Opinion

Brown v. Town of Hudson

Court
Superior Court of Maine
Filed
Feb 20, 2009
Status
Unpublished
On the bench
William R. Anderson
Cited by
0 cases
Authority
More cited than 34.2%

The opinion

STATE OF MAINE SUPERIOR COURT

PENOBSCOT, SS. FILED &E-- CIVIL ACTION

SUPERIORNJERED OCKET NO AP-P6-17

OURT :;\/~,); - r,?(,I"

CHERYL A. BROWN, I FE3 20 2D09 ,', it

G~R6REC~

00.

PEN' .

Plaintiff, DeSeor COUNTY oo~~\.O ~·L\~Rfl..R'l '.

v. \.;':'

TOWN OF HUDSON, SION and ORDER i\i'\' :\\\\~

..

Defendant.

In this administrative appeal, the plaintiff appeals from the decision of the

Hudson Code Enforcement Officer's decision to issue a stop work order on January 26,

2006. Originally, this 80B appeal sought review of the Board of Appeals' denial of her

administrative appeal of their CEO's issuance of a stop work order, but plaintiff later

filed an amended complaint for review asking the court to vacate the CEO's stop work

order. This judge was assigned this case on October I, 2008.

Plaintiff owns shorefront property located within the shoreland zoning district

on Little Pushaw Pond in Hudson, Maine. In the summer of 2005 she sought approval

to construct a garage on this property behind her home for her disabled son. She

submitted the requisite application to the CEO, Dalton Mullis. Mr. Mullis visited the

property to determine if the proposed construction fell within the 100' setback

provision as provided in the Town's Shoreland Zoning Ordinance. After making certain

measurements, he concluded that the project met the setback requirements, as it was

100' or more from the pond's high water mark. At an August 9,2005 Planning Board

meeting, the members considered plaintiff's Shoreland Zoning Application. In

considering the application, the members considered the following written comment

from CEO Mullis: "Today I made a site visit to the Cheryl Brown property at 248 Hay

Road. The purpose of my visit was to confirm the accuracy of information provided by

the applicant. I found the information to be correct. The proposed addition is 100' or

more from the high water line and the total lot coverage is well within the limits of the

Ordinance. In summary, I recommend approval of this application as submitted."

Administrative Record (A.R.), ex. #17. The Board approved Plaintiff's application at

that meeting. A.R. ex. #18.

Plaintiff made several attempts to pick up and pay for the permit that had been

approved, but due to the unavailability of the CEO she was unsuccessful, and

eventually began construction in accordance with the proposed plans without having

the permit. On January 26,2006, the Town's new Code Enforcement Officer, Richard

Fish, issued a stop work order for any further construction. By this time the building

was substantially completed. The basis for the stop work order was not that she was

building without a permit but that a new measurement taken by Mr. Fish in January

indicated that the structure was within 100' of the pond's high water mark. The town

now would not issue the permit that had been authorized earlier. Plaintiff, who was

serving in the military, returned to the area in February of that year and CEO Fish re­

issued the stop work order. He met with the plaintiff, and agreed to re-measure in the

springtime, when there would be no ice to potentially interfere with the measurement.

He then sent a letter to plaintiff, dated July 13, 2008, A.R. ex. #7A, informing her that the

structure is within the 100' setback area, that she had to strictly adhere to the stop work

order, and that she had to move the structure out of the 100' zone pursuant to an

attached consent agreement that she was requested to sign. In this correspondence, he

also indicated that if she did not agree to sign the agreement, she had "the right to

appeal our decision to the Hudson Board of appeals."

On August 10, 2006 plaintiff submitted a completed application requesting a

variance and appeal to the Town of Hudson's Board of Appeals in which she asserted

that the original Mullis measurement "should stand", and accompanied the application

with a memorandum from Mr. Mullis indicating his original approval based on his

measurement, and corroboraHng that plaintiff experienced difficulty in picking up and

paying for the permit because he was either too busy or not in the office when she

attempted to do so. A.R. ex. #7. On September II, 2006, the Board of Appeals issued its

decision denying the plaintiff's appeal and variance request and later, on October 15,

2006, denied her request for reconsideration. On October 26, 2006, the plaintiff filed this

appeal.

At no time has there been an allegation that the plaintiff did not build the

structure pursuant to the plan upon which the Mullis measurements were made. The

controversy arose from differing opinions concerning the location of the high water

mark of Little Pushaw Pond.

STANDARD OF REVIEW

In deciding an administrative appeal, ordinarily it is imperative for the Superior

Court to determine whether the decision of a board of appeals or the decision that was

appealed to the board of appeals is the operative decision to be reviewed. If the board of

appeals acted as an appellate body, then the Superior Court reviews the previous

decision, not the decision of the board of appeals. If the board of appeals acted as a

tribunal of original jurisdiction, then its decision is reviewed directly. The court has

reviewed several cases, including Yates v. Southwest Harbor, 2001 ME 2, 110, 763 A.2d

161, 164; Stewart v. Town of Sedgwick, 2000 ME 157, 14, 757 A.2d 773,776; and Gensheimer

v. Town of Phippsburg, 2005 ME 22, 17,868 A.2d 161,164; and concludes that a decision

on whether a board of appeals is authorized to act in an appellate or original capacity

depends on which portions of the relevant enabling ordinances are stressed. Although

the Hudson Board of Appeals Ordinance resembles in relevant areas the Southwest

Harbor ordinance that has been determined to authorize that Board of Appeals to act in

an appellate capacity, Yates, supra, at 113, it is not necessary for the court to decide in

which capacity the Hudson Board must act because the rationale for the court's decision

in this case applies to both the action of the Board of Appeals as well as the action of

CEO Fish, which that board reviewed. In other words, this Court's decision is the same

whether it is reviewing the Board's decision or the CEO's decision. For the same reason,

it doesn't matter whether the court is proceeding on the original complaint, appealing

the Board's decision, or the amended complaint, appealing the CEO's decision.

MOTION TO DISMISS

In this motion, the town asserts that the court does not have subject mater

jurisdiction to hear this appeal, arguing that the plaintiff filed the administrative appeal

of the stop work order with the Hudson Board of Appeals 152 days after the CEO

reissued the stop work order on January 26, 2006. The court denies this motion.

Al though the stop work order issued on that date, the plaintiff and CEO were working

together to resolve the measurement issue and had to wait until the ice left the pond

and the waters receded to an acceptable level so that the CEO could review his

measurement. After reviewing the measurement, he concluded his initial conclusions

were correct and notified the plaintiff of the result in the July 13, 2006 letter to Ms.

Brown that notified her then that if she did not agree and refused to sign the consent

agreement, "you have the right to appeal our decision to the Hudson Board of

Appeals". Based on these events, the court finds that the town implicitly informally

agreed to reconsider the stop work order and did not finalize that order until July 13,

2006. From that date, the plaintiff had thirty days to file her appeal and complied with

that requirement.

Additionally, consideririg the above circumstances, the Board of Appeals

implicitly waived or extended time limits for filing an appeal by hearing and deciding

the appeal as filed. Their Shoreland Zoning Ordinance authorizes the Board to waive

the thirty day requirement upon a showing of good cause.

DISCUSSION

An issue that immediately becomes apparent in evaluating this appeal is the

potential application of the doctrine of equitable estoppel. If applicable, the doctrine

would preclude the town from issuing a stop work order against plaintiff after she had

already been granted planning board approval for the project. The plaintiff has not

framed the issue in this way and she has not raised it explicitly in her pleadings. There

are two ways that equitable estoppel could be raised, the first being an appeal of the

Board of Appeal's failure to consider the doctrine. A board of appeals could not err as a

matter of law in failing to apply the doctrine because it does not have equitable

jurisdiction unless it is granted such jurisdiction by statute or ordinance. Tarason v.

Town of S. Berwick, 2005 ME 30 ~13, 868 A. 2d 230, 233. The Town of Hudson Land Use

Ordinance does not give the Board such jurisdiction. Alternatively, equitable estoppel

may be raised in the context of an administrative appeal by bringing an independent

action pursuant to M.R.Civ. P. 80B(i). See Donald G. Alexander, et aI, The Maine Rules of

Civil Procedure with Advisory Committee Notes and Practice Commentary 528 (MSBA 2008).

EqUitable estoppel has not been raised in an independent action in this proceeding.

In her primary argument, the plaintiff urges the court to apply Juliano v. Town of

Poland, 725 A. 2d 545, 547 (Me. 1999) to the facts of this case and find that the Town was

precluded from issuing a stop work order on plaintiff's project after having permit

approval earlier. Initially, the CEO approved the project as did the Planning Board, by

vote at the August 9, 2005 regular meeting. In the ensuing weeks she was unable to

obtain the permit that had been authorized because the CEO was unavailable whenever

she attempted to obtain the permit. Based on the Town's authorization, she began

construction without actually obtaining and paying for the permit. There is no

allegation that construction was not in conformity with the site plan that was approved.

In Juliano, the plaintiff obtained a building permit from the Poland CEO for an

addition to his commercial structure. Later, another CEO issued a stop work order

alleging that Mr. Juliano did not have a permit and had not completed the application

process. The Board of Appeals upheld the stop work order on the basis that the permit

that had been issued was invalid because the plaintiff's facility did not fall within a

permitted use. On appeal, the Superior Court upheld the stop work order and the

plaintiff appealed to the Law Court. That court vacated the stop work order, ruling that

the stop work order was in essence a challenge to the prior CEO's decision to issue the

permit. Since the stop work order was issued well beyond the time period allotted for

an appeal of the decision to issue the permit, it was not timely under the thirty day

appeal period established in the ordinance. In support of its decision, the Court noted

that strict compliance with the appeal procedure of the ordinance is necessary to ensure

that a person who has obtained a permit can rely on that permit with confidence. Id at

<j[7.

As in Juliano, the Town of Hudson, through its Code Enforcement Officer and a

vote of its Planning Board, granted approval for plaintiff's construction project, finding

that it did not violate the Shoreland Zoning 100' set back requirement. Almost five

months later, the new CEO issued a stop work order alleging that the structure that had

been built according to plan in fact violated the set back requirement. According to

§16(G) of Hudson's Shoreland Zoning Ordinance, a party aggrieved from a decision of

the CEO or the Planning Board can appeal to the Board of Appeals within 30 days of the

decision. This court finds that since this stop work order was in essence an untimely

appeal of the Planning Board's earlier approval, it is of no effect. Although it could be

argued that this is a different situation because the Juliano plaintiff had a permit in hand

and Ms. Brown did not, the court finds that this is a distinction without a difference.

The initial decision that was subject to appeal pursuant to §16(G) was the decision of the

planning board, not the ministerial function of handing out the permit.

The Stop work order issued on January 26, 2005 is hereby vacated.

The clerk is directed to incorporate this Decision and Order into the docket by

reference.

Dated: February 19, 2009

ILLIAl1 ANDERSON

JUDGE, DISTRICT COURT

AfR UF l.{ W'i

ATIEs~\~A~

-CLERK

Date Filed 10/23/06 PENOBSCOT Docket No. AP-2006-17

County

Action 80 B APPEAL

ASSIGNED TO JUSTICE ANDREW K MEAD

REASSIGNED TO JUSTICE KEVINK. CUDDY

REASSIGNED TO JUSTICE WILLIAM. R. ANDERSON

VHERYL A BROWN vs. TOWN OF HUDSON

Plainti ff' s Attorney Defendant's Attorney

EDMOND J. BEAROR, ESQ FARRELL, ROSENBLATT & RUSSEIL

APRIL A. BENTLEY, ESQ 61 MAIN ST SUITE 1

RUDMAN & WINCHELL, LLC POBOX 738

84 HARLOW STREET BANGOR ME 04402-0738

POBOX 1401 BY: ROGER L. HUBER ESQ

BANGOR, ME 04402-1401

n ............ ,...("

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.