Opinion

Penfold v. Peace Pipe Shore Rd.

Court
Superior Court of Maine
Filed
Nov 10, 2010
Status
Unpublished
On the bench
Nancy Mills
Cited by
0 cases
Authority
More cited than 34.2%

The opinion

STATE OF MAINE SUPERIOR COURT

KENNEBEC, ss CIVIL ACTION

D~f~ljI?:

N !'v' , REI:

j

rOil??

i

!. / :

~

c···

cJ:'

WILLIAM PENFOLD,

Plaintiff

ORDER ON MOTION FOR

v. SUMMARY JUDGMENT

PEACE PIPE SHORE ROAD

OWNERS' ASSOCIATION et al.,

Defendants

This matter is before the court on defendant Peace Pipe Shore Road Owners'

Association (Peace Pipe),s motion for summary judgment. Peace Pipe argues that the

plaintiff cannot hold Peace Pipe liable for any damage caused by water runoff resulting

from Peace Pipe's road repair work because of a waiver of liability provision in the

plaintiff's deed. The plaintiff, William Penfold, counters that the deed provision waives

only claims arising from repairs undertaken upon the road itself, and alleges that part

of the repair work that caused damage to him was undertaken upon his private land,

rather than upon the common roadway. For the following reasons, the motion is

denied. 1

FACTS

In the summer of 2008, Peace Pipe hired a contractor to perform culvert and

drainage work on Peace Pipe roads, including on a roadway abutting the plaintiff's

property, in connection with a grant and construction planning from the Kennebec

County Soil and Water Conservation District. (Def.'s S.M.F. CJICJI 6-8; Pl.'s Opp. S.M.F. CJICJI

I Because the parties' arguments on summary judgment are limited to the effect of the deed's language,

the court similarly limits its analysis and does not address the substance of the plaintiff's claims.

1

6-8.) This work was performed because, in the opinion of Peace Pipe, it was necessary

and useful for the beneficial use of Peace Pipe roads, streets, avenues, and ways, which

had been subject to erosion and puddling. (Def.'s S.M.F. <]I 9; Pl.'s Opp. S.M.F. <]I 9.)

The plaintiff has raised an issue of fact regarding whether the work included

excavation upon his property, and whether the road culvert extended onto his property.

(Pl.'s Opp. S.M.F. <]I12, Penfold Aft. <]I<]I 2, 3.) When the plaintiff arrived at his camp in

the spring of 2009, he noticed an eighteen-inch wide stream of water flowing under his

camp. (Def.'s S.M.F. <]I 11; Pl.'s Opp. S.M.F. <]I 11.) He traced the water flow back to a set

of culverts that had been installed during the 2008 road work. (Def.'s S.M.F. <]I 12, as

qualified by Pl.'s Opp. S.M.F. <]I 12; Penfold Dep. at 19:1-2 [referring to "the culvert"].)

The plaintiff noticed that the concrete supports of his camp had moved and were

leaning. (Def.'s S.M.F. <]I 11; Pl.'s Opp. S.M.F. <]I 11.) The drainage of water onto the

plaintiff's property continued throughout the balance of 2009, causing serious structural

damage to the plaintiff's property. (Def.'s S.M.F. <]I 13, Penfold Dep. at 35:17-36:6,?

According to the plaintiff, the camp is no longer safe to stay in due to the structural

damage. (Def.'s S.M.F. <]I 14; Pl.'s Opp. S.M.F. <]I 14; Penfold Dep. at 36:7-36:10.)

On December 10, 2009, the plaintiff filed a three-count complaint, in which he

alleged trespass, diversion of surface water, and negligence. On August 2, 2010, Peace

Pipe moved for summary judgment on the basis that the plaintiff's deed prohibited his

recovery for any damage to his property resulting from roadway construction that was,

in the view of Peace Pipe, necessary or advantageous.

The original deed from the grantor, Parker Lake Shores, Inc., to Raymond W.

Penfold, Sr. and Helene D. Penfold was signed June 30, 1962 and recorded at the

2 The plaintiff did not respond to paragraph 13 of Peace Pipe's statement of material facts.

2

Kennebec County [Registry] Of Deeds, Book 1348, page 8, and provided in pertinent

part:

The grantor for itself, its successors and assigns, hereby reserves the right

without further assent or permit from the grantees or their successors in

title, to itself or to grant to any public utility company, municipality, or

water company, the right to erect and lay or cause or permit to be erected,

laid, maintained, removed or repaired in all roads, streets, avenues or

ways on which said above premises described abuts, ... water, sewer and

gas pipes and conduits, catch basins, surface drains, and such other

customary or usual appurtenances, as may from time to time, in the

opinion of the grantor or any public utility company, water company or

municipality, be deemed necessary or useful in connection with the

beneficial use of said roads, streets, avenues and ways as shown on the

[Peace Pipe Shores Plot Plan] and only in and on said land previously

described when necessary to effectuate any of the foregoing purposes and

all claims for damages, if any by the construction, maintenance and repair

thereof or on account of temporary or other inconvenience caused thereby

against the grantor or any public utility company, or municipality, or any

of its agents or servants are hereby waived by the grantees for themselves

and their successors in titie.

(Def.'s S.M.F. f{[ 2 & Ex. 1; Pl.'s Opp. S.M.F. f{[ 2.)3 The plaintiff acquired the parcel by a

deed from Raymond W. Penfold, Jr. and Patricia Penfold, signed June 28, 2002, and

incorporating in the attached description of the property that it is "subject to all rights

and restrictions as described in deed from Parker Lake Shores, Inc. to Raymond W.

Penfold, Sr. and Helene D. Penfold dated June 30, 1982 and recorded in the Kennebec

County Registry of Deeds in Book 1348, Page 8." (Def.'s S.M.F. errerr 3-5 & Ex. 2; Pl.'s

Opp. S.M.F. f{[f{[ 3-5.)

3 The deed also provides:

Reserving unto the grantor, its successors, assigns, agents, employees or any person duly

authorized by the grantor, the right to enter upon these granted premises at all

reasonable times for the express purpose of repairing, replacing and maintaining water

pipes, drain pipes and septic tanks and all appurtenances thereto.

(Def.'s S.M.F. <JI 2 & Ex. 1.) Because reference to this language was not included in the Peace Pipe's

statement of material facts, it is not part of the summary judgment record, and not properly before the

court. See M.R. Civ. P. 56(h)(1); Levine v. R.BK Caly Corp., 2001 ME 77,114,5, 770 A.2d 653, 655.

3

STANDARD OF REVIEW

Summary judgment is appropriate when the court's review of the parties'

statements of material fact and cited record evidence indicates there are no genuine

issues of disputed material fact and that the moving party is entitled to jud.gment as a

matter of law. Dyer v. Dep't. of Transportation, 2008 :tv1E 106, err 14, 951 A.2d 82L 825. A

fact is material if it can affect the outcome of the case. Id. An issue of fact is genuine if

"there is sufficient evidence to require a fact-finder to choose between competing

versions of the truth at trial." Inkel v. Livingston, 2005 ME 42, err 4, 869 A.2d 745, 747.

11 Although no longer an extreme remedy, summary judgment is 'not a substitute

for trial.'" Cookson v. Brewer School Dep't 2009 ME 57, err 12, 974 A.2d 276, 280

(quoting Arrow Fastener Co. v. Wrabacon, Inc., 2007 ME 34, If[ 18, 917 A.2d 123, 127).

"Thus, 'even when one party's version of the facts appears more credible and

persuasive to the court, a summary judgment is inappropriate if a genuine factual

dispute exists that is material to the outcome,' in which case 'the dispute must be

resolved through fact-finding,' regardless of the nonmoving party's likelihood of

success." Id. (quoting Arrow Fastener Co., 2007 ME 34, err 17, 917 A.2d at 126-27). The

nonmoving party may not rely on "conclusory allegations, improbable inferences, and

unsupported speculation" to oppose summary judgment. Dyer, 2008 ME 106, c:rr 14, 951

A.2d at 825 (quoting Vives v. Fajardo, 472 F.3d 19, 21 (1st Cir. 2007)). r; A court may

properly enter a summary judgment in a case when the parties are not in dispute over

the facts, but differ only as to the legal conclusions to be drawn from those facts."

Tondreau v. Sherwin-Williams Co., 638 A.2d 728, 730 (Me. 1994) (citing Chadwick­

BaRoss, Inc. v. T. Buck Constr., Inc., 627 A.2d 532, 534 (Me. 1993)).

4

ANALYSIS

Construction of a deed is a question of law. Silsby v. Belch, 2008 ME 104, CJI 7, 952

A.2d 218, 221. "The relevant language will be given its ordinary meaning and this

meaning governs unless there is ambiguity present." Id.; see also Pettee v. Young, 2001

ME 156, CJI 8, 783 A.2d 637, 640 ("A court construing the language in a deed must give

the words their general and ordinary meaning, and must first attempt to construe the

language of the deed by looking only within the four corners of the instrument."

(quotations and citations omitted)).

Peace Pipe advances two arguments as to why the disputed provision entitles it

to summary judgment. First, Peace Pipe suggests that, while the plaintiff may have

alleged potentially compensable damage from excavation occurring on his property, he

cannot prevail on Peace Pipe's motion for summary judgment because he did not

distinguish this damage from the noncompensable damage resulting from the roadway

excavation. 4 (Def. Rep. to Pl.'s Opp'n to Def.'s Mot. Sum. J. 2-5.) Second, Peace Pipe

contends that the deed's provisions preclude the plaintiff's recovery for any damage

resulting from road repair, regardless of whether the challenged excavation occurred on

the plaintiff's private property or the roadway. (Def. Rep. to Pl.'s Opp'n to Def.'s Mot.

Sum. J, 5.) Because the second argument is a pure issue of law, specifically, of deed

interpretation, the court will address it first.

Deed

The defendant argues that the plaintiff's predecessor waived recovery of any and

all damages resulting from construction, maintenance, or repair of the roadway,

regardless of the location of the excavation, and cites three cases in support of this

interpretation of the deed: White County v. Wooten, 132 S.E.2d 653, 657 (Ga. 1963);

4 This argument was first raised in Peace Pipe's reply memorandum.

5

Wheeler v. Tones County, 113 S.E.2d 238, 240 (Ga. Ct. App. 1960); and McCommons v.

Greene County, 184 S.B. 897, 899 (Ga. Ct. App. 1936). The language of the deed does

not support this interpretation, and the cases cited in fact support the court's

determination that the waiver provision is insufficient to rule out the plaintiff's claims

at the summary judgment stage of proceedings. All three Georgia cases concerned

plaintiffs who were grantors, and thus had greater control over the language of their

deeds than the plaintiff here, who took by succession from a grantee subject to

reservations in the original deed. See White County, 132 S.B.2d at 654; Wheeler, 113

S.E.2d at 239; McCommons, 184 S.E. at 897. Moreover, all three deeds at issue in the

Georgia cases provided:

I do further grant the right to all necessary drainage in the construction

and maintenance of said road constructed over the5 said right of way and

on my lands adjacent thereto, and also release said County6 and State

Highway Board from any claim of damage8 arising on account of

construction oe said roads or fills and10 embankments, ditches or culverts

or bridges, on account of back water, changing of courses of streams, or in

any other manner.

White County, 132 S.E.2d at 654-55; Wheeler, 113 S.E.2d at 239; McCommons, 184 S.E. at

897. The Wheeler court interpreted this language as a three-fold "release by the grantor

to the defendant and the State Highway Department for damages arising (1) on account

of construction of roads, fills, etc., (2) on account of water backing up or changing its

JlI

course, and (3) 'in any other manner. Wheeler, 113 S.E.2d at 240. Because the damage

in all three cases was caused by the water backup, recovery for which the grantor had

5 The White County deed omits this "the." White County, 132 S.E.2d at 654.

6 The White County and Wheeler deeds do not capitalize "county." White County, 132 S.E.2d at 654,

Wheeler, 113 S.E.2d at 239.

7 The White County and Wheeler deeds refer to "Department" and not "Board." White County, 132 S.E.2d

at 654; Wheeler, 113 S.E.2d at 239.

8 The White County deed refers to "claims or damages." White County, 132 S.E.2d at 654.

9 The White County deed omits the phrase "construction of." Id.

10 The White County deed states "or" and not "and." White County, 132 S.E.2d at 654.

6

expressly disallowed in the deed's language, the courts interpreted these provisions as

preventing recovery. White County, 132 S.E.2d at 655, 657; Wheeler, 113 S.E.2d at 237;

McCommons, 184 S.E. at 897, 175.

In this case, the relevant deed provision includes a waiver of damages from

"construction, maintenance and repair" of the relevant roadways. (Def.'s S.M.F. err 2 &

Ex. 1.) The deed does not refer to "water backing up or changing its course," as the

deeds in the Georgia cases did. See Wheeler, 113 S.E.2d at 240. This deed does not

grant permission for necessary drainage from construction and maintenance of the road

to spread to adjacent lands.

This deed's reference to "land previously described" in connection with "the

beneficial use of said roads, streets, avenues and ways," means the land being used as

roads, streets, avenues and ways. This deed's reference to "said above premises

described abuts" refers to the plaintiff's property. (Def.'s S.M.F. err 2 & Ex. 1.) This deed

specifically limits the described activities to the roadway areas by providing that such

activities may occur and damages are waived "only in and on said land previously

described," i.e., the roads, streets, avenues and ways. Id. If the deed waived rights

generally, including those to involving private property, as Peace Pipe argues, it would

be unnecessary to specify that construction could occur "only" on any specified area.

The court concludes that the deed reflects the parties' intent to permit necessary and

useful activities upon the roads, streets, avenues and ways themselves, and to waive

damages resulting therefrom.

Damages

Peace Pipe also argues that it is entitled to summary judgment because the

plaintiff has not distinguished in his summary judgment pleadings the damage

resulting from the work performed upon the roadway from the damage resulting from

7

work performed upon the plaintiff's private property. The plaintiff has raised a

genuine issue of material fact regarding whether the excavation work included

excavation upon the plaintiff's private property, as well as a culvert extending from the

roadway onto the plaintiff's private property. (Pl.'s Opp. S.M.F. <JI<JI 10, 12, 16.) Citing

Mahar v. Stonewood Transport, the defendant contends that "[w]hen a cause of action

is based on the totality of conduct and the total damages resulting from that conduct,

the plaintiff has the burden to differentiate damages for events for which there is no

liability from damages for which there is liability, or forfeit the entire claim," and

summary judgment is the appropriate result in such a case. (Def. Rep. to Pl.'s Opp'n to

Def.'s Mot. Sum. J. 4.); see Mahar v. Stonewood Transp., 2003 ME 63,823 A.2d 540.

In Mahar, the Law Court entered summary judgment in favor of a corporate

defendant on the plaintiffs' claim of negligent supervision of the corporate defendant's

independent contractor or employee. l1 Id. at <JI 11, 823 A.2d at 543. The record

contained two tortious incidents involving the contractor/employee; one "might" have

been foreseeable to the corporate defendant based on prior actions of the

contractor / employee, but the other was not foreseeable. The plaintiffs based their

cause of action on both incidents and the total damages resulting from the incidents.

They did not attempt to separate the incidents. Id.

The Mahar court cited Barter v. Boothbay/Boothbay Harbor Community School

District for the general proposition that "a plaintiff seeking legal relief must plead all

theories of recovery then available to him." Barter, 564 A.2d 766, 768 (Me. 1989). Barter,

in turn, is a res judicata case, which provides in part:

[A] plaintiff seeking legal relief must plead all theories of recovery then

available to him; he cannot splinter his claim and litigate it separately in a

II "Maine has not yet recognized the independent tort of negligent supervision of an employee." Mahar,

2003 ME 63, <j[ 10, 823 A.2d 540, 543.

8

piecemeal fashion by asserting in a subsequent lawsuit other grounds of

recovery for the same claim when he had a reasonable opportunity to

raise and litigate the same grounds in the former action.

On this record, the plaintiff was not required to differentiate the damages. None

of Peace Pipe's statements of material fact addresses specifically the issue of delineation

of damage amounts based on causation. (See, ~ Def.'s S.M.F. CJICJI 15, 16; Pl.'s Opp.

S.M.F. <JI<JI 15, 16.). The relative amounts ot damages attributable to the potentially

compensable private property excavation and to the noncompensable roadway

excavation represent an issue of fact for trial.

The entry is

Defendant Peace Pipe Shore Road Owners' Association's

Motion for Summary Judgment is DENIED.

Date: November 10, 2010

ancy Mills

Justice, Superior Court

9

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.