Opinion

N.E. Marine Towing and Constr., Inc. v. City of Ellsworth

Court
Superior Court of Maine
Filed
Apr 17, 2008
Status
Unpublished
On the bench
Jeffrey L. Hjelm
Cited by
0 cases
Authority
More cited than 34.2%

The opinion

STATE OF MAINE SUPERIOR COURT

HANCOCK, SS. CIVIL ACTION

Docket No. CV-04-36 '

\ ,.

-.J

I) ~ l\ I L!

L;---; -" nl) J v - / ,<

~ c.~' '/'> .­

Northeast Marine Towing and

Construction, Inc.,

Plaintiff

v. Decision and Judgment

OONALDL.GARBRECHT

LAW LIBRARY

City of Ellsworth et aI.,

Defendants 1-,1 AY '.1 h .

A consolidated hearing was held on the complaint of plaintiff Northeast Marine

Towing and Construction, Inc. (NEM) and on the counterclaim of defendant City of

Ellsworth. At trial, a representative of NEM and counsel for NEM were present. The

defendants appeared through counsel and, during portions of the trial, through

representatives of those parties.

The pending claims arise out of a contract between NEM and the City, under

which NEM agreed to dredge a portion of the City's harbor in the Union River. For the

reasons stated in this order, the court concludes that NEM materially breached its contract

and that the City terminated the contract for cause. On this basis, the court awards relief

to the City. The court also concludes that defendant Woodard & Curran, Inc. (W&C)

was not a party to the contract, that it acted entirely as the City's agent and that it is not

liable to NEM.

A. Findin2s of fact

1. The project and the contract

The Union River extends from Union Bay, a saltwater body, to Ellsworth and

beyond. In the late 1990's, the Army Corps of Engineers (ACOE) initiated a project to

perform maintenance dredging of the federal navigational channel within the Union River

between Union Bay and the City's harbor. The purpose of this project was to improve

the quality of the channel for use by boats and other vessels. In coordination with the

1

ACOE project, the City initiated its own efforts to dredge sections of the harbor abutting

the terminus of the federal channel, near the City's public boat landing. The City's

dredging plans was one aspect of a harbor revitalization program. The proposed City

dredge would encompass both intertidal and subtidal areas of the harbor, covering

approximately 5 acres. The planned dredge would create a subsurface depth of five feet

below mean low water, which would be similar to the dredged depth of the federal

channel. The City initially estimated that, to achieve these goals, the dredge would result

in the removal of 28,000 cubic yards of sediment and other spoils.

The City engaged W&C to act as its agent in obtaining the permits necessary to

proceed with the dredge. W&C, as the City's agent, then filed a permit application with

the Maine Department of Natural Resources, which is within the Department of

Environmental Protection. See exhibit 8. In that application, the City disclosed to DEP

that W&C was acting as its agent. See exhibit 9b. W&C also filed a permit application

with ACOE. In December 1999 and July 2000 respectively, those agencies issued

permits to the City authorizing the municipal dredge project. See exhibit 18 (project

manual, which includes copies of the permits). With those permits in hand, in January

2001, the City - through W&C - issued a project manual with invitations to bid, as part

of the process of soliciting interest from marine dredging contractors. [d. W&C

subsequently amended the January 2001 project manual to provide that projected volume

of dredged material would be increased from 29,000 cubic yard to 35,500 CY. See

exhibit 225. James Moody, W&C's project manager for the proposed dredge, sent a copy

of the project manual to NEM's principal, Robert Twitchell. See exhibit 20. Moody

forwarded the project manual to six other contractors. NEM did not submit a bid, and in

fact the City received only one bid, which was from Prock Marine, a marine contractor

based in Rockland. See exhibit 21. Prock was the contractor that had also contracted

with ACOE to dredge the federal channel in the Union River. Prock's bid was based on a

price of $13.25 per cubic yard of spoils removed from the harbor. The City decided not

to accept Prock's bid because of the absence of any competitive bidding. See exhibit 23.

In April 2001, W&C issued a second project manual in a renewed effort to solicit

interest in the dredging project. See exhibit 24. This time, NEM submitted a bid, in

which it proposed to be paid at the rate of $12.50 per cubic yard. See exhibit 27. In its

2

proposal, NEM advised that to perform the work, it intended to acquire 2 barges, each

with a 250 cubic yard capacity. [d. Twitchell had intended to dump the dredged material

into one of those barges while the other one, which would already be filled, was hauled to

the dumping ground several miles away. This way, Twitchell planned to dredge and

remove 500 cubic yards per day (one load daily in each barge). In the end, however,

Twitchell purchased only one barge, which had a 300 CY capacity. Twitchell looked at a

second barge and was not satisfied with its condition. However, as he testified at trial, he

would not have purchased a second barge even if he had found one that was seaworthy.

In its bid, NEM expressly recognized that some parts of the project area might be

more difficult to dredge than others, and it therefore reserved the right to negotiate a

higher rate of compensation "prior to dredging." [d. NEM chose its proposed rate of

$12.50, nonetheless, for the specific purpose of attempting to underbid Prock, based on

the bid that Prock submitted previously. In its written bid, NEM represented that it was

"fully aware" of the terms and contents of the April 2001 project manual and the location

of the area to be dredged. [d. The City viewed NEM's bid favorably, and Twitchell and

the City's then-manager, Timothy King, held a pre-contract meeting on July 19,2001, to

further discuss the proposed dredging project. See exhibit 30.

Ultimately, on September 13,2001, NEM and the City entered into a contract

under which NEM would perform the dredging operation in the harbor area. See exhibit

32. As indicated in the contract, the parties estimated that the amount of material to be

dredged was 35,500 cubic yards. See id. at Bates 2347, 2349-50. Based on the amount

of materials that were projected to be dredged and removed, the total expected contract

price that the City would pay to NEM was $481,250 (25,000 CY at the rate of $12.50 per

CY, and 11,250 CY at the rate of $15 per Cy).l See id. at Bates 2292, 2349-50. Prior to

this project, the largest job that NEM had undertaken was worth approximately $40,000.

In previous projects, NEM used as many as six workers. For this job, NEM began with a

total of three workers, including Twitchell. One of those workers left NEM during the

first season, thus leaving only two workers during the balance of the time when NEM

was engaged in the dredge. Despite this history, the contract required NEM to provide

1 In January 2002, the contract price to $516,022 after the parties agreed to a change order

that affected the unit price per cubic yard of some of the spoils. See exhibit l04b.

3

competent and qualified personnel to do the work, see id. at Bates 2318, and it authorized

the City to terminate the contract for cause if NEM persistently failed to provide

"sufficient skilled workers or suitable materials or equipment" to conduct the dredging

operation, see id. at Bates 2340.

The contract expressly identified NEM and the City as the parties to the

agreement. W&C was not a party to the contract, and in fact the terms of the agreement

recite that W&C acted as the City's representative. See, e.g., exhibit 32 at Bates 2291,

2326. Thus, under the contractual arrangement to which NEM agreed, W&C was an

agent for a fully disclosed principal. The contract further provided that W&C's

involvement in the dredge project would not expose it to liability under claims sounding

in "contract, tort or otherwise... ," so long as W&C had acted in good faith when it

engaged in the otherwise actionable conduct. See exhibit 32 at Bates 2328.

Pursuant to the contract, time was stated to be "of the essence," and NEM was

required to substantially complete its performance by April 1,2002. See exhibit 32 at

Bates 2291-92,2347. NEM was required to work during specified hours six days per

week: Monday through Saturday. [d. at Bates 2344. NEM was entitled to be paid based

on the amount of material it removed from the dredge area. As is noted above, most of

spoils would generate payment of $12.50 per cubic yard. [d. at Bates 2349-50. For

several categories of material that was more difficult to remove, NEM would be paid at

the higher rate of $15 per cubic yard. [d. The amount of material that NEM removed

would be calculated based on pre-dredge and post-dredge surveys of the harbor floor. [d.

As would become apparent later in the dredging process, material removed from the

harbor would "fluff' and increase in bulk. However, NEM was entitled to payment based

on an in situ measurement, that is, the volume of the material before it was disturbed and

removed. Thus, the difference between the amounts of material on the harbor floor as

shown in the pre-dredge survey and post-dredge survey would establish the amount of

material that NEM removed in situ. /d. This would form the basis on which NEM's

payments would be established. Under the contract, NEM was responsible for providing

the survey work. [d. at Bates 2351-52. This arrangement stands to reason, because it is

in the contractor's interest to determine the amount of work that it has performed.

4

Under the contract, NEM was responsible for locating the boundaries of the

dredge area. See exhibit 32 at Bates 2351. The City's dredge area was a function of the

federal channel that Prock dredged. The City bore the responsibility to provide NEM

with information that would allow it (NEM) to establish the City's dredge boundaries.

Id. at Bates 2312. W&C was given the contractual authority to determine if the

information provided by the City to NEM was sufficient to allow NEM to locate the

dredge area. Id. This information was in the form of a map developed by or for ACOE,

which showed the location of federal channel coordinates. Those coordinates marked the

corners or angles of the federal channel boundary. Although the map, identified as C-7, 2

depicted a number of such coordinates, only any two of them were a sufficient basis to

layout the boundaries of the dredge. Twitchell testified that he did not receive a copy of

the map until mid-December 2001, which was subsequent to the date that NEM was to

commence its work. However, prior to that date, NEM was provided with a number of

documents that each referred to C-7 as an exhibit. Those documents included the January

2001 project manual, the April 2001 project manual, the August 2001 project manual

(which became the contract), a final project manual issued and sent to NEM in November

2001, and a separate transmittal in November 2001 (see exhibit 37). See also exhibit 35

at p. 2 (referring to deli very of three sets of plans to Twitchell; these plans included C-7).

The court finds it unlikely that the C-7 map would be omitted from so many different

documents, all of which Twitchell in fact received. Twitchell acknowledges that he did

receive the C-7 map in December and could not start the dredge until then. Taken by

itself, this delay is not significant. However, evidence that three C-7 maps were sent to

NEM calls Twitchell's testimony on this point into question, which affects the court's

assessment of other disputed factual points. Further, as is discussed below, NEM

developed a pattern of failing to comply with the scheduling requirements associated with

the dredging project, and this represents an early instance of that problem.

Along with many other provisions, the contract specified the procedure for change

orders and for resolution of disputes arising under the instrument. Finally, the contract

2 In one instance, a document that the City alleges included C-7 was described as "S-7."

With respect to ACOE documents, an "S" exhibit refers to a map of a structural feature or

object. The harbor did not include any structural elements, and so the best explanation is

that "S-7" was an incorrect reference to a document that actually was C-7.

5

authorized the City to terminate the contract either "for cause" or "for convenience." See

exhibit 32 at Bates 2340. The grounds that would justify a termination for cause are

identified in the agreement. See id. A termination not for cause would be a termination

for convenience. The parties' remedies associated with either form of termination are

also set out in the contract.

2. Execution of the contract throul:h the end of first season (September 2001­

.January 2002)

Under the terms of the contract, work was to commence on or after November 1,

2001, or whenever the City issued a "Notice to Proceed." The City issued that notice on

November 7,2001. See exhibit 32 at Bates 2297. As a condition to the commencement

of work, the City required NEM to submit a "schedule of values," which is used to

determine the amount that the City would pay to NEM as the project progressed. NEM

did not provide the City with such an outline prior to the time it began work in December

2001 - and in fact NEM never submitted a schedule of values at any time.

At the July 19 pre-contract meeting, NEM advised the City that it intended to

begin work at the end of October and continue through the end of January 2002. From

the time the contract was executed through the end of October, however, the City had no

contact with NEM. Because the City needed two weeks notice prior to the

commencement of NEM's dredging work, the start date was compromised. At the end of

October, Pat Ryder, an administrative assistant for the City, contacted Twitchell to

inquire if he could start the dredge work in mid-November. See exhibit 34. On

November 7, King, Twitchell and several others who were involved in the project met to

discuss the impending project. See exhibit 35. Twitchell advised that he would be in the

harbor on November 19 and anticipated that he would need 90 days to complete the

work. At the meeting, however, Twitchell indicated that he was unaware that he was

responsible to arrange for the pre-dredge survey of the project area. The City offered to

assist Twitchell in lining up a marine surveyor, despite the allocation of responsibility

under the contract, because the City wanted the project to get underway. By the date

when Twitchell had expected to begin the dredge, work had not commenced, in part

because of the delay in securing a surveyor. See, e.g., exhibit 39. However, NEM could

6

not have engaged in actual dredging operation until November 16, which is when the

City received permission to dump the spoils in the intended dumping area. See exhibit

184.

Twitchell eventually secured the firm of Plisga & Day to conduct the pre-dredge

survey. Stan Plisga traveled to the dredge site on December 4 for an initial view.

Twitchell was unavailable to meet Plisga there that day, apparently because he was

otherwise engaged, and so he asked Ryder to find someone to show Plisga the area.

Ryder and Moody, W&C's project manager, met with Plisga that day and to provided

him with information relevant to the survey work. See exhibits 41, 43. On December 4,

Moody also wrote to Twitchell about NEM's failure to begin work, despite NEM's prior

assurance that the dredge would begin in mid-November. See exhibit 42. On December

4, either in response to Moody's letter of the same date, or simply by coincidence,

Twitchell told Ryder that he could not begin work until December 11 because of

mechanical problems with the tugboat that NEM planned to use for the dredge. See

exhibit 43. Despite these representations, work did not actually begin until December 19,

more than a month after NEM could have started.

In December, an issue arose regarding the location of the City dredge. Under the

contract, the City was required to provide NEM with reference points that would allow

NEM to locate the dredge area on the face of the earth. See exhibit 32 at Bates 2312.

W&C, as the project engineer, was given the contractual authority to determine the

sufficiency of that information. [d. Then, it fell to NEM to establish a surveyed location

of the project boundaries based on the reference points provided by the City. [d. at Bates

2351. This would be the survey performed by Plisga & Day. This survey also had the

dual function, noted above, of allowing a determination of the amount of material that

NEM ended up removing during the course of the project, when that pre-dredge survey

was compared with a post-dredge survey.

The location of the City dredge was tied directly to the location of the federal

channel, because the two abutted each other. The ACOE survey was the definitive source

of information identifying the location of the latter. W&C, as the final arbiter on the

sufficiency of information that NEM would use to locate the project area, treated the

information that way, and this view is corroborated by the testimony of several non-party

7

witnesses. That survey provided navigational coordinates, or reference points,

associated with the location of the federal channel. See exhibit 17a (the C-7 survey). In

fact, that survey identified a number of such coordinates. However, the location of the

federal channel could be established by using only two of them, because once two such

points were located on the face of the earth, the surveyor could use the remaining

information in the survey to establish the courses and distances of the remaining lines.

When Plisga conducted the pre-dredge survey in December, NEM had not provided him

with the ACOE survey. Therefore, Plisga could only try to locate the City dredge area by

comparing and overlaying several other surveys to try to make them line up with each

other. This approach appeared to have good results. See exhibits 44, 175.

On December 19, NEM began the dredge. As is noted above, although NEM had

advised the City that it would be using two barges, it only acquired and used one. On the

first day of the dredge, Twitchell found that an area that he intended to dredge had

already been cleared on sediment and spoils - in other words, that it had already been

dredged. Accordingly, Twitchell reported that there were inconsistencies between the

ACOE survey that identified the coordinates for the federal channel, and the recent Plisga

& Day survey. See exhibit 226. Twitchell claims that he did not receive the federal

survey (the C-7) map until December 19. Although Twitchell did receive a copy of that

plan on that day, as is noted above the court finds that it was also provided to him earlier

in time. However, by December 21, Twitchell, who was now using the coordinates from

the ACOE survey, concluded that he had sufficient information to locate the City dredge

area and that the Plisga & Day survey needed to be corrected. See exhibits 50, 174.

Although it remained NEM's responsibility to resolve this issue, W&C's project

engineer, James Wilson, undertook to relay information from the federal survey to Plisga.

See exhibit 50. Several days later, however, Twitchell again expressed concerns about

discrepancies in the surveys, and the City's project representative, Charles Leavitt,

suggested that a meeting be held with W&C representatives and Twitchell to address the

issue. See exhibit 49. In fact, on December 26, Twitchell arrived at the dredge site and

asked Leavitt where Leavitt wanted him to dredge. See exhibit 175.

Brent Bridges, an employee of W&C who worked a project manager on the City

dredge, continued to try to work as a liaison between NEM and Plisga & Day to help

8

ensure that NEM was providing the surveyor with information that would be important to

the surveying work and identifying the correct location of the dredge area, as the contract

required NEM to do. See exhibit 175. However, it appears that as late as the end of

December or early January, Plisga & Day still did not have the coordinates that were

included in the C-7 ACOE survey. Id. By January 5, Twitchell nonetheless was satisfied

that he knew the location of the City channel and was dredging within those limits. See

exhibit 53. As Twitchell testified at trial, Leavitt, the City's on-site dredge inspector,

checked with him each day to see if NEM was carrying out the dredge in the correct

location, and he (Twitchell) was able to assure Leavitt that it was.

In addition to Twitchell's initial uncertainty regarding the location of the City's

dredge project, a second issue arose. When NEM began the dredging operation, Twitchell

found that there was an unexpectedly significant amount of lumber and timbers

embedded in the harbor floor. Most likely, this material had washed down the Union

River into the harbor when an upstream dam had failed many years earlier. The nature of

this material made the dredging process difficult because, with NEM's equipment, the

size and shape of the timbers made it difficult to secure and then to load then onto the

barge that NEM used to transport the dredging spoils to the dump area. Prior to the time

the parties entered into the contract, W&C had evaluated the harbor floor through probes.

See exhibit 29. That exploration did not reveal the presence of the wood or timbers that

NEM came across later. When the City applied for a DEP permit that would authorize

the dredge, it noted that the spoils would include, among other things, debris from the

dam washout. See exhibit 8 at section 1. Such material, however, does not appear to

have been specifically identified in the City's contract with NEM. 3

In a dredging operation, it is not uncommon for the dredging contractor to

encounter material that is different from what the parties expected. In fact, the parties'

contract addressed that possibility by establishing their resulting rights and

3 In a letter to the City Manger, Timothy King, W&C's project engineer, James Wilson,

noted that the project specifications referred to debris from the dam. The court was

unable to locate that referenced passage in the exhibits. For the reasons noted in the text,

however, even if NEM had been placed on advance notice of this material that proved

difficult to remove, the parties themselves agreed to a resolution, and so the issue is not

material to the adjudication of the parties' claims.

9

responsibilities in the portion of the contract that incorporates standard contractual terms.

See exhibit 32 at Bates 2311. Additionally, in its original written proposal to the City,

NEM foresaw some possibility that the dredge would involve spoils that were difficult to

remove, and NEM reserved the right to renegotiate the price for its work in that instance.

See exhibit 27. And at the meeting held in July 2001, prior to the time the parties

formally entered into the contract, Twitchell and representatives from the City and W&C

discussed the possibility that if the dredged materials were more difficult to remove than

the parties anticipated, there would be an adjustment to the price based on volume of

spoils, and in fact the area of the dredge project could be reduced because of the

increased cost to the City. See exhibit 30b.

Under the terms of the contract, NEM was authorized to seek a modification of

the agreement based on site conditions that turn out to be different from those described

in the contract itself. Such a request would be in writing. The City invited NEM to

submit such' a change order, and on January 22,2002, Twitchell did so. See exhibit 55.

In its proposed change order, NEM sought an increase in the amount it was paid "'per

yard dredged. '" Id. The City responded with a proposal for three rates of compensation

per cubic yard of spoils. See defendant's exhibit 57. Of the three, the rate applicable to a

particular load would be determined by the length of time it took NEM to dredge that

material comprising that load. Thus, for loads that took longer to dredge and load, NEM

would be paid more than for those loads that took less time. This proposal did not

purport to change the in situ unit of measurement. More importantly to this case, the

City's proposal was not one that would entitle NEM to be paid based on time alone. The

amount of time spent by NEM would be relevant only in determining which level of

compensation would be triggered. The amount of payment still was to be predicated on

the amount of spoils, measured by the cubic yard, that NEM recovered. This distinction

is germane because of Twitchell's trial testimony that under the change order, the basis

for payment was converted from volume of dredged materials to the amount of time for

the dredge. Upon persistent examination on the issue, Twitchell ultimately

acknowledged that the payment formula remained based on the volume of material that

NEM dredged and that the City's payments to NEM were not a function of time alone. In

evaluating his credibility on disputed matters, the court considers Twitchell's

10

equivocation of this fundamental aspect of the contract and his own proposed change

order, which the City accepted and which thereby became part of the contract.

NEM accepted the City's proposed change to the payment scheme. See exhibits

75,77. Made with NEM's full knowledge of the nature of the material to be dredged,

this change reflects the parties' agreement on the compensation structure. The change

order remained in effect for the balance of the first dredging season and for the entire

second dredging season.

During the first dredge season, NEM ended up working for a total of 40 days.

3. End of first season throu2h end of second season (January 2001-January

2002)

In July 2002, Twitchell advised City Manager King that NEM would begin the

second season of dredging on November 1, 2002, after mobilizing for that work in late

October. See exhibit 61. Twitchell also stated that NEM had obtained a second barge

and would use a larger excavator. [d. In fact, NEM did not move any of its equipment to

the harbor area until November 18. See exhibit 64. Twitchell testified at trial that he was

not able to begin the dredging work when he planned, because Prock was also in the

harbor working on the federal channel. However, when the City learned of this potential

conflict in October, it initiated a meeting with ACOE representatives because it did not

want NEM's work to be delayed. As Twitchell acknowledged, at the meeting, which was

held on October 25, 2002, the City pressed ACOE on the issue, and ACOE ultimately

agreed that NEM could begin its dredging operation on November 1. Although, both at

trial and at the time, Twitchell blamed Prock's presence as the reason why NEM did not

begin its work on November 1, the best evidence is that Prock did not pose such an

impediment. See, e.g., exhibit 65. In reality, NEM was not prepared to start on

November 1 because it was in the process of repairing a barge. See exhibits 63, 64. At

least some of the damage needing repairs occurred during the first dredge season, and at

least by the summer of 2002 Twitchell had decided to put a new bottom on the vessel.

He was still working on it in November and thus was unable to start at the time he had

represented to the City.

11

NEM did not begin the dredging operation for the second season until November

26. See exhibit 72. When NEM got underway, the work went slowly. One contributing

factor was a heavy layer of ice that formed in the harbor and in the dumping area. NEM

was unable to break through the ice and in fact asked to City to solicit ice-breaking

services from the Coast Guard. Contractually, however, it was NEM's responsibility to

provide all equipment and services necessary to perform its work. See exhibit 32 at Bates

2318, 2345. Because of the slow progress, the City was able to secure an extension of the

dredging season, enlarging the end of the season from mid-April to the end of that month.

See exhibit 84. Nonetheless, the delayed commencement of work at the beginning of the

second season caused NEM to lose time in the harbor prior to the onset of the ice.

For the second season, NEM used a different excavator. The new one had a

"thumb," which made it easier to secure and then move bulky objects such as timber. It

also had a larger capacity. The one used by NEM during the first season had a % CY

capacity; the successor could contain 2.5 CY in its bucket.

By the end of the 2002-03 dredging season, as calculated by the surveyor that

NEM had selected, NEM had removed 9,662 cubic yards of spoils, when measured in

situ. See exhibit 95b. This represented slightly more than 25% of the total amount to be

dredged. These calculations are based on Plisga & Day pre-dredge survey and an interim

survey that was conducted in mid-2003. See exhibits 95a-95d (surveys and meeting

minutes). As of the end of the second dredging season, however, the City had paid NEM

$266,082.75 -- more than half of the contract price. See exhibit 73a (payments for first

season), 93a (payments through end of second season), 102b, 150a. This discrepancy

was a function of the method by which the City made progress payments to NEM. Those

payments were based on visual estimates of the amount of material that NEM dredged

from the harbor area. As is discussed below, the dredged material expands in volume

when it is removed. Therefore, the visual estimate of volume after the material is brought

to the surface and loaded into a vessel tends to overstate the volume of material that

would be measured in situ. Consequently, when viewed as a function of the overall

amounts of material that NEM was obligated to remove and the total contract price, by

the end of the second dredge season NEM had been substantially overpaid for the work it

had completed up to that point.

12

NEM worked through the second dredge season pursuant to the January 2002

change order, which fixed the price per cubic yard that NEM dredged based on the

amount of time NEM took to dredge that particular load. NEM did not raise any

objection to that formula. As Twitchell testified at trial, by then NEM was aware of the

nature of the materials in the harbor floor. Therefore, NEM operated under the change

order, even as its work involved dredging and removing the timbers that led to the

parties' agreement in early 2002 to adjust the way the payments due to NEM were

calculated. And as is noted below, NEM expressed an intention to return for the third

dredge season pursuant to the payment schedule embodied in the January 2002 change

order.

No issues regarding the location of the City dredge arose during the second

dredging season. In early December 2002, there was a slight change in the location of

one of the coordinates that marked the federal channel. See exhibit 67. That one data

point moved less than one foot and had no material affect on the City's project or the

location of the dredge area.

4. End of second season throul:h termination of contract and completion of

dredl:e (April2003-December 2005)

As is noted above, even prior the end of the second dredging season, NEM

assured the City that it would return to the site and complete the dredging project

pursuant to the change order to which the parties had agreed in January 2002. See exhibit

77. When the 2002-03 season ended, NEM requested the City to release amounts that,

under the agreement, the City had retained and contractually was entitled to hold pending

satisfactory completion of the entire project. See exhibit 90. The amount of that

retainage was 10% of the payment otherwise due to NEM. See exhibit 32 at Bates 2292.

NEM would have a claim to all or a portion of that retainage only when it had completed

its performance under the agreement. Id. NEM based its request on its contention that it

had finished a portion of the dredge project and therefore felt entitled to receive the

retainage withheld for that part of the job. In its letter, NEM did not suggest that it felt

entitled to receive the retainage because of the bulking effect of the material as it was

dredged, which is discussed in more detail below. The City declined to give NEM those

13

retained amounts, largely because the payments it had made already to NEM were far in

excess of the proportion of work that NEM was required to perform under the contract.

Clearly, the City was within its rights to deny NEM the retainage at that time because the

contract did not provide for an interim release of the retainage and because the City had

overpaid NEM to date anyway. Nonetheless, NEM's very request for money it was not

entitled to receive holds significance because, along with other evidence noted in this

order, it demonstrates NEM's efforts to be paid in amounts exceeding its contractual

rights.

Prior to a letter dated October 20, 2003, NEM provided no suggestion of any

problem that would interfere with the dredging project that was set to resume for its third

season. King had left the position of City Manager during the summer of 2003, and in

October another municipal official wrote Twitchell to confirm that NEM would resume

the dredge on November 1. See exhibit 100. The City needed that confirmation in order

to prepare for that work. In response, Twitchell wrote back on October 20 and indicated,

rather tersely, that there were "issues" that needed to be addressed, and he requested a

meeting with dredge officials. See exhibit 101. This is the first notice NEM provided to

the City about any problem affecting the upcoming dredge season. Such a meeting was

held on November 10, see exhibit 102, which was ten days after the date when the third

dredging season was to have begun. During the meeting, Twitchell raised two issues.

First, Twitchell said that the dredging process caused the removed material to "fluff," or

increase in volume. This meant that the amount of material NEM handled was in a

greater volume than in its undisturbed state, and this in turn meant more work for NEM.

The extent of bulking varied, depending on the nature of the material being dredged. The

greatest extent of bulking occurred with spoils that included the timbers. Other spoils

that were free from the timbers did bulk, but to a lesser extent than the materials that

incorporated the timber and wood.

Tammy Pinkham, who also represented NEM, advised that the company could

not afford to do this work because of the magnitude of the fluffing. See exhibit 102a.

For the reasons noted above, because of the phenomenon by which the volume of the

dredged materials increases during the dredging process, the City had substantially

overpaid NEM for the work it had performed to date. NEM became aware of this

14

problem no later than the end of July 2003, when it was reported in the local media. See

exhibit 95e. Nonetheless, it did not raise the issue until it sent the letter of October 20,

and even then, NEM did not specify the nature of the problem it envisioned. Rather,

NEM did not identify the issue in a meaningful way until the November 10 meeting.

The second "concern" of Twitchell was the difficulty NEM encountered in lining

up a dredge inspector, who would be responsible for estimating the amount of material

that NEM dredged as it progressed with its work. Those estimates are used to determine

the amount of weekly progress payments paid to NEM. Under the contract, NEM bore

the responsibility to secure a qualified inspector. See exhibit 32 at Bates 2353. NEM, in

fact, had failed to pay the dump inspector who monitored the dredge earlier in the project.

See exhibit 88. Ultimately, the City secured an inspector who was to work during the

third dredge season. See exhibits 102b at Bates 1645; 196. (fhe City had to assure the

new inspector that it would guarantee payment for his services, because NEM had not

paid his predecessor.) Later, in December, after NEM was advised that the City had

found an inspector for the third season, NEM indicated that it was able to find two others

who would cost less. See exhibit 105.

At the November 10 meeting, the City instructed NEM to submit a written

proposal to address the bulking problem. Such a procedure is required by the contract.

See exhibit 32 at Bates 2329, 2332. However, as Twitchell acknowledged during his trial

testimony, Pinkham later advised the City that NEM was not willing to so. Thus, because

of NEM's refusal, W&C assessed the issue. Wilson, the W&C project engineer, then

wrote to Twitchell on December 3. See exhibit l02b. In that letter, Wilson offered a

detailed analysis of the fluffing effect and proposed an adjustment to the price of the

contract based on that circumstance. The proposal would increase the amount of the

contract price by approximately $20,000. That increase was predicated on the City's

analysis of the dredging work associated with the removal of the timbers and the

sediment in the areas where the timbers were embedded in the harbor floor. Under the

City's analysis, the price it would pay for spoils in areas not affected by the timber

material would continue to be controlled by the contract and the January 2002 change

order. Wilson also reiterated the need for NEM to provide additional information and to

submit its own proposed change order associated with the bulking issue because any

15

increases in the payment rate to NEM could require the City to reduce the amount of the

dredge area in order to stay within the City's budget for the project overall. Wilson

instructed NEM to reply by December 8.

By December 11, NEM had not responded to Wilson or the City. Wilson wrote

Twitchell again. See exhibit l04a. That letter enclosed a change order that W&C itself

had prepared, see exhibit l04b, even though the contract required NEM to create and

submit the proposal. Based on the amount of material that NEM still had to remove,

Wilson advised Twitchell that completion of the project by the end of the third dredge

season would require it to remove two barge loads per day, six days each week.

As of December 15, NEM still had not submitted materials relevant to its

complaint, and so a meeting with Twitchell was held that day at his insistence. See

exhibit 105. The meeting was held on short notice. At the meeting, Twitchell contended

that the City should release the retainage of approximately $25,000 to NEM, as it had

previously requested in April; that the City pay NEM based on the volume of spoils after

the spoils were dredged rather than in situ (in other words, based on its fluffed or bulked

volume); and that the amount paid by the City to NEM to date be deemed full

compensation for the work that NEM had performed to date and that the City would pay

NEM in full for all future work without regard to the overpayments that the City had

made to NEM already. As was described by Michelle Beal, the City's finance director

and a participant at the December 15 meeting, the City viewed Twitchell's proposal as

one that would repudiate the contract because it fundamentally deviated from the

payment terms of the existing contract as modified by the January 2002 change order.

Nonetheless, Twitchell was told that unless NEM made its own proposal to change the

payment structure of the contract, the City would not be in a position to entertain the

Issue.

During the meeting, Twitchell also advised that NEM would not work six days

per week, although NEM had failed to submit a proposed work schedule as the contract

required and as the City had requested. At trial, Twitchell initially indicated that he was

uncertain whether the contract required NEM to conduct the dredging work six days each

week. As he ultimately acknowledged at trial, however, the original contract in fact

requires NEM to work on the project six days per week during the dredging season. See

16

exhibit 32 at Bates 2344. Despite the contractual requirement obligating NEM to submit

a proposed schedule, see exhibit 32 at Bates 2308-09,2318, and despite repeated requests

from W&C for such a schedule, see, e.g., exhibits 36b, 42, 102a, 102b at Bates 1645,

NEM never submitted one. Twitchell also told City representatives that because NEM

was tied up with another project in Brooklin, it would not begin work in the harbor until

some unspecified date in January. See exhibits 105 (indicating that Twitchell reported

that NEM's other project was "behind schedule"), 109.

Significantly, of the issues that Twitchell raised at the December 15 meeting,

neither he nor any other representative of NEM complained that the City dredge

exceeded the terms of the dredge permits. As is discussed below, the City later sought an

amendment to the DEP permit to address the quantities of material removed during the

dredge and the relative location of the federal channel and the City dredge area. As part

of its legal claim against the City and W&C, NEM contends that the governmental permit

did not authorize the work that NEM was to perform under the contract. However,

Twitchell did not make such an allegation at the meeting, and he did not offer any such

concerns as a justification for NEM's failure to have resumed the dredge for the third

dredge season. In fact, Twitchell was not aware of any such issue affecting the permit

until January 2004, when he retained an engineer as a consultant to the project. See

exhibits 114, 185.

In a letter dated December 19, Twitchell wrote to Wilson. See exhibit 107. In

that letter, Twitchell advised that NEM could not begin dredging activities because of an

overlay problem that, he suggested, raised questions about the location of the dredging

area. As Twitchell described it in his letter, the overlay problem was the one that Wilson

himself had brought up in his December 3, 2003, letter to Twitchell. See exhibit 102b at

Bates 1645. In that letter, Wilson advised that he was going to explore the issue further

with ACOE and Plisga & Day, but he also asked Twitchell for his "input" because NEM

was responsible for coordinating the surveying responsibilities with Plisga & Day. As is

noted above, NEM was responsible for locating the dredge area. And as is discussed

further below, the overlay issue that Wilson noted in his December 3 issue ultimately

arose from a change made in 2003 to the location of the federal channel. This issue was

unrelated to the one that arose and was resolved during the first dredging season.

17

In his December 19 letter to Wilson, Twitchell also requested information about

the pre-dredging calculations and probes conducted prior to the formation of the contract.

Finally, Twitchell wrote, "Northeast Marine does not accept Woodard and Curran as the

on-site engineer to measure and calculate loads. An independent engineer, shall be hired,

agreeable to all parties involved. (no conflict of interest)." [d. In fact, under the

contract, W&C was authorized to determine the quantity of work that NEM performed as

the dredge progressed. See exhibit 32 at Bates 2327. Based on those measurements,

W&C would then make recommendation to the City about the amount of progress

payments that the City should pay to NEM. [d. at Bates 2336.

Twitchell wrote a separate letter of the same date, rejecting the City's proposal

outlined in Wilson's December 11 letter and describing its own proposed changes in the

contractual payment formula. See exhibit 108. In this second letter, NEM sought an

additional amount in excess of $100,000 for work already done, even though under the

existing contract, the City had substantially overpaid NEM for work performed to date.

This additional payment included NEM's expenses for equipment and ice breaking, even

though under the contract, NEM was responsible for all costs of materials and services

necessary to perform the work. See exhibit 32 at Bates 2345. This can only include

icebreaking work that might be necessary to allow NEM to continue the dredge. This

means that the expenses of performance, such as icebreaking, are not compensable by

themselves, and NEM could only recover such expenses through payments it received

from the City based on the in situ volume of materials it dredged. Any separate payment

for expenses of performance therefore would constitute a double payment. Additionally,

as proposed in the December 11 letter, NEM requested an increase in the amount paid per

cubic yard for future dredging. The proposed increase would have amounted to more

than twice the in situ rates to which the parties agreed previously in the original contract,

as modified in the January 2002 change order.

In a letter dated December 23, Wilson wrote Twitchell on behalf of the City

formally advising NEM that the City rejected the changes that NEM had proposed to the

payment structure. See exhibit 109. Wilson made it express that this decision triggered

the dispute resolution procedures established in the contract, and he reminded Twitchell

that under the contract, NEM was required to continue its performance under the contract

18

even while the dispute remained outstanding. Pursuant to the contract, W&C's rejection

of NEM's December 19 proposal would be the final word on the matter, unless NEM

appealed that rejection or requested dispute resolution. See exhibit 32 at Bates 2329.

NEM did not take either approach, and it also did not sign or agree to W&C's proposed

changes offered to NEM in the proposed change order dated December 11 (exhibit l04b).

In his letter, Wilson also informed Twitchell that, in the City's view, NEM was

responsible for unreasonable delays in the resumption of the dredging project because it

did not raise issues about the level of compensation within the time allowed by the

contract. Under the contract, any request for relief must be made "promptly" but within

no more than 30 days of the date a party learns of the basis for that relief. See exhibit 32

at Bates 2329. Wilson instructed Twitchell to provide a "realistic schedule" to complete

the project, prior to NEM's resumption of the dredge. The contract required NEM to do

this. See exhibit 32 at Bates 2339-40. (As is noted above, on several prior occasions, the

City had requested NEM to provide a progress schedule.) As an additional condition to

that resumption, Wilson also directed Twitchell to provide proof of an agreement that

NEM was to reach to secure a dump inspector. Wilson advised Twitchell that the City

expected NEM to comply with these conditions and mobilize in the harbor no later than

January 15,2004, and that failure to do so could be construed as a breach of the parties'

contract. Finally, Wilson wrote that W&C would coordinate with NEM in preparing a

"departure agreement with the City" in the event that NEM decided that it would not

continue its work on the dredge project

Several days later, Twitchell wrote to Beal and requested various information and

documents, including data from the probes that W&C conducted in 2001 and information

relevant to the pre-dredge survey. See exhibit 113. Twitchell imposed receipt of the pre­

dredge survey information as a condition to NEM's resumption of the dredge, which he

nevertheless stated would occur by January 15. Plisga & Day, however, had already

conducted the pre-dredge survey, which would be used - and was used - to establish a

baseline against which, with the use of a post-dredge survey, it would be possible to

calculate the amount of material removed during the dredge. NEM itself had selected

that surveying firm. In early January, NEM also retained an engineering firm to consult

about the extent and location of the dredge. See exhibit 114.

19

On January 5, the City declared a breach and formally notified NEM that it

demanded non-binding mediation to address the issues in dispute. See exhibit 163a. This

procedure is required under the contract. See exhibit 32 at Bates 2346. Because the

contract does not provide that the pendency of such a process tolls or suspends the

contractor's obligation to continue its performance, the City maintained contact with

NEM in anticipation that it would resume the dredging operation in January, as NEM

represented it would do. On this basis, Wilson again wrote Twitchell with directions

about which areas of the harbor should be dredged, in light of the fact that considerable

time had passed without any progress. See exhibit 116. Wilson also reiterated the need

for Twitchell to provide a proposed work schedule and for additional information.

As it turned out, the weather in mid-January, when Twitchell said he intended to

resume work, was difficult. On January 28, Twitchell's attorney wrote Beal and asked

for the City's assistance in securing the Coast Guard to break up ice that had formed in

the harbor and in the dumping area. See exhibit 121. As is noted above, NEM - and not

the City -- bore the responsibility to provide equipment and services necessary for the

dredge. Counsel also suggested that the City delay the ice-breaking work, to avoid the

possibility that the areas would freeze over again. The suggested delay was "a couple

weeks," which would mean that NEM would not resume work until mid-February. Also

in late January, NEM's attorney requested a meeting to discuss the issue regarding the

locations of the federal and city channels and regarding whether the DEP permit

accurately identified the location of the city dredge. See exhibit 185.

Such a meeting was never held. Instead, on February 4,2004, the City issued a

notice terminating the contract with NEM. See exhibit 123. As the contract authorized it

to do, the City purported to terminate the contract for cause rather than for convenience,

although the notice also provided that if the grounds underlying a termination for cause

were insufficient, the notice should be construed as one terminating the contract for

convenience. In that notice, the City recited five grounds for the termination: that NEM

persistently failed to perform its obligations under the contract; that NEM did not

perform in a timely way; that it disregarded the authority vested by the contract in W&C

as the project engineer; that NEM did not submit information as required, resulting in

further delays; and that NEM did not provide necessary equipment and personnel to

20

perform its obligations. In the notice, the City also demanded reimbursement of the

money that it contended it had overpaid NEM for work performed to date.

After the City severed its contractual ties with NEM, it began the process of

securing another marine contractor to complete the dredging project. In the end, it

entered into an agreement with Prock to finish the work. In late 2005, Prock dredged the

harbor area. At first, Prock used two 300 cubic yard capacity vessels (one dump scow

and one flatbed barge), and then replaced the barge with a 500 CY capacity scow. Prock

used an excavator with a bucket that held 6 CY of material. (NEM had began its dredge

using a 3A CY bucket and then used a larger, 2.5 CY bucket during the 2002-03 dredging

season.) As is shown by the records of Prock's work, see exhibit 145d, and through the

testimony of Prock's project manager, over the course of less than six weeks in

November and December, Prock removed more than 19,000 cubic yards of material from

the dredge area. In contrast to Prock's work, in the two seasons NEM carried out

dredging work, NEM had removed less than 10,000 cubic yards. Prock did not remove

all of the spoils that were the subject of NEM's contractual obligation, because under the

contract it executed with Prock, the City's budget did not allow that much work, and

because Prock dredged to a deeper depth (six feet below low water) than NEM was

required to do (five feet). It bears note that the prospect of reducing the area of the

dredge was something that existed even prior to the time the City entered into the

contract with NEM. At the July 2001 pre-contract meeting between the City and NEM,

the parties' principals discussed the possibility that if the dredging work was more

difficult than expected and the cost of the dredge increased as a result, the City would

reduce the scale of the dredge project in order to remain within budget. See exhibit 30b.

In the permit that the Maine Department of Environmental Protection had issued

to the City in December 1999, the agency authorized the City to dredge in both intertidal

and subtidal areas in and near the municipal harbor. Under the contract, the City was

responsible for obtaining all permits that were necessary for the dredge project. See

exhibit 32 at Bates 2345. With respect to the intertidal area, the permit authorized the

City to dredge 2,000 cubic yards of sediment from an area of 13,750 square feet, which is

approximately .3 acres. See exhibit 12. In May 2000, through correspondence with

ACOE, the city identified three areas within the intertidal zone where it planned to

21

dredge. See exhibit 13. See also exhibit 210. Those areas were located across from the

town dock (9,600 square feet, or .22 acres); the northwest corner of the dredge area

0,300 square feet, or .03 acres); and the area near Card's Cove 05,300 square feet, or

.35 acres). Put together, these three intertidal areas constitute 29,500 square feet, or

approximately .6 acres, which is twice the dredge area approved by DEP.

The discrepancy between the area estimates communicated to DEP and later to

ACOE resulted from the omission of the Card's Cove area as a section of intertidal land.

Card's Cove was within the overall dredge area allowed by DEP, but in its permit

application, the City viewed this area as subtidal. In fact, as it later learned, Card's Cove

was intertidal. Nevertheless, the City proceeded with the dredge project on the basis of

the DEP permit issued in 1999, which included Card's Cove as a subtidal portion, rather

than intertidal portion, of the dredge area. W&C did not seek to amend the permit

because whether Card's Cove was subtidal or intertidal, it was within the boundary of the

permitted dredging area, and W&C believed from prior experience that the matter would

not be of significance to DEP. Prior to the time the City terminated the contract with

NEM, NEM never raised the issue and never expressed an intention to terminate its work

because of a claim that the City had not secured a permit that would authorize all work

required under the contract. In fact, as Twitchell testified, NEM was not even aware of

this permit issue until sometime in January 2004, when it retained an engineer regarding

its work on the project. Rather, the issue came up in a March 2004 letter sent to NEM's

attorney by Stacie Beyer, the DEP representative who was involved with the dredge

project. See exhibit 124. Beyer's letter responded to a letter that NEM's attorney had

sent her. It does not appear that the record includes counsel's letter, and thus it is unclear

whether counsel raised the issue in his letter or whether Beyer herself raised it as part of a

discussion about the dredge project boundaries.

Nonetheless, in February 2005, W&C sought a modification of the DEP permit,

so that the permit would cover the additional volume of intertidal sediment and the

additional area from which that sediment had been removed. See exhibit 141a. The

modification would allow the removal of 7,050 CY from an intertidal area of 35,950

square feet. DEP granted the modification. See exhibit 141 b, 186. The modification

order noted that the amended permit did not affect the dredge boundaries. DEP issued its

22

amended permit after the intertidal area had been dredged. Thus, the amended permit

was retrospective (Le., after the fact, or "ATF'). Although Beyer's March 2004 letter to

NEM's counsel did note the importance of adhering to the limits established in the

original permit, a year later DEP readily amended the permit to allow the intertidal

dredging work that had already been performed because, as expressed in the order, the

work at issue had not breached the boundaries of the City dredge; because it actually

decreased the amount of subtidal dredging; and because it did not create any

environmental problems. As the DEP characterized it in its amended permit, the change

was "minor."

DEP's favorable treatment of the City's request for a modification to the dredge

permit corroborates the testimony of Michelle Beal, the City's finance director who also

served as the acting city manager in later 2003 and early 2004, after King left. Because

of the issues raised by NEM and its counsel earlier in 2004, the City wanted to meet with

Beyer to determine if a problem actually existed. Beal and Beyer met in September

2004. The meeting was brief, because Beyer told Beal that she (Beyer) was aware of the

issue. Beyer took the position, later embodied in the modified permit, that so long as the

City dredge did not breach the outer dredge boundaries set in the original permit, DEP

was not concerned with any deviation from the terms of the project as allowed by the

permit. In fact, despite DEP's awareness of the issue even prior to the meeting between

Beyer and Beal, the agency had not taken any enforcement action, and it did not even

communicate a concern to the City about the issue. Indeed, the City sought the amended

permit on its own initiative, rather than at DEP's suggestion.

In the middle of September 2003, Plisga & Day updated the survey of the City's

channel and of the dredging work that NEM had performed to date. As part of that

process, Plisga & Day requested and received information from ACOE about a new

survey it had commissioned. See exhibit 98. That information included coordinates of

the boundaries of the federal channel in the area of the City dredge. See id. The location

of the federal channel was significant to the City's project because, as is noted above, the

location of the latter was a function of the former. After receiving this information,

Plisga & Day prepared a new survey map. See exhibit 99. As part of its analysis of the

bulking factor that NEM raised in late 2003, W&C obtained the updated Plisga & Day

23

survey, and, Wilson (W&C' s project manager) testified, he then recognized that the

location of the federal channel appears to have moved from the location used in 2001.

See exhibit 141a (referring to a "change" in the location of the federal channel). Federal

authorities are authorized to change the location of a federal channel, and in fact they do

so. See also exhibit 119 (demonstrating that the location of the federal channel is subject

to occasional changes so as to enclose the deepest depths within the channel). The

change that arose from the 2003 survey was a separate issue from the one that arose in

December 2001. As is discussed above, that earlier problem arose because Plisga & Day

was not provided with the coordinates set out in the federal survey (C-7), which was the

touchstone for locating the City dredge.

The best evidence reveals that these boundary data that W&C received in 2003

did not have the effect of changing the location of the outer boundaries of the area that

DEP authorized for the City dredge. Rather, the apparent changes in the location of the

federal channel could have affected the common boundary of the federal channel and the

City dredge area. However, the City dredge area essentially surrounded the terminus of

the federal channel, and so any movement of the City-federal boundary did not constitute

a deviation from the outside perimeter of the City's dredge area. In its February 2005

application for a modification to the original DEP permit, Wilson explained this situation

to Beyer. See exhibit 141a. DEP recognized and acknowledged the situation and still

issued the amended permit because there was no change in the outer boundary of the

combined federal/City dredge area. See exhibit 141a, 186.

Despite Twitchell's occasional uncertainty about the location of the City dredge

project at the beginning of the first dredging season and the 2003 change in the location

of the internal federal-City dredge location, the evidence establishes that all of the

dredging work that NEM performed in the City dredge area was within the permitted

location and that NEM did not exceed the boundary created in the DEP permit.

B. Discussion and conclusions of law

NEM has asserted claims against the City and W&C for breach of contract (count

1). It also has set out a claim for recovery of damages from the City, associated with its

contention that the City terminated the contract for convenience, rather than for cause

24

(count 4).4 The City has asserted a counterclaim against NEM for breach of contract

(count 1 of the counterclaim) and for unjust enrichment (count 2 of the counterclaim).

The court will consider these claims separately.

1. NEM's claims a~ainst the City

NEM argues that the City breached the dredging contract in three ways: first, by

failing to secure a permit that would allow NEM to perform under the contract; second,

by failing to correctly identify the location of the City dredge; and third, by failing to

disclose the nature of the material that NEM would be contractually required to dredge.

The court concludes that NEM has not proven that the City is liable based on any of these

claims.

(a) Sufficiency of the dredge permit

NEM argues that the permit issued by DEP to the City did not allow it (NEM) to

perform the dredge work required by the contract. Under the contract, the City was

required to obtain a permit that would authorize the contracted dredge work to be done.

NEM argues that the DEP permit was deficient in two ways: first, that the permit only

allowed the City to dredge 2,000 CY of sediment from intertidal areas within the City's

overall dredge boundaries; and second, that the permit allowed the City to dredge .3 acres

of intertidal habitat. NEM's argument correctly states the terms of the permit's

restrictions. After the City obtained the DEP permit, it learned that the intertidal aspect

of the project exceeded both limits. The court nonetheless concludes that even if the City

failed to comply with its contractual obligation to obtain a permit that authorized the

extent of dredging in the intertidal areas of the City's dredge area that was actually done,

any such breach was not material.

The Law Court has defined the distinction between a total breach and a partial

breach of a contract:

When one party breaches a contract, the nonbreaching party may, depending on

the circumstances, either treat the breach as partial or total. A total breach of

contract is a non-performance of duty that is so material and important as to

justify the injured party in regarding the whole transaction as at an end ... If [the]

4 In its complaint, NEM also alleged that the City and W&C are liable for both fraudulent

and negligent misrepresentation (counts 2 and 3). Prior to trial, the court entered

summary judgment for the defendants on those two counts, leaving the claims noted in

the text.

25

breach is not sufficiently material and important for this, the breach is called a

partial breach. If a party elects to treat the breach as partial, however, it must still

perform its obligations in order for it to avoid also breaching the contract.

Down East Energy Corp. v. RMR, Inc., 1997 ME 148, ~ 10,697 A.2d 417, 421. For

purposes of this discussion, the court assumes that the City committed a breach of the

contract when it failed to obtain a permit from the Maine Department of Environmental

Protection that did not fully conform to the actual dredging project due to the two

deviations noted above.

The magnitude of any such breach - and the legal effects flowing from it - is best

gauged by the DEP's response to the City's application for an amendment to the original

permit. The requested amended permit was to reflect the work that was actually

performed in excess of the originally permitted dredge work. For that reason, it was to be

an ATF (after the fact) authorization. Perhaps through communications with NEM's

attorney after the City terminated the contract, DEP became aware in early 2004 that the

vol ume and area of intertidal dredging exceeded the limits established in the original

permit. Even when armed with that information, the agency did not take any steps to

intervene in the dredge project either through an enforcement action or with a simple

communication to the City advising it of a problem. Later in 2004, Beal, as a city

representative, took the initiative to meet with Beyer, the DEP agent involved in the

project, in order to discuss this very issue. Beyer assured Beal that the agency was not

concerned about the deviation. This perspective was subsequently embodied in the

amended permit issued by DEP in 2005. Among the findings that the agency articulated

to explain its decision to grant the amended permit, it characterized the intertidal

boundary and volume issues as "minor."

From this, the court concludes that any breach by the City was a partial breach.

Under the Down East Energy formulation, the breach would not justify a refusal by NEM

to perform its obligations under the contract. More importantly, however, NEM did not

invoke any deficiencies in the permit as a basis for non-performance. Rather, as is

discussed at greater length below, NEM's intransigence in performing its obligations in

late 2003 was ultimately rooted in its efforts to secure higher level of payment from the

City for work that it was already required to perform. NEM was not even aware that the

26

permit may not have covered the proposed dredge work until early January 2004, when it

retained independent engineering services.

Further, any such breach did not cause NEM to sustain damages. There were no

resulting delays in NEM's ability to work on site. Rather, NEM had declined to resume

its dredging work for unrelated reasons. Further, DEP did not seek any sanction from

any party to this action. NEM therefore was not exposed to penalties or other

consequences from any work that exceeded the limitations imposed in the original

permit. Therefore, NEM did not sustain any harm or prejudice because of any work it

performed beyond that authorized in the DEP permit, and consequently it has not proven

any damages arising from a breach of contract.

(b) Location of the City dredge

NEM's contention that the City breached the contract in this second way must be

predicated on an argument that the City did not provide it with sufficient information on

which it (NEM) could adequately establish the location of the City dredge project on the

face of the earth. This analysis is necessary, because under the contract, the City was

obligated only to provide NEM with reference points or other information that NEM

could then use to locate the City dredge area. Under the contract, W&C's involvement

on this issue was to assess whether the data provided by the City would allow NEM to

map out the location of the project.

On this record, there is no meaningful dispute that the coordinates for the federal

channel are a sufficient basis for locating the City dredge area. The City dredge area was

intended to compliment and coordinate with the federal channel, and so once the federal

channel is located, the location of City dredge area could be determined. The location of

the federal channel is defined by the coordinates or reference points set out in the C-7

survey. This means that because the City and W&C provided NEM with the C-7 survey,

they discharged their contractual responsibility. The remaining task of establishing the

location of the City dredge area as a function of the C-7 coordinates was NEM's

obligation.

NEM argues that there was a ongoing question about the location of the City's

dredge project throughout the duration of NEM's participation in it. However, the

evidence reveals that there were two distinct episodes that arguably raised questions

27

about the City dredge boundaries. Neither amounts to a breach of the contract

attributable to the City. The first occurred in late 2001, when NEM began the dredging

work. Although Twitchell disputes it, the preponderance of the evidence indicates that

NEM had been provided with the C-7 survey even prior to the beginning of the dredge

season. Even Twitchell agrees, however, that he received that document and the

accompanying information by December 19, 2001. Nonetheless, the record also

establishes that the surveying firm, Plisga & Day, did not come into possession of that

information until later. This meant that earlier in December, when the surveyors were

attempting to locate the City dredge area, they did not have the benefit of infonnation that

would be instrumental to that task. Instead, Stan Plisga had to try to align several surveys

in order to define the dredge area. Within the first few weeks of the dredging operation

in late December 2001 and early January 2002, Twitchell went back and forth on the

question of whether he was satisfied with the infonnation that Plisga & Day produced.

Ultimately, however, Plisga & Day acquired the information from the federal survey, and

Twitchell indicated that he knew the location of the dredging boundaries and was

satisfied that he was working within them. Indeed, surveys that were conducted after the

second dredging season, which was after NEM had performed all of the dredging work

that it ended up providing to the City, establish that NEM conducted its dredge fully

within the boundaries of the project. This tends to confirm that, instead of having

received faulty data, NEM actually had correct information about the project's location

and then used that information effectively.

Separate and distinct from this episode, in 2003 W&C discovered that the federal

channel had been re-Iocated. Despite NEM's argument that this was not a new

development but rather constituted a problem that existed throughout the time it worked

on the project, the court concludes that the better evidence establishes that questions

about the location of the federal channel - and thus of the City'S dredge area - were

generated by a federal survey conducted in 2003, which indicated that the location of the

federal channel had changed since 2001. W&C came across the new date as Wilson, a

W&C project manager, examined the bulking issue that was the focus of NEM's

reluctance to resume its dredging work. As part of that process, he analyzed the new

surveys that contained information about the amount of material that NEM had dredged

28

to date. It was these surveys that also revealed information about new federal

coordinates. When Wilson came across this information, he advised Twitchell about it in

his December 3 letter. Twitchell, on the other hand, had not raised any question about

the location of the City dredge area since January 2002, when he became confident that

NEM was dredging in the correct area after Plisga & Day was provided with the federal

coordinates from the C-7 survey.

The revelation of the new federal data in 2003 cannot be viewed as a breach by

the City of its contractual obligation to provide NEM with information that would allow

it to locate the dredge grounds. The City had just come across that information

unexpectedly and was in the process of evaluating it, when other factors led the City to

terminate the contract in early January 2004. Therefore, even if the new federal reference

points constituted a modification of the terms to the original contract because of its effect

on the location of the City dredge area, then the City did not breach its corresponding

obligation to provide those data to NEM.

(c) Nature of dredged materials

Almost immediately after NEM began the dredging work in December 2001, it

found that the dredge area was the site of timbers. This had not been fully revealed in the

information that the City, through W&C, had provided to NEM and other prospective

contractors. Timbers posed a considerable problem for NEM because of the equipment it

had brought to the dredge site. The bucket on the excavator was relatively small and thus

could not easily capture objects such as timbers, unlike more typical spoils such as

sediment that could be scooped up more easily. Additionally, the timbers were difficult

to load onto the barge that NEM used to transport the material to the dumping ground.

This type of complication was certainly not unforeseeable or unforeseen. In its

bid proposal, NEM acknowledged that if the material in the harbor made the dredge more

difficult than the parties expected, it expected to be able to renegotiate the price per cubic

yard that it would be paid. Additionally, even the standard form portion of the parties'

actual contract opened the door to price renegotiations in this circumstance. Thus, it is

plain from the record that in the marine dredging business, once a dredge operation gets

underway, it is not uncommon for the dredging contractor to encounter spoils that

enhance the difficulty of the dredging operation. That was the situation here.

29

The City promptly learned of the difficulty that NEM had begun to encounter in

December 2001. The parties conferred, and at the City's recommendation, NEM

followed the procedure established in the contract to propose a change order that would

adjust the amount of money that the City would pay to NEM due to the increased

difficulty. The City responded to NEM's proposal, and NEM accepted the City's

proposal. The court concludes that the resulting modification of the price structure in the

original contract represented a dispositive, final and informed accommodation of the

problem. In other words, once NEM was in the harbor and found that it would be

required to dredge materials that were different from what the parties had anticipated, the

parties responded with an adjustment that fully accounted for that new information.

Because NEM agreed to this resolution, it cannot be heard now to complain that the City

had breached the contract by failing to provide the very information that formed the basis

for the parties' accord.

To the extent that NEM is also alleging that it was harmed by the presence of

materials in the harbor floor other than the timbers, this argument also fails. When NEM

sought a substantial change in the payment formula in November and December 2003, it

contended that the increase in bulk of the dredged material correspondingly increased the

amount of work it would have to do. The effect of the timber on this "fluffing factor"

had been resolved with the January 2002 change order. This would leave only the

bulking effect of the other spoils in the dredge area. Nothing in the record suggests that

bulking of the non-timber material upon dredging is an unforeseeable and unexpected

phenomenon. Indeed, common sense suggests that this will happen. Therefore, there is

no basis on which NEM can argue that the City can be charged with any lack of

awareness of spoils material other than the timbers.

Even if the City were at fault in some way because it failed to disclose material

that bulked more than the parties could have expected, NEM has not preserved any claim

for relief here. In late December 2003, after considerable prodding, NEM submitted a

proposed change order to address the bulking factor. The City rejected that proposal.

Under the contract, that rejection became final unless NEM pursued an appeal or some

other form of recourse, such as mediation, prescribed in the contract. NEM did not take

any of those steps that were available to it. Consequently, it became bound by the City's

30

rejection of its proposed change order, which meant that the existing pricing formula ­

which included the change order to which NEM itself had agreed in January 2002 ­

remained in place. Because that pricing arrangement remained unchanged, the City

cannot be deemed to have breached the contract.

3. NEM's claims al:ainst W&C

In NEM's count that remains against W&C, NEM alleges that it is liable for

breach of contract. As is noted in the summary judgment order, NEM's remaining claim

against W&C is limited to its contention that W&C failed to provide NEM with

clarifications and interpretations as required by the contract. This claim requires proof

that W&C was a party to the contract, because otherwise W&C would not owe an

independent contractual duty to NEM. 5

W&C was not a party to the contract. The only parties to the contract were NEM

and the City. The contract expressly identifies W&C as the City's agent, and W&C held

itself out in that capacity throughout its work in the case. Because the contract fully

disclosed the existence of the agency relationship between W&C and the City, W&C

cannot be deemed a party to that contract. See RESTATEMENT (THIRD) OF THE LAW OF

AGENCY § 6.01 (2006); RESTATEMENT (SECOND) OF THE LAW OF AGENCY § 320(1958).

An exception to this general principal exists where the agent and the third-party (here,

NEM) agree that the agent is a party to the contract. See RESTATEMENT (THIRD) OF THE

LAW OF AGENCY § 6.01(1). The third-party bears the burden of proving such an

agreement. See id. at cmt. d(1). NEM has not argued that W&C entered into an

agreement with it (NEM) under which W&C would become a party to the contract, and

such an argument would not have support in this record. As the Restatement notes, "[a]n

agent is not a party to a contract if any portion of the parties' writing makes clear that the

agent acts solely in a representative capacity on behalf of a disclosed principal." /d. That

is the case here: the contract expressly designates W&C's role as that of the City's agent.

5 NEM does not argue that it is a third-party beneficiary of the contract between the City

and W&C under which the W&C had a separately enforceable duty to provide

engineering and other services associated with the dredge project. Although W&C has

offered an argument against such a contention, NEM does not pursue it as a theory of

liability, and so the court does not reach it here.

31

The contract also addresses the extent of any liability to which W&C would be

exposed on account of its work as the project engineer. Under its terms, W&C is

immunized from any claims based on decisions and actions made in good faith. Simply

put, NEM has not established that W&C acted in a way that fell short of good faith in any

aspect of its role. As is discussed further below, W&C and the City gave NEM

considerable opportunity to perform under the contract. They were tolerant of repeated

material delays, and even when NEM declined to resume the third season dredge, W&C

and the City showed considerable patience with the contractor.

NEM has argued that the City did not adequately disclose the intertidal aspects of

the dredge project to DEP when it sought the agency's permit. As is discussed above, it

appears that prior to the execution of the contract and the commencement of the actual

dredge work, W&C and the City knew or should have known that with respect to the

intertidal dredge the quantitative information in the permit application, and thus in the

terms of the permit itself, was inaccurate. However, the DEP representative ultimately

concluded that the inaccuracies were "minor," and the DEP issued the amended permit

that brought those deviations back within the allowable scope of work. Thus, because

this was not a significant issue, and because the problem did not create any harm to

NEM, any failure by W&C to clarify the issue with the agency prior to 2004 did not fall

short of good faith performance of its own obligations as the City's agent, and it did not

result in any independent liability or harm to NEM.

3. City's claims al:ainst NEM

In its counterclaim against NEM, the City alleges that it terminated its contract

with NEM for cause and that it is entitled to recover damages pursuant to the formula for

relief set out in the contract. In a separate count, it also seeks recovery for overpayments

it made to NEM during the course of the dredging operation, framing this issue as one for

unjust enrichment. The court concludes that the City was entitled to terminate the

contract for cause and that the rights and responsibilities of the City and NEM are

determined both pursuant to the remedial terms of the contract associated with such a

termination and under common law principles.

32

The contract authorized the City to tenninate the contract for cause in any of four

circumstances. See exhibit 32 at Bates 2340. The contract describes one of those

circumstances in the following way:

1. CONTRACTOR'S persistent failure to perform the Work in

accordance with the Contract Documents (including, but not limited to, failure to

supply sufficient skilled workers or suitable materials or equipment or failure to

adhere to the progress schedule...as adjusted from time to time...)....

ld.

The City has established by a preponderance of the evidence that NEM

persistently failed to perform its obligations under the contract in accordance with those

contractual requirements. NEM's persistent failure to satisfy its contractual perfonnance

culminated in its effective refusal to resume dredging operations in the third season, after

it unjustifiably delayed making the complaints about the terms of the agreement. The

events of 2003, however, must be seen in light of significant but less detenninative

circumstances that arose during the first two dredging seasons. The contract authorized

the City to terminate for cause only if NEM's failure to perform under the contract were

"persistent," thus making those prior circumstances relevant.

In the contract, NEM acknowledged that time for performance was "of the

essence." NEM agreed to substantially complete its performance by April 1,2002, which

turned out to be the end of merely the first dredging season. Further, the contract

required NEM to work six days per week. As late as December 15, 2004, - more than

two years after NEM entered into the contract --, NEM appeared to have been unaware of

this requirement, and Twitchell actually told City and W&C representatives that he

would refuse to work on that schedule.

In July 2001, Twitchell represented that NEM would begin work at the end of

October, which was when the permitted dredging season began. However, the City had

no further contact from NEM until a City employee initiated contact with NEM in late

October. The absence of any communication from NEM by itself delayed the start of the

dredge, because the City needed several weeks advance notice of that start date in order

to make arrangements for that work to begin. As of the beginning of November,

however, NEM had not arranged for a pre-dredge survey, and at the pre-dredge meeting

held on November 7, Twitchell seemed unaware that, despite the plain requirements of

33

the contract, he was responsible for securing that survey. This caused an additional

delay, despite the City's efforts to help NEM secure a surveyor. Even if NEM had

arranged for the survey, it could not have begun the dredge on a timely basis because its

tug needed repairs. The dredge finally began on December 19, more than a month and a

half late.

Once it was underway, the dredge progressed slowly during the first season

because NEM found that the harbor floor contained timbers, which made the dredging

work more difficult. None of the parties anticipated this situation, despite the probing

analysis that W&C had conducted even prior the time NEM and the City entered into the

agreement. Because this problem was unexpected, the resulting delays during the first

dredge season after that point cannot be charged to NEM. Nonetheless, these events

reveal the beginnings of a pattern of delay.

This pattern continued into the second season. In response to the slow pace that

characterized the first season, NEM obtained a second barge and a larger bucket for its

excavator, which also could move timbers more effectively. And in July 2002, NEM

advised the City that it would commence work on November 1,2002, which would be

the first day that dredging could be performed. However, NEM was not prepared to start

on that date because its barge was still under repairs for damage that, at least in part,

occurred during the first dredging season. NEM has not offered a satisfactory

explanation why, when the barge was damaged well prior to November 2002, the repairs

were not completed in time for the dredge to begin then as scheduled. It is significant

that at trial, Twitchell attempted to blame the presence of the federal dredging contractor,

Prock Marine, in the harbor as the explanation for NEM's late start. However, as

Twitchell ultimately acknowledged and as extrinsic evidence establishes, NEM was fully

aware that it could have worked in the harbor at the same time as Prock.

NEM ultimately began dredging the harbor for the second season in late

November. By then, it had lost nearly a month of valuable time to work. It had to

suspend operations for part of the winter because the harbor froze over. This

compounded the effects of the delay in November, because NEM became unable to make

up lost ground. NEM's lack of access to the dredge area also has significance on another

aspect of its failure to perform. Under the contract, NEM was required to provide

34

suitable equipment that would preclude a persistent failure to perform. NEM was unable

to work through the second season because it could not break up the ice in the harbor.

The same problem would have arisen during the third season, as would be demonstrated

by NEM's January 2004 request for the City to arrange for icebreaking services.

The end of the second season represented the last of NEM's work in the harbor.

As is noted above, some delays in NEM's progress during the first season were

understandable because of the unexpected encounters with the timbers among the dredge

spoils. However, NEM was fully aware of this issue when it began the second season,

and in fact, by securing more suitable equipment, it had taken steps to prepare for

dredging that material. Nonetheless, despite the absence of surprises, by the end of the

second season, NEM had completed barely more than one-quarter of the work required

under the contract. The court attributes this to the delays and lost work opportunities that

NEM created during the first two seasons. Additionally, because the harbor floor was

now a known quantity, the slow progress must also be seen as a reflection of insufficient

resources that NEM was dedicating to this project. As will be seen, this point is clearly

demonstrated by the effectiveness of the dredging work that Prock performed after NEM

was terminated from the project.

NEM's willingness to perform under the contract shifted in a fundamental way

sometime between February 2003 and October 2003. This change embodied a persistent

failure to perform, thus justifying the City's decision to terminate the contract in February

2005. By letter sent in early February 2003 to Timothy King, the City manager,

Twitchell provided assurances that NEM would return to the harbor in the fall and

resume work at that time and that it would continue the work pursuant to the existing

agreement. NEM had no contact with the City or with W&C until Twitchell responded to

a letter sent to him by King's successor in October. In that letter of October 20,

Twitchell reported that there were "issues that need to be resolved before the dredging

will resume." This raises the question, what happened between February and October

that prompted NEM to threaten a termination of its work? The court finds that in the

interim, through media accounts of the dredge project, NEM became aware that the City

had overpaid NEM for work performed to date. As is discussed above, this was caused

by the method of calculating the progress payments that the City made to NEM. Those

35

payments were based on visual estimates of the amount of material that NEM removed

from the harbor. Because the in situ volume is less than the volume after the spoils are

dredged, it had appeared that NEM had performed more work than it actually did.

Because NEM was paid based on the volume of dredged material, the City ended up

paying more than NEM had earned under the contract.

NEM's realization of the financial status of its work explains its responses in

November and December 2003. The focus of those substantive concerns as expressed to

the City and to W&C was on the amount of money it was to be paid for its work.

Although in February 2003 NEM expressed full willingness to work under the existing

contractual payment formula, by the end of that year NEM had made a demand for a

huge increase in the amount of those payments and for payments of expenses for which,

under the contract, it was responsible - even though there had not been any change in the

project or working conditions since NEM had sent its letter in February 2003 stating its

intention to return to the harbor under the contract.

Several aspects of NEM's demands justified the City'S termination of the contract

for cause. First, at best for NEM, NEM's dissatisfaction with the existing payment terms

arose in July 2003, when local media reported the fact that the City had overpaid NEM.

Under the contract, NEM was required to put the City on notice in writing of any dispute

"promptly" after the grounds for the dispute arise, but within no more than 30 days. This

means that if NEM did not know of the overpayment until July, it was required to notify

the City of a resulting dispute by August. Instead, NEM waited more than two months

after that contractual deadline. This resulted in a material delay in the project: because

NEM raised the issue on the cusp of the beginning of the third dredge season, valuable

time was lost during that season. That NEM waited as it did justified the City in

concluding that NEM did not intend to adhere to its performance obligations.

In fact, at least part of the basis for NEM's dissatisfaction with the payment terms

rests on the bulking factor caused by the timbers. This problem became apparent when

NEM first began its dredging work in December 2001. To this extent, NEM was not

entitled to ground a claimed dispute on the timbers, because it failed to raise the issue in a

timely way and because, just as importantly, the parties fully addressed and resolved this

issue through the January 2002 change order. Beyond this, to the extent that the bulking

36

issue that NEM raised in October 2003 was based on the bulking of spoils other than the

timbers, NEM must have been aware of that issue as it conducted the dredge of the

harbor during the first two seasons. Therefore, the basis for the dispute referenced in

Twitchell's October 2003 letter had been known to NEM for a considerable length of

time. As is noted immediately above, the contract required NEM to communicate a

dispute to the City at least by August 2003. However, because the basis for that

complaint was evident well prior to July 2003 (when the media reported the

overpayments), NEM's complaint first articulated in October 2003 may have been even

more untimely.

Additionally, when the parties' principals met on November 10, Twitchell was

instructed to submit a proposed change order reflecting a new payment formula that it felt

would address its complaint. This is the procedure required by the contract, and it is the

same procedure that, on W&C's suggestion, NEM followed in January 2002 when the

parties recognized that the timbers buried in the harbor floor would warrant an

adjustment of the payment terms. Despite this and subsequent requests for a proposed

change order, NEM did not submit one until December 19. At one point in the interim, a

NEM representative, Tammy Pinkham, told W&C that NEM would not provide a change

order. In the face of this, W&C prepared one on behalf of the City for NEM's own

consideration. In addition to revealing NEM's own refusal to perform under the contract,

these developments demonstrate the extent of the City's willingness to go beyond its own

responsibilities under the contract in an attempt to save the contractual relationship with

NEM.

When NEM did provide the City with a proposed change order, W&C promptly

evaluated it, and the City promptly rejected it. When W&C notified NEM of this ac!ion,

it also reminded NEM of NEM's recourse under the contract, which consisted of an

appeal or demand for dispute resolution. NEM did not invoke either of these procedures,

which meant, as W&C also noted in its rejection advice, that the contract would remain

in effect without change. Nonetheless, NEM still refused to resume its dredging

operation.

As these events were progressing, NEM provided even further evidence that it did

not intend to attach importance to the timeliness of its performance. First, at a meeting

37

held on December 15, Twitchell advised that NEM did not intend to work in the harbor

six days per week. In a letter that Wilson sent previously to Twitchell, W&C projected

that based on the amount of material that still needed to be removed from the harbor,

NEM would need to use two barges six days per week to complete the dredge during the

third season. Twitchell's refusal to submit to that proposed work schedule contravened

the terms of the contract. However, it also left open the question of how NEM itself

intended to complete the dredge job. Twitchell rejected W&C' s proposed schedule, but it

did not propose any alternative. Indeed, W&C had requested NEM to provide a progress

schedule a number of times. Despite these requests and the contractual requirement,

NEM never did so.

NEM's failure to resume the City dredge project for the third season resulted from

another reason unrelated to the terms of the contract. NEM was working on an unrelated

job and thus was unavailable to return to the harbor anyway. Twitchell advised the City

that this diversion would continue into sometime in January 2004. Then, in January, after

the City had declared a default but prior to its termination for cause in early February,

NEM's attorney advised the City that because of ice conditions in the harbor, NEM could

not dredge. Counsel suggested that because of anticipated weather conditions, NEM

could not be expected realistically to begin its work until mid-February.

The evident effects of NEM's refusal to return to the harbor were compounded by

the pace of the work performed during the first two seasons. Despite its presence in the

harbor for two winters, it had removed only approximately 25% of the material that was

involved in the project. The slow pace during the first season was justified because of the

problems removing the timber. However, NEM was on notice of that issue for the

second season and prepared for that known condition by obtaining different equipment.

Despite this, NEM remained unable to accomplish much of the work required by the

contract. The inadequacy of the resources that NEM brought to bear are shown not only

by this slow rate of progress, but by the manner in which Prock, as the successor

dredging contractor, accomplished the work that the contract required NEM to perform.

In less than two months (i.e., roughly one-third of a single dredging season), Prock

removed approximately twice the amount of spoils that NEM had dredged in two

seasons. Even if one were to allow for the possibility of differing work conditions (if, for

38

example, the areas that Prock dredged were not encumbered by timbers - although Prock

did fact some unique difficulty because it encountered boulders, see exhibit 263), the

court views this as powerful evidence that a properly equipped and staffed dredging

contractor would be fully capable of dredging the harbor expeditiously.

Thus, when NEM balked at resuming its work for the third season, the City then

began to lose even more time on the project by a contractor whose work progressed very

slowly even when it was performing. The history of unjustified and improper delays,

aggravated by the slow pace of progress, established that NEM had engaged in a

persistent failure to perform its work under the contract. For the reasons set out in the

discussion of NEM's claims against the City, NEM's failure to perform was not legally

justified. The court concludes that NEM was simply not equipped to manage this project.

NEM submitted a low bid for the contract, attempting to present a more attractive

proposal than the one it knew Prock had submitted previously. NEM began the project

late and then ran into unexpected problems with the timbers. However, the parties, now

aware of the problem, addressed it and agreed to an accommodation. Despite the

additional knowledge about the harbor conditions, NEM stilI was overmatched by the

project. In April 2003, NEM requested the City to turn over the retainage of

approximately $25,000, to which it had no present claim under the contract. Then, by

July 2003 when NEM learned that it had been paid more than it was entitled to receive

under the contract and thus might owe money back to the City for work performed to

date, the company took a hard line in an attempt to effect an extraordinary increase in the

compensation structure. This included retaining the overpayments, increasing the level

of future payments, and receiving reimbursement for the expenses of its work. The City

rejected that proposal; NEM did not seek any relief from that position; NEM did not

resume the dredge; and the City formalized the end of the relationship through notices of

default and termination for cause.

For these reasons and without reaching the other grounds urged by the City in

support of its claim for breach of contract, the court concludes that NEM committed a

material breach of contract and that is liable to the City for damages.

39

This leads to the question of damages arising from the City's termination of the

contract for cause. The contract identifies the elements and measure of damages when

the contractual relationship comes to an end under those circumstances:

If the unpaid balance of the Contract Price exceeds all claims, costs, losses, and

damages (including but not limited to all fees and charges of engineers, architects,

attorneys, and other professionals and all court or arbitration or other dispute

alternative costs) sustained by OWNER arising out of or relating to completing

the Work, such excess will be paid to CONTRACTOR. If such claims, costs,

losses, and damages exceed such unpaid balance, CONTRACTOR shall pay the

difference to OWNER. ...When exercising any rights or remedies under this

paragraph OWNER shall not be required to obtain the lowest price for the Work

performed.

. . .Where CONTRACTOR'S services have been so terminated by

OWNER [for cause], the termination will not affect any rights or remedies of

OWNER against CONTRACTOR then existing or which may thereafter accrue.

See exhibit 32 at Bates 2340.

The total contract price was $516,022, which includes the increased payments to

NEM based on the adjustments to the payment formula established in the January 2002

change order. See exhibit 104b. Of this amount, the City paid NEM $266,083. See

exhibit 150a. The unpaid balance is the difference between the two, or $249,939. This

figure, representing the amount that the City contracted to - but did not - pay for the

dredging project, is then compared to the combined costs arising from the breach and the

expenses to complete the work. If those costs exceeded the amount the City would have

paid NEM to perform in accordance with the contract, then the City is contractually

entitled to recover that difference from NEM. The contract thereby embodies the

common law notion that these damages put an aggrieved party "in the same position that

he or she would have enjoyed had there been no breach." Lee v. Scotia Prince Cruises

Ltd., 2003 ME 78, ~ 22, 828 A.2d 210, 216. The City claims that in this case, those post­

termination expenses and costs consist of the costs to complete the project and the

expenses incurred to adjudicate its claim against NEM. Under the contract, these

amounts are recoverable. The next step is to quantify them.

The largest single element of the City's damages claim against NEM is the cost

incurred by the City to have Prock perform the dredge work. That cost exceeded

$400,000. See exhibit 263. NEM argues that the project performed by Prock was

40

different that the project that it (NEM) contracted to perform. The basis of this

contention is the divergence between the amount of work required by the contract and the

more limited scope of work as set out in the original DEP permit, because the permit

authorized less dredging in the intertidal area than the contract indicated. However,

NEM's contractual obligation owed to the City was defined by the contract, which

included the depictions of the area to be dredged. The permit was a necessary step in the

execution of the project, and the City had the responsibility to obtain the permit. The

City did so, and subsequently it also easily obtained an amended permit that was in

accord with the actual work required by the contract. In the end, however, NEM was

contractually required to dredge the areas that were identified in that instrument, which

later became reflected in the amended permit. Prock's work was within the scope of the

contract that NEM had executed with the City, and so the City is entitled to recover the

expense incurred by the City to acquire performance by Prock for the work that NEM

itself was to provide.

NEM also opposes this element of damages because Prock dredged deeper into

the harbor floor than NEM was required to dig. Under the contract, NEM was to dredge

five feet below mean low water. Prock was paid based on a depth of six feet. 6 However,

Prock dredged a smaller volume than the amount that remained for NEM to remove, as of

the time the City terminated that contract. Further, Prock's work was within the NEM

contractual dredge area. Therefore, when measured by volume of spoil and by

geographical parameters, Prock's work did not exceed the overall scope of the dredge

work that NEM was to have performed. Because of these considerations, the different

dredge configuration defining Prock's work - deeper into the harbor floor but not to the

full limit of the contractual dredge boundaries - does not undermine the City's contention

that its damage analysis includes the full cost of Prock's work. Finally, the evidence

establishes that Prock's charges to the City were fair and reasonable.

In addition to the actual amount of money that the City paid to Prock, the City

incurred expenses for engineering and surveying services and other charges associated

6As Prock's project manager testified, in some areas Prock dredged seven feet deep,

although the City paid for six feet.

41

with the post-termination work. They are not in material dispute. The court accepts the

evidence of those costs as outlined in exhibit 263.

Finally, the City incurred dispute resolution costs and court expenses, including

attorney's fees of $87,699.13. 7 See exhibit 263, affidavit of attorney's fees. The

attorney's fees established in the affidavit of counsel includes a deductible of $5,000,

which is also included in exhibit 263. The amount of the City's deductible is therefore

not awarded separately. The costs of litigation have not been placed in material dispute.

The court independently concludes that those expenses are reasonable, including the

attorney's fees that may be gauged against the legal fees claimed by NEM.

Exclusive of attorney's fees, the total amount of the City's expenses incurred to

complete the dredge project and pursue dispute resol ution of the pending claims is

$481,995.15. This exceeds the unpaid balance of the NEM contract price by

$232,118.15. The City is entitled to recover this amount from NEM. The City is also

entitled to an award of attorney's fees in the amount of $87,699.13.

The City is also entitled to recover from NEM the amount that the City overpaid

NEM for the work it performed prior to the contract termination. The amount of the

City's excess payments is $107,375. Recovery of such damages is not specifically cited

in the contract. However, the damages provisions of the contract make plain that the

contractual measure of damages does not limit any other remedies that are available to

the City. This allows the court to consider this aspect of the City's damages claim.

The City has framed its claim to recover the overpayment as both a form of

contract recovery and as one for unjust enrichment. A party is entitled to relief for unjust

enrichment only when it does not stand in a contractual relationship with the breaching

party. See Cummings v. Bean, 2004 ME 93, 119,853 A.2d 221,224. Here, of course, the

City and NEM were parties to a contract. The City therefore cannot recover on that basis.

However, because NEM breached the contract and the City terminated the contract for

cause, the City is entitled - as a result of NEM's breach - to recover the amount that

NEM was paid but did not earn. An award based on this overpayment is necessary to

7 The City'S attorney has filed an affidavit in support of the claim for attorney's fees.

Counsel followed the affidavit with a letter dated May 1,2006, making a minor

correction in the total fees claimed.

42

restore the City to the position it would have been in absent the breach. Lee, 2003 ME 78,

, 22, 828 A.2d at 216.

Accordingly, the City has proven damages for breach of contract in the total

amount of $339,493.15, plus attorney's fees.

The entry shall be:

On the complaint, judgment is entered for the defendants.

On count 1 of the counterclaim, judgment is entered for the counterclaim plaintiff

City of Ellsworth and against counterclaim defendant Northeast Marine Towing and

Construction, Inc. in the amount of $339,493.15, plus pre-judgment interest at the annual

rate of 4.28% and post-judgment interest at the annual rate of 9.42%. Counterclaim

plaintiff is also awarded attorney's fees of $87,699.13. On count 2 of the counterclaim,

judgment is entered for the counterclaim defendant.

Defendant Woodard & Curran is awarded its costs of court. The award of costs of

court to defendant City of Ellsworth is included in the attorney's fees award and is not

addressed separately.

Dated: April 9, 2008

REceIVED 8: FILED

APR 17 2DDB

HANCOCK COUNTY

COURTS

43

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.