Opinion

Friends of Mitchell Field v. Town of Harpswell

Court
Superior Court of Maine
Filed
Sep 5, 2018
Status
Unpublished
On the bench
Andrew M. Horton
Cited by
0 cases
Authority
More cited than 34.2%

The opinion

STATE OF MAINE SUPERIOR COURT

Cumberland, ss . Civil Action

FRIENDS OF MITCHELL FIELD )

)

Plaintiff )

)

V. ) Docket No. PORSC-CV-18-0334

)

TOWN OF HARPSWELL ) STl'-TE OF MAl~~E ~

) Cumberland, ss. Clerk's Of1,ce

Defendant )

c;_;:-':> G5 2Di8

) ~#-~ ' " " l

\ '· \ '? E' I""' '

DECISION AND JUDGMENT

RECE\VED

This case is about a municipal water tower that has become a lightning rod of

contention in the Town of Harpswell after five years of discussion and study about its

future. One viewpoint is that the tower represents the best prospect for improved

cellular telephone reception in many parts of the Town, and that it can repaired,

repurposed and maintained at a reasonable cost at little or no expense to the Town

The other viewpoint is that it is an unsafe structure, that it is beyond repair at a

reasonable cost, that it is not optimal for cellular telephone purposes, and it that should

be demolished.

At a Town meeting in March 2018, the proponents of demolition prevailed in a

vote and the tower is scheduled to come down in a couple of weeks. This case reflects

an effort by proponents of saving the tower to stop the demolition and get another

Town vote on the future of the tower.

1

The case came before the court for an evidentiary hearing August 28, 2018.

Plaintiff Friends of Mitchell Field and Defendant Town of Harpswell both

participated with counsel and presented evidence through witness testimony and

exhibits. The hearing was electronically recorded.

Prior to the hearing, the parties filed a written stipulation of facts, which is

reproduced below in the paragraphs numbered 1 through 95. In addition, the parties

stipulated to the admission of 73 exhibits. 1 Additional exhibits were admitted during

the hearing.

The August 28, 2018 hearing was initially scheduled for purposes of Plaintiff

Friends of Mitchell Field's Motion for Preliminary Injunction, but, as set forth below,

the parties stipulated to consolidate hearing on the Motion with a hearing on the

merits "provided that both parties are able to get substantially all of their evidence in

at the hearing." See Stipulations ef Fact ~ l, infra. At oral argument, both parties

confirmed that they were able to complete their presentation of evidence and rested at

the close of the hearing. Accordingly, this Decision represents a final, appealable

judgment in this case.

Oral argument was held August 31, 2018, at which point the court took the case

under advisement. Based on the entire record, the court makes the following findings

of fact and adopts the analysis and conclusions oflaw set forth below.

1. Exhibits 8, 9, 10, 11 and Ht were incorrectly labeled and located in the court's exhibit book.

The exhibit numbers on those exhibits have been corrected to be consistent with the above index,

and the exhibits have been placed behind the correct number tabs in the court's book.

2

Stipulated Facts

The parties stipulated to the facts set forth in the following paragraphs I

through 95, without stipulating to any particular fact's relevance or significance:

I. The parties agree to consolidate the hearing on Plaintiffs Motion for

Preliminary Injunction with a hearing on the merits of the Verified Complaint

pursuant to M.R. Civ. P. 65(b)(92), provided that both parties are able to get

substantially all of their evidence in at the hearing.

2. Mitchell Field is a 118.5-acre former U.S. Navy site m the Town of

Harpswell ("Town") that has been owned by the Town since 2001.

3. Mitchell Field is the site of some old buildings and other site improvements

built by the U.S. Navy when it owned the site, including a water tower constructed by

the U .S. Navy around 1950 that is no longer in use.

4. The Mitchell Field water tower is located on one of the highest points of

land in South Harpswell.

5. Cell phone coverage is limited or not available in the South Harpswell, Orr's

Island and Bailey Island sections of Town and is spotty in other parts of Town,

including areas near the Mitchell Field Water Tower.

6. The Town of Harpswell follows a town meeting form of government. It is

governed by a three-member Board of Selectmen ("Board"). I ts legislative body is the

town meeting.

3

7. Richard Daniel has been the Chair of the Board continuously since March

27, 2014. Kevin Johnson has been a Board member since March 15, 2014. David

Chipman was elected to the Board on March 11, 2017.

8. FMF was incorporated as a non-profit entity on February 23, 2018. FMF

has no members and 3 to 9 directors. Exhibit 45 (Articles oflncorporation).

9. At the March 9, 2013 Annual Town Meeting, the voters defeated Article 38.

Exhibit 2 (March 2013 Annual Town Meeting Warrant and Results).

10. On July 1, 2014, Utility Service Group ("USG") performed a Condition

Assessment on the water tower for the Town and submitted a Report. Exhibit 3 (USG

Report).

11. September 6, 2014 email sent from Scott Kelley of USG to the Town

Administrator. Exhibit 4 ( email).

12. September 19, 2014 email sent by the Town Administrator to Scott Kelley

of USG. Exhibit 5 (email).

13. September 22, 2014 email sent by Scott Kelley of USG to the Town

Administrator. Exhibit 6 ( email).

14. At its January 14, 2016 meeting, the Board initially proposed putting an

article on the 2016 Town Meeting Warrant to spend $22,000 to demolish the water

tower. Exhibit 8 (Board Meeting Minutes).

15. At the January 28, 2016 Board meeting, David Chipman (who was not on

the Board at the time) asked the Board to add an article to the 2016 Town Meeting

4

Warrant to keep the tower. He was advised to present a proposed article. See Exhibit

9 (Board Meeting Minutes).

16. On or about February 22, 2016, a citizen's petition with 323 valid

signatures was presented to Town Clerk Rosalind Knight to add an article to the 2016

Town Meeting Warrant. Exhibit 11 (Letter from Town Clerk to Board dated

February 22, 2016).

17. On February 23, 2016, Preferred Tank & Tower of Henderson, Kentucky

provided the Town Treasurer, Marguerite Kelly, with a $75,000 quote to dismantle

the water tower. Exhibit 10 (Letter from Preferred Tank & Tower to Marguerite

Kelly dated February 23, 2016).

18. In its February 23, 2016 letter, Preferred Tank & Tower also provided the

Town with a quote to repair and renovate the water tower. See Exhibit 10 (Letter

from Preferred Tank & Tower to Marguerite Kelly dated February 23, 2016).

19. On March 1, 2016, Preferred Tank & Tower provided the Town with a

quote to repair and renovate the water tower based on full encapsulation. See Exhibit

12 (Quote from Preferred Tank & Tower to Marguerite Kelly dated March 1, 2016).

20. On or about March 2, 2016, a meeting was held at the Town office with

Board Chair Rick Daniel, Town Administrator Kristi Eiane, David Chipman, and

Dorothy Rosenberg to discuss revision of articles dealing with the water tower for

2016 Town Meeting Warrant. As a result, in addition to the citizen's petition article,

which remained on the warrant as Article 35, the Board of Selectmen placed Article

34 on the warrant. Exhibit 14 (2016 Annual Town Meeting Warrant and Results).

5

21. March 12, 2016: The 2016 Town Meeting approved Article 34, and

Article 35 was passed over. Exhibit 14 (2016 Annual Town Meeting Warrant and

Results).

22. On March 31, 2016, the Board voted to create a Water Tower Task Force

("WTTF") and adopted a specific charge for the WTTF's work. ("WTTF Charge").

Exhibit 15 (Board Meeting Minutes); Exhibit 16 (WTTF Charge).

23. On March 31, 2016, the Board appointed a WTTF Chair and four other

members to the WTTF. Exhibit 15 (Board Meeting Minutes).

24. The Chair of the WTTF was Board member Elinor Multer. The following

individuals were also appointed to the WTTF: Jim Knight, Nelson Barter, David

Chipman, and Dorothy Rosenberg. The Board also appointed two alternate members

of the WTTF: David Mercier and Donnette Goodenow. Exhibit 15 (Board Meeting

Minutes).

25. The WTTF held its first meeting on April 26, 2016. Exhibit 17 (WTTF

Meeting Minutes).

26. Steve Cox, Director of Engineering and Maine Water Company, attended

the May 17, 2016 WTTF meeting to provide information regarding the water tower.

Exhibit 18 (WTTF Meeting Minutes).

27. At a WTTF meeting held on September 6, 2016, David Libby, owner of

Communication Facilities, Inc. ("CFI"), made an informal presentation to the WTTF

on the possible use of the Mitchell Field water tower as a communications facility.

Exhibit 20 (WTTF Meeting Minutes).

6

28. On October 14, 2016, Town Planner Mark Eyerman prepared a

Communication Facilities Memo ("2016 CF Memo") and presented it to the WTTF

at their October 18, 2016 meeting. Exhibit 21 (Communications Facilities Memo,

dated October 14, 2016); Exhibit 22 (WTTF Meeting Minutes).

29. At its October 18, 2016 meeting and after discussion of the 2016

Communications Facilities Memo, the WTTF voted to issue an RFP for a water tower

communications site manager. Exhibit 22 (WTTF Meeting Minutes).

SO. At the October 18, 2016 WTTF meeting, the Task Force voted to

recommend to the Board that the Town contract with engineering firm Woodard and

Curran to, among other things, "assess the condition of the water tower to determine

if anything needs to be done on an interim basis to stabilize the tower for .3 to 5 years

while potential use of the tower as a communications facility is investigated further."

Exhibit 16 (WTTF Meeting Minutes) .

.31. On or about November 7, 2016, the Town issued an RFP to solicit

proposals for a water tower communications site manager ("2016 Town RFP").

Exhibit 24 (2016 Town RFP).

.32. On November 28, 2016, Northern Pride Communications, Inc. ("NPCI")

submitted its proposal for Water Tower Communications Site Manager in response

to the 2016 Town RFP. Exhibit 25 (NPCI response).

SS. On November 25, 2016, CFI submitted its proposal for Water Tower

Communications Site Manager in response to the 2016 Town RFP. Exhibit 26 (CFI

response).

7

34. At its December 6, 2016 meeting, the WTTF discussed scheduling

interviews for water tower communications site managers and reviewed a preliminary

list of questions to be asked of the two firms and reviewed a preliminary draft of the

Woodard & Curran report on cost comparison of options for water provision on

Mitchell Field. All Task Force members were given the opportunity to craft questions

for these interviews. See Exhibit 27 (WTTF Meeting Minutes).

3 5. March 20 1 7: Woodard & Curran prepared a Mitchell Field Water Tower

Assessment report for the Town. Exhibit 29 (Woodard & Curran Report).

36. March 11, 2017: The 2017 Town Meeting approved Article 35A. Exhibit

30 (Annual Town Meeting Warrant and Results).

37. The 2017 Town Meeting elected David Chipman to be on the Board to

replace retiring Elinor Multer. Exhibit 30 (Annual Town Meeting Warrant and

Results).

38. The Board appointed Board Chairman Richard Daniel to replace Elinor

Multer as the Chairman ofthe WTTF on March 15, 2017. Exhibit 31 (Board Meeting

Minutes).

39. At the March 29, 2017 WTTF meeting, the WTTF reviewed Woodard &

Curran's final report. Exhibit 33 (WTTF Meeting Minutes).

40. The water tower communication site manager interviews were scheduled

by Town Treasurer Marguerite Kelly. Exhibit 34 (Email exchange between

Marguerite Kelly and Dorothy Rosenberg dated March 30-31, 2017).

8

41. Interviews with CFI and NPCI applicants for the water tower

communications site manager were conducted on April 7, 2017. The interview

committee consisted of the WTTF Chair Richard Daniel, Town Administrator Kristi

Eiane, Town Treasurer Marguerite Kelly and Town Planner Mark Eyerman. Exhibit

27 (WTTF Meeting Minutes of Dec. 6, 2016); Exhibit 40 (WTTF Meeting Minutes

of April 18, 2017). David Chipman was present for a portion of the interviews.

42. On April 1.3, 2017, the Board appointed Ned Simmons to replace David

Mercier as an alternate member of the WTTF. Exhibit 36 (Board Meeting Minutes).

43. At a WTTF meeting on April 18, 2017, Town Treasurer Marguerite Kelly

and Town Planner Mark Eyerman reported on the interviews with communications

facility site managers. See Exhibit 37 (WTTF Meeting Minutes).

44. On or about April 10, 2017, NPCI revised its proposal by email. Exhibit

35 (Email to Marguerite Kelly).

45. On or about April 10, 2017, CFI withdrew its proposal after re-considering

the site, the recent engineering reports and potential carrier concerns. Exhibit 35

(Email to Marguerite Kelly).

46. The $10,000 approved in Article 35A at the 2017 Town Meeting was

never expended by the Town.

47. At the WTTF meeting held on May 23, 2017, Marguerite Kelly presented

the Task Force with a spreadsheet she had prepared laying out the various cost

estimates for the rehabilitation of the water tower. The Task Force agreed to

9

postpone making any recommendations until additional information could be

gathered. Exhibit .38 (WTTF Meeting Minutes, including attached spreadsheet).

48. At the September 12, 2017 meeting of the WTTF, Task Force member

David Chipman reported that he was "moving forward with the formation of a non­

profit organization to raise money for renovation of the water tower. Exhibit .39

(WTTF Meeting Minutes).

49. The WTTF held its last substantive meeting on October 20, 2017. At the

request of Task Force Chair Richard Daniel, recommendations discussed by the Task

Force were drafted by Town Planner Mark Eyerman and read aloud at the meeting.

Exhibit 40 (WTTF Meeting Minutes).

50. At its last meeting held on October 20, 2017, the WTTF voted 5-0 to place

two articles on the warrant for March 2018 town meeting: one to seek proposals from

entities to rehabilitate and manage the water tower, and the other to move forward

with the demolition of the water tower and raise and appropriate not more than

$40,000 for that purpose if the first article did not pass. Exhibit 40 (WTTF Meeting

Minutes).

5 I. Town Planner Mark Eyerman made a brief presentation to the Board at

its December 14, 2017 meeting summarizing the WTTF recommendation of placing

two articles on the warrant for the March 2018 Town Meeting. See Exhibit 41 (Board

Meeting Minutes).

52. On January 2.3, 2018, the Board held a workshop with three members of

the WTTF (Jim Knight, Dorothy Rosenberg and Ned Simmons)-, to refine the details

10

of a draft of the Request for Expressions of Interest to maintain and manage the water

tower for future Town uses. Robert McIntyre attended as an observer.

53. On January 25, 2018, the WTTF held its last meeting to approve the

minutes of the October 20, 2017 meeting. On that same day, the Board voted 2-0 to

dissolve the WTTF (Daniel and Chipman participating). Exhibit 42 (Board Meeting

Minutes).

54. On January 25, 2018, the Board issued a public Request for Expressions of

Interest and/or Proposals to Lease the Water Tower ("2018 Town RFP") revised to

incorporate suggestions from the January 23, 2018 workshop meeting. Exhibit 43

(2018 Town RFP).

55. On February 8, 2018, the Board placed Articles 29 and 30 on the 2018

Town Meeting Warrant as recommended by the WTTF. Exhibit 44 (Annual Town

Meeting Warrant and Results); Exhibit 54 (Board Meeting Minutes).

56. Lincoln/Haney Engineering Associates, Inc. prepared a report on the

water tower for FMF dated February 23, 2018. Exhibit 46 (Lincoln/Haney Report).

57. On February 26, 2018 FMF submitted multiple copies the February 26,

2018 Expression of Interest ("FMF Original Proposal") to the Town in response to

the 2018 Town RFP. See Exhibit 47 (FMF Original Proposal).

58. The FMF Original Proposal was the only response to the 2018 Town RFP

received by the Town.

59. The Board held a public workshop on Tuesday, March 6, 2018. The

primary purpose of the workshop was for the Board and others to gain a better

11

understanding ofthe proposal submitted by FMF in response to the 2018 Town RFP.

The Town invited FMF representatives to attend to discuss and answer questions

about the FMF Proposal. The Town also invited the Mitchell Field Committee to

send a representative to the workshop. Exhibit 49 (Email from Kristi Eiane to Board

members and Town staff, dated March 2, 2018). Robert McIntyre and John Ott

attended the workshop on behalf of FMF.

60. The Board's March 6, 2018 workshop was open to the public and noticed

to the public in advance of the workshop. Exhibit 49 (Email from Kristi Eiane to

Board, dated March 2, 2018).

61. Immediately following the conclusion of the March 6th Board workshop,

Robert McIntyre approached Town Administrator and asked her ifFMF could bring

a document to the Town Meeting for review by voters. Exhibit 50 ("The March 6

FMF Document"). Ms. Eiane told Mr. McIntyre that she would check into it and let

FMF know if the document could be distributed.

62. Town Administrator Kristi Eiane placed a phone call to the

McIntyre/Rosenberg residence on Friday, March 9, 2018 and spoke to Dorothy

Rosenberg, confirming that the March 6 FMF Document could be distributed at the

Town Meeting.

63. On Wednesday, March 7, 2018, Robert McIntyre, came into the town

office, accompanied by Hope Hilton, and gave Ms. Eiane a thumb drive and asked that

the FMF Proposal, which FMF had revised slightly following the Board workshop,

be posted on the Town's website. The thumb drive contained a Word version of the

12

revised FMF Proposal, entitled "Expressiions [sic] oflnterest By Friends of Mitchell

Field 26 February 2018." ("Corrected FMF Proposal") which was posted by town staff

on the town website that day. Exhibit 51 (Corrected FMF Proposal). This document

was removed from the town website after the March 10, 2018 Town Meeting.

64. At the March 10, 2018 Town Meeting, FMF was not allowed to place

written materials on the table near the door where voters entered on which official

Town documents are distributed.

65. Town staff directed FMF to place its written materials at a different table

at the Town meeting.

66. At the March 10, 2018 Town Meeting, the Moderator read Articles 29 and

30 aloud to the meeting. After each Article was moved and seconded, the Moderator

opened the floor to discussion of both Articles at the same time. Exhibit 52

(Transcript 2018 Town Meeting Discussion).

67. The Moderator presided over an open floor debate and discussion of

Articles 29 and 30 which continued for approximately one hour and 10 minutes.

Exhibit 52 (Transcript 2018 Town Meeting Discussion). The Moderator limited no

one who wished to speak during the discussion of the two articles .

68 . During the discussion of Articles 29 and 30 at the 2018 Town Meeting,

Robert McIntyre pointed out to the Town Meeting that written material describing

who FMF is was available on the different table at the Town Meeting. Mr. McIntyre

asked the moderator ifhe could "simply read that one page and then sit down." After

13

the moderator gave him permission to do so, he read a prepared statement aloud.

Exhibit 62 (Transcript 2018 Town Meeting Discussion).

69. The March 10, 2018 Town Meeting rejected Article 29 and approved

Article 30, which authorized demolition of the water tower. Exhibit 62 (Transcript

2018 Town Meeting Discussion); Exhibit 63 (Annual Town Meeting Warrant and

Results).

70. In April 2018, the Town had Katahdin Analytical Services perform

additional lead testing of the water tower lower legs and surrounding soil to provide

a baseline prior to demolition of the water tower. Exhibit 64 (Katahdin Analytical

Services report).

71. At a Board meeting held on April 19, 2018, Dorothy Rosenberg informed

the Board that a citizens' petition was being circulated to overturn the March 10, 2018

Town Meeting vote. See Exhibit 66 (Board Meeting Minutes).

72. On or about April 20, 2018, the Town issued a Request for Proposals to

Demolish the Water Tower at Mitchell Field (the "Demolition RFP"). Exhibit 66

(Demolition RFP).

73. On April 23, 2018, Dorothy Rosenberg sent an email to the Board, Town

Planner, and Town Administrator, and on April 24, Town Administrator Kristi Eiane

sent an email reply. Exhibit 67 (Email D. Rosenberg to Board, K. Eiane, and M.

Eyerman with attachments); Exhibit 59 (Email K. Eiane to D. Rosenberg with

attachments).

14

74. On April 23, 2018, Dorothy Rosenberg sent an email to the Town

Administrator. Exhibit 58 (Email D. Rosenberg to K. Eiane).

75. On or about April 26, 2018, a citizens' petition signed by 351 registered

voters, including FMF board members ("Citizens"), was submitted to the Town

requesting a secret ballot vote to repeal the 2018 Town Meeting vote approving

Article 30 and to authorize the Board to enter into an agreement with FMF to manage,

maintain and repair the water tower (the "Citizens' Petition"). Exhibit 60 (Citizens'

Petition).

76. In a letter dated April 30, 2018, the Town Clerk certified to the Board that

the 351 valid signatures of registered voters on the Citizens' Petition exceeded the

307 signature requirement to call a Special Town Meeting. Exhibit 61 (Town Clerk

letter to Board).

77. The Board rejected the Citizens' Petition after considerable discussion at

its May 2, 2018 meeting. Exhibit 62 (Board Meeting Minutes).

78. At FMF's direction, Maine Environmental Laboratory on or about May

24, 2018 tested paint samples reported by Robert McIntyre to be from the water

tower. Exhibit 66 (FMF Request to Board with Maine Environmental Laboratory

Report) .

79. At its May 9, 2018 meeting, the Board adopted written findings of fact and

made a written decision supporting its rejection of the Citizens' Petition after

consulting with the Town attorney. Exhibit 64 (Board Findings and Decision).

15

80. At the May 9, 2018 Board meeting, Robert McIntyre, on behalf ofFMF,

submitted a written request to the Board asking the Town Attorney to meet with

FMF legal representative. Exhibit 63 (FMF Request to Board).

81. On July 26, 2018, the Board awarded the demolition contract to Iseler

Demolition, Inc. from Romeo, Michigan ("Iseler"). Exhibit 73 (Iseler Contract).

82. On or about June 6, 2018, FMF board members Dorothy Rosenberg and

John Ott met with Town Administrator Kristi Eiane and Town Planner Mark

Eyerman and provided a copy of the May 24, 2018 Maine Environmental Laboratory

report on the paint samples.

83. At the June 7, 2018 Board meeting, FMF submitted a written request to

the Board for reconsideration of its May 9, 2018 finding and decision. Exhibit 66

(FMF Request to Board with Maine Environmental Laboratory Report).

84. The Board took up FMF's reconsideration request at its June 14, 2018.

The Board declined to reconsider its decision. See Exhibit 68 (Board Meeting

Minutes).

85. June 14, 2018: Robert McIntyre, one of the Citizens, presented a copy of

the Citizen's Petition to a Notary Public.

86. On June 14, 2018, the Notary Public signed a "Warrant for a Special Town

Meeting of the Town of Harpswell for a special town meeting to take place on August

11, 2018. Exhibit 67 ("June 14, 2018 Warrant").

16

87. At the June 14, 2018 Board meeting, Dorothy Rosenberg presented the

June 14, 2018 Warrant to the Board. Exhibit 67 ("June 14, 2018 Warrant"); Exhibit

68 (Board Meeting Minutes).

88. Following an executive session with the Town Attorney, the Board met in

open session on June 28, 2018 and voted to declare the June 14, 2018 Warrant invalid

and to direct the Town Clerk not to expend any funds in support of holding the special

town meeting called for in the June 14, 2018 Warrant. Exhibit 68 (Board Meeting

Minutes).

89. On July 1.3, the Notary Public signed a "Warrant for a Special Town

Meeting of the Town of Harpswell" dated July 1.3, 2018 for a special town meeting to

be held on August 10, 2018. Exhibit 71 ("July 1.3, 20.18 Warrant").

90. On or about July 13, 2018, the Town received the July 13, 2018 Warrant".

91. At the direction of the Notary Public, FMF placed ads in the Harpswell

Anchor and Brunswick Times Record for the August 10, 2018 special town meeting

and a "public hearing" to discuss the secret ballot referendum question on July 28,

2018. Exhibit 72 (Published notices of July 28 hearing).

92 . The Board received a letter from the Town Attorney, dated July 12, 2018,

concerning the validity of the June 14, 2018 Warrant. Exhibit 70 (Letter from

Attorney Tchao to Board).

93. The Board did not call a public hearing on the article contained in the July

13, 2018 Warrant.

17

94. No notice of the July 28, 2018 public hearing provided the language of the

article to be voted on by secret ballot.

95. On July 26, 2018, FMF cancelled its August 10th Special Town Meeting.

FMF also cancelled its July 28, 2018 Public Hearing and instead held a public

informational meeting to discuss the water tower on that same date.

The Court's Additional Findings of Fact

This section sets forth the additional findings made by the court based on the

entire record:

96. The Town of Harpswell acquired Mitchell Field, including the water

tower at issue in this case, from the United States Navy in 2001. See Stip. Ex. 1.

97. The Mitchell Field water tower was constructed in about 1950 and consists

of an elevated water tank sitting on four legs, with struts or braces between the legs.

The tank has a capacity of 100,000 gallons. The tank is 28 feet across and the tower

is 104 feet high. Stip. Ex. 3, at 2.

98. Although the evidence is unclear as to when the water tower ceased being

used to store water, the tank has been empty for many years.

99. As indicated in paragraph 5 above, cellular telephone coverage is limited,

spotty or unavailable in many parts of Harpswell. Plaintiff Friends of Mitchell Field

seek to preserve the Mitchell Field water tower largely, if not primarily, because they

view the top of the tower as the highest and best-suited location in the area for

installation of cellular telephone equipment that could significantly improve reception.

18

100. There is an actively used private air field near Mitchell Field, and the

Friends are concerned that Federal Aviation Administration standards would limit or

prohibit the erection of an adequate cellular communications tower in the vicinity.

However, there is no evidence that an adequate cellular communications tower could

not be constructed in parts of Harpswell farther from the air field.

101. The members and directors of Plaintiff include registered voters in the

Town of Harpswell, a point relevant to Plaintiffs standing, as discussed further below.

102. Article 38 on the warrant for the 2013 annual Town meeting proposed

the demolition of the Mitchell Field water tower. The defeat of that article indicated

that a majority of those voting wanted to explore alternatives to demolition.

103. In response, the Town retained Utility Service Group (USG) to evaluate

the condition of the water tower. USG's July 2014 report (Stip. Ex. 3). That report

presented a detailed assessment of the water tower's condition, and concluded that

"[o]verall the tank is in good sanitary and structural condition ... [and] [t]here are

no significant deficiencies that could not be rectified if the tank were to be returned to

active service." Stip. Ex. 3. The report identified a substantial number of repairs that

would be needed to restore the tank, but contained no estimates of cost.

104. Also, the report presented the results of a laboratory analysis of three

samples taken the tower to be tested for lead and chromium. See Stip. Ex. 3 (Eastern

Analytical laboratory report). Two of the samples tested at low levels oflead (180 and

690 mg/kg) but the third sample-taken from the exterior shell of the tank-tested

well above the safety limit for lead (47,000 mg/kg). Id.

19

105. The 47,000 mg/kg test was so high as to indicate that a repair of the tank

could require sealing or encapsulation of the exterior of the tank. On the other hand,

the result was so much higher than the other lead test results as to raise· the question

whether it was an outlier or aberration.

106. In a follow-up email to Town representatives on September 6, 2014,

Scott Kelley of USG provided the Town with estimates of the cost to "bring your tank

up to best level of service as a water storage tank." Stip. Ex. 4. The total estimated

cost was $332,500.

107. In the same e-mail message, Mr. Kelley issued a strong safety warning.

He wrote that allowing the water tower to remain standing without water in the tank

was "extremely risky," and recommended "that action be taken immediately. Severe

weather may lead to failure of the structure." Id. In a later e-mail to the Town

administrator, Mr. Kelley elaborated on his warning by writing, "This steel structure

was designed to have water in it. Without water it is a liability. With severe weather,

the structure may fall over without the designed weight of having water in it." Stip.

Ex. 6.

108. The three quotes that the Town later obtained from Preferred Tank &

Tower (Stip. Ex. 10, 12) were to help the Town understand what costs were associated

with demolishing and repairing the water tower. Preferred Tank quoted the

following costs:

$75,000 to demolish the water tower

$138,625 to repair it without sealing or encapsulating exterior surfaces

20

$337,125 to seal/encapsulate all exterior surfaces, to eliminate any risk from

high lead levels in the exterior coating

109. The Town's March 2016 annual meeting warrant included two articles

relating to the water tower. They were similar in wording. Article 34 was sponsored

by the Select Board and it would create a reserve fund of $22,000 to be used to fund

further analyses of the Town's options for the water tower. Article 35 resulted from

a voter petition and it would have committed the Town to spend $22,000 on repairing

and maintaining the tower. Article 34 was adopted by the voters and Article 35 was

passed over. See paragraph 21, supra.

110. As a result of the Town meeting vote, the Select Board at its March 31,

2016 meeting created the Water Tower Task Force (WTTF). The WTTF was

structured to include four Town residents as primary members, two more as

alternates, and a Select Board member to serve as chair. The Select Board decided to

appoint residents with differing viewpoints to the WTTF.

111. The WTTF met regularly during the middle months of 2016, gathering

information from people with expertise in the fields of public water supply, cellular

communications and cell tower construction and leasing. See Stip. Exs. 1 7-20 (WTTF

meeting minutes).

112. At its October 2016 meeting, the WTTF voted to ask the Town to issue

an RFP for a water tower site communications manager, and to ask the Town to

contract with the Woodard and Curran consulting engineers to focus on water supply

issues relating to the existing well and water tower. See Stip. Ex. 22. At the same

21

meeting, there was discussion about the availability of funding for the repair and

maintenance of the tower from private sources, but it was agreed that no commitments

should be made based on private funds without assurance that the funds would be

available when needed. See id.

113 . The Town Select Board granted both requests, issuing the RFP in

November and delegating to the WTTF the responsibility for evaluating proposals

submitted in response to the RFP. See Stip. Ex. 24. The Town also contracted with

the Woodard and Curran firm as the WTTF had recommended.

114. At the Town's annual meeting March 11, 2017, the voters adopted

Article 35A on the warrant, authorizing $10,000 in Town funds to be spent on

determining "the feasibility of placing wireless communications equipment on the

Mitchell Field Water Tower by obtaining information that includes the number of

interested carriers, what potential payments the Town may derive from equipment

placement, and a detailed description of the work required and associated costs to place

the Tower in service as a communications site." Stip. Ex. SO at 14.

115. Presumably the goal was for the Town to retain a water tower site

communications manager who, working with the WTTF, would compile the

information described in Article S5A. Things did not work out that way.

116. The WTTF designated an interview committee to meet with NPCI and

CFI, the two companies that submitted proposals in response to the RFP. Due to

member unavailability, however, the group that actually met with NPCI and CFI was

limited to Town staff and the chair of the Select Board.

'

22

117. After meeting with the interview committee, CFI withdrew its proposal

and NPCI revised its proposal. See Stip. Ex. 35. The email messages sent by CFI and

NPCI indi~ated that they were backing away because they had realized that the Town

anticipated that the costs of repairing and maintaining the tower would be covered by

the income from leasing the tower to cellular communications providers. Neither CFI

nor NPCI considered that expectation to be a reasonable one. In fact, CFI's email

message flatly indicated that the tower was not a viable option for placement ofcellular

communications equipment and "a new and separate freestanding tower is the only

viable option for the property." Id.

118. It appears that the interview committee led CFI and NPCI to think the

cost of repairing and maintaining the water tower would have to be covered by income

from leasing the tower for placement of cellular communications equipment, even

though no such decision had been made by the Town.

119. The interview committee presumably did not set out to scare away the

two companies that responded, but that is what the Friends of Mitchell Field appear

to claim happened. On the other hand, the Friends' claims of bias on the part of the

Town are largely refuted by the fact that, over a period of years, the Town, through

the voters at annual meeting and the Selectmen, readily agreed to many of the steps

that those who favored keeping the water tower had asked. Moreover, the Town staff

continued to investigate options for using the water tower for purposes of cellular

communications. See Stip. Ex. 40 (memoranda attached to minutes ofWTTF meeting

October 20, 201 7).

23

120. By the fall of 2017, it had become obvious that the WTTF process was

not going to generate a consensus report and recommendation on the future of the

water tower. The members of the WTTF were themselves divided, with two regular

members in favor of keeping the tower and the other two in favor of demolishing it.

121. The WTTF's mandate required the WTTF to issue a report and

recommendations at the end of its work, and the WTTF's report recommending that

two competing articles to be placed on the Town meeting warrant was likely as close

the only consensus report and recommendation the WTTF could have reached. See

Stip. Ex. 40.

122. The Select Board followed the WTTF's recommendation and also began

to set in motion processes to enable either alternative to be implemented. To enable

the "keep" article to be implemented should the voters favor it, the Select Board issued

a Request for Expressions of Interest and/or Proposals in January 2018, specifically

to enable outside groups within the community to submit proposals to lease and

maintain the water tower.

123. In response, some of the Harpswell residents who favored keeping the

water tower, including at least one member ofthe WTTF, formed the Plaintiff Friends

ofMitchell Field as a Maine nonprofit corporation in February 2018. See Stip. Ex. 45.

The Friends submitted their proposal to the Town February 26, 2018. Stip. Ex. 47.

The proposal included an assessment of the condition of the water tower performed at

Plaintiffs request by a structural engineer. Stip. Ex. 46. The assessment concluded

24

that "the effort to stabilize the condition of the water tower amounts to little more

than addressing some deferred maintenance issues." Id. at 2.

124. At the March 1, 2018 Select Board meeting, the Town administrator

informed the Board of the Friends' proposal and raised a couple of questions about the

insurance and financial components of the proposal. See Stip. Ex. 48. The Board

discussed the proposal at a workshop March 6. One question raised at the workshop

was whether the Friends' response that several of the Town's requirements were "Not

a Problem" meant that the requirements were agreed to.

125. The Friends decided to clarify their proposal by replacing the "Not a

Problem" phrase with the word "Agreed," and delivered a revised version of the

proposal to the Town on March 7, 2018. The Town posted the Friends' proposal on

its website later that day.

126. Meanwhile, representatives of the Friends were in touch with the Town

administrator regarding the March 10, 2018 annual Town meeting. A Friends

representative, Robert McIntyre, asked the Town administrator whether the Friends

could hand out copies of their proposal at the meeting. At the August 28, 2018 court

hearing, Mr. McIntyre testified that the Town administrator told him that the

proposal could not be distributed at Town meeting because it related to an article on

the Town meeting warrant. Whether this was in fact what was said is not clear,

because it is agreed that the Town administrator also said that the Friends could bring

a summary of their proposal to the meeting-which would also have related to an

article-if the summary were reviewed in advance with the Town's attorney. It would

25

make little sense for the proposal to be barred but a summary of it to be allowed. In

any event, the Town administrator later denied telling the Friends their proposal

could not be brought to Town meeting. See Stip. Ex. 62, at 8. 2

127. The Friends prepared a summary of their proposal and it was reviewed

by the Town's attorney as requested by the Town. See Stip. Ex. 50. However, the

Friends were told they could not hand out copies during the meeting, and instead

should leave copies on the table set aside for groups in the community to place

materials for Town meeting participants to pick up.

128. During the Town meeting, five of the six directors of the Friends of

Mitchell Field listed in the Friends' revised proposal spoke in favor of the "keep

article." See Stip. Ex. 52 at 6, 8-9, 10-11, 13-16, 20-21, 21-22. During his remarks

on behalf of the Friends, Mr. McIntyre directed the voters' attention to the Plaintiff's

materials. Id. at 11. Other speakers advocated for the "remove" article. There is no

indication that anyone was precluded from speaking until debate on the two articles

was closed.

129. After debate was closed, the vote at Town meeting was not to approve

the "keep" article, Article 29 but to approve the "remove" article, Article 30. See Stip.

Ex. 53, at 15 (annual Town meeting results).

2 A possible explanation for what seems to be a misunderstanding is that the Town

administrator said that the Friends could not hand out their proposal at the meeting, and the

Friends interpreted her statement to mean they could not bring the proposal to the meeting at

all.

26

ISO. At some point around this time, the Town decided to commission further

testing of lead levels on and around the tower, along with testing for asbestos. It

appears that the primary purpose of the testing was in connection with the Town's

development of a request for proposals for the demolition of the tower. The only

testing for lead done to date had been in connection with USG's July 2014 report.

IS 1. In April 2018, the Town received the results of the additional laboratory

tests it had commissioned. See Stip. Ex. 54. The test results indicated that four

samples-two of paint chips and two of soil taken from under or around the tower­

had lead levels well below the health safety limits for lead, and the 47,000 mg/kg level

reflected in the 2014 USG report. Id.

132. At the Select Board's April 19, -2018 meeting, the Board reviewed and

approved a request for proposals to demolish the Tower. Stip. Ex. 55, at 2. Also, the

Town administrator informed the Board of the new test results, which indicated that

the soil around the tower was within acceptable limits for lead and would not need to

be excavated as part of the demolition project. Id.

lSS. The Town's RFP for demolishing the water tower was issued April 20,

2018. See Stip. Ex. 56.

134. At the April 19 Select Board meeting, representatives of the Friends

advised the Board that a petition for the Board to revisit and undo the Town meeting

vote, based on new information, was in the works and would be submitted to the

Board. Id.

27

135. After the Select Board's April 19, 2018 meeting, representatives of the

Friends and the Town engaged in a dialogue about the significance of the new lead

test results. See Stip. Exs. 57-59.

1.36. For the Friends, the new lead test results confirmed that the 47,000

mg/kg test result obtained by USG in 2014 was not valid, in light of the fact that all

six of the other samples in the 2014 and 2018 tests had tested at lead levels well below

federal and state standards. The Friends were convinced that the "keep" or "remove"

issue had to be revisited because the Town's March 10, 2018 vote was based on

incomplete and misleading information. See Stip. Exs. 57, 58.

1.37. Following the April 19, 2018 Select Board meeting, Dorothy Rosenberg,

sent an email message to Town officials and staff pointing out that the new lead test

results showed that the "least expensive justification for demolition of the water tower

collapses. Without lead contamination, the water tower turns out to be the least

expensive option for providing cell phone service to the Neck, Bailey and Orr's

Islands." Stip. Ex. 57. The email said that the WTTF report contained "errors of

such magnitude as to invalidate its core conclusions," with the r~sult that the Select

Board had presented "incorrect and misleading information to the citizens of

Harpswell prior to the vote at Town meeting." The email called on the Select Board

to apologize to the citizens and correct the mistake. Id.

1.38. The Town Administrator responded in an April 24, 2018 email that

included a memorandum from the Town planner discussing the previous and new lead

test results. Stip. Ex. 59. The Town's view of the new lead test results was that the

28

disparity between the 47,000 mg/kg lead test result obtained by USG and the far

lower results in the other six samples tested simply reflected the presence of different

lead levels on different parts of the tower structure. See id.

139. On April 26, 2018, the Friends of Mitchell Field and other supporters of

keeping the water tower submitted petitions for the Select Board to convene a secret

ballot vote on whether to "repeal the decision of the Harpswell Town Meeting on

March 10, 2018 on Warrant Item #so and authorize the Select Board to enter into an

agreement with the non-profit corporation Friends of Mitchell Field ..." to repair,

manage and maintain the water tower. Stip. Ex. 60.

140. The wording of the petition was somewhat different than the wording of

Article 29, the "keep" article that the voters rejected at the March Town meeting.

Article 29. Article 29 asked the voters to decide whether to authorize the Town to

enter into an agreement for up to 20 years (and possible further extensions) with an

unspecified for-profit, non-profit or other entity. See Stip. Ex. 53. The question

advanced in the petition was whether the Town should enter into an agreement with

the Friends of Mitchell Field for five years. See Stip. Ex. 60.

141. The Town Clerk determined that the petition included 351 valid voter

signatures, well over the amount required for such a petition (and well over the

number of voters who had participated in the March 10, 2018 Town meeting) . See

Stip. Ex. 61.

142. The Select Board took up the petition at its May 2, 2018 meeting. After

a lengthy debate, the Board voted 2-1 to reject the petition. See Stip. Ex. 62. During

29

the discussion, the Friends told the Board that the Town administrator had refused to

permit them to distribute their proposal at the Town meeting, but the Town

administrator denied that she had done so. See id. at 8.

143. At its May 9, 2018 meeting, the Board adopted its Findings of Fact and

Decision Concerning Citizens' Petition Regarding Mitchell Field Water Tower. Stip.

Ex. 64.

144. At the Board's May 17, 2018 meeting, the Town administrator presented

to the Board the three bids that had been submitted in response to the Town's RFP

for demolition of the water tower. See Stip. Ex. 65, at 2.

145. The Friends and other proponents of keeping the water tower decided to

pursue their concerns in two different directions. First, they submitted to a notary

public the same petition they had submitted to the Board, for purposes of having the

notary convene a special town meeting pursuant to SO-A M.R.S. § 2521(4). They also

filed a request for reconsideration with the Select Board. See Stip. Ex. 66. The request

was based mainly on the new lead test results the Town had obtained in April, but

also on "allegations ofimpropriety on the part of town officials before, during and after

Town meeting." Id. at 2.

146. The notary to whom the Friends and other proponents of keeping the

water tower had presented the petition that the Select Board had rejected issued a

Warrant for a Special Town Meeting on June 14, 2018. See Stip. Exs. 67. The

Warrant called for a special Town meeting to be held at the Merriconeag Grange hall

August 11, 2018. Stip. Ex. 67. It was later determined that the hall was not available

30

that day, so the notary issued an amended warrant calling for a meeting on August

10, 2018. Stip. Ex. 71.

147. On the same day, June 14, 2018, the Board held a meeting at which a

lengthy debate about the request for reconsideration ensued. Stip. Ex. 68, at 2-3.

Accusations of bias and conflict of interest were made by both sides in the dispute

about the future of the tower. Id. The request for reconsideration was effectively

denied because neither of the two members of the Select Board who had voted to reject

the petition moved to reconsider. Id. at 3. The June 14, 2018 Board meeting also

included further discussion of the bids for demolishing the tower. Id. at 3-4.

148. At the Board's June 28, 2018 meeting, based on advice from the Town

attorney, the Board voted "to deem [the notary's] warrant invalid and to direct the

Clerk not to expend any funds on this effort." Stip. Ex. 69, at 2. The Board also voted

to enter into a contract with the low bidder in response to the RFP for the demolition

of the water tower, with a contingency relieving the Town of responsibility if the

demolition were enjoined. See id. at 2-3. The contract was executed effective July 26,

2018. See Stip. Ex. 73.

149. Meanwhile, the Friends placed advertisements in the Brunswick Times

Record for a July 28, 2018 hearing and an August 10, 2018 Town meeting on the

notary's amended warrant. See Stip. Ex. 72.

Ana"/ysis and Conclusions efLaw

150. Based on the Town's rejection of the notary warrant, the court

recommended that the hearing and Town meeting called by the notary not be held,

31

until the court could decide whether the petition to the notary was valid. The Friends

agreed to the recommendation, on the understanding that the court retained the

ability to order the Town to convene a hearing and vote on the notary's warrant.

151. The Plaintiff Friends' complaint seeks a declaratory judgment and

mandatory injunction to the effect that the Town is required to convene a hearing and

vote by secret ballot on the notary's warrant. The Friends also ask the court to enjoin

the Town from demolishing the water tower until and unless the Town holds the vote

that the Friends are seeking.

152. The Town has raised a variety of objections to the Friends' cause of

action, only some of which require extended discussion. The Town questions the

Friends' standing to sue. However, the court is prepared to assume, without deciding,

that the Friends have standing, based on the doctrine of associational standing. See

Warth v. Seldin, 422 U.S. 490,511 (1975). Plainly some of the directors of the Friends

actively participated in the proceedings at issue, and may have had standing had they

brought this case in their own names.

153. The Town also asserts that the Friends cannot challenge the May 9,

2018 Findings ofFact and Decision Concerning Citizens' Petition Regarding Mitchell

Field Water Tower under M. R. Civ. P. BOB because the complaint was not filed within

the deadline set by that rule. At oral argument, the Friends did not disagree that any

direct Rule BOB appeal from the Board's May 9, 2018 Findings of Fact and Decision

is time-barred. However, the Friends assert instead that the question before the court

is whether the petition submitted to the notary public was valid for purposes of

32

declaratory and injunctive relief in the nature of a writ of mandamus requiring the

Town to convene another Town meeting and vote on the question framed in the

petition. See 14 M.R.S. § 5301. 3

154. The Friends contend that the Town is required to call a Town meeting

and vote under the Maine statute allowing voters to petition a notary to call a town

meeting when town selectmen unreasonably reject a petition of the voters. See SO-A

M.R.S. § 2521(4), 2522. The statutes read as follows:

Petition for article in warrant: On the written petition of a number of

voters equal to at least 10% of the number of votes cast in the town at

the last gubernatorial election, but in no case less than 10, the municipal

officers shall either insert a particular article in the next warrant issued

or shall within 60 days call a special town meeting for its consideration.

so-A M.R.S. § 2522.

Petition by voters, if selectmen refuse. If the selectmen unreasonably

refuse to call a town meeting, a notary public may call the meeting on

the written petition of a number of voters equal to at least 10% of the

number of votes cast in the town at the last gubernatorial election, but

in no case less than 10.

so-A M.R.S. § 2521(4).

155. The Maine Law Court has interpreted both of these statutes in its

decision in Dunston v. Town oJYork, 590 A.2d 526 (Me. 1991). Despite the seemingly

mandatory "shall either insert ... or call" terminology within section 2522, the court

decided that the alternative petition remedy established in section 2521( 4) recognizes

"the authority of the selectmen to exercise their sound discretion in determining

3 The writ of mandamus has been abolished in Maine but mandatory injunctive relief in the

nature of a writ of mandamus remains available. See Dunston v. Town of York, 590 A.2d 526, 528

(Me. 1991).

33

whether the written petition required compliance with the provisions of section 2522."

Id. at 527.

156. At oral argument, the parties appeared to agree that the PlaintiffFriends

has the burden to establish their right to relief in this case, and that the burden has

two elements:

a. To prove that the Town Select Board's refusal to call a town meeting in

response to the petition submitted to the Board was unreasonable, i.e. an

abuse of their discretionary authority

b. To prove that the petition submitted to the notary public was valid.

See SO-A M.R.S. § 2521(4 ).

157. For the reasons set forth as follows, the court concludes, based on the

entire record, that the Friends have not proved either element of their burden.

158. With regard to the unreasonableness of the Select Board's refusal of the

petition, the Friends assert three grounds: that the petition presented a different

question than the question voted upon at Town meeting; that the petition was based

on new information that should have been presented to the voters at Town meeting,

and that there were improprieties before and at the Town meeting that justify a new

vote.

159. Although the wording of the petition was somewhat different than the

wording of article 29 on the Town meeting warrant, compare Stip. Exs. 5S and 60, the

Select Board could reasonably have decided at their May 9, 2018 meeting that the

34

petition was asking for a revote on the essentially the same question that had been

decided at the Town meeting-should the water tower be demolished or not?

160. The petition identified the Friends specifically as the entity with which

the Town would have an agreement whereas Article 29 did not. Still, the Select Board

could reasonably have decided that the voters were aware at the Town meeting that

the Friends were hoping to be the entity that contracted with the Town to repair and

maintain the water tower.

161. Maine law does not compel either a municipal board or a school board to

schedule a revote upon petition by voters on an issue that has already been acted on

by the electorate. See Heald v. School Administrative District No. 74, 387 A.2d 1, 4 (Me.

1978); Town if Vassalboro v. Denico, 1990 Me. Super. LEXIS 61. Under the Dunston

standard, the Harpswell Select Board's view that the fundamental question raised in

the petition had already been decided by the voters was a reasonable one.

162. As to the contention based on new lead test information, the Select Board

could reasonably have decided that the new lead test results were not the "game

changer" for voters that the Friends thought they were. The Town meeting vote to

demolish the tower did not hinge on the validity of the 2014 lead test results. Also,

the new test results did not prove that the high 47,000 mg/kg result was wrong,

particularly since the new results were from samples taken from other locations than

the exterior of the tank, where the sample that yielded the high test was taken.

163. As to alleged improprieties, the Friends failed to prove anything rising

to the level of an impropriety by Town officials or staff The Friends' allegations of

35

impropriety fall into three different categories. First, the allegation that the Select

Board Chairs who also chaired the WTTF were biased and prevented the WTTF from

meaningful exploration of the potential for saving the water tower. Second,

allegations that the Town staff was "biased" in favor of demolishing the tower. Third,

allegations that the Friends were prevented from bringing their proposal at the Town

meeting and were required to leave their summary on a table instead of being allowed

to pass it out.

164. The first chair of the WTTF was Select Board Member Elinor Multer.

When she left the Select Board, the current Select Board chair, Richard Daniel, took

her place as WTTF chair. Mr. Daniel testified at the August 28, 2018 hearing that he

favored demolishing the water tower for safety reasons.

165. The fact that Mr. Daniel had a viewpoint on the future of the tower does

not, in and of itself, prove anything. Select Board members can and should develop

positions on issues affecting the Town. The question is whether Mr. Daniel imposed

his viewpoint in an inappropriate manner while chairing the WTTF, and the record

does not show that he did.

166. Given that the other four members of the WTTF were divided on the

tower issue-two favoring saving the tower, two favoring demolishing it-Chair

Daniel plainly could have imposed his personal viewpoint upon the WTTF by

breaking the impasse and calling for a vote on whether to recommend demolition or

not. Had he done so, the WTTF would likely have issued a report by vote of .3-2 with

a specific recommendation in favor of demolition. But he did not force the issue in

36

that fashion. Instead, he voted, along with the others, to recommend the "keep" option,

even though he disagreed with it, along with the "remove" option.

167. Another allegation against Chair Daniel is that he did not support all of

the suggestions and recommendations made by WTTF member Dorothy Rosenberg,

who is a director of the Friends. This accusation as well does not prove any

impropriety-no member of any committee is entitled to have all her or his

suggestions and recommendations adopted by the committee or supported by the

committee chair.

168. The allegation that the Town staff was biased against saving the tower

is similarly not supported in the record. The record shows that Town staff continued

to support the WTTF and respond to WTTF members' requests until the WTTF

ceased to function after October 2017.

169. Likewise, the allegation that there were improprieties before and during

the 2018 Town meeting was not borne out in the evidence. The Friends' claim that

the Town administrator forbade them from bringing their proposal to the Town

meeting because it related to a Town meeting warrant article was not only denied by

the Town administrator, but also makes little sense given that the Friends were

admittedly allowed to place a summary of their proposal for distribution, which related

to Articles 29 and 30 as much as their proposal did. The Town's requirements that

the summary be reviewed by the Town attorney and that it be placed on a table of

materials rather than handed out likewise were not improper. There is no evidence

that the Friends were treated differently than other groups .

37

170. The Friends also appear to complain that the Town did not post their

proposal on the Town website for a sufficient length of time, and did not allow them

to put their summary on the table of Town materials. This argument overlooks the

fact that the Town was not required to endorse or support the Friends' proposal. The

Town's willingness to post the Friends' revised proposal on the Town website from

March 7 to March 10, 2018 was in fact more than the Friends were entitled to.

171. For the foregoing reasons, Plaintiff Friends has not proved that the

Harpswell Select Board unreasonably refused to grant their petition for purposes of

so-A M.R.S. § 2522 and 2521(4).

172. Even had the Friends met their burden of persuasion on the issue of

whether the Select Board unreasonably rejected their petition for purposes of .30-A

M.R.S. §§ 2521(4), their petition to the notary was defective because it was the same

petition addressed to the Select Board, and not a separate petition addressed to the

notary.

17.3. Section 2521(4) could have provided that the same petition that was

presented to the selectmen can be presented to a notary if the selectmen refuse it, but

it does not. Instead, section 2521(4) requires a different written petition to be

submitted to the notary, and there is a good reason for that. A petition addressed to

one entity for one purpose cannot simply be redirected to a different entity for a

different purpose. Here, it cannot be assumed that the signers of the petition to the

Select Board would necessarily support a petition addressed to a notary after the Select

38

Board had declined to act upon the petition. Some signers might accept the Select

Board decision and not want to take the next step.

For all of the foregoing reasons, the court finds and concludes that the

Plaintiff Friends of Mitchell Field has not proved that the Town is obligated to

schedule and hold a vote on the Friends' petition.

IT IS ORDERED AND ADJUDGED AS FOLLOWS:

1. Plaintiffs prayer for declaratory relief is granted in part and otherwise

denied. The court declares as follows:

(a) For purposes of 30-A M.R.S. § 2522, the Harpswell Select Board did not

unreasonably refuse to call a town meeting in response to the Plaintiff

Friends of Mitchell Field's petition submitted to the Board April 26, 2018,

(b) The petition submitted by Plaintiff Friends of Mitchell Field to a notary

public did not comply with 30-A M.R.S. § 2521(4) and therefore was not a

valid basis for convening town meeting under that section.

2. Plaintiffs prayer for injunctive relief is denied.

3. Except for the limited grant of declaratory relief in subparagraphs (a) and

(b), the Defendant Town of Harpswell is granted judgment on the Plaintiffs

complaint.

Pursuant to M.R. Civ. P . 79( a), the Clerk is hereby directed to incorporate

this Decision and Judgment by reference in the docket.

Dated September 5, 2018

A. M. Horton, Justice

Entered on the Docket: 9 . s. \~

39

Friends of Mitchell Field vs. Town of Harpswell, PORSC-CV-18-334

Plaintiff's Counsel:

Christopher Neagle, Esq .

Troubh Heisler

Defendant's Counsel:

Amy Tchao, Esq.

Drummond Woodsum

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.