TORT

Filing Date: 01/11/2019

Docket Events:

01/14/2019 FILING DOCUMENT - COMPLAINT FILED ON 01/11/2019

01/14/2019 Party(s): RJ BRENT LEVESQUE

ATTORNEY - RETAINED ENTERED ON 01/11/2019

Plaintiff's Attorney: FRED JAY MEYER

01/14/2019 ASSIGNMENT - SINGLE JUDGE/JUSTICE ASSIGNED TO JUSTICE ON 01/11/2019

DANIEL I BILLINGS , JUSTICE

01/24/2019 Party(s): CITY OF BATH

SUMMONS/SERVICE - ACK OF RECEIPT OF SUMM/COMP SERVED ON 01/14/2019

Defendant's Attorney: ROGER THERRIAULT

FOR THE CITY OF BATH

01/24/2019 Party(s): CITY OF BATH

SUMMONS/SERVICE - ACK OF RECEIPT OF SUMM/COMP FILED ON 01/24/2019

Plaintiff's Attorney: FRED JAY MEYER

01/29/2019 Party(s): CITY OF BATH

RESPONSIVE PLEADING - ANSWER & AFFIRMATIVE DEFENSE FILED ON 01/28/2019

Defendant's Attorney: JONATHAN BROGAN

01/29/2019 ORDER - SCHEDULING ORDER ENTERED ON 01/29/2019

DANIEL I BILLINGS , JUSTICE

ORDERED INCORPORATED BY REFERENCE AT THE SPECIFIC DIRECTION OF THE COURT. COPIES TO

PARTIES/COUNSEL

01/29/2019 DISCOVERY FILING - DISCOVERY DEADLINE ENTERED ON 10/29/2019

01/29/2019 Party(s): CITY OF BATH

Page 1 of 5 Printed on: 11/04/2020

STATE OF MAINE SUPERIOR COURT

SAGADAHOC, SS. CIVIL ACTION

DOCKET NO. CV-2019-001

)

R.J. BRENT LEVESQUE, )

)

Plaintiff, ) ORDER ON DEFENDANT'S

) MOTION FOR PARTIAL SUMMARY

V. ) JUDGMENT

)

CITY OF BATH, )

)

Defendant. )

This matter is before the Court on Defendant City of Bath's Motion for Partial

Summary Judgment. For the following reasons, Defendant's Motion is GRANTED.

SUMMARY JUDGMENT FACTUAL RECORD

On January 11, 2019, Plaintiff commenced this action alleging that the City of Bath

(the "City") "negligently designed, constructed, repaired, maintained and cleaned High

Street and the Drainage Facilities" in the vicinity of his residence, which caused personal

injury and property damage. 1 (PL's Compl. <[<JI 7-9,10,13.) The following facts are

undisputed.

Plaintiff has lived at 409 High Street in Bath, Maine for approximately twenty

years. (Supp.'g S.M.F. <JI 3.) Plaintiff's residence sits at the corner of High Street and

Corliss Street, approximately 8-10 feet from a sidewalk that runs alongside High Street.

(Supp.'g S.M.F. <[<j[ 4-5.) In 2014, the City redesigned and repaved High Street. (Supp.'g

S.M.F. <n 7.) Plaintiff alleges th.a t this is when he first began experiencing flooding,

1 Although not pleaded as such, Plaintiff appears to be seeking recovery under the Maine Tort

Claims Act, 14 M.R.S. §§ 8104-A(4) (2019), the so-called "Sewer Maintenance Statute," 23 M.R.S.

§ 3251 (2019), and the so-called "Highway Defect Statu te," 23 M.R.S. § 3655 (2019). (See Pl.'s

Opp'n to Def.'s Mot. Summ. J. 4, 5, 7.)

1

stating, when the contractor re-designed High Street in 2014 "it didn't do a very good

job." (Supp.'g S.M.F. <J[<J[ 8, 14.) Plaintiff references various flooding events between

December 2014 and March 2018. (Supp.'g S.M.F. 9I 10.) Specifically, during periods of

heavy rain or snow, water would back up in the City's drainage system, pool in the street,

and then flow over the curb and into his lawn, landscaping, driveway, garage, and

around his foundation. (Supp.'g S.M.F. <J[<J[ 9, 11.) The stormwater issues were

exacerbated by discharge from the bank on the west (southbound) side of High Street,

which caused water to flow over the street and onto his property. (Supp.'g S.M.F. 9I 12.)

Plaintiff retained Thomas W. Saucier ("Mr. Saucier"), a licensed engineer, to

corroborate and provide expert testimony regarding the "defects in the design,

construction, repair and maintenance of High Street and the drainage systems in the

vicinity of Plaintiff's residence." (Supp.'g S.M.F. 9I 15.) Mr. Saucier identified the

following material defects. First, the gutter line on east side of High Street - where the

curb meets the road -lacks sufficient grade to permit proper drainage. (Supp.'g S.M.F. 'lI

16.) According to Mr. Saucier, proper engineering practice requires a one percent

longitudinal slope, at minimum, a half percent slope. (Supp.'g S.M.F. <JI 17.) The slope

was at times less than a tenth of an inch. (Supp.'g S.M.F. <J[ 18.) Second, the distance from

the top of the curb to where it meets the pavement, the so called "reveal" was between

4.2 and 5.1 inches. This was inconsistent with the five-inch minimum required by the

design plan. (Supp.'g S.M.F. <J[ 20.) Had the reveal been consistent with the plan, there

may not have been as much overflow. (Supp.'g S.M.F. CJ[ 20.)

Third, the catch basin in front of Plaintiff's residence (on the east side of High

Street) should have been adjacent to the curb, and the grade around the catch basin is flat

- both flaws that could cause water to pond in front of Plaintiff's residence. (Supp.'g

S.M.F. <JI<JI 21-22.) Fourth, the road crown on the west side of High Street (opposite

2

Plaintiff's residence) is below engineering standards and not constructed in accordance

with the 2014 design plans. (Supp.'g S.M.F. (I(CI[ 23-25.) If drainage on the west side of

High Street is impeded by snow, ice or leaves, runoff can cross the street and exacerbate

ponding in front of Plaintiff's residence. (Supp.'g S.M.F. <[ 23.) Mr. Saucier stated that if

the road had been properly crowned, it would have acted as a barrier, and prevented

water from spilling across the street and onto Plaintiff's Property. (Supp.'g S.M.F. 'l['l[ 27­

28.) Fifth, when High Street was rehabilitated in 2014, grinding and grading were not

consistent with the design plans, which has been a "significant cause of the problems

with runoff flow and ponding ...." (Supp.'g S.M.F. 'l['l[ 29-30.) Sixth, Mr. Saucier stated

that the drainage outlet intersecting Corliss and High Street, and the one in front of

Plaintiff's residence, is inadequate to handle the amount of stormwater. (Supp.'g S.M.F.

<[<JI 31-35.) Lastly, Plaintiff also alleges that the City dug out a drainage ditch on the west

side of High Street to help alleviate drainage issues, and at some point, the City removed

a "drainpipe diffuser" at the end of a drainpipe, which caused water to discharge straight

at Plaintiff's property. (Supp.'g S.M.F. <JI'lI 36-37.)

The City moved for a partial summary judgment declaring that Plaintiff's claims

fall outside the scope of the Maine Torts Claims Act ("MTCA"), and so-called "Sewer

Maintenance Statute," and that Plaintiff's only cognizable claim is under the so-called

"Highway Defect Statute," 23 M.R.S. § 3655 (2019), which limits recovery to $6,000.

STANDARD OF REVIEW

A party is entitled to summary judgment when review of the parties' statements

of material facts and the record to which the statements refer, demonstrates that there is

no genuine issue as to any material fact in dispute, and that the moving party is entitled

to judgment as a matter of law. Dyer v. Dep't of Transp., 2008 ME 106, <[ 14, 951 A.2d 821;

M.R. Civ. P. 56(c). A contested fact is "material" if it could potentially affect the outcome

3

of the case. Id. A "genuine issue" of material fact exists if the claimed fact would require

a factfinder to "choose between competing versions of the truth." Id. (quoting

Farrington's Owners' Ass'n v. Conway Lake Resorts, Inc., 2005 ME 93, <JI 9, 878 A.2d 504).

Each parties' statements must include a reference to the record where "facts as would be

admissible in evidence" may be found. M.R. Civ. P. 56(e).

When deciding a motion for summary judgment, the court reviews the evidence

in the light most favorable to the non-moving party. Id. The evidence offered in support

of a genuine issue of material fact "need not be persuasive at that stage, but the evidence

must be sufficient to allow a fact-finder to make a factual determination without

speculating." Estate of Smith v. Cumberland Cty., 2013 ME 13, <JI 19, 60 A.3d 759.

DISCUSSION

The facts are generally uncontested. 2 The City does not dispute that Plaintiff is

potentially entitled to relief under the Highway Safety Statute. (Def.'s Reply Mot. Summ.

J. 1, n. 1.) After a thorough review of the briefs and applicable law, the Court concludes

that Plaintiff has not produced sufficient evidence demonstrating that he would be

entitled to relief under the Maine Tort Claims Act, ("MTCA"), 14 M.R.S. § 8104-A(4),

and/ or the Sewer Maintenance Statute, 23 M.R.S. § 3251 (2019).

I. Maine Tort Claims Act

The City first seeks a summary judgment on Plaintiff's claim under the MTCA. A

governmental entity is generally immune from tort claims seeking damages. 3 See Paschal

2 A genuine issue of fact exists as to the timing of the City's alleged negligent acts and omissions,

specifically with regards to the drainpipe diffuser. (Supp.'g S.M.F. 9[ 38.) Furthermore, Plaintill

contends that a City conshucted storm drain is located on his property, a prerequisite to maintain

a claim under the Sewer Maintenance Statute. (Add. S.M.F. CJ[ 40.)

3 "Except as otherwise expressly provided by statute, all governmental entities shall be immune

from suit on any and all tort claims seeking recovery of damages. When immunity is removed by

4

v. City of Bangor, 2000 ME 50, <JI 10, 747 A.2d 1194. The MTCA does, however, permit

recovery under the following exception:

A governmental entity is liable for its negligent acts or omissions arising out of

and occurring during the performance of construction, street cleaning or repair

operations on any highway, town way, sidewalk .... A governmental entity is not

liable for any defect, lack of repair or lack of sufficient railing in any highway,

town way, sidewalk, parking area, causeway, bridge, airport runway or taxiway

or in any appurtenance thereto.

14 M.R.S. § 8104-A(4). (Def.'s Mot. Summ. J. 7.) First, the only "construction" or "repair

operations" that allegedly took place within the two-year statute of limitations4 occurred

when the City dug out the drainage ditch on the west side of High Street and removed a

"drainpipe diffuser." (Supp.'g S.M.F. <fI<fI 36-37.) For purposes of the summary judgment

record, the Court accepts Plaintiff's contention that the City was involved. 5

With regards to "street cleaning," Plaintiff testified at deposition that during

storm events he would "call the city, and ... a guy would show up and come and clean

out the drains [across from my house ... approximately four hours after the event was

over." (Pl.'s Opp'n to Def's Mot. Summ. J. 8; Levesque Dep. 19.) This delay allegedly

damaged Plaintiff's property, and at times, Plaintiff had to clean the drains himself.

However, Section 8104-A(4) does not create a duty on the part of the City to clean

or repair its streets. Paschal v. City of Bangor, 2000 ME 50, <JI 12, 747 A.2d 1194. Rather, it

places a duty on the City to conduct its street cleaning and repair operations with due

this chapter, any claim for damages shall be brought in accordance with the terms of this chapter."

14 M.R.S. § 8103(1).

4 The MTCA has a two-year state of limitations, not one year as the City suggests. 14 M.R.S. §

8110 (any claim against a governmental entity under the MTCA must be commenced within 2

years after the cause of action accrues).

5 The City's attempt to clarify its involvement after introducing Paragraph 38 in its Statement of

Material Facts is improper. A moving party cannot introduce a new statement of material fact in

its reply brief accompanied by an affidavit attached to that reply. (See Def.'s Reply to Pl.'s Opp'n

4; Ex. B.)

5

care. Id. Put another way, to generate liability pursuant to Section 8104-A(4), "both the

governmental entity's negligence and the resulting injury to the claimant must occur

during the course of the construction, street cleaning, or repairs at issue." Rice v. City of

Biddeford, 2004 ME 128, <JI 11, 861 A.2d 668; Kitchen v. City of Calais, 666 A.2d 77 (Me. 1995)

("There is no evidence of any construction, street cleaning or repair operations taking

place in the parking area at the time [plaintiff fell over a raised curb in the parking area]").

Accordingly, "if an injury occurs only after repairs have been completed, immunity is not

waived by section 8104-A(4)." Rice, 2004 ME 128, <JI 11, 861 A.2d 668.

Viewing the evidence in the light most favorable to Plaintiff, Plaintiff failed to

produce sufficient evidence to support a finding that any personal injury or property

damage occurred during, and as a result, of the City's negligent construction, street

cleaning, or repair operations. Thus, Plaintiff's claims fall outside the scope of the MfCA.

II. Sewer Maintenance Statute

Although not pleaded as such, Plaintiff also appears to be seeking recovery under

the Sewer Maintenance Statute. 6 Pursuant to Section 3251, a town may construct ditches,

drains and culverts to carry water away from a road, and "over or through" another

person's land, when they find it necessary for the public convenience or to properly care

for the road. 23 M.R.S. § 3251 (2019). If the town fails to maintain and keep in good repair

6 "The municipal officers of a town may at the expense of the town constrnct ditches, drains and

culverts to carry water away from any highway or road therein, and over or through any lands

of persons or corporations, when they deem it necessary for public convenience or for the proper

cru:e of such highway or road, provided no such ditch, drain or culvert shall pass under or within

20 feet of any dwelling house without the consent of the owner thereof. Such ditches, drains and

culverts may be constructed under such highways or roads. Such ditches, drains or culverts shall

be under the control of said municipal officers and interference therewith may be punishable by

a fine of not more than $500 or by imprisonment for not more than 3 months, or by both. If such

town does no't maintain and keep in repair such ditches, drains and culverts, the owner or occupant of the

lands through or over which they pass may have his action aga'inst the town for damages thereby sustained."

23 M.R.S. § 3251 (2019) (emphasis added).

6

these ditches, drains or culverts, "the owner or occupant of the lands through or over

which they pass may have his action against the town for damages thereby sustained."

Id.

As threshold matter, Plaintiff failed to set forth facts evidencing that any ditch,

drain, or culvert pass "over or through" his property. (Add. S.M.F. 'l{ 40.) Paragraph 40

of Plaintiff's additional statement of material facts suggests that "a section of storm drain

located north of the northwest corner of Corliss Street and High street and east of the side

of Hight street, ... crosses the southwest corner of Plaintiff's Property." (Add. S.M.F. 'l{

40.) However, the evidence offered in support of this fact- an aerial image of Plaintiff's

property from the 2014 High Street Rehabilitation Plan - depicts a storm drain that

appears to be located entirely outside of Plaintiff's property boundary. Because the

record does not contain sufficient evidence demonstrating any ditch, drain or culvert is

located on his Property, Plaintiff cannot recover under the Sewer Maintenance Statute.

Even if the Court concludes that a genuine issue of material fact exists with regards

to the location of the drainage system, Plaintiff has not demonstrated that the City failed

to "maintain or keep in repair" the drainage system within the meaning of the statute.

The record demonstrates: (1) the City failed to comply with the 2014 High Street

Rehabilitation design plans; (2) the City failed to timely remove snow, leaves and debris;

and (3) the City removed the drainpipe diifuser. (Supp.'g S.M.F. 'l{'l{ 13, 27, 30-32, 36-37;

Pl.'s Opp'n to Def.'s Mot. Summ. J. 6.) The Court agrees with the City that liability cannot

be based on faulty design in the original plan of construction. Austin v. Inhabitants of St.

Albans, 144 Me. 111, 113-114, 65 A.2d 32 (Me. 1949) (there is no remedy under the statute

if the ditch, drain or culvert is not large enough to care for the amount of stormwater); see

Sait v. Town ofReadfield, 2004 Me. Super. LEXIS 52, at *19 (Feb. 6, 2004). The Court further

7

concludes that Plaintiff's remaining allegations fail to set forth sufficient evidence

demonstrating the City may be liable under the Sewer Maintenance Statute.

CONCLUSION

For the reasons stated above, the Defendant's Motion for Partial Summary

Judgment is GRANTED. Any recovery by the Plaintiff will be limited to $6,0000 under

the provisions of the Highway Defect Statute.

The Clerk is directed to incorporation this Order by reference into the docket for

this case, pursuant to Rule 79(a), Maine Rules of Civil Procedure

DATE: April 22, 2020

~_#_____

Daniel I. Billings, Justice

Maine Superior Court

8

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.